78
KARNATAKA STATE HIGHWAYS IMPROVEMENT PROJECT-II CONSULTANCY SERVICES FOR PREPARATION OF DETAILED PROJECT REPORT, BID DOCUMENTS AND ASSOCIATED INSTRUMENTS EPC PACKAGES FUNDED BY WORLD BANK DETAILED PROJECT REPORT - EPC PACKAGES LINK 67B - H CROSS TO CHINTAMANI BYPASS E2436 ENVIRONMENTAL MANAGEMENT PLAN V9 -. .....,' FILE coey Prepared for: Govt of Kamataka Public Works Dept. (PIU, KSHIP) April 2009 SCOTT WILSON LTD. UK (in JVwith) SCOTI WlLSON INDIA PVf. LTD. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

DETAILED PROJECT REPORT -EPC PACKAGES …documents.worldbank.org/curated/pt/...It can be observed from the ambient air quality of the project area except increase in suspended particulate

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

  • KARNATAKA STATE HIGHWAYS IMPROVEMENT PROJECT-II

    CONSULTANCY SERVICES FOR PREPARATION OF DETAILED PROJECT

    REPORT, BID DOCUMENTS AND ASSOCIATED INSTRUMENTS

    EPC PACKAGES FUNDED BY WORLD BANK

    DETAILED PROJECT REPORT - EPC PACKAGES LINK 67B - H CROSS TO CHINTAMANI BYPASS E2436 ENVIRONMENTAL MANAGEMENT PLAN V9

    -.

    .....,'

    FILE coey

    Prepared for:

    Govt of Kamataka

    Public Works

    Dept.

    (PIU, KSHIP)

    April 2009

    SCOTT WILSON LTD. UK (in JVwith) SCOTI WlLSON INDIA PVf. LTD.

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

  • Kan:.ataka State Highways Improvement Project - II Detailed Project Report Consultancy Services for Preparation ofDPR, Bid Documents Volume I Main Report and Associated Safeguard Instruments - EPC Packages Funded by World Bank

    DETAILED PROJECT REPORT - LIST OF CHAPTERS WITH APPENDCIES AND ANNEXURES SLNo. Volume No. Title Annexure I Appendix

    Volume I 1

    ,-,;,,"

    Volume II 2

    ,"", i

    Volume III 3

    Main i:'

  • Kamataka State Highways Improvement Project - II Detailed Project Report Consultancy Services for Preparation ofDPR, Bid Documents Volume IV -Part 1: EMF Report and Associated Instruments EPC Funded World Bank

    CHAPTER 1: INTRUODUCTION TABLE OF CONTENTS 1 INTRODUCTION ........................................................................................................................................ 1

    1.1 PROJECT BACKGROUND .......................................................................................................................... I

    1.2 SCOPE OF ENVIRONMENTAL ASSESSMENT: ............................................................................................. 1

    1.3 ENVIRONMENTAL MITIGATION AND ENHANCEMENT MEASURES ..•..••.......••......•......•••••................•••....... 2

    1.4 CLEARANCES REQUIRED FOR THE PROJECT....................••..•.........................•.......•••........•••...•.•.......••.•....• 3

    LIST OF TABLES

    TABLE 1: ROAD SELECTED FOR IMPROVEMENT IN KSHIP-II, EPC•..•....•.••.................•.......•......•.•..•........•.....•...•..... 1

    TABLE 2: ENVIRONMENTAL APPROVALS AND CLEARANCES REQUIRED PRIOR TO CONSTRUCTION PHASE................ 3

    TABLE 3: CLEARANCE REQUIRED FOR THE PROJECT - 67B .......•.•.........••........•.........•.......•.......••...............••.••.....•..• 3

    -

    Ii...

    Chapter 1: Introduction Scott Wilson

  • Karmtaka State Highways Improvement Project - II Detailed Project Report Consultancy Services for Preparation of DPR, Bid Docwnents Volume IV - Part 1: EMP Report and Associated Safeguard Instruments - EPC Packages Fund_ed_b-'y'-W_or_ld_B_ank_______________

    On the basis of above categorization, the proposed improvement of road link with less than 30 Km length involving additional right of way less than 20m involving land acquisition is not under the purview of EIA Notification. The project need not obtain environmental clearance from State Environmental Appraisal Committee, Karnataka. The length and RoW details of the proposed road link are as follows

    Average acquisition ,I l SH No. ! Length inILink Location of Roads width required (M)lm I Kms

    I - i 67B ~ Cross - Chinatmani Bypass (Corridor 65F i o82 29.0 ; ~~c~ I 1.3 Environmental Mitigation and Enhancement measures

    To achieve the environmental management standards, EMP has been prepared for the road project as

    per the requirements of World Bank OP 4.01. Mitigation measures have been devised in such a way

    that the contractor would be able to execute accurately. All studies relating to the project has finally

    come out with an implement able Environmental Management Plan. This plan has been recommended for feasible and cost-effective measures to avoid, prevent or reduce significant negative impacts on environment to acceptable levels. Apart from mitigation of the potential adverse impacts on the

    environmental components, the EMP identified opportunities that exist for the enhancements along the corridor; some road user facilities such as bus lay bys and waiting sheds (part of civil work) and parking areas. In order to implement the environmental management plan contractor needs to prepare specific plans for, Debris Disposal Plan (Includes collection, transportation, haul roads and disposal); Construction phase water management plan; Management plan for construction camp, Labour camps; Management plan for plant sites (WWM plant, Hot mix, Crushers etc.,); Accidents, Safety and Traffic management plan. EMP includes detailed specifications, bill of quantities (BOQ), execution drawings and contracting procedures for execution of the environmental mitigation and enhancement measures suggested. Since the project is to be implemented under ICB or NCB contracting, highest standards of project plarming, project management and project implementation are to be maintained. Therefore the contractor needs to resort to international good practices not only in the implementation of EMP but also in l1e construction activities. The success of the project management is directly linked to the effective implementation of the EMP measures. All mitigation measures, avoidance measures and environmental enhancement measures recommended are to be implemented in a timely and phased marmer. Proper understanding of all environmental management measures especially the. EMAP is a

    pre-requisite for all those working from the contractor's side.

    The institutional arrangements required at the PWD, contractors. and the CSC (Construction Supervision Consultant) have been defined properly for the smooth implementation of the project

    components. A positive attitude from the project management and the individual professional or staffs are always a prerequisite for success of the EMP implementation.

    The EMP specifies the environmental supervision, monitoring. The monitoring programme specifies

    parameters, reference standards, monitoring method, frequency, duration, location, reporting

    responsibilities, and other inputs (e.g., training). The EMAP on the other hand provides an action plan

    showing the mitigation measures, time of implementation, who will implement, at what location and

    who will supervise etc., This is provided for pre-construction, construction and post construction

    stages. The EMP listed all mandatory government clearance condition, and the statutes for procuring

    clearances.

    Cha,ter 1: Introductio·: Scott Wilson

  • Karnataka State Highways Improvement Project - II Detailed Project Report Consultancy Services for Preparation ofDPR, Bid Documents Volume IV Part I: EMP Report and Associated Safeguard Instruments - EPC Packages Funded by World Bank

    1,1

    r~·

    i .....

    CHAPTER 2: SUMMARY OF IMPACTS TABLE OF CONTENTS 2. S~Y OF IMPACTS ....................................................................................................................... 1

    2.1 AIR ENVIRONMENT ................................................................................................................................... 1

    2.1.1 Pre Construction & Construction Stage ......................................................................................... 1

    2.1.2 Operation Stage .............................................................................................................................. 2

    2.2 NOISE ENVIRONMENT ............................................................................................................................... 2

    2.2.1 Impact ofNoise during Pre-Construction Stage and Construction Stage ...................................... 2

    2.2.2 Impact ofnoise during operation Stage .......................................................................................... 3

    2.3 WATER ENVIRONMENT............................................................................................................................. 3

    2.4 LAND ENVIRONMENT ................................................................................................................................ 4

    2.4.1 LiIIld use Impact................ ........................................................................................................... 5

    2.4.1.1 Land use Impact at Construction phase ......................................................................................................6

    2.4.1.2 Land use impact during operation phase ....................................................................................................6

    2.5 BIOLOGICAL ENVIRONMENT ..................................................................................................................... 6

    2.5.1 Flora ............................................................................................................................................... 6

    2.5.2 Fauna.............................................................................................................................................. 6

    2.6 SOCIO ECONOMIC ENVIRONMENT ............................................................................................................. 6

    2.6.1 Cultural properties ......................................................................................................................... 7

    2.6.1.1 Temples and other Community assets .............................................................. .......................... 7

    2.6.1.2 Archaeological Structures ......................................................................................................... 7

    2.7 SMMARY OF PROJECT IMPACTS: ..................................................................................................... 7

    LIST OF TABLES

    TABLE 2-1 : EMISSION FACTORS OF DIFFERENT VEHICLES (GIKM) ........................................................................... 1

    TABLE 2-2: POLLUTION LOAD OF POLLUTANTS ALONG THE PROJECT ROUTE (IN TONsIKM) .................................. 1

    TABLE 2-3: NOISE LEVEL DUE TO TRAFFIC ALONG THE PROJECT ROAD .................................................................. 3

    TABLE 2-4: WATER SUPPLY UNITS LIKELY AFFECTED ALONG THE PROJECT AREA ................................................... 4

    TABLE 2-5: MAJOR BORROW MATERIAL REGIONS ALONG THE ROUTE ................................................................... 5

    TABLE 2-6: LIST OF IMPACTED TREES DUE TO PROPOSED PROJECT ROAD ............................................................... 6

    TABLE 2-7: SHIFTING OF ELECTRICAL AND TELEPHONE POLES ................................................................................ 7

    TABLE 2-8: COMMUNITY ASSETS GETTING AfFECTED ALONG THE PROPOSED ROAD .............................................. 7

    TABLE 2-9: SUMMARY OF ENVIRONMENTAL IMPACTS AND IsSUES......................................................................... 7

    -.:;;---::~--;;:---~-----;----------------

    (:haptL'r 2: Summary ofImpacts Scott Wilson

  • K.nnataka State Highways Improvement Project· II Detailed Project Report Consultancy Services for Preparation ofDPR, Bid Documents Volume IV Part 1: EMP Report and Associated Safeguard Instruments - EPC Packages Funded by World Bank

    diesel generators; stone crushing unit operations in the stone quarries and handling and storage of aggregates and sand at locations of batch mixing plants.

    It can be observed from the ambient air quality of the project area except increase in suspended particulate matter all other air quality parameters such as RPM, NOx, SOx, Pb, CO and HC are within

    the limits of ambient air quality standard.

    2.1.2 Operation Stage

    The introduction of new pavement will smoothen and widen the road, so the generation of fugitive

    dust is reduced during the operation stage and suitable pitching and embankment turfmg will control

    the erosion dust emission.

    1 he levels of S02, HC and NOx are likely to come down to greater extent by the operations of new

    roads with extensive savings in conswnption of fuel. There will be reduction of toxic gases being

    released. There may be localized impact from pollution with increase in nwnber of vehicles running on the road, adulterated fuel supply and poor maintenance of vehicles.

    The measures for the avoidance and mitigation measures for controlling the air pollution are in table

    3.1 Environmental mitigation plan. The increase in the width of pavement and landscaping decreases

    the dust emissions by traffic during operational phase.

    2.2 Noise Environment

    The baseline noise levels monitored in the project area indicate baseline noise level, which exceeds the

    permissible limits for silence areas such as schools, courts and hospitals. For other land uses the noise

    levels are well within the specified limits. But noise levels would increase significantly during construction phase due to movement of construction machinery and vehicles during construction &

    operation respectively. Thus, noise is a major area of concern, especially since a nwnber of sensitive

    r~ceptors have been located within Impact zone and are close to RoW.

    The impacts on noise due to the project will be of significance in both the construction as well as the

    operation stages.

    2.2.1 Impact of Noise during Pre-Construction Stage and Construction Stage

    Noise levels during the pre construction stage are mostly expected to be indicative of prevalent

    baseline levels apart from localised noise levels at locations where pre construction stage activities

    such as establishment of workers camps, stockyards are taking place. There will be increased noise

    levels due diversion of traffic on unpaved roads only for a short duration during the pre construction

    stage. Moreover, as these activities are not likely to be placed near settlement locations the increased

    noise impact is bound to be negligible.

    Various activities of road construction will increase noise levels in impacts zone of the project

    corridor. The construction activities includes the excavation for foundations and grading of the site and

    the construction of structures and facilities, movement of heavy vehicles, loading, transportation and

    unloading of construction materials and also there will be indirect influence which will be cwnulative

    to ambient noise level due to activities such as blasting at stone quarry sites, crushing plants, asphalt

    production plants, produce significant noise during construction stage.

    Enhancement in noise levels depends on many key factors such as traffic intensity, type and condition

    of the vehicles plying on the road, acceleration/deceleration/gear changes by the vehicles depending

    on the level ofcongestion and smoothness of road surface (IRC: 104-1988).

    2: Summary of Impacts 2 Scott Wilson

  • I

    Karnataka State Highways Improvement Project - II Detailed Project Report C·)nsultancy Services for Preparation of DPR, Bid Documents Volume IV Part 1: EMP Report 3lld Associated Safeguard Instruments EPC Packages Funded by World Bank

    Table 2-4: Water supply units likely affected along the project area

    Water W t lOver Head Publica er .Bore WaterHandLink cisternlPuLocation ToileUMaL' TanklGLPumps Wells TapsID mes ReservoirmpHouse n hole 67B 1 2H Cross - Chinatmani j 0 5 0 10

    Bypass (cor 65 F -In)

    Contractor needs to keep a copy of the EA and EMP in the site office. Other than the construction \vater issue, no major pollution points have been identified through out the length. No construction waste shall be disposed off in to the water bodies/valley/nala. The construction vehicles are prohibited from entering the water bodies for any purpose (including cleaning) other than the legitimate requirements to avoid major pollution points due to Petroleum oil and lubricants.

    It is very fundamental to conserve the water by way of constructing recharge pits wherever feasible

    along the project road. These recharge pits harvest rainwater from road surface to improve the ground w'ater table. Refer Appendix -2 for typical drawing.

    The construction water requirement could be an issue during construction at certain stretches of the project road. As a part of the planning, contractor has to prepare a contractor's construction water management plan as per the guidelines provided in Appendix -15,

    2.4 Land Environment

    :Most of the available stone material along the project area is granites gneiss and granitic schist. The metals required for the road construction is available very close to road enroute. Use of explosives is .,bsolutely necessary to break open the aggregates in the stone quarry. In order to use these materials, c:ontractor will have to establish a number of crushers along the project route from which impact will be very large and permanent in nature.

    There will be exploitation of natural resources and it also reduces natural beauty of the landscape and dters contours of the geographical region. There will be formation of deep and large depression from the quarry operations. This will be fatal for both the animals and humans in case fall in to depressions from surrounding habitat. Some times there is possibility of flying fragments of stones from l.mcontrolled blasting using explosives surrounding to quarry area prevails.

    Suspended particulate matter generatedn leads to degeneration of plant species and retards the growth of plant species as it reduces the transpiration process and also there will be considerable impact over -:he occupational workers in the quarries. During monsoon there will be collection of water in deep ditches this serves as breeding sites for mosquitoes.

    Borrow material includes gravel, murrum and sand. Generally gravel is collected from the wasteland, which is notified from Government or with the consent of farmers in case of farmland. Sand will be collected from river valleys this alters the course of flow and velocity of flow of water in rivers. Transport of the borrow materials to the construction sites is of significance, as almost all such areas • are accessible through dirt tracks. Spillage and compaction of soil along these tracks will be a

    significant irr.pact. Special transport facilities with special measures are required to transport

    bituminous material from the refmeries :0 work sites, as they are highly inflammable and to control accidental spills. Proper protection measures need to be worked out for the minimizing of such

    impacts during the haulage of borrows materials. A major source of dust during the construction stage

    is from stone crushing operations from the crusher and the vibrating screen. The dust, in addition causes an eyesore, reduces visibility thereby increasing safety concerns. Rehabilitation of borrows

    areas from which earth has been excavated, is a potential problem, which needs to be addressed and need to comply with management plan Appendix - 17. In addition to visual Hght, safety issues shall

    Chapter 2: Summary ofImpacts 4 Scott Wilson

  • Kamataka State Highways Improvement Project - II Cnnsultancy Services for Preparation ofDPR, Bid Documents arid Associated Safeguard Instruments - EPC Packages Funded by World Bank

    Detailed Project Report Volume IV - Part I: EMP Report

    2.4.1.1 Land use Impact at Construction phase

    During construction phase contractor activity will go beyond Building line. Even in secondary

    construction sites like borrow areas, quarry sites and water resource points the contractor's activity

    will cross the limit depending upon the demand for material availability. These will create demand and

    disturbances to the near by agricultural area, built up area etc. In case of any such issues it should be

    cleared within shortest period. Potential community impact related to economy growth are closely

    related to land acquisition, aesthetic and landscape considerations; noise, air quality etc., Other than

    the mitigation in these area no additional mitigation actions are warranted.

    2.4.1.2 Land use impact during operation phase

    Immediately after the construction phase it is necessary to ensure that no further deterioration or

    major land use change such as ribbon development will take place.

    2.5 Biological Environment

    2.5.1 Flora

    Total number oftrees to be felled in the project area for the road expansion is presented in Table 2.6

    Table 2-6: List of Impacted Trees due to Proposed Project road

    i Link ID

    Description of Link Link

    Length

    Trees Girth (

  • I

    Kamataka State Highways Improvement Project - II Detailed Project Report Consultancy Services for Preparation ofDPR, Bid Documents Volume IV -Part 1: EMP Report an.' Associated Safeguard Instnnnents - EPe Packages Funded by WorId Bank

    ....

    Addressed inAddressed in Design I Addressed in ImplementationImpacts! Issues O~eration stage

    stretches. Treatment of , design and BoQ. clean and slopes embankment slopes. identified for

    protection. Debris disposal The contractor shall prepare aDebris disposal has been The disposed areas

    given adequate importance to Debris Disposal Plan. need to be the level it requires. There The excess excavated material maintained by are many number of disposal during the road construction strengthening of locations such as burrow would be safely stored, turfing and areas identified along the transported and disposed of in the vegetation over the proposed road in consultation identified debris disposal areas. disposed site to with the local communities. avoid erosion of the

    i Guidelines for the disposed materials. preparation of the Debris disposal plan prepared.

    Religious and Cultural properties will be Provide enhancement measures Other than the safety Archaeological impacted. Local community according to the cultural property monitoring and sites & consultations & alignment rehabilitation programme. The maintenance of the Properties project will follow up thechanges to minimize the parking area no other

    impacts. implementation of the action would be enhancement measures with the required. permission from Dept.

    Demolition of An effective sequencing of theAll such unstable areas will No action required Retaining wall, be rehabilitated especially construction work would be breast wall etc., those in the vicinity of the required close to residential buildings. structures especially houses. Air pollution Widening of the road with Siting of construction camps Traffic emissions

    improved surface for the away from the settlements and control as per the smooth £low oftraffi other sensitive receptors along the legal requirements.

    construction corridors. Contractor , Regular air sampling shall resort to best practices to and monitoring reduce air pollution. during operation

    stage. Noise pollution Baseline data monitored and Use best equipments and Monitor noise levels

    recorded as a benchmark. machineries for reducing noise at periodically to Provision of noise barriers construction sites. Follow all understand the for sensitive receptors such procedures as per the legal norms. deviation from the as schools, hospitals etc. Use PPE wherever necessary. bench marks.

    Siting of construction camps ! away from sensitive receptors.

    Water Baseline data monitored and In acute water scarcity areas, the Monitor' water recorded as a benchmark. use of potable water for dust quality parameters Suitable measures to prevent suppression should be reviewed periodically to the silt and other pollutants regularly. Regular water understand the from reaching the nearby sprinkling required for ; deviation from the water bodies ! suppression of dust. benchmarks.

    Land The land requirement has During implementation, the Need to monitor requirements been considerably reduced by planned requirements will be ribbon

    proper i'lanning to match the reviewed and implemented to the developments. All requirements with in the actual requirement. Reinstate new construction ROW with minimum land work areas on completion of shall be sufficiently I acquisition, realignments and works. away from the

    I bypasses. project road edge.

    L I Displacement of I Minimized the displacement RAP implementation to involve Monitor and evaluate

    PAPs by proper planning in an NGO to ensure that the. (M&E) the selecting .final al~g.nment. policies are adhered to. I effectiveness of RAP iI' Com ensatIOn prOVISIOn as, implementation. I

    Chapter 2: Summary of Impacts 8 Scott Wilson

  • K amataka State Highways Improvement Project -II Detailee Project Report C)nsultancy Services for Preparation ofDPR. Bid Documents Volume IV Part 1: EMP Report and Associated Safeguard Instruments - EPC Packages Fun..~ed by World Bank

    CHAPTER 3: MITIGATION MEASURES TABLE OF CONTENTS 3. l\IITIGATION MEASURES .......................... _ .......................................................................................... 1

    LIST OF TABLES TABLE 3-1: ENVIRONMENTAL MANAGEMENT ACTION PLAN (PART-A) .................................................. 2

    TABLE 3-2: ENYIRONMENTALMANAGEMENTMEASURES-BRIDGES (PART-B) ................................................... 21

    jf~.

    -

    :::hapter 3: \1itigation Measure~ Scott Wilson

  • --

    -- ---

    i ( t 1 i

    Karnataka State Highways Improvement Project - II Detailed Project Report Consultancy Services for Preparation of DPR, Bid Documents Volume IV Part 1: EMP Report a~d AsSC)ciated Safeguard Instruments - EPC Packages Funded by World Bank

    Table 3-1: ENVIRONMENTAL MANAGEMENT ACTION PLAN (part-A) --'--',--- -- -~---

    ResponsibilityEnvironmental ReferenceSl. No. Management Measures SupervisionlPlanning andIssue Document

    MonitoringExecutioni-c:::-::c-. PRE-CONSTRUCTION STAGE

    Pre-construction activities by Karnataka state Hi!bways Improvement Pro.tect (KSHIP)

    The acquisition of land and private properties shall be carried out in accordance KSHIP,LA Act 1984 and Land Acquisition with the RAP and entitlement framework of the Project. Revenue Dept, its Amendments, PI KSHIP

    (If required) KSHIP has to ascertain that acquisition of land in the post design phase are CollaboratingKSHIP

    addressed and integrated into the EMP and relevant contract documents. Agencies-Clearance of Advance notice, as per RAP shall be given to the encroachers & squatters present

    KSHIP and in the Corridor of Impact, who need to be relocated. All R&R activities shall be EncroachmentlSqua

    RAP documents Revenue KSHIPP2 tters (change in undertaken. Entitlements as per KSHIP entitlement framework shall be completed

    Authorityland use) before construction starts. -

    Trees shall be removed from the Corridor of Impact before the actual commencement of the work with the permission from the state Forest Department.

    Contractor/Age CSC and/Cutting"shall not start until the implementation of the project in that particular

    P3 Tree Cutting MoRTH 201.6 ncy engaged by KSHIPlocation of cutting 100% confirmed.

    KSHIPStacking, transport and storage of the wood shall be done as per the relevant norms.

    -

    AlI efforts shall be made to preserve trees including evaluation of minor design adjustments/alternatives (as applicable) to save trees. Specific attention shall be given for protecting giant trees, green tunnels and locally important trees (religiously important etc.). Detail of the trees affected due to the proposed project road in given in (Appendix - 10) Tree cutting is to proceed only after all the legal requirements including attaining

    Contractor/AgePreservation of of In-principle and Formal Clearances form the Forest Dept.lMoEF are completed CSC and/P4 Appendix -10 ncy engaged by Trees and subsequently a written order is issued to the Contractor. KSHIP

    KSHIPParticular species declared as "protected" by the State's Forest Dept. in the private land shall be felled only after due clearance from the Forest Dept. is obtained. In the event of design changes, additional assessments including the possibility to save trees shall be made. Systematic corridor level documentation for the trees cut and those saved shall be

    .Il'laintained by the KSHIP

    Relocation of All community utilities and properties i.e., hand pumps, open wells, water supply KSHIP, other

    P5 lines, sewer lines, telephone cables, buildings and health centers shall not be RAP document Agencies / Community KSHIP Utilities and relocated before construction starts in the pr2.ie,!!oad. Details _of the cOmmunity Contractor

    Chapter 3: Mitigation Measures 2 Scott Wilson

  • ---

    -- ------

    ----

    --- ----

    ----

    ;l}I i ~ .'Ie s "

    Kamataka State Highways Improvement Project - II Detailed Project Report Consultancy Services for Preparation of DPR, Bid Documents Volume IV Part 1: EMP Report and Associated Safeguard Instruments - EPC Packages Funded by World Bank

    ,---' Responsibility

    Environmental ReferenceSf. No. Management Measures Planning and SupervisionlIssue Document Execution Mon!torin2f------

    Wherever there is extremely water scarcity areas exist the Water sprinkling shall be limited to one time in the morning. To balance this deficient information boards shall be erected at appropriate locations with a message to "Dust prone area take precautions.

    Ail vehicles, equipment and machinery to be procured for construction shall confirm to the relevant Bureau of India Standard (BIS) norms. The discharge

    Air pollution Other Construction standards promulgated under the Environment Protection Act, 1986 and Motor Contractor/Control Act, and Vehicles, Vehicles Act, 1988 shall be strictly adhered to. EnvironmentalP.7.4 Noise Rules and KSHIPEquipment and The silent/quiet equipment available in the market shall be used in the Project. Specialist ofMotor Vehicle Machinery The Contractor shall maintain a record of PUC for all vehicles and machinery used CSCAct, 1988 during the contract period which shall be produced to EO, KSHIP IPWD's verificatin whenever required.

    P8 IdentificatiOl' and Selection of Material Sources

    Finalizing soil borrowing earth and all logistic arrangements as well as compliance

    to environmental requirements, as applicable, shall be the sole responsibility of the

    Contractor. (Appendix-l 7).

    The Contractor shall not start borrowing earth from selected borrow area until the

    formal agreement is' signed between landowner and Contractor and a copy is

    submitted to the CSC. Contractorl Locations finalized by the Contractor shall be reported to the Environmental EnvironmentalP.8.! Borrow Areas Appendix-16,17 KSHIPSpecialist ofCSC and he shall submit the report to KSHIP. Specialist of Planning of haul roads for accessing borrows areas shall be undertaken during this CSC stage. The haul roads shall be routed to avoid agricultural areas as far as possible and shall use the existing village roads wherever available. The environmental personnel of the CSC shall be required to inspect every borrow area location prior to approval. The CSC should include the Request for Inspection form for borrow area approval from the environmental point of view. Contractor shall finalize the quarry for procurement of construction materials after

    --

    assessment of the availability of sufficient quantity of materials, quality and other logistic arrangements. MoRTH 111.3 & Environmental

    P.8.2 Quarry In case the Contractor decides to use quarries other than recommended by DPR Appendix-17,19 Contractor Specialist of consultant, then the Contractor should give substantiation. CSC Contractor shall also work out haul road network and report to Environmental Specialist of CSC and CSC shall inspect and in tum report to KSHIP before

    Chapter 3: Mitigation Measures 4 Scott Wilson

  • --- --- --- ----- ---

    ---

    ---

    ---

    i i i

    Kamataka State Highways Improvement Project - II Detailed Project Report Consultancy Services for Preparation ofDPR, Bid Documents Volume IV - Part I: EMP Report and Associated Safeguard Instruments EPC Packages Funded by World Bank

    Res~onsibilityEnvironmental ReferenceSI. No. Management Measures Planning and Supervision!

    Issue Document Monitoring The Contractor as per prevalent rules shall carry out negotiations with the landowners for obtaining their consent for temporary use of lands for construction

    Execution

    Arrangements for Environmentalcamp!constructionlborrow areas etc. Appendix-I3,16,P 12 Temporary TJand Contractor Specialist ofTemporary land arrangements shall not be from the forest reserves except under 17Requirement CSCspecial permission circumstances where it is un avoidable due to the vast forest reserves in the PIA. The KSHIP shall organize Orientation Sessions and regular training sessions at all

    Orientation of EMP and other stages of the project. This shall include on-site training (general as well as in the Contractor!

    Implementing training plan KSHIPspecific context of a sub-project). These sessions shall involve all staff of KSHIP CSC and P 13 developed by Agency and KSHIPinvolved in the implementation of EMP, Environmental Specialists of CSC and KSHIPContractors Contractors.

    CONSTRUCTION STAGE Activities to be Carried Out by the Contractor Cl Site Clearance

    If required vegetation shall be removed from the construction zone before

    commencement of construction. All works shall be carried out such that the

    damage or disruption of flora other than those identified for cutting is minimum.

    Only ground cover/shrubs that impinge directly on the permanent works or

    necessary temporary works shall be removed with prior approval from the Environmental

    MoRTH 201 &Clearing and Environmental Expert of CSC. Contractor Specialist ofC.I.l The Contractor, under any circumstances shall not cut or damage trees and forest Appendix-tO, 20 Grubbing CSC, KSHIP reserves (refer Appendix-I3). Trees identified under the project shall be cut only after receiving clearance from the Forest Dept.lDoEFlMoEF (as applicable) and after the receipt of KSHJP's written permission in this regard. Vegetation only with girth size ofover 30 cm shall be considered as trees and shall be compensated, in the event of KSHIP's instruction to undertake tree cutting. Appendix-l provides guidelines for the preparation of the contractors Debris IDisposal of Debris disposal plan. This is mainly to deal with sUIplus debris materials that would be Environmentalfrom dismantling available after adjusting for all insitu applications. Specialist and structures, road Other debris generated due to dismantling of the existing road shall be suitably Residentsurface and hill MoRTH202reused in the proposed construction zone, subjected to the structure suitability of ContractorC.l.2 Engineer ofAppendix-lward side the materials and approval of the Resident Engineer and Environmental Expert of

    CSC, EC, excavation for CSC as follows: KSHIPwidening of the For filling and leveling of School grounds and proposed parking areas.

    road The sub grade of the existing pavement shall be used as embankment fill material.

    Chapter 3: Mitigation Measures 6 Scott Wilson

  • I , J i i

    Kamataka State Highways Improvement Project - II Detailed Project Report Consultancy Services for Preparation of DPR, Bid Documents Volume IV - Part 1: EMP Report and Associated Safeguard Instruments - EPC Pa.ckages Funded by World Bank

    Sf. No. Environmental Issue Management Measures

    and Natural Habitats like Grasslands. Such spoils from excavation can be used to reclaim borrow pits and low-lying areas located in barren lands along the project road (if it so desired by the owner/community and approved by the Environmental Specialist, CSC). Non-bituminous wastes shall be dumped in borrow pits covered with a layer of 30cm soil to ensure that borrow pit is restored to original use. No new disposal site shall be created as part of the project, except with prior approval of the Environmental Specialist ofCSC. All waste materials shall be completely disposed and the site shaH be completely cleaned and certified by Environmental Specialist ofCSC before handing over. The Contractor at his cost shall resolve any claim, arising out of waste disposal or

    1----- ,lillY non-compliance that m!ly arise on account of lack of action on his part. The topsoil from all areas of cutting and all areas to be permanently covered shall be stripped off to a specified depth of ISO mm and stored in stockpiles. A portion of the temporarily acquired area and/or Right of Way shall be earmarked for storing topsoil. The locations for stock piling shall be pre-identified in consultation and with approval of Environmental Specialist of CSC. The following precautionary measures shall be taken to preserve them till they are used:

    (a) Stockpile shall be designed such that the slope does not exceed I :2(Vertical to horizontal), and height of the pile is restricted to 2 m.

    C.IA Stripping, stocking and preservation of top soil

    (b)

    To Retain soil and to allow percolation of water, silt fencing shall protect the edges ofthe pile. Stockpiles shall not be surcharged or otherwise loaded 1nd multiple handling shall be kept to a minimum to ensure that no compaction shall occur. The stockpiles shall be covered with gunny bags or vegetation.

    (c) It shall be ensured by the Contractor that the topsoil shall not be unnecessarily trafficked either before stripping or when in stockpiles.

    Such stockpiled topsoil shall be utilized for) Covering all disturbed areas including borrow areas, oruy in

    case where they are to be rehabilitated. ) Dressing of slopes of road embankment> Agricultural fields of

    farmers aC'l\lired t~IllPorarily land. The Contractor shall provide safe and convenient passage for vehicles, pedestrians

    C.l.S Accessibility and livestock to and from roadsides and property access connecting the project '--___..1..-_______-'--,-,-r~oad, providing temporary connecting road.

    ResponsibilityReference

    Planning and SupervisionlDocument Execution Monitoring

    MoRTH:301.3.2 MoRTH:301.7 Environmental MoRTH:30S.3.3 Contractor Specialist of and CSC,KSHTP MoRTH:30S.3.9

    Environmental Contractor Specialist of

    _----L_____---L, esc, KSHIP

    Chapter 3: Mitigation Measures 8 Scott Wilson

  • --------

    ------

    ~ l

    Karnataka State Highways Improvement Project-II Detailed Project Report Consultancy Services for Preparation ofDPR, Bid Documents Volume IV - Part I: EMP Report and Associated Safeguard Instruments EPC Packages Funded by World Bank

    r~~~~~~

    ResponsibilityReferenceEnvironmental Planning and Supervisionl81. No. Management Measures DocumentIssue Monitoring

    the sprinkling time depending on the local requirements. Contractor shall rehabilitate the borrow areas as soon as borrowing of soil is over from a particular borrow area in accordance with the approved Borrow Area Redevelopment Plan. The Contractor shall obtain materials from quarries only after consent of the Department of Mines & Geology and District Administration. In view of special situation of excavation of the ward hill side, Contractor shall get an opportunity to

    Execution

    EnvironmentalMoRTH: 111.3Quarry Operations Specialist ofC.2.2 use the same material for road construction. This shall require establishment of a ContractorAppendix -19 Crushers CSC, KSHIP

    be under taken as per the Appendix-B Policy guidelines for installation of stone Crushers.

    number of crushers along the roadsides. The crushers and all related activities shall

    ~~~-

    Except as may be provided in the contract or ordered or authorized by the Engineer, the Contractor shall not use explosives. Where the use of explosives is so provided or ordered or authorized, the Contractor shall comply with the requirements of the following Sub-Clauses of MoRTH 302 besides the law of the land as applicable. The Contractor shall at all times take every possible precaution and shall comply with appropriate laws and regulations relating to the importation, handling, transportation, storage and use of explosives. The contractor shall at all times when engaged in blasting operations, post sufficient warning flagmen, to the full satisfaction of the Engineer. 301.9 (i)

    C.2.3 Blasting Appendix-I 9 MoRTH:302.4The Contractor shall at all times make full liaison with and inform well in advance 304.5 and obtain such permission as is required from all Government Authorities, public bodies and private parties whomsoever concerned or affected or likely to be concerned or affected by blasting operations. Blasting shall be carried out only with permission of the Engineer. All the statutory laws, regulations, rules etc., pertaining to acquisition, transport, storage, handling and use of explosives shall be strictly followed. Blasting shall be carried out during fixed hours (preferably during mid-day) or as permitted by the Engineer. The timing should be made known to all the people within 1 OOOm (200m for pre-splitting) from the blasting site in all directions.

    Transporting Contractor shall maintain all roads (existing or built for the project), which are Environmentalused for transporting construction materials, equipment and machineries asConstructing

    C.2.4 Appendix-I 6 Contractor Specialist ofprecised. All vehicles delivering fine materials to the site shall be covered to avoidMaterials and Haul CSC, KSHIP

    Road Management spillage of materials. ~ ~~ -~~~~~~ ~~-

    Chapter 3: Mitigation Measures \0 Scott Wilson

  • ~.I t i i ,.'"

    Kamataka State Highways Improvement Project - II Detailed Project Report Consultancy Services for Preparation ofDPR; Bid Documents Volume IV - Part 1: EMP Report and Associated Safeguard Instruments EPC Packages Funded by World Bank

    -- --- ~m

    ResponsibilityEnvironmental Referencef:NO. Management Measures Planning and Supervision!Issue Document Execution _ Monitoringc-- ..

    ancillary sites close to water bodies. The fencing shall be provided prior to commencement of earthwork and continue till the stabilization of the embankment slopes, on the particular sub-section of the road. Contractor shall ensure that construction materials containing fine particles are stored in an enclosure such that sediment-laden water does not drain into nearby watercourse. The Contractor shall construct slope Protection works as per design, or as directed by the Environmental Specialist of CSC to control soil erosion and sedimentation through use of Breast walls, Retaining Walls, Plot Bioengineering methods, dykes, sedimentation chambers, basins, fibber mats, mulches, grasses, slope, drains and other devices. All temporary sedimentation, pollution control works and maintenance thereof shall be deemed as incidental to the earth work or other items of work and as such no separate payment shall be made for them. Contractor shall ensure the following aspects: MoRTH:30S.2.2.2

    Slope Protection Environmental)- After construction of road embankment, the side slopes shall be covered with MoRTH:306.2 Specialist ofC.3A and Control of Soil Contractor

    grass and shrubs (refer Appendix -10 and 18) as per design specifications. & Appendix 10Erosion CSC,KSHIP)- Turfmg works shall be taken up as soon as possible provided the season is and 18

    favorable for the establishment of grass sods. Other measures of slope stabilization shall include mulching netting and seeding of batters and drains immediately on completion of earthworks.

    )- In borrow pits, the depth shall be so regulated that the sides of the excavation shall have a slope no steeper than I vertical to 2 horizontal, from the edge of the final section of the bank.

    )- Along sections abutting water bodies, pitching as per design specification shall protect slopes.

    Pollution

    CA.l

    CA

    Water Pollution

    The Contractor shall take all precautionary measures to prevent entering of

    wastewater into streams, water bodies or the irrigation system during construction. Water Pollution EnvironmentalContractor shall avoid. construction works close to the streams or water bodies MoRTH:lllACA.l.1 from Construction Contractor Specialist ofduring monsoon. MoRTH:l11.1Wastes CSC,KSHlPContractor shall not wash his vehicles in river water and shall not enter riverbed

    _for that purpose.

    CA.IL MoRTH:1l1.4Water Pollution _ The Qontr!ictor_!ihall. ensure tha~1l ~nstruction_vehicle parkin..& lo~ations, Contractor Environmental

    Chapter 3: Mitigation Measures 12 Scott Wilson

    L

  • il k f 1 J r i iii ~

    Kamataka State Highways Improvement Project - II Detailed Project Report Consultancy Services for Preparation of DPR, Bid Documents Volume IV Part I: EMP Report and Associated Safeguard Instruments - EPC Packages Funded by World Bank ~-

    SI. No.

    ,-~~~

    Environmental Issue

    Vehicles, Equipment and MachinlJries

    Management Measures

    comply with the relevant statutory requirements of CPCB andIMotor Vehicles Rules. The Contractor shall submit PUC certificates for all vehicles/equipment/machinery used for the Project.

    Reference Document

    ~~~~

    Responsibility Planning and Supervision/

    I

    Execution Monit()ring I CSC,KSHIP

    -C.4.3 Noise Pollution

    CA.3.1

    Noise Pollution: Noise from Vehicles, Plants and Equipments

    The Contractor shall conftrm the following: :;.. All Construction plants and equipment used in construction shall strictly

    conform to the MoEF/CPCB noise standards. :;.. All Vehicles and equipment used in construction shall be fitted with exhaust

    silencers. :;..~ Servicing of all construction vehicles and machinery shall be done regularly

    and during routine servicing opt-rations, the effectiveness of exhaust silencers shall be checked and if found defective shall be replaced.

    :;.. The equipment available in the market should be procured, if the Contractor plans to purchase new equipment. For the old equipment, necessary or possible alterations must be carried out to reduce the noise levels to the possible extent.

    :;.. Maintenance of vehicles, equipment and machinery shall be regular and up to the satisfaction of the Environmental Specialist of CSC to keep noise levels at the minimum.

    At the construction sites within 150 m of the nearest habitation, noisy construction work such as crushing, operation of DG sets, use of high noise generation equipment shall be stopped during the night time between 10.00 pm to 6.00 am. Working hours of the construction activities shall be restricted around educational institutionslHealth Centers (silent zones) up to a distance of 100 m from the sensitive receptors I.e., School, Health Centers and Hospitals etc. Contractor shall provide noise barriers to the suggested locations of select Schools. List oflocations for noise barriers is given in (Appendix-6). Noise monitoring shall be carried out at the locations specified in Table 5.2 by the KSHIP and the Engineer through the approved monitoring agency.

    Noise Rules Published by MoEF Appendix-6 & Appendix-7

    Environmental Contractor Specialist of

    CSC, KSHIP

    C.S Safety Contractor shall provide: :;.. Protective footwear, protective goggles and nose masks to the workers

    employed in asphalt works to protect from the Benzene fumes, concrete works, crusher, etc.

    ----

    Appendix-9 Environmental

    Contractor Specialist of CSC, KSHIP

    C.5.! Personnel Safety Measures for Labour

    Chapter 3: Mitigation Measures \4 Scott Wilson

  • ------

    ---------

    ---------

    -----------

    I • J I j i i I i j I i i a

    Kamataka State Highways Improvement Project - II . Detailed Project Report Consultancy Services for Preparation of DPR, Bid Documents Volume IV - Part I; EMP Report and Associated Safeguard Instruments EPC Packages Funded by World Bank

    r~~

    ResponsibilityReferenceEnvironmental

    Sf. No. Planning and Supervision!Management Measures Issue Document Monitoring

    All machines to be used in the construction shall confonn to the relevant Indian Standards (IS) codes, shall be free from patent defect, shall be kept in good working order, shall be regularly inspected and properly maintained as per IS provision and to the satisfaction of the Environmental Expert ofCSC. Contractor shall take all reasonable precautions to prevent danger to the workers and public from fire, flood etc. resulting due to construction activities.

    Execution

    EnvironmentalContractContractor shall make required arrangements so that in case of any mishap all Risk Force Contractor Specialist ofAgreementC.5.4 necessary steps can be taken for prompt first aid treatment. Construction Safety Measure CSC,KSHIPAppendix-9Plan prepared by the Contractor shall identify necessary actions in the event of an etllergency. The Contractor shall arrange for-A readily available first aid unit including an adequate supply of sterilized dressing EnvironmentalContractmaterials and appliances as per the Factories Rules in every work zone. Contractor Specialist ofrequirement.C.5.6 First Aid A vailability of suitable transport at all times to take injured or sick person(s) to the Appendix-9 CSC, KSHIP nearest hospital.

    Equipment and trained nursing staff at construction camp.

    The Contractor shall provide, erect and maintain infonnatory!safety signs, MoRTH:801 Environmental

    MoRTH:802Infonnatory Signs hoardings written in English and local language (Kannada), wherever required or Specialist ofContractorC.5.7 as suggested by the Environmental Specialist ofCSC. &and Hoardings CSC,KSHlPAppendix-4

    Flora and Fauna: PlantationlPreservationlConservation Measures

    The Contractor shall do turfing on embankment slopes, plantation of shrubs as

    specified in the Contract.

    The compensatory forestation shall be carried out by the State Forest Department.

    C.6

    EnvironmentalMinimum 80 percent survival rate of the saplings shall be acceptable otherwise the Roadside Appendix-l 0 Contractor Specialist ofC.6.1 ContractorlForest Department shall replace dead plants at his own cost. Plantation Strategy

    CSC,KSHIPThe Environmental Specialist of CSC shall inspect regularly the survival rate of the trees planted by the Contractor in accordance with the plantation strategy suggested.

    c~~

    The Contractor shall take reasonable precaution to prevent his workmen or any other persons fonn removing and damaging any flora (plant/vegetation) and fauna

    Environmental(animal) including fishing in any water body and hunting of any animal If anyFlora and chance Appendix-I 3 Contractor Specialist ofC.6.2 animal is found near the construction site at any point of time, the Contractor shall found Fauna CSC,KSHlPimmediately upon discovery thereof acquaint in the Environmental Specialist of

    CSC and carry out his instructions for dealinj;( with the same.

    Chapter 3: Mitigation Measures 16 Scott Wilson

  • ---

    -- --

    ---

    -----

    --- ---

    ~

    jt i :i i i ,- i f ] (1 f ~

    Kamataka State Highways Improvement Project - II Detailed Project Report Consultancy Services for Preparation of DPR, Bid Documents Volume IV - Part I: EMP Report and Associated Safeguard Instruments - EPC Packages Funded by World Bank

    _. Responsibiliq

    ,

    I

    Environmental ReferenceI SI. No. Management Measures Planning and Supervision! IIssue Document Execution Monitoril!g I

    bottom of the tank at least 1 m above the surrounding ground level. I c) If water is drawn from any existing well, which is within 30 m proximity

    of any toilet, drain or other source of pollution, the well shall be disinfected before water is used for drinking.

    d) All such wells shall be entirely covered and provided with a trap door, which shall be dust proof and water proof.

    e) A reliable pump shall be fitted to each covered well. The trap door shall be kept locked and opened only for cleaning or inspection, which shall be done at least once in a month.

    f) Analysis of water shall be done every month as per parameters prescribed in IS 10500-1991.

    Environmental Specialist of CSC shall be required to inspect the labour camp once in a week to ensure the compliance of the EMP The Contractor shall ensure that )- The Sewage system for the camp are designed, built and operated in such a

    manner that no health hazards occurs and no pollution to the air, ground water or adjacent water courses take place

    )- Separate toiletslbathrooms, wherever required, Screened from those form men EnvironmentalSanitation and MoRTH:114.14

    Contractor Specialist ofC.7.3 (marked in vernacular) are to be provided for women Sewage System Appendix-21 CSC, KSHIP

    )- Night soil can be disposed of with the help of local municipal extractor or disposed of by putting layer of it at the bottom of a permanent tank prepared for the purpose and covered with 15 cm layer of waste or refuse and then covered with a layer of earth for fortnight.

    The Contractor shall provide garbage bins in the camps and ensure that these are

    )- Adequate water supply is to be provided in all toilets and urinals

    Environmental C.7.4 Waste Disposal regularly emptied and disposed off in a hygienic manner as per the Comprehensive Appendix-21 Contractor Specialist of

    Solid Waste Management Plan approved by the Environmental Specialist ofCSC. CSC, KSHIP C.S Contractor's Demobilization

    The KSHIP shall undertake seasonal monitoring of air, water, and noise and soil

    Environmentalquality through an approved monitoring agency. The parameters to be monitored,

    Environmental Appendix-7 and Specialist ofC.8.1 frequency and duration of monitoring as well as the locations to be monitored shall ContractorConditions Appendix -12 CSC and be as per the Monitoring Plan prepared. National Standard of Air, Noise and Water

    KSHIP, NHAI given in Appendix-7.

    Continuous The Environmental Specialist of CSC shall have continuous interactions with local Environmental EnvironmentalC.8.2 Appendix-16

    people around the project area to ensure that the construction activities are not Community Specialist of S~ecialist of

    Chapter 3: Mitigation Measures 18 Scott Wilson

    http:MoRTH:114.14

  • lil .~I,- r. I ( • j i :3 ~ i

    Kamataka State Highways Improvement Project - II Detailed Report Consultancy Services for Preparation of DPR, Bid Documents Volume IV Part I: Report and Associated Safeguard Instruments - EPC Packages Funded by World Bank

    SI. No. Environmental

    Issue Management Measures Reference Document

    Responsibility Planning and

    Execution Supervisionl Monitoring

    enhancement provision made under the project; status of rehabilitation of borrow areas; and effectiveness of noise barriers.

    0.2 Maintenance of Drainage

    PWD shall ensure that all drains (side drains, median drain and all cross drainages) are periodically cleared especially before monsoon season to facilitate the quick passage of rainwater and avoid flooding.

    Appendix -12 KSHIPIPWD KSHIPIPWD

    0.3 Pollution Monitoring

    The periodic monitoring of the ambient air quality, noise level, water (both ground and surface water) quality, soil quality in the selected locations as suggested in l'ollution monitoring plan through the KSPCB or its approved monitorin2 a2ency.

    Appendix-12 Pollution Monitoring Agency

    KSHIPIPWD

    0.4 Soil Erosion and Monitoring of Borrow Areas

    Visual Monitoring and inspection of soil erosion at borrow areas, quarries (if closed and rehabilitated), embankments and other places expected to be affected, shall be carried out once in every three months as suggested in monitoring plan.

    Appendix -12 KSHIPIPWD KSIDPIPWD

    --------

    KSIDP0.5 Public awareness on Noise levels and Health Affects

    However the public shall be advised to construct the noise barriers such as walls, double glazed windows and tree plantation between the roads and their property. The public awareness is necessary regarding the human health through the news papers and consultations and distribution ofpamphlets during the operation stage.

    Appendix-6 KSHIP

    Chapter 3: Measures 20 Scott Wilson

  • ----

    C.I.2

    , , _Il i j il I j I j i j i j l r 1 t j i.

    Kamataka State Highways Improvement Project - n Detailed Project Report Consultancy Services for Preparation ofDPR, Bid Documents Volume IV Part 1: EMP Report and Associated Safeguard Instruments - EPC Packages Funded by World Bank

    EnvironmentalSI. No.

    Issue

    Construction of temporary traffic diversions

    ~anagement~easures

    bed, embankment slopes except material which shall be reused in Construction. All debris requiring disposal shall be directly taken to the Pre identified disposal site and deposited as per approved Comprehensive Waste Disposal Locations. Debris generated shall be reused in the construction of temporary diversion of traffic, filling in embankment, slope protection work etc subject to the suitability of the materials and approval of the Engineer and Environmental Officer. All arrangements for dismantling, clearing debris and its transportation shall be considered incidental to the work and shall be planned and implemented by the Contractor as approved and directed by the Environmental Officer. Construction of temporary traffic diversions shall be carried out in accordance with the plans prepared and approved during pre-construction stage. Temporary diversions shall be constructed after receipt of approval from concerned authorities and under supervision of Environmental Officer. Warning boards should be placed at least 500 m and 200 m from the construction sites on both sides along with battery operated lamp!retro reflective lamps. Flashlights are provided at least 200 m before the construction site on either side giving warning to drivers before reaching construction sites. Signs, lights, barriers, cones, and other traffic control devices, as well as the riding surface of diversions shalt be maintained in a satisfactory condition till such time they are required as directed by the engineer. Contractor shall keep the temporary traffic diversions free of dust by sprinkling of water three times a day and as required under specific conditions (depending on weather conditions, construction in the settlement areas and volume of traffic). Contractor shall prepare a Detailed Traffic Control Plans and shall submit it to the Environmental Officer for approval, five days prior to commencement of works on any bridge. The traffic control plans shall contain details of temporary diversions, traffic safety arrangements i.e. lighting arrangement, signage's, arrangement of flagmen etc. The Contractor shall provide specific measures for safety of pedestrians and workers as a part of traffic control plans. The Contractor shall ensure that the diversion/detour is always maintained in running condition, particularly during the monsoon to avoid disruption of traffic flow. The Contractor shall also inform local community of changes to traffic routes,

    Reference Document

    IRC:SP 55 Appendix-4 Appendix-14

    Responsibility Planning and

    Execution

    Contractor

    Supervision! ~onitorin2

    I

    I

    CSC& Environmenta I Officer, CMU (KSHIP)

    ~--

    Chapter 3: Mitigation Measures 22 Scott Wilson

  • --------

    -----

    ----

    , 1 " ~ ~ i f "1 i I 1 t • 11 t

    Karnataka State Highways Improvement Project - II Detailed Project Report Consultancy Services for Preparation of DPR, Bid Documents Volume IV - Part I: EMP Report and Associated Safeguard Instruments - EPC Packages Funded by World Bank

    ResponsibilityEnvironmental Reference

    Management Measures Supervision!Planning andI Sl. No. Issue Document Monitoring

    construction work is expected to disrupt users of community water bodies or flow of surface water body is diverted. The Engineer!CMU shall ensure that contractor has served the notice to the downstream users of water well in advance. The Contractor shall take prior approval of the Irrigation Department or CMU (KSHlP) for any such activity. Since the rivers along the project road are most of the time dry, Aquatic Fauna

    Execution

    CSC& are very limited. Any impacts to the aquatic fauna shall be avoided. Environmenta

    Aquatic _Fauna I Officer, CMU

    JKSHlP} Minimum required labour should stay at night at bridge site and Contractor shall

    Labour

    Appendix-l 6 Contractor

    make necessary arrangement of toilets, waste sanitation, and Drinking Water Appendix-21 requirement at site.

    1-------C.2 Pollution C.2.1 Water Pollution

    C.2.1.l

    Water Polluti- n from Construction Wastes

    The Contractor should not discharge wastewater, generated during construction, into streams, water bodies or the irrigation system without preliminary treatment and should conform to Kamataka State Pollution Control Board. Cofferdams or formwork shall be such as to ensure still water conditions. All waste arising from the bridges construction activity is to be disposed off in the manner that is acceptable to the State Pollution Control Board and as per approved Comprehensive Waste Management Plan. Wastes must be collected, stored and reused in the construction/taken to approved disposal sites. The Environmental Officer shall certify that an wastes generated on bridge site have been disposed off as per norms or in environment friendly manner.

    Clause No 501.86 MoRTH Specification for Road and Bridge Works W (P&C) PAct 1981 Appendix-l 6

    CSC& Environmenta

    Contractor 1 Officer, CMU (KSHIP)

    To avoid contamination from fuel and lubricants, the vehicle and equipments Clause No CSC&

    shall be properly maintained and refueling/maintenance of vehicles shall not be 501.8.6 MoRTHContamination of Environmenta

    done near the bridge sites. Specification for water from fuel Contractor 1 Officer, Diesel Generator set shall be placed on a cement concrete platform with oil and Road and Bridge and lubricants CMU

    grease trap to control the oil ingress into soil/water bodies. Works W (P&C) (KSHIP)

    PAct 1981

    Chapter 3: Mitigation Measures 24 Scott Wilson

    C.2.1.2

  • ----- -----

    -- -

    C.3.1

    I. ~ Ii :i t ];

    Karnataka State Highways Improvement Project - II Detailed Project Report Consultancy Services tor Preparation of DPR, Bid Documents Volume IV - Part I: EMP Report and Associated Safeguard Instruments - EPC Packages Funded by World Bank

    ResponsibilityEnvironmental ReferenceI SI. No. ~anagement~easures Planning and SupervisionlIssue Document

    Execution ~onitorinL Tool box meeting shall be held at least once a week in order to brief workers about safety, do's and don't during construction. Toolbox safety meetings are on the job meetings and shall keep employees alert to work related accidents and illness. A toolbox meeting helps alert employees to workplace hazards, and by preventing accidents, illness and on the job injuries. The meeting should involve

    Tool Box groups of people who work together and face same sort of injury risks. The Appendix-9

    Meetings meetings should be so designed to raise employee's awareness following hazardous incidents, a recent injury or near miss. Toolbox meeting improve workplace safety and health, provide information and instructions, improve consultation and help identify hazards and deciding what action needs to be

    I-Jake~t() reduce the risks. Contractor shaH provide: )- Protective footwear, goggles and clothing to all workers employed on laying

    of wearing coat, preparing cement mortars for brick work, concreting, painting etc.

    )- Welder's protective eye shields to workers who are engaged in welding works

    );- Earplugs to workers exposed to loud noise, and workers working with jack hammer, joint cutting machines, vibrators etc.

    )- Adequate safety measures for workers during handling of materials at site are taken up. CSC&

    Personal Safety );- The Contractor shall comply with all regulations regarding safe scaffolding, Environmenta Measures for ladders, working platforms, gangway, stairwells, excavations, trenches and Appendix-9 I Officer, Labour

    Contractor safe means of entry and egress. CMU

    )- At every workplace, good and sufficient water supply shall be maintained to (KSHIP) avoid waterborne/water related/water based diseases to ensure the health and hygiene of workers.

    );- Persons working should wear safety helmets and rubber gloves );- Contractor at his own expenses shall put up necessary shoring, shuttering

    and planking or cut slopes to a safer angle or both with due regard to the safety of personnel and workers and to the satisfaction of the Engineer

    The Contractor shall comply with all the precautions as required for ensuring the safety of the workmen as per the International Labour Organization (ILO) Convention No. 62 as far as those are applicable to this contract.

    '-------

    Chapter 3: Mitigation Measures 26 Scott Wilson

  • --------

    ---

    f t ! i ) I i r i t & i 1 • i

    Karnataka State Highways Improvement Project - II Detailed Project Report Consultancy Services for Preparation of DPR, Bid Documents Volume IV Part I: EMP Report and Associated Safeguard Instruments EPC Packages Funded by World Bank

    ResponsibilityEnvironmental Reference81. No. Management Measures Planning and Supervision!Issue Document

    Execution Monitorinlt ! Chemicals Local exhausts shall be used to capture and exhaust benzene fumes while paving Clause Number CMU

    the bituminous mix at the worksites, thereby preventing the accumulation of (KSHIP) high exposure levels in the employee's breathing zone (Clause Number 111.5,

    501,6.2, MoRTH)

    MoRTH). Appendix-9 and In addition to engineering controls and provision of Personal Protective Appendix-20 Equipments, administrative controls such as work practices involving rotation of crews shall be used to reduce exposures to benzene. This could include limiting the amount of time employees spend working in high exposure areas by rotating personnel with frequent breaks. Hot mix plant areas shall be designated as regulated areas and access to these areas will be limited to trained persons only. All entrances and access ways shall be posted with signs bearing the information such as 'DANGER', 'Authorized Personnel Only', etc. Every employee working with asphalt shall receive training on the health hazards associated with exposure, description of the operations in the work area, work practices to reduce exposure, including engineering and administrative controls and Personal Protective Equipment required, etc. (Annexure 'A' to Clause Number 501, 6.2, MoRTH) Any skin contacts with epoxy materials; solvents and epoxy strippers should be avoided. Epoxy resin can cause irritation of skin particularly epoxy hardeners (B component) may cause a rash on skin in sensitive persons if incorrectly handled. The resin and hardener should not be allowed to come into direct contact with skin. The most effective protection is achieved by wearing polythene gloves, rubber gloves, with a cloth liner, and protective clothing. The official toxicity classification on container labels may be looked for before starting work. Barrier creams are recommended but are not substitutes for protective clothing. Eyes shall be protected where splashing could occur while spraying. Good ventilation shall be ensured and inhalation of vapors avoided. If materials are sprayed, a respirator shall be used. If skin contact occurs, it shall be immediately washed with a cleaner, followed by soap and water. Should eye contact occur, it shall be flushed immediately with plenty of water for IS minutes and a doctor called for

    _If contact occurs with the clothing, it shall be immediately changed to prevent

    Chapter 3: Mitigation Measures 28 Scott Wilson

    I

  • --

    -----

    -----

    -----

    t l r j

    Karnataka State Highways Improvement Project - II Consultancy Services for Preparation of DPR, Bid Documents and Associated Safeguard Instruments EPC Packages Funded by World Bank

    rsl. No. Environmental Issue PollutionC.3.6 Monitoring

    Management Measures

    CMU shall monitor water quality both upstream and downstream of bridges thrice a year at the site of new bridges.

    f C.4 Contractor's Demobilization Contractor shall prepare site restoration plans, which shall be approved by the

    Reference Document

    Appendix-7

    Detailed Project Report Volume IV Part I: EMP Report

    Responsibility Planning and Supervision!

    Execution MonitOring CMUthn'ugh approved Pollution EO KSHIP Monitoring Laboratory

    Cleanup

    C.4.1 Operations, Restoration and Rehabilitation

    Environmental Officer. The clean-up and restoration operations are to be implemented by the Contractor prior to demobilization. All spaces excavated and not occupied by the foundation or other permanent works shall be refilled with earth up to surface of surrounding ground. The Contractor shall clear all temporary structures; dispose all surplus material laying in waterway or around bridge site as per Comprehensive Waste

    Appendix-21

    CSC& Environmenta

    Contractor I Officer, CMU (KSHlP)

    -~-

    Management Plan and approved by Environmental Officer.

    The bridge construction site shall be left clean and tidy, at the contractor's

    expense, to the satisfaction to the Environmental Officer.

    OPERATION STAGE

    Activities to be Carried Out by the CMU (Construction Management Unit)

    M 't . oUt onngo lOt'

    . pera Ion P rn e ormance

    Pollution0.2

    Monitoring

    0.3 Safety Measures

    The KSHIP shall monitor the operational performance of the various mitigation ---

    . d . h £; f . . . k f h .measures came out m t e orm 0 n ver trammg wor s as a part 0 t e project Appendix-I 2 KSHIP KSHIPTh . d' I d£;' . . I d th r S '1e m wators se ecte or momtonng mc u e e water qua Ity status, OJ erosion etc.

    The periodic monitoring of the surface water quality at the selected locations as Pollution

    suggested in pollution monitoring plan shall be responsibility of KSHIP. These MonitoringAppendix -12 KSHIPlocations shall be monitored once during operation stage. Agency

    throughCMU Contractor shall submit Accident Safety and Hazardous Chemical Spill Management Plan and shall get it approved by the "EO KSHIP". The plan Appendix-20

    ~ sh()uld also have details of detours in case ofemergency. ~-~

    Chapter 3: Mitigation Measures 30 Scott Wilson

  • Kamataka State Highways Improvement Project - II Detailed Project Report Consultancy Services for Preparation ofDPR, Bid Documents Volume IV Part 1: EMF Report and Ass.i.dated Safeguard Instruments EPC Packages Funded by World Bank

    4. Monitoring Programme

    The monitoring programme consists of perfonnance indicators, reporting formats and necessary

    budgetary provision. Out of this, the budgetary provisions are confidential and are not supposed to be

    part of the disclosure statement. The budgetary statements are provided in section 8.0 for the purpose

    of evaluation of the EMP.

    The contractors monitoring plan should be in accordance with the baseline environmental monitoring,

    locations provided in the environmental impact assessment report.

    The monitoring plan has the following objective

    • To ensure effective implementation ofEMP

    • To comply with all applicable environmental, safety, labour and local legislation

    • To ensure that public opinions and obligations are taken in to account and respected to the required satisfaction level

    • To modify the mitigation measures or implementing additional measures, if required 4.1 Performance indicators

    Environmental components identified of a particular significance in affecting the environment at

    critical locations have been suggested as perfonnance indicators (PIs).

    For example near the construction site, a thick layer of dust over the near by vegetation/leaf is an

    indication that the dust control measures are not effective. The performance indicators shall be

    evaluated under three heads as;

    • Environmental condition indicators to determine efficiency of environmental management measures in control of air, noise, water and soil pollution.

    • Environmental management indicators to determine compliance with the suggested environmental management measures. -

    • Operational performance indicators and monitoring plans prepared for the road sections are presented in Table 5.1. Details of the performance indicative parameters

    for each of the component have to be identified and reported during all stages of the

    implementation.

    Table 4-1: Performance Indicators and monitoring plan

    SL No

    Monitoring plan!

    Performance Description of Item Indicator Stage

    IResponsibi lity

    indicators 1 Monitoring • No. of trees planted (Total) Road side Post Forest

    plan • No. of trees under and other constructi Department Compensatory Mforestation plantation on stage andKSlllP

    • No. ofTrees planted along areas Road sides

    • No. of Trees planted at other locations(such as camps, borrow areas, debris disposal sites and plant areas)

    • No. of trees planted at enhancement sites I I

    Programme Scott Wilson

  • Kamataka State Highways Improvement Project - II Detailed Project Rep,rt Consultancy Services for Preparation ofDPR, Bid Documents Volume IV - Part I: EMP Report and Associated Safeguard InslT'lIUents ~ EPC Packages Funded by World Bank

    ,.--: Monitoring

    I I

    Sl. plan! Description of Item Indicator Stage i Responsibi

    No Performance i

    lity indicators

    9 Monitoring Statutory environmental monitoring as Environme Constructi Contractor plan per the conditions stipulated in the ntal status on

    c(,msents/ permission issued by PCB at constructio

    : n plant I Sites

    10 Monitoring Environmental parameter monitoring Air quality, Constructi KSHIP plan in accordance with the frequency and Noise on and through

    duration of monitoring as well as the quality, . Operation external locations as per the Monitoring plan Soil agency given in Table 4.2 quality,

    Water quality

    11 Monitoring Before the onset of monsoon all the Silting of Constructi Contractor plan debris/excavated materials shall be water on and should

    cleaned from the work sites and bodies be disposed of at the pre -identified supervised approved locations by the

    Environme . ntal

    specialist ofCSC_.

    12 Performance Implementation of enhancement Enhanceme Constructi Contractor indicators measures for nts on

    • Parking areas • Tourism • Cultural properties • Religious properties • Other oxbow land

    development 13 Performance • No. of Training sessions Training Constructi KSHIP

    indicators organized for Imparted on and - Department staff Operation - Contractors al Phase -Combined

    • No. of people trained - Department staff - Contractors i

    14 Performance Slope protection measures . Work sites Constructi IContractor indicators • Length (by type) on

    • No. ofLocations i 15 Performance Drainage Work sites Constructi Contractor

    indicators • Length on • No. of Locations

    16 Performance Safety provisions Work sites Constructi Contractor indicators • Signage (by type and No.) on

    • GuardRails • Guide Rails --

    17 ! Performance No. of chute drains provided Work sites Constructi Contractor-.

    i

    i

    I

    Chapter 4: Monitoring Programme 3 Scott Wilson

  • - -

    i , i 1 !Ii t i.

    Kamataka State Highways Improvement Project - II Detailed Project Report Consultancy Services for Preparation of DPR, Bid Documents Volume IV Part I: EMP Report and Associated Safeguard Instruments - EPC Packages Funded by World Bank

    Table 4-2: Environmental monitoring for Air, Water, Noise and Soil .... ..._ ......

    Attribute Parameter Frequency No of Implementation samples

    Special guidance Standards Duration Location

    Air CO,NOx, Once in every Two years Construction plant 48 KSHIPIPWD SPM,RPM,Pb

    High volume sampler to be Air (prevention located 50m from the plant four months Sites and major and control of or

    and S02 during establishments along in the down wind direction. pollution) Rules. as Use method specified by the project corridor CPCB,1994 construction directed CPCB for 24 hr sampling and operation. including base line

    monitored stations Water Once in every Two years Drinking water 24 KSHIPIPWD

    Factors as Important Grab sample collected from IS for Inland

    surface waters (IS: four months samples from the or

    decided by the

    source and analyze as per during2296,1982) and labour camps and as

    ENV.

    standard methods for

    from hand pumps, for drinking water construction directed Specialist of

    examination (IS: 10500-1991) and operation. Surface water from the

    the CSC water courses along the road project.

    Noise Two years KSHIPIPWD on db (A) scale

    Once in every Near the construction 48Noise Levels Equivalent noise levels MoEFNoise four months camps, working zones, or

    level meter kept at a Rules 2000 using and integrated noise

    during sensitive receptors at as desired distance of 15m from edge major human ofpavement Leq in db (A)

    construction and operation settlements along the

    of day time and night time stage road ...._ .......- ~··cc·:····-····

    ·Soil Monitoring of Sample of soil collected Threshold for each Two samples Two years Construction KSHIPIPWD N, P,K, Na,

    28 contaminant set by each during camp/plant sites and and analyzed using or

    Cl, Organic IRIS database of the Pre & post productive agricultural absorption spectrometer as desired Carbon, Pb, USPEA until monsoon lands abutting traffic and Oil & standards are season for the detours and traffic Grease constructionavailable to use. diversions and major

    period and intersections. operation stage.

    Chapter 4: Monitoring Programme 5 Scott Wilson

    I

  • Karnataka State Highways Improvement Project. II Detailed Project Report

    Consultancy Services for Preparation ofDPR, Bid Documents Volume IV - Part 1: EMP Report

    I' 1

    .'ill'! Associated Safeguard Instruments :epe Packages Funde.ol by World Bank

    This reporting will be as follows:

    • Reporting by the contractor to the esc • Reporting by esc to KSHIPIPWD • Reporting by KSHIPIPWD for the information ofall interested parties.

    Table 4-3: Reporting System

    Construction Contractor Supervision consultant KSHIPIPWD

    (CSC)Item

    Reporting Oversee

    Report to Supervision compliance

    toKSHIP monitorin2

    WB

    Construction Stage Monitoring of Before start of Regular Quarterly Quarterly construction work site and construction camp

    r-.-:=' As required As required Quarterly Quarterly I :::'~1Pollution monitoring 'toring

    Debris Weekly As required Quarterly Quarterly Quarterly disposal area 'Monitoring Implementation Regular Quarterly Quarterly Half yearly Enhancements

    lop soil Weekly Weekly Monthly Quarterly Halfyearly ~,reservations Borrow Regular Weekly Monthly • Quarterly Half yearly area/quarry area / Debris disposal area Tree cutting Weekly Weekly Monthly Quarterly Halfyearly Tree Monthly Monthly Monthly Quarterly Halfyearly plantation Operation stage Pollution Quarterly Quarterly Quarterly Asper After Monitoring monitoring monitoring

    plan

    World bank(WB)

    Desired supervision

    Half yearly

    Half yearly

    Half yearly

    Yearly

    Yearly

    Yearly

    Yearly Yearly

    Twice during operation phase

    Chapler 4: Monitoring Programme 7 Scott Wilson

    http:Funde.ol

  • Kamataka State Highways Improvement Project - II Detailed Project Report Consultancy Services for Preparation ofDPR, Bid Documents Volume IV - Part I: EMP Report and Associated Safeguard Instruments - EPC Packages Funded by World Bank

    -:

    I Forest Construction Supervision

    Contractor Department Consultant (Csq

    Format' Item Stage Implementation Implementation Reporting

    No. & Reporting to & Reporting to Supervision to KSHIP! Engineer KSHlPIPWD PWD

    -" extraction

    -" EMSl3 Deviations and Construction - Monthly Quarterly corrective Actions

    1---" EMSl4 Tree plantation Construction Quarterly Quarterly

    and ! Operation

    1---" EM S15 I Plantation of Construction As applicable Quarterly As As

    I shrubs and grass and applicable applicable I ~eration

    'E~iSI6 Implementation of Construction Monthly - Regular Quarterly Enhancement measures for cultural properties, parking areas and incidental spaces

    r--" Status Regarding Operation - Half Rehabilitation of yearly Borrow Areas

    ~"

    Noise barrier Operation As applicable - Quarterly Quarterly i construction

    -""

    I Survival rate of Operation Quarterly Quarterly i plants

    '--" EMS17 Debris generated During Through out " - Regular Quarterly

    due to road construction the widening construction

    period during widening

    The Environmental officer of CSC can make required changes in the formats specified in Appendix 12 of EMP to ensure effective reporting of environmental issues. Some of the formats should be included in the request for inspection such as Debris disposal area approval request. For making any

    required changes in the frequency of reporting and change in the contents of the report for effective and simple for implementation and monitoring, CSC should discuss the reporting formats with the Contractor and KSHIP. This will not only ensure that the environmental provisions are addressed but also link the satisfactory compliance to environmental procedures prior to approval of the Interim Payment Certificate (IPC) by the Engineer. In the regular monthly meeting the environmental aspects should also be discussed and the staff responsible for the implementation of the environmental management from the contractor, KSHIPIPWD and CSC should also be present.

    'Chapter 4: Monitoring Programme 9 Scott Wilson

  • Karnataka State Highways Improvement Project - II Detailed Project Report Consultancy Services for Preparation ofDPR, Bid Documents Volume IV - Part 1: EMP Report and Associated Instruments - Funded World Bank

    5. Institutional arrangements

    Institutional arrangements are intended to achieve certain level of quality in the project during

    mplementation of various project components by the government of Karnataka (GOK) as specified

    by the various conditions of loan agreement between the World Bank and the GOK. These are

    basically to meet the World bank safe guard policies that in turn will make sure that the country laws

    (National and State level) are not violated during the pre construction, construction and Operational

    (defect liability period) stages of the project.

    The Chief Project Officer heads KSHIP. He will be responsible for the successful implementation of

    the Project. The Chief engineer is also the Project Director in the KSHIP set up for the

    implementation of the project. The project director (PD) is assisted by Project hnplementation Unit

    (pru), Environmental and Social Expert at the head office. The Environmental social management Unit (ESMU) on other hand consists of Environmental Management Plan hnplementation Unit

    (EMPIU) and Social Development Resettlement Cell (SDRC). The SDRC is headed by a Chief

    Administrative Officer (CAO). The Project Director will be heading the overall functioning of the

    Environmental and Social Management Unit (ESMU).

    Each PIU will have the following staff

    • One Environmental Engineer

    • One Assistant Conservator ofForest

    • One Assistant Environmental Engineer each at five subdivisions with two Assistant

    Engineers at division

    • One Range Forest Officer each at five subdivisions with additional RFO at division

    • One Social Development officer for RAP implementation

    • One Assistant Engineer for Encumbrances / Technical

    The Executive Engineers (EEs) and supporting staff as employer's representatives nominated for the

    project will be responsible for the implementation of the project under the division. At present KSHlP

    is a small organization. Competent highway professional can be drawn from the large pool of efficient

    engineers of the PWD. The Environmental and Social Expert of KSHIP will look after the

    environmental issues during the project preparation, implementation and operation with the assistance

    of the Environmental Specialist of the Project Design and Environmental Officer (EO) of the CSC.

    The structure is shown in Figure 5.1

    The CSC should have the following staff.

    Resident Engineers, Assistant Resident Engineers in addition to Team Leader (Engineer) and

    following professional.

    • Pavement / Materials Specialist

    • Procurement / Contract management Specialist

    • Structural/Bridge Engineer

    • Senior material Engineer

    • Highway / Pavement Engineers

    • Material Engineers

    • Bridge Engineers

    lI""mUl~.UIla.t Arrangement Scott Wilson

  • t

    Kamataka State Highways Improvement Project - II Consultancy Services for Preparation of DPR, Bid Documents and Associated Safeguard Instruments - EPC Packages Funded by World Bank

    Detailed Project Report Volume IV - Part I: EMP Report

    Figure 5.1: Implementation arrangement for the EMP works

    L ENVIRONl\·IENT l\L.\NAC£M£NT PLAN Il\IPLEl\IENTATlON UNIT (£MPIU) Project D:rector

    \lI I Chief Aclministrativ~ officer

    '" < >I 'E:nv:ronmental Engineer As~istant Conserva!or of Forest Supervisi0 fJ

    Consultant~ t .... I .. Do:::umentation Bnd I .". Ran~e forest I.... r Training .. Officer

    J~ J'

    I Assl Emf Engineer Asst En'll Engineer IE- Additional R.FO 'If " " ,~

    l~: A;st Env As:;tEr.v AsstEnv AsstulV RFO,

    ~ngg Etlgg Engg Engg, ~ Qulb~r~

  • Karnataka State Hi