Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
1
Developments in environmental law in 2012-2013
James Burton1
Based on previous papers by Stephen Tromans QC, Justine Thornton, Ned Helme,
Philippa Jackson and Daniel Stedman Jones2
Overview
1. This paper considers developments in environmental law in 2012 and 2013. It does
not pretend to be comprehensive.3 Issues covered include: private nuisance;
enforcement; EIA; SEA; habitats; waste; and environmental judicial review,
including the new Aarhus Convention costs regime embodied in the CPR.
2. It also includes a short digest of other cases.
Private Nuisance
3. It is worth remembering that until relatively recently the tort of private nuisance was
something of a litigation backwater, perhaps with the honourable exception of tree
root claims. Certainly if judged by the number of reported cases. The reasons why
were many and various, and the planning system is perhaps owed some credit for
doing its job reasonably well and keeping incompatible uses apart. But three obvious
and interlinked factors that tended to discourage claims were (a) their relatively low
value, (b) the high cost of litigation (often requiring expensive expert evidence) and
(c) difficulties in securing funding protection. Unsurprisingly, individual potential
claimant homeowners tended to grin and bear it rather than confront what was
typically a commercial concern causing the problem.
4. Then, claimant solicitors increasingly began to apply the tools made available to them
by the CPR and Access to Justice reforms; group litigation orders, CFAs and, most
importantly, ATE insurance. The relatively low value of the claims had not changed,
but solicitors were now willing to pursue these claims, and claimants could do so safe
in the knowledge that they were at no risk as to costs so long as they followed advice.
1 Barrister, Thirty Nine Essex Street Chambers; [email protected] 2 Barristers, Thirty Nine Essex Street Chambers. 3 For a reasonably comprehensive overview of developments month-by-month, see the Bulletins to the Encyclopedia of Environmental Law (Sweet & Maxwell) (“the Encyclopedia”).
2
5. Barr v Biffa was one such group action, an odour nuisance claim arising out of the
Defendant’s use of the Westmill 2 landfill in Hertfordshire. The Court of Appeal’s
decision ([2012] EWCA Civ 312) has attracted a great deal of commentary, but
perhaps the most remarkable feature of the case is that some considered the appellate
result was ever in doubt.
6. The principles underlying the tort of nuisance have barely altered since they were first
firmly established in the 19th century, including when challenged by the emergence of
a statutory town planning system in the mid-20th century. The courts’ response to that
(see the Gillingham Docks case) was not necessarily to alter the basic principles, but
rather to acknowledge that the character of an area that informs the ultimate test of
reasonable give and take between neighbours (the twin concepts of reasonableness of
user and reasonableness of interference) might be changed by a sufficiently
strategic/significant grant of planning permission. Put in terms of the old saw about
what might be a nuisance in Berkeley Square not necessarily being so in Bermondsey,
a sufficiently significant grant of planning permission might make Bermondsey a little
more like Mayfair, or vice versa. A fortiori in the case of more than one similar
strategic/significant planning permissions in an area.
7. In Barr v Biffa the Defendant relied upon compliance with its environmental permit
as a complete answer to the claims against it. In essence, its case was that the modern
regulatory regime had overtaken the common law. However, the environmental
permitting regime was not only not intended to supplant the common law of nuisance,
it is also plainly not apt to deal with the land-use planning issues that may result in a
change in character. As such, the first-instance decision of Coulson J, accepting the
Defendant’s case regarding the significance of compliance with its environmental
permit, was ripe for challenge.4
8. Allowing the appeal, the Court of Appeal re-affirmed classic principles. Carnwath LJ
(as he then was) explained the basics:
36. “In my view this case is governed by conventional principles of the law of
nuisance, which are well-settled, and can be found in any of the leading
textbooks. Thus, in Clerk & Lindsell on Torts 20th ed. chap 20, the third category
4 See, for example, our extended discussion of the first instance decision in Encyclopedia Bulletin 176.
3
of nuisance is that caused by a person “unduly interfering with his neighbour in
the comfortable and convenient enjoyment of land”. Typical examples include
“creating smells by the carrying on of an offensive manufacture or otherwise”:
paras. 20-06 to 20-09. Relevant to this case are the following rules:
(i) There is no absolute standard; it is a question of degree whether the
interference is sufficiently serious to constitute a nuisance. That is to be decided
by reference to all the circumstances of the case: para. 20-10.
ii) There must be a real interference with the comfort or convenience of living,
according to the standards of the average man (para. 20-11), or in the familiar
words of Knight Bruce VC: “… not merely according to elegant or dainty modes
and habits of living, but according to plain and sober and simple notions among
the English people” (Walter v Selfe (1851) 4 De G&Sm 315, at p 322).
iii) The character of the neighbourhood area must be taken into account. Again in
familiar 19th century language, “what would be a nuisance in Belgrave Square
would not necessarily be so in Bermondsey…”: para. 20-13, citing Thesiger LJ,
Sturges v Bridgman (1879) 11 ChD 852, 856.
iv) The duration of an interference is an element in assessing its actionability, but
it is not a decisive factor; a temporary interference which is substantial will be an
actionable nuisance: para. 20-16.
v) Statutory authority may be a defence to an action in nuisance, but only if
statutory authority to commit a nuisance is express or necessarily implied. The
latter will apply where a statute authorises the user of land in a way which will
“inevitably” involve a nuisance, even if every reasonable precaution is taken:
para. 20-87.
vi) The public utility of the activity in question is not a defence: para. 20-107.
9. In short, the character of the neighbourhood coupled with the nature of the
interference are the key planks in the analysis of give-and-take.
10. A more successful attempt to rely upon the modern regulatory regime, albeit the
planning regime that the common law of nuisance has long accommodated, was
Coventry v Lawrence [2012] 1 WLR 2127, where the Court held that motor racing
activities, carried on for a considerable time, first without permission, then with the
4
benefit of a Certificate of Lawful Use and then a planning permission subject to
detailed conditions, had indeed become part of the “character of the neighbourhood”
against which the reasonableness of the defendant's use of the land (and so the alleged
nuisance) had to be judged.
11. The case involved the ownership and operation of a stadium and track used for
various forms of motor sport racing at Mildenhall, Suffolk. There was a long
planning history, including temporary permissions, a CLEUD and then permanent
planning permission for the track in 2002. Planning officers’ reports over the years
between 1992 and 2002 showed that the local planning authority had given careful
consideration to the differing interests of those who lived in the locality; the need to
protect residents from undue disturbance, but also the valuable social function of the
facility. The Claimants had purchased a bungalow in 2006, which was 560 metres
from the stadium, and 864 metres from the track. Whether they were aware of the
Stadium and Track activities before purchase was a matter of dispute. They argued
that the use generated such noise as to amount to a nuisance to them in their home,
and made complaints to the District Council, which served breach of Condition
Notices, and also Statutory Nuisance Abatement Notices, which abatement works
were completed in January 2009 to the Council’s satisfaction. Those works reduced,
but did not eliminate, the noise. The Claimants brought private nuisance proceedings,
seeking damages and injunctions. They also sought aggravated and exemplary
damages. The first instance judge rejected the claims for aggravated and exemplary
damages, but awarded ordinary damages for the nuisance and granted injunctions to
limit the noise which could be generated. He noted that there was no authority for the
proposition that one could acquire a right to cause nuisance-generating noise by
prescription, and found that the law did not recognise an easement of noise. On
appeal against both key findings, Jackson L.J. summarized the law relevant to the
first ground in four propositions:
(i) A planning authority by the grant of planning permission cannot authorise the
commission of a nuisance;
(ii) Nevertheless the grant of planning permission followed by the
implementation of such permission may change the character of a locality;
5
(iii) It is a question of fact in every case whether the grant of planning permission
followed by steps to implement such permission do have the effect of changing
the character of the locality; and
(iv) If the character of a locality is changed as a consequence of planning
permission having been granted and implemented, then:
(a) the question whether particular activities in that locality constitute a nuisance
must be decided against the background of its changed character; and
(b) one consequence may be that otherwise offensive activities in that locality
cease to constitute a nuisance.
12. When the Claimants had bought the bungalow, the noise of motor sports emanating
from the track and the stadium were an established part of the character of the locality
and they could not be left out of account when considering whether a nuisance had
occurred. Had the Appellants conducted their business at noise levels above those
permitted by the planning permissions, the Respondents might have been able to make
out a case in nuisance, but that did not appear to be the case. Accordingly the appeal
was allowed on the first ground, namely the consequence of obtaining and
implementing the various planning permissions, hence the alleged nuisance had not
been established and the claim stood to be dismissed.
13. In relation to the second ground, Lewison L.J. added that in his judgment there was no
doubt that the law would recognise an easement exercisable between certain times of
day, and could see no reason in principle why an easement exercisable during certain
times of the year was incapable of creation. The question of whether an ‘easement of
noise’ was possible was one which should be left open.
14. Whilst Coventry v Lawrence turns on its own facts, it does suggest a more
sympathetic judicial approach to the significance of planning permission than has
historically been the case.
15. Permission to appeal to the Supreme Court in Barr v Biffa having been refused, but
granted in Coventry v Lawrence we await the Supreme Court’s decision in the latter
and the re-run of Barr v Biffa before Coulson J in the TCC, but in the meantime we
have Anslow v Norton [2012] EWHC 2610 to consider.
6
16. Anslow was a group action by claimants who alleged a private nuisance through
emissions of phenolic and sulphurous odours, noise, smoke and dust from a foundry,
and is probably the most significant first instance case post Barr v Biffa. Only the
odour complaints had merit. The court (HHJ McKenna QC) applied the classic
principles reaffirmed in Barr v Biffa, but the case is interesting for three reasons:
(1) The central role of the odour experts including the use of odour
modelling;
(2) The fact that the judge decided upon an odour unit threshold
for nuisance by reference to the EA’ H4 guidance note, albeit
one a little above that typically sought by the EA when setting
permit conditions for this type of odour; and
(3) The approach to quantification of damages.
17. The (lengthy) judgment includes a comprehensive consideration of the
merits/demerits of the approach taken by the various odour experts involved. It was
clear that the odours in question were not to be equated with “less offensive” odours
such as those from a bakery (for which H4 suggests a threshold of 6OU). Equally it
was not “most offensive”. Ultimately the Judge decided on an odour unit threshold of
5. That is a little above the level one would expect based on H4, but given an action
for nuisance will not lie unless the interference is “substantial” seems justified.
18. The approach to quantification of damage was novel. This was not a case where it was
possible to determine a loss of value by reference to decreased rental, and the Judge
was reluctant to extrapolate from the evidence of local surveyors. Ultimately, the
approach taken was to arrive at an annual sum to represent loss of enjoyment due to
odour interference and multiply it by the number of affected years, with the result
compared to awards in the personal injury sphere with a view to ensuring that it did
not result in a level of compensation for those who have suffered nuisance that would
appear disproportionate compared to those who have suffered injury.
19. The Court’s approach certainly has the benefit of simplicity, but it is open to criticism.
Nuisance is a tort to land, and damage is the loss of value to the affected property
interest. By apparently severing the link between land values and the award, the
Court arguably stepped too far away from basic principles. However, Anslow was not
7
appealed (it is understood the defendant was impecunious) and it will be some time
before quantification is considered at appellate level.
20. Another case to grapple with the implications of Barr v Biffa and Coventry v
Lawrence was Thomas v Merthyr Tydfil Car Auction Ltd [2013] Env. LR 12. The
Claimants complained of noise and fumes amounting to a nuisance arising from a
vehicle auction business. The Defendant business was granted planning permission to
use the land for storage, parking and valeting of vehicles to be sold at auction.
Applying Biffa and Coventry in the Court of Appeal, Wyn Williams J gave judgment
for the claimants in granting a limited award of general damages of £9,000. The case
is being appealed as the Supreme Court’s judgment in Coventry is awaited.
21. Finally, in Dobson & Others v Thames Water Utilities Ltd (where damages were
sought in relation to odour nuisance from the defendant’s waste water treatment
works) the TCC has now given judgment regarding the correct approach to awarding
interest on general damages for nuisance, claimed under section 35A of the Senior
Courts Act 1981 (see [2012] EWHC 986 (TCC)).
22. The Claimants argued that as the damages were based on a percentage of the monthly
rental values which could be obtained for the properties owned by them, and were
assessed as a sum by way of damages annually, the interest should be awarded at the
full special account rate from the end of each calendar year during which the nuisance
was suffered until payment. The Defendant argued (1) that the damages awarded
related to non-pecuniary loss for interference with the enjoyment and amenity of land,
and so the quantum was assessed as at the date of the judgment and not at any earlier
point of time; and (2) that the interest rate on general damages for non-economic loss,
such as for nuisance or personal injury, should be two per cent per annum between the
service of proceedings and the date of judgment, rather than the full special account
rate claimed. Ramsey J found that general damages for personal injury or death raised
issues which were different and not relevant to an award of general damages for
nuisance. There was no authority as to the principles upon which the statutory
discretion to award interest should be exercised in the case of an award of damages
for nuisance. The approach taken had been to assess the damages to which each
claimant had been entitled for a particular year, so that the total sum awarded
constituted a number of sums awarded for each year. That approach meant that there
8
was an ascertainable amount of damages for each year to which a claimant was
entitled. Any award of interest was not compensation for that damage done, but for
the particular claimant being deprived of the money which should have been paid to
them. Accordingly, it was appropriate for the court to exercise its discretion and
award interest under s.35A on each annual sum awarded as damages. There was no
basis for applying the two per cent rate used in the context of damages for personal
injury. The special account rate which varied from time to time reflected the fact that
a party had been kept out of the money for a particular period. Whilst it was not
generally used as a rate of interest applied to debt and damages outside personal
injury claims, that rate had reflected a margin of 0 per cent to 2.75 per cent above the
Bank of England base rate over the relevant period. It would not under or over-
compensate the claimants and so would be adopted as the appropriate rate.
23. If anything, this decision further underlines the tension between awards of “general”
damages in nuisance claims, not pegged to property values, as approved in Anslow
and the classic position.
Enforcement
Nullity
24. The classic statement of the test for validity of an enforcement notice is that of
Upjohn LJ in Miller-Mead v. Minister of Housing and Local Government [1963] 2
Q.B. 196:
"does the notice tell (the person on whom it is served) fairly what he has done
wrong and what he must do to remedy it?"
25. The recipient is:
"entitled to say that he must find out from within the four corners of the
document exactly what he is required to do or abstain from doing"
26. A notice will be a nullity where it is defective on its face. It may, for example, fail
altogether to specify a date upon which it is to take effect. That defect must be fatal to
the notice: without it, the notice never can take effect. Or the notice may fail to define
9
a period within which the required steps are to be taken; or it may do so in such an
ambiguous manner as to fall short of the statutory requirement that these matters be
"specified" in the notice. There are a variety of ways in which a careless regulator
may produce a worthless piece of paper.
27. But the easiest trap to fall into, and the most deadly given it often requires litigation to
achieve recognition of nullity, is a failure to sufficiently specify steps to be taken.
28. This crops up time and again. In statutory nuisance cases, the leading authority
covering the requirements of a notice as a whole remains R v Falmouth Port Health
Authority, ex p South West Water [2001] QB 445 (CA). South West Water had
installed a sewage outfall at Black Rock, replacing outfalls at Middle Point and
Pennance Point which were affecting the quality of bathing waters at three nearby
beaches. The water company had the benefit of a discharge consent for the outlet from
the EA. The Health Authority received complaints about the outlet, and resolved to
serve an abatement notice pursuant to s.80 EPA 1990, alleging statutory nuisance
under s.79(1)(h) of that Act, namely a nuisance under s.259(1)(a) of the Public Health
Act 1936 because the watercourse known as Carrick Roads was so foul or in such a
state as to be prejudicial to health or a nuisance. The abatement notice required the
cessation of discharge from the outfall within three months of service, pursuant to
s.80(1)(a) EPA 1990 as follows:
"within three months from the service of this notice…cease the discharge of
sewage…via the said New Long Sea Outfall from the sewerage system"
29. The notice imposed no requirement under s.80(1)(b) EPA 1990 for, "the execution of
such works, and the taking of such other steps, as may be necessary for any of those
purposes". The water company complained that it was defective as a result. The Court
of Appeal disagreed, but added an important rider:
"in all cases the local authority can if it wishes leave the choice of means of
abatement to the perpetrator of the nuisance. If, however, the means of
abatement are required by the local authority, then they must be specified; the
Network case, 93 LGR 280 and the Sterling case [1996] Env. LR 121 remain
good law."
10
30. Sterling Homes v Birmingham City Council [1996] Env.LR 121 (Divisional Court)
concerned an industrial operation in close proximity to a residential property known
as Queen's Court. Part of the operation involved stamping, pressing and toolmaking
with a 450 ton press known as "Big Bertha". The operation of the press gave rise to a
great deal of noise and vibration which could be felt by some of the occupants of
Queen's Court. Sterling Homes owned Queen's Court, and had been the applicant for
planning permission. Given the building's location near to an industrial operation the
planning permission had included conditions designed to ensure that noise did not
unduly affect residential amenity. Sterling believed it had identified a way to ensure
that was achieved. In practice, its solution proved false.
31. In due course the City Council investigated a complaint of statutory nuisance and
proceeded to serve an abatement notice, so far as material as follows:
"TAKE NOTICE that Birmingham City Council being satisfied of the
existence of a statutory nuisance at:
Number 1 in Queen's Court ...
arising from
The transmission of noise and vibration through the structure of the premises
from the nearby industrial unit so as to be prejudicial to health or a nuisance.
Do hereby require you to abate the said nuisance within 56 days from the
service of this notice upon you, and for that same purpose require you to carry
out such works as may be necessary to ensure that the noise and vibration does
not cause prejudice to health or a nuisance, take any other steps as may be
necessary for that purpose."
32. On a casual reading, that notice might appear sufficient. It is not. A direction that a
person carry out "such works as may be necessary" requires the person to take steps
but then fails to specify the steps to be taken. It is this kind of vague catch-all
language that is a particular pitfall in these cases.
33. The notice in Sterling was a nullity, with the result that the appeal was allowed and
the matter remitted to the magistrates with a direction to acquit.
34. However, enforcing authorities continue to fall into the trap.
11
35. In R. (on the application of European Metal Recycling Ltd) v Environment Agency
[2012] EWHC 2361 (Admin) HHJ Pelling QC (sitting as a high court judge)
considered a claim for judicial review seeking, inter alia, declaratory relief that a
suspension notice issued by the EA was a nullity. The claimant operated a sizeable
scrap metal facility, subject to an environmental permit. Its activities generated noise,
and there were considerable neighbour complaints. As of 31st August 2011 the
conditions to the permit required that:
"Emissions from the activities shall be free from noise and vibration at levels
likely to cause pollution outside the Site, as perceived by an authorised officer
of the Environment Agency, unless the operator has used appropriate
measures, including but not limited to those specified in any approved noise
and vibration management plan to prevent or where that is not practical to
minimise the noise and vibration".
36. Complaints continued, and the EA resolved to serve a suspension notice pursuant to
Reg.37 of the Permitting Regs 2010. The notice provided, so far as material, that:
"Under regulation 37 … we may suspend an environmental permit if we
consider that operation of the regulated facility involves a risk of serious
pollution.
Accordingly the Environment Agency has decided to suspend the
environmental permit to the extent specified in Schedule 1 with effect from
midnight on 26th February 2012.
In addition you are required to take the steps specified in Schedule 2 to
remove the risk.
The reason for this decision is that we consider that the noise arising from
operation of the regulated facility involves a risk of serious pollution.
…
Schedule 1
Extent to which the Environmental Permit is suspended
All movement of waste onto, within and off the site.
…
12
Schedule 2
Steps to Be Taken To Remove Risk of Serious Pollution
Design and implement measures that eliminate the risk of serious pollution
from noise …[by] 31 August 2012."
37. The EA's position was not that all noise from the site was to cease, but that noise
constituting serious pollution should cease. The EA has issued guidance concerning
its enforcement activities. As regards suspension notices it states that, amongst other
things, the notice must … "say what the risk of serious pollution is … say what steps
must be taken to remove the risk …".
38. The claimant challenged Schedule 2 of the notice on the following grounds:
i) It failed to specify what if any steps were required to be taken; and/or
ii) It failed to provide a defined threshold criterion objective, or defined threshold
criteria or objectives, that had to be satisfied by (the claimant) if it was to comply;
and/or
iii) It was otherwise vague and imprecise.
39. It was common ground that "specify" within Reg.37 meant "to state explicitly", but as
the Judge observed the crucial question was what it was that was required to be stated
explicitly. He noted that, unlike abatement notices under the statutory nuisance
provisions, Reg.37 makes it mandatory upon the EA to specify the steps that must be
taken. As regards the contents of Sch.2 to the notice, he said this at §25:
Schedule 2 to the SN specifies the steps that have to be taken as being to
"…Design and implement measures that eliminate the risk of serious pollution
from noise". As a matter of language a requirement to state explicitly the steps
required to be taken to eliminate an identified risk cannot sensibly be said to
be satisfied by a requirement to design and implement measures to eliminate
that risk. There is no material difference between a measure and a step, or
between "eliminate" and "remove", or between "taken" and "design and
implement" in this context. In my judgment it is obvious as a matter of
language that a requirement to state explicitly the steps that must be taken to
13
remove an identified risk is not satisfied by a statement requiring the recipient
to take steps to remove the identified risk. If this is correct as a matter of
language I do not see how a requirement to design and implement measures to
eliminate the risk is any more compliant. Had the EA's position been that any
noise emanating from the Site as a result of regulated activity pursuant to the
Permit had to be eliminated then it might have been possible to say that a
provision to this effect was satisfactory because it required the elimination of
all noise. However, it is not the EA's case that this is what is required. Thus it
seems to me that as a matter of language, what is required for Schedule 2 to be
compliant with Regulation 37(4)(a)(ii) is the identification of either outcomes
or criteria that have to be achieved by whatever means EMR choose to adopt
and/or the identification of specific steps that are required to be taken.
40. The suspension notice was therefore a nullity and of no effect.
41. Unless the enforcing authority take real care when drafting notices they may not only
end up with egg on their face and an adverse costs bill, but the nuisance that they wish
to enforce against may go unchecked for some considerable time whilst the
ramifications of what might be no more than a drafting error are resolved.
42. However, the Courts will tend to attempt to save notices rather than strike them down.
43. In R. (on the application of Fullers Farming Ltd) v Milton Keynes Council ([2011]
EWHC 3784 (Admin)) the Administrative Court dismissed an appeal against the
serving of an abatement notice on grounds that it was defective for not specifying the
type of Statutory Nuisance alleged. The Appellant was a farming enterprise which
carried out fertilizing operations involving the spreading of chicken litter manure into
fields. Best practice would have been to plough in the chicken litter following the
spreading, but on one occasion the tractor which was to plough in the chicken litter
suffered a puncture rendering the operation unsuccessful. As a result, an odour arose
and the respondent local authority served an abatement notice under Part III of the
Environmental Protection Act 1990, having determined that the odour constituted a
statutory nuisance under s.79(1)(d). The Appellant appealed on the grounds that the
notice was defective as it failed to specify whether the statutory nuisance in question
was one which constituted by an odour being prejudicial to health or merely an odour
which was a nuisance.
14
44. The District Judge held that the notice was not defective and the Appellant appealed
to the Administrative Court. Wyn Williams J found that it was not necessary for an
abatement notice to set out precisely whether the nuisance alleged was one which was
prejudicial to health or a common-law nuisance, or both. There was a requirement
that the acts which constituted the statutory nuisance were sufficiently alleged so that
the person served with the notice knew what he was being required to do to abate the
nuisance. The District Judge had not erred in law in ruling that the abatement notice
was not required to set out which of the two forms of statutory nuisance in the form of
odour was alleged.
Abuse of process
45. The case of London Borough of Newham v John Knights (ABP) Limited is an
interesting case study in enforcement under the Environmental Permitting
Regulations. The company were prosecuted for alleged breaches of an environmental
permit and in particular the odour conditions. The company ran an abuse of process
argument that a Planning Inspector and not the Criminal Courts should consider
complex matters like BAT for odour control. The abuse argument was rejected. The
company was convicted and fined £120,000, plus £68,000 costs, plus compensation
orders of £250 each to affected residents. This is the largest fine yet obtained by a
local authority under the environmental permitting regime (the second largest being
the £75,000 imposed on the same company in February 2011).
Environmental Impact Assessment
46. EIA is an area that has generated a significant quantity of case law over recent
decades. It has continues to do so. The 2011 Directive merely codified matters, rather
than changing the litigation landscape. Whether a proposed amendment to the EIA
Directive will do anything to stem the flow of EIA litigation, as appears to be the
Commission’s aim, remains to be seen.
15
Test for EIA development
47. In R (Loader) v SSCLG and others [2012] 3 CMLR 29 the Court of Appeal has given
helpful guidance regarding the proper test for EIA to be applied at screening, and in
particular regarding the meaning of "significant effects on the environment" within
Art.2.1 of the Directive (85/337/EEC):
"Member States shall adopt all measures necessary to ensure that, before
consent is given, projects likely to have significant effects on the environment
by virtue, inter alia, of their nature, size or location are made subject to a
requirement for development consent and an assessment with regard to their
effects. Those projects are defined in Article 4".
48. The project in question was the redevelopment of a bowls club for 41 sheltered
apartments, along with a reconfigured bowling green. The Claimant/Appellant
challenged a negative Screening Direction under the old EIA Regs (the 1999 Regs),
but there is no difference between the Directive/1999 Regs and the codified 2011
Directive/2011 Regs relevant to the issue here. The Screening Direction was in fact
made after the proposal had already won permission once (on appeal) only for that
decision to be quashed and remitted to a different Inspector for redetermination.
49. The Claimant's complaint was that the Screening Direction approached "significant
effects" too narrowly, without due regard to the precautionary and preventative
principles enshrined in Art.191(2) of the Treaty, and in particular that the test of
"significance" should be that found in the Commission's 2001 Guidance on EIA
Screening, which suggests checklists for screening, as follows:
"Those responsible for making screening decisions often find difficulties in
defining what is "significant". A useful simply check is to ask whether the
effect is one that ought to be considered and to have an influence on the
development consent decision…"
50. On that basis, the Claimant advanced the following test:
"a significant environmental effect, as defined by the Directive, is one that has
a real prospect of influencing the outcome of the application for development
consent."
16
51. Plainly, this formulation placed a significant gloss on the language of Art.2.1 of the
Directive, and ran counter to a long line of domestic authority that the test is that
framed by Art.2.1, without gloss, and a matter for judgment of the competent
authority. The Claimant sought to buttress his argument by reference to the approach
taken to appropriate assessment under the Habitats Directive; see Waddenzee etc.
52. The Court of Appeal rejected the Claimant's formulation (Pill LJ suggesting at [46]
that such an approach would "devalue the entire concept") and affirmed that the test to
be applied is: "is this project likely to have significant effects on the environment?", a
matter of judgment for the competent authority having regard to the particular
circumstances and applying the criteria set out in the EIA Regulations, including
taking into account mitigation where sufficiently certain.
53. The Court of Appeal did emphasise, though, that the decision-maker must have regard
to the precautionary principle and the degree of uncertainty as to environmental
impact at the date of the decision. There would be some cases where the uncertainties
are such that a negative decision cannot be taken [44].
54. The same concepts appear elsewhere in environmental law, and it will be interesting
to see whether this fairly restrictive approach to those matters that require EIA will
bear on the approach to the new Aarhus costs regime.
55. In Champion v North Norfolk District Council & Natural England [2013] EWHC
1065, the Council had granted planning permission for the erection of two silos, a
lorry park and other development near a river designated as an SSI and an EU Special
Area of Conservation ("SAC"). The proximity of the river gave rise to a risk of
pollution, and the Council had carried out ecological and flood risk assessments and
consulted Natural England, which advised that there would not be a likely significant
effect on the river as a result of the grant of planning permission, and that no EIA or
Appropriate Assessment was therefore required. However the Council granted
planning permission subject to conditions requiring the water quality to be monitored,
which addressed the risk of pollution.
56. The Claimant challenged the grant of permission on the grounds that the Council's
decision was internally inconsistent and irrational. The imposition of conditions could
only be justified if there was a risk of pollution, and this conclusion could not be
17
reconciled with the decision that an EIA or Appropriate Assessment was not required.
The High Court agreed. It held that the Council could not rationally adopt both
positions at once, and that the decision should be quashed in order for the Council to
reconsider whether there was a relevant risk of pollution. If there was no such risk,
the Council could grant planning permission, but would not be entitled to impose the
conditions for the control of pollution. If there was such a risk, the Council would
have to require an Appropriate Assessment and an EIA.
Split projects
57. Three recent cases concerning splitting are of note. Generally speaking, the courts are
alive to attempts to "salami-slice" projects and will stamp down on those seeking to
avoid the requirements of the Directive by such means. Equally, the courts will not
force developers to undertake EIA of hypothetical or speculative add-ons to projects.
58. The first of the three cases is Bowen-West v SSCLG [2012] EWCA Civ 321 in which
Laws LJ held that the question whether an environmental statement for the deposit of
low level radioactive waste should have considered a larger scheme (a future
expansion of the landfill in question intended to be achieved by 2026) within the
context of "indirect, secondary or cumulative effects" (para.4 of Pt I of Sch.4 to the
1999 Regs) was an issue of fact and judgment. The Court rejected the Appellant's
contention that the question is one of law and declined to refer the matter to the ECJ.
It is understood that the Supreme Court has refused permission to appeal.
59. The second is R (Burridge) v Breckland DC [2013] EWCA Civ 228, in which the
Court of Appeal considered the screening opinion requirements of the 1999
Regulations in the context of a renewable energy facility application which had been
'split' into two sites. In the High Court, HHJ Waksman QC held that Regulation 7
required the authority to consider the "application before it" and that the
"development in question" referred only to the development in the individual
application. This decision was challenged in the Court of Appeal, on the basis that,
although this construction accorded with domestic principles of construction, a
broader purposive construction of the Regulations focusing on the proper 'project' was
required under Marleasing principles.
18
60. The Court of Appeal held that the domestic Regulations must be construed in light of
the purpose of the Directive's focus on projects, and this could require several
planning applications to be screened together. Having found that the planning
permissions in question had been granted in breach of the Regulations the Court was,
however, divided on how it should exercise its discretion, ultimately deciding to
refuse to quash on the facts following evidence from the planning officer after the fact
that the applications had been screened together. Permission to appeal has been
sought and it may be that the Supreme Court accepts to invitation to give further
guidance as to the principles to apply when exercising judicial discretion in EIA
cases.
61. The third case is Catt v Brighton and Hove City Council [2013] EWHC 977
(Admin), which will be familiar to practitioners from previous EIA challenges by the
same Claimant. Lindblom J dismissed the latest claims for judicial review of three
planning permissions granted by Brighton and Hove City Council, for development at
Withdean Stadium.
62. The main issue was whether, in screening the development under the EIA
Regulations, the Council had unlawfully split the project into sub-projects. The
Council conceded that its first screening opinion was flawed, but argued that its errors
in the first opinion had been remedied in a second opinion, in which it had considered
the impacts of the development as extended, and as a whole.
63. Rejecting the challenge, Lindblom J held in relation to this issue that there could be
no doubt that the second opinion screened not only the extension to the development,
but the development on the site in its extended form, as it would be as a result of the
proposals. It did not divide a long-term project into a series of temporary consents,
and it did not screen less than the full project [79]. It did not leave out consideration
of cumulative effects, but in considering the cumulative effects, it would have been
wrong to consider uses of the site that had ceased [80-81]. Equally, it had not erred
by limiting the screening exercise to the definite proposals for "Phase 1" of the
development, without also going on to screen provisional or possible options for
future development, which "were too uncertain, not only in their content and timing,
but also in their prospect of coming to fruition, to be regarded as part of the project."
[85-86].
19
Screening
64. EIA development is, of course, development that falls into either Sch.1 or Sch.2 of the
Town and Country Planning (Environmental Impact Assessment) Regulations 2011
(previously 1999). However, less well known is that the Secretary of State has power,
pursuant to Reg.4(8) of the EIA Regulations (now replaced by Regulation 4(9) of the
2011 Regulations), to subject an application for planning permission to EIA screening
even where it falls outside the criteria/thresholds set by Schedules 1 and 2.
Increasingly, objectors to development, including rival developers, are seeking to
challenge a refusal by the Secretary of State to exercise the Reg.4(8) power. R ((1)
Threadneedle (2) Zurich) v (1) Southwark LBC (2) Secretary of State, & ors [2012]
EWHC 855 (Admin) was one such case. The result was a clear judgment from
Lindblom J emphasising the discretionary nature of the Reg.4(8) power.
65. The development in question was student accommodation in Southwark. It fell
outside Sch.1 of the EIA Regulations and was well below the threshold for an urban
development project under Sch.2. The local planning authority, Southwark, had
consistently answered requests for a screening opinion with a "negative" screen, that
the development was not EIA development. Despite those conclusions, which as per
Berkeley v The Secretary of State [2002] EWCA Civ 1012 meant that the Council
need not go further, the Council had proceeded to consider whether, in fact and in
light of Sch.3 to the EIA Regulations, the development would have significant effects
upon the environment. It had concluded not.
66. The Claimants had an interest in a nearby site, which they wished to redevelop. They
argued that the index development would, cumulatively with other development
consented or proposed, have impacts upon daylight, historic London monuments and
key views across the capital. When the Secretary of State indicated that he was
considering called the planning application in for his consideration, they wrote to him
urging him to do so and arguing that if he did so he should exercise his power under
Reg.4(8) and screen. In fact, the Secretary of State decided not to call in, the
application remained with the Council and it proceeded to grant planning permission.
20
67. Faced with the Claimants' pre-action letter warning of judicial review, the Secretary of
State made plain that he had not even considered exercising his Reg.4(8) power, as
once the decision had been taken not to call the application in, the condition precedent
to the Claimants' request that he do so if he called the application in had not been met.
68. The key question for the Court was whether the Secretary of State erred in law by not
even considering whether to exercise his Reg.4(8) discretion.
69. Lindblom J noted that the Reg.4(8) power is, in effect, a power, reserved to the
Secretary of State alone, to deem a project EIA development even though it is not, and
in that sense plainly a power to make an exception to the normal operation of the
statutory regime under the EIA regulations. The effect of a Reg. 4(8) direction is to
require the submission and consideration of an environmental statement before the
decision-maker can lawfully grant planning permission, and such a direction "shall
determine for the purpose of [the EIA Regulations] whether development is or is not
EIA development".
70. The decision of the Court of Appeal in Berkeley v The Secretary of State for the
Environment, Transport and the Regions and another ("Berkeley (No.3)") [2002] 1 P.
& C.R. 265 (at paras. 47(5) and 49) was on point. There the Court of Appeal held that
the EIA Directive was appropriately transposed into domestic law by incorporating
into the EIA Regulations, in Sch. 2, thresholds and criteria by which to determine
whether a particular development is EIA development, leaving to the Secretary of
State the discretionary power to direct, under Reg. 4(8), that a particular development
is EIA development even though it does not qualify as such under either Sch. 1 or
Sch. 2. The decision also established that Reg.4(8) was not required for the adequate
transposition of the EIA Directive, but was permitted by it, as recognised by the first
instance judgment of Mr Duncan Ouseley QC, as he then was, sitting as a deputy
judge of the High Court in Berkeley (No.3) [2001] J.P.L. 660 (at para. 39), where he
noted that Reg. 4(8) is "not purely a domestic add on" and "should be seen and
construed as part of the United Kingdom's implementation of [the EIA Directive]"
(ibid., para. 40).
71. Building on that jurisprudence, the Judge identified four features of the Reg.4(8)
power "worth noting":
21
(1) Reg.4(8) is unlike others in the EIA Regulations in that no
procedure for it is prescribed (see paras. 37 and 38 of Collins
J's judgment in R (Baker v Bath and North East Somerset
Council [2009] EWHC 595 (Admin));
(2) the power may be used only by the Secretary of State (see
paras. 34 and 44 in the first instance judgment in Berkeley
(No.3));
(3) a decision not to exercise the power in regulation 4(8) will not
amount to a breach either of the EIA Directive or the EIA
regulations (see para. 39 of the judgment of the Court of
Appeal in Berkeley (No.3));
(4) there is no general obligation on the Secretary of State to
consider making a Reg.4(8) direction; such an obligation
would be inimical to the purpose of the EIA regulations in
providing thresholds and criteria (see paras. 37 and 46 of the
first instance judgment in Berkeley (No.3), and para. 45 of the
Court of Appeal's judgment).
72. The Judge also noted that the power is exceptional, as the procedure in Circular 02/99,
§77(b), where LPAs may "exceptionally" draw a particular development to the
attention of the Secretary of State, makes clear. The same was true of interested
parties. He saw force in the submission, for the Secretary of State, that he is,
ordinarily, only required to consider exercising his power in regulation 4(8) at the
instigation of a local planning authority, or a third party, if an express request to do so
is made to him, bringing to his attention a particular feature of the development that is
said to be likely to have a significant effect on the environment.
73. Whether or not it had been lawful for the Secretary of State not to consider his
Reg.4(8) power depended on the context. Here there had been no true request for him
to do so, given the conditional nature of the request. Nor had it been wrong of him, in
the absence of a true request, not to do so. The challenge failed.
74. In R (on the application of Holder) v Gedling Borough Council [2013] EWHC 1611
(Admin) (8 June 2013), the Claimant sought to challenge the lawfulness of a
22
screening opinion, on the grounds that the Council had erred in law and failed to
apply paragraph 44 of Circular 02/99, which stated that the thresholds set out in
Annex A of that Circular were not determinative of the question of whether an EIA
was required, but rather should be taken into account together with the general
guidance contained in that circular. In other words, the thresholds set out at Annex A
were an aid to, not a substitute for, analysis of the need for an EIA. The Claimant
contended that, on the face of the screening opinion, the Council's planning officer
had looked no further than the threshold, which she had used as a substitute for proper
analysis.
75. The court agreed that the natural reading of the opinion was that the threshold was
determinative of the analysis. However, the planning officer had provided a witness
statement in which she explained that she had, in fact, carried out the requisite
analysis. The court accepted this evidence, and the challenge therefore failed on the
facts. The court also noted that the Claimant had not sought to argue that the decision
that no EIA was required was itself legally flawed; and that such a submission would
be very difficult to sustain in light of the principles established in Loader v Secretary
of State for Communities and Local Government, referred to above.
Concept of 'consent'
76. In Case C-121/11 Pro-Braine ASBL and others v Commune de Braine-le-Chateau
(19 April 2012) the Third Chamber of the ECJ held that a definitive decision relating
to the carrying on of operations at an existing landfill site, taken on the basis of a
conditioning plan, pursuant to Article 14(b) of the Landfill Directive (1999/31), does
not constitute a 'consent' within the meaning of Article 1(2) of the EIA Directive
unless that decision authorises a change to or extension of that installation or site,
through works or interventions involving alterations to its physical aspect, which may
have significant adverse effects on the environment within the meaning of point 13 of
Annex II to the EIA Directive and thus constitute a 'project' within the meaning of
Article 1(2) of that Directive.
Definition of 'development'
23
77. In R (Save Woolley Valley Action Group Ltd) v Bath and North East Somerset
Council [2013] Env LR 8 Lang J found that the Council had erred in law in taking too
narrow an approach to the meaning of 'development' in relation to some poultry units.
On the basis of that error, the Council had not addressed itself to the question of
whether the units fell within the scope of the EIA Directive or Regulations. Lang J
found that the units were capable of coming under 'intensive livestock installation'
under the Regulations and, as such, should have been considered by the Council for
an EIA. Of particular interest in this case is Lang J's view (see [113]) that the EIA
Directive could only be effectively implemented in the UK if the definition of
'development' in section 55 of the TCPA was interpreted broadly, so as to include
projects which required an EIA under either the Directive or the Regulations.
78. In R. (on the application of Lyon) v Cambridge City Council [2012] EWHC 2684
(Admin) the claimant sought judicial of a decision to grant planning permission for
the demolition of an existing sports pavilion and the relocation and erection of a new
sports pavilion, together with a Protective Costs Order. It was argued that the
proposed development fell within the scope of the Town and Country Planning
(Environmental Impact Assessment) Regulations 2011 (S.I. 2011/1824) as it was a
Schedule 2 development likely to have significant effects on the environment by
virtue of factors such as its nature, size or location and the area of the development
exceeded 0.5 hectares. Accordingly, the Claimant argued that the Defendant local
planning authority's failure to carry out a screening opinion as required by Regulation
7 and Schedule 2, paragraph 10 (b) of the Regulations rendered the grant unlawful.
The Defendant refused to accept that the proposed sports pavilion was an "urban
development project" for the purposes of Sch.2; that even if it was there was no
reasonable basis for concluding that its construction would have significant effects
upon the environment; that, in any event, the area of the proposed development was
less than 0.5 hectares; and that even on the Claimant's own calculations the error, if
any, in calculating the area of the development was de minimis.
79. HHJ Birtles found that the demolition of the existing pavilion and the construction of
a new sports pavilion as described in the Planning Committee report could not amount
to an "urban development project". Schedule 2 paragraph 10 was headed
"infrastructure projects" and all of the developments listed in paragraph 10 (a)-(p)
24
were infrastructure projects. In any true meaning of the construction of the phrase
"infrastructure projects" the construction of a small sports pavilion on a small sports
pitch could not be classed as an infrastructure project. Paragraph 10(b) supported that
because the references were to "the construction of shopping centres and car parks,
sport stadiums, leisure centres and multiplex cinemas." The proposed development
was a far cry from a sports stadium or a leisure centre. If that was not correct, there
was the question of whether or not there was a reasonable basis for the Defendant
concluding that significant environmental effects were not likely. The Defendant had
taken the view that the development was not likely to have significant effects on the
environment by virtue of factors such as its nature, size or location, and had been
entitled to do so. The third issue was the area of the project. Schedule 2 Regulation
10(b) provided that the Regulations only bit if the area of the development exceeded
0.5 hectares. Although the Court of Appeal in R (on the application of Goodman and
Hedges) v London Borough of Lewisham ([2003] Env LR 28) had not specifically
addressed the issue of the correct approach for the court in deciding whether a
proposed development was an urban development project within the second criterion
of Schedule 2 paragraph 10(b) (i.e. the precise area), that seemed to be a matter of fact
and not a matter of interpretation of phrases in a piece of legislation. As such it was
only reviewable on traditional Wednesbury grounds. The Defendant's evidence was
compelling and it was not arguable that its decision on the issue had been unlawful.
Consultation
80. In R (Halebank Parish Council) v Halton Borough Council [2012] EWHC 1889
(Admin) HHJ Gilbart QC found that a decision not to extend a consultation period on
an environmental statement amounted to a breach of Article 6 of the EIA Directive
and a breach of a procedural legitimate expectation the Parish Council had as to the
conduct of the consultation process.
EIA and enforcement
81. R (Baker) v Bath and North East Somerset Council & Hinton Organics Ltd has
come before the court again, this time in relation to the issue of enforcement: see
25
[2013] EWHC 946 (Admin). Hinton Organics Ltd operates a waste-composting site.
The Claimant lives near the site. In a judgment dated 19 February 2009, Collins J
held that paragraph 13 of Schedule 2 of the 1999 EIA Regulations did not properly
implement applicable EU law, with the result that applications required to be
screened. This led to various planning permissions on the site being quashed, but
Hinton Organics continued to operate the site after this date. The Secretary of State
subsequently made positive screening directions and, accordingly, there were before
the Council three live applications for planning permission which would, if granted,
operate with retrospective effect. The purported environmental statement submitted
by Hinton Organics was inadequate and, fourteen months later, the Council decided to
grant a further three months to present a complete environmental statement. The issue
of whether an enforcement notice should be issued was therefore withdrawn from its
agenda.
82. The Claimant sought to challenge this decision by way of judicial review. The court,
in dismissing the claim, held that there was no duty on the authority under EU law
immediately to issue an enforcement notice in the circumstances. It noted that the
statements produced by Hinton Organics were "significantly deficient", and that it had
offered no real explanation, convincing or otherwise, for this failure. It considered
that by allowing Hinton Organics a further opportunity, the Council ran the risk of
acting inconsistently with established case law concerning its obligations under the
EIA Directive. However, notwithstanding these misgivings, the court concluded that
the authority had reached a fair, reasonable and proportionate decision on the relevant
issue. In particular, there was objectively a real probability that Hinton Organics
would produce a compliant environmental statement, notwithstanding past failures;
and the deadline set was not a lengthy one. Moreover "the issue of an enforcement
notice would not be likely to bring the unauthorised operations to an end, but would
be likely only to transfer the planning applications, supported by such environmental
statement, to the Secretary of State" [34]. The grant of retrospective planning
permission in respect of an EIA development was permissible if there were
exceptional circumstances, Ardagh Glass Ltd v Chester City Council [2010] EWCA
Civ 172, [2011] 1 All E.R. 476.
26
The role of inspectors
83. Judge Keyser QC has drawn attention to the limited role of Inspectors under
Regulation 9(2) of the 1999 EIA Regulations (now Regulation 12(2) of the 2011
Regulations) in Gregory v Welsh Ministers [2013] EWHC 63 (Admin).
84. If on a section 78 appeal there is a question as to whether the application is an EIA
application: (i) a negative screening opinion from the local planning authority is not
conclusive of the issue; and (ii) the Inspector's role is to ask himself whether the
application "may be" an EIA application; if he answers that in the affirmative he must
refer the question to the Secretary of State and has no jurisdiction to determine the
appeal (except by refusing planning permission) before he receives a screening
direction.
Proposed amendment to the EIA Directive
85. The EIA Directive has been in existence for over 25 years. It is considered by the
European Commission to be in need of a "comprehensive overhaul". On 26 October
2012 the Commission published a draft Directive proposing various amendments to
the current Directive (2011/92/EU). Amongst the amendments are a change to the
definition of "project" in Art 1 to make it clear that demolition works are included and
amending Art 2(3) to introduce an EIA "one-stop shop" to allow for the coordination
of assessment procedures under the EIA Directive and other EU legislation. The
Commission also proposes an amendment to Art 4 to streamline the screening
procedure and to seek to enhance the consistency of Member States' approaches to
ensure that EIAs are required only when it is clear that there are significant
environmental impacts.
86. Perhaps more important are proposals to ensure that alternatives are considered within
ESs (so moving EIA in line with SEA – though query whether the new text actually
achieves this) and provisions to ensure post-development monitoring of key
environmental effects.
87. Given that the new Directive is not expected to become law until March 2014, a more
extensive consideration is reserved for a future occasion.
27
SEA
Non-compulsory plans/programmes
88. In Inter-Environnement Bruxelles ASBL & Others v Région de Bruxelles-Capitale
(Case C‑567/10) the ECJ gave judgment in a case regarding the application of the
SEA Directive (2001/42) to procedures for the repeal of land use plans that were not
compulsory under national law. Proceedings were brought by Belgian NGOs alleging
that domestic law was incompatible with Directive 2001/42 in that it did not require
an environmental report to be drawn up for the total or partial repeal of the plans.
Whilst, formally, Article 2(a) of the directive related only to the adoption and
modification of land development plans, the applicants argued that, in order to
preserve its effectiveness, the directive had to be interpreted as also applying to the
repeal of those plans. In the present case, repeal of a specific land use plan modified
the context in which planning permissions were issued and were liable to amend the
framework for consents issued for future projects. The applicants also argued that
‘plans and programmes’ within the meaning of Article 2(a) were, generally, those
provided for by national legislative or regulatory provisions and not only those whose
adoption was compulsory under those provisions. They submitted that it would not be
consistent with the objective and practical effect of the directive to exclude from its
scope a repealing measure whose adoption, although optional, had taken place. The
Constitutional Court referred two questions to the ECJ:
“(1) Must the definition of ‘plans and programmes’ in Article 2(a) of
Directive 2001/42 … be interpreted as excluding from the scope of that
directive a procedure for the total or partial repeal of a plan such as that
applicable to a specific land use plan, provided for in [the domestic
provisions]?; and
(2) Must the word ‘required’ in Article 2(a) of that directive be understood
as excluding from the definition of ‘plans and programmes’ plans which are
provided for by legislative provisions but the adoption of which is not
compulsory, such as the specific land use plans referred to in [the domestic
provisions]?”
28
89. The court found that plans and programmes whose adoption was regulated by national
legislative or regulatory provisions, which determined the competent authorities for
adopting them and the procedure for preparing them, had to be regarded as ‘required’
within the meaning, and for the application, of Directive 2001/42. Accordingly, they
had to be subject to an assessment of their environmental effects as laid down in the
directive. It followed that the answer to the second question was that the concept of
plans and programmes ‘which are required by legislative, regulatory or administrative
provisions’, appearing in Article 2(a) of Directive 2001/42, included specific land
development plans, such as the one covered by the national legislation at issue in the
main proceedings. On the first question, the directive referred expressly only to
measures modifying plans and programmes, and not to repealing measures. Given its
objective of providing for a high level of protection of the environment, however, the
provisions which delimited the directive’s scope, in particular those setting out the
definitions of the measures envisaged by the directive, had to be interpreted broadly.
It was possible that the partial or total repeal of a plan or programme was likely to
have significant effects on the environment, since it may involve a modification of the
planning envisaged in the territories concerned. Thus, a repealing measure may give
rise to significant effects on the environment because such a measure necessarily
entailed a modification of the legal reference framework and consequently altered the
environmental effects which had been assessed under the procedure prescribed by
Directive 2001/42.
90. Inasmuch as the repeal of a plan or programme may modify the state of the
environment as examined at the time of adoption of the measure which was to be
repealed, it had to be taken into consideration with a view to scrutiny of the
subsequent effects that it might have on the environment. Accordingly, Article 2(a)
had to be interpreted as meaning that a procedure for the total or partial repeal of a
land use plan, such as the procedure laid down in the domestic provisions, fell in
principle within the scope of the directive, so that it was subject to the rules relating to
the assessment of effects on the environment laid down. In principle, that was not the
case if the repealed measure fell within a hierarchy of town and country planning
measures, as long as those measures laid down sufficiently precise rules governing
land use, they had themselves been the subject of an assessment of their
environmental effects, and it might reasonably be considered that the interests which
29
the directive was designed to protect had been taken into account sufficiently within
that framework.
91. For a domestic application, see Wakil.
Habitats
Adverse effects
92. In Case C-258/11 Sweetman v An Bord Pleanála , the Court of Justice responded to
a request from the Irish Supreme Court for a preliminary ruling on the interpretation
of Article 6 of the Council Directive 92/43/EEC (the Habitats Directive).
93. The underlying dispute concerned An Bord Pleanála’s grant of a development consent
on 20 November 2008 for the N6 Galway Bypass. The road scheme involves the
permanent loss within the Lough Corrib SCI of approximately 1.47 hectare of karstic
limestone pavement which is a priority habitat type referred to in Annexe 1 to the
Directive. The Lough Corrib was not formally designated as a SCI until after the
decision at issue but under National Law, the An Bord Pleanála was required to apply
equivalent legal protections to those under Article 6 (2) of the Habitats Directive to
the site from 2006 onwards. An Bord Pleanála had concluded that the proposed
development would not adversely affect the integrity of this candidate special Area of
Conservation.
94. Mr Sweetman applied to the High Court seeking judicial review of the grant of the
consent on the grounds that An Bord Pleanála had erred in its interpretation of Article
6 of the Habitats Directive in reaching this conclusion. At first instance he was
unsuccessful but was granted permission to appeal before the Supreme Court. The
Supreme Court sought clarification as to the circumstances in which, where an
appropriate assessment of a plan or project is carried out pursuant to Article 6(3) of
the Habitats Directive, such a plan or project is likely to have ‘an adverse effect on the
integrity of the site’. The Supreme Court stated that the judgment in Case C 127/02
Waddenvereniging and Vogelbeschermingsvereniging [2004] ECR I 7405 had not
fully dispelled its doubts.
95. The Court dealt with the questions referred together noting that in essence the
Supreme Court was asking whether Article 6(3) of the Habitats Directive must be
30
interpreted as meaning that in a situation such as that in the main proceedings a plan
or project not directly connected with or necessary to the management of a site
adversely affects the integrity of that site and further, that the referring court sought
clarification as to the possible effect of the precautionary principle and the question of
the relationship between Article 6(3) and Article 6(4) of the Habitats Directive for the
purposes of that interpretation.
96. The Court reiterated that Article 6(3) of the Habitats Directive establishes an
assessment procedure intended to ensure, by means of a prior examination, that a plan
or project not directly connected with or necessary to the management of the site
concerned but likely to have a significant effect on it is authorised only to the extent
that it will not adversely affect the integrity of that site. This procedure comprises two
stages - (i) the assessment and (ii) the consideration of whether there are adverse
effects. In appraising the scope of the expression ‘adversely affect the integrity of the
site’ in its overall context, the provisions of Article 6 of the Habitats Directive must
be construed as a coherent whole in the light of the conservation objectives pursued
by the directive.
97. Article 6(2) to (4) of the Habitats Directive impose upon the Member States a series
of specific obligations and procedures designed, as is clear from Article 2(2) of the
directive, to maintain, or as the case may be restore, at a favourable conservation
status natural habitats and, in particular, special areas of conservation. Article 1(e) of
the Habitats Directive establishes that the conservation status of a natural habitat is
taken as ‘favourable’ when, in particular, its natural range and areas it covers within
that range are stable or increasing and the specific structure and functions which are
necessary for its long-term maintenance exist and are likely to continue to exist for the
foreseeable future. The Habitats Directive has the aim that the Member States take
appropriate protective measures to preserve the ecological characteristics of sites
which host natural habitat types (see Case C 308/08 Commission v Spain [2010] ECR
I 4281, paragraph 21, and Case C 404/09 Commission v Spain, paragraph 163).
Consequently, it should be inferred that in order for the integrity of a site as a natural
habitat not to be adversely affected for the purposes of the second sentence of Article
6(3) of the Habitats Directive the site needs to be preserved at a favourable
conservation status; this entails the lasting preservation of the constitutive
31
characteristics of the site concerned that are connected to the presence of a natural
habitat type whose preservation was the objective justifying the designation of that
site in the list of SCIs, in accordance with the directive.
98. Authorisation for a plan or project, as referred to in Article 6(3) of the Habitats
Directive, may therefore be given only on condition that the competent authorities –
once all aspects of the plan or project have been identified which can, by themselves
or in combination with other plans or projects, affect the conservation objectives of
the site concerned, and in the light of the best scientific knowledge in the field – are
certain that the plan or project will not have lasting adverse effects on the integrity of
that site. That is so where no reasonable scientific doubt remains as to the absence of
such effects: Case C 404/09 Commission v Spain, paragraph 99, and Solvay and
Others, paragraph 67. Since the authority must refuse to authorise the plan or project
being considered where uncertainty remains as to the absence of adverse effects on
the integrity of the site, the authorisation criterion laid down in the second sentence of
Article 6(3) of the Habitats Directive integrates the precautionary principle and makes
it possible to prevent in an effective manner adverse effects on the integrity of
protected sites as a result of the plans or projects being considered. A less stringent
authorisation criterion than that in question could not ensure as effectively the
fulfilment of the objective of site protection intended under that provision:
Waddenvereniging and Vogelbeschermingsvereniging, paragraphs 57 and 58.
99. The assessment under Article 6(3) cannot have lacunae and must contain complete,
precise and definitive findings and conclusions capable of removing all reasonable
scientific doubt as to the effects of the works proposed on the protected site
concerned. It is for the national court to establish whether the assessment of the
implications for the site meets these requirements.
100. Accordingly the Court concluded that Article 6(3) of the Habitats Directive must be
interpreted as meaning that a plan or project not directly connected with or necessary
to the management of a site will adversely affect the integrity of that site if it is liable
to prevent the lasting preservation of the constitutive characteristics of the site that are
connected to the presence of a priority natural habitat whose conservation was the
objective justifying the designation of the site in the list of SCIs, in accordance with
the directive. The precautionary principle should be applied for the purposes of that
32
appraisal. If the competent authority “concludes that the plan or project will lead to
the irreparable loss of the whole or part of a priority natural habitat type whose
conservation was the objective that justified the designation of the site… the view
should be taken that such a plan or project will adversely affect the integrity of the
site” [47]”.
Duties of planning authorities
101. In R (on the application of Prideaux) v Buckinghamshire County Council [2013]
EWHC 1054 and R (Kolb) v Buckinghamshire County Council [2013] EWHC 1055,
Lindblom J considered two judicial review claims against Buckinghamshire County
Council’s grant of planning permission for the construction of an energy from waste
facility, to treat up to 300,000 tonnes of residual waste each year. The first claim was
brought on three grounds, namely (i) whether the Council had complied with its duties
in respect of European Protected Species (namely bats and great crested newts); (ii)
whether the Council unlawfully failed to apply relevant national policy on nature
conservation in the NPPF; (iii) whether the Council had failed to provide adequate
reasons. The second claim was brought by Mr Kolb as a litigant-in-person, and
focused on the way in which the Council had considered flood risk.
102. Lindblom J dismissed both claims, but his reasoning in relation to the first ground in
Prideaux is of particular significance. He found that the Council had “discharged its
duty under regulation 9(5) in this case with no less rigour than was required to comply
with the approach indicated by the Supreme Court in Morge. It did at least as much
as it had to do to satisfy itself that the necessary derogations were not unlikely to be
licensed”. He held that the relevant legal duty on the planning authority was that set
out in Morge v Hampshire County Council [2011] UKSC 2, namely to have regard to
the requirements of the Habitats Directive so far as those requirements may be
affected by the decision whether or not to grant a planning permission, and that the
more onerous test established by HHJ Waksman QC in (Woolley) v Cheshire East
Borough Council [2010] Env LR 5 could no longer be regarded as good law5.
5 See paragraph 27 of that judgment
33
103. The court also considered what was meant by the phrase “no satisfactory alternatives”
in the test to be applied for licensing derogations from the Habitats Directive. It held
that there was no requirement to undertake a comparative assessment of the possible
effects of each suggested alternative on the European Protected Species. Moreover
Article 16 of the Habitats Directive “does not provide that a licence must be refused if
an alternative emerges with no foreseeable impact on European Protected Species, or
an impact less harmful than that of the project in hand”, and the suggestion that an
alternative could only be regarded as satisfactory when that was so was incorrect. He
concluded that:
“113…To be satisfactory an alternative has to be a real option, not merely a
theoretical one. When planning permission for it would likely be refused
because, for instance, it would strain the capacity of local roads, or disturb
people in their homes, or mar the setting of a listed building, or harm flora or
fauna important in a Site of Special Scientific Interest, it may well be
reasonable to dismiss it as a “satisfactory alternative”. Without the planning
permission it would require a hypothetical option of that kind would not be a
real alternative; it could not meet the identified need.
114. Judging what is, or may be, a satisfactory alternative in a particular case
requires a focus on what is sought to be achieved through the derogation, and
on the likely effects of the works on the species in question.”
Multiple authorities
104. The Court of Appeal has given practical guidance upon division of responsibility for
appropriate assessment under the Habitats Directive (92/443/EEC) and the domestic
implementing regulations, the Habitats and Species Regulations 2010 (“the Habitats
Regulations”), when a plan or project requires a permission, consent or authorisation
from multiple competent authorities, each with responsibilities under Reg.61 of the
Habitats Regulations. A classic case is when a project requires both a planning
consent, either from the local planning authority or, if the application is called in, the
Secretary of State, and also an environmental permit from the Environment Agency.
34
105. That was the position in Cornwall Waste Forum St Dennis Branch v (1) Secretary of
State (2) SITA Cornwall Ltd [2012] EWCA Civ 379, where the project in question
was a waste power plant located near St Austell in the vicinity of two Special Areas of
Conservation and the applicant, SITA Cornwall Ltd, applied for planning permission
and an environmental permit in parallel. Regulation 65, dealing with co-ordination
where more than one competent authority is involved, explains at (2) that nothing in
Reg.61(1) requires a competent authority “to assess any implications of a plan or
project which would be more appropriately assessed under that provision by another
competent authority.”
106. The Environment Agency issued a draft permit some time before the planning
application reached the Secretary of State’s appointed Inspector, the Secretary of State
having recovered the application for his determination. However, prior to the
planning inquiry the Planning Inspectorate advised objectors, including both the
Cornwall Waste Forum St Dennis Branch, that the Inspector would, if he considered
the Reg.61 threshold test met, himself carry out an appropriate assessment of the
project and advise the Secretary of State accordingly. Hence the objectors aimed their
fire regarding appropriate assessment at the Inspector, not the Environment Agency.
In particular, before the Inspector they criticised the Agency’s approach to the so-
called “1% rule”: that is, that if the long term “process contribution” for a pollutant is
less than 1% of the relevant Air Quality Standard, its effects are deemed
“insignificant” (see Environmental Permit para A3.1(ii)). Both the Forum and the
County Council argued at the inquiry that the “1% rule” should not be applied where
pollution levels were already substantially above the “critical load”.
107. During the course of the Inquiry concessions made by the County Council’s witnesses
in relation to water quality, hydrology, dust and traffic emissions, led to the position
whereby the only impacts requiring appropriate assessment were those pertaining to
air quality due to emissions from the stack. Those were matters that would be
controlled by the permitting regime operated by the Environment Agency rather than
the development control regime operated by the local planning authority/the Secretary
of State, and hence the Inspector considered it right to rely upon the Agency’s
appropriate assessment. That was after the Agency had issued a final permit. The
35
Secretary of State adopted his Inspector’s position, and deferred to the Agency’s
appropriate assessment. He granted planning permission.
108. The Forum’s challenge succeeded at first instance before Collins J, largely on the
basis of breach of a procedural legitimate expectation that the Secretary of State
himself would act as competent authority and conduct an appropriate assessment, not
defer to the Environment Agency, thus denying the Forum the opportunity to take
“arguable” points against the 1% rule with the Agency.
109. The Court of Appeal allowed the Secretary of State’s appeal and restored the planning
permission. Carnwath LJ, gave the lead and only judgment. He noted, firstly, that the
competent authority was the Secretary of State, not the Planning Inspector nor the
Inspector, neither of whom had authority to give a commitment that the Secretary of
State would conduct a Reg.61 appropriate assessment. Secondly, that circumstances
had changed since the Planning Inspectorate’s pre-inquiry representation. Thirdly,
and most importantly, that in the context of this planning appeal the debate about
responsibility under the Habitats Directive was in itself of no practical significance.
That was because whether or not the Secretary of State remained the decision-maker
for the purposes of the Habitats Directive, he could not avoid responsibility for the
planning decision, one aspect of which, as he recognised, was whether there would be
“harm to acknowledged nature conservation interests”. On the facts of this case the
two issues were inextricably linked. By the same token, in so far as the possibility of
harm to those interests arose from stack emissions, he was entitled – in either capacity
– to be guided by the expertise of the relevant specialist agencies, the Environment
Agency and Natural England. It would be only if their guidance was shown to be
flawed in some material way that his own decision, relying on that guidance, would
become open to challenge for the same reason.
110. The Forum had made no submission that the Agency’s approach to the 1% rule was
legally flawed. Hence there was no true case made against the only substantive
criticism of the Secretary of State’s decision, namely his reliance, through the
Agency, on the 1% rule as a test of “significance” under the Directive.
Appropriate assessment and material considerations
36
111. The Court of Appeal has rejected an application for judicial review relating to impacts
on the Carmarthen Bay European Marine Site. In R (on the application of Hughes) v
Carmarthenshire County Council & Others ([2012] EWCA Civ 1509), the Claimant
was a licensed cocklepicker and chair of the Llanelli Cocklepickers Association,
which was concerned about cockle mortality in Carmarthen Bay. The area comprised
the Carmarthen Bay and Estuary Special Area of Conservation, Carmarthen Bay
Special Protection Area and the Burry Inlet Special Protection Area and Ramsar Site.
Those sites were often collectively referred to as the “European Site”. The Claimant
sought to challenge the grant of reserved matters approval for two substantial
residential developments. He was concerned that the water quality in the bay would
be adversely affected by the drainage from the two developments. It was common
ground that an ‘appropriate assessment’ had to be carried out for each development in
accordance with the requirements of the Habitats Directive (92/43) before the
approval of reserved matters could lawfully be granted. It was also common ground
that in each case an appropriate assessment was carried out and published before
reserved matters approval was granted. The Claimant argued that the appropriate
assessments were not lawful because the Defendant County Council had: a) failed to
have regard to a material consideration, namely the views of the Environment Agency
for Wales, in particular as those views were expressed in its ‘Review of Consents’;
and b) had regard to an irrelevant consideration, namely certain “infrastructure
works”, which were relied upon as mitigating the impact of the drainage from the two
developments.
112. All of the relevant statutory bodies, the Environment Agency for Wales, the
Countryside Council for Wales, the County Council, Cardiff City Council and Welsh
Water, had reached a consensus in a non-binding Memorandum of Understanding in
February 2010. As part of the Memorandum, the Environment Agency was
undertaking a Review of [Discharge] Consents. As an interim measure, the local
councils were funding nutrient removal processes at treatment works, in order to free
up capacity for new residential property developments (including those the subject of
the judicial review application). The claimant argued that the Review of Consents cast
doubt on the Memorandum of Understanding because of nutrient contamination of the
Bay from agricultural run offs elsewhere. The Environment Agency had not
challenged the lawfulness of the reserved matters approvals. On the second ground,
37
the claimant argued that in undertaking the appropriate assessment the council was
required to consider the impact of the projects, the two housing developments, and in
doing that the County Council could not ‘trade off’ the beneficial effects of the
“infrastructure works” because they were not part of the projects in question. When
considering the question of cumulative impact of the projects when combined with
others, the County Council could not “pick off” some beneficial works and then
ignore the wider picture: that the integrity on the site had not been achieved and more
works were needed in order to achieve this.
113. Lord Justice Sullivan (with whom Lord Justice Patten and Sir David Keene agreed)
noted that the Environment Agency had written to the claimant but that nothing in that
letter suggested that, for the purposes of the appropriate assessments, its Review of
Consents added anything material to the consensus which had been reached in the
Memorandum of Understanding to which it was a party. Nor did it suggest that the
appropriate assessments failed to consider any material factor that it might have
wished to have been considered from its point of view. Nothing in the Review of
Consents had affected the consensus in the Memorandum. A revised Memorandum
had been published after the Review of Consents which had reaffirmed the position
regarding scope for additional residential development. There was no substance
whatsoever in the first limb of the claimant’s challenge to the appropriate
assessments. The “infrastructure works” that were the subject of the second ground
had been completed before the appropriate assessments were published. It would
make it much more difficult, if not impossible to release the 2000 new dwellings,
which all of the relevant statutory authorities had agreed could be accommodated
without having an adverse effect on the bay because of the infrastructure works that
had been undertaken, until such time as the water quality of the bay had been
improved by further measures to deal with other sources of pollution such as
agricultural run-off, because site integrity would not have been achieved until those
further measures have been implemented. The Directive did not compel such an
unrealistic conclusion. In effect, it treated a failure to contribute to a wider
improvement in environmental quality as an adverse impact on environmental quality.
Article 64 of the Directive was concerned with the consideration on review of existing
consents and not with the granting of new consents, but Article 64(3) indicated the
common sense approach:
38
“ The decision, or the consent, permission or other authorisation, may be
affirmed if it appears to the competent authority reviewing it that other action
taken or to be taken by them, or by another authority, will secure that the plan
or project does not adversely affect the integrity of the site.”
114. Looking at the matter through the prism of that paragraph, an action had been taken
and infrastructure works provided by Welsh Water were in operation. All the relevant
statutory authorities were agreed that, given the existence of those works, the two
housing developments would not adversely affect the current nutrient status of the
bay. The fact that it was an objective to improve that status and the two developments
would not contribute to that improvement did not mean that they would have an
adverse effect on the integrity of the European site. For those reasons, the claims for
judicial review would be dismissed.
IROPI
115. Elliott v SSCLG [2013] EWCA Civ 703 concerned a challenge to the proposed
“makeover” of Crystal Palace Park. There were five grounds of challenge, the fourth
of which concerned bats and raised issues relating to “imperative reasons of
overriding public interest” for the purposes of Regulation 62 of the Habitats
Regulations. The Inspector had raised an issue as to whether the planned makeover
might constitute IROPI but had not decided the point. The SSCLG did not spell out
that he had considered IROPI but Keith J held that he must have done so. The point
of wider interest in the case concerns Keith J’s assessment of the Claimant’s
contention that the need to raise funds for a development could not as a matter of
Community law constitute exceptional circumstances forming the basis of an IROPI.
116. At first instance, Keith J noted the passage in Solvay v Region Wallonne (C-182/10)
where the ECJ stated at [76]-[77] that “[w]orks intended for the location or expansion
of an undertaking [will] only in exceptional circumstances” satisfy the condition that
the development “must be of such importance that it can be weighed up against [the]
directive’s objective of the conservation of natural habitats …”. But he went on to
find that:
39
“you cannot get from that that if a particular feature of a set of proposals was
included only because it would provide some of the funding for the
development as a whole, and if it happened to be that aspect of the
development which would have an impact on the conservation of natural
habitats, there cannot have been imperative reasons of overriding public
interest for permitting the development”.
117. The Claimant therefore failed on the habitats ground and also failed on the other
grounds. The Court of Appeal dismissed the appeal, Laws LJ giving the lead
judgment upholding Keith J on all points.
Waste
Deposit
118. In R (Thames Water Utilities Ltd) v Bromley Magistrates' Court and The
Environment Agency [2013] EWHC 472 (Admin), a two-judge Administrative Court
(Gross LJ and Singh J) dismissed Thames Water's application for judicial review of
the decision of Bromley Magistrates' Court (District Judge Lynch), that unintentional
escapes of sewage from Thames Water's system in 2003 amounted to "deposits" for
the purposes of s.33(1)(a) of the EPA 1990.
119. The Court (Gross LJ giving the lead judgment, with which Singh J agreed) found that
the word "deposit" in ss.33(1)(a) was to be given its ordinary meaning, which
meaning included unintentional escapes, and that this conclusion was supported by
the statutory scheme as a whole.
120. Though the case concerned unintentional escapes of sewage, it is of general
application to all "deposits" for the purposes of s.33(1)(a).
121. The underlying facts concerned a number of occasions between February and April
2003, when sewage escaped from Thames Water's system onto land in the London
Borough of Bromley. The land included residential properties, allotments and the
public highway. The EA brought criminal proceedings in 2004, which included
charges that by the escapes Thames Water had contravened s.33(1)(a) EPA. Thames
Water was eventually convicted, after the question of whether the sewage that had
escaped from its system was "controlled waste" had been to both the CJEU and the
40
Court of Appeal. Thames Water was convicted by the District Judge primarily on the
basis that "deposit" was an ordinary English word, apt to include unintentional as well
as intentional acts, and that the s.33(7) defence further supported that conclusion.
122. It is worth remembering that ss.33 and 34 of the EPA provide, so far as material, that:
33.(1) ….a person shall not -(a) deposit controlled waste, or knowingly cause
or knowingly permit controlled waste to be deposited in or on any land unless
a waste management licence authorising the deposit is in force and the deposit
is in accordance with the licence;
[contravention of s.33(1) is an offence]
(7) It shall be a defence for a person charged with an offence under this
section to prove
-(a) that he took all reasonable precautions and exercised all due diligence to
avoid the commission of the offence
34. (1) ….it shall be the duty of any person who imports, produces, carries,
keeps, treats or disposes of controlled waste or, as a broker, has control of
such waste, to take all such measures applicable to him in that capacity as are
reasonable in the circumstances –
(a) to prevent any contravention by any other person of section 33 above;
……
(b) to prevent the escape of the waste from his control or that of any other
person; ….
123. The Court's focus was, of course, on the "first limb" of s.33(1)(a), it being assumed
that Thames Water had neither known nor intended the escapes of sewage to occur.
124. In finding against Thames Water, and giving s.33(1)(a) the broader interpretation
contended for by the EA and found by the District Judge below, the Administrative
Court considered first the ordinary English meaning of the word "deposit", agreeing
with the District Judge that this was "put, place(d) or set down", and then found that a
construction by reference to ordinary usage was appropriate. Hence the test for the
41
Court was "whether an unintended escape falls within a reasonable range of meanings
for "deposit" ". It had no real difficulty in finding that it did, basing its judgement on
the following: the striking contrast between the first "limb" of s.33(1)(a), which
contains no requirement of "knowledge", and the second and third "limbs", which do;
and the existence of the statutory defence of due diligence pursuant to s.33(7), which
would ameliorate the potential harshness of an offence of strict liability that required
no mens rea.
125. The Court rejected Thames Water's contentions that the existence of s.34 was proof
that s.33 applied only to "intentional" deposits, else the EA would be free to prefer the
more serious s.33 offence and cast the burden of proof on the defendant. The answer
to that contention was straightforward on the present facts; s.34 had no application,
because the sewage was not "controlled" waste until it had escaped the system, as up
until that point it was within the provisions of the Urban Waste Water Directive
(91/271/EEC) and so outside the Waste Directive (75/442/EEC) as "already covered
by other legislation". As the EA put it "that which was in the pipes was not controlled
waste; once it had escaped, it was not in the control of Thames" and so, on the present
facts, s.34 had "no scope…to bite".
126. Whilst the Court's reasons for rejecting Thames Water's reliance upon the existence of
s.34 seem well-founded on the facts before it, the potential difficulty is that its
conclusion that a "deposit" for the purposes of s.33(1)(a) can include an unintentional
escape is of general application, not limited to escapes from a sewerage system
governed by its own particular statutory regime. It rejected Thames Water's example
of a shopper who trips, falls and in the process "deposits" the contents of their
shopping bag as having little force, on the basis that the s.33(7) defence would be
available and that prosecutors and the courts would see to it that such unwarranted
cases would not be pursued. However, there will doubtless be other, more pertinent,
examples thrown up on the inevitably unpredictable canvas humanity paints, where
the force of this judgment will be felt most acutely.
Scope of duty of care
42
127. The Administrative Court has provided guidance on the scope of the Duty of Care for
Waste imposed by virtue of section 34 of the Environmental Protection Act 1990. See
Mountpace Ltd v Haringey London Borough Council [2012] EWHC 698 (Admin).
Transfrontier shipment of waste
128. R v Ezeemo [2012] EWCA Crim 2064, saw the Court of Appeal consider the
Transfrontier Shipment of Waste regime6 for the third time7 in 12 months. The cases
before the Court arose from the large scale high profile prosecutions by the Agency in
relation to the shipping of televisions and paper to Africa and South Korea. Whilst
the prosecutions have been hugely expensive for the Agency and the fines low, the
Agency will no doubt be satisfied that all Defendants pleaded guilty or changed their
plea over the course of 18 months as the Court of Appeal successively rejected their
defences.
129. In short, the three cases establish the following about the regime: 1) the criminal
offence of transporting hazardous waste to a country that is not a member of the
OECD is one of strict liability and is not ultra vires the EU parent Regulation or
disproportionate. 2) Art 36 of the EU Reg (exports for recovery to non OECD
countries is prohibited ) contains 2 simple but key concepts a) waste must be destined
for recovery b) export is the action of waste leaving the EU. 3) Waste can be destined
for foreign parts long before it gets anywhere near the English/Welsh docks but it is a
question of fact to determine when it is ‘destined’ for another country. 4) The breadth
of activities caught by the regime is wide – anyone involved in the transport of waste
(by road, rail, sea) from point of origin where waste is collected/stored to the point it
is delivered to the foreign country. 5) Whether household waste has become paper
waste is a question of fact for the jury. There appears to be a de minimis threshold for
‘contamination’ by other materials but this is a question of fact (but the CA thought
the EA should produce guidance).
6 EU Regulation 1013/2006 and UK TFS Regulations (2007) 7 The other cases are KV & Othrs v R [2011] EWCA Crim 2342 and R v Ideal Paper Co
[2011] EWCA Crim 3237
43
Environmental judicial review
Intensity of review
130. The courts have tended to adopt a relatively deferential approach to environmental
decision makers like the Environment Agency and Natural England, interfering only
where the decision-maker can be shown to have acted irrationally in the traditional
Wednesbury sense. However Lang J in R (Manchester Ship Canal Co Ltd & Peel
Holdings Ltd) v Environment Agency [2012] EWHC 1643 took an interventionist
approach to the interpretation of the Environment Agency’s flood defence policies
and the Court of Appeal has recently dismissed the EA’s appeal; [2013] EWCA Civ
542. By categorising sluices along the Manchester Ship Canal as formal flood
defences for the purpose of assessing flood risk, the EA had misunderstood and
misconstrued its own policies.
131. For the moment, this can be viewed as nothing more than an application of the (new)
approach to policy interpretation laid down in Tesco v Dundee.
Discretion
132. Berkeley v Sec of State remains the high point for claimants seeking to argue that the
Court has no discretion not to quash a defective environmental decision. Lord
Carnwath has however been mounting a steady campaign to limit its boundaries, the
latest expression of which is in Walton v The Scottish Ministers [2012] UKSC 44 at
[124]-[140]. The domestic courts are to balance the principle of ‘effectiveness’ in
exercising rights under European law with the practical effect of any breach and the
public interest, Lord Carnwath finding (at [139]):
“Where the court is satisfied that the applicant has been able in practice to
enjoy the rights conferred by the European legislation, and where a procedural
challenge would fail under domestic law because the breach has caused no
substantial prejudice, I see nothing in principle or authority to require the
courts to adopt a different approach merely because the procedural
requirement arises from a European rather than a domestic source.”
133. This may provide the basis for the exercise of greater discretion in granting remedies
than has been apparent over the last decade or so.
44
Promptness
134. It has been a central requirement of judicial review that a claim should be filed
promptly and in any event not later than 3 months after the grounds to make the claim
first arose. So far as decisions under the planning acts from 1st July 2013 are
concerned, that position has now been altered by CPR Rule 54.5(5) and (6), which
replaces the “within three months and in any event promptly” time limit with a
straight six weeks. However, there will still be environmental JR claims where the
ordinary rule applies.
135. Following C-406/08 Uniplex; R. (Buglife) v Medway Council and R (U & Partners
(East Anglia) Ltd) v The Broads Authority, it is clear that promptness is disapplied in
environmental cases which raise EU law. However, the Court of Appeal’s decision in
Berky v Newport City Council [2012] EWCA Civ 378 is now the leading case in the
domestic context.
136. The Claimant in Berky sought judicial review of a grant of planning permission for a
supermarket on the basis of inadequate reasoning in EIA screening, bias and
irrationality, but failed at the first hurdle; promptness. On appeal from refusal of
permission, the Court of Appeal gave obiter but extensive consideration to the
question of whether or not Uniplex and legal certainty applied not only to excluded
promptness from the EIA ground but also the “domestic” grounds, and further
whether s.31(6) of the Senior Courts Act 1981 might allow refusal of relief on
grounds of delay even if Uniplex barred reliance on a lack of promptitude. Their
Lordships gave three differing opinions on the subject. A majority felt that s.31(6)
would offend the principle of legal certainty just as much as the promptness
requirement, but equally the Court was happy to countenance a differing approach to
domestic as opposed to EU grounds.
137. It remains to be seen how long it remains the position that there are different timing
requirements for making a claim according to whether the claim raises matters of EU
law or not.
Consultation
45
138. R (Friends of the Earth, Homesun, Solar Century & Others) v Secretary of State for
Energy and Climate Change [2012] EWCA Civ 28, is authority for the proposition
that, exceptionally, a challenge to a potential decision can be brought during a
consultation period on the decision. The proposed change of position there would
have affected vested rights to feed-in-tariffs for small scale renewables and done so
retrospectively from their implementation, contrary to the scheme of the enabling act.
The Court of Appeal readily upheld Mitting J at first instance and struck down the
consultation. The case turned more on principles of general application than anything
specific to environmental law, but is perhaps another example of judicial willingness
to engage with a challenge because it touches environmental issues, so of interest to
all, rather than particularly individual interests.
139. In this context, note the Ministry of Justice Consultation Paper entitled “Judicial
Review Proposals for Reform” Ministry of Justice, Consultation Paper CP25/2012.
Administrative decision making and expert evidence and reasons
140. Inspectors, who are experts in their own right, are finding it tricky to know how much
they need to explain the view they take of expert evidence before them. The Courts
also appear to be struggling. The present position is that Inspectors need only give the
main reasons for their decisions, not why it is they have decided to reject the evidence
of a particular expert. In Macarthur v Secretary of State for Communities and Local
Government [2013] EWHC 3 (Admin) Lang J made clear that she thought the Court
of Appeal in RWE v N Power had got it wrong with the consequence that ‘an
unsuccessful party will usually not know, in any detail, why the evidence of an expert
has been accepted or rejected by the Inspector and therefore will not be able to discern
whether the Inspector has correctly understood and applied the evidence of the
expert’. She was however bound to follow the Court of Appeal and did so. It looks
like this issue will rumble on.
Costs protection in environmental cases and the Aarhus Convention
141. Funding has always been an issue for administrative challenges to environmental
decision-making. However exercised a person or a group might be about, say, a
46
negative screening decision for EIA Directive Annex II development, or a worryingly
imprecise condition to an environmental permit, it requires real commitment to take
on a substantial costs risk in an area of litigation where ATE insurance has been
notoriously difficult to come by and where there might well be no impact on that most
British obsession (property prices). The natural response has been to seek whatever
costs protection the system allows. Equally, the courts have generally, though not
invariably, been prepared to accept that challenges to environmental decision-making
are brought for the benefit of all, relieving claimants of the need to make the running
on each and every PCO hurdle.
142. As a result, environmental judicial review has tended to lead the way in seeking to
relax the Cornerhouse requirements for PCOs, often with a leg up from the Aarhus
Convention. In the case of such as EIA challenges, the incorporation of Aarhus
Art.9(4) into the EU Directives improved matters, but even there the uncertain nature
of the position as regards the actual cap did much to put many potential claimants off.
Whilst the courts struggled with the practical implementation of the Aarhus Art.9(4)
requirement that litigation not be “prohibitively expensive”, and whether this was to
be decided on an 'objective' basis (by reference to the average citizen) or on a
'subjective' basis (ie the Claimant in question), we spent what seemed an age waiting
for the CJEU to respond to the Supreme Court’s reference in C-260/11 Edwards v
Environment Agency:
How should a national court approach the question of awards of costs against
a member of the public who is an unsuccessful claimant in an environmental
claim, having regard to the requirements of Article 9 (4) of the Aarhus
Convention, as implemented by Article 10a 85/337/EEC and Article 15a
96/61/EEC (“the Directives”)?
Should the question of whether the cost of the litigation is or is not
prohibitively expensive within the meaning of Article 9 (4) of the Aarhus
Convention as implemented by the Directives be decided on an objective basis
(by reference, for example, to the ability of an ordinary member of the public
to meet the potential liability for costs), or should it be decided on a subjective
basis (by reference to the means of the potential claimant) or upon some
combination of these two bases?
47
Or is this entirely a matter for national law of the Member State subject only
to achieving the result laid down by the Directives, namely that the
proceedings in question are not “prohibitively expensive”?
In considering whether proceedings are, or are not, “prohibitively expensive,
is it relevant that the claimant had not in fact been deterred from bringing or
continuing with the proceedings?
Is a different approach to these issues permissible at the stage of (i) an appeal
or (ii) a second appeal from that which requires to be taken at first instance?
143. In the meantime, Jackson LJ spent some time considering environmental challenges
for the purposes of his report. From the summary of consultation responses, it seems
he was rather impressed by the views of a certain Cambridge firm well known for its
claimant work in the environmental field (that claimant lawyers had no need of CFA
uplifts, and that it should be possible to successfully prosecute an “environmental”
judicial review for no more than some £30,000).
144. Until 1st April 2013, funding had been less of an issue for individuals seeking to
uphold private environmental rights in the face of a nuisance, these claims being
treated much like personal injury litigation, but the abolition of recoverable ATE,
without an equivalent to the QOCS regime that will now cover personal injury, means
that it will now come to take centre stage.
145. Oral argument in Edwards was heard by the CJEU last autumn. The Commission
intervened on the side of Denmark and Greece and Ireland on behalf of the UK.
Advocate General Kokott suggested in her opinion, at §2, that “in examining whether
costs of proceedings are prohibitive, account must be taken of the objective and
subjective circumstances of the case, with the aim of enabling wide access to justice.”
She said further that “it is necessary always, hence including when determining the
costs which can be expected of claimants having capacity to pay, to take due account
of the public interest in environmental protection.”
146. On 11 April 2013, the CJEU presented its judgment, which advanced the position
very little. It held that the requirement that “judicial proceedings should not be
prohibitively expensive means” that persons covered by the relevant European
48
legislation “should not be prevented from seeking, or pursuing a claim for, a review
by the courts that falls within the scope of those articles by reason of the financial
burden that might arise as a result.” The judgment went on, at §45:
Where a national court is called upon to make an order for costs against a member
of the public who is an unsuccessful claimant in an environmental dispute or, more
generally, where it is required – as courts in the United Kingdom may be – to state
its views, at an earlier stage of the proceedings, on a possible capping of the costs
for which the unsuccessful party may be liable, it must satisfy itself that that
requirement has been complied with, taking into account both the interests of the
person wishing to defend his rights and the public interest in the protection of the
environment.
46. It must therefore be held that, where the national court is required to determine,
in the context referred to in paragraph 41 of the present judgment, whether judicial
proceedings on environmental matters are prohibitively expensive for a claimant, it
cannot act solely on the basis of that claimant’s financial situation but must also
carry out an objective analysis of the amount of the costs. It may also take into
account the situation of the parties concerned, whether the claimant has a
reasonable prospect of success, the importance of what is at stake for the claimant
and for the protection of the environment, the complexity of the relevant law and
procedure, the potentially frivolous nature of the claim at its various stages, and the
existence of a national legal aid scheme or a costs protection regime.
147. It seemed that we had waited a very long time to be told nothing that we did not
already know.
148. However, Lord Justice Jackson had by then reported and wheels had begun to turn at
the Ministry of Justice, in the form of a costs regime for judicial review cases falling
within the scope of the Aarhus Convention and the EU Public Participation Directive.
A PCO would limit the liability of a claimant to pay a defendant’s costs to £5,000,
and £10,000 in the case of an organisation. It would limit the liability of a defendant
to pay the claimant’s costs to £35,000.
49
149. These reforms have now been introduced into the CPR by CPR Rule 45.41 and
following:
a. An Aarhus Convention claim is now defined in CPR 45.41 as “a claim for
judicial review of a decision, act or omission all or part of which is subject
to the provisions of the UN ECE Convention on Access to Information,
Public Participation in Decision making and Access to Justice in
Environmental Matters… including a claim which proceeds on the basis
that the decision, act or omission, or part of it, is so subject.”
b. CPR 45.42 provides that the Claimant must state on the claim form that the
claim is an Aarhus Convention claim and that the Claimant wishes the
special rules to apply.
c. Costs are limited as above.
d. The Defendant is able to challenge whether the claimant is in fact an
Aarhus Convention claim under CPR 45.44.
e. However, the Defendant does so at its own substantial costs risk – if it
loses that argument it will pay the costs of the issue on the indemnity
basis.
150. We are still waiting for the first authoritative decision on the new Rules, the High
Court having sidestepped the issue when considering a challenge to consent for
demolition of a listed building on the Sheffield Hospital case last week. It is fair to
say that previous judicial sidesteps, in relation to, say, non-EIA town and country
planning (e.g. R (Macrae) v Herefordshire [2012] EWCA Civ , where the Court of
Appeal was also able to sidestep promptness in non-EIA cases) and private nuisance
(e.g. Austin & Others v Miller Argent (South Wales) Ltd ([2011] EWCA Civ. 928,
where £200 per claimant in a group action not prohibitively expensive, but the Court
of Appeal did not need to decide whether private nuisance might fall within Aarhus as
a matter of principle given the points taken on appeal had not been run below) mean
that there is not a wealth of previous authority to draw upon. However, drawing the
threads together from case law and the proposed amendments to the EIA Directive,
we can note the following:
50
The courts having shown a determination to keep the application of the EIA
Directive within bounds, limited to projects likely to have “significant effects”
on the environment (e.g. Loader) and the Commission having taken the view
that some further clarification of the EIA Directive is required to achieve the
same end.
That would suggest that it is unlikely that the courts will permit Art.9(3) Aarhus
to be interpreted such that it applies to each and every challenge to a grant of
planning permission, let alone private nuisance proceedings. Particularly when
that approach would arguable render Art.9(2) otiose.
However, the removal of Legal Aid, and non-recoverability of ATE, are
powerful factors weighing on the judicial mind, and might prise Art.9 open to a
wider cohort.
151. This author’s forecast is that only those claimants bringing claims squarely within
Art.9(1) or 9(2) will feel confident of protection under 45.41 etc.
Other Areas - Case Digest
Air quality
152. In March 2013 the Supreme Court heard the case of R(oao ClientEarth) v Secretary
of State for Environment Food and Rural Affairs (UKSC 2012/0179). The issue
arising is whether, as regards areas where compliance with nitrogen dioxide limits set
out in Directive 2008/50/EC (the Air Quality Directive) cannot be achieved by 1
January 2010, the Air Quality Directive requires the Respondent to prepare an air
quality plan which demonstrates compliance by 1 January 2015.
153. The case was heard in the Supreme Court and their Lordships made a reference to the
CJEU with the following questions:
Where in a given zone or agglomeration conformity with the limit values for
nitrogen dioxide cannot be achieved by the deadline of 1 January 2010
specified in annex XI of Directive 2008/50/EC (“the Directive”), is a Member
State obliged pursuant to the Directive and/or article 4 TEU to seek
postponement of the deadline in accordance with article 22 of the Directive?
51
If so, in what circumstances (if any) may a Member State be relieved of that
obligation?
If the answer to (i) is no, to what extent (if at all) are the obligations of
Member State which has failed to comply with article 13 , and has not made
an application under article 22 , affected by article 23 (in particular its second
paragraph)?
In the event of non-compliance with article 13 , and in the absence of an
application under article 22 , what (if any) remedies must a national court
provide as a matter of European law in order to comply with article 30 of the
Directive and/or article 4 or art19 TEU ?
154. In addition, the court held that, in any event, the UK was in breach of Article 13 of the
Air Quality Directive (which the Government acknowledged) and that, in this regard
at least, enforcement action could now be taken.
Freedom of Information
155. In Birkett v DEFRA [2011] EWCA Civ 1606, the Court of Appeal has held that a
public authority that holds environmental information for the purposes of the
Environmental Information Regulations 2004 and, faced with a request for
information made pursuant to the Regulations, refuses to give disclosure and states its
reliance upon one of the permitted exceptions in accordance with Reg.14(3), may then
rely as of right upon a different exception or exceptions in proceedings before the
Information Commissioner and/or the First-Tier Tribunal (General Regulatory
Chamber) (Information Rights) so long as the new or additional exceptions are set out
within the notice of appeal, or response to a notice of appeal.
IPPC directive
156. The meaning of sows in subheading 6.6(c) of Annex 1 was considered in Møller v.
Haderslev Kommune (Case C-585/10). The Court found that the expression ‘places
52
for sows’, in subheading 6.6(c) of Annex I to Directive 96/61, has to be interpreted as
meaning that it includes places for gilts.
Liability of parent for actions of subsidiary
157. The conclusions of the Court of Appeal in Chandler v Cape plc [2012] EWCA Civ
525 may prove of wider application than the asbestos personal injury litigation they
arose in.
158. In appropriate circumstances the law may impose on a parent company responsibility
for the health and safety of its subsidiary’s employees. Those circumstances include a
situation where, as in the present case: (1) the businesses of the parent and subsidiary
are in a relevant respect the same; (2) the parent has, or ought to have, superior
knowledge on some relevant aspect of health and safety in the particular industry; (3)
the subsidiary’s system of work is unsafe as the parent company knew or ought to
have known; and (4) the parent knew or ought to have foreseen that the subsidiary or
its employees would rely on it using that superior knowledge for the employee’s
protection.
Contaminated Land
159. The Administrative Court has granted a declaration that a grant of planning
permission was unlawful because of failure to address contaminated land issues; R.
(on the application of Gawthorpe) v Sedgemoor DC [2012] EWHC 2020 (Admin).
EU emissions trading and aviation
160. In Case C-366/10, Air Transport Association of America et al. v. Secretary of State
for Energy and Climate Change, the European Court upheld the validity of the
application of EU emissions trading to passenger aircraft. The decision repays careful
attention on various fronts, in particular the close analysis of the relevance of
international agreements and public international law generally to the approach in
considering Directives. In the event, no incompatibility was found between Directive
2008/01 and the international material, in particular the EU/US “Open Skies”
53
Bilateral Agreement signed in Washington DC in 2007. The key point was that the
EU ETS scheme was (a) non-discriminatory and (b) was not in the nature of an
obligatory levy, duty, tax, fee or charge.
Rylands & Fletcher and fire
161. The Court of Appeal has handed down judgment considering the application of the
rule in Rylands v Fletcher to cases involving the escape of fire; Mark Stannard (t/a
Wyvern Tyres v Gore [2012] EWCA Civ 1248.
162. The Appellant carried on business supplying, fitting and balancing car and van tyres.
The business was conducted at a Trading Estate in Hereford. The Respondent’s
premises were behind the Appellant’s. At first instance the Recorder found that the
defendant “squeezed stock” into the room, some tyres being “haphazardly and
untidily” and others were “piled high in ‘chimneys’” ”, some of them being located
along the wall which divided the Respondent’s premises from the Appellant’s. A fire
broke out as a result of an electrical problem and spread to the Respondent’s premises.
The fire spread with great intensity and rapidity. A claim was brought in both
negligence and strict liability under Rylands v Fletcher. The negligence claim was
dismissed as there was no evidence of negligence in maintaining the electrical system
or appliances. The Recorder found that there had plainly been an ‘escape’ within the
meaning of the Rylands v. Fletcher rule and that liability therefore turned on whether
or not the Appellant’s activities on the premises were dangerous and a non-natural use
of his land. Although the tyres were not themselves flammable, the Recorder found
that they had a special fire risk quality if ignited and that risk was foreseeable. He
also considered that the numbers involved and haphazard means of the storage of
tyres was a state of affairs created by the Appellant that was out of the ordinary.
Finding that to be non-natural use, judgment was entered for the Respondent. The
Appellant appealed on the ground that the Recorder had erred in his application of the
test for strict liability under the rule in Rylands v Fletcher as applied to fire cases.
163. The Court of Appeal allowed the appeal, Ward L.J. finding that the proper approach
was:
(1) The defendant must be the owner or occupier of land.
54
(2) He must bring or keep or collect an exceptionally dangerous or mischievous
thing on his land.
(3) He must have recognised or ought reasonably to have recognised, judged by the
standards appropriate at the relevant place and time, that there is an exceptionally
high risk of danger or mischief if that thing should escape, however unlikely an
escape may have been thought to be.
(4) His use of his land must, having regard to all the circumstances of time and
place, be extraordinary and unusual.
(5) The thing must escape from his property into or onto the property of another.
(6) The escape must cause damage of a relevant kind to the rights and enjoyment of
the claimant’s land.
(7) Damages for death or personal injury are not recoverable.
(8) It is not necessary to establish the defendant’s negligence but an Act of God or
the act of a stranger will provide a defence.
164. The next question was whether there was any other or some special rule for cases
involving damage caused by the spread of fire. Cases of fire damage were likely to be
very difficult to bring within the rule because: (1) it was the “thing” which had been
brought onto the land which must escape, not the fire which was started or increased
by the “thing”; (2) while fire may be a dangerous thing, the occasions when fire as
such was brought onto the land may be limited to cases where the fire had been
deliberately or negligently started by the occupier or one for whom he was
responsible; and (3) in any event, starting a fire on one’s land may well be an ordinary
use of the land. Applying these principles to the case under appeal:
(1) The “thing” brought onto Wyvern’s premises was a large stock of tyres.
(2) Tyres, as such, were not exceptionally dangerous or mischievous.
(3) There was no evidence that Mr Stannard recognised nor ought he reasonably to
have recognised that there was an exceptionally high risk of danger or mischief if
the tyres, as such, should escape.
(4) The tyres did not escape. What escaped was the fire, the ferocity of which was
stoked by the tyres which were burning on, and remained burning on, Wyvern’s
55
premises. The Recorder had been wrong to conclude it was the escape of fire that
brought the case within Rylands v Fletcher principles.
(5) In any event, keeping a stock of tyres on the premises of a tyre-fitting business,
even a very large stock, was not for the time and place an extraordinary or unusual
use of the land. Here again the Recorder erred.
(6) Therefore Rylands v Fletcher liability was not established and, no negligence
having been proved, the claim failed and the appeal would be allowed.
JAMES BURTON
Thirty Nine Essex Street, WC2R 3AT
1st July 2013
Thirty Nine Essex Street LLP is a governance and holding entity and a limited liability partnership registered in England and Wales (registered number
0C360005) with its registered office at 39 Essex Street, London WC2R 3AT Thirty Nine Essex Street's members provide legal and advocacy services as
independent, self-employed barristers and no entity connected with Thirty Nine Essex Street provides any legal services. Thirty Nine Essex Street (Services)
Limited manages the administrative, operational and support functions of Chambers and is a company incorporated in England and Wales (company number
7385894) with its registered office at 39 Essex Street, London WC2R 3AT