Upload
dinhdan
View
219
Download
0
Embed Size (px)
Citation preview
DRAFT Water Resources Technical Bulletin Page 1
DRAFT Water Resources Technical Bulletin
This guidance is intended to clarify how the Water Resources Goal and Objectives of the
Regional Policy Plan (RPP) are to be applied and interpreted in Cape Cod Commission
Development of Regional Impact (DRI) project review. This technical bulletin presents specific
methods by which a project can meet these goals and objectives.
The applicability and materiality of these goals and objectives to a project will be determined on
a case-by-case basis considering a number of factors including the location relative to Water
Resource Areas (identified on page 2), context (as defined by the Placetype of the location),
scale, use, and other characteristics of a project.
The Role of Cape Cod Placetypes
The RPP incorporates a framework for regional land use policies and regulations based on
local form and context as identified through categories of Placetypes found and desired on Cape
Cod.
The Placetypes are determined in two ways: some are depicted on a map adopted by the
Commission as part of the Technical Guidance for review of DRIs, which may be amended from
time to time as land use patterns and regional land use priorities change, and the remainder are
determined using the character descriptions set forth in Section 8 of the RPP and the Technical
Guidance.
The project context, as defined by the Placetype of the location, provides the lens through which
the Commission will review the project under the RPP. Additional detail can be found in the
Cape Cod Placetypes section of the Technical Guidance.
Water Resources Goal: To maintain a sustainable supply of high quality untreated drinking water and protect, preserve or restore the ecological integrity of fresh and marine surface waters.
• Objective WR1 – Protect and preserve groundwater quality
• Objective WR2 –Protect, preserve and restore fresh water resources
• Objective WR3 –Protect, preserve and restore marine water resources
• Objective WR4 – Manage and treat stormwater to protect and preserve water quality
• Objective WR5 – Manage groundwater withdrawals and discharges to maintain hydrologic balance and protect surface and groundwater resources
DRAFT Water Resources Technical Bulletin Page 2
Table of Contents
Introduction.............................................................................................................. 3
Summary of Methods ................................................................................................ 4
Detailed Methods for Meeting Objective WR1............................................................ 10
For all projects ..................................................................................................... 10
For Projects Proposing Private Wastewater Systems ............................................... 12
For Projects Proposing Wastewater Treatment Facilities ......................................... 13
For Projects within Wellhead Protection Areas (WHPAs) and Potential Public Water Supply Areas (PPWSAs) ........................................................................................ 14
Detailed Methods for Meeting Objective WR2............................................................ 16
Detailed Methods for Meeting Objective WR3............................................................ 17
Detailed Methods for Meeting Objective WR4............................................................ 19
Stormwater system design ................................................................................... 19
Detailed Methods for Meeting Objective WR5............................................................ 21
detailed Water Resources Application Requirements .................................................. 22
Definitions .............................................................................................................. 23
References ............................................................................................................. 24
Appendix A: Nitrogen Loading Guidance for Water Resources .................................... 25
Appendix B: Estimation Of High Ground-Water Levels ............................................... 31
Appendix C: Monetary Nitrogen Offset...................................................................... 32
Note on Application Materials and Water Resource Areas Maps
Application materials should provide sufficient detail to demonstrate that the project meets the
applicable goals and objectives, but typically include:
A. Project description including site location, applicable Water Resource Areas, and
narrative of proposed wastewater, stormwater and drinking water systems
B. Site-wide nitrogen loading calculation
C. Site plan including applicable grading, drainage, and utilities
D. Stormwater treatment and capacity calculations
E. Operations and maintenance plan(s)
*These items may not be required for all projects. See guidance on page 22 for more information. The Water Resource Areas, which are defined on page 22, can be viewed in the RPP Data
Viewer, and include:
• Wellhead Protection Areas (WHPA)
• Fresh Water Recharge Areas (FWRA)
• Marine Water Recharge Areas (MWRA)
• Potential Public Water Supply Area (PPWSA)
• Impaired Areas
DRAFT Water Resources Technical Bulletin Page 3
INTRODUCTION
Cape Cod’s water resources include fresh and marine waters as well as natural and built systems.
The Cape Cod Aquifer, which serves as the primary link between all of the water resources on
Cape, is relied upon to provide drinking water and wastewater disposal capacity for the human
population, plays an integral role in maintaining plant and animal habitat in marine and
freshwater settings, and ultimately underlies many of the scenic and recreational opportunities
that serve as the primary economic driver for the region. Consistent with the Cape Cod Area
Wide Water Quality Management Plan (the “208 Plan), maintaining the integrity and health of
the aquifer and the various systems connected to it while encouraging provision of water
resource infrastructure and growth that is appropriate in form and location is the primary
purpose of the Water Resources goal and objectives.
This Technical Guidance provides examples of various methods and strategies that DRI projects
may use to satisfy the Water Resources Goal and Objectives of the RPP. Through
implementation of these methods and strategies, DRI projects can support the protection of
critical water resources through development that is consistent with the vision for the region.
Although the majority of methods discussed in this Technical Guidance are intended to be
flexible, certain methods will be required of all DRI’s where a particular Water Resources
objective is applicable.
DRAFT Water Resources Technical Bulletin Page 4
SUMMARY OF METHODS
Goal: To maintain a sustainable supply of high quality untreated drinking water and protect, preserve or restore the
ecological integrity of fresh and marine surface waters.
Objective WR1 – Protect, preserve and restore groundwater quality
Methods
All DRIs must employ the following methods to meet Objective WR1:
• Project is limited to a maximum site-wide nitrogen loading concentration of 5 parts per million (ppm) except
as provided below for Impaired Areas and Potential Public Water Supply Areas (PPWSA),
• No adverse impacts on downgradient existing or proposed drinking water wells.
• Septic systems and other sources of contamination are sited to avoid adversely impacting downgradient existing or proposed drinking water wells.
Additional methods to meet Objective WR1:
• Utilize site design and operational best practices to preserve groundwater quality
• Review existing Environmental Site Assessment(s) as available for previously developed properties and incorporate findings into project design
For projects in an Impaired Area outside of other mapped water resource areas (see RPP Data viewer):
• If proposed site-wide nitrogen loading concentration exceeds 5 ppm, demonstrate no adverse impact on ponds, wetlands, marine waters, public or private drinking water supply wells, and potential water supply wells.
For projects in Potential Public Water Supply Areas:
• Site wide nitrogen loading must be less than 1 ppm.
All projects proposing private wastewater systems designed for flows greater than 2,000 gallons per day (gpd) and requiring greater treatment efficiency than specified by MassDEP permit or approval letter must:
• Enter into an Operation, Monitoring, and Compliance agreement with the Cape Cod Commission and local Board of Health.
All Wastewater Treatment Facility DRIs must:
• Consistently achieve 5 ppm or lower total nitrogen in wastewater effluent or in groundwater at downgradient
property boundary.
Additional methods for wastewater treatment facility DRI’s to meet Objective WR1:
• Utilize wastewater treatment facilities including private treatment facilities to protect and/or restore ground water quality provided that such facilities will not adversely impact water or other natural resources.
• Locate treatment facilities outside FEMA V zones, A zones, and floodways; ACECs, wetlands and buffer areas, barrier beaches, coastal dunes, or critical wildlife habitat. Treatment facilities are proposed in FEMA A zones only to remediate water quality problems from existing
nitrogen sources within that zone.
DRAFT Water Resources Technical Bulletin Page 5
All DRIs within Wellhead Protection Areas (WHPA) or Potential Public Water Supply Areas (PPWSA) (see WHPA
and PPWSA layers in the RPP Data Viewer) must employ the following methods to meet Objective WR1:
• All development, construction, clearing, and staging occurs at least 400 feet from identified future well sites.
• Projects with a high risk of contaminating groundwater, such as fleet storage, vehicle maintenance areas and
loading docks, include a mechanical shut-off valve or other flow-arresting device in stormwater systems
between the stormwater capture structures and the leaching structures.
Additional Methods for DRI’s within WHPA and/or PPWSA’s to meet Objective WR1:
• Do not discharge effluent from private wastewater treatment facilities
• Use private wastewater treatment facilities to remediate existing water quality problems in the water supply
area.
• Do not use, treat, generate, handle, store or dispose of Hazardous Materials or Hazardous Wastes, except for
Household Quantities
o Redevelopment projects reduce the quantity of hazardous materials on the project site from the prior
use and adequately document that reduction
o Permanently eliminate the same or greater quantity of Hazardous Materials or Wastes at another
facility, project, or site within the same WHPA or PPWSA and adequately document that reduction
• Non-residential development and redevelopment employs integrated pest management and/or biorational
landscape management practices protective of water quality
• Roadway and parking area designs and materials minimize impervious surfaces
Objective WR2 –Protect, preserve and restore fresh water resources
Methods
All DRIs within a Freshwater Recharge Area (FWRA) must employ the following methods to meet Objective WR2:
• New development prevents loading of nutrients and other contaminants to fresh water resources.
• Redevelopment mitigates loading from nutrients and other contaminants to fresh water resources to the
maximum extent practicable.
• Maintain or enhance vegetated buffer zones along shorelines to ponds and lakes
All projects within a FWRA where septic effluent disposal is proposed within 300 feet of the high water level of a
freshwater pond; or wastewater treatment facilities effluent disposal is proposed anywhere in the watershed to a
freshwater pond must:
• Demonstrate that phosphorus transported by groundwater does not discharge into the pond or its
tributaries.
DRAFT Water Resources Technical Bulletin Page 6
Objective WR3 –Protect, preserve and restore marine water resources
Methods
All DRIs in a Marine Water Recharge Area (MWRA) where a critical nitrogen load has been determined through
either a Total Maximum Daily Load or Massachusetts Estuaries Project (MEP) Technical Report must employ the
following methods to meet Objective WR3:
• Not add nitrogen to a MWRA watershed unless:
o There is a MassDEP Watershed Permit or locally adopted nutrient management plan, deemed
consistent with the 208 Plan by the Cape Cod Commission, in the sub-watershed in which the project is
proposed, and the approved nutrient management plan calls for initiation of nutrient reduction actions
or strategies sufficient to offset nutrient contribution(s) from the project within five years of project
approval; or
o the project is in an area with available sewer connections, or is in a Placetype where nitrogen additions
may be offset through a monetary contribution to address water quality problems in the affected
surface waters.
All DRI’s in a MWRA where there are water quality problems that are scientifically documented and a critical load has
not been determined must employ the following methods to meet Objective WR3:
• Maintain or reduce nitrogen loading relative to existing levels.
Objective WR3 Areas of Emphasis by Placetype
Natural
Areas
Rural
Development
Areas
Suburban
Development
Areas
Historic
Areas
Maritime
Areas
Community
Activity
Centers
Industrial
Activity
Centers
Military and
Transportation
Areas
Development
is discouraged
in Natural
Areas and
monetary N-
offsets are not
permitted.
Sewer is
generally not
anticipated in
rural areas,
therefore
monetary N-
offsets are not
permitted.
Monetary N-
offsets may be
permitted at
Commission’s
discretion.
Monetary N-
offsets may be
permitted in
Historic Areas
at
Commission’s
discretion.
Monetary
N-offset are
permitted in
Maritime
Areas where
sewer is not
yet
available.
Monetary N-
offsets are
permitted in
Community
Activity
Centers where
sewer is not
yet available.
Monetary N-
offset are
permitted in
Industrial
Areas where
sewer is not
yet
available.
Monetary N-
offset are
permitted in
Military /
Transportation
Areas where
sewer is not yet
available.
* The nitrogen offset rate is based on cost efficiencies associated with wastewater collection and municipal treatment as described in Appendix C.
DRAFT Water Resources Technical Bulletin Page 7
Objective WR4 – Manage and treat stormwater to protect and preserve water quality
Methods
All DRIs, with the exception of redevelopment projects as discussed below, must employ the following methods to meet Objective WR4:
• Provide a stormwater management system that prevents adverse impacts to water resources and other natural resources.
• Prevent discharge of untreated stormwater to marine and fresh surface water and natural wetlands by treating runoff from development, including areas located outside the jurisdiction of the Massachusetts Wetlands Protection Act
• Provide storage and treatment capacity sufficient to store, treat, and infiltrate all runoff from parking areas and roadways onsite
• Locate new infiltration to maintain a minimum two-foot separation between points of infiltration and the maximum high water table.
• Design stormwater systems according to the Massachusetts Stormwater Handbook to: o accommodate the 25-year 24-hour storm o remove at least 80% total suspended solids (TSS) o provide water quality treatment capacity for the first inch of stormwater runoff using biofiltration,
bioretention, or other Treatment BMPs as detailed in the Stormwater Handbook
For redevelopment projects:
• Reduce impervious area coverage and improve site conditions to enhance stormwater retention, water quality treatment, and recharge over existing conditions.
• Include natural areas in stormwater system design. Additional methods to meet Objective WR4:
• Manage and directly infiltrate roof runoff separately where site constraints limit capacity for water quality treatment, unless there is an identified rooftop water quality concern requiring additional treatment or management.
• Design stormwater systems to remove at least 44% total suspended solids prior to discharge into subsurface leaching facilities.
DRAFT Water Resources Technical Bulletin Page 8
Objective WR4 Areas of Emphasis by Placetype
Natural
Areas
Rural
Development
Areas
Suburban
Development
Areas
Historic
Areas
Maritime
Areas
Community
Activity
Centers
Industrial
Activity
Centers
Military and
Transportation
Areas
Prioritize protection of
mature trees and wooded
areas and utilize natural
drainage features to manage
stormwater. Minimize
construction footprint, land
disturbance during and
after construction, and
impervious area creation to
maintain natural filtration
and recharge processes. Use
LID features that provide
water quality treatment
during storm events and
environmental or
recreational function at
other times, and optimize
BMPs for nitrogen removal.
Cluster
development
to maximize
contiguous
natural areas.
Minimize
stormwater
runoff by
reducing
road/driveway
widths and
using
permeable
features to
break up large
impervious
areas.
Utilize permeable
material choices when
designing roadways,
parking, and walkways
where land area and
subsurface access may be
limited. Employ
rainwater re-use
techniques in ways that
maintain local character.
Explore opportunities for
development of off-site
shared district or
community scale
stormwater treatment.
Prioritize
inclusion of
green space
that can
provide
treatment and
infiltration
capacity for
redevelopment
/ infill projects.
Utilize
subsurface
storage and
infiltration
measures
where site
constraints
limit above
ground
treatment
capacity.
Where
applicable
maintain or
improve gray
infrastructure
to support
development of
shared off-site
district or
community
scale
stormwater
treatment.
Prioritize inclusion of green
space that can provide
treatment and infiltration
capacity for redevelopment /
infill projects. Utilize
permeable material choices
when designing lower traffic
roadways, parking, and
walkways, and subsurface
storage and infiltration
measures where site
constraints limit above
ground treatment capacity.
Where applicable maintain or
improve gray infrastructure
to support development of
shared off-site district or
community scale stormwater
treatment. Design sites to
minimize exposure of
stormwater runoff to
hazardous materials,
hazardous wastes, and other
potential contaminants.
Design stormwater systems
to treat higher potential
pollutant loads and contain
runoff via flow arresting
device or otherwise in the
event of a spill / release.
DRAFT Water Resources Technical Bulletin Page 9
Objective WR5 – Manage groundwater withdrawals and discharges to maintain hydrologic balance in a way that is
protective of surface and groundwater resources
Methods
All DRIs must employ the following methods to meet Objective WR5:
• Design water withdrawals and wastewater discharges in a manner that protects surface water and wetland
habitat from groundwater pumping and, in the case of effluent disposal from water table mounding issues
(e.g., breakout, flooding, water table separation).
For projects proposing to withdraw >20,000 gallons of water per day from the site:
• Provide a groundwater study that demonstrates the project will not have adverse impacts on groundwater
levels or adjacent surface waters and wetlands.
DRAFT Water Resources Technical Bulletin Page 10
DETAILED METHODS FOR MEETING OBJECTIVE WR1
Objective WR1: Protect and Preserve Groundwater Quality
Nitrogen loading
Protection of Cape Cod’s groundwater resources is critical for the protection of human health.
The Cape Cod aquifer was designated as a Sole Source Aquifer (47 FR 30282) by the US
Environmental Protection Agency (USEPA) in 1982, recognizing the complete dependence of
the population on groundwater as its source for drinking water. The aquifer is primarily
recharged by precipitation but also receives discharges of wastewater and stormwater, which
can introduce contaminants into Cape Cod’s primary source of drinking water. Nitrate-nitrogen
(NO3-N) is a primary contaminant of concern due to its potential human health effects, for
which USEPA has established a maximum contaminant level (MCL) of 10 parts per million
(ppm). In addition, high NO3 concentrations in groundwater have also been correlated with
higher concentrations of regulated drinking water contaminants (e.g., volatile organic
compounds and compounds of emerging concern). For these reasons the nitrogen loading
requirements must be met by all DRI’s.
Detail on the methods for meeting Objective WR1 is provided below:
For all projects
Under the Safe Drinking Water Act, public supply wells which exceed 5 ppm NO3-N are subject
to additional monitoring requirements, and wells that exceed the MCL (10 ppm NO3-N) cannot
obtain variances or exemptions, thus requiring expensive treatment or being removed from
operation. In aerobic subsurface environments like Cape Cod’s unconfined aquifers, nitrate is
highly persistent with natural chemical reactions providing minimal removal. Consequently,
limiting the amount of nitrogen introduced to the aquifer is the most effective way to reduce
NO3-N concentrations in groundwater and protect Cape Cod’s drinking water.
5 ppm Nitrogen Loading Standard
The Cape Cod Commission has adopted a loading standard of 5 ppm NO3-N which based on a
statistical analysis is designed to keep violations of the USEPA MCL for NO3-N to less than 1 in
10 samples, while maintaining an additional margin of safety during times of simultaneous low
recharge (i.e., drought conditions) and high loading (summer peak season). This standard is
designed to protect human health, as well as current and potential future drinking water
resources. A site-wide nitrogen loading calculation takes into account all sources of nitrogen
from the project site post-development and divides this cumulative nitrogen input by the water
input (recharge) for the entire project site. Instructions on the information required and
method for calculating site-wide nitrogen loading are available in Appendix A – Nitrogen
Loading. Applicants seeking to reduce site-wide nitrogen loading may do so by providing
advanced treatment of wastewater flows to remove additional nitrogen, reducing the volume of
wastewater flows, increasing natural area on-site, decreasing fertilized lawn area, and
incorporating stormwater Best Management Practices (BMPs) optimized for nitrogen removal.
DRAFT Water Resources Technical Bulletin Page 11
Impacts of development on local drinking water wells
The 5 ppm nitrogen loading standard is designed to protect the Cape Cod aquifer as a whole, but
localized impacts of a project on the groundwater resources also need to be considered. As
nitrogen and other wastewater constituents will follow the flow of groundwater, the direction of
groundwater flow at the project site will determine where wastewater effluent travels. The
location of septic and other wastewater disposal systems, direction of groundwater flow, and
proximity of public or private drinking water wells at the site and on neighboring parcels should
be examined to verify that a project even when complying with site-wide loading standards is
not contaminating nearby drinking water resources. Applicants should identify existing or
proposed drinking water wells within 400 feet of project boundaries. Groundwater flow
direction should be determined using a water table map, which may be generated from
groundwater elevation data (possible sources might include the United States Geological Survey,
Massachusetts Department of Environmental Protection, or the town). The direction of
groundwater flow should be used to locate wastewater treatment systems (including septic)
appropriately so that effluent does not flow directly into downstream drinking water sources.
Site assessments for previously developed properties
Sites that have been previously developed, particularly those with uses that historically have
used/generated hazardous materials or hazardous wastes (e.g., gas stations, auto repair
facilities, dry cleaners, manufacturing facilities) may contain contaminated soil or groundwater
even if site assessment and remediation activities have been conducted under the Massachusetts
Contingency Plan (MCP). To prevent the unintentional mobilization of contaminants into
groundwater, documentation of all Environmental Site Assessments and remedial actions
should be supplied for Commission review to ensure the best available information regarding
surface and subsurface site conditions is considered when evaluating the project design.
Best development practices for site design
Low impact development is the practice of using innovative stormwater management systems
that are modeled after natural hydrologic features. Low impact development techniques
manage rainfall at the source using uniformly distributed decentralized micro-scale controls,
and small cost-effective landscape features located at the lot level. They also facilitate compact,
clustered development and minimize impervious surfaces.
Environmentally sensitive site design incorporates low impact development techniques to
prevent the generation of stormwater and non-point source pollution by reducing impervious
surfaces, disconnecting flow paths, treating stormwater at its source, maximizing open space,
minimizing disturbance, protecting natural features and processes, and/or enhancing wildlife
habitat.
Additional resources regarding site design best practices are available from the United States
Environmental Protection Agency (https://www.epa.gov/sites/production/files/2015-
11/documents/region3_factsheet_lid_esd.pdf), the Metropolitan Area Planning Council
(https://www.mapc.org/resource-library/low-impact-development-toolkit/), and other State
DRAFT Water Resources Technical Bulletin Page 12
and regional environmental and planning agencies (e.g. https://growsmartmaine.org/wp-
content/uploads/2015/08/Enviro_Sensitive_Design-Final-21-Nov-06.pdf).
Use of shared infrastructure
Shared wastewater treatment utilizes a single system to treat wastewater from multiple units of
development. This practice can facilitate higher density development, reduce environmental
impacts and treatment costs, and enhance open space preservation as it only requires a single
location for wastewater disposal and may require less total area for disposal. In cases where a
parcel is subdivided or residential lots are to be sold individually, a covenant will need to be
entered into by the homeowners for operation and maintenance of a shared system in order to
meet Objective WR1 via this method.
Multi-unit development is also encouraged to include community or public water supplies as
alternatives to multiple private wells, in order to avoid potential impacts from wastewater
disposal and challenges of siting and associated setback requirements for multiple water supply
wells.
For Projects Proposing Private Wastewater Systems
Operation, Monitoring, and Compliance Agreements
When a wastewater system of sufficient capacity (greater than 2,000 gallons per day design
flow) is proposed to operate with greater removal efficiency than currently certified by MassDEP
permit or letter of approval in order to meet Water Resources objectives, an Operation
Monitoring and Compliance (OMC) Agreement is required to ensure treatment goals are met.
The OMC agreement should be entered into between the applicant, Cape Cod Commission, and
the local Board of Health, and generally consists of:
• Treatment specifications
o Wastewater flow limit
o Effluent quality limits
• Monitoring requirements
o Sampling locations
o Analyses required
o Sampling frequency
• Reporting requirements
o Frequency of reporting
o Enforcement actions
• Operations and maintenance plan and staffing
DRAFT Water Resources Technical Bulletin Page 13
For Projects Proposing Wastewater Treatment Facilities
Wastewater Treatment Facilities
Wastewater collection and treatment systems that have a design flow of greater than
10,000gallons per day are considered a wastewater treatment facility (WWTF).
Location of Wastewater Treatment Facilities
WWTFs are likely to play a role in many towns’ nutrient reduction strategies, therefore it is
important that public and private facilities are deployed in a coordinated and strategic manner.
Nutrient reduction strategies may be laid out in a town’s Comprehensive Waste Management
Plan (CWMP), a Targeted Watershed Management Plan (TWMP) that may involve several
towns, or in other planning documents. When a nutrient reduction strategy has been deemed
consistent with the Cape Cod Area Wide Water Quality Management Plan Update (208 Plan
Update) by the Cape Cod Commission, private WWTFs that are not owned or operated by a
town, municipality or district may be located in areas where a) no public WWTF is proposed
within three years of the proposed project construction date under the nutrient reduction
strategy, or b) where the nutrient reduction strategy relies upon the proposed private WWTFs to
achieve nutrient reduction goals. In areas where an approved nutrient management plan is not
yet in place, private WWTFs are an encouraged strategy for maintaining or improving
groundwater quality.
Certain natural resource areas are not appropriate locations for WWTF installation.
Discharging treated wastewater to sensitive environmental areas, such as Areas of Critical
Environmental Concern (ACECs), wetlands and buffer areas, barrier beaches, coastal dunes, and
critical wildlife habitats may negatively impact those resources by degrading water quality
and/or modifying natural hydrologic processes. In addition, the vulnerability of FEMA V zones,
FEMA A zones, floodways, barrier beaches and coastal dunes to natural disaster (flooding,
storm surge, etc.) makes them generally inappropriate for siting WWTFs. A WWTF may be
proposed in FEMA A zones only when it is designed to specifically tie-in and treat existing
sources of wastewater within that same FEMA A zone. Applicants can determine whether a
project site is within any of the prohibited zones by consulting the RPP Data Viewer for further
detail.
Wastewater treatment and collection systems that are proposed within FEMA flood zones
should be designed to prevent elevated groundwater or floodwaters from entering the collection
system during storm events.
5 ppm Nitrogen Concentration Limit in Effluent or at Downgradient Boundary
Projects proposing WWTFs are required to maintain nitrogen at 5 ppm or lower when measured
at the downgradient property boundary. As it can be assumed that nitrogen discharged to
groundwater will flow advectively without dilution to the property boundary, nitrogen
concentrations generally remain constant or decrease slightly following discharge. WWTF
effluent nitrogen is monitored as part of a MassDEP groundwater discharge permit (GWDP),
and projects with 5 ppm nitrogen or less in effluent are deemed to have met this requirement.
DRAFT Water Resources Technical Bulletin Page 14
Projects proposing to discharge nitrogen at concentrations greater than 5 ppm may use a
groundwater model, or groundwater monitoring data to demonstrate that nitrogen
concentration in groundwater at the downgradient property boundary will not exceed 5 ppm
and the results must be submitted to the Commission for review and confirmation.
For Projects within Wellhead Protection Areas (WHPAs) and Potential Public Water Supply Areas (PPWSAs)
Protection of existing and future drinking water wells (WHPAs and PPWSAs)
As additional development on land areas that contribute (or may contribute in the future) to
drinking water wells will directly impact drinking water quality, certain additional protections
are required to prevent excessive nutrient loading and minimize the risk of contamination.
Lands receiving precipitation that contribute to the recharge of public drinking water supply
wells are considered Wellhead Protection Areas (WHPA). These include MADEP approved
Zone IIs, interim wellhead protection areas, and certain town delineated water protection
districts that extend beyond the Zone II limits.
Potential Public Water Supply Areas (PPWSAs) were first identified in the Priority Land
Acquisition Assessment Project (PLAAP) as areas that may be suitable for future development of
drinking water supplies. These land areas meet various requirements including minimum
parcel size, surrounding land uses that are protective of groundwater quality, and the absence of
incompatible upgradient or nearby land uses (e.g., landfills, hazardous waste sites or
contaminant plumes, dense development).
Hazardous Materials Limitations
Any chemical or substance that when released into the environment will pose a significant
contaminant threat to groundwater and drinking water supplies is considered a hazardous
material. Examples include petroleum products, petroleum distillates, organic and inorganic
solvents, oil-based paints, oil-based stains, insecticides, herbicides, rodenticides, and pesticides.
Any Hazardous Waste, Universal Waste, or Waste as defined in the Massachusetts Hazardous
Waste Regulations (310 CMR 30.010) are considered Hazardous Wastes. Hazardous Wastes do
not include Hazardous Materials or biomedical wastes regulated under the Massachusetts State
Sanitary Code (105 CMR 480.00). Hazardous Materials do not include Hazardous Wastes,
Articles, Consumer Products, or Cosmetics.
In order to minimize the potential risk of introducing contamination to existing or future water
supplies, the following limits on hazardous materials / hazardous wastes apply in WHPAs and
PPWSAs.
(a) 275 gallons of oil on site at any time to be used for heating of a structure, or to supply an
emergency generator
(b) 25 gallons or equivalent dry weight, total, of Hazardous material(s) on site at any time
(excluding oil as classified in part (a))
DRAFT Water Resources Technical Bulletin Page 15
(c) 55 gallons of Hazardous Waste generated at the Very Small Quantity Generator level as
defined in Massachusetts Hazardous Waste Regulations (310 CMR 30.000) and
accumulated or stored on-site at any time.
Applicants should provide to the Commission an inventory which includes the identities and
quantities of expected and potential hazardous materials/wastes that will be generated, used, or
stored on site for the proposed use. Similar inventories should be provided for the previous use
(when applicants propose to reduce the quantity of hazardous materials present on site through
redevelopment) or for the proposed offset site (when applicants propose to eliminate the same
or greater quantity of hazardous materials from another project, site, or facility within the same
WHPA or PPWSA).
Certain types of development even when remaining within the above limits on hazardous
materials and hazardous wastes may present a greater potential for contaminating groundwater.
Stormwater systems serving areas used for fleet storage, vehicle maintenance, electrical
transmission/generation. loading docks, waste handling, and any other use with greater
potential for groundwater contamination must include a means to halt discharge from the
stormwater system (flow arresting device) in the event of a spill, accident, or release of any
source of contamination.
1 ppm nitrogen limit
PPWSAs are a finite and increasingly limited resource that require extra levels of protection to
ensure they remain available to provide a stable drinking water system able to meet future water
supply needs.
In order to maintain the suitability of PPWSAs to supply drinking water in the future, site wide
nitrogen loading is limited to 1 ppm in these areas.
Landscape Management Practices
Landscaping is an important part of development that may play a role in screening, stormwater
treatment and overall visual aesthetics. Proper maintenance of landscaping is necessary to
maintain its continued function, and several approaches are encouraged to minimize the
environmental impacts presented by chemical fertilizer and pesticide usage during these
activities. Additional detail regarding landscaping is provided in the Community Design
Technical Bulletin.
Integrated pest management and biorational landscape management make use of an inspection
and monitoring approach, along with a variety of pest control measures to maintain pest
populations below levels that can cause significant damage or loss to installed landscaping. Soil
nutrient and moisture testing should be employed with fertilization and irrigation methods
tailored to the specific site conditions. Accurate identification of pests and monitoring of their
populations should be used to determine rate and frequency for applying pest control (which
may include chemical, cultural, and biological controls) to maintain pest population levels below
identified thresholds. If no effective non-pesticide control measures are available, a key concept
of integrated pest management is that selected pesticides should result in the lowest possible
DRAFT Water Resources Technical Bulletin Page 16
risk to health or the environment. The University of Massachusetts Extension provides a more
detailed background and ongoing guidance regarding integrated pest management at
(http://ag.umass.edu/integrated-pest-management).
Roadway and Parking Area Design
In WHPAs and PPWSAs, roadways and parking areas should be designed to minimize
impervious area, with pervious construction materials used whenever possible to minimize the
impact of stormwater on drinking water supplies.
Projects in Impaired Areas
Areas where water quality has been degraded by land uses such as high-density residential,
commercial, or industrial development; landfills, septage, and wastewater treatment discharges;
and areas downgradient of these sources that are similarly impacted are considered Impaired
Areas.
Projects located in Impaired Areas that are outside other mapped water resource areas including
WHPA’s, PPWSA, MWRAs and FWRAs may use existing groundwater quality data, distance
from existing natural or built water resources, and position upstream or downstream of those
resources relative to groundwater flow direction to demonstrate that nitrogen loading above 5
ppm will not adversely impact those resources.
DETAILED METHODS FOR MEETING OBJECTIVE WR2
Objective WR2: Prevent loading of phosphorous to fresh water resources
Phosphorous, unlike nitrogen, is attenuated in the subsurface. Studies of phosphorous
transport indicate that phosphorous loads associated with septic systems are typically
attenuated within 300 feet of downgradient transport, through sorption to soil minerals or
uptake during microbial or plant growth. Therefore, siting septic systems outside a 300 foot
upgradient buffer to fresh surface waters, and maintaining or increasing the width of vegetative
buffers with active plant growth will be protective of water quality. For projects with sufficiently
large flows in pond recharge areas, the phosphorous load may exceed the attenuation rate of the
soils and ultimately result additional phosphorous loading to the pond even when the discharge
is located greater than 300 feet upgradient of the pond. In these situations, additional modeling
which looks at groundwater flow, soil characteristics, and wastewater characteristics will be
required to characterize the site and evaluate the expected extent of phosphorous transport.
DRAFT Water Resources Technical Bulletin Page 17
DETAILED METHODS FOR MEETING OBJECTIVE WR3
Objective WR3 – Prevent and mitigate loading of nutrients and other contaminants to marine
water resources.
Cape Cod’s marine waters provide a variety of complex habitats necessary to support shellfish
populations, marine fisheries, migratory birds, and many other plant and wildlife populations.
Less than 25% of the Cape Cod land surface drains to open marine waters (e.g., Cape Cod Canal,
Cape Cod Bay, Nantucket Sound, Atlantic Ocean). Instead, the majority of land surfaces
discharge to estuaries or coastal embayments through groundwater flow in the Cape Cod
aquifer. Marine Water Recharge Areas (MRWA) are defined as watershed areas that contribute
to a marine embayment as defined by the topography of the water table.
As of 2018, the Massachusetts Estuary Project (MEP) has studied 40 of Cape Cod’s 53 coastal
embayments. MEP continues to study coastal embayments on Cape Cod to determine the
critical nitrogen load for each embayment, which is the maximum amount of nitrogen input that
can be assimilated without negatively impacting ecosystem function and provision of habitat. A
total maximum daily load (TMDL) is the maximum amount of a pollutant that a waterbody can
assimilate on a daily basis and still support a healthy ecosystem, which for Cape Cod’s coastal
embayments is determined by MassDEP based on the results of the MEP studies. Four of the
embayments studied to date have been found to have assimilative capacity for nitrogen;
therefore, no TMDL is necessary at this time. The remaining watersheds that have been studied
require nitrogen reduction to achieve healthy ecosystem function.
Additional information about the MEP, embayment reports, and applicable TMDLs is available
at the MassDEP website (https://www.mass.gov/guides/the-massachusetts-estuaries-project-
and-reports).
The Cape Cod Section 208 Area Wide Water Quality Management Plan (208 Plan Update) was
completed in 2015 in response to the need for a new approach to planning for and implementing
nitrogen reduction plans and projects to achieve the critical nitrogen loads. The 208 Plan
Update expands the available nutrient reduction strategies beyond source reduction to include
remediation and restoration approaches. This allows for a range of strategies to be employed,
depending on the placetype and context within the watershed of the area where nitrogen
reduction is needed (ex. in-embayment strategies, such as the use of aquaculture, may be used
in watersheds where low density development causes inefficient source reduction from a cost
perspective). The 208 Plan Update provides a framework for applying watershed based
solutions to reduce nitrogen in impaired embayments. CWMPs, TWMPs, and other municipal
nutrient management plans and projects deemed consistent with the 208 Plan Update and those
that are permitted by MassDEP through a watershed permit determine the approach and timing
of solutions within an individual watershed or sub-watershed, and development that conforms
with the approved nutrient management plan is considered to meet Objective WR3.
Development is generally prohibited from adding nitrogen to areas that contribute to nitrogen-
overloaded coastal waters. Embayments which have nitrogen loading greater than or equal to
their critical nitrogen loads are considered nitrogen-overloaded and may or may not have a
TMDL associated with them. Documented water quality problems may also exist (e.g., shellfish
DRAFT Water Resources Technical Bulletin Page 18
or beach closures, failure to meet Massachusetts Surface Water Quality Standards) in areas
where a critical nitrogen load or TMDL has not yet been established, in which case projects are
required to mitigate or offset any proposed nitrogen load as described below. Nitrogen
additions from the proposed project may be mitigated by connecting existing development to an
existing sewer system, by tying-in and providing wastewater treatment to existing development
currently served by septic systems, or by other means that result in the overall nitrogen load
within the (sub)watershed being maintained or reduced. Applicants proposing to use this form
of mitigation should provide a calculation of the expected nitrogen load generated by the
project, the existing nitrogen sources (number, type, estimated load) proposed for mitigation,
and a detailed description of the means by which treatment of those sources will be
implemented (which could include financing of sewer tie-ins, a contract to provide wastewater
treatment, installation and operation of I/A systems at existing properties, or other means of
demonstrating how the proposed mitigation will ultimately be achieved).
Projects proposed in Placetype areas where development is encouraged and infrastructure
needed to meet nitrogen reduction requirements is lacking may provide a monetary offset of the
project’s nitrogen load which can be used to support expansion of wastewater treatment
operations.
Monetary Nitrogen Offset
Placetype Monetary Nitrogen Offset Available
Natural Areas No
Rural Development Areas No
Suburban Development Areas Where appropriate
Historic Character Areas Where appropriate
Maritime Area Yes
Community Activity Center Yes
Industrial Activity Center Yes
Military and Transportation Areas Yes
Activity centers may have existing sewer collection and treatment systems, or have sufficient
density of development and other infrastructure to justify future connection to sewer systems.
To promote the desired development density and facilitate future sewering, projects in
Community Activity Centers, Maritime Areas, Industrial Activity Centers or Military and
Transportation Areas without available sewer connections may contribute a monetary offset
calculated as up to $8,290 per kilogram nitrogen load to be offset. The monetary offset is based
on the cost of removing one kilogram of nitrogen per year for 20 years using a conventional
sewer collection system and municipal wastewater treatment. The monetary offset is calculated
based on reductions from 26.25 ppm, consistent with the MEP assumption for a standard septic
system and with values used for planning purposes in watershedMVP. See Appendix C for
further information on the methodology. Patterns of development in Suburban Development
Areas are generally too spread out to make centralized wastewater collection financially feasible,
DRAFT Water Resources Technical Bulletin Page 19
while Historic Character Areas may present special challenges to sewering in terms of access
below grade and age of existing infrastructure. For these reasons monetary offsets are allowed
in limited circumstances at the discretion of the Commission in those Placetype Areas. Factors
that will be considered in determining offsets in these placetypes might include, but are not
limited to, existing development, business and community activity, a community’s vision for the
area as described in their Local Comprehensive Plan or other planning documents, and any
plans for construction of infrastructure that will take place within five years.
DETAILED METHODS FOR MEETING OBJECTIVE WR4
Objective WR4: Manage and treat stormwater to protect and preserve water quality
Undisturbed natural areas generally slow the velocity of runoff, allowing natural processes to
remove nutrients and contaminants and facilitating recharge so that rain largely stays where it
falls. When natural areas are covered by impervious surfaces, the resulting stormwater runoff
from rainfall or snow melt travels at higher velocities and in more concentrated flows, making
both infiltration and removal of nutrients or contaminants more challenging. As rainfall
amounts and patterns continue to change, the increased frequency of high intensity storms
present challenges and risks to many forms of infrastructure. Stormwater systems designed to
handle increased runoff in a distributed and decentralized manner should be an integral part of
community planning for water quality, flood protection, climate resilience, and capital
infrastructure. Across the Commonwealth of Massachusetts, untreated stormwater runoff is the
single largest source of water body impairment. In order to maintain and improve the health of
Cape Cod’s water resources and the communities that depend on them, it is critical to manage
both the quantity and quality of stormwater runoff that is generated by development.
Stormwater system design
To protect existing water resources and maintain safety by preventing flooding/ponding of
water on roadways, stormwater systems should be designed to both capture and infiltrate
rainfall from roadways, parking lots, and rooftops on the project site. Stormwater runoff
collects sediment, bacteria, nutrients, and pollutants from the impervious surfaces it flows over,
which negatively impact ground and surface water resources if not adequately treated. Properly
designed and maintained treatment BMPs minimize the amount of these pollutants that are
ultimately discharged to surface waters and groundwater. The Massachusetts Stormwater
Handbook (https://www.mass.gov/guides/massachusetts-stormwater-handbook-and-
stormwater-standards) provides guidance for designing stormwater structures to meet the water
quality treatment and storage/infiltration aspects of Objective WR4. To best account for
changing patterns in precipitation, updated projections for extreme precipitation events should
be used whenever designing new stormwater systems. The Massachusetts Stormwater
Handbook currently uses precipitation data from U.S. Weather Service Technical Paper 40,
which was published in 1961. Projections from the National Oceanic and Atmospheric
Administration (NOAA Atlas 14, published 2015) and Northeast Regional Climate Center
(Extreme Precipitation Analysis, http://precip.eas.cornell.edu/) utilize much more recent data
than Technical Paper 40, and MassDEP currently recommends using the most conservative
(largest) rainfall volume from among the three resources.
DRAFT Water Resources Technical Bulletin Page 20
Applicants should provide a stormwater maintenance and operation plan certified by a Professional Engineer that details a schedule for inspection, monitoring, and maintenance; and identifies the party responsible for implementation. The applicant should also agree to provide a Professional Engineer certified letter that details inspection of the stormwater facilities one year after completion and certifies that the system was installed and continues to function as designed and approved.
Separation from High Groundwater
A calculation of the high groundwater level should be performed to ensure that stormwater
facilities are designed to maintain the proper 2 foot separation from the water table under all
conditions. Appendix B – Estimation of High Groundwater Levels describes a calculation that
may be used to adjust water levels measured at discrete Cape Cod locations and estimate high
groundwater levels at those same locations. The approach was developed in cooperation with
the US Geological Survey and is based on historic long-term groundwater-level measurements at
index wells located across Cape Cod.
Total Suspended Solids Removal and Water Quality Treatment Volume
Stormwater systems should be designed to remove 80% of Total Suspended Solids (TSS) and
provide water quality treatment for the first inch of precipitation from all impervious surfaces
on the site. An estimate of the TSS removal achieved in the stormwater treatment train(s) can
be performed using MassDEP’s TSS Removal Calculation Worksheet.
(https://www.mass.gov/files/documents/2016/08/nn/tss.xls)
The required water quality treatment volume can be calculated using the following equation.
WQ treatment volume (ft3) = impervious area (ft2) * (1 inch / 12 inches per foot)
Storage/treatment volume provided by most stormwater BMPs can be calculated with a stage-
storage table, where the incremental volume of each stage is given by
Incremental volume (ft3) = (elevation2 – elevation1) * ((area2+area1)/2)
Table 1: Example stage-storage volume calculation
Elevation (ft) Surface Area
(ft2)
Incremental
volume (ft3)
Cumulative
volume (ft3)
72.5 210 0 0
73 660 217.5 217.5
73.5 1,020 420 637.5
74 1,500 630 1267.5
The Massachusetts Stormwater Handbook contains detailed explanations, examples, and
guidance for additional methods which may be used to calculate required volume(s) in Volume
3, Chapter 1 – Standard 4.
DRAFT Water Resources Technical Bulletin Page 21
DETAILED METHODS FOR MEETING OBJECTIVE WR5
Objective WR5: Manage groundwater withdrawals and discharges to maintain hydrologic
balance in a way that is protective of surface and groundwater resources
Projects that exceed 20,000 gpd withdrawals should provide adequate groundwater
characterization to demonstrate that drawdown of the groundwater due to pumping will not
negatively impact nearby surface waters and wetlands, which may be connected to and fed by
groundwater. The study should include mapping of surface water morphology and comparison
of existing and affected water-table fluctuations. In addition, wastewater discharges should
provide adequate groundwater characterization to determine the maximum expected height of
groundwater mounds and the potential for groundwater with this additional mounding to
breakout above the land surface. Projects should provide a high groundwater estimation
consistent with the methodology of Appendix B –Estimation of High Groundwater Levels to
incorporate into modeling of potential mounding.
DRAFT Water Resources Technical Bulletin Page 22
DETAILED WATER RESOURCES APPLICATION REQUIREMENTS
1. The project narrative should include a description of the site location and any applicable
resource areas, existing site conditions, and how the proposed project will change those
conditions during and after construction. Areas that should be considered include:
a. Presence of existing and proposed drinking water wells within 400 feet of project
boundaries
b. Quantity of wastewater generation expected and proposed treatment
c. Source of drinking water supply
d. Changes in natural and impervious area cover
e. Stormwater management and treatment
f. for previously developed sites a description of historical site usage, and if a
reportable release under the MCP has occurred at the project site or if a Site
Release Tracking Number (RTN) has been assigned for the site by MassDEP, a
Chapter 21E site assessment or other Environmental Site Assessment
information should be submitted for Commission review.
2. A calculation of site-wide nitrogen loading should be performed using the method
described in Appendix A.
3. The site design should specify the location of the proposed septic system or wastewater
treatment facility and identify downgradient resources as described in WR1 – detailed
methods.
4. The stormwater report should include a description of the proposed system (for small
systems, the description in the project narrative may be sufficient) and the following
information as necessary:
a. Soil survey and / or boring logs
b. Calculation of high groundwater level to ensure that stormwater facilities are
designed with proper separation from the water table as described in WR4 –
detailed methods.
c. Estimate of TSS removal achieved in stormwater treatment train(s) using
MassDEP’s TSS Removal Calculation Worksheet
(https://www.mass.gov/files/documents/2016/08/nn/tss.xls)
d. Calculation of required water quality treatment volume and treatment volume
provided as described in WR4 – detailed methods.
e. Engineering design drawings or cut sheets for proposed stormwater system
components
5. Operations and maintenance plans for all proposed water systems (drinking water
supply, stormwater, and wastewater treatment) should be submitted for Commission
review
DRAFT Water Resources Technical Bulletin Page 23
DEFINITIONS
Best Management Practice (BMP) – structural or procedural control measures implemented to
reduce the quantity and velocity of stormwater runoff, and improve water quality
Fresh Water Recharge Area (FWRA) – Watershed area that contributes to a fresh water pond as
defined by the topography of the water table.
Hazardous Material – Any chemical or substance that when released into the environment will
pose a significant contaminant threat to groundwater and drinking water supplies.
Hazardous Materials / Hazardous Wastes, Household Quantity of – quantities less than the
following limits are considered Household Quantities:
(d) 275 gallons of oil on site at any time to be used for heating of a structure, or to supply an
emergency generator
(e) 25 gallons or equivalent dry weight, total, of Hazardous material(s) on site at any time
(excluding oil as classified in part (a))
(f) 55 gallons of Hazardous Waste generated at the Very Small Quantity Generator level as
defined in Massachusetts Hazardous Waste Regulations (310 CMR 30.000) and
accumulated or stored on-site at any time.
Hazardous Waste – Any Hazardous Waste, Universal Waste, or Waste as defined in the
Massachusetts Hazardous Waste Regulations (310 CMR 30.010), not including Hazardous
Materials or biomedical wastes regulated under the Massachusetts State Sanitary Code (105
CMR 480.00).
Impaired Area –Impaired Areas are where groundwater may have been degraded by point and
non-point sources of pollution, including but not limited to areas with unsewered residential
developments with an average lot size of less than 20,000 square feet; landfills, septage, and
wastewater treatment plant discharge sites; and areas of high-density commercial and industrial
development and those downgradient areas where groundwater may have been degraded by
those sources.
Impervious Area – Land area that is covered by surfaces which do not permit precipitation to
naturally recharge. Typically includes paved surfaces, roadways, parking areas, and rooftops.
Infill – Development of new housing, commercial, or other amenities on scattered or
discontinuous sites within existing substantially built-up areas.
Marine Water Recharge Area (MWRA) – Watershed area that contributes to a marine
embayment as defined by the topography of the water table, and determined by United States
Geological Survey (USGS) modeling as part of the Massachusetts Estuaries Project (MEP)
Potential Public Water Supply Area (PPWSA) – Land identified as suitable for the development
of public water supplies.
DRAFT Water Resources Technical Bulletin Page 24
Wastewater treatment facility (WWTF) – Wastewater treatment and collection systems that are
designed to treat flows greater than 10,000 gallons per day.
Wellhead Protection Area (WHPA) - Lands receiving precipitation that contribute to the
recharge of public drinking water supply wells are considered Wellhead Protection Areas
(WHPA). These include MADEP approved Zone IIs, interim wellhead protection areas, and
certain town delineated water protection districts that extend beyond the Zone II limits.
REFERENCES
Cape Cod Commission, 1992. Estimation of High Groundwater Levels for Construction and
Land Development, Technical Bulletin 92-001
Cape Cod Commission, 1999. Priority Land Acquisition Assessment Project – A guide to
evaluating the suitability of land for future water supply sites
Cape Cod Commission, 2001. Priority Land Acquisition Assessment Project Phase II
Massachusetts Estuaries Project and Reports
https://www.mass.gov/guides/the-massachusetts-estuaries-project-and-reports
The Massachusetts Stormwater Handbook and Stormwater Standards
(https://www.mass.gov/guides/massachusetts-stormwater-handbook-and-stormwater-
standards)
National Weather Service, 1961. Technical Paper 40: Rainfall Frequency Atlas of the United
States
National Oceanic and Atmospheric Administration, 2015. Atlas 14 Precipitation Frequency Data
Server
https://hdsc.nws.noaa.gov/hdsc/pfds/pfds_map_cont.html
Northeast Regional Climate Center, 2011. Extreme Precipitation Analysis.
http://precip.eas.cornell.edu/
USGS, 1986. Ground-Water Resources of Cape Cod, Massachusetts Hydrologic Investigations
Atlas-692
United States Environmental Protection Agency, 2009. Incorporating Environmentally
Sensitive Development into Municipal Stormwater Programs
https://www.epa.gov/sites/production/files/2015-
11/documents/region3_factsheet_lid_esd.pdf
Metropolitan Area Planning Council, 2014. Low Impact Development Toolkit
https://www.mapc.org/resource-library/low-impact-development-toolkit/
Grow Smart Maine, 2015. Building “Smart”: Environmentally Sensitive Design
https://growsmartmaine.org/wp-content/uploads/2015/08/Enviro_Sensitive_Design-Final-
21-Nov-06.pdf
University of Massachusetts Extension, 2018. Integrated Pest Management Program
http://ag.umass.edu/integrated-pest-management
DRAFT Water Resources Technical Bulletin Page 25
APPENDIX A: NITROGEN LOADING GUIDANCE FOR WATER RESOURCES
The Water Resource Goal of the Cape Cod Commission’s Regional Policy Plan is “to maintain a
sustainable supply of high quality untreated drinking water and protect, preserve or restore the
ecological integrity of fresh and marine surface waters.” The Water Resources Technical
Bulletin contains five (5) Objectives that are distinguished by Water Resource Area and
Placetype. The Water Resource Areas are: Wellhead Protection Areas, Fresh Water Recharge
Areas, Marine Water Recharge Areas, and Potential Water Supply Areas. The Water Resources
Technical Bulletin also recognizes Impaired Areas where water quality may have been impaired
from existing development.
THE APPLICANT WILL NEED TO KNOW SPECIFIC PROJECT INFORMATION TO
COMPLETE A NITROGEN LOADING CALCULATION
A methodology has been adopted by the Commission for calculating groundwater nitrogen
loading concentrations. The methodology is based on information and parameters describing
wastewater flows; stormwater runoff volumes; lawn sizes, fertilization and leaching rates;
respective nitrogen masses and concentrations attributable to these nitrogen sources, and
precipitation dilution factors as described below and shown in the example calculations.
WORKSHEET INSTRUCTIONS
The applicant will need to know the information listed below to complete a Nitrogen Loading
calculation:
Identify the Water Resource Area the project is located in, if any (RPP Data Viewer);
1. Upland area of site (square feet);
2. Wastewater flow rate (calculated pursuant to 310 CMR 15.203);
3. Actual Flow rate determined by occupancy rate;
4. Average residential flow rate, calculated from the Title 5 design + the Actual Flow rate
5. Type of septic system proposed (e.g. alternative design pursuant to 310 CMR 15.280);
6. Paved and roof areas (assumed 2,500 square feet for residential projects);
7. Proposed lawn area (assumed 5,000 square feet for residential projects);
A summary of Nitrogen Loading conversion factors and sample calculations are shown on the
following pages.
A Nitrogen Loading and Mitigation Worksheet is available at < link to be inserted in final
draft>.
DRAFT Water Resources Technical Bulletin Page 26
SUMMARY OF NITROGEN LOADING VALUES
TARGET CONCENTRATION: 5 ppm (milligram/liter) NO3-N
WASTEWATER Residential Concentration: 35 ppm NO3-N Flow: Title 5 (310 CMR 15.02) Non-residential Concentration: 35 ppm NO3-N Flow: Title 5 Design or actual documented flows
OCCUPANCY: Range (Actual town rate to 2 people per bedroom)
LAWNS Area: 5,000 ft2 Fertilizer: 3 lbs/1,000 ft2 of lawn Leaching: 25% RECHARGE From impervious surfaces: 40 inches per year Concentrations Road runoff: 1.5 ppm NO3-N Roof runoff: 0.75 ppm NO3-N Natural areas Barnstable: 18 inches per year Bourne: 21 in/yr Brewster: 17 in/yr Chatham: 16 in/yr Dennis: 18 in/yr Eastham: 16 in/yr Falmouth: 21 in/yr Harwich: 17 in/yr Mashpee: 19 in/yr Orleans: 16 in/yr Provincetown: 16 in/yr Sandwich: 19 in/yr Truro: 16 in/yr Wellfleet: 16 in/yr Yarmouth: 18 in/yr
DRAFT Water Resources Technical Bulletin Page 27
DRAFT Water Resources Technical Bulletin Page 28
DRAFT Water Resources Technical Bulletin Page 29
Water Resources Nitrogen Loading and Mitigation WorksheetSee Technical Bulletin 91-001 for further details: http://www.capecodcommission.org/regulatory/NitrogenLoadTechbulletin.pdf
Project Nitrogen Load Wastewater Proposed development Existing (if redevelopment)
Calculate (A') through (P') as w/ (A) through (P):
1. Enter value Project Title-5 wastewater flows: gpd (a) Title-5 wastewater flows: gpd
Enter value Actual wastewater flows: * (b) Actual wastewater flows: *
Calculated value Average wastewater flows: gpd (a)+(b) 2= (A) Ave. wastewater flows: gpd (A')
Place √ in applicable box: * Title-5 flows prescribed by TB91-001 for commercial uses
Yes No
Will the project be connected to sewer ? Place √ in applicable box:
Yes No
Is project Title-5 wastewater flow 10,000 gpd or greater ? Is existing development on sewer ?
(If 'Yes', then the project must be reviewed for consistency with MPS WR6) (If 'Yes', then go to line 2.)
Place √ in applicable box and multiply unsewered wastewater flow by applicable conversion factor:
Standard Title-5 System (35-ppm-N) x 0.048359 Standard Title-5 System
DEP-approved I/A System (25-ppm-N) x 0.034542 DEP-approved I/A System (commercial)
DEP-approved I/A System (19-ppm-N) x 0.026252 Type of system: ________________ DEP-approved I/A System (residential)
Groundwater Discharge (10-ppm-N) x 0.013817 Wastewater Treatment Facility (GWDP)
Calculated value Wastewater nitrogen load (Title-5 flows) = kg-N/yr (B) kg-N/yr (B')
ALARM
Calculated value Wastewater nitrogen load (Actual flows) = kg-N/yr (C) kg-N/yr (C')
ALARM wastewater offsets
Stormwater Runoff
Town: ___________________
Enter value Recharge rate for town (for natural areas from Technical Bulletin 91-001): (RECH)
Enter value Project site area: acres (D) Project site area: acres (D)
Enter value Project site wetland area: acres (E) Project site wetland area: acres (E)
Calculated value Project site upland area: acres (F) Project site upland area: acres (F)
Calculated value Pervious unpaved upland: acres (G) Pervious unpaved upland: acres (G')
Enter values % using LID Paved area: s.f. (H) Paved area: s.f. (H')
Factor may be adjusted for employment of LID → x 1.4158E-04 1.416E-04
Calculated value = kg-N/yr (I) Paving runoff offset: kg-N/yr (I')
Enter value Roof area: s.f. (J) Roof area: s.f. (J')
x 7.0792E-05
Calculated value = kg-N/yr (K) Roof runoff offset: kg-N/yr (K')
Fertilizer
Enter value Managed turf: s.f. Managed turf: s.f.
x 3.4019E-04
Calculated value = kg-N/yr (L) Fertilizer offset: kg-N/yr (L')
Total Nitrogen Load
Calculated value Total project nitrogen load (Title-5 flows): kg-N/yr (M)= (B)+(I)+(K)+(L) kg-N/yr (M')
Calculated value Total project nitrogen load (Actual flows): kg-N/yr (N)= (C)+(I)+(K)+(L) Existing nitrogen load (Actual flows): kg-N/yr (N')
Calculated value Nitrogen load per acre (Average): kg-N/yr/acre (O)= (M)+(N) 2 (F) Nitrogen offset per acre: kg-N/yr/acre (O')
Nitrogen Loading Concentration Existing nitrogen loading concentrations:
Calculated value
Project nitrogen loading concentration (Title-5 flows):
Calculated value
Project nitrogen loading concentration (Actual flows):
Calculated value
Project nitrogen loading concentration (Average):
next page -->
Actual flows
(P)=
(R')(R)=
}
(Q)=
Recharge rate for town (inches; for natural areas
from Technical Bulletin 91-001):
(a)723.76 + (G)x(RECH)9.7286 + (H)10,594 + (K)0.75 Title-5 flowsppm-N
ppm-N
Average
_________(M)_________
ppm-N
DRAFT
(P)+(Q) 2
(Q')
ppm-N ppm-N
_________(N)_________
(b)723.76 + (G)x(RECH)9.7286 + (H)10,594 + (K)0.75
Existing nitrogen load (Title-5 flows):
ppm-N (P')
DRAFT Water Resources Technical Bulletin Page 30
Resource/ Impact Based Criteria
Marine Water Recharge Areas
Yes No
2.
(If 'No', then go to line 3.)
Enter value Fair Share nitrogen-loading limit** : kg-N/year/acre (S)
Does project's nitrogen load (O) exceed the existing load (O') AND the critical nitrogen load (S) ?
(If 'No', then go to line 3.)
Calculated value Excess project nitrogen load to be mitigated: kg-N/yr (T)= LESSER OF (O)-(S) x(F) AND (O)-(O') x(F)
x 1,550
Calculated value = $ (U)
Place √ in box if applicant intends to make this payment (S)
(If not checked, then the project must provide an alternative strategy for meeting its Fair Share nitrogen load pursuant to MPS WR3.4)
Groundwater Quality
Yes No
3. Does the project's nitrogen loading concentration in groundwater (R) exceed the greater of 5 ppm or the existing concentration (R') ?
(If 'Yes' and the project is located in a Water Quality Improvement Area (Map WR5), the project may need to provide an alternative strategy for meeting MPS WR1.1 and WR5.4)
Potential Public Water Supply Areas
Yes No
4. Is project in a Potential Public Water Supply Area (PPWSA, Map WR2) ?
(If 'No', then go to line 5.)
Has the Town or local water district documented the release of the site from consideration as a PPWSA ?
(If 'Yes', then go to line 5.)
Does the project's nitrogen loading concentration (R) exceed the greater of 1 ppm or the existing concentration (R') ?
(If 'Yes', the project must provide an alternative strategy for meeting MPS WR2.6)
Does the project use, treat, generate, store or dispose of hazardous materials in excess of the greater of a) household quantities or b) existing quantities ?
(If 'Yes', the project must provide an alternative strategy for meeting MPS WR2.2)
Wellhead ProtectionAreas
Yes No
5. Is project in a Wellhead Protection Area (WHPA, Map WR2) ?
(If 'No', then go to line 6.)
Does the project's nitrogen loading concentration (R) exceed the greater of 5 ppm or the existing concentration (R') ?
(If 'Yes' and the project is located in a Water Quality Improvement Area (Map WR5), the project must provide an alternative strategy for meeting MPS WR2.1)
Does the project use, treat, generate, store or dispose of hazardous materials in excess of the greater of a) household quantities or b) existing quantities ?
(If 'Yes', the project must provide an alternative strategy for meeting MPS WR2.2)
Fresh Water Recharge Areas
Yes No
6. Is project wastewater disposed of within 300 feet of a stream or fresh surface water body (Map WR4)?
(If 'No', then go to line 7.)
Is the project located hydraulically upgradient of a stream or fresh surface water body ?
(If 'Yes', the project must provide an alternative strategy for meeting MPS WR4.1)
Other Potential Impacts
Yes No
7. Will the project withdraw more than 20,000 gallons of water per day ?
(If 'Yes', then the project must provide documentation demonstrating that there will not be significant impacts to water levels, surface waters and wetlands)
8.
Name of Marine Water Recharge Area sub-embayment
(from RPP Water Resource Classification Map II ):
Is the project in Marine Water Recharge Area (MWRA, Map WR3) with a nitrogen-loading limit OR in a MWRA that discharges to coastal waters with documented impaired water quality** ?
The project must demonstrate compliance with MPS WR1 and MPS WR7, including use of Low Impact Development to mitigate impacts of stormwater runoff and O & M plans for maintaining stormwater infrastructure and landscaping.
** Fair Share nitrogen-loading limit is determined through either a Total Maximum Daily Load (TMDL), a Massachusetts Estuaries Project-accepted technical report, or specified by a Commission-approved comprehensive wastewater management plan pursuant to MPS
WR3.1 & WR3.3. If a nitrogen-loading limit is unavailable and impaired water quality has been documented for the receiving coastal waters, the nitrogen loading limit shall be 0 kg-N/yr per acre pursuant to MPS WR3.2.
DRAFT Water Resources Technical Bulletin Page 31
APPENDIX B: ESTIMATION OF HIGH GROUND-WATER LEVELS
The Water Resources Technical Bulletin Appendix B - Estimation of High GW is available at
<link to be inserted in final draft>.
DRAFT Water Resources Technical Bulletin Page 32
APPENDIX C: MONETARY NITROGEN OFFSET
For projects that will not connect to sewer, monetary nitrogen offsets may be allowed in certain
circumstances. The appropriate Placetypes and methods for providing a monetary nitrogen
offset are generally set forth in the 2018 Water Resource Technical Bulletin.
Nitrogen Management Policy
The 2018 RPP encourages growth in certain areas, such as Community Activity Centers, and
discourages growth in other areas, such as in Natural Areas. For that reason, the per kilogram
nitrogen monetary offset may be applied up to the maximum amount of $8,290; however, a
lesser dollar amount per kilogram of nitrogen ($0 to less than $8,290) may be applied in areas
where growth is encouraged.
The maximum dollar per kilogram amount of $8,290 for nitrogen offsets is based on Capital and
20-year O&M costs for nitrogen removal by conventional sewering as derived from the
Comparison of Costs for Wastewater Management Systems Applicable to Cape Cod, updated in
2014. The infrastructure and operational costs in the 2014 report have not been adjusted for
inflation to present day costs. In this regard, the $8,290 per kilogram figure is a conservative
estimate of actual costs in that todays costs will be higher.
Calculation of Monetary Nitrogen Offset
Calculated cost to remove nitrogen with a typical wastewater treatment facility:
Capital cost (assumed design flow of 1.5 mgd; 100 linear feet per parcel connected)
$181 million (present worth based on 2014 Cost Report numbers)
• Operations & Maintenance
$1.50 million per year (20-yr planning period)
• Total present worth based on 2014 Cost Report numbers (capital + O&M)
$206 million
• Load removed (20-yr planning period)
24,800 kg-N per year
• Cost efficiency
$8,290 / kg-N removed per year
Example offset
• 30-unit residential sub-division (mix of 2- and 3-bedroom)
• Actual flow: 125 gpd per unit; 3,760 gpd total
• Wastewater load to be offset: 136 kg-N/yr
• Calculation of monetary offset
$1.13 million = $206 million x 136 kg-N/yr / 24,800 kg-N/yr
= $8,290 / kg-N per year x 136 kg-N/yr