Distribution Circuit Load Forecasting Using AMI Data Bradley Lawson – SAS Mark Konya - SAS

Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

  • Upload
    others

  • View
    7

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

Distribution Circuit Load Forecasting Using AMI DataBradley Lawson – SASMark Konya - SAS

Page 2: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

What is Distribution Circuit Load Forecasting?

• Very short to very long-term forecasts of distribution circuit loads

• at intermediate distribution circuit locations between customer meters and substation feeder buses

• using AMI (Advanced Metering Infrastructure) data

• Provides significant advantages to distribution system planners and operators in a number of areas

• anticipation of device overloads

• facilitation of switching operations

Page 3: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

Why Hourly Distribution Circuit Load Forecasting?

• Now have AMI (Advanced Metering Infrastructure) data

• The pattern of customer loads matter when changes are taking place

• Knowing customer’s peak load is not enough, need to know how it fits with all the other customers on the distribution feeder.

• More chance for localized problems. (Know the feeder pattern, but problems could arise on the local/transformer.)

• More chance for localized opportunities. (DR)

• Hourly modeling helps anticipate localized loads from severe weather

Page 4: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

Grid Disruption Will Continue

4

Rooftop and community solar

Electric vehicles

Customer battery

Smart home

Page 5: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

The Residential Customer

5

Customer loads

Roof Top Solar

Storage

Electric Vehicles

+

+

-Customer

+

Page 6: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

The New Residential Customer

6

Customer loads

Roof Top Solar

Storage

Electric Vehicles

+/0

+/-

-

Demand Response

+/-

+/-

Page 7: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

Effect of Solar and Wind Generation

Page 8: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

North Carolina Solar

8

Data Current Through:Q3 2018

Installed (MW): 4,671

National Ranking: 2nd (2nd in 2017)

State Homes Powered by Solar: 533,796

Percentage of State's Electricity from Solar: 5.44%

Solar Jobs: 7,622

Prices have fallen 43% over the last 5 years

Growth Projection and Ranking:

3,671 MW over the next 5 years (ranks 4th)

https://www.seia.org/state-solar-policy/north-carolina-solar

Page 9: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

Mitigating the duck curve with storage

Page 10: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

10

Electric vehicles

Page 11: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

Electric Vehicles

0.0

5.0

10.0

15.0

20.0

25.0

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Hourly Household Load

Home Load

0.0

5.0

10.0

15.0

20.0

25.0

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

EV Charge Start 6 PM

Home Load EV Load

Page 12: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

Electric Vehicles

0.0

5.0

10.0

15.0

20.0

25.0

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

EV Charge Start 9 PM

Home Load EV Load

0.0

5.0

10.0

15.0

20.0

25.0

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

EV Charge Start Midnight

Home Load EV Load

Page 13: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

13

METERING ADVANCES

Page 14: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

Billed and unbilled sales

14

JAN FEB

Billed Sales MHW Unbilled Sales

Bill Cycle 1

Bill Cycle 20

Page 15: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

Metering

15

AMR - Automated Meter reading

Reads meter once per month

• No hourly Data

• Read in cycle – never a calendar month

• Data no different from traditional meter

AMI - Automated Metering Infrastructure

Read meter continuously

• Hourly data……Big Data

Page 16: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

AMI Meters

16

Page 17: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

17

How is hourly forecasting different from monthly or daily?

Page 18: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

What is the Challenge of Hourly Forecasting?

18

Page 19: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

What is the Challenge of Hourly Forecasting?

19

Page 20: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

Simple Load Forecast Model

20

𝑳𝒐𝒂𝒅 = 𝑰𝒏𝒕𝒆𝒓𝒄𝒆𝒑𝒕 + 𝜷𝟏 ∗ (𝑻𝒆𝒎𝒑𝒆𝒓𝒂𝒕𝒖𝒓𝒆 < 𝟔𝟎) +𝜷𝟐 ∗ (𝑻𝒆𝒎𝒑𝒆𝒓𝒂𝒕𝒖𝒓𝒆 > 𝟔𝟎)

Page 21: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

Degree Days

21

Daily Average Temperature (DAT) = (maximum + minimum)/2

Heating Degree Days = 65 degrees F – DAT Where temperatures are below 65

Cooling Degree Days = DAT- 65 degrees F Where temperatures are above 65

𝑳𝒐𝒂𝒅 = 𝑰𝒏𝒕𝒆𝒓𝒄𝒆𝒑𝒕 + 𝜷𝟏 ∗ (𝑯𝑫𝑫𝟔𝟓) + 𝜷𝟐 ∗ (𝑪𝑫𝑫𝟔𝟓)

Page 22: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

What is the Challenge of Hourly Forecasting?

22

Page 23: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

What is the Challenge of Hourly Forecasting?

23

Page 24: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

What causes the differences

24

• Heating/Cooling

• Schools

• Pool pumps

Season or Month

• Lower loads on Saturdays and Sundays

• Drop off of Industrial load on Friday

• SchoolsDay of Week

• Family life patterns

• Businesses open and close

• Industrial Plants – 1/2/3 shiftsHour of Day

Page 25: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

What should a hourly load forecast model consider?

25

Temperature

Season or Month

Day of Week

Hour of Day

Page 26: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

26

DATA

Page 27: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

“Before (adopting analytics), we spent 80 percent of our time processing data and just 20 percent analyzing it. Those percentages have now flip-flopped, freeing up more time for us to plan and launch data-driven operational activities.”

Page 28: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

Forecast process

28

Historic hourly load and Temperature DataForecast Hourly

Temperature Data

Fit a modelForecast Hourly

Future Load

Page 29: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

Data for hourly forecasting

29

• Need at least a year of data to build models/Two or three years are better

• Hourly (AMI) load data

• Temperature

Page 30: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

Data needs to be cleaned

30

• Data problems

• AMI - missing

• Temperature – missing & incorrect

• Demand response & solar reduced load

Page 31: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

Residential behind the meter solar

31

Page 32: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

32

Distribution Circuit Load Forecasting

Page 33: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

Levels of the power system

Page 34: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

Illustration of Feeder Circuit

34

Page 35: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

Customer Segmentation

• May want to forecast individual customers as a segment of the population rather than from their individual data.

Page 36: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

40%

07:00 16:00 22:00

00:00 05:00 10:00 15:00 20:00 24:00

Page 37: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

33%

07:00 16:00 22:00

00:00 05:00 10:00 15:00 20:00 24:00

Page 38: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

57%

07:00 16:00 22:00

00:00 05:00 10:00 15:00 20:00 24:00

Page 39: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

Lingering issues

• Behind the meter solar reductions

• Identify customers with solar

• Customers with EVs

• Phase identification

• Forecast by customer type

Page 40: Distribution Circuit Load Forecasting Using AMI Data · Why Hourly Distribution Circuit Load Forecasting? •Now have AMI (Advanced Metering Infrastructure) data •The pattern of

www.electricities.com

FOLLOW US ON SOCIAL MEDIA:

@ncpublicpower

facebook.com/Electricities

@ElectriCitiesNC