32
DRAFT Water Resources Technical Bulletin Page 1 DRAFT Water Resources Technical Bulletin This guidance is intended to clarify how the Water Resources Goal and Objectives of the Regional Policy Plan (RPP) are to be applied and interpreted in Cape Cod Commission Development of Regional Impact (DRI) project review. This technical bulletin presents specific methods by which a project can meet these goals and objectives. The applicability and materiality of these goals and objectives to a project will be determined on a case-by-case basis considering a number of factors including the location relative to Water Resource Areas (identified on page 2), context (as defined by the Placetype of the location), scale, use, and other characteristics of a project. The Role of Cape Cod Placetypes The RPP incorporates a framework for regional land use policies and regulations based on local form and context as identified through categories of Placetypes found and desired on Cape Cod. The Placetypes are determined in two ways: some are depicted on a map adopted by the Commission as part of the Technical Guidance for review of DRIs, which may be amended from time to time as land use patterns and regional land use priorities change, and the remainder are determined using the character descriptions set forth in Section 8 of the RPP and the Technical Guidance. The project context, as defined by the Placetype of the location, provides the lens through which the Commission will review the project under the RPP. Additional detail can be found in the Cape Cod Placetypes section of the Technical Guidance. Water Resources Goal: To maintain a sustainable supply of high quality untreated drinking water and protect, preserve or restore the ecological integrity of fresh and marine surface waters. Objective WR1 – Protect and preserve groundwater quality Objective WR2 –Protect, preserve and restore fresh water resources Objective WR3 –Protect, preserve and restore marine water resources Objective WR4 – Manage and treat stormwater to protect and preserve water quality Objective WR5 – Manage groundwater withdrawals and discharges to maintain hydrologic balance and protect surface and groundwater resources

DRAFT Water Resources Technical Bulletin · and PPWSA layers in the RPP Data Viewer) must employ the following methods to meet Objective WR1: • All development, construction, clearing,

  • Upload
    dinhdan

  • View
    219

  • Download
    0

Embed Size (px)

Citation preview

Page 1: DRAFT Water Resources Technical Bulletin · and PPWSA layers in the RPP Data Viewer) must employ the following methods to meet Objective WR1: • All development, construction, clearing,

DRAFT Water Resources Technical Bulletin Page 1

DRAFT Water Resources Technical Bulletin

This guidance is intended to clarify how the Water Resources Goal and Objectives of the

Regional Policy Plan (RPP) are to be applied and interpreted in Cape Cod Commission

Development of Regional Impact (DRI) project review. This technical bulletin presents specific

methods by which a project can meet these goals and objectives.

The applicability and materiality of these goals and objectives to a project will be determined on

a case-by-case basis considering a number of factors including the location relative to Water

Resource Areas (identified on page 2), context (as defined by the Placetype of the location),

scale, use, and other characteristics of a project.

The Role of Cape Cod Placetypes

The RPP incorporates a framework for regional land use policies and regulations based on

local form and context as identified through categories of Placetypes found and desired on Cape

Cod.

The Placetypes are determined in two ways: some are depicted on a map adopted by the

Commission as part of the Technical Guidance for review of DRIs, which may be amended from

time to time as land use patterns and regional land use priorities change, and the remainder are

determined using the character descriptions set forth in Section 8 of the RPP and the Technical

Guidance.

The project context, as defined by the Placetype of the location, provides the lens through which

the Commission will review the project under the RPP. Additional detail can be found in the

Cape Cod Placetypes section of the Technical Guidance.

Water Resources Goal: To maintain a sustainable supply of high quality untreated drinking water and protect, preserve or restore the ecological integrity of fresh and marine surface waters.

• Objective WR1 – Protect and preserve groundwater quality

• Objective WR2 –Protect, preserve and restore fresh water resources

• Objective WR3 –Protect, preserve and restore marine water resources

• Objective WR4 – Manage and treat stormwater to protect and preserve water quality

• Objective WR5 – Manage groundwater withdrawals and discharges to maintain hydrologic balance and protect surface and groundwater resources

Page 2: DRAFT Water Resources Technical Bulletin · and PPWSA layers in the RPP Data Viewer) must employ the following methods to meet Objective WR1: • All development, construction, clearing,

DRAFT Water Resources Technical Bulletin Page 2

Table of Contents

Introduction.............................................................................................................. 3

Summary of Methods ................................................................................................ 4

Detailed Methods for Meeting Objective WR1............................................................ 10

For all projects ..................................................................................................... 10

For Projects Proposing Private Wastewater Systems ............................................... 12

For Projects Proposing Wastewater Treatment Facilities ......................................... 13

For Projects within Wellhead Protection Areas (WHPAs) and Potential Public Water Supply Areas (PPWSAs) ........................................................................................ 14

Detailed Methods for Meeting Objective WR2............................................................ 16

Detailed Methods for Meeting Objective WR3............................................................ 17

Detailed Methods for Meeting Objective WR4............................................................ 19

Stormwater system design ................................................................................... 19

Detailed Methods for Meeting Objective WR5............................................................ 21

detailed Water Resources Application Requirements .................................................. 22

Definitions .............................................................................................................. 23

References ............................................................................................................. 24

Appendix A: Nitrogen Loading Guidance for Water Resources .................................... 25

Appendix B: Estimation Of High Ground-Water Levels ............................................... 31

Appendix C: Monetary Nitrogen Offset...................................................................... 32

Note on Application Materials and Water Resource Areas Maps

Application materials should provide sufficient detail to demonstrate that the project meets the

applicable goals and objectives, but typically include:

A. Project description including site location, applicable Water Resource Areas, and

narrative of proposed wastewater, stormwater and drinking water systems

B. Site-wide nitrogen loading calculation

C. Site plan including applicable grading, drainage, and utilities

D. Stormwater treatment and capacity calculations

E. Operations and maintenance plan(s)

*These items may not be required for all projects. See guidance on page 22 for more information. The Water Resource Areas, which are defined on page 22, can be viewed in the RPP Data

Viewer, and include:

• Wellhead Protection Areas (WHPA)

• Fresh Water Recharge Areas (FWRA)

• Marine Water Recharge Areas (MWRA)

• Potential Public Water Supply Area (PPWSA)

• Impaired Areas

Page 3: DRAFT Water Resources Technical Bulletin · and PPWSA layers in the RPP Data Viewer) must employ the following methods to meet Objective WR1: • All development, construction, clearing,

DRAFT Water Resources Technical Bulletin Page 3

INTRODUCTION

Cape Cod’s water resources include fresh and marine waters as well as natural and built systems.

The Cape Cod Aquifer, which serves as the primary link between all of the water resources on

Cape, is relied upon to provide drinking water and wastewater disposal capacity for the human

population, plays an integral role in maintaining plant and animal habitat in marine and

freshwater settings, and ultimately underlies many of the scenic and recreational opportunities

that serve as the primary economic driver for the region. Consistent with the Cape Cod Area

Wide Water Quality Management Plan (the “208 Plan), maintaining the integrity and health of

the aquifer and the various systems connected to it while encouraging provision of water

resource infrastructure and growth that is appropriate in form and location is the primary

purpose of the Water Resources goal and objectives.

This Technical Guidance provides examples of various methods and strategies that DRI projects

may use to satisfy the Water Resources Goal and Objectives of the RPP. Through

implementation of these methods and strategies, DRI projects can support the protection of

critical water resources through development that is consistent with the vision for the region.

Although the majority of methods discussed in this Technical Guidance are intended to be

flexible, certain methods will be required of all DRI’s where a particular Water Resources

objective is applicable.

Page 4: DRAFT Water Resources Technical Bulletin · and PPWSA layers in the RPP Data Viewer) must employ the following methods to meet Objective WR1: • All development, construction, clearing,

DRAFT Water Resources Technical Bulletin Page 4

SUMMARY OF METHODS

Goal: To maintain a sustainable supply of high quality untreated drinking water and protect, preserve or restore the

ecological integrity of fresh and marine surface waters.

Objective WR1 – Protect, preserve and restore groundwater quality

Methods

All DRIs must employ the following methods to meet Objective WR1:

• Project is limited to a maximum site-wide nitrogen loading concentration of 5 parts per million (ppm) except

as provided below for Impaired Areas and Potential Public Water Supply Areas (PPWSA),

• No adverse impacts on downgradient existing or proposed drinking water wells.

• Septic systems and other sources of contamination are sited to avoid adversely impacting downgradient existing or proposed drinking water wells.

Additional methods to meet Objective WR1:

• Utilize site design and operational best practices to preserve groundwater quality

• Review existing Environmental Site Assessment(s) as available for previously developed properties and incorporate findings into project design

For projects in an Impaired Area outside of other mapped water resource areas (see RPP Data viewer):

• If proposed site-wide nitrogen loading concentration exceeds 5 ppm, demonstrate no adverse impact on ponds, wetlands, marine waters, public or private drinking water supply wells, and potential water supply wells.

For projects in Potential Public Water Supply Areas:

• Site wide nitrogen loading must be less than 1 ppm.

All projects proposing private wastewater systems designed for flows greater than 2,000 gallons per day (gpd) and requiring greater treatment efficiency than specified by MassDEP permit or approval letter must:

• Enter into an Operation, Monitoring, and Compliance agreement with the Cape Cod Commission and local Board of Health.

All Wastewater Treatment Facility DRIs must:

• Consistently achieve 5 ppm or lower total nitrogen in wastewater effluent or in groundwater at downgradient

property boundary.

Additional methods for wastewater treatment facility DRI’s to meet Objective WR1:

• Utilize wastewater treatment facilities including private treatment facilities to protect and/or restore ground water quality provided that such facilities will not adversely impact water or other natural resources.

• Locate treatment facilities outside FEMA V zones, A zones, and floodways; ACECs, wetlands and buffer areas, barrier beaches, coastal dunes, or critical wildlife habitat. Treatment facilities are proposed in FEMA A zones only to remediate water quality problems from existing

nitrogen sources within that zone.

Page 5: DRAFT Water Resources Technical Bulletin · and PPWSA layers in the RPP Data Viewer) must employ the following methods to meet Objective WR1: • All development, construction, clearing,

DRAFT Water Resources Technical Bulletin Page 5

All DRIs within Wellhead Protection Areas (WHPA) or Potential Public Water Supply Areas (PPWSA) (see WHPA

and PPWSA layers in the RPP Data Viewer) must employ the following methods to meet Objective WR1:

• All development, construction, clearing, and staging occurs at least 400 feet from identified future well sites.

• Projects with a high risk of contaminating groundwater, such as fleet storage, vehicle maintenance areas and

loading docks, include a mechanical shut-off valve or other flow-arresting device in stormwater systems

between the stormwater capture structures and the leaching structures.

Additional Methods for DRI’s within WHPA and/or PPWSA’s to meet Objective WR1:

• Do not discharge effluent from private wastewater treatment facilities

• Use private wastewater treatment facilities to remediate existing water quality problems in the water supply

area.

• Do not use, treat, generate, handle, store or dispose of Hazardous Materials or Hazardous Wastes, except for

Household Quantities

o Redevelopment projects reduce the quantity of hazardous materials on the project site from the prior

use and adequately document that reduction

o Permanently eliminate the same or greater quantity of Hazardous Materials or Wastes at another

facility, project, or site within the same WHPA or PPWSA and adequately document that reduction

• Non-residential development and redevelopment employs integrated pest management and/or biorational

landscape management practices protective of water quality

• Roadway and parking area designs and materials minimize impervious surfaces

Objective WR2 –Protect, preserve and restore fresh water resources

Methods

All DRIs within a Freshwater Recharge Area (FWRA) must employ the following methods to meet Objective WR2:

• New development prevents loading of nutrients and other contaminants to fresh water resources.

• Redevelopment mitigates loading from nutrients and other contaminants to fresh water resources to the

maximum extent practicable.

• Maintain or enhance vegetated buffer zones along shorelines to ponds and lakes

All projects within a FWRA where septic effluent disposal is proposed within 300 feet of the high water level of a

freshwater pond; or wastewater treatment facilities effluent disposal is proposed anywhere in the watershed to a

freshwater pond must:

• Demonstrate that phosphorus transported by groundwater does not discharge into the pond or its

tributaries.

Page 6: DRAFT Water Resources Technical Bulletin · and PPWSA layers in the RPP Data Viewer) must employ the following methods to meet Objective WR1: • All development, construction, clearing,

DRAFT Water Resources Technical Bulletin Page 6

Objective WR3 –Protect, preserve and restore marine water resources

Methods

All DRIs in a Marine Water Recharge Area (MWRA) where a critical nitrogen load has been determined through

either a Total Maximum Daily Load or Massachusetts Estuaries Project (MEP) Technical Report must employ the

following methods to meet Objective WR3:

• Not add nitrogen to a MWRA watershed unless:

o There is a MassDEP Watershed Permit or locally adopted nutrient management plan, deemed

consistent with the 208 Plan by the Cape Cod Commission, in the sub-watershed in which the project is

proposed, and the approved nutrient management plan calls for initiation of nutrient reduction actions

or strategies sufficient to offset nutrient contribution(s) from the project within five years of project

approval; or

o the project is in an area with available sewer connections, or is in a Placetype where nitrogen additions

may be offset through a monetary contribution to address water quality problems in the affected

surface waters.

All DRI’s in a MWRA where there are water quality problems that are scientifically documented and a critical load has

not been determined must employ the following methods to meet Objective WR3:

• Maintain or reduce nitrogen loading relative to existing levels.

Objective WR3 Areas of Emphasis by Placetype

Natural

Areas

Rural

Development

Areas

Suburban

Development

Areas

Historic

Areas

Maritime

Areas

Community

Activity

Centers

Industrial

Activity

Centers

Military and

Transportation

Areas

Development

is discouraged

in Natural

Areas and

monetary N-

offsets are not

permitted.

Sewer is

generally not

anticipated in

rural areas,

therefore

monetary N-

offsets are not

permitted.

Monetary N-

offsets may be

permitted at

Commission’s

discretion.

Monetary N-

offsets may be

permitted in

Historic Areas

at

Commission’s

discretion.

Monetary

N-offset are

permitted in

Maritime

Areas where

sewer is not

yet

available.

Monetary N-

offsets are

permitted in

Community

Activity

Centers where

sewer is not

yet available.

Monetary N-

offset are

permitted in

Industrial

Areas where

sewer is not

yet

available.

Monetary N-

offset are

permitted in

Military /

Transportation

Areas where

sewer is not yet

available.

* The nitrogen offset rate is based on cost efficiencies associated with wastewater collection and municipal treatment as described in Appendix C.

Page 7: DRAFT Water Resources Technical Bulletin · and PPWSA layers in the RPP Data Viewer) must employ the following methods to meet Objective WR1: • All development, construction, clearing,

DRAFT Water Resources Technical Bulletin Page 7

Objective WR4 – Manage and treat stormwater to protect and preserve water quality

Methods

All DRIs, with the exception of redevelopment projects as discussed below, must employ the following methods to meet Objective WR4:

• Provide a stormwater management system that prevents adverse impacts to water resources and other natural resources.

• Prevent discharge of untreated stormwater to marine and fresh surface water and natural wetlands by treating runoff from development, including areas located outside the jurisdiction of the Massachusetts Wetlands Protection Act

• Provide storage and treatment capacity sufficient to store, treat, and infiltrate all runoff from parking areas and roadways onsite

• Locate new infiltration to maintain a minimum two-foot separation between points of infiltration and the maximum high water table.

• Design stormwater systems according to the Massachusetts Stormwater Handbook to: o accommodate the 25-year 24-hour storm o remove at least 80% total suspended solids (TSS) o provide water quality treatment capacity for the first inch of stormwater runoff using biofiltration,

bioretention, or other Treatment BMPs as detailed in the Stormwater Handbook

For redevelopment projects:

• Reduce impervious area coverage and improve site conditions to enhance stormwater retention, water quality treatment, and recharge over existing conditions.

• Include natural areas in stormwater system design. Additional methods to meet Objective WR4:

• Manage and directly infiltrate roof runoff separately where site constraints limit capacity for water quality treatment, unless there is an identified rooftop water quality concern requiring additional treatment or management.

• Design stormwater systems to remove at least 44% total suspended solids prior to discharge into subsurface leaching facilities.

Page 8: DRAFT Water Resources Technical Bulletin · and PPWSA layers in the RPP Data Viewer) must employ the following methods to meet Objective WR1: • All development, construction, clearing,

DRAFT Water Resources Technical Bulletin Page 8

Objective WR4 Areas of Emphasis by Placetype

Natural

Areas

Rural

Development

Areas

Suburban

Development

Areas

Historic

Areas

Maritime

Areas

Community

Activity

Centers

Industrial

Activity

Centers

Military and

Transportation

Areas

Prioritize protection of

mature trees and wooded

areas and utilize natural

drainage features to manage

stormwater. Minimize

construction footprint, land

disturbance during and

after construction, and

impervious area creation to

maintain natural filtration

and recharge processes. Use

LID features that provide

water quality treatment

during storm events and

environmental or

recreational function at

other times, and optimize

BMPs for nitrogen removal.

Cluster

development

to maximize

contiguous

natural areas.

Minimize

stormwater

runoff by

reducing

road/driveway

widths and

using

permeable

features to

break up large

impervious

areas.

Utilize permeable

material choices when

designing roadways,

parking, and walkways

where land area and

subsurface access may be

limited. Employ

rainwater re-use

techniques in ways that

maintain local character.

Explore opportunities for

development of off-site

shared district or

community scale

stormwater treatment.

Prioritize

inclusion of

green space

that can

provide

treatment and

infiltration

capacity for

redevelopment

/ infill projects.

Utilize

subsurface

storage and

infiltration

measures

where site

constraints

limit above

ground

treatment

capacity.

Where

applicable

maintain or

improve gray

infrastructure

to support

development of

shared off-site

district or

community

scale

stormwater

treatment.

Prioritize inclusion of green

space that can provide

treatment and infiltration

capacity for redevelopment /

infill projects. Utilize

permeable material choices

when designing lower traffic

roadways, parking, and

walkways, and subsurface

storage and infiltration

measures where site

constraints limit above

ground treatment capacity.

Where applicable maintain or

improve gray infrastructure

to support development of

shared off-site district or

community scale stormwater

treatment. Design sites to

minimize exposure of

stormwater runoff to

hazardous materials,

hazardous wastes, and other

potential contaminants.

Design stormwater systems

to treat higher potential

pollutant loads and contain

runoff via flow arresting

device or otherwise in the

event of a spill / release.

Page 9: DRAFT Water Resources Technical Bulletin · and PPWSA layers in the RPP Data Viewer) must employ the following methods to meet Objective WR1: • All development, construction, clearing,

DRAFT Water Resources Technical Bulletin Page 9

Objective WR5 – Manage groundwater withdrawals and discharges to maintain hydrologic balance in a way that is

protective of surface and groundwater resources

Methods

All DRIs must employ the following methods to meet Objective WR5:

• Design water withdrawals and wastewater discharges in a manner that protects surface water and wetland

habitat from groundwater pumping and, in the case of effluent disposal from water table mounding issues

(e.g., breakout, flooding, water table separation).

For projects proposing to withdraw >20,000 gallons of water per day from the site:

• Provide a groundwater study that demonstrates the project will not have adverse impacts on groundwater

levels or adjacent surface waters and wetlands.

Page 10: DRAFT Water Resources Technical Bulletin · and PPWSA layers in the RPP Data Viewer) must employ the following methods to meet Objective WR1: • All development, construction, clearing,

DRAFT Water Resources Technical Bulletin Page 10

DETAILED METHODS FOR MEETING OBJECTIVE WR1

Objective WR1: Protect and Preserve Groundwater Quality

Nitrogen loading

Protection of Cape Cod’s groundwater resources is critical for the protection of human health.

The Cape Cod aquifer was designated as a Sole Source Aquifer (47 FR 30282) by the US

Environmental Protection Agency (USEPA) in 1982, recognizing the complete dependence of

the population on groundwater as its source for drinking water. The aquifer is primarily

recharged by precipitation but also receives discharges of wastewater and stormwater, which

can introduce contaminants into Cape Cod’s primary source of drinking water. Nitrate-nitrogen

(NO3-N) is a primary contaminant of concern due to its potential human health effects, for

which USEPA has established a maximum contaminant level (MCL) of 10 parts per million

(ppm). In addition, high NO3 concentrations in groundwater have also been correlated with

higher concentrations of regulated drinking water contaminants (e.g., volatile organic

compounds and compounds of emerging concern). For these reasons the nitrogen loading

requirements must be met by all DRI’s.

Detail on the methods for meeting Objective WR1 is provided below:

For all projects

Under the Safe Drinking Water Act, public supply wells which exceed 5 ppm NO3-N are subject

to additional monitoring requirements, and wells that exceed the MCL (10 ppm NO3-N) cannot

obtain variances or exemptions, thus requiring expensive treatment or being removed from

operation. In aerobic subsurface environments like Cape Cod’s unconfined aquifers, nitrate is

highly persistent with natural chemical reactions providing minimal removal. Consequently,

limiting the amount of nitrogen introduced to the aquifer is the most effective way to reduce

NO3-N concentrations in groundwater and protect Cape Cod’s drinking water.

5 ppm Nitrogen Loading Standard

The Cape Cod Commission has adopted a loading standard of 5 ppm NO3-N which based on a

statistical analysis is designed to keep violations of the USEPA MCL for NO3-N to less than 1 in

10 samples, while maintaining an additional margin of safety during times of simultaneous low

recharge (i.e., drought conditions) and high loading (summer peak season). This standard is

designed to protect human health, as well as current and potential future drinking water

resources. A site-wide nitrogen loading calculation takes into account all sources of nitrogen

from the project site post-development and divides this cumulative nitrogen input by the water

input (recharge) for the entire project site. Instructions on the information required and

method for calculating site-wide nitrogen loading are available in Appendix A – Nitrogen

Loading. Applicants seeking to reduce site-wide nitrogen loading may do so by providing

advanced treatment of wastewater flows to remove additional nitrogen, reducing the volume of

wastewater flows, increasing natural area on-site, decreasing fertilized lawn area, and

incorporating stormwater Best Management Practices (BMPs) optimized for nitrogen removal.

Page 11: DRAFT Water Resources Technical Bulletin · and PPWSA layers in the RPP Data Viewer) must employ the following methods to meet Objective WR1: • All development, construction, clearing,

DRAFT Water Resources Technical Bulletin Page 11

Impacts of development on local drinking water wells

The 5 ppm nitrogen loading standard is designed to protect the Cape Cod aquifer as a whole, but

localized impacts of a project on the groundwater resources also need to be considered. As

nitrogen and other wastewater constituents will follow the flow of groundwater, the direction of

groundwater flow at the project site will determine where wastewater effluent travels. The

location of septic and other wastewater disposal systems, direction of groundwater flow, and

proximity of public or private drinking water wells at the site and on neighboring parcels should

be examined to verify that a project even when complying with site-wide loading standards is

not contaminating nearby drinking water resources. Applicants should identify existing or

proposed drinking water wells within 400 feet of project boundaries. Groundwater flow

direction should be determined using a water table map, which may be generated from

groundwater elevation data (possible sources might include the United States Geological Survey,

Massachusetts Department of Environmental Protection, or the town). The direction of

groundwater flow should be used to locate wastewater treatment systems (including septic)

appropriately so that effluent does not flow directly into downstream drinking water sources.

Site assessments for previously developed properties

Sites that have been previously developed, particularly those with uses that historically have

used/generated hazardous materials or hazardous wastes (e.g., gas stations, auto repair

facilities, dry cleaners, manufacturing facilities) may contain contaminated soil or groundwater

even if site assessment and remediation activities have been conducted under the Massachusetts

Contingency Plan (MCP). To prevent the unintentional mobilization of contaminants into

groundwater, documentation of all Environmental Site Assessments and remedial actions

should be supplied for Commission review to ensure the best available information regarding

surface and subsurface site conditions is considered when evaluating the project design.

Best development practices for site design

Low impact development is the practice of using innovative stormwater management systems

that are modeled after natural hydrologic features. Low impact development techniques

manage rainfall at the source using uniformly distributed decentralized micro-scale controls,

and small cost-effective landscape features located at the lot level. They also facilitate compact,

clustered development and minimize impervious surfaces.

Environmentally sensitive site design incorporates low impact development techniques to

prevent the generation of stormwater and non-point source pollution by reducing impervious

surfaces, disconnecting flow paths, treating stormwater at its source, maximizing open space,

minimizing disturbance, protecting natural features and processes, and/or enhancing wildlife

habitat.

Additional resources regarding site design best practices are available from the United States

Environmental Protection Agency (https://www.epa.gov/sites/production/files/2015-

11/documents/region3_factsheet_lid_esd.pdf), the Metropolitan Area Planning Council

(https://www.mapc.org/resource-library/low-impact-development-toolkit/), and other State

Page 12: DRAFT Water Resources Technical Bulletin · and PPWSA layers in the RPP Data Viewer) must employ the following methods to meet Objective WR1: • All development, construction, clearing,

DRAFT Water Resources Technical Bulletin Page 12

and regional environmental and planning agencies (e.g. https://growsmartmaine.org/wp-

content/uploads/2015/08/Enviro_Sensitive_Design-Final-21-Nov-06.pdf).

Use of shared infrastructure

Shared wastewater treatment utilizes a single system to treat wastewater from multiple units of

development. This practice can facilitate higher density development, reduce environmental

impacts and treatment costs, and enhance open space preservation as it only requires a single

location for wastewater disposal and may require less total area for disposal. In cases where a

parcel is subdivided or residential lots are to be sold individually, a covenant will need to be

entered into by the homeowners for operation and maintenance of a shared system in order to

meet Objective WR1 via this method.

Multi-unit development is also encouraged to include community or public water supplies as

alternatives to multiple private wells, in order to avoid potential impacts from wastewater

disposal and challenges of siting and associated setback requirements for multiple water supply

wells.

For Projects Proposing Private Wastewater Systems

Operation, Monitoring, and Compliance Agreements

When a wastewater system of sufficient capacity (greater than 2,000 gallons per day design

flow) is proposed to operate with greater removal efficiency than currently certified by MassDEP

permit or letter of approval in order to meet Water Resources objectives, an Operation

Monitoring and Compliance (OMC) Agreement is required to ensure treatment goals are met.

The OMC agreement should be entered into between the applicant, Cape Cod Commission, and

the local Board of Health, and generally consists of:

• Treatment specifications

o Wastewater flow limit

o Effluent quality limits

• Monitoring requirements

o Sampling locations

o Analyses required

o Sampling frequency

• Reporting requirements

o Frequency of reporting

o Enforcement actions

• Operations and maintenance plan and staffing

Page 13: DRAFT Water Resources Technical Bulletin · and PPWSA layers in the RPP Data Viewer) must employ the following methods to meet Objective WR1: • All development, construction, clearing,

DRAFT Water Resources Technical Bulletin Page 13

For Projects Proposing Wastewater Treatment Facilities

Wastewater Treatment Facilities

Wastewater collection and treatment systems that have a design flow of greater than

10,000gallons per day are considered a wastewater treatment facility (WWTF).

Location of Wastewater Treatment Facilities

WWTFs are likely to play a role in many towns’ nutrient reduction strategies, therefore it is

important that public and private facilities are deployed in a coordinated and strategic manner.

Nutrient reduction strategies may be laid out in a town’s Comprehensive Waste Management

Plan (CWMP), a Targeted Watershed Management Plan (TWMP) that may involve several

towns, or in other planning documents. When a nutrient reduction strategy has been deemed

consistent with the Cape Cod Area Wide Water Quality Management Plan Update (208 Plan

Update) by the Cape Cod Commission, private WWTFs that are not owned or operated by a

town, municipality or district may be located in areas where a) no public WWTF is proposed

within three years of the proposed project construction date under the nutrient reduction

strategy, or b) where the nutrient reduction strategy relies upon the proposed private WWTFs to

achieve nutrient reduction goals. In areas where an approved nutrient management plan is not

yet in place, private WWTFs are an encouraged strategy for maintaining or improving

groundwater quality.

Certain natural resource areas are not appropriate locations for WWTF installation.

Discharging treated wastewater to sensitive environmental areas, such as Areas of Critical

Environmental Concern (ACECs), wetlands and buffer areas, barrier beaches, coastal dunes, and

critical wildlife habitats may negatively impact those resources by degrading water quality

and/or modifying natural hydrologic processes. In addition, the vulnerability of FEMA V zones,

FEMA A zones, floodways, barrier beaches and coastal dunes to natural disaster (flooding,

storm surge, etc.) makes them generally inappropriate for siting WWTFs. A WWTF may be

proposed in FEMA A zones only when it is designed to specifically tie-in and treat existing

sources of wastewater within that same FEMA A zone. Applicants can determine whether a

project site is within any of the prohibited zones by consulting the RPP Data Viewer for further

detail.

Wastewater treatment and collection systems that are proposed within FEMA flood zones

should be designed to prevent elevated groundwater or floodwaters from entering the collection

system during storm events.

5 ppm Nitrogen Concentration Limit in Effluent or at Downgradient Boundary

Projects proposing WWTFs are required to maintain nitrogen at 5 ppm or lower when measured

at the downgradient property boundary. As it can be assumed that nitrogen discharged to

groundwater will flow advectively without dilution to the property boundary, nitrogen

concentrations generally remain constant or decrease slightly following discharge. WWTF

effluent nitrogen is monitored as part of a MassDEP groundwater discharge permit (GWDP),

and projects with 5 ppm nitrogen or less in effluent are deemed to have met this requirement.

Page 14: DRAFT Water Resources Technical Bulletin · and PPWSA layers in the RPP Data Viewer) must employ the following methods to meet Objective WR1: • All development, construction, clearing,

DRAFT Water Resources Technical Bulletin Page 14

Projects proposing to discharge nitrogen at concentrations greater than 5 ppm may use a

groundwater model, or groundwater monitoring data to demonstrate that nitrogen

concentration in groundwater at the downgradient property boundary will not exceed 5 ppm

and the results must be submitted to the Commission for review and confirmation.

For Projects within Wellhead Protection Areas (WHPAs) and Potential Public Water Supply Areas (PPWSAs)

Protection of existing and future drinking water wells (WHPAs and PPWSAs)

As additional development on land areas that contribute (or may contribute in the future) to

drinking water wells will directly impact drinking water quality, certain additional protections

are required to prevent excessive nutrient loading and minimize the risk of contamination.

Lands receiving precipitation that contribute to the recharge of public drinking water supply

wells are considered Wellhead Protection Areas (WHPA). These include MADEP approved

Zone IIs, interim wellhead protection areas, and certain town delineated water protection

districts that extend beyond the Zone II limits.

Potential Public Water Supply Areas (PPWSAs) were first identified in the Priority Land

Acquisition Assessment Project (PLAAP) as areas that may be suitable for future development of

drinking water supplies. These land areas meet various requirements including minimum

parcel size, surrounding land uses that are protective of groundwater quality, and the absence of

incompatible upgradient or nearby land uses (e.g., landfills, hazardous waste sites or

contaminant plumes, dense development).

Hazardous Materials Limitations

Any chemical or substance that when released into the environment will pose a significant

contaminant threat to groundwater and drinking water supplies is considered a hazardous

material. Examples include petroleum products, petroleum distillates, organic and inorganic

solvents, oil-based paints, oil-based stains, insecticides, herbicides, rodenticides, and pesticides.

Any Hazardous Waste, Universal Waste, or Waste as defined in the Massachusetts Hazardous

Waste Regulations (310 CMR 30.010) are considered Hazardous Wastes. Hazardous Wastes do

not include Hazardous Materials or biomedical wastes regulated under the Massachusetts State

Sanitary Code (105 CMR 480.00). Hazardous Materials do not include Hazardous Wastes,

Articles, Consumer Products, or Cosmetics.

In order to minimize the potential risk of introducing contamination to existing or future water

supplies, the following limits on hazardous materials / hazardous wastes apply in WHPAs and

PPWSAs.

(a) 275 gallons of oil on site at any time to be used for heating of a structure, or to supply an

emergency generator

(b) 25 gallons or equivalent dry weight, total, of Hazardous material(s) on site at any time

(excluding oil as classified in part (a))

Page 15: DRAFT Water Resources Technical Bulletin · and PPWSA layers in the RPP Data Viewer) must employ the following methods to meet Objective WR1: • All development, construction, clearing,

DRAFT Water Resources Technical Bulletin Page 15

(c) 55 gallons of Hazardous Waste generated at the Very Small Quantity Generator level as

defined in Massachusetts Hazardous Waste Regulations (310 CMR 30.000) and

accumulated or stored on-site at any time.

Applicants should provide to the Commission an inventory which includes the identities and

quantities of expected and potential hazardous materials/wastes that will be generated, used, or

stored on site for the proposed use. Similar inventories should be provided for the previous use

(when applicants propose to reduce the quantity of hazardous materials present on site through

redevelopment) or for the proposed offset site (when applicants propose to eliminate the same

or greater quantity of hazardous materials from another project, site, or facility within the same

WHPA or PPWSA).

Certain types of development even when remaining within the above limits on hazardous

materials and hazardous wastes may present a greater potential for contaminating groundwater.

Stormwater systems serving areas used for fleet storage, vehicle maintenance, electrical

transmission/generation. loading docks, waste handling, and any other use with greater

potential for groundwater contamination must include a means to halt discharge from the

stormwater system (flow arresting device) in the event of a spill, accident, or release of any

source of contamination.

1 ppm nitrogen limit

PPWSAs are a finite and increasingly limited resource that require extra levels of protection to

ensure they remain available to provide a stable drinking water system able to meet future water

supply needs.

In order to maintain the suitability of PPWSAs to supply drinking water in the future, site wide

nitrogen loading is limited to 1 ppm in these areas.

Landscape Management Practices

Landscaping is an important part of development that may play a role in screening, stormwater

treatment and overall visual aesthetics. Proper maintenance of landscaping is necessary to

maintain its continued function, and several approaches are encouraged to minimize the

environmental impacts presented by chemical fertilizer and pesticide usage during these

activities. Additional detail regarding landscaping is provided in the Community Design

Technical Bulletin.

Integrated pest management and biorational landscape management make use of an inspection

and monitoring approach, along with a variety of pest control measures to maintain pest

populations below levels that can cause significant damage or loss to installed landscaping. Soil

nutrient and moisture testing should be employed with fertilization and irrigation methods

tailored to the specific site conditions. Accurate identification of pests and monitoring of their

populations should be used to determine rate and frequency for applying pest control (which

may include chemical, cultural, and biological controls) to maintain pest population levels below

identified thresholds. If no effective non-pesticide control measures are available, a key concept

of integrated pest management is that selected pesticides should result in the lowest possible

Page 16: DRAFT Water Resources Technical Bulletin · and PPWSA layers in the RPP Data Viewer) must employ the following methods to meet Objective WR1: • All development, construction, clearing,

DRAFT Water Resources Technical Bulletin Page 16

risk to health or the environment. The University of Massachusetts Extension provides a more

detailed background and ongoing guidance regarding integrated pest management at

(http://ag.umass.edu/integrated-pest-management).

Roadway and Parking Area Design

In WHPAs and PPWSAs, roadways and parking areas should be designed to minimize

impervious area, with pervious construction materials used whenever possible to minimize the

impact of stormwater on drinking water supplies.

Projects in Impaired Areas

Areas where water quality has been degraded by land uses such as high-density residential,

commercial, or industrial development; landfills, septage, and wastewater treatment discharges;

and areas downgradient of these sources that are similarly impacted are considered Impaired

Areas.

Projects located in Impaired Areas that are outside other mapped water resource areas including

WHPA’s, PPWSA, MWRAs and FWRAs may use existing groundwater quality data, distance

from existing natural or built water resources, and position upstream or downstream of those

resources relative to groundwater flow direction to demonstrate that nitrogen loading above 5

ppm will not adversely impact those resources.

DETAILED METHODS FOR MEETING OBJECTIVE WR2

Objective WR2: Prevent loading of phosphorous to fresh water resources

Phosphorous, unlike nitrogen, is attenuated in the subsurface. Studies of phosphorous

transport indicate that phosphorous loads associated with septic systems are typically

attenuated within 300 feet of downgradient transport, through sorption to soil minerals or

uptake during microbial or plant growth. Therefore, siting septic systems outside a 300 foot

upgradient buffer to fresh surface waters, and maintaining or increasing the width of vegetative

buffers with active plant growth will be protective of water quality. For projects with sufficiently

large flows in pond recharge areas, the phosphorous load may exceed the attenuation rate of the

soils and ultimately result additional phosphorous loading to the pond even when the discharge

is located greater than 300 feet upgradient of the pond. In these situations, additional modeling

which looks at groundwater flow, soil characteristics, and wastewater characteristics will be

required to characterize the site and evaluate the expected extent of phosphorous transport.

Page 17: DRAFT Water Resources Technical Bulletin · and PPWSA layers in the RPP Data Viewer) must employ the following methods to meet Objective WR1: • All development, construction, clearing,

DRAFT Water Resources Technical Bulletin Page 17

DETAILED METHODS FOR MEETING OBJECTIVE WR3

Objective WR3 – Prevent and mitigate loading of nutrients and other contaminants to marine

water resources.

Cape Cod’s marine waters provide a variety of complex habitats necessary to support shellfish

populations, marine fisheries, migratory birds, and many other plant and wildlife populations.

Less than 25% of the Cape Cod land surface drains to open marine waters (e.g., Cape Cod Canal,

Cape Cod Bay, Nantucket Sound, Atlantic Ocean). Instead, the majority of land surfaces

discharge to estuaries or coastal embayments through groundwater flow in the Cape Cod

aquifer. Marine Water Recharge Areas (MRWA) are defined as watershed areas that contribute

to a marine embayment as defined by the topography of the water table.

As of 2018, the Massachusetts Estuary Project (MEP) has studied 40 of Cape Cod’s 53 coastal

embayments. MEP continues to study coastal embayments on Cape Cod to determine the

critical nitrogen load for each embayment, which is the maximum amount of nitrogen input that

can be assimilated without negatively impacting ecosystem function and provision of habitat. A

total maximum daily load (TMDL) is the maximum amount of a pollutant that a waterbody can

assimilate on a daily basis and still support a healthy ecosystem, which for Cape Cod’s coastal

embayments is determined by MassDEP based on the results of the MEP studies. Four of the

embayments studied to date have been found to have assimilative capacity for nitrogen;

therefore, no TMDL is necessary at this time. The remaining watersheds that have been studied

require nitrogen reduction to achieve healthy ecosystem function.

Additional information about the MEP, embayment reports, and applicable TMDLs is available

at the MassDEP website (https://www.mass.gov/guides/the-massachusetts-estuaries-project-

and-reports).

The Cape Cod Section 208 Area Wide Water Quality Management Plan (208 Plan Update) was

completed in 2015 in response to the need for a new approach to planning for and implementing

nitrogen reduction plans and projects to achieve the critical nitrogen loads. The 208 Plan

Update expands the available nutrient reduction strategies beyond source reduction to include

remediation and restoration approaches. This allows for a range of strategies to be employed,

depending on the placetype and context within the watershed of the area where nitrogen

reduction is needed (ex. in-embayment strategies, such as the use of aquaculture, may be used

in watersheds where low density development causes inefficient source reduction from a cost

perspective). The 208 Plan Update provides a framework for applying watershed based

solutions to reduce nitrogen in impaired embayments. CWMPs, TWMPs, and other municipal

nutrient management plans and projects deemed consistent with the 208 Plan Update and those

that are permitted by MassDEP through a watershed permit determine the approach and timing

of solutions within an individual watershed or sub-watershed, and development that conforms

with the approved nutrient management plan is considered to meet Objective WR3.

Development is generally prohibited from adding nitrogen to areas that contribute to nitrogen-

overloaded coastal waters. Embayments which have nitrogen loading greater than or equal to

their critical nitrogen loads are considered nitrogen-overloaded and may or may not have a

TMDL associated with them. Documented water quality problems may also exist (e.g., shellfish

Page 18: DRAFT Water Resources Technical Bulletin · and PPWSA layers in the RPP Data Viewer) must employ the following methods to meet Objective WR1: • All development, construction, clearing,

DRAFT Water Resources Technical Bulletin Page 18

or beach closures, failure to meet Massachusetts Surface Water Quality Standards) in areas

where a critical nitrogen load or TMDL has not yet been established, in which case projects are

required to mitigate or offset any proposed nitrogen load as described below. Nitrogen

additions from the proposed project may be mitigated by connecting existing development to an

existing sewer system, by tying-in and providing wastewater treatment to existing development

currently served by septic systems, or by other means that result in the overall nitrogen load

within the (sub)watershed being maintained or reduced. Applicants proposing to use this form

of mitigation should provide a calculation of the expected nitrogen load generated by the

project, the existing nitrogen sources (number, type, estimated load) proposed for mitigation,

and a detailed description of the means by which treatment of those sources will be

implemented (which could include financing of sewer tie-ins, a contract to provide wastewater

treatment, installation and operation of I/A systems at existing properties, or other means of

demonstrating how the proposed mitigation will ultimately be achieved).

Projects proposed in Placetype areas where development is encouraged and infrastructure

needed to meet nitrogen reduction requirements is lacking may provide a monetary offset of the

project’s nitrogen load which can be used to support expansion of wastewater treatment

operations.

Monetary Nitrogen Offset

Placetype Monetary Nitrogen Offset Available

Natural Areas No

Rural Development Areas No

Suburban Development Areas Where appropriate

Historic Character Areas Where appropriate

Maritime Area Yes

Community Activity Center Yes

Industrial Activity Center Yes

Military and Transportation Areas Yes

Activity centers may have existing sewer collection and treatment systems, or have sufficient

density of development and other infrastructure to justify future connection to sewer systems.

To promote the desired development density and facilitate future sewering, projects in

Community Activity Centers, Maritime Areas, Industrial Activity Centers or Military and

Transportation Areas without available sewer connections may contribute a monetary offset

calculated as up to $8,290 per kilogram nitrogen load to be offset. The monetary offset is based

on the cost of removing one kilogram of nitrogen per year for 20 years using a conventional

sewer collection system and municipal wastewater treatment. The monetary offset is calculated

based on reductions from 26.25 ppm, consistent with the MEP assumption for a standard septic

system and with values used for planning purposes in watershedMVP. See Appendix C for

further information on the methodology. Patterns of development in Suburban Development

Areas are generally too spread out to make centralized wastewater collection financially feasible,

Page 19: DRAFT Water Resources Technical Bulletin · and PPWSA layers in the RPP Data Viewer) must employ the following methods to meet Objective WR1: • All development, construction, clearing,

DRAFT Water Resources Technical Bulletin Page 19

while Historic Character Areas may present special challenges to sewering in terms of access

below grade and age of existing infrastructure. For these reasons monetary offsets are allowed

in limited circumstances at the discretion of the Commission in those Placetype Areas. Factors

that will be considered in determining offsets in these placetypes might include, but are not

limited to, existing development, business and community activity, a community’s vision for the

area as described in their Local Comprehensive Plan or other planning documents, and any

plans for construction of infrastructure that will take place within five years.

DETAILED METHODS FOR MEETING OBJECTIVE WR4

Objective WR4: Manage and treat stormwater to protect and preserve water quality

Undisturbed natural areas generally slow the velocity of runoff, allowing natural processes to

remove nutrients and contaminants and facilitating recharge so that rain largely stays where it

falls. When natural areas are covered by impervious surfaces, the resulting stormwater runoff

from rainfall or snow melt travels at higher velocities and in more concentrated flows, making

both infiltration and removal of nutrients or contaminants more challenging. As rainfall

amounts and patterns continue to change, the increased frequency of high intensity storms

present challenges and risks to many forms of infrastructure. Stormwater systems designed to

handle increased runoff in a distributed and decentralized manner should be an integral part of

community planning for water quality, flood protection, climate resilience, and capital

infrastructure. Across the Commonwealth of Massachusetts, untreated stormwater runoff is the

single largest source of water body impairment. In order to maintain and improve the health of

Cape Cod’s water resources and the communities that depend on them, it is critical to manage

both the quantity and quality of stormwater runoff that is generated by development.

Stormwater system design

To protect existing water resources and maintain safety by preventing flooding/ponding of

water on roadways, stormwater systems should be designed to both capture and infiltrate

rainfall from roadways, parking lots, and rooftops on the project site. Stormwater runoff

collects sediment, bacteria, nutrients, and pollutants from the impervious surfaces it flows over,

which negatively impact ground and surface water resources if not adequately treated. Properly

designed and maintained treatment BMPs minimize the amount of these pollutants that are

ultimately discharged to surface waters and groundwater. The Massachusetts Stormwater

Handbook (https://www.mass.gov/guides/massachusetts-stormwater-handbook-and-

stormwater-standards) provides guidance for designing stormwater structures to meet the water

quality treatment and storage/infiltration aspects of Objective WR4. To best account for

changing patterns in precipitation, updated projections for extreme precipitation events should

be used whenever designing new stormwater systems. The Massachusetts Stormwater

Handbook currently uses precipitation data from U.S. Weather Service Technical Paper 40,

which was published in 1961. Projections from the National Oceanic and Atmospheric

Administration (NOAA Atlas 14, published 2015) and Northeast Regional Climate Center

(Extreme Precipitation Analysis, http://precip.eas.cornell.edu/) utilize much more recent data

than Technical Paper 40, and MassDEP currently recommends using the most conservative

(largest) rainfall volume from among the three resources.

Page 20: DRAFT Water Resources Technical Bulletin · and PPWSA layers in the RPP Data Viewer) must employ the following methods to meet Objective WR1: • All development, construction, clearing,

DRAFT Water Resources Technical Bulletin Page 20

Applicants should provide a stormwater maintenance and operation plan certified by a Professional Engineer that details a schedule for inspection, monitoring, and maintenance; and identifies the party responsible for implementation. The applicant should also agree to provide a Professional Engineer certified letter that details inspection of the stormwater facilities one year after completion and certifies that the system was installed and continues to function as designed and approved.

Separation from High Groundwater

A calculation of the high groundwater level should be performed to ensure that stormwater

facilities are designed to maintain the proper 2 foot separation from the water table under all

conditions. Appendix B – Estimation of High Groundwater Levels describes a calculation that

may be used to adjust water levels measured at discrete Cape Cod locations and estimate high

groundwater levels at those same locations. The approach was developed in cooperation with

the US Geological Survey and is based on historic long-term groundwater-level measurements at

index wells located across Cape Cod.

Total Suspended Solids Removal and Water Quality Treatment Volume

Stormwater systems should be designed to remove 80% of Total Suspended Solids (TSS) and

provide water quality treatment for the first inch of precipitation from all impervious surfaces

on the site. An estimate of the TSS removal achieved in the stormwater treatment train(s) can

be performed using MassDEP’s TSS Removal Calculation Worksheet.

(https://www.mass.gov/files/documents/2016/08/nn/tss.xls)

The required water quality treatment volume can be calculated using the following equation.

WQ treatment volume (ft3) = impervious area (ft2) * (1 inch / 12 inches per foot)

Storage/treatment volume provided by most stormwater BMPs can be calculated with a stage-

storage table, where the incremental volume of each stage is given by

Incremental volume (ft3) = (elevation2 – elevation1) * ((area2+area1)/2)

Table 1: Example stage-storage volume calculation

Elevation (ft) Surface Area

(ft2)

Incremental

volume (ft3)

Cumulative

volume (ft3)

72.5 210 0 0

73 660 217.5 217.5

73.5 1,020 420 637.5

74 1,500 630 1267.5

The Massachusetts Stormwater Handbook contains detailed explanations, examples, and

guidance for additional methods which may be used to calculate required volume(s) in Volume

3, Chapter 1 – Standard 4.

Page 21: DRAFT Water Resources Technical Bulletin · and PPWSA layers in the RPP Data Viewer) must employ the following methods to meet Objective WR1: • All development, construction, clearing,

DRAFT Water Resources Technical Bulletin Page 21

DETAILED METHODS FOR MEETING OBJECTIVE WR5

Objective WR5: Manage groundwater withdrawals and discharges to maintain hydrologic

balance in a way that is protective of surface and groundwater resources

Projects that exceed 20,000 gpd withdrawals should provide adequate groundwater

characterization to demonstrate that drawdown of the groundwater due to pumping will not

negatively impact nearby surface waters and wetlands, which may be connected to and fed by

groundwater. The study should include mapping of surface water morphology and comparison

of existing and affected water-table fluctuations. In addition, wastewater discharges should

provide adequate groundwater characterization to determine the maximum expected height of

groundwater mounds and the potential for groundwater with this additional mounding to

breakout above the land surface. Projects should provide a high groundwater estimation

consistent with the methodology of Appendix B –Estimation of High Groundwater Levels to

incorporate into modeling of potential mounding.

Page 22: DRAFT Water Resources Technical Bulletin · and PPWSA layers in the RPP Data Viewer) must employ the following methods to meet Objective WR1: • All development, construction, clearing,

DRAFT Water Resources Technical Bulletin Page 22

DETAILED WATER RESOURCES APPLICATION REQUIREMENTS

1. The project narrative should include a description of the site location and any applicable

resource areas, existing site conditions, and how the proposed project will change those

conditions during and after construction. Areas that should be considered include:

a. Presence of existing and proposed drinking water wells within 400 feet of project

boundaries

b. Quantity of wastewater generation expected and proposed treatment

c. Source of drinking water supply

d. Changes in natural and impervious area cover

e. Stormwater management and treatment

f. for previously developed sites a description of historical site usage, and if a

reportable release under the MCP has occurred at the project site or if a Site

Release Tracking Number (RTN) has been assigned for the site by MassDEP, a

Chapter 21E site assessment or other Environmental Site Assessment

information should be submitted for Commission review.

2. A calculation of site-wide nitrogen loading should be performed using the method

described in Appendix A.

3. The site design should specify the location of the proposed septic system or wastewater

treatment facility and identify downgradient resources as described in WR1 – detailed

methods.

4. The stormwater report should include a description of the proposed system (for small

systems, the description in the project narrative may be sufficient) and the following

information as necessary:

a. Soil survey and / or boring logs

b. Calculation of high groundwater level to ensure that stormwater facilities are

designed with proper separation from the water table as described in WR4 –

detailed methods.

c. Estimate of TSS removal achieved in stormwater treatment train(s) using

MassDEP’s TSS Removal Calculation Worksheet

(https://www.mass.gov/files/documents/2016/08/nn/tss.xls)

d. Calculation of required water quality treatment volume and treatment volume

provided as described in WR4 – detailed methods.

e. Engineering design drawings or cut sheets for proposed stormwater system

components

5. Operations and maintenance plans for all proposed water systems (drinking water

supply, stormwater, and wastewater treatment) should be submitted for Commission

review

Page 23: DRAFT Water Resources Technical Bulletin · and PPWSA layers in the RPP Data Viewer) must employ the following methods to meet Objective WR1: • All development, construction, clearing,

DRAFT Water Resources Technical Bulletin Page 23

DEFINITIONS

Best Management Practice (BMP) – structural or procedural control measures implemented to

reduce the quantity and velocity of stormwater runoff, and improve water quality

Fresh Water Recharge Area (FWRA) – Watershed area that contributes to a fresh water pond as

defined by the topography of the water table.

Hazardous Material – Any chemical or substance that when released into the environment will

pose a significant contaminant threat to groundwater and drinking water supplies.

Hazardous Materials / Hazardous Wastes, Household Quantity of – quantities less than the

following limits are considered Household Quantities:

(d) 275 gallons of oil on site at any time to be used for heating of a structure, or to supply an

emergency generator

(e) 25 gallons or equivalent dry weight, total, of Hazardous material(s) on site at any time

(excluding oil as classified in part (a))

(f) 55 gallons of Hazardous Waste generated at the Very Small Quantity Generator level as

defined in Massachusetts Hazardous Waste Regulations (310 CMR 30.000) and

accumulated or stored on-site at any time.

Hazardous Waste – Any Hazardous Waste, Universal Waste, or Waste as defined in the

Massachusetts Hazardous Waste Regulations (310 CMR 30.010), not including Hazardous

Materials or biomedical wastes regulated under the Massachusetts State Sanitary Code (105

CMR 480.00).

Impaired Area –Impaired Areas are where groundwater may have been degraded by point and

non-point sources of pollution, including but not limited to areas with unsewered residential

developments with an average lot size of less than 20,000 square feet; landfills, septage, and

wastewater treatment plant discharge sites; and areas of high-density commercial and industrial

development and those downgradient areas where groundwater may have been degraded by

those sources.

Impervious Area – Land area that is covered by surfaces which do not permit precipitation to

naturally recharge. Typically includes paved surfaces, roadways, parking areas, and rooftops.

Infill – Development of new housing, commercial, or other amenities on scattered or

discontinuous sites within existing substantially built-up areas.

Marine Water Recharge Area (MWRA) – Watershed area that contributes to a marine

embayment as defined by the topography of the water table, and determined by United States

Geological Survey (USGS) modeling as part of the Massachusetts Estuaries Project (MEP)

Potential Public Water Supply Area (PPWSA) – Land identified as suitable for the development

of public water supplies.

Page 24: DRAFT Water Resources Technical Bulletin · and PPWSA layers in the RPP Data Viewer) must employ the following methods to meet Objective WR1: • All development, construction, clearing,

DRAFT Water Resources Technical Bulletin Page 24

Wastewater treatment facility (WWTF) – Wastewater treatment and collection systems that are

designed to treat flows greater than 10,000 gallons per day.

Wellhead Protection Area (WHPA) - Lands receiving precipitation that contribute to the

recharge of public drinking water supply wells are considered Wellhead Protection Areas

(WHPA). These include MADEP approved Zone IIs, interim wellhead protection areas, and

certain town delineated water protection districts that extend beyond the Zone II limits.

REFERENCES

Cape Cod Commission, 1992. Estimation of High Groundwater Levels for Construction and

Land Development, Technical Bulletin 92-001

Cape Cod Commission, 1999. Priority Land Acquisition Assessment Project – A guide to

evaluating the suitability of land for future water supply sites

Cape Cod Commission, 2001. Priority Land Acquisition Assessment Project Phase II

Massachusetts Estuaries Project and Reports

https://www.mass.gov/guides/the-massachusetts-estuaries-project-and-reports

The Massachusetts Stormwater Handbook and Stormwater Standards

(https://www.mass.gov/guides/massachusetts-stormwater-handbook-and-stormwater-

standards)

National Weather Service, 1961. Technical Paper 40: Rainfall Frequency Atlas of the United

States

National Oceanic and Atmospheric Administration, 2015. Atlas 14 Precipitation Frequency Data

Server

https://hdsc.nws.noaa.gov/hdsc/pfds/pfds_map_cont.html

Northeast Regional Climate Center, 2011. Extreme Precipitation Analysis.

http://precip.eas.cornell.edu/

USGS, 1986. Ground-Water Resources of Cape Cod, Massachusetts Hydrologic Investigations

Atlas-692

United States Environmental Protection Agency, 2009. Incorporating Environmentally

Sensitive Development into Municipal Stormwater Programs

https://www.epa.gov/sites/production/files/2015-

11/documents/region3_factsheet_lid_esd.pdf

Metropolitan Area Planning Council, 2014. Low Impact Development Toolkit

https://www.mapc.org/resource-library/low-impact-development-toolkit/

Grow Smart Maine, 2015. Building “Smart”: Environmentally Sensitive Design

https://growsmartmaine.org/wp-content/uploads/2015/08/Enviro_Sensitive_Design-Final-

21-Nov-06.pdf

University of Massachusetts Extension, 2018. Integrated Pest Management Program

http://ag.umass.edu/integrated-pest-management

Page 25: DRAFT Water Resources Technical Bulletin · and PPWSA layers in the RPP Data Viewer) must employ the following methods to meet Objective WR1: • All development, construction, clearing,

DRAFT Water Resources Technical Bulletin Page 25

APPENDIX A: NITROGEN LOADING GUIDANCE FOR WATER RESOURCES

The Water Resource Goal of the Cape Cod Commission’s Regional Policy Plan is “to maintain a

sustainable supply of high quality untreated drinking water and protect, preserve or restore the

ecological integrity of fresh and marine surface waters.” The Water Resources Technical

Bulletin contains five (5) Objectives that are distinguished by Water Resource Area and

Placetype. The Water Resource Areas are: Wellhead Protection Areas, Fresh Water Recharge

Areas, Marine Water Recharge Areas, and Potential Water Supply Areas. The Water Resources

Technical Bulletin also recognizes Impaired Areas where water quality may have been impaired

from existing development.

THE APPLICANT WILL NEED TO KNOW SPECIFIC PROJECT INFORMATION TO

COMPLETE A NITROGEN LOADING CALCULATION

A methodology has been adopted by the Commission for calculating groundwater nitrogen

loading concentrations. The methodology is based on information and parameters describing

wastewater flows; stormwater runoff volumes; lawn sizes, fertilization and leaching rates;

respective nitrogen masses and concentrations attributable to these nitrogen sources, and

precipitation dilution factors as described below and shown in the example calculations.

WORKSHEET INSTRUCTIONS

The applicant will need to know the information listed below to complete a Nitrogen Loading

calculation:

Identify the Water Resource Area the project is located in, if any (RPP Data Viewer);

1. Upland area of site (square feet);

2. Wastewater flow rate (calculated pursuant to 310 CMR 15.203);

3. Actual Flow rate determined by occupancy rate;

4. Average residential flow rate, calculated from the Title 5 design + the Actual Flow rate

5. Type of septic system proposed (e.g. alternative design pursuant to 310 CMR 15.280);

6. Paved and roof areas (assumed 2,500 square feet for residential projects);

7. Proposed lawn area (assumed 5,000 square feet for residential projects);

A summary of Nitrogen Loading conversion factors and sample calculations are shown on the

following pages.

A Nitrogen Loading and Mitigation Worksheet is available at < link to be inserted in final

draft>.

Page 26: DRAFT Water Resources Technical Bulletin · and PPWSA layers in the RPP Data Viewer) must employ the following methods to meet Objective WR1: • All development, construction, clearing,

DRAFT Water Resources Technical Bulletin Page 26

SUMMARY OF NITROGEN LOADING VALUES

TARGET CONCENTRATION: 5 ppm (milligram/liter) NO3-N

WASTEWATER Residential Concentration: 35 ppm NO3-N Flow: Title 5 (310 CMR 15.02) Non-residential Concentration: 35 ppm NO3-N Flow: Title 5 Design or actual documented flows

OCCUPANCY: Range (Actual town rate to 2 people per bedroom)

LAWNS Area: 5,000 ft2 Fertilizer: 3 lbs/1,000 ft2 of lawn Leaching: 25% RECHARGE From impervious surfaces: 40 inches per year Concentrations Road runoff: 1.5 ppm NO3-N Roof runoff: 0.75 ppm NO3-N Natural areas Barnstable: 18 inches per year Bourne: 21 in/yr Brewster: 17 in/yr Chatham: 16 in/yr Dennis: 18 in/yr Eastham: 16 in/yr Falmouth: 21 in/yr Harwich: 17 in/yr Mashpee: 19 in/yr Orleans: 16 in/yr Provincetown: 16 in/yr Sandwich: 19 in/yr Truro: 16 in/yr Wellfleet: 16 in/yr Yarmouth: 18 in/yr

Page 27: DRAFT Water Resources Technical Bulletin · and PPWSA layers in the RPP Data Viewer) must employ the following methods to meet Objective WR1: • All development, construction, clearing,

DRAFT Water Resources Technical Bulletin Page 27

Page 28: DRAFT Water Resources Technical Bulletin · and PPWSA layers in the RPP Data Viewer) must employ the following methods to meet Objective WR1: • All development, construction, clearing,

DRAFT Water Resources Technical Bulletin Page 28

Page 29: DRAFT Water Resources Technical Bulletin · and PPWSA layers in the RPP Data Viewer) must employ the following methods to meet Objective WR1: • All development, construction, clearing,

DRAFT Water Resources Technical Bulletin Page 29

Water Resources Nitrogen Loading and Mitigation WorksheetSee Technical Bulletin 91-001 for further details: http://www.capecodcommission.org/regulatory/NitrogenLoadTechbulletin.pdf

Project Nitrogen Load Wastewater Proposed development Existing (if redevelopment)

Calculate (A') through (P') as w/ (A) through (P):

1. Enter value Project Title-5 wastewater flows: gpd (a) Title-5 wastewater flows: gpd

Enter value Actual wastewater flows: * (b) Actual wastewater flows: *

Calculated value Average wastewater flows: gpd (a)+(b) 2= (A) Ave. wastewater flows: gpd (A')

Place √ in applicable box: * Title-5 flows prescribed by TB91-001 for commercial uses

Yes No

Will the project be connected to sewer ? Place √ in applicable box:

Yes No

Is project Title-5 wastewater flow 10,000 gpd or greater ? Is existing development on sewer ?

(If 'Yes', then the project must be reviewed for consistency with MPS WR6) (If 'Yes', then go to line 2.)

Place √ in applicable box and multiply unsewered wastewater flow by applicable conversion factor:

Standard Title-5 System (35-ppm-N) x 0.048359 Standard Title-5 System

DEP-approved I/A System (25-ppm-N) x 0.034542 DEP-approved I/A System (commercial)

DEP-approved I/A System (19-ppm-N) x 0.026252 Type of system: ________________ DEP-approved I/A System (residential)

Groundwater Discharge (10-ppm-N) x 0.013817 Wastewater Treatment Facility (GWDP)

Calculated value Wastewater nitrogen load (Title-5 flows) = kg-N/yr (B) kg-N/yr (B')

ALARM

Calculated value Wastewater nitrogen load (Actual flows) = kg-N/yr (C) kg-N/yr (C')

ALARM wastewater offsets

Stormwater Runoff

Town: ___________________

Enter value Recharge rate for town (for natural areas from Technical Bulletin 91-001): (RECH)

Enter value Project site area: acres (D) Project site area: acres (D)

Enter value Project site wetland area: acres (E) Project site wetland area: acres (E)

Calculated value Project site upland area: acres (F) Project site upland area: acres (F)

Calculated value Pervious unpaved upland: acres (G) Pervious unpaved upland: acres (G')

Enter values % using LID Paved area: s.f. (H) Paved area: s.f. (H')

Factor may be adjusted for employment of LID → x 1.4158E-04 1.416E-04

Calculated value = kg-N/yr (I) Paving runoff offset: kg-N/yr (I')

Enter value Roof area: s.f. (J) Roof area: s.f. (J')

x 7.0792E-05

Calculated value = kg-N/yr (K) Roof runoff offset: kg-N/yr (K')

Fertilizer

Enter value Managed turf: s.f. Managed turf: s.f.

x 3.4019E-04

Calculated value = kg-N/yr (L) Fertilizer offset: kg-N/yr (L')

Total Nitrogen Load

Calculated value Total project nitrogen load (Title-5 flows): kg-N/yr (M)= (B)+(I)+(K)+(L) kg-N/yr (M')

Calculated value Total project nitrogen load (Actual flows): kg-N/yr (N)= (C)+(I)+(K)+(L) Existing nitrogen load (Actual flows): kg-N/yr (N')

Calculated value Nitrogen load per acre (Average): kg-N/yr/acre (O)= (M)+(N) 2 (F) Nitrogen offset per acre: kg-N/yr/acre (O')

Nitrogen Loading Concentration Existing nitrogen loading concentrations:

Calculated value

Project nitrogen loading concentration (Title-5 flows):

Calculated value

Project nitrogen loading concentration (Actual flows):

Calculated value

Project nitrogen loading concentration (Average):

next page -->

Actual flows

(P)=

(R')(R)=

}

(Q)=

Recharge rate for town (inches; for natural areas

from Technical Bulletin 91-001):

(a)723.76 + (G)x(RECH)9.7286 + (H)10,594 + (K)0.75 Title-5 flowsppm-N

ppm-N

Average

_________(M)_________

ppm-N

DRAFT

(P)+(Q) 2

(Q')

ppm-N ppm-N

_________(N)_________

(b)723.76 + (G)x(RECH)9.7286 + (H)10,594 + (K)0.75

Existing nitrogen load (Title-5 flows):

ppm-N (P')

Page 30: DRAFT Water Resources Technical Bulletin · and PPWSA layers in the RPP Data Viewer) must employ the following methods to meet Objective WR1: • All development, construction, clearing,

DRAFT Water Resources Technical Bulletin Page 30

Resource/ Impact Based Criteria

Marine Water Recharge Areas

Yes No

2.

(If 'No', then go to line 3.)

Enter value Fair Share nitrogen-loading limit** : kg-N/year/acre (S)

Does project's nitrogen load (O) exceed the existing load (O') AND the critical nitrogen load (S) ?

(If 'No', then go to line 3.)

Calculated value Excess project nitrogen load to be mitigated: kg-N/yr (T)= LESSER OF (O)-(S) x(F) AND (O)-(O') x(F)

x 1,550

Calculated value = $ (U)

Place √ in box if applicant intends to make this payment (S)

(If not checked, then the project must provide an alternative strategy for meeting its Fair Share nitrogen load pursuant to MPS WR3.4)

Groundwater Quality

Yes No

3. Does the project's nitrogen loading concentration in groundwater (R) exceed the greater of 5 ppm or the existing concentration (R') ?

(If 'Yes' and the project is located in a Water Quality Improvement Area (Map WR5), the project may need to provide an alternative strategy for meeting MPS WR1.1 and WR5.4)

Potential Public Water Supply Areas

Yes No

4. Is project in a Potential Public Water Supply Area (PPWSA, Map WR2) ?

(If 'No', then go to line 5.)

Has the Town or local water district documented the release of the site from consideration as a PPWSA ?

(If 'Yes', then go to line 5.)

Does the project's nitrogen loading concentration (R) exceed the greater of 1 ppm or the existing concentration (R') ?

(If 'Yes', the project must provide an alternative strategy for meeting MPS WR2.6)

Does the project use, treat, generate, store or dispose of hazardous materials in excess of the greater of a) household quantities or b) existing quantities ?

(If 'Yes', the project must provide an alternative strategy for meeting MPS WR2.2)

Wellhead ProtectionAreas

Yes No

5. Is project in a Wellhead Protection Area (WHPA, Map WR2) ?

(If 'No', then go to line 6.)

Does the project's nitrogen loading concentration (R) exceed the greater of 5 ppm or the existing concentration (R') ?

(If 'Yes' and the project is located in a Water Quality Improvement Area (Map WR5), the project must provide an alternative strategy for meeting MPS WR2.1)

Does the project use, treat, generate, store or dispose of hazardous materials in excess of the greater of a) household quantities or b) existing quantities ?

(If 'Yes', the project must provide an alternative strategy for meeting MPS WR2.2)

Fresh Water Recharge Areas

Yes No

6. Is project wastewater disposed of within 300 feet of a stream or fresh surface water body (Map WR4)?

(If 'No', then go to line 7.)

Is the project located hydraulically upgradient of a stream or fresh surface water body ?

(If 'Yes', the project must provide an alternative strategy for meeting MPS WR4.1)

Other Potential Impacts

Yes No

7. Will the project withdraw more than 20,000 gallons of water per day ?

(If 'Yes', then the project must provide documentation demonstrating that there will not be significant impacts to water levels, surface waters and wetlands)

8.

Name of Marine Water Recharge Area sub-embayment

(from RPP Water Resource Classification Map II ):

Is the project in Marine Water Recharge Area (MWRA, Map WR3) with a nitrogen-loading limit OR in a MWRA that discharges to coastal waters with documented impaired water quality** ?

The project must demonstrate compliance with MPS WR1 and MPS WR7, including use of Low Impact Development to mitigate impacts of stormwater runoff and O & M plans for maintaining stormwater infrastructure and landscaping.

** Fair Share nitrogen-loading limit is determined through either a Total Maximum Daily Load (TMDL), a Massachusetts Estuaries Project-accepted technical report, or specified by a Commission-approved comprehensive wastewater management plan pursuant to MPS

WR3.1 & WR3.3. If a nitrogen-loading limit is unavailable and impaired water quality has been documented for the receiving coastal waters, the nitrogen loading limit shall be 0 kg-N/yr per acre pursuant to MPS WR3.2.

Page 31: DRAFT Water Resources Technical Bulletin · and PPWSA layers in the RPP Data Viewer) must employ the following methods to meet Objective WR1: • All development, construction, clearing,

DRAFT Water Resources Technical Bulletin Page 31

APPENDIX B: ESTIMATION OF HIGH GROUND-WATER LEVELS

The Water Resources Technical Bulletin Appendix B - Estimation of High GW is available at

<link to be inserted in final draft>.

Page 32: DRAFT Water Resources Technical Bulletin · and PPWSA layers in the RPP Data Viewer) must employ the following methods to meet Objective WR1: • All development, construction, clearing,

DRAFT Water Resources Technical Bulletin Page 32

APPENDIX C: MONETARY NITROGEN OFFSET

For projects that will not connect to sewer, monetary nitrogen offsets may be allowed in certain

circumstances. The appropriate Placetypes and methods for providing a monetary nitrogen

offset are generally set forth in the 2018 Water Resource Technical Bulletin.

Nitrogen Management Policy

The 2018 RPP encourages growth in certain areas, such as Community Activity Centers, and

discourages growth in other areas, such as in Natural Areas. For that reason, the per kilogram

nitrogen monetary offset may be applied up to the maximum amount of $8,290; however, a

lesser dollar amount per kilogram of nitrogen ($0 to less than $8,290) may be applied in areas

where growth is encouraged.

The maximum dollar per kilogram amount of $8,290 for nitrogen offsets is based on Capital and

20-year O&M costs for nitrogen removal by conventional sewering as derived from the

Comparison of Costs for Wastewater Management Systems Applicable to Cape Cod, updated in

2014. The infrastructure and operational costs in the 2014 report have not been adjusted for

inflation to present day costs. In this regard, the $8,290 per kilogram figure is a conservative

estimate of actual costs in that todays costs will be higher.

Calculation of Monetary Nitrogen Offset

Calculated cost to remove nitrogen with a typical wastewater treatment facility:

Capital cost (assumed design flow of 1.5 mgd; 100 linear feet per parcel connected)

$181 million (present worth based on 2014 Cost Report numbers)

• Operations & Maintenance

$1.50 million per year (20-yr planning period)

• Total present worth based on 2014 Cost Report numbers (capital + O&M)

$206 million

• Load removed (20-yr planning period)

24,800 kg-N per year

• Cost efficiency

$8,290 / kg-N removed per year

Example offset

• 30-unit residential sub-division (mix of 2- and 3-bedroom)

• Actual flow: 125 gpd per unit; 3,760 gpd total

• Wastewater load to be offset: 136 kg-N/yr

• Calculation of monetary offset

$1.13 million = $206 million x 136 kg-N/yr / 24,800 kg-N/yr

= $8,290 / kg-N per year x 136 kg-N/yr