OPTION RO 7/21/08
OPTIONCLIENT Study Number Date Item No. City of Cedar Rapids Sasaki Associates Inc. 21493.02 9/10/08
Structural S9A Study
Title: Cedar Rapids River Corridor Redevelopment Flood Control Study
TITLE: Increase Cedar River Channel Cross Section by Dredging
DESCRIPTION:
Dredge Cedar River channel to provide an increased section to allow a higher flow rate. Based on dredging the river from the Five in One Dam (cross section T) to the south side of the landfill (cross section F). The typical cross section uses a minimum bottom width of 300 feet sloping from an invert elevation of 699.0 feet to 692.0 feet. Approximately 183,000 cubic yards of material removed from the channel, which includes rock excavation.
ADVANTAGES: Increased flow would reduce flood crest in Cedar Rapids.
DISADVANTAGES: Dredging likely to need permitting from several agencies. Spoil may include hazardous wastes (may contain phosphates, high pesticide levels and other farm runoff chemicals) which will need remediation or special waste disposal. Only small dredges can be used in river due to the available water depths (versus large dredges in Mississippi) which will cause high costs. High cost to remove/transport dredge material out of river floodway and floodplain. Short term option unless continuing maintenance dredging is performed. Although crest is reduced in Cedar Rapids, crests remain the same downstream.
Potential Reduction in 100-year Flood Crest: 0 ft to 0.4 ft. Potential Reduction in 500-year Flood Crest: 0 ft to 0.3 ft. Potential Reduction in 2008 Flood Crest: 0 ft to 0.2 ft. Likely Timeline Before Benefits Occur: 10 to 20 years ROM Cost Estimate: $26,000,000
COST DEVELOPMENTDate Item
9/9/2008
StudyTitle
Quantity Unit Labor andMaterials
Total
24,540 CY $38 $932,520
158,209 CY $114 $18,035,826
24,540 CY $38 $932,520
S9ACedar Rapids River Corridor Redevelopment Flood Control Study
Item
Project Length (15,730 ft/3 +/- miles)
Wet
Rock
Disposal
CLIENT Study NumberCity of Cedar Rapids Sasaki Associates Inc. 21493.02
Excavation (182,749 CY)
Dredging
158,209 CY $38 $6,011,942
1 LS $350,000 $350,000
$26,262,808
Use $26,000,000
Permitting
Total
Rock
jlk:mjh:fs2:mp3:21493:06:04:Options_Forms:AppA_att2_Cost_mjhR1_MK.xls ______
S
T
I
R
N
L
M
O
P
Q
J
K
F
H
G
0 1,500 3,000 4,500750Feet
City of Cedar RapidsS9A - Increase Cedar River Channel
Cross Section by Dredging
LegendCross Section LineFlood Control Option
OPTION RO 7/21/08
OPTIONCLIENT Study Number Date Item No. City of Cedar Rapids Sasaki Associates Inc. 21493.02 9/10/08
Structural S9B Study
Title: Cedar Rapids River Corridor Redevelopment Flood Control Study
TITLE: Increase Cedar River Channel Cross Section by Widening Channel
DESCRIPTION:
Dredge/widen Cedar River channel to provide an increased cross section area to allow a higher flow rate. Based on widening the river channel from the Five in One Dam (cross section T) to the south side of the landfill (cross section F). The typical cross section uses a minimum bottom width of 700 feet sloping from an invert elevation of 699.0 feet to 692.0 feet. Approximately 1,644,000 cubic yards of material removed from the channel, which includes rock excavation and 1,150,000 cubic yards of material removed form the banks. See figure for Option S9A.
ADVANTAGES: Increased cross section area to convey flow would reduce flood crest in Cedar Rapids.
DISADVANTAGES: Dredging/excavation likely to need permitting from several agencies. Spoil may include hazardous wastes (may contain phosphates and other farm runoff chemicals) which will need remediation or special waste disposal. High cost to remove/transport dredge material out of river floodway and floodplain. Short term option unless continuing maintenance dredging is performed. Although crest is reduced in Cedar Rapids, crests remain the same downstream.
Potential Reduction in 100-year Flood Crest: 0 ft to 3.8 ft. Potential Reduction in 500-year Flood Crest: 0 ft to 3.3 ft. Potential Reduction in 2008 Flood Crest: 0 ft to 3.2 ft. Likely Timeline Before Benefits Occur: 10 to 20 years ROM Cost Estimate: $333,000,000
COST DEVELOPMENTDate Item
9/9/2008
StudyTitle
Quantity Unit Labor andMaterials
Total
652,463 CY $19 $12,396,797
992,665 CY $38 $37,721,270
1,148,926 CY $114 $130,977,564
Excavation
Earth - Wet
Rock
Study NumberCity of Cedar Rapids Sasaki Associates Inc. 21493.02
CLIENT
Item
S9BCedar Rapids River Corridor Redevelopment Flood Control Study
Side Embankment
Dredging
Project Length - (15,730 ft/3 Miles)
652,463 CY $38 $24,793,594
992,665 CY $38 $37,721,270
1,148,926 CY $38 $43,659,188
50 AC $17,267 $863,350
3 EA $14,232 $42,696
8 EA $189,750 $1,518,000
3 EA $1,900,000 $5,700,000
3 Miles $3,795,000 $11,385,000
Structure Removal
Private
Infrastructure
Commercial
Industrial
Utilities
Clearing & Grubbing
Rock
Earth
Dry
Wet
Disposal
jlk:mjh:fs2:mp3:21493:06:04:Options_Forms:AppA_att2_Cost_mjhR1_MK.xls ______
COST DEVELOPMENTDate Item
9/9/2008
StudyTitle
Quantity Unit Labor andMaterials
Total
Study NumberCity of Cedar Rapids Sasaki Associates Inc. 21493.02
CLIENT
Item
S9BCedar Rapids River Corridor Redevelopment Flood Control Study
2 Miles $2,846,250 $5,692,500
3 EA $5,692,500 $17,077,500
1 EA $2,846,250 $2,846,250
1 LS $500,000 $500,000
Highway
Railway
Permitting
Bridges
Roads
$332,894,979
Use $333,000,000
Total
jlk:mjh:fs2:mp3:21493:06:04:Options_Forms:AppA_att2_Cost_mjhR1_MK.xls ______