_______New BTS Site Integration Drive Test Procedure______ 1 New BTS Site Integration Drive Test Procedure & Guidelines Prepared By: Zeeshan Asghar RF Consultant Aircom International Huawei/Warid Project

Drive Test Procedure

Embed Size (px)

Citation preview

_______New BTS Site Integration Drive Test Procedure______

1

New BTS Site Integration

Drive Test Procedure & Guidelines

Prepared By:

Zeeshan Asghar

RF Consultant

Aircom International

Huawei/Warid Project

_______New BTS Site Integration Drive Test Procedure______

2

Table of contents

Procedure Summary ............................................................................................ 3

1. Drive test preparation ......................................................................................... 4

2. Drive test ............................................................................................................ 5

3. Drive test report.................................................................................................. 8

4. Annexes .............................................................................................................. 9

_______New BTS Site Integration Drive Test Procedure______

3

Procedure Summary

The purpose of this document is to define the process flow and the drive test procedures

to be followed by Huawei & Sub-Con DT and RF engineers to verify the functionality of

the new sites in the rollout of WARID telecommunications network as part of the New

Site Integration Process. A high level block diagram of the steps to be followed on this

Drive Test Process is shown in Figure 1.

Figure 1: Drive Test Process– Steps Overview

The steps defined for this process are described below:

1. Drive test preparation Prepare the test equipment (hardware and software) for the measurements.

2. Drive test Actual drive test.

3. Data post processing

Post processing activities (logs post-processing, compile, filter, export to Mapinfo

tables, etc).

4. Drive test report Drive Test Report production for the site.

The steps for the completion of each phase will be described in the sections below:

1 Drive test

preparation

2

Drive test

3 Data post

processing

4

Drive test report

DT Report

Completed –

Submit for

Approval

_______New BTS Site Integration Drive Test Procedure______

4

1. Drive test preparation

Some preparation activities must be initially performed in order to set up the testing

equipment. This step will prepare the test equipment and set the software and hardware

details for the measurements. The DT check list must be completed during this DT stage

and delivered with the drive test report.

1.1 Expected results

The measurement system is set and all test cases are set

The measurement team is ready for the drive test

1.2 Procedure

The drive test engineer shall use a map of the area to be driven with a “marked” route

that will be provided by Huawei RF engineers, so that each site is driven thoroughly

in the amount of time given. DT engineer will emphasize on the site’s coverage

objective (town, village, major roads, etc).

He shall then make sure that all equipment are ready:

1. DC to AC Inverter

2. laptop with TEMS software

3. laptop power adaptor

4. TEMS dongle

5. Latest BTS/ CELL file for TEMS, which will be provided time to time from

Huawei RF engineers.

6. USB hub

7. GPS receiver

8. Car cigarette lighter extension cable for phone chargers and GPS

9. TEMS test mobiles

10. USB data cables to mobiles

11. Test mobile battery chargers or a full charged backup battery per mobile

He shall make sure that TEMS mobiles are connected on hub holders and placed on

the car’s dashboard.

He should carry a contact list with the responsible RF engineers (See the concern RF

engineers Contacts below) and the OMC engineers (See the concern OMC engineers

Contacts below) on shift.

_______New BTS Site Integration Drive Test Procedure______

5

1.3 Deliverables

To consider this activity completed the following deliverables must be produced:

List of constrains related to this activity (if any)

The DT check list [Annex 01] must be completed

The measurement team is ready for the drive test

2. Drive test

This step will perform the actual drive test defined for the site under test. Each drive test

must be clearly documented. Additionally, the time of the drive test activity must be

synchronised with the RF Engineers and OMC Engineers of Huawei, so that each

drive test data set collected can be correlated with the OMC statistics in order to produce

KPI snapshots.

2.1 Expected results

The drive test has been completed as planned

Any issues have been documented and reported

2.2 Procedure

All test calls should be terminated to a test number. Test number should be of Warid.

The drive testing scripts should be configured to provide the following test sequences:

1. MS1: configured to run on dedicated mode one continuous test call (Short calls

of duration of 120 seconds. Establish the short calls as per the DT route; mean DT

engineer will establish the new short call after every 120 seconds). If the call is

dropped during 120 seconds the DT engineer should re-establish a new call

immediately.

2. MS2: configured to run on idle mode throughout the drive test.

Each drive test should be clearly documented (duration, major events, issues etc).

Before going to the drive test route, the DT Coordinator of Sub-Con OR Drive Test

Engineer should contact the OMC shift engineer to make sure the site is alarm and

H/Wor S/W problem free. If there will be any alarm of any other H/W or S/W

issues, he must inform the RF engineers of Huawei at the same time, so they can send

the BSS teams there.

_______New BTS Site Integration Drive Test Procedure______

6

Once the drive test team is on the site and before starting the measurements they

should coordinate with the OMC shift engineer and the DT coordinator to unlock the

site.

Prior to this test, PCU, SGSN and other GPRS connectivity network elements have to

be verified that are working.

During the drive tests the engineer should ensure that there are no swapped (crossed)

sectors problems, all neighbours declared in the CDD are present and all RF

frequencies given are correct.

During the drive tests the DT engineer should note all major events (drop calls,

blocked calls, handover failures) and shall identify their main causes. He must have to

mention the Layer 3 cause value in the report because of which the event occurred

(See the report format).

To avoid the Re-drive, during the Test, if the DT engineer will find the following

issues then at the same time, he must inform the DT coordinator so the DT

coordinator will inform the RF engineers so they can resolve the issue at the same

time.

Handover failures, without the reason of timer expiry.

Call establishment problems

Neighbour missing

Call drops

Blocked calls

Sector swap

Bad C/I

Bad RX quality

Bad Rx Levels in idle mode

Intra Cell Handovers, Intra Band Handovers & Inter cell handovers problems.

Call is not camping over TCH, means call is camping over BCCH only.

Ping Pong Handovers means too many handovers at any interval or on whole

cell or site.

Upon completion of the DT activity the DT engineer should verify that all log files

are not corrupted. In case of any log file problems the DT team should repeat the test

immediately. Finally he should report to the DT coordinator the successful

completion of the drive test.

Due to the file size, upon completion of DT, DT engineer will export the log files

after merging them and then plot the RX level idle and RX quality plot over Mapinfo

and send it to the DT coordinator so he will ensure that there is no problem over the

site regarding to sectors swap and bad quality. If DT coordinator will find any issues

or not sure about that, then he must inform the RF engineer of Huawei.

The DT coordinator should then ensure that the site is locked again after the specified

end time of the DT activity.

The DT coordinator should handover the log files and the list with the description of

the major events and their causes (drop calls, blocked calls, handover failures) to

Huawei local office.

_______New BTS Site Integration Drive Test Procedure______

7

Drive Test Types & Acceptance Details

Sites with Urban Objective

– Radius of area to collect data for acceptance procedure: 1 km

Sites with Rural Objective

– Radius of area to collect data for acceptance procedure: 4 km

Sites with Highway Objective

– Linear Area to collect data for acceptance procedure: 7 km on each

Direction of the road of the target (highway)

Note: The radius of area depends upon the height of the Antenna. As the height

increase the radius area also increase.

Sites with Urban Objective

RX Level Threshold: 85% of the samples shall have greater and equal to -75dbm

RxQual Threshold: 80% of the values shall be between 0-4,

where samples of value 4 shall be less than and equal to 20%.

Values 6 and 7 shall be _ 10% of the total samples

C/I Threshold: 90% of the samples less are in between 12 to 30

Sites with Rural Objective

RX Level Threshold: 70% of the samples shall have greater and equal to -75dbm

RxQual Threshold: 80% of the values shall be between 0-4,

where samples of value 4 shall be less than and equal to 20%.

Values 6 and 7 shall be _ 10% of the total samples

C/I Threshold: 90% of the samples less are in between 12 to 30

Sites with Highways and Roads Objective

RX Level Threshold: 85% of the samples shall have greater and equal to -80dbm

RxQual Threshold: 80% of the values shall be between 0-4,

where samples of value 4 shall be less than and equal to 20%.

Values 6 and 7 shall be _ 10% of the total samples

C/I Threshold: 90% of the samples less are in between 12 to 30

_______New BTS Site Integration Drive Test Procedure______

8

2.3 Deliverables

To consider this activity completed the following deliverables must be produced:

List of constrains related to this activity (if any)

Log files delivered to Huawei local office

Site Integration Report ( See the Report format below)

3. Drive test report

This step will produce the final DT report which shall contain all RF indicators, as per the

report template below.

We have added few new points in the report, which are

Regarding to Handover Relationship Table, we have to strictly follow the following

We have to check the neighbor relation as per CDD, and then confirm it with the

OMC that whether all the neighbor relations are defined in the OMC or not.

If there is any missing relation which is not exist in OMC but exist in CDD then

we will ask the OMC guy to add it and while preparing the report we will mention

that this neighbor relation wasn’t added in the OMC before, but we have added

it.

If all the neighbor relations in the OMC are according to CDD then we will put all

the neighbor relations in the report.

If we there is no handover occurred between any relations according to CDD then

we just put "NOT OK" in front of that relation in the report and give the reason

why there was no handover occurred. (See the report template for reference)

In any case, we must put all the neighbor relationships according to CDD in the

report, all we need to do is to write the status in front of the relation. We write

OK-(if the handover is occurred) NOT OK (If the handover is not occurred). For

NOT OK, we will mention the reason that why there was no handover occurred.

If there is no road available or if there is no access to any road which is given in the

route area, then we will have to take the snaps of the area that why there is no access

to the road. We have to paste the snaps in the report, for the reference please kindly

checks the report template.

The drive test report should be send with in 12 hours after the DT completed, to the

RF Engineers of Huawei.

_______New BTS Site Integration Drive Test Procedure______

9

4. Annexes

DT Check list

DT checklist.xls

Drive Test report template

Report Template