Documents: Rodeo, Texans have $66M plan to demolish dome

Embed Size (px)

DESCRIPTION

The Houston Livestock Show and Rodeo and the NFL's Houston Texans have devised a $66 million plan to demolish the vacant Astrodome and turn the site into an outdoor green space that is reminiscent of downtown's Discovery Green and also pays tribute to the historic stadium.

Citation preview

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    1/37

    February 21

    ASTRODOME SITE STUDY

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    2/37

    Project Goals - A plan that pays tribute to the Astrodomes history and acts asthe outdoor fulcrum of Reliant Park

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    3/37

    The Astrodome impedes circulation flow along two major axes of Reliant Park.

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    4/37

    Removal of the Astrodome leaves an open green space that

    will be an amenity for the citizens of Harris County.

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    5/37

    Case Study:

    Discovery Green Programmed urban park

    Regional Attraction Transformed Downtown

    Successful open spaces are a catalyst for

    development of surrounding properties

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    6/37

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    7/37

    February 21

    Discovery Gre

    Capacity: 52,3estimate 1 person/

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    8/37

    February 21

    Cynthia Woods Mitchell Pavili

    Capacity: 16,5

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    9/37

    February 21

    Sam Houston Race Pa

    Capacity: 15,0

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    10/37

    February 21

    International Festiv

    Capacity: 50,0

    Open Area:385,000sf Open Area: 385,000sf

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    11/37

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    12/37

    30 0

    28 0

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    13/37

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    14/37

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    15/37

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    16/37

    Astrodome History Walking Tour

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    17/37

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    18/37

    I

    I

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    19/37

    I

    I

    Master PlanReliants Backyard

    Phase II

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    20/37

    I

    I

    Phase II

    LIGHT RAIL STATION

    CirculationVehicle and Pedestrian

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    21/37

    I

    I

    534,600sf

    316,800sf

    27,500sf

    39,600sf

    Current CarnTotal Area: 918

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    22/37

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    23/37

    February 21

    Dome GreArea: 385,0

    8.8 a

    Capacity: 38(estimate 1 perso

    Astrodo

    Hallof Fa

    Area: 25,Contains serv

    storage area for the

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    24/37

    February 21

    Carnival and RodeoHall of Fame Centered on Green

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    25/37

    February 21

    Outdoor ConcertHall of Fame Centered on Green

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    26/37

    February 21

    Outdoor ConcertHall of Fame Centered on Green

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    27/37

    February 21

    Game Day TailgateHall of Fame Centered on Green

    Parking Count: 45

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    28/37

    February 21

    2017 Superbowl

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    29/37

    2017 Superbowl

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    30/37

    February 21

    Tensile Structure

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    31/37

    Tensile Structure

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    32/37

    May 3Astrodome Hall of Fame

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    33/37

    February 21Astrodome Hall of Fame

    MEN'S

    VESTIBULE

    VESTIBULE

    ENTRY

    GIFT SHOP

    STORAGE

    WMN'S

    EXHIBITS

    FLEXIBLE SPACE

    CAFE

    KITCHEN

    ENTRY

    Overall sf: 25,000

    Schematic Plan

    Dinning sf: 7,850

    Seating Capacity: 300-500

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    34/37

    L I N B E C K Astrodome Hall of Fame L I N B E C K Astrodome Ha

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    35/37

    February 21

    L I N B E C K Astrodome Hall of FameConcept Construction Budget Summary

    February 20, 2014

    Construction Cost Summary -Site Study

    Summary $/SF Total $

    1 Phase 1 - Demo / Backfill / Utilities 1,151,300 GSF $17.74/SF $20,426,211

    2 Phase 2 - Museum / Hardscape & Landscape 605,000 GSF $29.78/SF $18,018,884

    3 Phase 3 - Columns / Structural 385,000 GSF $45.35/SF $17,458,747

    Total Construction Costs 1,756,300 GSF $31.83/SF $55,903,841

    General Clarifications1. Budget pricing is based upon "Astrodome Site Study" dated January 22, 2014 & "Narratives and Exhibits" document prepared by Walter P Moore dated January 18, 2013.2. All pricing is based on February 2014 material and/or labor costs. Any future escalation costs are specifically excluded.

    . This pricing assumes that all work will be per ormed concurrently.4. Demolition Costs include Implosion. Asbestos costs not included, assumed complete.5. An Allowance (2% of the Sitework cost) has been included for traffic signal timing, revisions to concrete and revisions to gate

    structures in order to accommodate the extra traffic.6. This pricing excludes stages and temporary exhibits.

    Based on ROM Estimate of $56M we suggest a $53M to $58M Budget.

    L I N B E C K Astrodome Ha Concept Construct

    Febru

    Ground Level 385,000 SFBelow Ground 766,300 SF

    Hardscape/Landscape 605,000 SFLinbeck Category: New construction GB Area: 1,756,300 SF

    Estimator: DJ Story Height: 1 FL

    Description Quantity Unit $ Total Cost Cost/GSF % Total Commen

    A. Demolition1. Pre-Demolition Survey 1 LS $13,117.98 $13,118 $0.01 0.02%2. Asbestos Removal $0 $0.00 0.00% Not Required3. MEP Disconnect / Make Safe 1 LS $327,949.62 $327,950 $0.19 0.59%4 . I mp lo si on o f B ui ld in g 1 ,1 51 ,3 00 S F $ 3. 94 $ 4, 53 0, 82 1 $ 2. 58 8 .1 0% I nc lu de s P ro te ct io n t o E5 . Tem po ra ry S ho ri ng 1 L S $ 19 6,7 69 .7 7 $ 19 6,7 70 $ 0.11 0 .3 5% E xt g Co nc F lo or Fr ami

    Subtotal Demolition $5,068,658 $2.89 9.07%

    B. Foundation1. Excavation $0 $0.00 0.00% Not Required2. Backfill 397,500 CY $26.24 $10,428,798 $5.94 18.65% Place Select Fill3. Cathodic Protection $0 $0.00 0.00% Not Required4. Spread Footings 72 EA $ 13,385.18 $963,733 $0.55 1.72%5. Continuous Footings 2,100 LF $214.79 $451,054 $0.26 0.81%6. Tower Crane Foundation 4 EA $45,912.95 $183,652 $0.10 0.33%

    Subtotal Foundation $12,027,237 $6.85 21.51%

    C. Structure1. Columns 72 EA $191,442.53 $13,783,862 $7.85 24.66%2. Miscellaneous Steel 385,000 SF $1.31 $505,042 $0.29 0.90%3. Tower Crane - 4 Each $0 $0.00 0.01% Not Required4. Truck Crane - 3 Hyrdos 20 MO $29,515.47 $590,309 $0.34 0.01%5. Erect / Remove Tower Crane $0 $0.00 0.01% Not Required6. Tower Crane Operators $0 $0.00 0.01% Not Required7. Truck Crane Operators 277 WK $3,541.86 $981,094 $0.56 1.75%

    Subtotal Structure $15,860,308 $9.03 28.37%

    D. Enclosure Not Required

    Subtotal Enclosure $0 $0.00 0.00%

    E. Finishes / Specialties Not RequiredSubtotal Finishes $0 $0.00 0.00%

    F.MEP1. Plumbing, Drainage 385,000 SF $0.66 $252,521 $0.14 0.45%Subtotal MEP $252,521 $0.14 0.45%

    G. Conveying Systems & Equipment Not RequiredSubtotal Conveyors & Equipment $0 $0.00 0.00%

    H. Sitework1. Utilities2. Sanitary Sewer Cut & Plugs 7 EA $3,279.50 $22,956 $0.01 0.04%3. Waterline Cut & Plugs 5 EA $3,279.50 $16,397 $0.01 0.03%4. Storm Sewer Cut & Plugs 27 EA $3,279.50 $88,546 $0.05 0.16%5. Grease Trap Abandonment 2 EA $6,558.99 $13,118 $0.01 0.02%6. Gas System 1 LS $ 65,589.92 $65,590 $0.04 0.12%7. Electrical8. Sub Station 385,000 SF $6.56 $2,525,212 $1.44 4.52%9. R e-Feed Reliant Arena 385,000 SF $3.28 $1,262,606 $0.72 2.26%

    10. Re-Route Conduit 385,000 SF $1.05 $404,034 $0.23 0.72%11. Lighting w/ Poles 385,000 SF $0.52 $202,017 $0.12 0.36%12. Temporary Power 385,000 SF $0.20 $75,756 $0.04 0.14%13. Telephone Service - AT&T $0 $0.00 0.00% By Others14. Plaza - Renovate / Rework / Landscape15. Museum & Visi tor Center 210,000 SF $10.49 $2,203,821 $1.25 3.94%16. Carruth Plaza 150,000 SF $10.49 $1,574,158 $0.90 2.82%17. Retail Promenade 220,000 SF $10.49 $2,308,765 $1.31 4.13%18. Dome Museum 25,000 SF $459.13 $11,478,237 $6.54 20.53%19. Tra ff ic S igna l/Conc re te /Gate R evis ions 1 LS $453, 902. 35 $453, 902 $0. 26 0 .81% Allowance

    Subtotal Sitework $22,695,117 $12.92 40.60%

    Total $55,903,841 $31.83 100.00%

    L I N B E C K Astrodome Hall of FL I N B E C K Astrodome Hall of Fame

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    36/37

    February 21

    L I N B E C K Astrodome Hall of F

    Project Schedule Summ

    February 20, 2

    Start Finis

    Owner release team to proceed 6/2/14 6/2/1

    Center Point Substation

    Center Point agreement 6/2/14 6/27/

    Relocate Substation (12 months) 6/30/14 6/26/

    Design Work (8 months)

    Schematic Design Phase 6/2/14 8/1/1

    Design Development Phase 8/4/14 10/3/

    Construction Document Phase 10/6/14 2/6/1

    Develop GMP 2/9/15 3/6/1

    Owner Approval 3/9/15 3/20/

    Construction (32 months)

    Notice to Proceed w/ Construction 6/2/14

    Mobilize 6/2/14 6/20/

    Phase 1 - Underground Utilities 6/23/14 1/2/1

    Phase 1 - Demolition and Backfill of Astrodome 4/17/15 4/14/

    Phase 2 - Plaza and Astrodome Hall of Fame 4/15/16 2/2/1

    Phase 3 - Commemorative Columns 4/1/16 10/4/

    Sitework & Completion 6/15/16 11/1/

    Substantial Completion 2/3/1Super Bowl 2/5/1

    L I N B E C K Astrodome Hall of Fame

    Concept Project Budget

    February 20, 2014

    Construction $55,903,841

    Hazardous Material & Abatement (not included)

    FF&E items - Allowance $500,000

    Security Cameras - Allowance $200,000

    A/E team Consultant Fees $3,000,000

    Architect

    Structural Engineer

    MEP Engineer

    Civil Engineer

    Landscape

    Lighting

    Graphics

    Code

    IT/AV

    Specifiations

    Traffic

    3D Renderings $7,500

    Survey $75,000

    Geotechnical Report $50,000

    Permit Fees (not included)

    CenterPoint Fees - Allowance $100,000

    Materials Testing $200,000

    Reimbursables $75,000

    Subtotal $60,036,341

    Owner Contingency (10%) $6,003,634

    TOTAL PROJECT COSTS $66,039,975

    ID Name Duration Start Finish

    Jan 2014Apr Jul Oct

    Jan 2015Apr Jul Oct

    Jan 2016Apr Jul Oct

    Jan 2017Apr Jul Oct

    Jan 2018Apr Jul

    Nov 2013

  • 5/22/2018 Documents: Rodeo, Texans have $66M plan to demolish dome

    37/37

    ID Name Duration Start Finish

    1 ST00110 Commissioner's Court Decision 0 Days 5/15/2014 (*)

    2 ST00087 Release Design Team to Proceed 0 Days 6/2/2014 (*)

    3 ST00065 CenterPoint Agreement 20d 6/2/2014 6/27/2014

    4 ST00020 Design Work 220d 6/2/2014 4/3/2015

    5 ST00220 Prepare SD Drawings 45d 6/2/2014 8/1/2014

    6 ST00100 SD Drawing Budget 10d 8/4/2014 8/15/2014

    7 ST00180 Prepare DD Drawings 45d 8/4/2014 10/3/2014

    8 ST00230 DD Drawing Budget 15d 10/6/2014 10/24/2014

    9 ST00211 Submit for Demo Permit 20d 10/6/2014 10/31/2014

    10 ST00192 Prepare CDs 90d 10/6/2014 2/6/2015

    11 ST00155 Submit for Permit 40d 2/9/2015 4/3/2015

    12 ST00136 Develop GMP 20d 2/9/2015 3/6/2015

    13 ST00117 Approvals 10d 3/9/2015 3/20/2015

    14 ST00076 Contracts & Expediting 195d 10/27/2014 7/24/2015

    15 ST00073 Demo Contr ac t & Submi ttal 45d 10/27/2014 12/26/2014

    16 ST00067 Steel Contract & Submittals 80d 3/9/2015 6/26/2015

    17 ST00055 Rebar Contract & Submittals 25d 3/9/2015 4/10/2015

    18 S T0 00 53 M us eum Co nt ra ct s & E xpe di ti ng 10 0d 3/ 9/ 20 15 7 /2 4/ 20 15

    19 ST00030 Phase 1-Demo/Backfill/Centerpoint 489d 6/2/2014 4/14/2016

    20 ST00040 Secure Site 15d 6/2/2014 6/20/2014

    21 S T0 00 50 R el oc at e Ce nt er Po int S ub st at io n 26 0d 6/ 30 /2 01 4 6 /2 6/ 20 15

    22 ST00070 Trace, Cut & Cap Utilities 140d 6/23/2014 1/2/2015

    23 ST00090 Demolition 160d 4/17/2015 11/26/2015

    24 ST00075 Backfill 160d 9/4/2015 4/14/2016

    25 Phase 2-Plaza & Dome Museum 210d 4/15/2016 2/2/2017

    26 ST00376 Foundation 30d 4/15/2016 5/26/2016

    27 ST00386 Structure 40d 5/27/2016 7/21/2016

    28 ST00396 Enclosure 60d 7/22/2016 10/13/2016

    29 ST00406 Interiors 40d 10/14/2016 12/8/2016

    30 ST00416 Completion A ctivities 40d 12/9/2016 2/2/2017

    31 ST0 01 20 Pha se 3 -Columns 1 33 d 4 /1 /2 01 6 1 0/4/20 16

    32 S T0 01 30 D ri ll ed P ie r ( 4 p er c ol um n/ 28 8 e a) 25 d 4/ 1/ 20 16 5 /5 /2 01 6

    33 ST00140 Pier Cap (72 ea) 60d 4/6/2016 6/28/2016

    34 ST00150 Erect Columns 20d 6/15/2016 7/12/2016

    35 ST00160 Detail Columns 40d 6/22/2016 8/16/2016

    36 ST00170 Cladding 75d 6/22/2016 10/4/2016

    37 ST00320 Sitework 75d 6/15/2016 9/27/2016

    38 ST00330 Completion Activities 20d 10/5/2016 11/1/2016

    39 ST00340 Substantial Completion 0 Days 2/3/2017

    4 0 ST0 03 50 Sup er Bow l 0 Days 2/5/2017 (*)

    wk -5Aprwk 9

    Julwk 22

    Octwk 35 wk 48

    Aprwk 61

    Julwk 74

    Octwk 87 wk 100

    Aprwk 113

    Julwk 126

    Octwk 139 wk 153

    Aprwk 165

    Julwk 178

    Octwk 192 wk 205

    Aprwk 218

    Julwk 231wk -13

    Commissioner's Court DecisionRelease Design Team to Proceed

    CenterPoint AgreementDesign Work

    Prepare SD DrawingsSD Drawing Budget

    Prepare DD DrawingsDD Drawing BudgetSubmit for Demo Permit

    Prepare CDsSubmit for Permit

    Develop GMPApprovals

    Contracts & ExpeditingDemo Contract & Submittal

    Steel Contract & SubmittalsRebar Contract & Submittals

    Museum Contracts & ExpeditingPhase 1-Demo/Backfill/Centerpoint

    Secure SiteRelocate CenterPoint Substation

    Trace, Cut & Cap UtilitiesDemolition

    Backfill

    Phase 2-Plaza & Dome MuseumFoundation

    StructureEnclosure

    InteriorsCompletion Activities

    Phase 3-ColumnsDrilled Pier (4 per column/288 ea)

    Pier Cap (72 ea)Erect Columns

    Detail ColumnsCladdingSitework

    Completion Activities

    Substantial CompletionSuper BowlProjecttitle Astrodome Hall of FameProgrammetitle

    Client Texans/Houston Rodeo

    Dated 2/19/2014 Drawnby Mark Gore ProgrammeNo

    Rev No Rev comments

    Notes

    : _ -