DCP 12 May 2010 Jan Godlewski PH-DT-PO1
DETECTOR COOLING PROJECTWP2 CO2 activities status report
Jan Godlewski PH-DT-PO
https://espace.cern.ch/CO2/default.aspx
DCP 12 May 2010 Jan Godlewski PH-DT-PO2
Cooling plant for tests
Actual statusActual status Next stepsNext steps Missing partsMissing parts Tests programTests program
DCP 12 May 2010 Jan Godlewski PH-DT-PO3
Status
Test stand at cryolab Pressure test (120 bar) done Chiller connected and tested Sensors installed and connected to control rack DAQ checked and debugged
Possibility of remote log-in to follow test stand function
ALICE Silicon Pixel Detector interested in CO2 activities Claudio Bortolin and Rosario Turrisi have joined CO2 group
DCP 12 May 2010 Jan Godlewski PH-DT-PO4
Minutes from the last meeting
DCP 12 May 2010 Jan Godlewski PH-DT-PO5
P&I
DCP 12 May 2010 Jan Godlewski PH-DT-PO6
CO2 progress and issues on the control system
CO2 PLC PVSS UNICOS project creation status:
1 – Excel specification preparation √2 – PLC hardware configuration √3 – PLC & PVSS instance generation √4 – Process logic program preparation √5 – Specific functions preparation √ 6 – Code compilation √7 – Loading to PLC √8 – PVSS Data Server configuration √9 – PVSS panels creation √10 – Commissioning & operation – began – all sensors values are archived
SCADA server
Logic Generator
Instance Generator
Specification
SIEMENS PLC
From Łukasz
DCP 12 May 2010 Jan Godlewski PH-DT-PO7
CO2 progress and issues on the control system
Signal-electrical installation:
1 – Control rack completed √2 – Plant frame equipped with cable trays √2 – Signals cables in place and 90% connected √3 – Power cables in place and connected √4 – All sensors ,actuators and cables labeled √5 – All PT100 connected with additional connector to ensure in case of failure fast sensor replacement √
From Łukasz
DCP 12 May 2010 Jan Godlewski PH-DT-PO8
Missing parts and things to do
Missing parts Accumulator from NIKHEF
Hans Postema in contact with NIKHEF We are requesting it for mid of June
Expansion valve for accumulator cooling Should come these days
Some sensors Valves extensions for cold running
Still to do Installing and connecting accumulator Installing valves extension Insulation Final commissioning of control system
DCP 12 May 2010 Jan Godlewski PH-DT-PO9
Summary
CO2 test standCO2 test stand Test stand ready for “warm” operation We are waiting for accumulator from NIKHEF First thing to test will be ATLAS Pixel stave (first half of June)