Upload
vuongkiet
View
217
Download
2
Embed Size (px)
Citation preview
Robert Edwards, ManagerDepartment of Energy
Portsmouth/Paducah Project OfficeNovember 18, 2016
DOE Environmental Management On-site Waste Disposal
2016 Intergovernmental Meeting
www.energy.gov/EM 2
Environmental Cleanup–a Key DOE Strategic Goal
• EM supports DOE’s Strategic Plan to
position the Department to meet the
challenges of the 21st century and
the nation’s Manhattan Project and
Cold War legacy responsibilities.
• Goal is to reduce the environmental
liability associated with the EM
program (third largest US government
financial liability).
• Waste Management is a key element
in achieving success.
www.energy.gov/EM 3
DOE EM Waste Management Approach
Management strategy set through
Waste Management Programmatic EIS
• Treatment
All sites conduct minimal
treatment/packaging
• Storage
All sites store on-site pending disposal
• Disposal
SRS, Oak Ridge, Idaho, Hanford, NNSS,
and LANL may dispose LLW on-site at
existing landfills
All sites may dispose LLW at commercial
facilities if cost effective
• Remediation/D&D LLW may be
similarly disposed
www.energy.gov/EM 4
Waste Management Planning - Large Sites
WashingtonHanford
Richland Operations OfficeOffice of River Protection
New MexicoLos Alamos
IdahoIdaho National Laboratory
MissouriWeldon Springs
KentuckyPaducah
South Carolina Savannah River
Tennessee Oak Ridge
OhioFernaldPortsmouth
In 1999, the major cleanup site estimates indicated approximately 50
million cubic meters of environmental media and demolition debris
needed to be addressed.
www.energy.gov/EM 5
DOE EM Waste Management Alternatives
Off-site alternative
Make a site-wide decision to ship
waste that does not meet existing
landfill disposal criteria to licensed
off-site disposal facilities
On-site alternative
• Design, build, and operate
on-site waste disposal
facility
• May continue to dispose of
waste that meets existing
landfill requirements.
• Ship waste not meeting on-site
disposal criteria to licensed off-
site disposal facilities
No-action alternative
Continue making decisions project-
by-project
Offsite shipping routes (representative)
www.energy.gov/EM 6
Alternative Considerations
On-site Alternative Considerations
• Depth to groundwater
• Distance to residential property,
floodplains, streams, and DOE
property boundary
• Expandability (aesthetics)
• Terrain stability
• Impacts to NEPA
considerations (e.g., wetlands,
threatened or endangered
species, etc.)
Off-site Alternative Considerations
• Transportation risk
• Waste packaging
• State equity
• Cost
• Uncertainty in future disposal
capacity
• Uncertainty in future disposal
waste acceptance
www.energy.gov/EM 77
CERCLA Decision Process
Public comment
period (45 days)
Public meeting will
be held
Provide a
Responsiveness
Summary to
comments received
during the public
comment period
Ongoing project
briefings with
SSAB/CAB,
community leaders,
and other
interested parties
CERCLA Process
Regulatory
concurrence
Public Participation
RI/FS
Report*
Description of and
rationale supporting
the recommended
alternative
Regulatory
concurrence
Proposed
Plan
Public comment
period (45 days)
Public meeting will
be held
Formal Public
Participation
Final decision
document
Record of Decision
(ROD)
Plan for enhanced
public participation
www.energy.gov/EM 8
DOE EM Onsite Waste Disposal
Fernald
Los Alamos National LaboratoryTechnical Area 54, Area G
Portsmouth
Paducah
Idaho National LaboratoryIdaho CERCLA Disposal Facility
RWMC LLW Disposal Facility
Idaho Tank Farm Facility
Remote-Handled LLW Facility
Hanford Site200 West Burial Grounds
200 East Burial Grounds
Integrated Disposal Facility
ERDF
18 Tank Farms
Savannah River SiteE Area LLW Facility
Saltstone Disposal Facility
F Area Tank Farm
H Area Tank Farm
Nevada National Security SiteArea 5 Rad Waste Management
Area 3 Rad Waste Management
Oak RidgeEM Waste Management Facility
EM Disposal Facility (expansion cell)
SWSA 6
Existing CERCLA Disposal Facility
LLW Operations Disposal Facility
Closed Disposal FacilityFuture CERCLA Disposal Facility/Decision
Future LLW Disposal Facility
Disposal Facilities
Weldon Springs
www.energy.gov/EM 9
Weldon Spring Site
• Construction groundbreaking for on-site cell occurred April 24, 1997.
• The disposal cell contains approximately 1.48 million cubic yards of waste.
• Final placement of waste in the disposal cell took place on June 3, 2001.
• Transferred to Office of Legacy Management in 2003; now part of Weldon Spring
Interpretive Center.
www.energy.gov/EM 10
Hanford Environmental Restoration Disposal Facility – ERDF
• Disposal construction completed; operations began in 1996
• Operating facility covering 107 acres.
• 18 million tons of contaminated soil, debris and solid wastes from
cleanup activities at the Hanford site have been placed in the
disposal facility.
www.energy.gov/EM 11
2006
• Operations began in the first of
eight cells in 1997.
• Excavated and dispositioned
over 2.95 million cubic yards of
contaminated soil and debris
• The final cap of cell 8 was
installed in 2006
• The site transferred to the Office
of Legacy Management in 2006
• Site renamed Fernald Reserve
in 2007
Fernald On-Site Disposal Facility (OSDF)
www.energy.gov/EM 12
Idaho CERCLA Disposal Facility (ICDF)
• Idaho Cleanup Project is one of Idaho’s three site missions
• Construction of the first landfill cell began in 2001; placement of waste began in
September 2003
• Operations continue with a capacity of 510,000 cubic yards of waste
www.energy.gov/EM 13
Oak Ridge Environmental Management Waste Management Facility (EMWMF)
• Operations began in 2002
• Capacity of 2.2M cubic yards is approximately 70% full
• Cleanup of the K-25 site anticipated to be complete in 2020
www.energy.gov/EM 14
Site Activities
• Surveillance and Maintenance
Routine
Operational
• CERCLA Five-Year Reviews
• Site-Specific Working Groups
Share Lessons Learned
Independent Technical Reviews
• Stakeholder and Public Outreach
Public Meetings
SSAB/CAB meetings
Site Specific meetings
www.energy.gov/EM 15
Low Level Waste Disposal Facility Federal Review Group (LFRG)
• LFRG: Internal regulatory oversight group for Low-Level Waste
(LLW), including CERCLA disposal facilities to protect long-term
environmental and public impact
LFRG reports directly to EM senior management
Membership:
Co-Chairs from EM 4.31 and EM 4.2
DOE-HQ Organizations – EM, AU, NNSA, NE, SC
DOE Sites – ID, EM-LA, NSO, ORO, ORP, PPPO, RL, SRS
• Currently there are 13 disposal facilities (LLW & CERCLA)
All facilities require a Performance Assessment (PA) and Composite
Analysis (CA)
All 13 disposal sites require Disposal Authorization Statements (DAS)
All documentation required to be updated and revised periodically
www.energy.gov/EM 16
DOE Office of Legacy Management
• Monitoring and Oversight
continue after DOE EM’s
mission is complete
• Sites transfer to Office of
Legacy Management
• Post-closure responsibilities of
LM maintain oversight of
onsite waste disposal facilities Regulatory monitoring
requirements continue
Public outreach and
information continues
www.energy.gov/EM 17
Onsite Waste Disposal Benefit
• Over lifecycle, provides cost savings in contrast to off-site disposal
• Accelerates cleanup by allowing more funds to be directed to cleanup
• Reduces program risk by allowing control of waste disposal availability, increasing success rate for sequencing strategies and project execution
• Reduces transportation risk and eliminates associated carbon emissions
www.energy.gov/EM 18
Current Decisions – Portsmouth OSWDF
• A Record of Decision was signed in 2015 between DOE and Ohio EPA for the construction of the On-site Waste Disposal Facility to support cleanup efforts at the Portsmouth Gaseous Diffusion Plant
• Construction efforts began in 2016, clearing 300 acres, installing a 3,000’ raw water line, a 10,000’ fence and ancillary facilities
www.energy.gov/EM 19
Current Decisions – Oak Ridge EMDF
• A new onsite disposal facility is currently
being planned in Oak Ridge to support
future cleanup work at Y-12 and ORNL
• The new facility is estimated to be
roughly 2.2M cy in capacity and be
located in Bear Creek Valley, not far
from the existing EMWMF
• The project is currently near the end of
the RI/FS phase
• The FFA parties have reached a tentative
agreement on a path forward; Proposed
Plan anticipated in spring/summer 2017
www.energy.gov/EM 20
Current Decisions – Paducah OSWDF
• Place On-Site Waste Disposal
Facility Decision and potential
construction on hold for 10 years –
re-appropriate current funds for the
C-400 investigation
• Continue Lifecycle baseline
planning to fully integrate
sequencing remedial actions and
D&D of PGDP
• Delay burial grounds actions until
after the potential OSWDF is
constructed to maximize fill-to-
debris ratio
www.energy.gov/EM 21
Waste Management Summary
In these budget-constrained times, it is more important than ever that DOE optimize its waste management system to ensure environmental cleanup can continue
• Continued integration and flexibility are critical • Financial and economic factors present real constraints • Pending and contemplated regulatory changes will also have impact
The Path Forward….
• Continue to encourage innovation and identification of new disposition options
• Continue close consultation with and among stakeholders • Ensure plans are risk informed