  • 7/27/2019 dr0_04072013

    1/9

    Maharashtra State Electricity TransmissionCompany Ltd.

    Daily system Report

    04/Jul/2013

    for

    State Load Dispatch Center,Airoli

    0 of 8

  • 7/27/2019 dr0_04072013

    2/9

    Daily system Report for 04/Jul/2013

    State Load Dispatch Center,Airoli (MSETCL)

    THURSDAY

    I GENERATION (MUs) II EXCHANGES (MUs)A) MSGENCO Daily Monthly

    1) Thermal

    3) Gas

    2) Hydro

    Total MSGENCO

    B) 1) JSW JAIGAD

    5) Wind Generation

    4) Other CPP / IPP

    C) TPCL & REL

    1) TPCL Thermal

    2) TPCL Hydro

    TOTAL TPCL3) REL Thermal

    D) STATE

    1) Thermal

    2) Hydro3) Gas4) Wind

    TOTAL STATE

    (A1+C1+C3)

    (A2+B5+C2)

    (A3)

    (B4)

    E) Central Sector Daily Monthly

    1) Gujrat

    2) Madhya Pradesh

    3) Chattisgarh

    4) Maharashtra

    8) Pench (Excess)

    # Total Cent. Sector

    F) Other Exchanges

    1) With TPCL (Excess)

    1) MSEDCL Bilateral

    H) ENERGY CATERED (MUs)

    1) MSEDCL

    2) TPCL

    3) REL

    TOTAL STATE

    DETAILS OF MAHARASHTRA STATE PEAK DEMAND(MW)

    MSGENCO Thermal

    MSGENCO Hydro

    MSGENCO Gas

    MSGENCO Total Generation

    Central Sector Receipt

    Exchange with Mumbai

    MSEDCL DEMAND MET

    MSEDCL DEMAND

    TPCL GENERATION

    R-INFRA GENERATION

    TPCL+R-INFRA DEMAND

    STATE DEMAND MET

    STATE DEMAND

    Frequency (Hz)

    FREQUENCY PARTICULARS

    MAXIMUM FREQ. MINIMUM FREQ. AVERAGE FREQ. FREQ. BELOW 49.2 Hz

    * Displayed for information, not added in total. # Total Cent. Sector includes MSEDCL and TPCL bilateral power.

    PARTICULARS

    72.217 322.643

    7.419 21.377

    10.305 42.144

    89.941 386.16420.503 65.949

    29.281 110.861

    4.697 32.591

    24.169 93.279

    4.886 20.012

    29.055 113.29111.950 45.841

    108.336 461.763

    12.647 42.591

    10.305 42.144

    29.281 110.861

    216.729 810.973

    13.532 37.917

    17.428 73.109

    3.460 26.720

    55.802 227.775

    -0.342 -1.202

    94.778 385.315

    -17.441 -71.103

    39.013 148.717

    253.061 1046.893

    38.455 151.063

    19.988 79.169

    311.504 1277.125

    3203

    A. Morning Peak at 11Hrs

    B. Evening Peak at 20Hrs

    C. Night Minimum at 5Hrs

    178

    428

    3809

    4555

    -1157

    11168

    11225

    1283

    526

    2966

    14134

    14191

    49.96 49.82 50.04

    50.36 Hz at 17.08 Hrs 49.64 Hz at 19.45 Hrs 50 0 % of Time(min)

    2827

    689

    3945

    429

    4969

    -707

    11398

    11469

    1475

    525

    2707

    14105

    14176

    3028

    77

    3554

    449

    2993

    -450

    9676

    9732

    841

    398

    1689

    11365

    11421

    Shift Engineer Shift Incharge

    G) Bilateral Power *

    Include PX -1.230 -2.0092) MUMBAI Bilateral 12.363 54.798

    Include PX 1.970 5.019

    3) MUMBAI Schedule 12.363 54.798

    WIND 1368 898 1272

    6) PENCH (MS) 0.342 1.202

    5) CPP 56.160 153.614(B1+B2+B3)

    CPP / IPP 2593 2267 2280

    Load Shedding 57 71 56

    5) Goa

    6) TAPS 1&2 Injection

    7) RGPPL Injection

    -5.166 -19.193

    3.713 14.812

    6.351 25.377

    2) WPCL 7.920 32.034

    3) ADANI 23.040 103.880

    1 of 8

  • 7/27/2019 dr0_04072013

    3/9

    Daily and Progressive Generation,Maximum,Minimum,OLC Details for 04/Jul/2013

    State Load Dispatch Center,Airoli (MSETCL)

    Generating

    unit

    Generation

    Daily

    (Mus)

    OLC

    (MW)Monthly

    (Mus)

    Max

    (MW)

    Min

    (MW)

    Koradi

    2.28 154 0 1302.28Unit 5

    3.17 150 100 11012.48Unit 6

    0.00 0 0 00.00Unit 7

    5.44 14.77Total 240Bhusawal

    3.10 145 100 16014.16Unit 2

    2.84 140 95 16013.98Unit 3

    5.30 335 0 21517.38Unit 4

    0.00 0 012.40Unit 5

    11.24 57.92Total 535

    Parli

    0.00 0 00.00Unit 3

    0.00 0 00.00Unit 4

    0.00 0 00.00Unit 5

    0.00 0 00.00Unit 6

    0.00 0 00.00Unit 7

    0.00 0.00Total

    Chandrapur

    3.37 147 128 16013.37Unit 1

    3.32 147 130 15013.98Unit 2

    0.00 0 0 08.81Unit 3

    0.00 0 0 00.00Unit 4

    4.36 200 155 20020.28Unit 5

    3.38 184 115 15016.62Unit 6

    5.07 240 185 20022.35Unit 7

    19.50 95.40Total 860

    Paras4.06 193 153 16016.03Unit 3

    4.13 190 150 17016.88Unit 4

    8.18 32.91Total 330

    Khaparkheda

    2.28 110 65 1209.42Unit 1

    0.00 0 0 06.80Unit 2

    3.36 154 125 1509.27Unit 3

    3.38 155 130 14016.46Unit 4

    6.38 290 240 30029.77Unit 5

    15.39 71.72Total 710

    Nasik4.18 190 170 19516.72Unit 3

    4.17 181 170 18016.57Unit 4

    4.11 192 162 19516.65Unit 5

    12.46 49.93Total 570

    Uran

    10.30 450 233 43042.14All Units

    10.30 42.14Total 430

    PENCH (MS)

    0.34 27 01.20Pench (MS)

    0.34 1.20Total

    Koyna

    1.98 440 40 5206.42Stage 1-2

    1.56 443 0 2501.70Stage 4

    1.47 160 0 2405.12Stage 3

    Generating

    unit

    Generation

    Daily

    (Mus)

    OLC

    (MW)Monthly

    (Mus)

    Max

    (MW)

    Min

    (MW)

    5.00 13.24Total 1010

    Hydro

    0.00 0 0 00.00KDPH

    0.00 0 0 610.56VTRNA

    0.00 0 0 600.60TILLARI0.00 0 00.00BHTGR/VEER

    0.51 81 0 801.92BHIRA T.R.

    0.05 2 20.05RNGR+BHTSA

    0.28 34 00.29BHANDARDRA

    0.00 0 00.00ELDARY

    0.24 10 10 00.97SMLHY_PTN

    1.35 250 03.76GHATGHAR

    2.42 8.14Total 201

    Wind

    2.06 5.55MalharPeth

    2.71 8.55Vankuswadi

    1.38 2.22ATIT

    0.76 3.04Kale

    2.60 27.26Satara

    1.37 3.31Shirala

    1.60 1.96K Mahankal

    0.53 1.43Supa

    4.29 14.57Vita

    6.82 26.87Dondaicha

    1.41 4.45Sakri

    0.70 2.66Nandurbar

    1.66 4.71Khandke

    1.40 4.30Khaparale29.28 110.86Total

    CPP

    20.50 927 781 79065.95JSW_JAIGAD

    7.92 376 244 34532.03WARDHA

    23.04 1220 550 1234103.88Adani

    4.70 032.59Other_CPPs

    56.16 234.45Total 2369

    Tata

    0.00 0 0 00.00Trombay 4

    10.35 502 318 50039.04Trombay 5

    3.71 202 147 50014.41Trombay 62.90 123 114 12011.67Trombay 7A

    1.61 68 65 606.47Trombay 7B

    5.59 253 188 25021.68Trombay 8

    4.89 387 0 44720.01TATA Hydro

    29.06 113.29Total 1877

    REL

    11.95 526 398 50045.841&2

    11.95 45.84Total 500

    Cent_Sect

    4793Share

    Total 4793

    72.22 322.64 3245

    7.42 21.38 1211

    State Total 216.73 810.97 14425Total

    Hydro

    Thermal

    89.94 386.16 4886

    MSPGCL

    Thml+Gas 82.52 364.79 36753.53 8.12 770Koyna 12&4 Total

    2 of 8

  • 7/27/2019 dr0_04072013

    4/9

    State Load Dispatch Center,Airoli (MSETCL)

    Hourly Load Data As on 04/Jul/2013

    THM HY GAS

    TOTALCS

    SHARECS

    RECPTMum.S

    CH.

    Mum.NET

    EXCH.

    MSEDCLDEMAND

    MET

    LOADSHEDDI

    NG

    MSEDCLDEMANDWITH LS

    TPCL + R-INFRA

    DEMAND

    STATEDEMAND

    FREQ.(Hz)

    MSPGCL GEN.TIMESR.NO.

    WINDCPP /IPP

    1 2981 91 441 3513 3445 3354 50.042025102598810171-683-405 122841586 2375

    2 2946 86 444 3476 3268 3092 49.9418489971569915-610-385 118191539 2392

    3 3021 86 446 3553 3229 2876 50.0017649908569852-531-376 116721575 2353

    4 3017 65 446 3528 3203 2900 50.1816999850569794-468-361 115491510 2298

    5 3028 77 449 3554 2844 2993 50.0416899732569676-450-355 114211272 2280

    6 3038 156 450 3644 3324 3323 49.991779104035610347-483-369 121821327 2509

    7 2992 140 447 3579 3755 3875 50.021911109905610934-585-432 129011399 2640

    8 3096 153 449 3698 4129 3902 50.052075111035611047-546-432 131781340 2640

    9 3110 170 444 3724 4137 3923 50.052394110945611038-542-432 134881294 2639

    10 3144 183 429 3756 4405 4221 49.922723109825610926-873-524 137051175 2647

    11 3203 178 428 3809 4778 4555 49.962966112255711168-1157-768 141911368 2593

    12 3029 101 427 3557 4673 4578 49.963018105985710541-1073-807 136161190 2289

    13 3049 92 432 3573 4397 4353 49.9429831044811710331-1079-761 134311264 2220

    14 2978 168 435 3581 4158 4262 50.062873103236110262-932-536 131961100 2251

    15 2995 318 428 3741 4467 4000 50.032912103996110338-903-658 133111257 2243

    16 3039 194 432 3665 4458 4145 50.042909104516110390-902-657 133601261 2221

    17 3086 166 436 3688 4256 3813 50.112888102236110162-881-610 131111213 2329

    18 2967 173 436 3576 3578 3493 50.15283410013619952-854-444 128471211 2509

    19 2790 186 438 3414 3830 3979 50.032714104326110371-713-468 131461226 2454

    20 2827 689 429 3945 4525 4969 49.822707114697111398-707-508 1417689 8 2 26 7

    21 2820 1349 433 4602 4479 4581 49.8726121153410511429-608-525 1414680 2 2 02 8

    22 2998 1048 435 4481 4610 4639 49.932502114688011388-581-538 1397083 9 1 98 6

    23 2995 823 438 4256 4419 4447 49.892378109866310923-606-529 1336480 9 1 99 4

    24 3068 727 233 4028 4342 4505 49.942243107706210708-674-484 1301382 6 2 00 3

    72.22MUs 7.42 10.30 89.94 96.71 94.78 -12.36 -17.44 253.06 1.57 254.63 58.45 313.08 50.00

    NOTE : ALL VALUES IN MWMumbai Sch./Net Exch is shown with reference to MSETCL System. (+) indicates Mum. to MSETCL and (-) indicatesMSETCL to Mum. Mumbai Schedule is calculated for MSETCL periphery (taking 4% loss for import & 4.85% MSETCL loss

    29.28

    # Without Applying Load Diversity Factor

    56.16

    3 of 8

  • 7/27/2019 dr0_04072013

    5/9

    State Load Dispatch Center,Airoli (MSETCL)

    Details of Generating Unit Outages/Trippings for 04/Jul/2013Position as on 6.30 Hrs of 05/Jul/2013

    Name of Generating

    Unit

    Tripped

    Date

    Trippe

    d TimeSync.Date

    Sync.

    TimeReason of OutageCapacity

    Expected

    Date

    PLANNED OUTAGE

    Parli Unit 4 28/11/2012 02.37 Continued. water shortage.210

    Cent_Sect Tarapur 2 31/12/2012 17.05 Continued. Refuelling work160

    Parli Unit 625/01/2013 19.49 Continued.

    Water Shortage/AOH from

    06.03.2013250

    Parli Unit 3 13/02/2013 23.50 Continued. Water Shortage210

    Parli Unit 5 14/02/2013 22.45 Continued. Water Shortage210

    Parli Unit 7 17/02/2013 01.00 Continued. Water Shortage.250

    Chandrapur Unit 4 15/06/2013 13.33 Continued. Annual Overhaul210

    Koyna Unit 5 01/07/2013 07.35 Continued. Maint.Work.80FORCED OUTAGE

    CPP Adani U-2 22/04/2013 13.47 Continued. ID fan problem.660

    Dabhol 3B 28/05/2013 21.58 Continued. Gas shortage.230

    Dabhol 1B 28/05/2013 22.02 Continued. Gas shortage.230

    Koyna Unit 11 04/06/2013 13.25 Continued. Rotar Fault.80

    Dabhol 3A 06/06/2013 08.28 Continued. Gas Shortage230

    Dabhol 3X 06/06/2013 08.28 Continued. Gas Shortage290

    Dabhol 2A 06/06/2013 09.10 Continued. Gas Shortage230

    CPP WPCL U-4 12/06/2013 03.27 Continued. Turbine Balancing.135

    Uran Unit 8 21/06/2013 10.15 Continued. Gas Shortage.108

    Dabhol 1X 27/06/2013 21.46 Continued. Gas Shortage290

    Dabhol 1A 27/06/2013 21.47 Continued. Gas Shortage230

    Koradi Unit 730/06/2013 09.42 Continued.

    GC-2 Heavy Gland Flag

    Leakage.210

    Khaparkheda Unit 2 02/07/2013 23.43 05/07/2013 05.21 Boiler Vailidity Extention.210

    Chandrapur Unit 3 03/07/2013 10.50 Continued. Boiler Tube Leakage.210

    CPP VIPL 03/07/2013 12.29 Continued. CHP Problem.300

    Bhusawal Unit 5 03/07/2013 23.40 Continued. ESP Problem.500

    Koradi Unit 5 04/07/2013 11.05 04/07/2013 15.08 Low Vaccum.200

    Bhusawal Unit 4 04/07/2013 17.42 04/07/2013 20.43 Bus Fault.500

    CPP Adani U1 04/07/2013 20.11 Continued. BOILER TUBE LEAKAGE660

    Uran Unit 6 04/07/2013 23.11 Continued. Turbine Trip.108

    Uran Unit 5 05/07/2013 00.30 Continued. Turbine Trip.108

    Bhusawal Unit 4 05/07/2013 00.50 05/07/2013 02.40 Drum Level High.500

    4 of 8

  • 7/27/2019 dr0_04072013

    6/9

    Details of Line outages/Trippings for 04/Jul/2013

    State Load Dispatch Center,Airoli (MSETCL)

    Position as on 6.30 Hrs of 05/Jul/2013

    Name of LineTripped

    Date

    Tripped

    Time

    Synchronise

    d Date

    Synchronise

    d TimeReason of Outage

    InterState

    400KVVoltage Level : PLANNED OUTAGEOutage Type

    Lamboti - Solapur (PGCIL) 03/07/2013 09.30 04/07/2013 06.12 Replacement of R Ph CVT.(RFC)400KVVoltage Level : HAND TRIPPEDOutage Type

    Kolhapur - Mapusa - I 06/06/2013 16.44 Continued. Over Voltage

    Chandrapur-Bhadravti - I 09/06/2013 16.16 Continued. Over Voltage

    Kolhapur-Solapur (PG) II 13/06/2013 17.07 Continued. Over Voltage.

    Seoni-Wardha-II 765KV. 14/06/2013 10.54 Continued. Over Voltage

    Solapur PG - Parly PG - I 01/07/2013 17.10 Continued. Over Voltage.

    Dhule-Sar'Sarovar - II 03/07/2013 21.06 04/07/2013 19.32 Over Voltage.

    Akola - Wardha - II 04/07/2013 03.20 04/07/2013 05.53 Over Voltage.

    Warora - Tiroda - II 04/07/2013 19.44 Continued. Over Voltage.( One Unit on Bar)

    400KVVoltage Level : TRIPPEDOutage Type

    Koradi-Satpur 14/06/2013 02.02 Continued. Over Voltage.

    Akola - Aurangabad- II 03/07/2013 14.51 Continued.Bus Bar Protection

    Operated.(Opportunity Outage)

    Koradi-Bhilai 03/07/2013 21.40 04/07/2013 13.17 Over Voltage.

    Akola - Wardha - I 04/07/2013 13.06 04/07/2013 20.01 Over Voltage.

    Akola - Aurangabad - I 04/07/2013 16.00 05/07/2013 07.21Bus Bar Protection Operated @

    Aurangabad Main Bus - II.

    Solapur - Solapur (PG) 04/07/2013 18.36 05/07/2013 06.45 Over Voltage.

    Akola - Wardha - I 05/07/2013 02.21 05/07/2013 05.49 Over Voltage.

    Akola - Wardha - II 05/07/2013 02.21 Continued. Over Voltage.

    IntraState

    400KVVoltage Level : PLANNED OUTAGEOutage Type

    400/220 KV 500 MVA ICT-

    I @ Deepnagar07/06/2013 17.03 Continued.

    ICT charged through Tie Bay due to

    higher Tan Delta Values of HV side R

    Phase Bus-II CT

    Bus - I @ Lonikand 04/07/2013 10.25 04/07/2013 19.45 Conductor Repair Work.

    400/220 KV 500 MVA ICT

    - I @ Solapur04/07/2013 11.26 05/07/2013 06.07 Replacement of Y Ph.CVT.

    Bus - I @ Lamboti 04/07/2013 11.26 05/07/2013 06.07 Replacement of Y Ph.CVT.

    400/220 KV 315 MVA ICT- I @ Aurangabad

    04/07/2013 18.24 04/07/2013 18.26 For Bus Arrangement.

    220KVVoltage Level : PLANNED OUTAGEOutage Type

    Main CB of 220/100kV 200

    MVA ICTIII @ Padgha22/05/2013 10.46 Continued.

    Repl.of A bus,B bus isolator under

    JICA scheme.ICT on TBC.

    Wadkhal - NDIL - I 04/07/2013 10.03 04/07/2013 16.32 Pilot Wire Replacement Work.

    Vankushwadi - MIDC

    Satara.04/07/2013 10.43 04/07/2013 14.15 Due to Outage on Bus @ Vankuswadi.

    Vankuswade-Malharpeth 04/07/2013 10.47 04/07/2013 14.12 Due to Outage on Bus @ Vankuswadi.

    Main Bus @ Vankushwadi 04/07/2013 10.47 04/07/2013 14.00 Replacement of Insulator String.

    Bhugaon-Pusad 04/07/2013 11.06 04/07/2013 15.19 Repl.of Defective R Ph.Insulator String.

    Lonand - SonaAlloys 04/07/2013 13.55 04/07/2013 19.37 Scada Work @ Sonaalloy S/S.

    220KVVoltage Level : FORCED OUTAGEOutage Type

    Wardha Power -Warora -II 04/07/2013 00.22 04/07/2013 02.20To Attend Hot Spot on B Ph.Wave

    Trap.

    Jejuri-Phursungi - I 04/07/2013 15.42 04/07/2013 15.49 To Remove Crow Nest from W/T.

    5 of 8

  • 7/27/2019 dr0_04072013

    7/9

    Details of Line outages/Trippings for 04/Jul/2013

    State Load Dispatch Center,Airoli (MSETCL)

    Position as on 6.30 Hrs of 05/Jul/2013

    Name of LineTripped

    Date

    Tripped

    Time

    Synchronise

    d Date

    Synchronise

    d TimeReason of Outage

    400KVVoltage Level : HAND TRIPPEDOutage Type

    400/220 KV 100 MVA

    Spare Unit @ Koradi12/07/2012 07.11 Continued. Main Buchholz prot.operated

    400/220 KV 105 MVA

    Spare ICT Unit @

    Bhusawal - II

    02/02/2013 10.17 Continued. Low Oil Pressure Alarm Received.

    Dabhol - Nagothane - I 06/06/2013 21.21 Continued. Over Voltage

    Karad - Newkoyna - I 23/06/2013 16.36 Continued. Over Voltage

    Dabhol - New Koyna - I 30/06/2013 10.42 Continued. Over Voltage.

    Karad - Kolhapur - II 02/07/2013 21.23 Continued. Over Voltage.

    Deepnagar-Aurangabad-I 03/07/2013 16.53 04/07/2013 18.18 Over Voltage.

    Karad - Kolhapur - I 03/07/2013 20.53 04/07/2013 08.52 Over Voltage.

    Lonikand- Koyna Stage IV 04/07/2013 00.19 Continued. Over Voltage.

    Deepnagar-Aurangabad-I 04/07/2013 18.51 Continued. Over Voltage.

    220KVVoltage Level : HAND TRIPPEDOutage Type

    Kalwa-Mulund-I 04/07/2013 12.07 Continued.Sparking @ Y Ph Jumper Between

    Bus & Isolator @ Mulund S/S.

    400KVVoltage Level : TRIPPEDOutage Type

    400/11.5KV 90 MVA STN

    T/F III @ 400KV C'PUR25/09/2012 15.38 Continued.

    Differential protection operated

    Declared Faulty by Genco.

    Koradi - II - Indiabull 03/07/2013 04.04 04/07/2013 09.10 Over Voltage.

    Chandrapur - Parli - III 03/07/2013 21.40 04/07/2013 09.45 Over Voltage.

    Koradi - New Koradi 03/07/2013 21.40 04/07/2013 08.58 Over Voltage.

    Akola - Indiabull(Nandgaonpeth)

    04/07/2013 02.40 04/07/2013 06.26 Over Voltage.

    Koradi-Khaparkheda-I 04/07/2013 12.22 04/07/2013 14.57 Over Voltage.

    Koradi - New Koradi 04/07/2013 13.06 04/07/2013 17.55 Over Voltage.

    Koradi - II - Indiabull 04/07/2013 13.06 04/07/2013 19.25 Over Voltage.

    Akola - Indiabull

    (Nandgaonpeth)04/07/2013 13.06 Continued. Over Voltage.

    Bableshwar-Aurangabad 04/07/2013 16.00 04/07/2013 18.13Bus Bar Protection Operated @

    Aurangabad Main Bus - II.

    400/220KV 315MVA ICT-II

    @ Aurangabad.04/07/2013 16.00 04/07/2013 18.17

    Bus Bar Protection Operated @

    Aurangabad Main Bus - II.

    400/220 KV 315 MVA ICT- I @ Aurangabad

    04/07/2013 16.00 04/07/2013 16.51Bus Bar Protection Operated @Aurangabad Main Bus - II.

    Aurangabad-Deepnagar-II 04/07/2013 16.00 04/07/2013 16.47Bus Bar Protection Operated @

    Aurangabad Main Bus - II.

    Main Bus- II @

    Aurangabad04/07/2013 16.00 04/07/2013 17.39

    Bus Bar Protection Operated @

    Aurangabad Main Bus - II.

    Dhule - Babhaleshwar - I 04/07/2013 16.16 04/07/2013 16.52 Over Voltage.

    Deepnagar-Aurangabad-II 04/07/2013 17.42 04/07/2013 18.50Bus Bar Protection Operated While

    Taking Spare ICT in Service.

    Bus - II @ Deepnagar 04/07/2013 17.42 04/07/2013 18.18Bus Bar Protection Operated While

    Taking Spare ICT in Service.

    400/220 KV,500MVA ICT-II at Deepnagar. 04/07/2013 17.42 04/07/2013 18.26 Bus Bar Protection Operated WhileTaking Spare ICT in Service.

    Dhule - Babhaleshwar - I 04/07/2013 23.50 05/07/2013 02.21 Over Voltage.

    Koradi - II - Indiabull 05/07/2013 01.14 05/07/2013 06.43 Over Voltage.

    Akola - Bhusawal 05/07/2013 02.21 Continued. Over Voltage.

    220KVVoltage Level : TRIPPEDOutage Type

    6 of 8

  • 7/27/2019 dr0_04072013

    8/9

    Details of Line outages/Trippings for 04/Jul/2013

    State Load Dispatch Center,Airoli (MSETCL)

    Position as on 6.30 Hrs of 05/Jul/2013

    Name of LineTripped

    Date

    Tripped

    Time

    Synchronise

    d Date

    Synchronise

    d TimeReason of Outage

    220/100 KV,200MVA ICT -

    I at Padgha07/06/2013 17.48 Continued. Diff.Protection

    220/132 KV 100 MVA T/F

    - I @ Valve 04/07/2013 04.49 04/07/2013 07.15 Diff. Protection.220/132 KV 100 MVA T/F

    - II @ Valve04/07/2013 04.49 04/07/2013 09.56 Diff. Protection.

    Aurangabad-Jalna-I 04/07/2013 16.47 04/07/2013 16.54 Load Trimming Operated.

    Aurangabad-Jalna-II 04/07/2013 16.47 04/07/2013 16.54 Load Trimming Operated.

    132KVVoltage Level : TRIPPEDOutage Type

    Nandurbar-Visarwadi 04/07/2013 03.35 04/07/2013 10.20 Distance Protection Z-I R Ph.

    7 of 8

  • 7/27/2019 dr0_04072013

    9/9

    Details of On Line Capacity for 05/Jul/2013

    State Load Dispatch Center,Airoli (MSETCL)

    Generating unitDerated Capacity

    (MW)OLC (MW)

    Koradi

    200 150Unit 5

    210 145Unit 6

    210 0Unit 7

    620 295

    Bhusawal

    210 130Unit 2

    210 130Unit 3

    500 210Unit 4

    500 0Unit 5

    1420 470

    Parli

    210 0Unit 3

    210 0Unit 4

    210 0Unit 5

    250 0Unit 6

    250 0Unit 71130 0

    Chandrapur

    210 160Unit 1

    210 150Unit 2

    210 0Unit 3

    210 0Unit 4

    500 200Unit 5

    500 200Unit 6

    500 250Unit 7

    2340 960

    Paras

    250 200Unit 3

    250 200Unit 4

    500 400

    Khaparkheda

    210 160Unit 1

    210 0Unit 2

    210 170Unit 3

    210 170Unit 4

    500 350Unit 5

    1340 850

    Nasik

    210 195Unit 3210 180Unit 4

    210 195Unit 5

    630 570

    Uran

    852 350All Units

    852 350

    PENCH (MS)

    53Pench (MS)

    53

    Koyna

    600 520Stage 1-2

    1000 250Stage 4

    320 240Stage 3

    1920 1010

    Hydro

    40 0KDPH

    60 61VTRNA

    Generating unitDerated Capacity

    (MW)OLC (MW)

    60 60TILLARI

    21 0BHTGR/VEER

    80 80BHIRA T.R.

    20 0RNGR+BHTSA

    45 0BHANDARDRA23 0ELDARY

    12 0SMLHY_PTN

    250 0GHATGHAR

    611 201

    Wind

    0MalharPeth

    0Vankuswadi

    0ATIT

    0Kale

    0Satara

    0Shirala

    0K Mahankal

    0Supa

    0Vita

    0Dondaicha

    0Sakri

    0Nandurbar

    0Khandke

    0Khaparale

    0

    CPP

    1200 900JSW_JAIGAD

    405 340WARDHA1320 617Adani

    300Other_CPPs

    3225 1857

    Tata

    150 0Trombay 4

    500 500Trombay 5

    500 500Trombay 6

    120 120Trombay 7A

    60 60Trombay 7B

    250 250Trombay 8

    444 447TATA Hydro

    2024 1877REL

    500 5001&2

    500 500

    Cent_Sect

    3455 4525Share

    3455 4525