SKADS meeting – 8/2/04
DS3 – Overview
Significantly over budget: 1.4 m€
Basis: 2 national man-months : 1 EU funded man-month
all equipment costs national funding (none requested in original SKADS proposal)
Why: Very significant increase in DS3-T1 activity
T1 568 2123
T2 190 910
T3 420 1410
T4 176 716
T5 18 800
Coord. 60 122