Upload
others
View
7
Download
0
Embed Size (px)
Citation preview
Wind Farm Collie Hill
DRAFT Project Description Report
Prepared by:
Prepared for:
Wind Farm Collie Hill
DRAFT Project Description Report
Prepared by: M.K. Ince and Associates Ltd.
Prepared for: Wind Farm Collie Hill LP
November 16, 2012
DRAFT Project Description Report
Wind Farm Collie Hill DRAFT Project Description Report
M.K. Ince and Associates Ltd. i November 16, 2012
Table of Contents
1 PROJECT OVERVIEW ...................................................................................................................................... 1
1.1 REGULATORY AND REPORTING REQUIREMENTS ....................................................................................................... 1 1.2 CONTACT INFORMATION .................................................................................................................................... 2 1.3 REQUIRED AUTHORIZATIONS ............................................................................................................................... 2
2 PROJECT DESCRIPTION .................................................................................................................................. 4
2.1 PROJECT STRUCTURES & TURBINE TECHNOLOGIES ................................................................................................... 4 2.2 PROJECT LOCATION ........................................................................................................................................... 4 2.3 PROJECT ACTIVITIES ........................................................................................................................................... 8
2.3.1 Planning ................................................................................................................................................... 8 2.3.2 Construction ............................................................................................................................................. 8 2.3.3 Operation and Maintenance .................................................................................................................. 10 2.3.4 Decommissioning ................................................................................................................................... 10
3 PROJECT ENVIRONMENTAL FEATURES ........................................................................................................ 12
3.1 ARCHAEOLOGICAL AND CULTURAL HERITAGE RESOURCES ....................................................................................... 12 3.2 AIR ............................................................................................................................................................... 12 3.3 PUBLIC HEALTH AND SAFETY ............................................................................................................................. 12 3.4 WATER BODIES AND GROUNDWATER ................................................................................................................. 14 3.5 LAND USE ...................................................................................................................................................... 14 3.6 BIRDS ........................................................................................................................................................... 15 3.7 BATS ............................................................................................................................................................ 16 3.8 NATURAL HERITAGE FEATURES AND SIGNIFICANT WILDLIFE..................................................................................... 16
4 CONCLUSION ............................................................................................................................................... 18
5 REFERENCES ................................................................................................................................................ 19
Table of Tables
Table 1-1 Ontario Regulation 359/09 Project Description Report Requirements ......................................................... 1
Table 1-2 Municipal and Conservation Authority Permits/Approvals ........................................................................... 2
Table 1-3 Provincial Permits/Approvals ........................................................................................................................ 2
Table 1-4 Federal Permits/Approvals ............................................................................................................................ 3
Table of Figures
Figure 2-1 Project Overview Map .................................................................................................................................. 6
Figure 2-2 Project Location Map ................................................................................................................................... 7
Wind Farm Collie Hill DRAFT Project Description Report
M.K. Ince and Associates Ltd. 1 November 16, 2012
1 PROJECT OVERVIEW
The Wind Farm Collie Hill project is a 5.4 MW Class 4 Wind Energy Generation Facility proposed on
private agricultural lands within the Township of Asphodel-Norwood by Wind Farm Collie Hill LP. The
facility will consist of three (3) REPower MM100 wind turbines (or similarly appropriate technology),
each with a nameplate capacity of 1.8 MW. A Power Purchase Agreement (PPA) has been acquired for
the project under Ontario’s Feed-In Tariff (FIT) Program.
The purpose of the Wind Farm Collie Hill project is to generate energy from a clean, renewable source
and to provide electricity to Ontario consumers. The promotion of wind energy within the Township of
Asphodel-Norwood will displace greenhouse gases, air pollution, and toxic solid waste from traditional
energy production methods in the Province of Ontario. This will greatly contribute to the preservation of
the natural environment.
The proposal includes the construction, operation, maintenance and decommissioning of these wind
energy projects and their associated access roads, substation, distribution lines and poles, and other
infrastructure.
1.1 Regulatory and Reporting Requirements
The Green Energy and Green Economy Act, passed in the Province of Ontario in 2009, mandates a
Renewable Energy Approval (REA) process under the Environmental Protection Act, Ontario Regulation
359/09 for specified classes of renewable energy projects. The Wind Farm Collie Hill wind project is
subject to this process, which will evaluate the project’s environmental and community impacts and
mitigate or avoid them where necessary. M.K. Ince & Associates prepared this Project Description Report
(PDR) to meet the requirements of Ontario Regulation 359/09 and provide a brief overview of the
proposed project to stakeholders.
The reporting requirements set out by O.Reg 359/09 are summarized with reference to specific sections of
the Project Description Report in Table 1-1.This checklist should be used for reference purposes only
and should not replace a full reading of the report.
Table 1-1 Ontario Regulation 359/09 Project Description Report Requirements
Required Documentation Location in Report
Set out a description of the following in respect of the renewable energy project;
Any energy sources to be used to generate electricity at the renewable energy
generation facility. Section 2.1
The facilities, equipment or technology that will be used to convert the renewable
energy source or any other energy source to electricity. Section 2.1
If applicable, the class of the renewable energy generation facility. Section 1
The activities that will be engaged in as part of the renewable energy generation
facility. Section 2.3
The name plate capacity of the renewable energy generation facility. Section 1
The ownership of the land on which the project location is to be situated. Section 2.2
Wind Farm Collie Hill DRAFT Project Description Report
M.K. Ince and Associates Ltd. 2 November 16, 2012
Any negative environmental effects that may result from engaging in the project. Section 3
An unbound, well-marked, legible and reproducible map that is an appropriate size
to fit on a 215 mm by 280 mm page, showing the project location and the land
within 300 m of the project location. Figure 2-2
1.2 Contact Information
The proponent of the Wind Farm Collie Hill project is Wind Farm Collie Hill LP. M.K. Ince and
Associates Ltd. (MKI) is providing consulting services for the project.
Contact information is as follows:
Ingo Stuckmann
Wind Farm Collie Hill LP
WindWorks Power Corp
346 Waverley Street
Ottawa, ON K2P 0W5
Email : [email protected]
Katie Meyer-Beck
M.K. Ince and Associates Ltd.
11 Cross St., Dundas, ON L9H 2R3
Tel: 905-628-0077
Fax: 905-628-1329
Email: [email protected]
1.3 Required Authorizations
The project will require permits from Federal, Provincial, and Municipal levels of government. The list
presented below covers some of the key permits and approvals that will be required in order to construct
the Wind Farm Collie Hill project.
Table 1-2 Municipal and Conservation Authority Permits/Approvals
Permit Responsible Agency Info
Building Permit Township of Asphodel-
Norwood
Ontario Building Code compliance
Road right of way
agreement
County of Peterborough Required for running electrical cabling in or
under existing road rights of way
Entrance permit County of Peterborough May be required for upgrades to existing
entrances
Table 1-3 Provincial Permits/Approvals
Permit Responsible Agency Info
Renewable Energy
Approval (REA)
Ministry of Environment,
Ministry of Natural Resources
Project approval, environmental impact
assessment
Connection
Agreement
Hydro One Networks Inc.,
IESO
Process requirements for project grid
connection
Transportation Permit Ministry of Transportation Highway road traffic and safety
Generator’s License Ontario Energy Board Interconnection to provincial grid
Wind Farm Collie Hill DRAFT Project Description Report
M.K. Ince and Associates Ltd. 3 November 16, 2012
Table 1-4 Federal Permits/Approvals
Permit Responsible Agency Info
Navigational
Clearances
Transport Canada, NAV
Canada
Radar, navigational lighting, blade markings,
aeronautical clearance
Wind Farm Collie Hill DRAFT Project Description Report
M.K. Ince and Associates Ltd. 4 November 16, 2012
2 PROJECT DESCRIPTION
2.1 Project Structures & Turbine Technologies
Wind turbines convert the kinetic energy of surface winds into electrical energy in the form of electricity.
There are four major components of a wind turbine: the blades, the shaft, the generator, and the tower,
which supports the first three. As the wind travels across the turbine blades, a lift force – similar to that
which allows airplanes to fly – causes the blades to turn. The turbine blades rotate the shaft, which is
connected to either a direct drive generator or an induction generator, thus producing electricity.
As currently envisioned, the wind turbine type proposed for the Wind Farm Collie Hill is the
REPower MM100 WTG. This turbine has three (3) fibreglass blades equipped with lightning arrestors.
This model has a total swept area of 7854 m². The rotor diameter is 100 m and the hub height will be
100.0 m, for a maximum total height of 150 m above grade. Each tower will be conical, made of steel and
be approximately 5 m in diameter at the base. During operation, the blades rotate clockwise at speeds
between 7.8 and 13.9 rpm (revolutions per minute). The blades of the MM100 are pitch-controlled and
are designed to cut out when wind speeds exceed 22.0 m/s (79.2 km/h). The manufacturer’s specifications
of the REPower MM100 wind turbine are included in the Wind Turbine Specifications Report in the final
REA submission.
The base of each turbine will be a poured concrete foundation with reinforcing steel bars. The foundation
will contain a mounting ring to which the base of the tower will be attached. The foundation
specifications will depend on the results of a geotechnical investigation of the proposed wind farm
location.
Transformers will be installed either adjacent to or within the base of each turbine tower and will step up
the voltage from the generator voltage to a higher intermediate voltage for connection to the internal
project substation and collector system. The substation of the wind park will house metering,
communication equipment, control devices, and a transformer which will step up the voltage to 44 kV to
match the local distribution lines. Connection from the substation to the existing distribution grid will be
carried out via a length of overhead cabling to be built and owned by Hydro One. The overhead cabling
will run within existing road easements to the M28 Feeder of the Otonabee Transmission Station.
2.2 Project Location
The facility is proposed on privately-owned agricultural lands near the community of Hastings in the
Township of Asphodel-Norwood, a municipality of the County of Peterborough. All turbine locations
have been sited within the area bounded by Centre Line to the North, River Road to the South, Fifth Line
to the West and Sixth Line the East. An overview of the project location is illustrated in Figure 2-1.
The Wind Farm Collie Hill project location is an area encompassing all facility components including the
following:
• turbine foundations and towers,
• the bladeswept area,
• crane pads and turbine component laydown areas,
• access/construction roads,
• parking lot,
• administration area,
Wind Farm Collie Hill DRAFT Project Description Report
M.K. Ince and Associates Ltd. 5 November 16, 2012
• electrical cabling, and
• the substation.
Figure 2-2 depicts the above mentioned project components and also identifies the boundaries of the
project location.
Wind Farm Collie Hill DRAFT Project Description Report
M.K. Ince and Associates Ltd. 6 November 16, 2012
Figure 2-1 Project Overview Map
Wind Farm Collie Hill DRAFT Project Description Report
M.K. Ince and Associates Ltd. 7 November 16, 2012
Figure 2-2 Project Location Map
Wind Farm Collie Hill DRAFT Project Description Report
M.K. Ince and Associates Ltd. 8 November 16, 2012
2.3 Project Activities
2.3.1 Planning
The initial stages of the project development process involved various studies to plan, assess and appropriately
design the proposed Wind Farm Collie Hill project. Project planning activities included the following.
Installation of a meteorological tower was undertaken to monitor local wind patterns and determine generation
potential.
Consultation with stakeholders, including the public, planning and permitting authorities, representatives of the
municipalities, aboriginal groups, provincial and federal agencies, and other relevant parties was undertaken as
per O.Reg. 359/09. The first of two public meetings was held on August 23, 2010 at Asphodel-Norwood
Community Centre. The second and final public meeting is planned for early 2013.
The Renewable Energy Approval process has been carried out by M.K. Ince and Associates Ltd., which has
provided consulting services to conduct the necessary environmental studies and prepare the Renewable Energy
Approval Application documents as per Ontario Regulation 359/09. All environmental studies have been
completed and made available to the public 60 days prior to the final open house.
The results of the planning studies are available in the final REA reports that have been made public at the
proponent's website: www.zeroemissionpeople.com.
2.3.2 Construction
The construction phase of the Wind Farm Collie Hill project is planned for the second half of 2013 and is
expected to take approximately four months to complete.
Turbine construction will be undertaken in stages which are described in detail in the Construction Plan Report to
be submitted as part of the REA Application. The construction activities involved in the Wind Farm Collie Hill
project are outlined below:
Surveying and siting to mark the turbine locations, boundaries of foundation excavation, road and cabling routes,
etc.
Site clearing to remove vegetation at the locations of proposed infrastructure. The facility was designed to remain
on agricultural land and avoid wooded areas to the extent possible.
Construction of non-paved gravel surface roads and an administration area will be undertaken to allow access to
each individual wind turbine site, the parking lot and the temporary Site Office. This will involve the excavation
and grading of topsoil, deposition of aggregate and gravel materials, and further grading and compaction as
necessary. Roads have been designed to follow existing pathways, where possible, and be located to minimize the
impact on current land uses.
Construction of crane pads and laydown areas will be undertaken. A ‘pad’ area of approximately 25 m x 45 m
adjacent to each turbine location will be excavated, graded and constructed using an aggregate base with a gravel
surface in order to support the weight of heavy machinery. Rotor laydown areas will be graded where necessary
and will not require aggregate or gravel.
Wind Farm Collie Hill DRAFT Project Description Report
M.K. Ince and Associates Ltd. 9 November 16, 2012
Construction of concrete turbine foundations reinforced by steel rebar will be undertaken approximately two to
four weeks prior to turbine erection to allow for curing. Foundation design, including the foundation type and
dimensions, will be finalized based on the results of the geotechnical surveys at the turbine locations. De-watering
of the foundation pits may be required during periods of significant rainfall.
Delivery of equipment such as cranes, and turbine components will be accomplished with oversized trucks on
public roadways after obtaining the necessary permits from the Ministry of Transportation.
Turbine assembly and installation will be accomplished using two large cranes supported on the pad area adjacent
to each turbine site. The rotor will be assembled on the ground and raised during a time with calm winds and is
highly weather dependent. Alternatively, the hub will be installed into the nacelle and then each blade will be
lifted individually by the cranes.
Transformer installation and electrical works will involve the installation of the transformer on the concrete pad
adjacent to the base of each turbine tower, or within the tower if possible. An electrical connection will also be
made between the transformers and the turbine nacelles with cabling routed underground through the foundation.
Cabling for the project internal electrical collector system will also be buried and, will run adjacent to internal
project access roads or, for a short distance, within the road easement of Regional Road 2.
Substation construction will involve the construction of a concrete foundation which will include a large reservoir
to be filled with aggregate/gravel, allowing for any oil accidentally spilled from the transformers to be captured
within the interstitial space between the aggregate. Rebar, concrete formwork and substation equipment will be
assembled and installed. The cabling of the substation will be connected to the buried cabling of the project
collector system and the Hydro One network. Connection from the substation to the existing distribution grid will
be carried out via a length of overhead cabling, to be built and owned by the generator
The substation of the wind park will house metering, communication equipment, control devices, and a step up
transformer. The substation will require an area of approximately 30 m x 40 m and will be fenced to prevent
unauthorized access.
Water Taking is only anticipated in the event that rainfall accumulates in excavated areas and does not drain
rapidly enough for construction activities to continue in a timely manner. Any other water required for
construction activities, such as for dust control, will be brought in from off site.
Turbine Commissioning will involve a series of tests that will be performed on the wind turbine to confirm
protection system functionality and compatibility with the electricity grid.
Waste Disposal during construction will include the separation of waste, to be placed in disposal bins which will
be removed and disposed of by a licensed waste removal contractor.
Removal of Crane Pads and temporary construction roads will take place at the end of the construction phase, if
requested by the landowner. Aggregate and gravel will be excavated and removed from site. Topsoil that was
previously stockpiled on site will be used to backfill the excavated areas.
Site Rehabilitation upon commissioning of the turbines will restore portions of agricultural lands temporarily
disturbed through construction by grading, repairing tile drainage where necessary, re-applying topsoil, and de-
compacting soil where necessary. Non-agricultural areas will have topsoil re-applied; they will be re-graded with
due consideration to natural drainage patterns and seeded with non-invasive native grasses and herbaceous plants.
Wind Farm Collie Hill DRAFT Project Description Report
M.K. Ince and Associates Ltd. 10 November 16, 2012
2.3.3 Operation and Maintenance
Following the construction phase, the Wind Farm Collie Hill project is expected to be operational by the first half
of 2014. The operation phase is expected to be carried out continuously over the anticipated project life of 20
years in accordance with the project’s FIT Contract. Further details regarding project activities throughout the
operational phase of the facility are included in the Design and Operations Report in the REA submission for the
project and are summarized below.
Wind turbine operation on a day-to-day basis requires almost no human intervention. Dedicated supervisory
control and data acquisition (SCADA) systems will be used to capture real-time turbine feedback and monitor
outputs. When winds are sufficient, the turbine blades will rotate at a speed of 7.8 to 13.9 rpm (revolutions per
minute). The turbines will not operate in cases of mechanical breakdown, extreme weather conditions and during
maintenance.
Wind farm maintenance will involve regular inspection and maintenance, including routine oil changes, motor
maintenance and lubricant and fluid replacement. Periodically, major components of the wind turbines such as
blades or generators may require replacement, which may require reconstruction of the crane pads.
Environmental monitoring of environmental impacts will take place post-construction to assess any project-
related impacts to the environment. Complete descriptions of monitoring plans are provided in the Environmental
Effects Monitoring Plan contained in the Design and Operations Report.
Waste management at the facility will involve the collection of waste materials including oils, solvents, lubricants
and physical parts that will be brought off-site and disposed of according to relevant regulations.
Noise and air emissions during the operation of the turbines will consist solely of noise, largely composed of
aerodynamic noise associated with the passing of air over the rotating blades of the turbine as well as some
mechanical noise emitting from the rotating parts of the turbine. Further details pertaining to noise emission from
the turbines and nearby receptors are described in the Design and Operations Report and the Noise Impact
Assessment included in the final REA submission. No other air emissions will be generated by the operation of
this wind energy facility.
Water taking and stormwater management activities will be limited as no water taking, sewage management, or
biomass equipment processes will occur at the facility during the operations phase of the project. The only
stormwater management during the operations phase of the project will be related to any ongoing post-
construction erosion and sedimentation controls, discussed in the Environmental Effects Monitoring Plan
contained in the Design and Operations Report.
2.3.4 Decommissioning
The Feed-in Tariff (FIT) contract awarded to the Wind Farm Collie Hill project has a 20-year term beginning
from the Commercial Operation Date (i.e. the date upon which the turbines are commercially operational). At the
conclusion of this term, the decision will be made whether to continue operating the facility – conducting
maintenance and upgrades as necessary and selling the electricity through a new power purchase agreement or
through the spot market – or to decommission the wind park entirely.
Regardless of any decisions to extend the life of the project, decommissioning will eventually be necessary.
Detailed information regarding decommissioning activities is provided in the Decommissioning Plan Report
included in the final REA submission. The activities planned in the decommissioning phase of the Wind Farm
Collie Hill project include the following.
Wind Farm Collie Hill DRAFT Project Description Report
M.K. Ince and Associates Ltd. 11 November 16, 2012
Site clearing and preparation will involve the removal of vegetation from road corridors, crane pads or at turbine
sites as required. Any vegetation cleared from the site requiring off-site disposal will be taken to local waste
disposal facilities.
Road and crane pad construction/modification will take place as necessary and may involve the excavation of
topsoil, clearing grading and the possible use of geotextile and/or aggregate material depending on local
geotechnical conditions.
Removal of turbines and ancillary equipment will involve the disassembly of the turbines on site. Transformers at
the base of the turbines will be disconnected and drained. The turbine parts will be removed, then reused,
refurbished or recycled where possible. Oil will be disposed of according to relevant regulations. Turbine
foundations will be broken up and removed to a depth of approximately 1 m. This activity will take
approximately two months.
Removal of roads, administration area, and electrical infrastructure will involve the excavation of installed gravel
and aggregate, the removal of any overhead cabling and poles, as well as the removal all substation equipment
from the site. The substation foundation will be removed to a depth of approximately 1 m. The material removed
will be reused and recycled if possible or disposed of at appropriate waste facilities. The excavated areas will be
filled with soil from on site. Underground cabling will be left in place and only the ends will be removed as
excavating cabling often causes greater environmental disruption than leaving the cables in place. Similarly, the
installed culvert will be left in place.
Site rehabilitation and waste management will involve remediation and re-vegetation of disturbed land. Topsoil
stripped during decommissioning will be re-applied. Agricultural areas will be returned to agricultural use. All
damaged tile drains will be fixed. Re-vegetation will use native non-invasive grasses and herbaceous plants. This
activity will take approximately two weeks.
Wind Farm Collie Hill DRAFT Project Description Report
M.K. Ince and Associates Ltd. 12 November 16, 2012
3 PROJECT ENVIRONMENTAL FEATURES
3.1 Archaeological and Cultural Heritage Resources
Archaeological Resources may be uncovered or damaged by equipment during construction, major
maintenance or decommissioning activities. However, pre-construction Stage 1 and Stage 2
Archaeological Assessments identified no archeological resources and thus the risk of damage to
archaeological resources resulting from the Wind Farm Collie Hill project is considered to be low. In the
event that archeological resources are uncovered during any phase of the project, work will be stopped
and Ministry of Tourism, Culture and Sport (MTCS) and First Nations officials will be notified.
Cultural Heritage Resources can potentially be impacted by development. Specifically, wind turbines can
create shadows that alter the appearance of heritage resources; change the surrounding environment or
context of a heritage site; or obstruct significant views. Pre-construction assessments of cultural heritage
identified 2 resources of heritage value in the study area, one of which has the potential to be impacted by
construction activities. However, maintenance of a 50 m buffer zone between the building and below-
grade construction activities is expected to address any risks to cultural resources.
3.2 Air
Dust and Odour may result from construction and decommissioning activities, particularly site clearing,
and grading. During operation, use of gravel roads by maintenance workers during dry periods has the
potential to create dust similar to any other gravel or dirt path in the vicinity. This effect is anticipated to
be minor in terms of impact and limited in geographic and temporal extent.
Noise emissions above levels typical in a rural area may result from the operation of construction
equipment; however, noise receptors are not expected to be significantly affected due to the limited nature
of construction, maintenance and decommissioning activities. During operation, the turbines will create
noise, largely composed of aerodynamic noise associated with the passing of air over the rotating blades
of the turbine as well as some mechanical noise emitting from the rotating parts of the turbine. Local
residents may experience an increase in noise levels in proximity to the turbines during turbine operation.
Predictive noise modeling has been conducted to assess turbine-related sound levels at nearby receptors
under worst-case conditions and has identified that the project is in compliance with the Ontario Ministry
of Environment’s Noise Guidelines for Wind Farms (October 2008). These guidelines mandate a limit of
40 dBA at the nearest noise receptors, so no significant impacts are anticipated. Further detail related to
the project-related noise and mitigation measures is provided in the Design and Operations Report and
Noise Impact Assessment.
3.3 Public Health and Safety
Impacts to public health and safety from the Wind Farm Collie Hill project are expected to be minimal.
Detailed assessments of potential health and safety impacts were conducted and included the following.
Fires could unexpectedly result from the construction, operation, or decommissioning of the project.
Alternatively, it is possible that a fire started off-site could spread into the project area. In the unlikely
Wind Farm Collie Hill DRAFT Project Description Report
M.K. Ince and Associates Ltd. 13 November 16, 2012
event of fire, appropriate mitigation measures and contingency measure have been prepared to manage
the risk of fire. These are detailed in the Design and Operations Report.
Construction poses a potential risk of injury to members of the general public if they were to come on
site, due to the presence of heavy machinery and construction equipment. However, the implementation
of mitigation measures to inform the public and limit unauthorized access is anticipated to minimize this
risk. These are detailed in the Construction Plan Report and the Design and Operations Report.
Ice Throw is a potential negative project-related impact to public health that was assessed in a pre-
construction review of existing literature. With appropriate mitigation measures including turbine
setbacks from residences and automatic monitoring of ice accretion throughout turbine operation, the risk
of ice throw affecting the public is anticipated to be minimal.
Blade Failure resulting in blade throw is a potential result of turbine operation. However, the risk of blade
failure is very low and, with regular maintenance, no impacts are anticipated.
Aeronautical Safety is a potential issue due to the height of the turbines. Appropriate lighting of turbines
as determined through consultation with Transport Canada and the Department of National Defense is
anticipated to mitigate the project’s impact to aeronautical safety.
Shadow Flicker assessments completed in the pre-construction stage of the project have determined that
potential shadow flicker resulting from the project occurs at a frequency below 2.5 Hz and is thus
considered a potential nuisance impact, as opposed to a health impact.
Human Health impacts have occasionally been reported by people living near wind turbine generators and
include: nausea/vertigo, headaches, dizziness, anxiety, tachycardia (rapid heart rate), tinnitus (ringing in
the ears), and sleep deprivation resulting in mood disorders and difficulty concentrating. These symptoms
are not experienced by all local residents, but have recently been reported by a small number of
individuals. A pre-construction desktop analysis of peer-reviewed literature discussing the impacts of
wind turbines to human health indicated that risks to human health are not anticipated to result directly
from properly-sited wind turbines. One recent literature review states: "To date, no peer reviewed articles
demonstrate a direct causal link between people living in proximity to modern wind turbines, the noise
they emit and resulting physiological health effects. If anything, reported health effects are likely
attributed to a number of environmental stressors that result in an annoyed/stressed state in a segment of
the population" (Knopper and Ollson, 2011). The Wind Farm Collie Hill project has been designed in
accordance with all applicable Ontario regulations and as such is not expected to cause impacts to human
health. Further details related to the potential for human health risks are included in the Design and
Operations Report.
Electro-Magnetic Radiation and extremely low frequency electric fields will be generated by the
distribution lines, transformer station, and generators at the Project. As the strength of these fields is
similar to that resulting from existing infrastructure, and decrease quickly with distance, no significant
ELF fields are expected to impact nearby land users.
Further details pertaining to project-related impacts and mitigation measures are included in the Design
and Operations Report as part of the final REA submission.
Wind Farm Collie Hill DRAFT Project Description Report
M.K. Ince and Associates Ltd. 14 November 16, 2012
3.4 Water Bodies and Groundwater
As part of the REA process, identification and assessment of water bodies in or within 120 m of the
project location was undertaken through a records review and site investigations. This assessment
identified two seeps within 120 m of the project location.
Potential project-related impacts to soil and groundwater include the following.
Spills and leaks of petroleum, oil and lubricants may result in their accidental and uncontrolled release,
which would lead to adverse effects on terrestrial habitat and species, soil, groundwater quality and
human health and safety. However, the implementation of appropriate mitigation and contingency
measures, which are fully described in the Design and Operations Report, are expected to minimize these
risks.
Impacts due to erosion and sedimentation from clearing, grading, excavating and potential soil and root
compaction during construction, major maintenance activities and decommissioning, may result in
changes to stormwater patterns. This may increase erosion and concomitant impacts to surface water in
the vicinity of the project location. The implementation of appropriate mitigation, monitoring and
contingency measures is expected to minimize these risks. These measures are described within the
Construction Plan Report and Design and Operations Report.
Impacts from products for snow removal may result from excessive salt or sand use which may cause
saline runoff that could impact local groundwater or contribute to sediment-laden runoff that may cause
blockages in drainage structures. With the implementation of appropriate mitigation measures (described
in the Design and Operations Report), these impacts are expected to be minimal.
Impacts from water takings may occur if de-watering is required in excavated areas. Water takings are
only anticipated in the event that rainfall accumulates in excavated areas and does not drain rapidly
enough for construction activities to continue in a timely manner. In these cases pumps will be used to
remove rainwater from the excavated areas. The water will be pumped from pits into the adjacent fields,
and will include filtration of silt as necessary. It is possible that more than 50,000 L/day of water will
need to be removed. No negative impacts are anticipated from the removal of the rainfall from excavated
areas as the excavated areas are well removed from existing water courses and surface water flows will
therefore not be impacted. De-watering is not anticipated to impact ground water as excavation is not
anticipated to reach the water table.
Further details pertaining to project-related impacts and mitigation measures are included in the Design
and Operations Report as part of the final REA submission.
3.5 Land Use
The land use in and adjacent to the project area is and has traditionally been agricultural. The Wind Farm
Collie Hill project location is primarily composed of fields used in the production of cash crops, such as
soy, corn, and wheat.
The Township of Asphodel-Norwood designates the Wind Farm Collie Hill project lands as ‘Restricted
Agricultural’ and ‘Rural.’ The operation of a wind energy facility is not anticipated to significantly impact
land use and resources in the project area.
Wind Farm Collie Hill DRAFT Project Description Report
M.K. Ince and Associates Ltd. 15 November 16, 2012
Potential impacts to current land use are discussed in greater detail in the Construction Plan Report and
Design and Operations Report which include the following considerations:
Traffic volume and size may be affected by construction traffic that may inconvenience local residents.
However, minimal impacts to provincial and local infrastructure are anticipated as increases to traffic
volume will be limited in extent and duration.
Impacts due to change of land use may result because project infrastructure will be located almost entirely
on agricultural areas, which will remove a limited amount of agricultural area from production. The
project turbines and related infrastructure have been sited to minimize disturbance to existing land use.
Thus, impact due to change of land use are anticipated to be minimal.
Waste, if improperly disposed of can be unsightly and cause human safety and health concerns and has
the potential to contaminate soils, surface- and groundwater if the waste is toxic. Mitigation and
contingency measures have been prepared to ensure that waste from the facility is managed such that the
potential for adverse impacts is reduced. These are further detailed in the Construction Plan Report,
Design and Operations Report, and Decommissioning Plan Report.
Telecommunications may be impacted by the tower and blades of wind turbines. A pre-construction
assessment of these impacts has been undertaken as per RABC/CanWEA Guidelines. Minor impacts to
over-the-air television broadcast reception are possible, and will be mitigated on a case-by-case basis. No
other impacts to communications infrastructure are anticipated.
Visual landscapes in the local area will be impacted, as the wind farm will be a highly visible feature from
some vantage points. All three turbines will be lit, in response to a request from the Department of
National Defense, however the lighting will be synchronized in order to minimize light pollution at night.
The Wind Farm Collie Hill project is not anticipated to have significant negative residual impacts on land
use and resources in the project area. Details regarding appropriate mitigation measures are provided in
the Design and Operations Report.
3.6 Birds
Mortality surveys at wind facilities in North America suggest that bird mortality is occurring as a result of
interactions with turbines. A review of post-construction monitoring studies at 46 wind farms across the
United States found that most wind farms reported fewer than 4 bird fatalities per megawatt per year
(NWCC, 2010). Most fatalities noted occurred during bird migration periods though were highly varied
regionally (NWCC, 2010). Mortality data from the MNR suggests that operational wind farms in Ontario
average roughly 2.5 bird deaths per turbine per year (OMNR, 2011b). A full description of monitoring
plans and mitigation measures is provided in the Environmental Effects Monitoring Plan contained in the
Design and Operations Report.
Disturbance during the construction and decommissioning phases due to the presence of humans and
machinery and the associated noise will likely cause birds to avoid areas under construction. Breeding
behaviour has the potential to be impacted. Although it is expected that many resident birds will become
habituated to the wind turbines, there may be some behavioural impacts during operation. Avoidance of
the wind farm may result in habitat fragmentation for some species.
Habitat loss during the construction phase due to the clearing of vegetated areas may occur. Breeding bird
habitat may be impacted, however clearing will be avoided during the breeding season (May to July). If
Wind Farm Collie Hill DRAFT Project Description Report
M.K. Ince and Associates Ltd. 16 November 16, 2012
any tree clearing is to be conducted during breeding season a biologist will search the area to be cleared
and if any active nests are found in the area they will be staked off and avoided until breeding activities
have ceased.
Pre-construction site investigations in the project study area conducted as part of the Natural Heritage
Assessment identified no significant bird habitat. The project study area, as it consists of already-
disturbed primarily agricultural lands with low value for bird species, is not sensitive habitat, nor is it a
major migration route for birds. Impacts of the wind farm on birds are thus expected to be low.
Impacts and mitigation measures including a post-construction monitoring program are fully described in
the Construction Plan Report and in relevant sections of the Design and Operations Report including the
Environmental Effects Monitoring Plan.
3.7 Bats
Mortality of bats as a result of direct collision or barotrauma is a potential negative impact of wind turbine
facilities as bats are less equipped to avoid turbine blades because their navigational systems depend on
echolocation, which detects objects in their flight path.
A review of post-construction monitoring studies at 46 wind farms across the United States found most
wind farms reported fewer than 10 bat fatalities per megawatt per year (NWCC, 2010). Most fatalities
occurred during bat migration periods, although this pattern showed high regional variability (NWCC,
2010). Data from the MNR suggests that operational wind farms in Ontario average roughly 4-14 bat
deaths, per year per turbine (OMNR, 2011a).
Disturbance to bats during the construction phase due to the presence of humans and machinery will
likely cause bats to avoid the areas under construction and thus has the potential to impact breeding
behaviour. For some species habitat fragmentation due to the presence of turbine and access roads may
impact behaviour.
Habitat loss during the construction phase due to the clearing of vegetated areas may occur. No
significant bat maternity roosts were identified during pre-construction surveys therefore minimal impacts
are anticipated. Cleared areas have been minimized to the extent possible.
Impacts and mitigation measures including a post-construction monitoring program are fully described in
the Construction Plan Report and in relevant sections of the Design and Operations Report including the
Environmental Effects Monitoring Plan.
3.8 Natural Heritage Features and Significant Wildlife
Pre-construction assessment of natural heritage features and significant wildlife involved records reviews
and site visits to ascertain the presence of natural heritage features on site. The results of the Natural
Heritage Assessment identified the following significant features in or within 120 m of the project
location:
• 3 wooded areas
• 1 wetland
• 2 amphibian breeding habitat
• 1 snake hibernacula
Wind Farm Collie Hill DRAFT Project Description Report
M.K. Ince and Associates Ltd. 17 November 16, 2012
• 1 seepage area
As a part of the NHA and REA processes, potential project impacts on significant natural heritage
features were identified and are summarized briefly below:
• Potential for contamination of soils from spills and leaks
• Potential for erosion and/or sedimentation
• Potential for disturbance of wildlife using wooded or seepage areas
• Potential for short term, localized dust generation during construction and decommissioning
activities
• Possible temporary disruption frogs or toads living in wooded areas or wetlands as a result of
construction activities
• Erosion may affect water quality in the wetland or ephemeral ponds which support breeding
populations of amphibians
• Snakes migrating from hibernacula during the spring emergence period or returning in the fall
may experience direct injury or mortality by construction vehicles operating in the area
The potential impacts to natural heritage features listed above are not expected to result in significant
residual impacts as mitigation measures and monitoring plans have been prepared as appropriate and are
detailed in the Natural Heritage Environmental Impact Assessment and the Environmental Effects
Monitoring Plan contained in the Design and Operations Report.
Wind Farm Collie Hill DRAFT Project Description Report
M.K. Ince and Associates Ltd. 18 November 16, 2012
4 CONCLUSION
The Wind Farm Collie Hill project, proposed by Wind Farm Collie Hill LP, will have a nameplate
capacity of 5.4 MW. The project infrastructure will consist of three REPower MM100 wind turbine
generators (or similarly appropriate technology) each of 1.8 MW capacity, as well as associated
infrastructure, including pad-mounted transformers, electrical cabling, access roads, an administration
area and a substation. The project will be constructed on privately-owned agricultural lands near the
community of Hastings in the Township of Asphodel-Norwood, a municipality of the County of
Peterborough. The Wind Farm Collie Hill project has received a Power Purchase Agreement under
Ontario’s Feed-In Tariff (FIT) program. This Class 4 wind energy project is subject to the Renewable
Energy Approval (REA) process per Ontario Regulation 359/09 under the Environmental Protection Act.
Environmental studies carried out under the REA process will ensure that the Wind Farm Collie Hill
project produces clean, emissions-free electricity while minimizing negative environmental effects.
Wind Farm Collie Hill DRAFT Project Description Report
M.K. Ince and Associates Ltd. 19 November 16, 2012
5 REFERENCES
Ministry of Natural Resources, 2011. Bat and Bat Habitats: Guidelines for Wind Power Projects.
http://www.mnr.gov.on.ca/stdprodconsume/groups/lr/@mnr/@renewable/documents/document/st
dprod_088155.pdf
Ministry of Natural Resources, 2011. Bird and Bird Habitats: Guidelines for Wind Power Projects.
http://www.mnr.gov.on.ca/stdprodconsume/groups/lr/@mnr/@renewable/documents/document/st
dprod_071273.pdf
Knopper, L., Ollson, C. (2011). Health effects and wind turbines: A review of the literature.
Environmental Health 10: 1-10.
National Wind Coordinating Collaborative (NWCC). Wind Turbine Interactions with Birds, Bats, and
their Habitats: A Summary of Research Results and Priority Questions Spring 2010.
http://www.nationalwind.org
Ontario Ministry of Environment (MOE). 2008. Noise Guidelines for Wind Farms: Interpretation for
Applying MOE NPC Publications to Wind Power Generation Facilities.
http://www.ene.gov.on.ca/publications/4709e.pdf Last retrieved May 28, 2010.
Renewable Energy Approvals Under Part V.0.1 of the Act, Ontario Regulation 359/09 made under the
Environmental Protection Act, R.S.O. 1990, Chapter E.19.
Township of Asphodel-Norwood. Official Plan 2008.
http://www.asphodelnorwood.com/documents/Official%20Plan.pdf