Upload
lykhue
View
220
Download
3
Embed Size (px)
Citation preview
Development of a Supercritical Oxy-combustion Power Cycle with 99% Carbon Capture
Southwest Research Institute® and Thar Energy L.L.C. • Engineering development, technology
assessment, and economic analysis used to evaluate technical risk and cost of a novel supercritical oxy-combustion power cycle
• Optimized cycle couples a coal-fired supercritical oxy-combustor with a supercritical CO2 power cycle to achieve 40% efficiency at low firing temperature, 650 C
– Cycle is limited by TRL of critical components • COE $121/MWe with 99% carbon capture
– 49% increase over Supercritical Steam Without Carbon Capture ($81/MWe), exceeding the 35% target
– 21% reduction in cost as compared to Supercritical Steam with 90% Carbon Capture ($137/MWe).
• Phase 1 completed in September 2013, Extended to March 2014 to cover closeout
• Budget $1.25 million • Ready to demonstrate supercritical oxy-
combustor and critical low TRL technologies
Supported by DOE Project DE-FE0009395
DE-FE0009395
Novel Supercritical Carbon Dioxide Power Cycle Utilizing Pressurized Oxy-combustion In Conjunction
With Cryogenic Compression
Project Closeout
Southwest Research Institute ® and
Thar Energy L.L.C.
Period of Performance: 10/01/2012 – 09/30/2013
Outline
• Project and Participants Overview • Core Technologies • Techno-economic Analysis • Technology Gap Analysis • Bench Scale Testing • Path Forward
DE-FE0009395 Project Closeout 2/21/2014
PROJECT OVERVIEW
DE-FE0009395 Project Closeout 2/21/2014
Project Scope • Evaluate a novel supercritical oxy-combustion power cycle
for meeting the DOE goals of: – Over 90% CO2 removal for less than 35% increase in cost of
electricity (COE) when compared to a Supercritical Pulverized Coal Plant without CO2 capture
• Cycle evaluation based on: – Cycle and economic modeling to qualify cost and cycle
performance – Technology gap assessment to identify critical low TRL
components and technologies – Bench scale testing to back up cycle models and evaluate state
of low TRL technologies • Propose development path to address low TRL components
DE-FE0009395 Project Closeout 2/21/2014
Participants
Southwest Research Institute
• Project role – Project management – Cycle analysis and
optimization – Bench scale testing – Oxy-combustor design
• Key personnel – Dr. Klaus Brun – Dr. Aaron McClung – Dr. Rebecca Owston
Thar Energy LLC
• Project role – Technical gap analysis – Economic analysis
• Key personnel – Dr. Lalit Chordia – Mr. John Davis – Dr. Rachmadian "Doni"
Wulandana
DE-FE0009395 Project Closeout 2/21/2014
Southwest Research Institute • Independent, nonprofit applied research and
development organization founded in 1947 • Eleven technical divisions
– Aerospace Electronics, Systems Engineering & Training
– Applied Physics – Applied Power – Automation & Data Systems – Chemistry & Chemical Engineering – Engine, Emissions & Vehicle Research – Fuels & Lubricants Research – Geosciences & Engineering – Mechanical Engineering – Signal Exploitation & Geolocation – Space Science & Engineering
• Total 2013 revenue of $592 million – 38% Industry, 36% Govt., 26% Govt. Sub – $6.7 million was reinvested for internal
research and development • Over 2,800 staff
– 275 PhD’s / 499 Master's / 762 Bachelor's
• Over 1,200 acres facility in San Antonio, Texas
– 200+ buildings, 2.2 million sq. ft of laboratories & offices
– Pressurized Closed Flow Loops – Subsea and High Altitude Test Chambers – Race Oval and Crash Test Track – Explosives and Ballistics Ranges – Radar and Antenna Ranges – Fire testing buildings – Turbomachinery labs
Benefiting government, industry and the public through innovative science and technology
2.1 Miles
1.2
Mile
s
Machinery Program • Fluids & Machinery Engineering
Department – Mechanical Engineering Division (18)
• Capabilities – Root cause failure analysis – Rotordynamic design/audit – Pipeline/plant simulation – CFD and FEA analysis – Test rig design – Performance testing
• Current DOE Programs – Phase 3 pilot scale CO2 compression
demonstration – Sunshot sCO2 turbomahinery
development and demonstration – SunShot high inlet temperature
combustor development and demonstration
• Recent Commercial Projects – Test stands for LNG and CNG process
evaluation – Air Cycle Machine Design, Build, and
Test – Numerical Propulsion System
Simulation® (NPSS®) Consortium Management
DE-FE0009395 Project Closeout 2/21/2014
9
Thar companies: Thar Energy LLC Systems for fuel production, power generation
and geothermal heating and cooling Thar Process, Inc. Supercritical fluid process design and toll
extractions from organic feedstocks
Shown here: Pharmaceutical production system … Good Manufacturing Process … Supercritical fluid extraction
Core competencies: 25+ years commercializing “Green”
supercritical fluid technologies (SCF)
Designer and developer of supercritical fluid processes, systems & major components
Industrial scale 24/7/365 installations, world wide:
Food Chemicals Nutraceutical Pharmaceutical Chemical
Heat exchangers for high pressure, high temperature application
Funding
Participant Type Project Budget Cost Share POC Southwest Research Institute®
Not for Profit $ 715,000.00 $ - Aaron McClung
Thar Energy LLC. For Profit $ 535,000.00 $ 250,000.00 John Davis
Project Total $ 1,250,000.00 $ 250,000.00
DE-FE0009395 Project Closeout 2/21/2014
Period of Performance: 10/01/2012 through 09/30/2013
DOE Supercritical Oxy-Combustion Phase I: Development of a Supercritical Oxy-combustion Power Cycle
with 99% Carbon Capture
• Optimized cycle couples a coal-fired supercritical oxy-combustor with a supercritical CO2 power cycle to achieve 40% efficiency at a low firing temperature of 650 C
• COE $121/MWe with 99% carbon capture
– 49% over Supercritical Steam Without Carbon Capture ($81/MWe), exceeding the 35% target
– 21% reduction in cost as compared to Supercritical Steam with 90% Carbon Capture ($137/MWe).
• Phase I completed in September 2013, budget $1.25 million
• Ready to demonstrate supercritical oxy-combustor and critical low TRL technologies
DE-FE0009395 Project Closeout 2/21/2014
Final Supercritical Oxy-combustion Cycle Configuration
HXMAIN1 HXCLEANPRECOOL
HXLOW HXHIGH
EXPANDER
COMP1
COMP2
P6 P7a
P8
P1
P2
P3
P5
P7b
P7
P4
P4b
Combustor
O2
Coal Slurry
C2
C3
C4
FLUE GAS CLEANUP
C5C6
C0
Sequestration Ready CO2
High Temperature Power LoopRecompression sCO2 Power Cycle
Combustion LoopCoal Fired Supercritical Oxy-Combustion
H2O, CaCO2, CaSO4, Hg
H2O, O2, CaCO2
COOLING OUT
COOLING INBOOST
BOOST C7
P4a
CYCLONE
C1
C1b
Power Block Thermal Loop Overall
Efficiency [%] 48 Thermal 78.9 HHV / 81.8 LVH 37.9 HHV / 39.3 LHV
CO2 Flow [kg/s] 4887 4930 Recycle
P high / P low [atm] 290 / 82 100 / 93
T high / T low [C] 650 / 20 653 / 78
DE-FE0009395 Project Closeout 2/21/2014
Combustion Loop TRL
DE-FE0009395 Project Closeout 2/21/2014
Component/Sub-system Technology Type
Operating Conditions
Assumed or Specified Performance Characteristics Assumptions Regarding Anticipated Application Issues Technology Readiness
Inlet Outlet
Tem
pera
ture
[C]
Pres
sure
[atm
]
Tem
pera
ture
[C]
Pres
sure
[atm
]
Combustion Loop Coal Pulverizer Generic 25 1 25 1 < 9 kw-h/ton TRL 9 Slury Pump Generic 25 1 30 92.25 60% Efficiency TRL 9 Supercritical oxy-combustor New vertical flow swirl combustor 450 95 93 92.25 98+% combustion efficiency Combustor to be demonstrated in
Phase 2 TRL 6 at the
completion of Phase 2 demonstration
Dry pulverized coal feed Supercritical CO2 slurry 25 1 <450 110 Minimal added water content TRL 2 Dry pulverized coal feed Posimetric Pump 25 1 <450 110 Dry feed Demonstrated systems can not
achieve pressure ratio TRL 4
Removal of solid products of combustion Lock-hopper 703 92 80 1 Fluid and thermal losses, impact on efficiency unknown
TRL 4
Cyclone Separator Generic 703 93 703 91 98% Removal 3 atm dP
Materials considerations and thermal insulation for hot gas
cleanup
TRL 9
Recouperator (HXMAIN) Compact micro-channel heat exchanger
703 91 460 88 5 C Pinch Point 3 atm dP
See Note 3 TRL 7, See Note 1
Pre-heater (HXCLEAN) Compact micro-channel heat exchanger
460 88 162 85 5 C Pinch Point 3 atm dP
See Note 3 TRL 7, See Note 1
Sulfur Cleanup Under evaluation for hot, high pressure cleanup
162 85 ? ? Under Evaluation to identify technologies compatible with loop conditions
High efficiency requirements drive the need for hot, high pressure
cleanup
TRL 5 - 9 depending on cleanup
conditions
Water Removal Under evaluation for hot, high pressure cleanup
162 85 ? ? Under Evaluation to identify technologies compatible with loop conditions
High efficiency requirements drive the need for hot, high pressure
cleanup
TRL 5 - 9 depending on cleanup
conditions
Boost Pump Generic 150 80 95 Seals and materials for supercirtical CO2
TRL 9
Air Separation Unit Cryogenic 30 1 450 93 140 kWh/t for 95% O2 based on literature TRL 9
Note 1: TRL 7 at the completion of a compantion DOE SunShot Project in 2016 (DE-EE0005804)
Note 2: TRL 7 at the completion of a compantion DOE SunShot Project in 2013 (FC26-05NT42650)
Note 3: Materials and manufacturing assumptions for cost and performance
Note 4: Turbomachinery layout and design is being adressed in other DOE sponsored programs (DE-EE0005804)
Power Loop TRL
DE-FE0009395 Project Closeout 2/21/2014
Component/Sub-system Technology Type
Operating Conditions
Assumed or Specified Performance Characteristics Assumptions Regarding Anticipated Application Issues Technology Readiness
Inlet Outlet
Tem
pera
ture
[C]
Pres
sure
[atm
]
Tem
pera
ture
[C]
Pres
sure
[atm
]
Power Loop Supercritical CO2 Recompression Cycle
TRL 7, See Note 1
sCO2 Turbo-expander 650 290 509 86 90+% efficiency See Note 4 TRL 7, See Note 1
Recouperator (HXHIGH) Compact micro-channel heat exchanger
509 86 213 84 5 C Pinch Point 3 atm dP
See Note 3 TRL 7, See Note 1
Recouperator (HXLOW) Compact micro-channel heat exchanger
213 84 70 83 5 C Pinch Point 3 atm dP
See Note 3 TRL 7, See Note 1
sCO2 Pump/Compressor 70 83 190 290 05+% efficiency See Note 4 TRL 7, See Note 2
sCO2 Pump/Compressor 25 82 60 290 05+% efficiency See Note 4 TRL 7, See Note 2
Pre-cooler Compact micro-channel heat exchanger
70 83 25 82 5 C Pinch Point 3 atm dP
See Note 3 TRL 7, See Note 1
Note 1: TRL 7 at the completion of a compantion DOE SunShot Project in 2016 (DE-EE0005804) Note 2: TRL 7 at the completion of a compantion DOE SunShot Project in 2013 (FC26-05NT42650) Note 3: Materials and manufacturing assumptions for cost and performance Note 4: Turbomachinery layout and design is being adressed in other DOE sponsored programs (DE-EE0005804)
Economic Assessment
• Revised* COE of $121/Mwe with 99% carbon capture – 49% over Supercritical Steam Without Carbon
Capture ($81/MWe), exceeding the 35% target – 21% reduction in cost as compared to Supercritical
Steam with 90% Carbon Capture ($137/MWe).
DE-FE0009395 Project Closeout 2/21/2014
* COE revised based on feedback from the Phase II Application
Technology Development: Proposed follow on
• 1 MWth Supercritical Oxy-combustor Demonstration
• Test bed for technology development – Supercritical oxy-combustor – Particulate cleaning of the compact
microchannel heat exchanger – Solids injection at pressure – Solids removal at pressure
• Advance technologies from TRL 2, Technology Concept, to TRL 6, Pilot Scale System Demonstrated in a Relevant Environment
• Operate with coal water slurry, plan for dry feed or sCO2 slurry extension
DE-FE0009395 Project Closeout 2/21/2014
Supercritical Oxy-combustor Cyclone
Separator
Underflow Particulate Separation
Boost Compressor Water
Scrubber
Supercritical Oxy-combustor
Cyclone Separator
Underflow Particulate Separation
Water Scrubber
Cooling Tower
Oxy-Combustion Test Loop • Major components
– Charge Compressor or Pressurized CO2 Feed – Combustor
• Oxygen feed • Coal slurry feed
– Cyclone separator • Solids removal and handling
– Recuperater – Water scrubber and cleanup
• Liquid removal and handling • CO2 removal and handling
– Cooling Tower – Boost Compressor
• Operating Conditions – 450 – 650 C (800 – 1200 F) – 102 atm (1500 psi)
• Flow Rates: 1 MWth – 3.4 kg/s Hot side flow rate – 3.2 kg/s CO2 recycle – 0.05 kg/s Coal feed – 0.08 kg/s O2 Feed – 4.25 kg/s H2O Recycle
DE-FE0009395 Project Closeout 2/21/2014
HXCLEAN
Combustor
O2
Coal SlurryC2
C4
FLUE GAS CLEANUP
C5C6
C0
Coal Fired Supercritical Oxy-Combustion Test Loop
H2O, Products of Combustion
H2O
BOOST
C7
CYCLONE
C1
C1b
CO2 Capture and Disposal
Underflow Particulate Removal
CO2H2O
Solids
TECHNOLOGY OVERVIEW
DE-FE0009395 Project Closeout 2/21/2014
Proposed Cycle: Cryogenic Pressurized Oxy-combustion (CPOC)
• Transcritical cycle (gas, liquid, and supercritical states)
• Leverage iso-thermal compression to minimize compression work
DE-FE0009395 Project Closeout 2/21/2014
Proposed Cycle: Supercritical Oxy-combustion
• Leverages recent SunShot and DOE-NE cycles development
• Efficiencies up to 60% possible for the power block
DE-FE0009395 Project Closeout 2/21/2014
Anticipated Technology Areas • Primary
– Pressurized oxy-combustion • Negate need for CO2 recompression • Increase combustion and cycle efficiencies
• Secondary – High-pressure and high-temperature cleanup technologies
• Required to commercialize a sCO2 oxy-combustion cycle • Tertiary
– High efficiency power cycle • Must be cost effective to be a viable commercial project
• Unplanned – Solid fuel injection at pressure
• Impact of slurrying agent (water) on efficiency – Solid waste removal at pressure
• Removal of (hot) solid waste under pressure
DE-FE0009395 Project Closeout 2/21/2014
Direct Fired Cycles
• Managing contaminants – Fly ash and particulates (erosion, clogging) – Heavy metals (corrosion) – Water (corrosion) – Gasses (expander performance, corrosion)
• Gas quality – Gas composition will vary with fuel and cleanup
technology, equipment condition
DE-FE0009395 Project Closeout 2/21/2014
Indirect Cycles
• Anticipated technology developments contained in the thermal loop – High pressure oxy-combustor – Cleanup (Fly-ash, Metals, Water, Gases) of supercritical
CO2 • Power cycle is tertiary for this project
– Any power cycle can be integrated into dual loop configuration with minimal modification
– Technology enhancements can be re-integrated into a single loop configuration down the line
• Potential efficiency hit with interface heat exchanger
DE-FE0009395 Project Closeout 2/21/2014
TECHNO-ECONOMIC ANALYSIS
DE-FE0009395 Project Closeout 2/21/2014
Approach
DE-FE0009395 Project Closeout 2/21/2014
Cycle Model Components and flow rates
Components and operating conditions
Operating Conditions
Sensitivity of LCOE w.r.t. Cycle Economic Model Sensitivity of LCOE
w.r.t. Technology
Component specifications and
TRLComponent cost Technology Gap
Analysis
Bench Scale Testing
Combustor Design
Demonstration Effort
(Phase 2 Proposal)
Operating Conditions
Cycle layout and design
Combustor cost
Component Costs
Selected Components
Final Combustor Design
Combustion Characteristics
Combustor Performance
Analysis Methods • Cycle models
– Aspen Plus 7.3.2 – Power cycle models without combustion for comparison and
optimization – Optimized cycle with combustion
• Economics – DOE Power Systems Financial Model (PSFM) – Plant specifics determined by QGESS and FOA – Component costs incorporated from Tech Gap Analysis – Plant performance determined by cycle analysis
• Technology Gap Analysis – Required components determined by initial and optimized cycle
layouts – Component level technology assessment determined through
discussion with vendors and literature search
DE-FE0009395 Project Closeout 2/21/2014
Cycle Analysis
• Aspen Plus 7.3.2 for cycle performance analysis – Mature component specifications from vendor or
QGESS Process Modeling Design Parameters – Low TRL component data from engineering
assessment • Evaluated baseline power block performance of
the two proposed cycles • Incorporated combustion model into selected
cycle • Optimize cycle configuration for high efficiency,
low cost
DE-FE0009395 Project Closeout 2/21/2014
CPOC Power Block
CPOC w/out Combustion Thermal Efficiency
DE-FE0009395 Project Closeout 2/21/2014
PUMP
EXPANDER
HEATIN
HEATOUTB10B1
DE SIGN-SPECB2
B3
CALCULAT ORB4
DE SIGN-SPECB5
5000
56162
0.00
0
5000
56162
1.00
1
14
56162
1.002
300
56162
0.00
4
-59098
1585
9
394
10
-3930
WNETW
7795216
6Q
5000
56162
0.00
5
300
56162
1.00
3
7081080
S3
7081080
QCOOLQ
sCO2 Recompression Power Block
sCO2 w/out Combustion Thermal Efficiency
DE-FE0009395 Project Closeout 2/21/2014
EXPANDER
COMP1
COMP2
RECEIVER
COOL
PRECOOL
HXHIGHHXLOW
MIXER1
SPLIT1
CALCU LATORPOST
TRAN SFERT-TEMP
TRAN SFERT-PRES
S1
S2
S3
S4
S5S6
S7
S8
S9
S11
S12
S13 S14
S15
Cycle Layout Challenges • Recuperated sCO2 power block has a narrow thermal input band
– Change in temperature across power block is only 250 C – Minimize thermal losses through the system – Hot combustor inlet
• Gas phase cleanup must occur at low temperature to condense water, remove sulfur, condensable gasses
• Particulate removal prior to gas turbine (direct) or interface heat exchanger (indirect)
– Leads to hot particulate removal – Particulates are at pressure, must be removed to ambient conditions
• Combustor operating pressure – Direct fired combustor must operate at high side turbine pressure, 270 atm – Indirect fired combustor can operate at reduced pressure, above75 atm – Higher pressure required advanced pulverized coal injection technologies
• Indirect cycle incurs efficiency penalty due to interface heat exchanger • Coal-water slurry feed has significant efficiency impact depending on water
content – Losses due to heat of vaporization are not recoverable
DE-FE0009395 Project Closeout 2/21/2014
Indirect Cycle Model with Supercritical Oxy-Combustor
MIX-COAL
CYCLONERGIBBS
Q=-182132974
SLRYPUM P
CALCULAT ORC-YIELD
RYIELD
Q=182132974
MIX1
HEAT-AUX
Q=0
CALCULAT ORASU WM IX1
HXMAIN1
Q=1230727570
SPLIT
Q=0
DE SIGN-SPECC-COAL
DE SIGN-SPECCO2M ASS
CALCULAT ORC-RECY
HXCLEAN
Q=2275090230
BOOSTW=18889203
S-SEQ
B6
Q=0
CALCULAT ORC-PRES
HIERARCHY
PWR1
DE SIGN-SPECP1MDOT
CALCULAT ORPOST-CYC
NET-SUM
CALCULAT ORTHPWR1
DE SIGN-SPECCO2TEMP
B4
W=3607442
CALCULAT ORC-SLRY
B1
Q=0
DE SIGN-SPECH20-BAL
DE SIGN-SPECT-H20
30.00
1.0000
70.6260COAL-IN
30.00
1.0000
0.0000H2O-IN
29.92
1.0000
70.6260SLRYLOWP
653.00
99.0000
5107.6395
PRODUCTS
653.00
97.0000
5101.7970
CHOT
653.00
97.0000
5.8425SOLIDS
30.00
100.0000
107.2103
O2-IN
453.77
100.0000
4929.8033
CO2-RET
100.0000
70.6260SLRYHIGP
450.00
100.0000
70.6260S10
0.0000
RY-BYPAS
29.84
100.0000
70.6260RY-IN
450.00
100.0000
70.6260
IN-BURN
-182132974.00
QBURN
29.84
100.0000
70.6260SLRY-HOT
48030200.10
WASUW
48030200.10
CWNET
0.00
WSLRPMP
456.77
96.0000
5101.7970
CMID
453.77
290.0000
4887.0782PCOLD1
650.00
290.0000
4887.0782PHOT1
453.77
100.0000
4929.8033
CO2-RET1
78.33
93.0000
5062.0485CL-CO2
78.33
93.0000
132.2452
TOSEQ
78.33
93.0000
4929.8033
CLEAN3
78.71
94.0000
6135.3682
CLEAN1
78.33
93.0000
1073.3198
CL-H2O
100.47
95.0000
5101.7970WCOLD
84.88
100.0000
4929.8033
CLEAN2
-604112926.00
WPOWER1
-533556589.00
WNETW
18889203.10
WCLEAN
650.00
290.0000
4887.0782
PHOT1B
121.80
149.7000
132.2452
PIPELINE
3607442.02
SEQ-COM P
30.00
95.0000
1033.5712
H2O-SCRU
Temperature (C)
Pressure (atm)
Mass Flow Rate (kg/sec)
Duty (Watt)
Power(Watt)
Q Duty (Watt)
W Power(Watt)
Cleanup
DE SIGN-SPECH20-FRAC
DE SIGN-SPECH2O-SFRA
DE-FE0009395 Project Closeout 2/21/2014
EXPANDER
W=-846993775
COMP1
W=103709586
COMP2
W=139171263
COOL
Q=-0
PRECOOL
Q=-626685163
HXHIGH
Q=1902612830
HXLOW
Q=781401058
MIXER1
SPLIT1
CALCULAT ORPOST
TRANSFE RT-PRES
B1
DE SIGN-SPECDSPLIT
DUMMY
Q=0
650.00
290.0000
4887.0782
S1
509.27
85.7242
4887.0782S2
177.72
84.1451
4887.0782
S3
59.98
82.8621
4887.0782S4
59.98
82.8621
1710.4774S5
174.72
290.0000
1710.4774S6
174.72
290.0000
1710.4774S7
174.72
290.0000
4887.0782
S8
453.77
290.0000
4887.0782
S9 PCOLD1(OUT)
20.00
81.8752
3176.6008S12
49.92
290.0000
3176.6008
S13
174.72
290.0000
3176.6008
S14
650.00
290.0000
4887.0782
S15PHOT1(IN)
-846993775.00S10139171263.00S16
59.98
82.8621
3176.6008
S11
103709586.00
S17
-604112926.00
WPOWER WPOWER1(OUT)
Temperature (C)
Pressure (atm)
Mass Flow Rate (kg/sec)
Power(Wat t)
Q Duty (Wat t)
W Power(Wat t)
Power Block Cleanup
Combustor
Final Supercritical Oxy-combustion Cycle Configuration
HXMAIN1 HXCLEANPRECOOL
HXLOW HXHIGH
EXPANDER
COMP1
COMP2
P6 P7a
P8
P1
P2
P3
P5
P7b
P7
P4
P4b
Combustor
O2
Coal Slurry
C2
C3
C4
FLUE GAS CLEANUP
C5C6
C0
Sequestration Ready CO2
High Temperature Power LoopRecompression sCO2 Power Cycle
Combustion LoopCoal Fired Supercritical Oxy-Combustion
H2O, CaCO2, CaSO4, Hg
H2O, O2, CaCO2
COOLING OUT
COOLING INBOOST
BOOST C7
P4a
CYCLONE
C1
C1b
Power Block Thermal Loop Overall
Efficiency [%] 48 Thermal 78.9 HHV / 81.8 LVH 37.9 HHV / 39.3 LHV
CO2 Flow [kg/s] 4887 4930 Recycle
P high / P low [atm] 290 / 82 100 / 93
T high / T low [C] 650 / 20 653 / 78
DE-FE0009395 Project Closeout 2/21/2014
Economic Assessment
• Reported COE of $162/MWe with 99% carbon capture in June 2013
• Revised* COE of $121/Mwe with 99% carbon capture – 49% over Supercritical Steam Without Carbon
Capture ($81/MWe), exceeding the 35% target – 21% reduction in cost as compared to Supercritical
Steam with 90% Carbon Capture ($137/MWe).
DE-FE0009395 Project Closeout 2/21/2014
* COE revised based on feedback from the Phase II Application
Revisions to COE Calculation
• Per DOE Feedback – Revise coal cost from $10.25/ton to $36.57/ton in
calculating TOC (based on 2012 QGESS Feedstock Costs)
– Installation factor should not have been applied when calculating BEC
• Changes to match analysis – Revise initial fuel requirements for calculating TOC
based on predicted 39% HHV plant efficiency, reduce inventory from 6102 ton/d to 5000 ton/d
DE-FE0009395 Project Closeout 2/21/2014
Estimated equipment costs, 550 MW pressurized oxy-combustion power plant, single power block
Base cost Units Spare cost Spares Total Process equipment $ Million operating $ Million on hand $ Million Core systems Cyclones, inc. linings, peripherals $53 18 52.7 - Spare cyclones 2.9 2 5.9 FGD, inc. metals removal $45 1 45.0 -- Spare scrubber 6 1.7 1 1.7 -- Spare hydrocyclone 12 0.1 2 0.2 Piping, combustion side $30 1 29.9 ASU ex pumps $160 4 160.0 -- Standby ASU spare 40.0 1 40.0 Pumps for liq. O2 $6 8 6.0 -- Spare pump 0.8 1 0.8 Coal slurry preparation $2 1 2.0 1 4.4 SunShot power loop @ $1,200/kWe $660 1 66.0 1 726.0 HXs, combustion side $140 8 140.1 -- Spare HX 17.5 2 35.0 Combustor, No spare $68 1 68.0 0 67.7 1st Subtotal (BEC), Core systems $1,164 1,315.3 Support facilities* Coal receiving 24.4 Coal crushing 16.6 Ducting and stack 21.3 Ash handling 6.5 Accessory electric plant 32.2 Instrumentation & control 12.1 2nd Subtotal (BEC), Ancilliary systems 113.1 Total BEC, equipment 1,428.4 * Numbers drawn from NETL Bituminous Coal Utility study, 2012 update, Case 12 (PC with sequestration)
DE-FE0009395 Project Closeout 2/21/2014
Capital costs according to PSFM guidelines (in red)
Totals for: Portion Cumulative
Capital cost category Basis Factor $ Million $ Million BEC - Bare Erected Cost
Process equipment ** Itemized cost summary 1,315.30 Support facilities *** NETL, 2012 update, Case 12 113.1
Total BEC 1,428.40 1,428.40 EPC - Engineering Project Costs Total EPC portion 0-10% BEC, "process in use" 10% 142.84 1,571.24 * TPC - Total Project Costs
Process cost 5-20% of process capital 20% 314.248 Project cost 15-30% of BEC+EPC+process cost 30% 471.372
Total TPC portion 785.62 2,356.86 TOC - Total Overnight Cost
Royalties Assume zero 0 Pre-production Gross estimate 1 - 6 mos labor Included in gross estimate - 1 mo maintenance materials Included in gross estimate - 1 mo non-fuel consumables Included in gross estimate - 1 mo waste disposable Included in gross estimate Working capital Accounted for in PSFM model Inventory capital: - Spare parts 0.5% of cum TPC 0.50% 19.4 - Initial fuel (60 days) 5,000 ton/d $36.00 13.34 - Initial CaCO3 (60 days) 1.45 kg/s = 3.2 lb/s makeup $0.20 0.1 Land, for PC-type utility 300 acres 3,000 0.9 Financing - cost of securing it Percent of TPC 2.70% 105 Other owner's costs Percent of TPC 15% 583.4
Total Owner's cost 722.14 3,079.00 TASC - Total As-Spent Capital
Escalation while expending capital Accounted for in PSFM model 0 Interest while expending capital Accounted for in PSFM model 0
Total TASC 0 3,079.00 Analysis:
TASC by PSFM calculation 2,505.12 **
w/ TS&M w/ TS&M Benchmark COE Case 11, 2012 update 80.95 N/A Benchmark COE w/ 90% CCS Case 12, 2012 update 137.28 147.47 COE by PSFM Includes O&M N/A 121.21
* Cumulative amount goes to Cell B37, "Plant Inputs" page of PFSM workbook ** TASC calculation comes from Cell B12 of the "COE Calculation" page of the PSFM workbook
DE-FE0009395 Project Closeout 2/21/2014
From Tech Gap analysis
Operations and maintenance cost in $ thousand
Operations and maintenance cost, $ thousand Bold items entered on O&M page of PSFM workbook
PSFM page,
Cost items Measure Rate $/h $1,000/y Cell ID Source: Variable costs: Labor:
Operating labor base rate $/hr $33.3
6 $33.36 69 BLS, NAICS 221100 job category 51-0000, May 2013 Operating labor burden % of base 30% $10.01 21 B27 Rate from Exhibit 4-13, Case 12, August 2012 Labor O-H charge rate % of labor 25% $10.84 23 Rate from Exhibit 4-13, Case 12, August 2012 Subtotal: Operating labor wages ex burden, per operator 92 B26 Calculated Total: Operating labor cost per operator 113 Calculated Estimated operating laborers 65 B25 Calculation based on Exhibit 4-13 oper. labor cost Administrative and supervisory Total 1,674 Exhibit 4-13, Case 12, August 2012
Administrative and supervisory Per operator 25.56 B28 Calculated
Consumables: Water Total 3,804 B31 Exhibit 4-13, Case 12, August 2012 Chemicals Total 24,914 B32 Exhibit 4-13, Case 12, August 2012 Waste disposal Total 5,129 B34 Exhibit 4-13, Case 12, August 2012
Fixed costs: Administrative and supervisory Total 3,348 B37 Exhibit 4-13, Case 12, August 2012 Taxes and insurance 39,025 B38 Exhibit 4-13, Case 12, August 2012 Maintenance costs % EPC/yr 3% 86,527 B39 Thar assumption
Assumptions and Benchmarks: Base hours in year: 2,080
*Operating labor cost: $7,384,208 per yr *Maintenance labor cost: $12,705,913 per yr (included in overall maintenance percentage)
*Administrative & support labor cost: $5,022,530 per yr (assume 1/3 variable, 2/3 fixed) *Property taxes and insurance: $39,024,956 per yr
* Benchmarks taken from Exhibit 4-13, Case 12, August 2012
DE-FE0009395 Project Closeout 2/21/2014
TECHNOLOGY GAP ANALYSIS
DE-FE0009395 Project Closeout 2/21/2014
Methodology
• Tabulate components required for the cycle layouts – Identify commercially available components – Identify relevant technologies, vendors for non-standard or immature
components
• Provide component cost and performance feedback to economic and cycle models
DE-FE0009395 Project Closeout 2/21/2014
Combustion Loop TRL
DE-FE0009395 Project Closeout 2/21/2014
Component/Sub-system Technology Type
Operating Conditions
Assumed or Specified Performance Characteristics Assumptions Regarding Anticipated Application Issues Technology Readiness
Inlet Outlet
Tem
pera
ture
[C]
Pres
sure
[atm
]
Tem
pera
ture
[C]
Pres
sure
[atm
]
Combustion Loop Coal Pulverizer Generic 25 1 25 1 < 9 kw-h/ton TRL 9 Slury Pump Generic 25 1 30 92.25 60% Efficiency TRL 9 Supercritical oxy-combustor New vertical flow swirl combustor 450 95 93 92.25 98+% combustion efficiency Combustor to be demonstrated in
Phase 2 TRL 6 at the
completion of Phase 2 demonstration
Dry pulverized coal feed Supercritical CO2 slurry 25 1 <450 110 Minimal added water content TRL 2 Dry pulverized coal feed Posimetric Pump 25 1 <450 110 Dry feed Demonstrated systems can not
achieve pressure ratio TRL 4
Removal of solid products of combustion Lock-hopper 703 92 80 1 Fluid and thermal losses, impact on efficiency unknown
TRL 4
Cyclone Separator Generic 703 93 703 91 98% Removal 3 atm dP
Materials considerations and thermal insulation for hot gas
cleanup
TRL 9
Recouperator (HXMAIN) Compact micro-channel heat exchanger
703 91 460 88 5 C Pinch Point 3 atm dP
See Note 3 TRL 7, See Note 1
Pre-heater (HXCLEAN) Compact micro-channel heat exchanger
460 88 162 85 5 C Pinch Point 3 atm dP
See Note 3 TRL 7, See Note 1
Sulfur Cleanup Under evaluation for hot, high pressure cleanup
162 85 ? ? Under Evaluation to identify technologies compatible with loop conditions
High efficiency requirements drive the need for hot, high pressure
cleanup
TRL 5 - 9 depending on cleanup
conditions
Water Removal Under evaluation for hot, high pressure cleanup
162 85 ? ? Under Evaluation to identify technologies compatible with loop conditions
High efficiency requirements drive the need for hot, high pressure
cleanup
TRL 5 - 9 depending on cleanup
conditions
Boost Pump Generic 150 80 95 Seals and materials for supercirtical CO2
TRL 9
Air Separation Unit Cryogenic 30 1 450 93 140 kWh/t for 95% O2 based on literature TRL 9
Note 1: TRL 7 at the completion of a compantion DOE SunShot Project in 2016 (DE-EE0005804)
Note 2: TRL 7 at the completion of a compantion DOE SunShot Project in 2013 (FC26-05NT42650)
Note 3: Materials and manufacturing assumptions for cost and performance
Note 4: Turbomachinery layout and design is being adressed in other DOE sponsored programs (DE-EE0005804)
Power Loop TRL
DE-FE0009395 Project Closeout 2/21/2014
Component/Sub-system Technology Type
Operating Conditions
Assumed or Specified Performance Characteristics Assumptions Regarding Anticipated Application Issues Technology Readiness
Inlet Outlet
Tem
pera
ture
[C]
Pres
sure
[atm
]
Tem
pera
ture
[C]
Pres
sure
[atm
]
Power Loop Supercritical CO2 Recompression Cycle
TRL 7, See Note 1
sCO2 Turbo-expander 650 290 509 86 90+% efficiency See Note 4 TRL 7, See Note 1
Recouperator (HXHIGH) Compact micro-channel heat exchanger
509 86 213 84 5 C Pinch Point 3 atm dP
See Note 3 TRL 7, See Note 1
Recouperator (HXLOW) Compact micro-channel heat exchanger
213 84 70 83 5 C Pinch Point 3 atm dP
See Note 3 TRL 7, See Note 1
sCO2 Pump/Compressor 70 83 190 290 05+% efficiency See Note 4 TRL 7, See Note 2
sCO2 Pump/Compressor 25 82 60 290 05+% efficiency See Note 4 TRL 7, See Note 2
Pre-cooler Compact micro-channel heat exchanger
70 83 25 82 5 C Pinch Point 3 atm dP
See Note 3 TRL 7, See Note 1
Note 1: TRL 7 at the completion of a compantion DOE SunShot Project in 2016 (DE-EE0005804) Note 2: TRL 7 at the completion of a compantion DOE SunShot Project in 2013 (FC26-05NT42650) Note 3: Materials and manufacturing assumptions for cost and performance Note 4: Turbomachinery layout and design is being adressed in other DOE sponsored programs (DE-EE0005804)
Critical Components • Supercritical oxy-combustor for solid fuels
– Novel, low TRL component • Compact, micro-channel heat exchanger
– Initial development under SunShot DE-EE0005804 – Tolerance to particulate loading and cleaning methods
should be demonstrated • Coal-water slurry feed
– Water content has large impact on cycle performance • Particulate removal
– Represents a technical challenge – Potential source for significant thermal and efficiency
losses
DE-FE0009395 Project Closeout 2/21/2014
SwRI Oxy-Combustor Concept • Pulverized coal + water slurry
– Recycle water from combustion loop cleanup
– Water provides flame temperature control
• Rotating impeller fuel injector – Optimize shear-mixing of slurry,
CO2, and O2 – Controlled fuel injection rate
through impeller, O2 injection controls flame position
• CO2 cooled liner – Flame position, diffusion, and
dilution control – Flame centering – Wall temperature buffering
Coal Slurry
Liner Casing
Impeller
sCO2 O2
Mixing Zone
Motor
O2
Startup: Fuel (NG, Oil) + Pilot/Torch Igniter
DE-FE0009395 Project Closeout 2/21/2014
Combustor Design • Designed to feed a coal-water
slurry and O2 into supercritical CO2 – Inlet Temperature 450 C (842 F) – Inlet Pressure 96.5 bar (1400 psi) – Firing Temperature 700 C (1292 F)
• Limited data on coal combustion at elevated pressures
• Combustor design through simulation, augmented with coal combustion properties testing
• Flow rates at 550 MWe – Coal 50 kg/s – O2 80 kg/s – H2O 50 kg/s – CO2 4000+ kg/s
Rotary Atomizer
O2 Feed
Coal-water slurry feed
CO2 Feed
Combustion zone
CO2 Feed
Inner liner
Concept
Analysis
Design
Coal Slurry CFD Modeling – Particle Physics Coal Slurry Droplet Physics: DPM (Discrete Phase Model)
– Evaporation (heat transfer via convection and radiation) – Devolatilization of Coal – Gas Phase Reactions:
• C1.18H3.32O0.68N0.0503S0.224 + 1.09O2 1.18CO + 1.66H2O + 0.0251N2 + 0.0224SO2 • CO + 0.5O2 CO2 Residence Time (s)
Example: 100 𝜇𝜇m slurry particle size (50/50 coal-water, wt. %) using stochastic tracking for turbulent dispersion of particles.
CO2 inlet
O2 inlet Coal feed
Slurry injection
O2 injection
Combustion zone
Supercritical Oxy-combustor
• Completed initial design during Phase I – Sized for 1 MWth – Flow optimization with
reactions using Fluent and Chemkin
– Structural analysis for 100 atm, 650 C
• Initial test stand design to demonstrate the swirl combustor
DE-FE0009395 Project Closeout 2/21/2014
Micro-channel compact heat exchanger tolerant of particulate loading
• Compact, low cost heat exchangers are a key technology impacting footprint and cost of the supercritical oxy-combustion cycle – Microchannel heat exchangers are currently at a low
TRL, but are actively being developed for multiple applications including supercritical CO2 power cycles.
• It is expected that 1-5 micron may pass through the cyclone separator – Heat exchanger sparing and cleaning are important
considerations.
DE-FE0009395 Project Closeout 2/21/2014
CWS Alternatives
• Water concentration has a direct influence on combustion efficiencies – Loss due to latent heat
of vaporization
• Steam is not an asset for this cycle configuration
• Alternative injection technologies include – sCO2 as a slurrying agent – Posimetric pump
DE-FE0009395 Project Closeout 2/21/2014
% Water/Coal
by weight
% Efficiency
(HHV)
% Efficiency
(LHV)
0.0 37.50 38.90
25.0 35.18 36.51
50.0 29.70 30.80
sCO2 Slurry Feed Concept • Variation on the LICADO
process and the work of Botero
• Utilize a selective agglomeration process to separate pulverized coal based on carbon content
• High carbon content is entrained in CO2
• Two operational modes – Separate below combustor
pressure and pressurize slurry – Separate at elevated pressure
using CO2 boost
DE-FE0009395 Project Closeout 2/21/2014
Particulate Removal • Cyclone separator used to
remove fly ash from hot gas stream prior to the micro channel heat exchanger
• Fly ash must be captured from underflow and depressurized for treatment or removal
• Two concepts identified for further investigation – Lock chamber installed in
between two off-phase control valves (left)
– Water injection with orifice pressure reduction (right)
DE-FE0009395 Project Closeout 2/21/2014
BENCH SCALE TESTING
DE-FE0009395 Project Closeout 2/21/2014
Bench Scale Testing
• Combustion properties of pulverized coal in CO2 – Coal slurry preparation – Injector visualization – Combustion testing using the IQT
• Rotary atomizer visualization – Evaluate idealized atomizer for atomizing coal slurry
into CO2 – Density ratio O(1) compared to O(100) to O(1000) for
typical rotary atomizer applications – Documented in final report
DE-FE0009395 Project Closeout 2/21/2014
Combustion Properties Testing
• Measure autoignition delay for pulverized coal in supercritical CO2
• Evaluated using SwRI’s Ignition Quality Tester (IQT) – Standard test apparatus for developed by SwRI
• Preliminary work included slurry preparation, injector modification, injector visualization
DE-FE0009395 Project Closeout 2/21/2014
Slurry Preparation
• PRB coal provided by CPS Energy of San Antonio
• Refined to 15 µm and 7 µm for compatibility with the IQT injection system
• Slurries of varying ratios prepared using water, iso-octane, and tolunine
DE-FE0009395 Project Closeout 2/21/2014
Particulate distribution and agglomeration in a 20% coal and iso-octane slurry
Injector Visualization
• Need to verify spray pattern using modified IQT injector – Ensure proper distrubution – Minimize contact with IQT wall
• Utilize Optical Bomb operated by SwRI Div. 3 – Used for combustion testing and visualization – Rated for pressure, not temperature and pressure
DE-FE0009395 Project Closeout 2/21/2014
Stock Injector Modified Injector
Injector Visualization
DE-FE0009395 Project Closeout 2/21/2014
1/5400 s 2/5400 s 3/5400 s
Diesel into air at 12.8 bar with
needle valve
Diesel into air at 1 bar with
needle valve tip removed
Sand slurry into air at 1 bar
with needle valve tip removed
Slurry is carried with greater momentum compared to typical diesel injection
IQT Autoignition Delay Testing • The Ignition Quality Test Apparatus (IQT™) is
a bench top constant-volume combustion chamber
• Used to quantify the reactivity of fuel and lubricants
• Method – Heated combustion chamber is filled with
compressed gas at elevated pressure – Test fluid is injected using a pump-line-nozzle
injector – Ignition delay is then measured as shown at
lower right • Modifications for Coal Slurry
– Stock fuel pump replaced with a variable displacement pump
– Injector tip modified to flow solid fuel slurry – Testing run in diagnostics mode to acquire
needle lift and combustion trace on an oscilloscope
DE-FE0009395 Project Closeout 2/21/2014
Typical Test Results
• 40% coal – iso-octane slurry with 15 µm coal particles clogged after two injections
• 20% coal – iso-octane slurry with 7.5 µm coal particles provided consistent ignition
DE-FE0009395 Project Closeout 2/21/2014
Autoignition Delay Timing
Fuel Skin Temperature Charge Air
Temperature Avg. Ignition Delay [°C] [°C] [msec]
Iso-
Oct
ane
568 538 9.7748 500 475 12.4238 450 420 27.321
437.5 411 32.543 431 406 38.695 428 400 38.982 426 399 40.705 425 398 42.9845
425.5 398 40.852 400 376 no-combustion
20%
Coa
l Con
cent
ratio
n,
7.5𝜇𝜇
m P
artic
le S
ize 423 395 20.052
423 395 14.968 420 394 21.167 415 391 28.653 400 376 27.879 400 373 46.721 400 373 27.209
DE-FE0009395 Project Closeout 2/21/2014
0
10
20
30
40
50
350 400 450 500 550
Aver
age
Igni
tion
Dela
y (m
s)
Charge Air Temperature (oC)
20% Coal - Iso-Octane Slurry, 7.5 µm\
0
10
20
30
40
50
350 400 450 500 550
Aver
age
Igni
tion
Dela
y (m
s)
Charge Air Temperature (oC)
Iso-Octane
PATH FORWARD
DE-FE0009395 Project Closeout 2/21/2014
Proposed Phase II: 1 MWth Supercritical Oxy-combustor Demonstration
• Test bed for technology development – Supercritical combustor – Particulate cleaning of the compact microchannel heat exchanger – Solids injection at pressure (sCO2 slurry, posimetric pump) – Solids removal at pressure
• Advance technologies from TRL 2, Technology Concept, to TRL 6, Pilot Scale System Demonstrated in a Relevant Environment
• Operate with coal water slurry, plan for dry feed or sCO2 slurry extension
Supercritical Oxy-combustor
Cyclone Separator
Underflow Particulate
Separation
Boost Compressor Water
Scrubber Supercritical
Oxy-combustor
Cyclone Separator
Underflow Particulate
Separation
Water Scrubber
Cooling Tower
DE-FE0009395 Project Closeout 2/21/2014
Critical Components Development Path
• Supercritical oxy-combustor for solid fuels – Initial design completed for Phase II Demonstration
• Compact, micro-channel heat exchanger – Tolerance to particulate loading and cleaning methods
should be demonstrated • Coal-water slurry feed
– Coal-sCO2 slurry – Posimetric pump
• Particulate removal – Adaption of conventional technologies
DE-FE0009395 Project Closeout 2/21/2014
Oxy-Combustion Test Loop • Test Hardware
– Charge Compressor or Pressurized CO2 Feed – Combustor
• Oxygen feed • Coal slurry feed
– Cyclone separator • Solids removal and handling
– Recuperater – Water scrubber and cleanup
• Liquid removal and handling • CO2 removal and handling
– Cooling Tower – Boost Compressor
• Operating Conditions – 450 – 650 C (800 – 1200 F) – 102 atm (1500 psi)
• Flow Rates: 1 MWth – 3.4 kg/s Hot side flow rate – 3.2 kg/s CO2 recycle – 0.05 kg/s Coal feed – 0.08 kg/s O2 Feed – 4.25 kg/s H2O Recycle
B278
DE-FE0009395 Project Closeout 2/21/2014
WRAPUP
DE-FE0009395 Project Closeout 2/21/2014
Development of a Supercritical Oxy-combustion Power Cycle with 99% Carbon Capture
Southwest Research Institute® and Thar Energy L.L.C. • Engineering development, technology
assessment, and economic analysis used to evaluate technical risk and cost of a novel supercritical oxy-combustion power cycle
• Optimized cycle couples a coal-fired supercritical oxy-combustor with a supercritical CO2 power cycle to achieve 40% efficiency at low firing temperature, 650 C
– Cycle is limited by TRL of critical components • COE $121/MWe with 99% carbon capture
– 49% increase over Supercritical Steam Without Carbon Capture ($81/MWe), exceeding the 35% target
– 21% reduction in cost as compared to Supercritical Steam with 90% Carbon Capture ($137/MWe).
• Phase 1 completed in September 2013, Extended to March 2014 to cover closeout
• Budget $1.25 million • Ready to demonstrate supercritical oxy-
combustor and critical low TRL technologies
Supported by DOE Project DE-FE0009395