Upload
palisadian-post
View
217
Download
0
Embed Size (px)
Citation preview
7/29/2019 DS 104 task force meeting Oct. 30, 2012
1/4
Los Angeles Department of Water and Power
DS 104 Task Force Meeting
Meeting Summary
Tuesday, October 30, 2012
Palisades Lutheran Church
15905 Sunset Boulevard
Los Angeles, CA 90272
Task Force Members:
Present:
Christine Abraham
Jeff Beall
Joyce Brunelle
Kelly Comras
Gil Dembo
Christy Dennis
Peter Duke
Paul GlasgallAmy Kalp
Joyce Wong Kup
Jim Rea
Danielle Samulon
Haldis Toppel
Hank Wright
Marc Zussman
Absent:
None
Project Team:
Mike Mercado (Environmental Project Manager, LADWP)
Chuck Holloway (Manger of Environmental Assessment, LADWP)
Eric Hartman (Power System Engineering Division, Manager of Major Projects, LADWP)
James Chestnut (Engineering Geologist Associate, Geology and Soils Group, Power System
Engineering Division, LADWP)
Victoria Cross (Government and Neighborhood Relations Liaison, LADWP)
Norman Kulla (Northern District Director and Senior Counsel, Office of Councilman Bill
Rosendahl)
Bill Piazza (Environmental Assessment Coordinator, LAUSD)
Jeannie Kamm (Deputy of School & Community Affairs, LAUSD)
Nancy Graham (Task Force Facilitator, AECOM)Ana Nolan (Community Outreach Specialist, AECOM)
Other attendees:
Andrew DeBlock (Senior Field Representative, Assemblymember Betsy Butler, 53rd
District)
7/29/2019 DS 104 task force meeting Oct. 30, 2012
2/4
Proceedings:
1. Opening discussion
The suggestion of a new site (at the foot of Bienveneda canyon) was considered for inclusion, but was
discarded after the site was discussed in further detail, siting that it is dangerous and replete with
liability issues. Norman Kulla, with Councilman Bill Rosendahls office, informed the group that the
location was a former haul site with many geological issues. The City of Los Angeles, Bureau of
Sanitation, completed a sewer project on the site and it has been the subject of disputes between the
owner and the surrounding property owners ever since. The location of many slope failures, the area is
also home to a riparian habitat that flows continuously down the center of the site. It has been for sale
for many years.
Due to the recent public consternation about the task force and site selection, it was suggested that
LADWP become more responsive to the community, however, it was mentioned that LADWP has been
consistently posting Task Force meeting summaries and presentations to the dedicated DS 104 website.
It was suggested that the LADWP work with the local press because it appears that people are not
reading the information posted to the website. This was followed by a discussion about the Task Forceand the process. The Task Force was reminded that each member was selected to incorporate a variety
of backgrounds representing a true cross-section of Pacific Palisades community. LADWP is giving the
group as much information as they have on each site so that the Task Force has the ability to make the
most informed decision. Sites that are ultimately placed in the top tier (no tiering has taken place to
date) will require further research and investigation into potential geological and environmental issues,
which will take months. If LADWP finds serious issues with a site, it will need to be removed as an
option.
It was agreed that, once sites are placed into tiers, all three tiers will be presented at the community
meeting so that the public may see all of the sites that have been examined by the Task Force. The goal
is to focus on the 3-4 sites which will ultimately fall into Tier 1 as it is harder to have a focused meeting
around 15-16 sites. The purpose of the workshop is to hear from the community about what the Task
Force has been working on and create a venue to better understand how people feel about the choices
that are on the table. LADWP is looking for a site agreed upon by their staff and the community. Some
Task Force members added that if, in the end, the community does not agree on any of the 3-4 sites that
the Task Force has chosen then their work has been for naught. The Department of Water and Power
Board of Commissioners will make the final site decision and will take into consideration the dedicated
effort by the Task Force and LADWP staff.
It is the intention of LADWP staff to begin the California Environmental Quality Act (CEQA) process with
3-4 possible sites so that they can begin analyzing the engineering of those sites. The CEQA process also
has a public outreach component which will provide the community with more opportunities to give
input.
Given recent weather events on the East Coast, questions were raised about safety, specifically
explosions and fires, within distributing stations. Eric Hartman stated that, to his knowledge, LADWP
has never experienced an explosion in a sub-station. There have been small fires on occasion. A cable in
DS 29 once over-heated and smoke was emitted, however, there was not a resulting fire.
7/29/2019 DS 104 task force meeting Oct. 30, 2012
3/4
2. Geologic Overview of the Pacific Palisades Area by Jim Chestnut
The presentation given was in order to provide basic concepts that would be helpful for Task Force
members to apply to the site selection process. Jim reviewed geologic conditions which should be
considered. These include existing conditions (such as landslides, faulting, weak bedding, and steep
slopes) and potential conditions (such as landslides from seismic shaking, liquefaction, and faulting). Jim
also talked about geologic materials and reviewed a seismic hazard map of the area. He focused on the
Alquist-Priolo active fault map and reviewed construction mitigation techniques for various conditions.
Questions were raised about the construction standards for distributing stations and the effect of
earthquakes on these facilities. Distributing stations are built to meet LADWP standards, as well as state
building and construction standards. LADWP considers distributing stations essential facilities (in the
same category as schools and hospitals), and therefore require the highest safety standards. Vendors for
the internal equipment are required to conduct shake-table tests to confirm that the equipment can
tolerate a maximum amount of shaking. Distributing stations are built to sustain an approximate 7.8
magnitude earthquake and LADWP has certain engineering mitigation measures that they can build in
order to mitigate geological issues. For reference, no fire occurred at Rinaldi Switching Station resulting
from the Northridge earthquake. This station was at the epicenter of the 1994 earthquake.
Within the information distributed at the last Task Force meeting (October 17, 2012), the Alquist-Priolofault line was mentioned about only one site, Site 4. This is due to the fact that there has been much
more investigation completed on Site 4 by potential developers, and the information that is presented in
these meetings is based upon what is available by records searches. Therefore, more information exists
about this site than about the other sites (3, 9, and 10) that were discussed in detail at the prior
meeting. That said, the current reports for Site 4 are vague, stating only a potential for a fault line, and
further geologic analysis would have to be completed by LADWP to make a conclusive determination.
There were questions raised regarding the future tiering system and concern that proper geology
reports could not be performed on every site. LADWP is giving the Task Force all of the information it
can on each site and will do everything possible, within the timeframe of the Task Force, to determine
issues related to sites. If LADWP says that there are potential challenges to a site, then the group shouldfactor that into the tiering process. This includes issues such as the past denials from California State
Parks when LADWP has attempted to purchase Site 9B.
Marc Zussman gave the group information about Site 4, obtained after he called the broker for more
information. A discussion ensued about Task Force members reaching out to brokers or property
owners. Several Task Force members believe that it is their responsibility to do their homework and
obtain as much information about the sites as possible. Gil Denbo asked LADWP staff how they felt
about Task Force members reaching out to property owners on behalf of the Department and whether
or not this could contaminate future negotiations. Eric Hartman stated that it was fine for Task Force
members to walk sites and get information for themselves, but not on behalf of LADWP. The
Department has real estate specialists that LADWP staff must coordinate with when they want more
information on a particular property. Eric is happy to have the Departments Real Estate Specialists
make any inquiries on behalf of the Task Force or a Task Force member. The group concluded that
inquiries should be made by task force members, only when acting as an individual. No reference or
connection to LADWP activities should be made.
3. Electromagnetic Field (EMF) presentation by Chuck Holloway
Chuck Holloway presented basic information about EMF including sources, terms and how EMF relates
to distributing stations. Chuck also talked about studies that have been conducted over the years
analyzing potential correlations between long-term EMF exposure and disease, explaining that there are
7/29/2019 DS 104 task force meeting Oct. 30, 2012
4/4
no conclusive determinations. Since the early 1990s, policies have been put in place and measures have
been take and to reduce EMF exposure. These measures include no- and low-cost measures, continued
research, education programs, stakeholder involvements, and field management policy guidelines.
Bill Piazza added that LAUSD has its own policies on EMF and radio fields and stated that LADWP has
been very good when it comes to wire-placement around schools. Although there are many activists
that talk about acceptable levels of EMF and have specific numbers, LAUSD does not. The District has
conducted their own studies and benchmark their acceptable levels of exposure on typical background
and ambient EMF levels found within a wired classroom or other rooms with typical electrical usages.
It was asked whether or not LAUSD has a policy on locating schools next to facilities such as distributing
stations. Bill explained that it depends on the voltage rating and size of the lines. Setback policies are
triggered when a nearby facility measures 50 kV or more. DS 104 is a facility with a maximum of 34.5
kV, a voltage too low to trigger the enforcement of setbacks. However, LAUSD will be looking at
potential EMFs associated with the station, as well as the lines coming and going from the station, and
will solicit field strengths from LADWP.
Inquiries were made regarding the distance between DS 66 and the Brentwood School. Bill said that the
school is approximately 200-300 feet away from the station. The playground is estimated to be about
200 feet away. Others thought it was closer than that and it was suggested that the distance bemeasured. Bill confirmed that the substation was built prior to the construction of the school and that
there have never been any inquiries or studies conducted as a result of a cancer cluster concern. Chuck
identified that EMF levels just outside of the station have been measured at 3 mG, which is considered
ambient. Great concerns were expressed by some Task Force members over EMF exposure and it is
suggested that each member use their own discretion on how EMF should influence their decision-
making.
4. Closing
Information on the next four sites investigated (5, 13, 14, and 15), which was not presented at this
meeting, will be reviewed at the following Task Force meeting, scheduled for Wednesday, November 14,2012.