INTEGRATED WATERSHED MANAGEMENT PROGRAMME(IWMP)

DETAILED PROJECT REPORT

OF

LUNGLEI – III (LOWER PHAIRUANGLUI)

WATERSHED PROJECT

Prepared by

The Block Development Officer : Rural Development Block Lungsen

Page 2: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 1 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

    

TABLE OF CONTENTS   

Page No.  

CHAPTER 1: INTRODUCTION                                                                                                                        5 

CHAPTER 2: PROJECT BACKGROUND____________________________________________________________6­13 

  2.1: Location 

    Table No. 1:  Basic Project Information. 

2.2: Need of Watershed Development Programme 

    Table No. 2: Weightage of the Project  

2.3: Other Developmental Project/schemes running in the Project Area 

Table No. 3 Developmental Projects/schemes running in the Project Area 

2.4: Previous watershed programme in the Project Area 

Map No. 1: Location Map of Lunglei IWMP ‐ III 

Map No. 2: Watershed Map of Lunglei District 

 

CHAPTER 3: BASIC INFORMATION OF THE PROJECT AREA                   14­22 

3.1: Geography and Geo‐hydrology  

3.1.2:  Soil and Topography: 

3.1.3:  Soil Classification: 

3.1.4:  Land and Agriculture:  

Table No. 4:  Land‐use Pattern in the Project Area 

Table No. 5:  Agro Climatic Condition 

Table No. 6:  Flood and Drought in the Project Area 

Table No. 7:  Soil erosion in the Project Area 

3.2:  Socio‐Economic Profile  

3.2.1: Demographic and Ethnographic Status:  

Table No. 8:  Demography and Land Distribution 

  3.2.2 Socio‐Economic Condition 

  3.3:  Livelihood Pattern 

Table No. 9: Summary of Livelihoods 

Page 3: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 2 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

CHAPTER 4: PROJECT APPROACH AND STRATEGIES                              23­26 

4.1:  Opportunities for intervention 

4.2:  Implementation Approach and Methodology 

4.3:  Convergence Strategy 

 

CHARTER 5: PROJECT OBJECTIVES AND SCOPE                                                                              27­28  

  5.1:   Project objectives 

5.2:   Project Core Values 

 

CHAPTER 6: BUDGETING                         29 

              6.1: Budgeting and Budget Components  

    Table No. 10: Budget at a glance 

 

CHAPTER 7: DESCRIPTION OF PROJECT COMPONENTS AND ACTIVITIES               30­81 

  7.1: Scientific Planning 

  7.2: Institutional Set up & Organization of community 

  7.2.:1 Community Institution building  

Table No. 11: List of existing Self Help Groups in the Project Area 

  7.2.2: Capacity Building 

Table No.12: Capacity Building Plan  

7.3: Physical activities to be undertaken  

  7.3.1: Entry Point Activity (EPA) 

    Table No. 13: Entry Point Activities (EPA) 

  7.3.2: Detailed Cost Estimates for works taken up under Entry Point Activities (EPA) 

    Table No. 14: Cost Estimate for construction of Water Harvesting Tank 

    Table No. 15: Cost Estimate for construction of Public Urinal 

    Table No. 16: Cost Estimate for construction of Agriculture link road 

    Table No. 17: Cost Estimate for construction of Resting Shed 

   7.3.3. Natural Resources Management 

    Table No. 18: Model Technical Specification of Stone Bund 

    Table No. 19: Cost Estimation for Bund 

Table No. 20: Model Technical Specification of Staggered Contour Trenches Table 

No. 21: Cost Estimation of Staggered Contour Trenches 

Table No. 22: Model Technical Specification of Bordered Contour Trenches 

Table No. 23: Cost Estimation for Bordered Contour Trench 

Page 4: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 3 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

Table No. 24: Model Technical Specification for Afforestation 

Table No. 25: Cost Estimation for Afforestation Activities. 

    Table No. 26: Cost Estimate for construction of Check Dam Type ‘A’ 

    Table No. 27: Cost Estimate for construction of Check Dam Type ‘B’ 

    Table No. 28: Cost Estimate for construction of Check Dam Type ‘C’ 

Table No. 29: Model Technical Details of Earthen Bund 

Table No. 30: Cost Estimation for Earthen Bund (Per Unit) 

Table No.31:  Cost Estimate for Construction of Agriculture Link Road (per unit) 

Table No. 32: Model Technical Details of Farm Pond (Per Unit) 

Table No. 33: Cost Estimation of Farm Pond    (Per Unit) 

  7.3.4: Activities under Farm Production System   

    Table No. 34: Per Unit Cost‐benefit analyses for Bamboo Cultivation 

    Table No. 35: Per Unit Cost‐benefit analyses for Passion fruit Cultivation 

    Table No. 36: Per Unit Cost‐benefit analyses for Arecanut Cultivation  

Table No. 37: Per Unit Cost‐benefit analyses for Greenhouse farming 

  7.3.5:   Activities under Livelihood Production System   

    Table No. 38: Per Unit Cost‐benefit analyses for Dairy farming 

    Table No. 39: Per Unit Cost‐benefit analyses for Poultry farming (Layer) 

    Table No. 40: Per Unit Cost‐benefit analyses for Poultry farming (Broiler) 

    Table No. 41: Per Unit Cost‐benefit analyses for Hill cattle/Methuen rearing 

    Table No. 42: Per Unit Cost‐benefit analyses for Goat/Sheep rearing 

    Table No. 43: Per Unit Cost‐benefit analyses for Pig rearing 

    Table No. 44: Per Unit Cost‐benefit analyses for Aquaculture 

Table No. 45: Cost Estimation for a Vermi‐Compost Unit 

Table No. 46: Per Unit Cost‐benefit analyses for Electronic goods servicing 

Table No. 47: Per Unit Cost‐benefit analyses for Carpentry 

Table No. 48: Per Unit Cost‐benefit analyses for Petty Trade 

Table No. 49: Per Unit Cost‐benefit analyses for Tailoring 

 

CHAPTER   8:  PROJECT PHASING AND YEAR­WISE ACTION PLAN                82­87 

Table No. 50: Project Phasing Strategy 

                           Table No. 51: Year Wise Action Plan 

 

CHAPTER 9: CONSOLIDATION AND WITHDRAWAL MECHANISM                88­93 

 

Page 5: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 4 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

CHAPTER 10: EXPECTED OUTCOMES                              94­98

  8.1.1 Drinking water 

Table No. 52: Status of Drinking Water  

8.1.2 Migration 

Table No. 53: Migration from the Project Area 

8.1.3 Crops  

Table No. 54: Major Crops grown and their productivity  

8.1.4 Vegetative cover  

8.1.5 Livestock  

8.1.6 Linkages 

8.1.7 Employment 

Table No. 55: Employment Generation  

8.1.8 Ground water table 

Table No. 56: Ground Water Table depth in the Project Area. 

 

CHAPTER 11:  LOGICAL FRAMEWORK ANALYSIS                     99­101 

CHAPTER 12:  MONITORING AND EVALUATION               102­103 

CHAPTER 13:  MAPPING                       104­140 

Location Map 

Lunglei District Watershed Map 

Contour Map 

Drainage Map 

Elevation Map 

Slope Map 

Wasteland Map 

ANNEXURES:                        141­150 

 Annexure I  : Approval and Acceptance Certificates of Detailed Project Report 

Annexure II  : Memorandum of Understanding between Project Implementing  

     Agency and Watershed Committee, Phairuangkai    

Annexure III  : Memorandum of Understanding between Project Implementing  

     Agency and Watershed Committee, Rotlang ‘W’ 

Annexure IV  : Memorandum of Understanding between Project Implementing  

     Agency and Watershed Committee, Runtung 

  Annexure V  : Model Rules and Regulations of Society 

 

Page 6: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 5 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

Chapter – 1:  Introduction 

 

With  a  geographical  area  of  about  21,087  Sq  km  and  perched  on  the  high  hills  of  the 

North Eastern part of  the  country, Mizoram has a very difficult  terrain. Over 80% of  the  total 

geographical area of the state is covered with steep hills. The percentage of rural population is 

50.36  of  which  20.56  %  are  poor.  Broadly,  the  persistence  of  rural  poverty  is  a  result  of 

inadequate  access  to  natural  resources,  over  dependence  on  land,  low  productivity  due  to 

inadequate  use  of  technology,  deficient  infrastructure,  inability  of  rural  people  engaged  in 

traditional  occupational  crafts  to  upgrade  their  skill,  inaccessibility  to  agricultural  land  and  

limited livelihood opportunities by the  rural poor.  

While  60.60%  of  population  comprises  of  cultivators,  agriculture  &  allied  sectors 

contribute only 16.7% of the Gross State Domestic Product (GSDP).This share is declining over 

the  years.  Though  agriculture  is  the mainstay  of  the  state,  only  5% of  the  total  area  is  under 

cultivation, of which only 11%  is  irrigated. The high dependence  for  livelihood on  this  sector, 

with  limited  irrigation  potential  resulting  only  in  single  crop  in  major  portions  of  the  land, 

suggests the need to explore options for income earning potential from this sector. 

  Again, the declining per capita land and fresh water availability coupled with soil erosion 

and degrading land and water resources are posing serious threat to food, environmental, social 

and  economic  security  in  the  State.  Land  degradation  due  to  soil  erosion,  low  water  use 

efficiency,  poor  livestock  productivity,  lack  of  assured  and  remunerative  marketing 

opportunities and poor infrastructure are areas of important concerns. Sustainable development 

of  these rainfed areas, enhancement of  their productivity with  effective resource conservation 

and use of  improved  rainfed  technology  is  an urgent need. The  challenge  in  rainfed Mizoram, 

therefore,  is  to  improve  rural  livelihoods  through  participatory watershed  development with 

focus on integrated farming systems for enhancing income, productivity and livelihood security 

in a sustainable manner. 

   Therefore,  the major  objective behind  the watershed development  approach under  the 

“Integrated  Watershed  Management  Programme”  implemented  by  the  Department  of  Land 

Resources,  Ministry  of  Rural  Development,  Government  of  India  is  to  enhance  and  stabilize 

production  through  improved  technology  and  efficient  use  of  natural  resources  for  over  all 

development of land and inhabitants of the watershed.  

  

Page 7: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 6 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

Chapter­2:  Project Background  

 2.1 Location  

Lunglei  III Watershed Project  is  located within  Lungsen Development  Block  in  Lunglei 

District of Mizoram. The Watershed consists of seven Micro‐watersheds  viz. Lower Phairuanglui 

–  I,    Lower  Phairuanglui  –  II,  Lower  Phairuanglui  –  III,  Lower  Phairuanglui  –  VI,  Lower 

Phairuanglui  –  V,  Lower  Phairuanglui  –  VI,  Lower  Phairuanglui  –  VII  coded  as  3c3c4blc, 

3c3c4c1a,  3c3c4b1b,  3c3c4c1c,  3c3c4d1a,  3c3c4c1d,  3c3c4d2d  respectively.  The  area  lies 

between latitude of 22  47’  23”  to  22  51’ 53” N and longitude of 92  37’  47”  to  92  42’ 17” 

E. The Project Area falls under the “Hilly area” as per the DoLR Classification. Total area of the 

Watershed  is  about  5043  Ha,  of  which  5000  Ha  has  been  undertaken  to  be  treated  under 

Integrated Watershed Management Programme (IWMP). 

   The  nearest  town  is  Lunglei  which  is  about  20  Km  from  Phairuangkai  and  is  well 

connected by pucca road. The watershed includes three villages of Phairuangkai, Rotlang W and 

Runtung along the banks of the Phairuanglui River. The area is inhabited mostly by the Chakma, 

Pang  and  Bru  communities  and  they  are  the  poorest  and  most  backward  communities  in 

Mizoram. The livelihood of these people is primarily based on primitive  and rainfed agriculture, 

animal husbandry and wage labour.  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 8: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 7 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

MAP – 1: LOCATION MAP OF LUNGLEI – III     

  

Page 9: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 8 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

MAP – 2:  WATERSHED MAP OF LUNGLEI DISTRICT   

  

Page 10: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 9 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

Table 1: Basic Project Information.    

     2.2:  Need of Watershed Development Programme  

Watershed Development  Programme  is  prioritised  on  the  basis  of  thirteen  parameters 

namely  Poverty  Index,  Percentage  of  SC/ST,  Actual  wages,  Percentage  of  small  and marginal 

farmers, Ground water  status, Moisture  Index, Area under  rainfed agriculture, Drinking water 

situation  in  the  area,  Percentage  of  the  degraded  land,  Productivity  potential  of  the  land, 

Continuity of another watershed that has already developed/treated, Cluster approach for plain 

or for hilly terrain. Based on these thirteen parameters a composite ranking was given to Lunglei 

Watershed‐III Project as given in Table No. 2.  

The  total  number  of  families  under  BPL  is  270,  which  is  above  80%  of  the  total 

households of the village. Hence a score of 10 is allotted. The percentage of schedule tribes in the 

1   Name of the Scheme/Programme   Integrated Watershed Management Programme (I.W.M.P)  

2   Name of the Project   Lunglei III 3   Name and Code of Micro Watersheds   Lower Phairuanglui – I:          3c3c4blc 

Lower Phairuanglui – II:        3c3c4c1a  Lower Phairuanglui – III:       3c3c4clb Lower Phairuanglui – IV:      3c3c4c1c Lower Phairuanglui – V:       3c3c4d1a Lower Phairuanglui – VI:      3c3c4dld  Lower Phairuanglui – VII:     3c3c4d2d  

4  Name of the Type of the Project  Hilly 5  Names and Census Codes of Villages 

Covered 1. Phairuangkai      00048500 2. Rotlang ‘W’         00048600 3. Runtung               00055200 

6   Name of the Block   Lungsen 7   Name of the District   Lunglei 8  Name of the State   Mizoram 9  Basin/catchment/sub catchment   Phairuang River  10  Latitude   22  47’  23”  to  22  51’ 53” 11  Longitude   92  37’  47”  to  92  42’ 17” 12  Total geographical area of the Project 

(in ha.)  5043 

13  Effective Project Area (in ha.)   5000  14   Total project cost (Rs. in lakh )   750  

15  Name of the P.I.A.   Block Development Officer, Lungsen Rural Development Block 

Page 11: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 10 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

village is about 95 per cent to the total population; hence a score of 10 was allotted. More than 

80 per cent of the farmers are small and marginal by nature and the actual wages earned by the 

labour  is  less  than  the minimum wages and ground water  status  is  critical hence a  composite 

rank of 5, 10 and 10 are allotted respectively.  

Since the rainfall received is erratic and irregular, the moisture index is low and the area 

is  classified  under  DDP  block.  Drinking  water  is  problematic  in  the  village.  The  soil  is  very 

permeable and production of the land can be significantly enriched with the availability of timely 

irrigation. Lunglei III watershed falls in continuity with other watersheds and Cluster approach 

was followed taking into consideration four micro‐watersheds covering a total area of 5000 Ha. 

Thus  all  the  parameters  taken  together  give  a  cumulative  score  of  112.5  to  the  watershed 

(reference Table 2 below).  

  

Table no. 2: Weightage of the Project   Project Name 

Project type 

Weightage 

 Lunglei III 

 Hilly 

i  ii  iii  iv  v  vi  vii  viii  ix  x  xi  xii  Xiii 

10  10  5  10 10 5  15  7.5  15  10  5  NA  10 

    

Table no. 3: Criteria and Weightage for selection of watershed  

 Sl No. 

Criteria  Maximum score 

Ranges & scores 

I  Poverty index (% of poor to population) 

10  Above 80 % (10) 

80 to 50 % (7.5) 

50 to 20 % (5) 

Below 20 % (2.5) 

ii  % of SC/ ST population 

10  More than 40 % (10) 

20 to 40 % (5) 

Less than 20 % (3) 

 

iii  Actual wages  5  Actual wages are 

significantly lower than minimum wages (5) 

Actual wages are equal to or higher than minimum wages (0) 

   

iv  % of small and marginal farmers 

10  More than 80 % (10) 

50 to 80 % (5) 

Less than 50 % (3) 

 

Page 12: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 11 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

V  Ground water status 

5  Over exploited (5) 

Critical (3)  Sub critical (2) 

Safe (0)

vi  Moisture index/ DPAP/ DDP Block 

15  ‐66.7 & below (15) 

DDP Block 

‐33.3 to ‐66.6 (10) DPAP Block 

0 to ‐33.2 (0) 

Non DPAP/ DDP Block 

 

vii  Area under rain‐fed agriculture 

15  More than 90 % (15) 

80 to 90 % (10) 

70 to 80% (5) 

Above 70 % (Reject)

viii  Drinking water  10  No source (10) 

Problematic village (7.5) 

Partially covered (5) 

Fully covered (0) 

ix  Degraded land  15  High –above 20 % (15) 

Medium –10 to 20 % 

(10) 

Low‐less than 10 % of TGA (5) 

 

X  Productivity potential of the land 

15  Lands with low 

production & where 

productivity can be 

significantly enhanced with 

reasonable efforts (15) 

Lands with moderate production & where productivity can be enhanced with 

reasonable efforts (10) 

Lands with high 

production & where 

productivity can be 

marginally enhanced with 

reasonable efforts (5) 

 

xi  Contiguity to another watershed that has already been developed/ 

treated 

10  Contiguous to previously treated 

watershed & contiguity within the micro 

watersheds in the project 

(10) 

Contiguity within the micro 

watersheds in the 

project but non 

contiguous to 

previously treated 

watershed (5) 

Neither contiguous 

to previously treated 

watershed nor 

contiguity within the micro 

watersheds in the 

project (0) 

 

   

2.2 Other Developmental Project/schemes running in the Project Area  

Some of the important poverty reduction programmes implemented by Mizoram and the 

progress  of  implementation  is  summarised  below.  These  programmes  include  the  Mahatma 

Gandhi National Rural Employment Guarantee Scheme (MGNREGS), Border Area Development 

Programme  (BADP),  Swarnajayanti  Gram  Swarojgar  Yojana  (SGSY)  and  Indira  Awaas  Yojana 

Page 13: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 12 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

(IAY). All  these  schemes are  centrally  sponsored  schemes,  except  for BADP which  is  a  central 

sector programme.  

i). Mahatma Gandhi National Rural Employment Guarantee Scheme (MGNREGS)

The basic objective of National Rural Employment Guarantee Act (NREGA) is to enhance 

livelihood security in rural areas by providing at least 100 days of guaranteed wage employment 

in a financial year to every household whose adult members volunteer to do unskilled manual 

work.  This  work  guarantee  can  also  serve  other  objectives;  generating  productive  assets, 

protecting  the  environment,  empowering  rural  women,  reducing  rural  urban  migration  and 

fostering  social  equity,  among  others.  Construction  of  village  extension  roads,  widening  of 

existing  roads,  retaining  walls,  culverts,  RCC  Bridges,  Water  Harvesting  and  Afforestation 

activity has been taken‐up under MGNREGA.  

ii). Border Area Development Programme (BADP): 

The main objective of the BADP is to meet the special developmental needs of the people 

living in remote and inaccessible areas situated near the international border and to bridge the 

gap  in the physical and social  infrastructure of such areas. The aim is  to  transform the border 

areas by  ensuring multifaceted development  and  to  saturate  the  border  areas with  the  entire 

essential  infrastructure  through  convergence  of  schemes  and  participatory  approach.  This 

programme  is  implemented  in  villages  situated  in  International  border  viz.  Indo–Bangladesh 

border and Indo–Myanmar border. Two Community Halls, Concrete internal roads, Playgrounds 

with Pavilions, Widening of Inter‐Village Road, Market Buildings, Public Bathrooms etc has been 

constructed under this Programme in the Project Area. 

 iii). Swarnjayanti Gram Swarozgar Yojana (SGSY) 

The  objective  of  SGSY  is  to  bring  the  assisted  poor  families  (Swarozgaris)  above  the 

poverty line by ensuring appreciable increase in incomes over a period of time.  This objective is 

to be  achieved by  inter‐alia organizing  the  rural poor  into Self Help Groups  (SHGs)  through a 

process  of  social  mobilization,  their  training  and  capacity  building  and  provision  of  income‐

generating  assets  through  a mix  of  bank  credit  and  government  subsidy.  Families  below  the 

Poverty  Line  (BPL)  in  rural  areas  constitute  the  target  group  of  the  SGSY.   Within  the  target 

group, special safeguards have been provided to vulnerable sections, by way of reserving 50% 

benefits  for  SCs/STs,  40%  for women  and  3%  for  disabled  persons.Two  Self‐help  Groups  are 

linked  with  bank  subsidy  of  Rs  1,00,000/‐  each  for  animal  husbandry  and  4  individual 

Swarozgaris of various trades have been assisted with subsidy of Rs.10,000/‐ each  

 

 

Page 14: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 13 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

iv). Indira Awaas Yojana (IAY) 

  The  objective  of  IAY  is  primarily  to  help  construction/up  gradation  of  dwelling  unit  of 

Scheduled  Castes/Tribes  and  other  BPL  rural  households  by  providing  them  lump  sum 

assistance. The amount of assistance provided per dwelling unit used to be Rs. 25,000/‐ and Rs. 

27,500/‐ for plain areas and hilly/difficult areas respectively for new construction and  

Rs. 12,500/‐ for up‐gradation of Kutcha houses. Since 1.4.2008, the assistance is now enhanced 

to  Rs.  35,000/‐  in  plain  areas  and  Rs.  38,500/‐  in  hilly/difficult  areas.  For  up‐gradation,  the 

assistance is also enhanced to Rs. 15,000/‐ per unit.  Total of 50 houses have been constructed in 

the Project Area under Indira Awaas Yojana. 

  

Table No. 4: Developmental Programmes Running In The Project Area:   

Sl. No 

Name of the Programme/ Scheme 

Sponsoring Agency 

Objectives of the 

programme/ scheme 

Villages covered 

Estimated number of beneficiaries 

1  2  3  4  5  6 

1  MGNREGS Rural 

Development Dept. 

Employment  3  465 household 

2  IAY Rural 

Development Dept. 

Housing  3  50 

3  BADP  MHA  Infrastructure  2    

4  SGSY Rural 

Development Dept. 

Livelihood  3  25 

 

Page 15: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 14 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

Chapter – 3:  Basic Information of the Project Area  

3.1. Geography and Geo­hydrology   3.1.1 Land use pattern:   

The net geographical  area of Lunglei‐III Watershed  is  about 8718 ha out of which 6%  is  forest 

area. About 37.2% of  land  is under agriculture which  is completely rain‐fed. About 58.17% of the total 

land is classified under wasteland of which 98.5 percent is cultivable and rest is uncultivable and hilly.  

 3.1.2 Agro­climatic Condition: 

Climate  is  one of  the most  important  factors  of  a  geographical  environment  to which man  is  a 

subject. It control man’s activities like agriculture, forestry, supply of water, industries etc., the climate of 

Mizoram  as  a whole  is  controlled  by  its  location,  physiographic  conditions,  pressure  regime  in North‐

west India and Bay of Bengal, warm and moist maritime tropical air masses from the Bay of Bengal, local 

mountains and valley winds. 

Lunglei District enjoys a moderate climate owing to its tropical location. It is neither very hot nor 

too cold throughout the year. And the district falls under the direct influence of southwest monsoon. As 

such  the  project  area  is  receiving  an  adequate  amount  of  rainfall,  which  is  responsible  for  a  humid 

tropical  climate  characterized  by  short  winter  and  long  summer  with  heavy  rainfall.  During  winter 

season,  the  temperature varies  from 8 C  to 24 C and  in summer  from 18 C  to 32 C. However,  cyclonic 

storm  is  often  experienced  in  the  western  part  of  the  district.  Normally,  heavy  rain  fall  from May  to 

September  and maximum rainfall  is  received during  the month of  August.  The  average  annual  rainfall 

during the last 5 years is 2615 mm. 

 

3.1.3  Soil Classification:  

Soil is the product of interaction between parent materials, climate and biotic factors as modified 

by the terrain conditions and the direction over which the interaction has been going on. The soils of the 

district are generally sandstone and shale. The derived soils are mostly red and yellow loamy. The soil is 

acidic in nature due to heavy rainfall. It contains a high amount of organic carbon and is high in nitrogen, 

low in phosphorous and potassium content. 

 

3.1.4 Land and Agriculture:  

Lack of surface water source and high salinity of ground water has limited the sufficient base for 

irrigation as well as for drinking purpose.  The average land holding is about 2.41 ha ranging from 1 to 4 

ha. Lack of sources of irrigation force the majority of the farmers to migrate to ensure their livelihood. 

This affects directly the demographic profile of the village.  Some of the farmers take up rain‐fed castor 

crop if rainfall is good.  The land conservation measures such as earthen bunds and farm bunds in the 

area will help them to take up a rabi crop of mustard in the residual moisture.

Page 16: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 15 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

Table No. 4: Land-use Pattern in the Project Area:  

Table No. 5:  Agro Climatic Condition  

Sl No. 

Name of the Project 

Name of the Agro­Climatic 

zone covers Project area 

Area     (in Ha) 

Name of the Villages 

Major soil type  Topography. 

Ave.rain fall in mm 

(Preceding 5yrs average) 

Major crops 

          Type  Area  (in Ha) 

    Name  Area     (in Ha) 

1  Lunglei –III (Lower Phairuanglui) 

Humid Sub‐Tropical  5043 

PhairuangkaiRotlang ‘W’ Runtung 

a) Humic Hapladults 

b) Typic Dystrochrepts 

5043  Undulating  2510m 

Paddy, Maize, Sugarcane, Oil seed 

45 

Sl. No Name of Watersheds Names of

Villages

Geographical Area of the

Village

( in Ha )

Forest Area

( in Ha )

Land Under Agricultural

Use

( in Ha )

Rainfed Areas

( in Ha )

Permanent Pastures

( in Ha )

Wasteland

Cultivable

( in Ha )

Non Cultivable ( in Ha )

1 2 3 4 5 6 7 8 9 10

1

Lower Phairuanglui–I Lower Phairuanglui–II Lower Phairuanglui–III Lower Phairuanglui–IV Lower Phairuanglui–V Lower Phairuanglui–VI Lower Phairuanglui–VII

Phairuangkai 1762 50 5 1762 0 1700 7 Rotlang ‘W’ 1900 100 10 1900 0 1750 10 Runtung 5056 350 30 5056 0 1550 55

Total 8718 500 3248 8718 0 5000 72

Page 17: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 16 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

   Table No. 6: Flood and Drought in the Project Area   

  Sl. No  Particulars  Villages  Periodicity  Not effected       Annual  Any other 

(specify)  

          Not affected 

    

Table No. 7:  Soil erosion in the Project Area    

Cause  Type of erosion  Area affected (Ha) 

Run off (mm/yr) 

Ave soil loss (Ton/ha/yr) 

Run off by Heavy Rain  Sheet & Rill  315  18mm 

Jhum paddy 20% slope = 23.50 Tons/ha/yr 40% slope = 31.0 Ton/ha/yr  

Source: Report of Agriculture Production 2008 – 2009. District Agriculture Officer, Lunglei.      3.2. Socio­Economic Profile   3.2.1 Demographic and Ethnographic Status:  

In  spite  of  high  per  capita  of  land  available,  the  production  of  crops  cannot  meet 

requirement  due  to  low  availability  of  inputs,  scarcity  of  irrigation  facilities  as  well  as 

remoteness  of  the  areas.  As  such  20‐30%  of  the  inhabitants  migrate  yearly.  To  increase 

production  of  food  grains  for  the  rural  poor  families,  improvement  and  development  of  land 

resources  and  provision  of  irrigation  facilities  will  constitute  the  main  thrust  areas  of  the 

project. 

Lunglei III   Watershed Project has a total of 445  households with a population of 2048 

(as per base­line survey) out of which 1089 are male and 959 female .The sex ratio is 880 female 

to 1000 male. There are 1638 BPL families. The average family size is 4.6.  Density of population 

in the project area of 23 persons per hectare of land and per capita availably of land is 4.26. The 

major tribes in the village are Mizo, Bru, Pang and Chakma. 

  

Page 18: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 17 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

Table No. 8: Demography and Land Distribution  

Name of the Village 

No. of Household 

Male Population

Female Population

Total Population

Density of Population (person/Ha) 

Per Capita Availability of Land 

Phairuangkai  280  688  589  1277  72  1.38 

Rotlang ‘W’  125  290  270  560  29  3.39 

Runtung  40  111  100  211  4  23.96 

Total  445  1089  959  2048  23  4.26 

   3.2.2 Socio­Economic Condition: 

 

The financial position of the people is generally poor. The density of the population in the 

area is low.  There is no important industry in the area. 

 

3.3. Livelihood pattern:  

 

The villagers earn their livelihood from animal husbandry and agriculture and during 

lean seasons they generally migrate for wage labour to other parts of the state.  

 

 

 

 

 

 

 

Page 19: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 18 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

 

PROBLEM TYPOLOGY OF THE WATERSHED (PRA)  

Sl.No  Problem area  Problem analysis Proposed interventions to 

overcome problems 

1  Soil Conservation (Slope, soil loss, rainfall, productivity, etc) 

Steep slope; heavy soil erosion; large wasteland; low productivity. 

Afforestation, Bunding, Trenching, Terracing etc. 

2  Water conservation (Water budget, Ground water norms, productivity)  Low water table; draught; low rainfall; dry months 

Construction of Water Harvest Tanks, Check Dams, Trenching etc 

3  Crop coverage – {80% of w/s area should be with canopy}  Low crop coverage 

Plantation, Trenching etc 

4  Agriculture productivity (Crop wise compare with dist. Average)  Low productivity; low cropped area. 

Vermi‐composting, Plantation, Terracing etc. 

5  Livestock productivity Underdeveloped livestock rearing; ignorance and absence of animal health care; unavailability of capital funds. 

Fodder Banks, Vety care, Scientific Livestock rearing etc. 

6  Existing Livelihood activities for Asset less persons  Wage labour; subsistence economy 

Development of Carpentry etc, Capacity development and institution building, Provision of Funds 

7  Community Based Organizations & Social capital base 

Economically disorganized community; no organizations based on economic development. 

Development of WCs, SHGs , UGs, SHG Federations 

8  Capacity Building (participation, awareness of watershed community  Low quality of human recourses 

Awareness campaigns, Training of all stakeholders etc. 

9  Any Other (specify)    

  

 

Page 20: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 19 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

 FGD 1: LIVESTOCK GROUP 

   

Work out the physical & financial requirements for the entire Village based on the total animal population  

Sl. No 

Type of Animals 

No. of Animals with 

rearers 

Problem typology (Describe) 

Proposed interventions 

Units Required 

 

Proposed cost (In Rs. Lakhs) 

Animal reproduction 

Animal Health 

Animal management (feed etc) 

Marketing/Trading 

Skills in managem

ent 

Any other 

(specify) 

1  2  3  4  5  6  7  8  9  10  11  12 

  NAME OF VILLAGE:  PHAIRUANGKAI 

1  Milch Animals 

NA  NA  NA  NA  NA  NA  NA  Cattle Rearing Dairy Farming and Fodder Banks 

2 @2.50            per Unit 

2  Draught Animals 

NA  NA  NA  Unsuitable terrain 

NA  NA  NA 

3 Small 

ruminants (Poultry)  

265  Low Low; Vety care absent  

Low skill level; low availability of feed 

Low production; local needs not served 

Low skill level 

NA  Poultry farming  5  @2.50            per Unit

Small ruminants (Goat/ Sheep) 

45  Low Low; Vety care absent  

Low skill level; low availability of feed 

Low production; local needs not served 

Low skill level 

NA  Goat farming  3 @2.50            per Unit

5 Small 

ruminants (Pig) 

70  Low Low; Vety care absent  

Low skill level; low availability of feed 

Low production; local needs not served 

Low skill level  NA  Piggery farming  6 

@2.50            per Unit

Page 21: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 20 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

  NAME OF VILLAGE:  ROTLANG ‘W’ 

1  Milch Animals 

NA  NA  NA  NA  NA  NA  NA  Cattle Rearing Dairy Farming and Fodder Banks 

2 @2.50            per Unit

2 Draught Animals 

NA  NA  NA Unsuitable terrain 

NA  NA  NA 

3 Small 

ruminants (Poultry)  

170  Low Low; Vety care absent  

Low skill level; low availability of feed 

Low production; local needs not served 

Low skill level 

NA  Poultry farming  3  @2.50            per Unit

Small ruminants (Goat/ Sheep) 

25  Low Low; Vety care absent  

Low skill level; low availability of feed 

Low production; local needs not served 

Low skill level  NA  Goat farming  2 

@2.50            per Unit

5 Small 

ruminants (Pig) 

30  Low Low; Vety care absent  

Low skill level; low availability of feed 

Low production; local needs not served 

Low skill level  NA  Piggery farming  2 

@2.50            per Unit

  NAME OF VILLAGE:  RUNTUNG 

1 Milch Animals  2  Low 

Low; Vety care absent  

Scarce  NA  NA  NA  Cattle Rearing Dairy Farming and Fodder Banks 

1  @2.50            per Unit

2 Draught Animals  1  Low 

Low; Vety care absent  

Unsuitable terrain  NA  NA  NA 

3 Small 

ruminants (Poultry)  

103  Low Low; Vety care absent  

Low skill level; low availability of feed 

Low production; local needs not served 

Low skill level  NA  Poultry farming  2 

@2.50            per Unit

Small ruminants (Goat/ Sheep) 

20  Low Low; Vety care absent  

Low skill level; low availability of feed 

Low production; local needs not served 

Low skill level  NA  Goat farming  1 

@2.50            per Unit

5 Small 

ruminants (Pig) 

20  Low Low; Vety care absent  

Low skill level; low availability of feed 

Low production; local needs not served 

Low skill level 

NA  Piggery farming  1 @2.50            per Unit

   

Page 22: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 21 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

 FGD 2: ENTERPRISE DEVELOPMENT GROUP 

 Proposed interventions for Existing Livelihoods 

 

Sl.No Homogenous 

Group Type  of activity 

Average income per 

month 

Problem typology 

Proposed interventions 

Units required 

Unit Cost (In Rs. Lakhs) Procurement 

Production/Service 

Marketing  Skills 

1  2  3  4  5  6  7  8  9  10  11 

1  Micro‐ Enterprises 

Petty Trade  7000/‐  High costs  Local needs; 

low profit  Local  Low level 

Higher investment Skill upgradation Tree Plantation 

15  0.25 

2  Artisans  Carpentry  7500/‐ Scarce raw  material and equipments; 

Local needs; low profit  Local  Low 

level  12  0.25 

  

 

Page 23: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 22 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

 Table No. 9: Summary of Livelihoods 

 

Sl.No Name of Village 

Existing livelihood 

Possible livelihood interventions under 

the project 

Current status of migration (No. of people) 

Main reasons for migration 

1  2  3  4  5  6 

1  Phairuangkai 

Agriculture: Rice from Jhum & WRC        Others Activities : Poultry, Piggery, Goatery 

1. Agriculture:       Land Development       Work for cereal     

Production.  2. Horticulture         Development: For different fruits, crops & Oil Seed 

3. Soil & Moisture Conservation: 

     Bench Terrace, Contour Bund, PRWH etc. 

4. Fishery Dev. 5. Other Homestead Activities  Livestock, Bamboo Craft, Tailoring, Carpentry etc.  

64 

In search of better 

livelihood 

2  Rotlang ‘W’  28 

3  Runtung  11 

    

Page 24: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 23 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

 Chapter – 4:  Project Approach and Strategies 

4.1  Opportunities for intervention 

i). The Project will provide an opportunity for the poor communities, women and the youth 

in particular,  to  form groups  to  increase  their  voice  and  accessibility  to  services  as well  as  to 

strengthen  their  capacity  to  plan  and  implement  programmes  for  economic  and  social 

betterment.  

 ii). The youth, who form about  25 per cent of the total population in the project area, will 

have an opportunity to come together and acquire necessary vocational skills which are relevant 

to the local economy and to take up employment/self‐employment for which there is at present 

few avenues.  

iii). Presently, the poor people in the project area do not have food security for part of the 

year.  The  Project  provides  an  opportunity  for  them  to  improve  food  security  through 

interventions  in  agriculture,  allied  occupations,  and  other  livelihood  activities  and  through 

better management of the natural resources. 

iv).  Channelling  various  development  schemes  particularly  concerning  women  and 

Children through SHGs formed under this project.  

v).   The project will provide platform for women to discuss common problems. 

 vi).  It will  improve awareness  level of  rural women on various development schemes and 

government agencies implementing them.  

 

4.2   Implementation Approach and Methodology 

  The  proposed  design  of  the  project  will  take  note  of  the  shortcomings  of  previous 

programmes  to  improve  plan  strategy  and  focus  on  effective  implementation  for  target 

realization.  The  basic  thrust  of  the  project  is  aimed  at  empowering  poor  households  in  rural 

areas  to directly deal with wide and diverse  range of  problems  and  constraints  that  hampers 

livelihood developments as well as  to place them in a better position  to capture opportunities 

for  livelihood  improvement. These problems  express  themselves  (a)  at  the household  level  in 

terms of food security, (b) at the production system level in terms of low productivity, (c) at the 

community  level  poor  infrastructure  and  service  delivery  and  (d)  at  the  supply  chain  level  in 

terms  of  inadequate  access  to  input  and  output  markets  including  financial  services.  These 

problems  are  interrelated  leading  to  vicious  cycles  and  resulting  in  poverty  traps;  often 

Page 25: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 24 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

exacerbated  by  natural  resource  degradation  as  is  now  conspicuously  happening  in Mizoram 

with declining Jhum cycles being a case in point. 

In order to break out of these poverty traps there  is a need for a holistic approach that 

allows  for dealing with  these  interrelated problems  in a simultaneous  fashion.  It will  focus on 

introducing approaches which: 

• are more responsive to communities’ perceptions of needs and priorities; 

• involve communities more in decision making and planning; 

• make communities more responsible for management of their development programmes 

in order to generate a greater sense of ownership of development interventions; 

• build on the traditional values of community participation; and 

• Utilize the strengths of village institutions and other community organizations. 

 

The Project will  take  into account various on‐going schemes presently at various stages of 

implementation and would facilitate complementing each other and thereby optimize benefits to 

the  targeted beneficiaries. The  first  element of  this  strategy will be  to  introduce participatory 

planning  and  monitoring  processes  and  finance  priority  activities  identified  through  the 

involvement of all stakeholders especially the beneficiaries which will reflect in more productive 

and sustainable use of the available resources. Such planning & monitoring will:  

• assist farmers in the gradual conversion of their presently unsustainable farming systems 

into a more sustainable system through micro financing  

• promoting permanent plantation crops in fallow Jhum fields; 

• introduce crops and agronomic practices which contribute to soil conservation; 

• promote water resource conservation and enhance water‐use efficiency for irrigation; 

• build on the natural advantages of the area through greater emphasis on agro‐forestry as 

sources of livelihood as well as environmental protection; 

• enhance rural income through promoting livestock and fishery enterprise; 

• adopt  strategies  suited  to  the  remoteness  of  region  through  emphasis  on  low  input 

technology and on high value/low volume; and 

• introduce  contract  farming  approach  offering  windows  of  opportunity  for  marketing 

outside the region; 

Emphasis will be given on  social  empowerment  through  formation  of  Self Help Groups 

and rationalization of land utilization according to its suitability for different purposes. The most 

vulnerable  steep  slopes will  be  taken  out  of  agricultural  usage  and  converted  to  forestry  and 

perennial tree crops. Forestry, agro‐forestry and perennial crops development programmes are 

Page 26: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 25 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

planned to first generate livelihood resources for Jhum cultivators and then to gradually reduce 

their dependency on Jhum. Food security strategies will build on the present trend of optimizing 

land utilization  through  switching  to more productive  cash  crops whilst  ensuring  a minimum 

level of home food production.  

The  second  element  of  this  strategy  will  focus  on  developing  self‐reliant  community 

institutions  to  manage  implementation  of  the  project  activities  and  sustain  and  further 

development  in  the  long  term.  A  flexible  approach will  be  required  in  order  to  cater  for  the 

different  socio‐cultural  characteristics  of  the  various  tribal  communities.  As  most  traditional 

community  institutions  exhibit  deficiencies  which  impair  their  suitability  for  management  of 

development  under  the  project,  communities  will  be  encouraged  to  establish  a  Village 

Development Committee  as an arm of the traditional village council, providing for greater focus 

on  vulnerable  groups;  broader  representation  including  women,  youth  and  the  marginalized 

groups; greater accountability and transparency in their operations and greater involvement of 

women in community affairs. The process for establishing the Village Development Committees 

will be in tune with local customs and will be based on consensus of the entire community.  

 

 

4.3 Convergence Strategy:  

• The    implementation    of    a  project    with    emphasis    on    livelihood    development    for  

sustainability    is    often    constrained    by    lack    of  awareness    about    other  rural 

developmental programmes such as SGSY  ,MGNREGS etc,   absence   of   professionals   at 

field  level  to  provide  technical  support,  lack  of  professional  advice  in  preparation  of  

projects    and  absence  of marketing support‐backward &  forward  linkages.    

• Under  the  Project,  SHGs  formation  as  a  measure  for  institution  building  for  social 

empowerment  can be  converged with  funds under  SGSY.   More over  Rural Haat  at  the 

District  with  project  cost  of  Rs.1.5  Crores  to  be  constructed  under  SGSY  will  provide 

necessary marketing infrastructures for SHGs. 

• Under  this  project,  awareness  campaign  among  SHGs  will  be  given  importance  as  a 

means of  social  empowerment which will  help  the  rural  people  in  getting  to  know  the 

various  developmental  schemes  implemented.  This  will  create  behavioural  change 

among the people towards monitoring of implementation of such schemes and there by 

empowered themselves as a strong grassroots level monitoring body.  

Page 27: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 26 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

• The various livelihood activities to be taken up under the Project can be complemented 

by implementation of MGNREGS Scheme. Under MGNREGS , Afforestation , conservation 

of water and land development are the prioritised permissible works and by converging 

with  this  Project  the  much  needed  support  for  farmers  with  requirement  of  upfront 

capital as well as management of natural resources in the form of water conservation and 

forest  protection  can  be  successfully  achieved.  Under  MGNREGS,  SHGs  can  be  given 

Project Implementing Agency role. With better formation of SHG under this Project, SHG 

may be given responsibility of implementation of developmental works on a pilot project 

basis under MGNREGS thereby empowering them to take initiatives. 

• It is proposed that of the 20 (Twenty) Kms of Agricultural Link Roads to be constructed 

under  this Project,  8  (Eight) Kms of  the  road will  be  constructed  through  convergence 

with MGNREGS. 

• Construction of 200 Ha of Terraces as Natural Resources Development under the Project 

will also be undertaken under MGNREGS during a five‐year period.  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 28: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 27 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

 

Chapter 5:  Project Objectives and Scope 

  5.1   Project objectives: 

  The development objective of the Watershed Project would be to  improve capacity 

and opportunities  for  the  targeted  rural  poor  to  achieve  sustainable  livelihoods.  To  achieve  this 

objective the Project will stress on: 

• Conservation, development and sustainable management of natural recourses including 

their use. 

• Enhancement of agricultural productivity and production in sustainable manner. 

• Restoration of ecological balance in the degraded and fragile rainfed ecosystem 

• Empowerment of women through provision of economic opportunities 

• Creation of sustained employment opportunities for the rural community including the 

landless. 

• Enhance participation of the rural poor in economic activities. 

• Increase income among project target households through assets and market linkages. 

 

5.2 Project Core Values: 

  The Project staffs, including the Watershed Development Team, the Watershed 

Association and the community will adhere to the following non‐negotiable principles of the 

project: 

1) Transparency:  All  the  activities  undertaken will  entail  decisions  to  be  taken 

involving  all  those  directly  concerned  in  the  project  activities.  The  process 

followed would be open, clear and accessible to all. 

2) Participation:  The  project will  ensure  participation  of  all  stakeholders.  Each 

decision  taken  would  follow  a  participatory  process  and  there  would  be  no 

imposition at any level. 

3) Team Work  and  Accountability:  At  each  level  the  responsibilities  will  be 

mutually  and  collectively  owned.  Each  stakeholder  is  responsible  for  actions 

taken. 

Page 29: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 28 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

4) Demand  driven:  The  project  will  endeavour  the  stakeholders  to  have  each 

activity  including  group  building,  activity  undertaken  and  preparation  and 

implementation of livelihoods plan based on their demand. 

5) Facilitation:  The  project  implementers  would  play  only  a  catalytic  role  and 

strive to hand over the responsibility to the community to the maximum extent 

possible.  

6) Process Oriented: The entire project implementation has a unique/standard 

process  for  every  stage.  These  standards  will  be  followed  by  all  the 

stakeholders. 

                     

Page 30: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 29 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

Chapter – 6:  Budgeting  

 6.1   Budgeting and Budget Components         

As  provided  in  the  Common  Guidelines,  the  cost  of  the  project  is  divided  into  various 

components  given  in  Table  No.  10  below.  It  helps  us  in  further  identifying  activities  under 

different components and allocate appropriate funds.  

 

Table No. 10: Budget at a Glance 

  

 

SL. No.  COMPONENT  PERCENTAGE OF 

TOTAL OUTLAY AMOUNT 

(in Rs. Lakhs) 

1  2  3  4 

A.  NET PROJECT COST    750.0 

B.  MANAGEMENT COMPONENT   

1.  Administrative Charges  10%  75.0 

2.  Entry Point Activity  4%  30.0 

3.  Capacity Building and Training  5%  37.5 

4.  DPR Preparation  1%  7.5 

5.  Monitoring  1%  7.5 

6.  Evaluation  1%  7.5 

C.  DEVELOPMENT COMPONENT   

7.  Natural Resources Management  50%  375.0 

8.  Livelihood Support System  10%  75 

9.  Farm Production System  13%  97.5 

10.  Consolidation Phase  5%  37.5 

  TOTAL  100%  750.0 

Page 31: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 30 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

 

Chapter 7: Detailed Description of Project Components and Activities 

  

Various studies have revealed that there is need of a systematic and scientific approach to 

deal  with  watershed  development.  The  Common  Guidelines  for  Integrated  Watershed 

Management  Programme  framed  fresh  and  flexible  paradigms  for  watershed  development. 

Detailed description of Components and Activities to be taken up in Lunglei III Watershed are as 

below: 

 

  7.1. Scientific Planning:    i) Cluster Approach   

This envisages a broader vision of Geo‐hydrological unit which involves treating a cluster 

of  micro‐watersheds.  Lunglei  III  Watershed  consists  of  seven  Micro‐watersheds    viz.  Lower 

Phairuanglui  –  I,    Lower Phairuanglui  –  II,  Lower Phairuanglui  –  III,  Lower Phairuanglui  – VI, 

Lower Phairuanglui – V, Lower Phairuanglui – VI, Lower Phairuanglui – VII coded as 3c3c4blc, 

3c3c4c1a,  3c3c4b1b,  3c3c4c1c,  3c3c4d1a,  3c3c4c1d,  3c3c4d2d  respectively.  Further,  the 

watershed is in continuation with other watershed which gives an element of continuation of the 

programme.  

  ii) Base line Survey   

To access the impact of the programme, a detailed Baseline Survey was conducted. This 

will act as a benchmark for any intervention during and post implementation of the project. The 

detailed baseline survey undertaken involved household census survey, Bio‐physical survey and 

Village  level data collection. Household census survey  includes a detailed questionnaire which 

was been filled by visiting each and every household in the three villages. This gave details of the 

demographic  profile  of  the  village,  the  literacy  percentage,  SC/ST  population,  number  of  BPL 

household,  etc.,  and  various  schemes  running  and  their  benefits.  Bio‐physical  survey  was 

undertaken to identify various natural resources available in the village including soil typology, 

wells in the area, crop taken in the field etc.  

     

Page 32: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 31 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

iii) Participatory Rural Appraisal (PRA)   

The  past  experience  of  watershed  has  given  tremendous  input  to  focus  on  creating 

accountability  of  the  stakeholders  towards  the  programme.  This  has  created  an  emphasis  to 

include  all  the  stakeholder  communities  and  their  local  and  Indigenous  Technological 

Knowledge (ITK) while planning for any activity. Participatory approach provides a new path for 

planning,  implementing,  monitoring  and  post‐withdrawal  activities  with  complete 

accountability  of  the  stakeholders.  Various  PRA  techniques  like  resource  mapping,  social 

mapping, and season calendars were used to understand the physical and social orientation of 

the  village  in  general  and  watershed  in  specific.  These  tools  put  the  villagers  at  ease  than 

complicated questionnaires.  

 iv). Use of GIS and Remote Sensing for planning   

Use  of  various  scientific  tools  has  been  promoted  at  various  stages  of  watershed 

development. Geographical  Information System (GIS) has been used  for prioritization process. 

Various  layers of maps relating to Geo‐morphology, Soil, BPL Population, ground water Status, 

drinking water situation, slope percent etc. were created. These were all given proper Weightage 

according to DoLR specification. This helped in prioritization of various watershed areas.  

 

7.2 Institutional Set up &Organization of community  i) Project Implementing Agency 

 Project  Implementing  Agency  will  put  together  a  dedicated  Watershed  Development 

Team. The Project Implementing Agency will provide necessary technical guidance to the Gram 

Panchayat for preparation of development plans for the watershed through Participatory Rural 

Appraisal  exercise,  undertake  community  organization  and  trainings  for  the  village 

communities,  supervise  watershed  development  activities,  inspect  and  authenticate  project 

accounts,  monitor  and  review  the  overall  project  implementation  and  set  up  institutional 

arrangements for post –project operation and maintenance of  assets created during the project 

period. 

 ii) Watershed Development Team 

 The Watershed Development Team is an integral part of the PIA and will be set up by the 

PIA.  Watershed  Development  Team  will  consist  of  technically  trained  persons.  One  woman 

member  with  experience  in  social  mobilization  is  included  in  the  WDT.  Block  Development 

Officer,  Lungsen  will  be  the  Team  Leader  of  WDT.  Team  leader  will  Co‐ordinate  with  other 

Page 33: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 32 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

members for smooth implementation of the project. WDT will assist Gram Sabha in constitution 

of  the Watershed Committee and their  functioning, organizing and nurturing User Groups and 

Self Help Groups, conducting the participatory Baseline Surveys, training and capacity building, 

preparing  detailed  resource  development  plans  including  water  and  soil  conservation, 

undertake  engineering  surveys,  prepare  engineering  drawing  and  cost  estimates  for  any 

structures to be built. 

7.2.1 Community Institution building     The  project  will  promote  a  community  institutional  model  taking  into  consideration 

experiences  and  lessons  learned  from other  rural  livelihoods  projects  taken up/supported  by 

the  Government/Banks.  The  basic  unit  of  the  community  based  institutional  model  will  be 

Watershed Committees (WCs), User Groups (UGs) and Self Help Groups (SHGs). The Watershed 

Committee is a group representing all rural poor households. SHGs are small groups of the poor, 

formed on the basis of social affinity and common interests, in each village. Each SHG will have a 

minimum of  ten  families;  one  or  two members  from  each  household  and  at  least  50% of  the 

member shall be women. The project will provide intensive, hand‐holding support to the SHGs 

in order to help them become vibrant, self managed and sustainable organizations, founded on 

the principles of mutual trust and self‐help among the members. Each SHG will follow a clearly 

laid‐out  sequential  path  of  gradual  development  that will  include  responsible management  of 

group funds through savings and inter‐lending.  

i) Watershed Committee (WC):   

It  is  a  committee  constituted by Gram Sabha  to  implement  the Watershed Project with 

technical  support  of  Watershed  Development  Team  (WDT)  in  the  village.  This  committee  is 

registered  under  Society  Registration  Act  1860.  The  Gram  Sabha  of  the  village  selects  the 

Chairman  of  the  Watershed  Committee  with  the  Secretary.  Capacity  building  training  to  the 

Watershed Committee will  be  given by WDT. The Watershed Committee has  a  pivotal  role  to 

play during and after the project implementation period. 

 ii) User Group:   

User Groups are normally formed to manage an activity or asset created under the programme

on a long term basis. The user group collect user charges from their members, oversee the works and

manage the benefits. It was decided that each group would formulate certain internal rules and have a

feeling of ownership with community spirit.

Page 34: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 33 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

iii) Self Help Group (SHG):   

Self Help Groups  are motivated,  small  homogenous  groups organized  together  through 

credit  and  thrift  activities.  Self  help  group  initiative  especially  for  women  help  uplift  their 

livelihood. Generally self help groups include landless and poor women.  

Before  formation of  the SHGs, during PRA activities, Focussed Group Discussions (FGDs) were 

held with the women, which came up with the following observations: 

  

• Lack of proper credit facilities due to low intervention of formal financial credit 

      Institution 

• Lack of attitude for saving among poor people 

• Lack of knowledge on credit and thrift activity and banking.  

 Strategy for formation of SHGs: 

All the targeted households in the village would be encouraged to form SHGs. Each SHG will 

have a minimum of 10 families. Project beneficiaries form SHGs after agreeing with the concept and 

principles  of  the  Project.  They  will  decide  the  group  name,  and  elect  office  bearers  (President, 

Secretary); jointly open a bank account and the President and Secretary will be the signatories. 

 

(i) Capacity building inputs:  

Capacity building inputs would be provided based on the stage in which the SHG is. WDT 

will  help  strengthen  the  group’s  processes  in  management  of  the  saving,  loan  vetting  and 

repayment, and good governance through norm setting. The concept of credit appraisal, conflict 

resolution etc. are also introduced. 

(ii) Strategy for Existing SHGs:  

There are many SHGs already  in existence  in  the project area. Most of  these have been 

promoted under various programmes. These groups would also be eligible beneficiaries under 

the Project. 

 

 

 

 

 

Page 35: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 34 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

Table No. 11: List of existing Self Help Groups in the Project Area  

 

   7.2.2 Capacity Building    

i) Trainings Trainings will be conducted for all stakeholders in specialised institutions. 

   ii)   Tour & Exposure Visits 

Various tours and exposure visits of WDT members, WC members, UGs and SHGs 

have been planned within the state and out of the state to the successful projects, so that 

all the stakeholders can adopt the successful techniques and researches. 

 

Sl. No. 

Name of Group 

Name of the Village 

Date of Formatio

Members Savings  per head /  per 

month (Rs.) 

RemarksST  Others Total 

1  2  3  4  5  6  7  8  9 

1  Kumtluang  SHG  Rotlang ‘W’  05/06/05 10  0  10  120.00   

2  Vanapa  SHG  Rotlang ‘W’  27/07/05 10  0  10  120.00   

3  Taitesena  SHG  Rotlang ‘W’  01/09/05 10  0  10  120.00   

4  Dyna  SHG  Rotlang ‘W’  01/09/08 10  0  10  100.00   

5  Nauban SHG  Rotlang ‘W’  25/05/10 10  0  10  103.00   

6  Ainawn SHG  Rotlang ‘W’  12/04/09 10  0  10  103.00   

7  Chawnpui SHG  Phairuangkai  14/03/08 10  0  10  110.00   

8  Ropuiliani SHG  Phairuangkai  15/07/08 10  0  10  120.00   

9  Tumchhingi SHG  Phairuangkai  07/07/08 10  0  10  120.00   

Page 36: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 35 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

 Table No.12: Capacity Building Plan (All financial figures in Rs. Lakh) 

 

  CAPACITY BUILDING INSTITUTIONS IN MIZORAM IDENTIFIED FOR IMPLEMENTATION OF 

LUNGLEI­III WATERSHED PROJECT   

Sl. No  Name of Institution  Type  Specialization 

1  State Institute for Rural Development, Kolasib  State Government  Rural Development and 

Watershed Management 

2  Extension Training Centre, Pukpui  State Government  Rural Development and 

Watershed Management 

3  Rural Self Employment Training Institute, Zemabawk

State Government  Carpentry etc 

4  Indian Council for Agricultural Research, Kolasib

Central Government  Agriculture, Horticulture and allied Subjects 

Integrated Training Centre, Hnathial 

State Government  Agriculture, Horticulture and allied Subjects 

6  Industrial Training Institute, Aizawl  State Government  Mechanic, Electrician etc 

   

Sl. No 

Activity No of 

Persons 

Frequency/ No of Training Programmes 

Estimated Cost 

(In Rs.Lakhs) 1  2  3  4  5 

1  Training of Project Stakeholders ‐ WDT  5  3  1.5 

2  Training of Project Stakeholders ‐ WCs  50  5  1.5 

3  Training of Project Stakeholders ‐ SHGs  300  8  11.0 

4  Training of Project Stakeholders ‐ UGs  700  11  11.0 

5  Exposure Tours and Visits  ‐  4  7.5 

6  Street Plays  ‐  Unspecified  0.5 

7  Video Shows and Documentation  ‐  Unspecified  2.5 

8  Pamphlets and Posters  ‐  ‐  0.5 

9  Banners and Hoardings  ‐  ‐  2.5   TOTAL  37.5 

Page 37: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 36 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

7.3 Physical Activities to Be Undertaken  7.3.1 Entry Point Activity (EPA)   

EPA activities are taken up under watershed projects to build a rapport with the village 

community  at  the  beginning  of  the  project;  generally,  certain  important  works  which  are  in 

urgent demand of  the  local  community  are  taken up. A  group Discussion was  conducted with 

Watershed Development Committees regarding the EPA activity. It was conveyed to the WC that 

an amount of Rs. 30 Lakhs was allotted for EPA activity, which was 4 per cent of total allocated 

budget. The villagers discussed various activities which they felt is important and finally decided 

on those given below. 

   

Table No.13 Entry point activities (EPA)   

     

Sl. No 

Names of Villages 

Amount Earmarked for EPA 

(In Rs. Lakh) 

Entry Point Activities Planned Estimated Cost (In Rs. Lakhs) 

1  2  3  4  5 

1 Phairuangkai Rotlang  ’W’ Runtung 

30.0 

Construction of Agriculture Link Road, 4 Kms.   15.0 

Construction of Public Urinal (6 Units @ Rs.25000.00 each)  1.50 

Construction of Rainwater Harvesting Structures (3 Units @ Rs.3 Lakhs each) 

9.0 

Construction of R.C.C Resting Inns  (3 Units @ Rs.1.5 Lakhs) 

4.50 

Page 38: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 37 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

 7.3.2 Detailed Cost Estimates for works taken up under Entry Point Activities (EPA)   

Table No. 14 Cost Estimate for construction of Water Harvesting Tank  

Sl. No. Description No. L B W Qnty. Unit Rate Amount

1 2 3 4 5 6 7 8 9 10

1/2.08

Earthwork in excavation in foundation trenches etc not exceeding 2 m depth etc a) Hard Soil

Column - 9 1.10 1.10 1.10 11.98 m3

Total 11.98 m3 163.60 1959.93

2/4.05 Providng and laying cement concrete 1:3:6

Foundation 9 1.10 1.10 0.20 2.18 m3

Total 2.18 m3 3991.60 8701.69

3/5.01

Providng and laying RCC 1:2:4

(a) all work upto fdn. & plinth level

Foundation- 9 1.10 1.10 0.45 4.90 m3

Total 4.90 m3 4859.40 23813.49

b) Columns - 9 0.30 0.30 2.00 1.62 m3

Wall 4 3.00 2.40 0.20 5.76 m3

Total 7.38 m3 4991.00 36833.58

c) Beams - 6 0.20 0.30 3.00 1.08 m3

Suspended Floor/Roof 1 3.00 3.00 0.12 1.08 m3

1 3.00 3.00 0.20 1.80 m3

Total 3.96 m3 6093.30 24129.47

4/5.06

HYSD bars reinforcement for RCC work etc

Fdn. @ 100 kg/m3 490.05 Kg

Columns @ 310 kg/m3 502.20 Kg

Beam @ 270 kg/m3 291.60 Kg

Page 39: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 38 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

Suspended Floor/Roof/Wall @ 100 kg/m3

864.00 Kg

Total 2147.85 Kg 49.40 106103.79

5/5.08

Centering and Shuttering including strutting, propping etc.

c) Column - 34 0.30 2.00 20.40 m2 241.60 4928.64

d) Beam 6 0.20 3.00 3.60 m2

8 0.30 3.00 7.20 m2

Total 10.80 m2 184.20 1989.36

Suspended Floor/Roof 2 3.00 3.00 18.00 m2 276.00 4968.00

Wall 8 3.00 2.40 57.60 m2 206.30 11882.88

6/21.21

12mm Cement plaster 1:4 finished with a floating coat of neat cement.

1 3.00 3.00 9.00 m2

4 3.00 2.40 28.80 m2

Net Total 37.80 m2 163.80 6191.64

7/18.05

Providing & fixing GI pipe complete with GI fitting

20mm dia. Nominal bore 1 3.00 3.00 Rm 122.30 366.90

40mm dia. Nominal bore 1 1.25 1.25 Rm 248.20 310.25

TOTAL = 232179.1

Add 6% for site development = 13930.78

NET TOTAL = 246110.9

Add 21.90 % for Cost Index = 53898.18

Grand Total 300008.7

Say 300000.0

(Rupees Three Lakh) only

Page 40: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 39 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

        

Page 41: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 40 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

Table No. 15 Cost Estimate for construction of Public Urinal  

Sl. No. Description No. L B W Qnty. Unit Rate Amount 1 2 3 4 5 6 7 8 9 10

1/2.08

Earthwork in excavation in foundation trenches etc not exceeding 2 m depth etc a) Ordinary Soil

1 0.60 0.60 2.00 0.72 m3

6 0.60 0.60 0.60 1.30 m3

Total 2.02 m3 109.10 220.38

2/5.01

Providng and laying RCC 1:2:4

(a) all work upto fdn. & plinth level

Foundation- 6 0.60 0.60 0.20 0.43 m3

Post 6 0.20 0.20 1.90 0.46 m3

Total 0.89 m3 4859.40 4315.15

3/5.06

HYSD bars reinforcement for RCC work etc Fdn. @ 100 kg/m3 43.20 Kg Columns @ 310 kg/m3 141.36 Kg Total 184.56 Kg 49.40 9117.26

4/5.08

Centering and Shuttering including strutting, propping etc. Post 24 1.90 0.30 13.68 m2 241.60 3305.09

5/6.09

7.5 cm thick brick masonry with first class brick in superstucture above plinth level upto floor etc (a) in cement mortar 1:3 Walling 2 1.50 2.00 6.00 m2 3 1.50 1.20 5.40 m2 Total 11.40 m2

6/12.02

Cement Concrete flooring 1:2:4 finished with a floating coat of neat cement c) 75 mm thick 1 1.80 2.00 3.60 m2 429.70 1546.92

7/21.12 15mm cement plaster 1:3 4 1.50 2.00 6.00 m2 6 1.50 1.20 10.80 m2 Total 16.80 m2 169.80 2852.64

8/21.85

Distempering with oil bound washable distemper or new work (two or more coats)

Qnty BF item No 7/21.12 16.80 m2 49.00 823.20 TOTAL = 22180.64 Add 21.90 % for Cost Index = 4857.56 Grand Total 27038.20 Say 27000.00 (Rupees One Lakh Fifty Thousand) only  

Page 42: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 41 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

  

   

Page 43: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 42 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

Table No. 16 Cost Estimate for construction of Agriculture link road  

( As per PWD (MZ) SOR 2008 - Rural Road )

TOTAL LENGTH : 4000 M

Sl. No. Description Unit L

(m) W (m) Qty Rate

(in Rs) Amount ( in Rs)

1 2 6 3 4 5 7 8

1/2.2

Clearing and Grubbing of road length including uprooting wild vegetation, shrubs, etc. complete (i) Manual means (A) in area of Thorny jungle

Ha 4000.00 3.50 1.40 26638.00 37293.20

2/2.3

Cutting of Trees including cutting of trunks, and removal of stumps and roots, compaction of back filling etc.

(i) Girth above 300mm-600mm No. 115 103.00 11845.00

(ii) Girth above 600mm-900mm No. 89 192.00 17088.00

(iii) Girth above 900mm-1800mm No. 40 360.00 14400.00

3/8.3

(ii)(A) Excavation in hilly area by Mechanical means m3. Qty taken from

E/W Table 15682.14 55.00 862517.70

(iv) Excavation in hilly area in ordinary rock not required blasting by Mechanical means

m3 Qty taken from E/W Table 4780.86 95.00 454181.70

TOTAL: 1397325.60 For Surveying ( Detailed Survey Estimate attached): 102690.00

GRAND TOTAL: 1500015.60

( SAY ): 1500000.00

( Rupees Fifteen Lakhs) only     

Page 44: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 43 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

ESTIMATE FOR SURVEYING

TOTAL LENGTH : 4000 m

Sl. No. Description Unit No L

(m) W(m)

H/D(m) Qty Rate

(in Rs) Amount ( in Rs)

1 2 6 3 4 5 7 8

PRELIMINARY SURVEY 

1/2.2

Jungle clearance for Initial Stage (i) By Manual means:  (a) In area of thorny Jungle: 

m2  1  4000  1     4000.00  2.277  9108.00 

DETAILED SURVEY 

2/2.2 Jungle clearance for Detailed Survey (i) By Manual means:  

m2  1  4000  1.5     6000.00  2.277  13662.00 

TRACE PATH CUTTING 

3/8.3

Earthwork in Hill road.  (i)Excavation in hilly area in Soil by Manual  means 

m3  1  4000  0.6  0.45  1080  74.00  79920.00 

TOTAL:    102690.00

(Rupees One Lakh two thousand six hundred ninety) only.   

      

Page 45: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 44 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

 Table No. 17 Cost Estimate for construction Of Resting Shed 

  

Sl. No. Description No. L B W Qnty. Unit Rate Amount 1 2 3 4 5 6 7 8 9 10

1/2.08

Earthwork in excavation in foundation trenches etc not exceeding 2 m depth etc a) Ordinary Soil Column - 4 1.00 1.00 1.00 4.00 m3 Tie Beams - 2 4.00 0.20 0.20 0.32 m3 2 3.00 0.20 0.20 0.24 m3 Total 4.56 m3 109.10 497.50

2/5.01

Providng and laying RCC 1:2:4 (a) all work upto fdn. & plinth level Foundation- 4 0.90 0.90 0.20 0.65 m3 Tie Beams - 2 4.55 0.20 0.30 0.55 m3 2 3.10 0.20 0.30 0.37 m3 Shelves - 1 4.55 0.60 0.10 0.27 m3 2 1.68 0.60 0.10 0.20 m3 2 1.90 0.60 0.10 0.23 m3 Total 2.27 m3 4859.40 11024.03 b) Columns - 4 3.40 0.20 0.20 0.54 m3 4991.00 2695.14 c) Beams - 2 4.55 0.20 0.30 0.55 m3 2 3.10 0.20 0.20 0.25 m3 Total 1.34 m3 5093.30 6825.02

3/5.06

HYSD bars reinforcement for RCC work etc Fdn. @ 100 kg/m3 64.80 Kg Columns @ 310 kg/m3 167.40 Kg Beam @ 270 kg/m3 609.66 Kg Shelves @ 100 kg/m3 70.26 Kg Total 912.12 Kg 49.40 45058.73

Page 46: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 45 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

4/5.08

Centering and Shuttering including strutting, propping etc. c) Column - 16 3.40 0.25 13.60 m2 241.60 3285.76 d) Beam 2 4.55 0.20 1.82 m2 4 4.55 0.30 5.46 m2 2 3.10 0.20 1.24 m2 4 3.10 0.30 3.72 m2 Total 12.24 m2 184.20 2254.61

5/6.09

7.5 cm thick brick masonry with first class brick in superstucture above plinth level upto floor etc (a) in cement mortar 1:3 Walling 6 0.60 0.73 2.63 m2 2 4.55 0.75 6.83 m2 2 3.10 0.75 4.65 m2 Total 14.10 m2 Deduct openning Door 'D' 1 1.20 0.75 0.89 m2 Net Total 13.21 m2 425.90 5625.71

6/9.08

Providing & fixing 1st class local wood in trusses etc including hoisting, fixing in position etc complete Rafter - 10 4.00 0.10 0.075 0.30 m3 Colar - 10 2.40 0.10 0.075 0.18 m3 Purlin - 10 5.10 0.08 0.050 0.19 m3 Total 0.67 m3 13579.80 9098.47

7/12.02

Cement Concrete flooring 1:2:4 finished with a floating coat of neat

Page 47: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 46 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

cement

c) 75 mm thick 1 4.55 3.10 14.09 m2 429.70 6054.26

8/16.01

Providing corrugated GS sheet roofing fixed with necessary nut, bolt and washers etc complete (e) 0.63 mm thick 2 4.10 5.10 41.82 m2 319.90 13378.22

9/16.06

Providing & fixing 0.63 mm thick plain GS sheet ridges etc complete (b) 0.63 mm thick 1 5.10 5.10 Rm 251.30 1281.63

10/21.12

15mm cement plaster 1:3 2 13.00 26.00 m2 2 1.00 4.55 9.09 m2 2 0.85 3.10 5.24 m2 4 0.85 1.85 6.24 m2 Total 46.57 m2 169.80 7907.59

11/21.85

Distempering with oil bound washable distemper or new work (two or more coats) Qnty BF item No 10/21.13 46.57 m2 49.00 2281.93

TOTAL = 117268.59 Add 5% for site development = 5863.43 NET TOTAL = 123132.02 Add 21.90 % for Cost Index = 26965.91 Grand Total 150097.93 Say 150000.00 (Rupees One Lakh Fifty Thousand) only

     

Page 48: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 47 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

 7.3.3. Natural Resources Management:   

A multi‐tier Ridge to Valley Sequence Approach will be utilized for implementation of 

watershed development works. A net budget of 50 % is allotted for these works.  

 Ridge Area Treatment Plans:  Water  resources  originate  from  the  Ridge  area.  This  involves  hilly  and  forest  and 

wasteland region in the watershed. For the ridge area the following structures are proposed:  

    i). Stone Bunding  

  ii). Staggered Contour Trenches  

 iii). Border Contour Trenching with Tree plantations  

 

i). Stone Bunding  Stone bunds will be constructed along contours or streams. It will be adopted where the 

water velocity is high and where basically stone of radius 100‐150 mm is available. It helps in:  

· Control of erosion by reducing the slope of the cultivated land  

· Increasing the infiltration of rainwater 

Main advantages as compared to the normal contour bunding are:  

· Ridge area of the project has much steeper slopes  

· The region has shallow soil depth.  

· It is a more permanent structure if well maintained  

· It is self – stabilizing  

 ii). Staggered Contour Trenches  

Trenches  are  any  form of depression or micro pit  constructed over  the  land  surface  in 

order  to  prevent  soil  erosion  and  to  absorb  rainwater  in  non‐arable  lands.  Trenches  will  be 

constructed along the contours on hill slopes with vegetative supports for forestry, moisture and 

soil  conservation  and  horticulture  land  uses.  Contour  Trenches  will  be  used  on  both  on  hill 

slopes as well as on degraded and barren waste lands. The trenches break the slope and reduce 

the  velocity  of  surface  runoff.  It  can  be  used  in  all  slopes  irrespective  of  rainfall  conditions, 

varying soil properties. For vegetative support forage grasses as well as economic trees can be 

planted.  Periodical  maintenance  by  way  of  unearthing  of  the  trenches  and  depositing  on  the 

downhill  side  ought  to  be  given  due  attention  by  the  beneficiaries  themselves.  SCT  are  been 

planned to be constructed in the hilly terrain where slope is not so steep.  

 

 

Page 49: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 48 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

iii). Border Contour Trenching:  

Border contour trenches will be constructed to collect the runoff below the hills so that 

plantation of trees can be taken up.  

 

Slope treatment:  

The second tier treatment is the Slope Treatment. This is generally done on agricultural 

land  or  waste  land.  This  generally  includes  water  conservation  or  surface  water  storage 

structures. This being highly labour intensive, will involve more of manual labour; so, funds from 

Mahatma Gandhi National Rural Employment Guarantee Scheme (MGNREGS) will be utilized as 

a measure of Convergence.  

Following structures are proposed in these areas:  

  i).  Terracing 

ii).      Check Dams 

iii).  Earthen Bund  

iv).    Afforestation 

v).  Farm Ponds 

vi).  Agriculture Link Roads 

vii).  Water Harvest Tanks  

 

Construction of agriculture link roads is much needed as 80% of the Project area is not 

accessible by roads. Construction of roads will enable movement of goods and services as well as 

ensure better implementation of works.   A total  length of 20 kms of roads will be constructed. 

Cost for constructed of 8 kms of the road will be met from MGNREGS funds. 

  Construction of Check Dams,  Farm Ponds  and Water Harvesting Structures will  ensure 

conservation of water during  the rainy season and thereby raise  the water  table. They will be 

constructed across existing streams and rivers. They will serve as sources of irrigation for farms 

and will also be used for aquaculture. 

  Afforestation and earth bunds will aid water and soil conservation, regenerate forests in 

wastelands and barren lands as well as improve ecological balance in the wastelands.  

Terraces  will  be  constructed  on  all  suitable  lands  for  plantation  of  agriculture  and 

horticulture crops as well as  for Wet Rice Cultivation. Cost  for construction of  terraces will be 

converged with MGNREGS funds. 

 

  

Page 50: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 49 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

  

Table No. 18: Model Technical Specification of Stone Bund  

 Particulars  Value  Unit 

Length of bund  3.60  M 

Bottom with of bund  1.00  M 

Top width  0.45  M 

Depth above a ground level  0.60  M 

Depth of foundation  0.20  M 

No. of Units   5000  Nos 

   

Table No. 19: Estimation for Stone Bund (Per Unit)  

Sl. No. 

Description  No.  L  B  H  Qnty.  Unit  Rate  Amount (In Rs) 

1  2  3  4  5  6  7  8  9  10 

Clearing grass and removal of rubbish upto a distance of 50m outside the periphery of the areas cleared.                              By manual means. 

   3.60  1.00

  

3.60  Sqm 3.40  12.24 

Constructing hand packed dry stone walls with stone boulders including excavation in foundation trench, etc. including supply of stone, labour etc complete. 

   3.60  0.73 0.80 2.09  cum 1042  2175.70 

      TOTAL  2187.94 

     

GRAND TOTAL                                        Cost of Construction of 3000 Units 

(2187.94x3000)  65,63,820.00 

  (Rupees Sixty­five Lakhs, Sixty­three Thousand and Eight Hundred and Twenty) only 

Page 51: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 50 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

  

Table No. 20: Model Technical Specification of Staggered Contour Trenches (Per Unit)  

 

Particulars  Value  Unit 

Trench Length  17.5  M 

Trench width  0.45  M 

Trench Depth  0.45  M 

No. of Trenches proposed for construction  16080  No. 

   

Table No. 21: Cost Estimation of Staggered Contour Trenches  

Sl. No.  Description  No.  L  B  H  Qnty.  Unit  Rate  Amount 

1  2  3  4  5  6  7  8  9  10 

Surface dressing of ground including removing vegetation and inequalities not exceeding 15cm deep and disposal of rubbish, lead upto 50m and lift upto 1.50m 

1  30.00 0.75    22.50  Sqm  18.80  423.00 

Earth works in excavation in foundation/Trenches etc. not exceeding 1.5m depth including dressing  of side, ramming of bottom, refilling of blank spaces with soil and disposal of surplus excavated soil upto 50m. 

1  30.00 0.60 0.60 10.80  cum  151.90  1640.52 

3  Sowing of seed on the constructed ridge  1  30.00       30  m  1.50  45.00 

4  Supply of Stylo Seed @ 4 gm/m in two lines  2  30.00     2.4  kg  6.00  14.40 

Overseeding of grasses in between two furrows including seed treatment and pellet making etc. complete @ 27gm/m 

27  30.00     8.10  kg  8.50  68.85 

TOTAL  2191.80 GRAND TOTAL 

{ Cost of Construction of 5590 Units (2191.8x5590)}  122,52,156.00 

(Rupees One Hundred Twenty­two Lakhs Fifty­two Thousand One Hundred and Fifty­six) only

Page 52: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 51 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

 Table No. 22: Model Technical Specification of Bordered Contour Trenches (Per Unit)   

Particulars  Value  Unit 

1  2  3 

Trench Length  30.00  M 

Trench type  Trapezoidal    Trench depth  1.00  M Trench width  2.00  M Trench Top width  5.00  M Trench cross section  3.50  Sqm Total units  300.00  nos.     

 Table No. 23: Cost Estimation for Bordered Contour Trench  

  Sl. No.  Description  No.  L  W  D  Qnty.  Unit  Rate  Amount 

1  2  3  4  5  6  7  8  9  10 

Surface dressing of ground including removing vegetation and inequalities not exceeding 15cm deep and disposal of rubbish, lead upto 50m and lift upto 1.50m    

30.00 2.00    60.00  Sgm  18.90  1134.00 

Earth works in excavation in foundation/Trenches etc. not exceeding 1.5m depth including dressing of sides and ramming of  bottom, refilling of blank spaces with soil and disposal of surplus excavated soil upto 50m. Ordinary Soil.    

30.00 3.50 1.00 105.00  cum  151.90  15949.50 

       TOTAL   17083.50 

     GRAND TOTAL                                      

{Cost of Construction of 300 Units(300x17083.50)}  5125050.00 

(Rupees Fifty­one Lakhs, Twenty­five Thousand and Fifty) only 

  

  

Page 53: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 52 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

 Table No. 24:  Technical Details of Afforestation Activities (per Ha) 

 

Particulars  Value  Unit 

1  2  3 

Crop Name  Champ, Hollock, Toonaciliata etc.    

Plant to Plant Spacing  8.00  m Row to Row Spacing  8.00  m Pit Length  0.90  m Pit Width  0.90  m Pit Depth  0.90  m No. of Plant per Hac  1250  No. Gap Filling  25  % Plantation Area (Per Unit)  1  Ha Total  Plantation Area  100  Ha  

Table No. 25: Per Unit Cost Estimation for Afforestation Activities (1Ha Area)  

Sl. No. Description No. L B W Qnty. Unit Rate Amount

1 2 3 4 5 6 7 8 9 10

1

Earthwork in excavation in trenches not exceeding 1.5m depth including dressing of sides and ramming of bottom, refilling of soil up to 0.20m and disposal of surplus soil lead upto 50m.

1250 0.75 0.75 0.75 527.34 cum 18.00 9492.19

2

Plants sampling for Plantation not less than 30cm height including loading and unloading of plants, Transportation of Plants from nursery to camp site upto 20km

1250 1250 Nos 17.40 21750.00

3 Rehandling of Plants from camp site to actual planting site up to 500m

1250 1250 Nos 1.50 1875.00

4 Weeding & Hoeing two times (twice in a year) 1250 1250 Nos 2.10 2625.00

TOTAL 35742.19Grand Total {for 100 Units (100 Ha) = (100x35742.19)} = Rs.35,74,219.00 

(Rupees Thirty­five Lakhs, Seventy­four Thousand, Two­hundred and Nineteen)

  

Page 54: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 53 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

Table No. 26: Cost Estimate for construction of Check Dam Type ‘A’  

Sl. No. Description No. L B W Qnty. Uni

t Rate Amount

1 2 3 4 5 6 7 8 9 10

1/2.08

Earthwork in excavation in foundation trenches etc not exceeding 2 m depth etc b) Hard Soil

Foundation 1 30.0

0 1.50

0.60 27.00 m3

2 3.00 1.00

0.60 3.60 m3

Total 30.60 m3 163.60 5006.16

2/7.03

Course rubble masonry with hard stone in foundation up to one storey above and below ground level including curing etc. complete. A.(c) In cement mortar 1:6

Check Dam Foundation. 1 30.0

0 1.20

0.40 14.40 m3

Apron. 1 30.00

1.00

0.15 4.50 m3

Total 18.90 m3 2948.70 55730.43 B.(b) In cement mortar 1:4 Check Dam superstructure above plinth level.

1 30.00

0.90

4.10

110.70 m3

Wing wall 2 3.00 0.7 4.50 19.71 m3

Total 130.41 m3 3784.10 493484.48

3/21.24

20mm cement plaster 1:3 finished with a floating coat of neat cement.

1 30.00

0.56 16.80 m2 247.50 4158.00

TOTAL = 558379.07

Add 21.90 % for cost index   =  122285.02 

GRAND TOTAL   =  680664.09 SAY   =  680660.00 

                                                For construction of 2 Units. @ Rs. 680660.00  =   Rs. 1361320.00 (Rupees Thirteen  Lakhs Sixty­one Thousand Three Hundred Twenty) only

 

Page 55: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 54 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

 Table No. 27: Model Cost Estimate for construction of Check Dam Type ‘B’ 

   

Sl. No. Description No. L B W Qnty. Unit Rate Amount

1 2 3 4 5 6 7 8 9 10

1/2.08

Earthwork in excavation in foundation trenches etc not exceeding 2 m depth etc b) Hard Soil

Foundation 1 25.00 1.50 0.60 22.50 m3

2 3.00 1.00 0.60 3.60 m3

Total 26.10 m3 163.60 4269.96

2/7.03

Course rubble masonry with hard stone in foundation in to one storey above and below ground level including curing etc. complete. A.(c) In cement mortar 1:6

Check Dam Foundation. 1 25.00 1.20 0.4 12.00 m3 Apron. 1 25.00 1.00 0.15 3.75 m3

Total 15.75 m3 2948.70 46442.03 B.(b) In cement mortar 1:4 Check Dam superstructure above plinth level.

1 25.00 0.90 3.60 81.00 m3

Wing wall 2 3.00 0.73 3.60 15.77 m3 Total 96.77 m3 3784.10 366179.79

3/21.24

20mm cement plaster 1:3 finished with a floating coat of neat cement.

1 25.00 0.60 15.00 m2 247.50 3712.50

TOTAL = 420604.27

Add 21.90 % for cost index = 92112.34 GRAND TOTAL = 512716.61

SAY = 513000.00 For 5 Units @ Rs. 513000.00 = Rs. 25,65,000.00

(Rupees Twenty-five Lakhs and Sixty-five Thousand) only      

Page 56: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 55 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

 Table No. 28: Cost Estimate for construction of Check Dam Type ‘C’ 

  

Sl. No. Description No. L B W Qnty. Unit Rate Amount

1 2 3 4 5 6 7 8 9 10

1/2.08

Earthwork in excavation in foundation trenches etc not exceeding 2 m depth etc b) Hard Soil

Foundation 1 20.00 1.50 0.60 18.00 m3

2 3.00 1.00 0.60 3.60 m3

Total 21.60 m3 163.60 3533.76

2/7.03

Course rubble masonry with hard stone in foundation up to one storey above and below ground level including curring etc. complete. A.(c) In cement mortar 1:6

Check Dam Foundation. 1 20.00 1.20 0.2 4.80 m3 Apron. 1 20.00 1.00 0.2 3.00 m3

Total 7.80 m3 2948.70 22999.86 B.(b) In cement mortar 1:4 Check Dam superstructure above plinth level.

1 20.00 0.90 3.30 59.40 m3

Wing wall 2 3.00 0.73 3.30 14.45 m3 Total 73.85 m3 3784.10 279470.92

3/21.24

20mm cement plaster 1:3 finished with a floating coat of neat cement.

1 20.00 0.60 12.00 m2 247.50 2970.00

TOTAL = 308974.54

Add 21.90 % for cost index = 67665.42 GRAND TOTAL = 376639.97

SAY = 377000.00 For 6 Units. @ Rs. 377000.00 = Rs. 22,62,000.00                             (Rupees Twenty­two Lakhs Sixty­two Thousand) only 

      

Page 57: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 56 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

 Table No. 29: Model Technical Details of Earthen Bund 

 

Particulars  Value  Units 

1  2  3 

Structure length  20.00  m 

No. of Earth Bund  150  No. 

Structure height  1.30  m 

Bund top width  0.90  m 

Base width  2.90  m 

Structure Cross‐section area  1.90  Sqm 

Downstream slope  1:1   

Upstream slope  2:1   

 

Table No. 30: Cost Estimation of Earthen Bund 

 

Sl.No  Description  Unit  No.  Length  Width  Height  Quantity  Rate Amount (In 

Rupees) 

1. 

Clearing grass, bush, sapling etc. by manual means 

Sqm  1  20.00  4.00    80.00  2.4  192.000 

2. 

Earthwork in excavation including breaking of clods etc. with combine lead upto 15 metres. Ordinary soil 

Cum  1  20.00  1.90  1.00  38.00  55.40  2105.2 

          Total  2297.20 

  Grand Total For Construction of 150 Units (2297.20x150) = Rs.344580.00  

  (Rupees Three Lakhs Forty­four Thousand, Five Hundred and Eighty) Only  

 

 

Page 58: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 57 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

 

Table No.31: Model per Unit Estimate for Construction of Agriculture Link Road 

 (1 Unit=1000m) 

(As per PWD (MZ) SOR 2008 ­ Rural Road) 

 

 

Estimate for Cost of Survey (Per Unit): 

Sl. No. Description Unit No L

(m) W(m)

H/D(m) Qty Rate

(in Rs) Amount ( in Rs)

1 2 6 3 4 5 7 8

PRELIMINARY SURVEY 

1/2.2

Jungle clearance for Initial Stage (i) By Manual means:  (a) In area of thorny Jungle: 

m2  1  1000  1     1000.00  2.277  2277.00 

DETAILED SURVEY 

2/2.2 Jungle clearance for Detailed Survey (i) By Manual means:  

m2  1  1000  1.5     1500.00  2.277  3415.50 

TRACE PATH CUTTING 

3/8.3

Earthwork in Hill road.  (i)Excavation in hilly area in Soil by Manual  means 

m3  1  1000  0.6  0.45  270  74.00  19980.00 

TOTAL:    25672.50 

(Rupees Twenty­five Thousand Six hundred Seventy­two) only.  

   

 

 

 

 

Page 59: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 58 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

Detailed Estimate (per Unit): 

Sl. No. Description Unit L

(m) W (m) Qty Rate

(in Rs) Amount ( in Rs)

1 2 6 3 4 5 7 8

1/2.2

Clearing and Grubbing of road length including uprooting wildvegetation, shrubs, etc. complete (i) Manual means (A) in area of Trony jungle

Ha 1000.00 3.50 0.35 26638.00 9323.30

2/2.3

Cutting of Trees including cutting of trunks, and removal of stumps and roots, compection of back filling etc.

(i) Grith above 300mm-600mm No 28 103.00 2884.00

(ii) Grith above 600mm-900mm No 22 192.00 4224.00 (iii) Grith above 900mm-1800mm No 10 360.00 3600.00

3/8.3

(ii)(A) Excavation in hilly area by Mechanical means m3 Qty taken from E/W

Table 3920.54 55.00 215629.43

(iv) Excavation in hilly area in ordinary rock not required blasting by Mechanical means

m3 Qty taken from E/W Table 1195.22 95.00 113545.43

Sub-total: 349206.16 For Surveying ( Detailed Survey Estimate attached): 25672.50

Total: 3,75,000.00 GRAND TOTAL: For Construction of 8 Units (8 x 375000.00) = Rs. 30,00,000.00

(Rupees Thirty Lakhs) only  

 

Table No. 32: Model Technical Details of Farm Pond  

Particulars  Value  Unit 

1  2  3 

Pond Length  15.00  M 

Pond Width     

Pond Depth  2.4  M 

Side slope  2:1   

 

 

 

Page 60: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 59 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

 

Table No. 33: Cost Estimation of Farm Pond 

 

Sl. No 

Description  No.  Unit  Length  Width  Height  Qnty  Rate  Amount (In Rupees) 

1 Clearing bushes, vegetation etc. by manual means 

1  Sqm  15  5.6    84.00  2.40  210.60 

Earthwork in excavation including breaking of clods etc. with combined lead upto 15 m. Ordinary soil 

1  Cum  15  15.00  2.4  540.00  55.40  29916.00 

TOTAL  30126.60 

GRAND TOTAL  (for construction of 15 Units@ Rs. 30126.60 per Unit)  451899.00 

SAY  451855.00 

(Rupees Four Lakhs, Fifty­one Thousand Eight Hundred and Fifty­five) only 

 

 

 

7.3.4: Activities under Farm Production System 

The following activities will be taken up under Farm Production System: 

• Bamboo Cultivation 

• Passion fruit Cultivation 

• Arecanut Cultivation  

• Greenhouse farming/Protected Cultivation 

• Rubber Cultivation 

They have been  found  to be most  suitable with reference  to  the  climate and soil  in  the 

project area and also taking into consideration the readily available market for these products. 

They will be  intercropped with other vegetables and plants such as banana, bird’s eye chillies, 

tomato etc. 

 

 

 

 

 

Page 61: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 60 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

Table No. 34: Per Unit Cost­benefit analyses for Bamboo Cultivation 

 Unit Area      :  2 Hectares. Unit Cost      :  Rs. 2, 50,000.00  I. MAIN TRADE: SN  Particulars  Quantity  Rate (Rs)  Amount (Rs) 

First Year 

i)   Planting materials (clump)  2500 nos.  10.00  25,000.00

ii) Tools & Implements  LS  LS  4,500.00

iii) Area preparation  200 MD  132.00  26,400.00

iv) Fire Prevention Line  180 MD  132.00  23,760.00

v) Pit Digging and Contour Bund  120 MD  132.00  15,840.00

vi) Construction of Contour Bund  100 MD  132.00  13,200.00

vii) Transportation  LS  LS  4,500.00

Total of 1st Year  1,13,200.00 

Second Year 

i) Water Storage Tank  (2000 litres each)  2 Nos.  8/lit  32,000.00 

ii) PVC pipe    LS  14,000.00 

iii) Fire Prevention Line  80 MD  132.00  10,560.00 

iv) Weeding  90 MD  132.00  11,880.00 

Total of 2nd Year  68,440.00 

Third Year 

i)  Fire Prevention Line  80 MD  132.00  10,560.00 

ii)  Weeding  90 MD  132.00  11,880.00 

Total of 3rd Year  22,440.00 

Grand Total of 1st + 2nd + 3rd Year  2,04,080.00 

 

II. SUBSIDIARY TRADE: 

SN  Particulars  Quantity  Rate (Rs)  Amount (Rs) 

A.       Vegetable garden (800 Sq.m) 

i) Land  Preparation  including  construction  of contour bunds 

40MD  132.00  5,280.00

ii) Vegetable seeds  LS  LS  2,090.00 

iii) Weeding (3 times)  40MD  132.00  5,280.00 

iv) Organic manure/FYM  LS  LS  2,000.00 

v) Transportation and handling  LS  LS  1,000.00 

Sub Total of A  15,650.00 

Page 62: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 61 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

B.        Poultry (100 sq. m) 

i)  Chicks  100 Nos.  45.00  4,500.00 

ii)  Poultry feed  LS  LS  4,000.00 

iii)  Poultry shed  LS  LS  5,000.00 

iv)  Sanitation/Health Care  LS  LS  1590.00 

v)  Transportation and Handling  LS  LS  1090.00 

Sub Total of B  16,180.00 

C.        Piggery (100 sq.m) 

i)  Piglet  2 Nos.  3000.00  6,000.00 

Ii)  Pig Feed  LS  LS  3,000.00 

iii)  Pig Sty  1 no.  LS  4,000.00 

iv)  Sanitation/Health Care  LS  LS  1000.00 

vi)  Transportation and Handling  LS  LS  1,090.00 

Sub Total of C  14,090.00 

Total of II( A + B + C)  45,920.00 

Total of I + II  2,50,800.00 

III. COST­BENEFIT ANALYSIS: 

Year  Trade  Cost  Income  Net Income 

 

 

Bamboo  1,13,200.00 (‐)1,13,200.00

Vegetable garden  15,650.00 I9,719.00 (+)4,069.00

Poultry  16,180.00 33,800.00 (+)17,620.00

Piggery  14,090.00 33,050.00 (+)18,960.00

Sub­Total  1,59,120.00  86,569.00  (­)72,551.00 

 

 

Bamboo   68,440.00 (‐) 68,440.00

Vegetable garden  15,650.00 I9,719.00 (+)4,069.00

Poultry  16,180.00 33,800.00 (+)17,620.00

Piggery  14,090.00 33,050.00 (+)18,960.00

Sub Total  1,14,360.00  86,569.00  (­)27,791.00 

 

 

Bamboo  22,440.00 (‐)22,440.00

Vegetable garden  15,650.00 I9,719.00 (+)4,069.00

Poultry  16,180.00 33,800.00 (+)17,620.00

Piggery  14,090.00 33,050.00 (+)18,960.00

Sub Total  68,360.00  86,569.00  (+)18,209.00 

Page 63: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 62 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

 

 

Table No.  35: Per Unit Cost­benefit analyses for Passion fruit Cultivation 

Unit Area     :  2 Hectares. Unit Cost    :  Rs. 2, 50,000.00 

Sl. No. 

Particulars  Quantity Rate (Rs.) 

Amount (Rs.) 

I.  1st Year          

   i) Seedlings  5000 nos.  3.00       15,000.00 

   ii) G.I. wire  16.0 qtls.  7950.00    1,27,200.00

   iii) Pit digging and planting  60 MD  132.00       7,920.00

   iv) Collection of wooden post  60 MD  132.00       7,920.00

   v) Erection of trailing (pergola)  60 MD  132.00       7,920.00 

   vi) Weeding  100 MD  132.00        13,200.00 

   vii) Transportation  L.S  L.S        4000.00 

   Total of 1st Year      1,83,160.00  

II.  2nd Year        

   i) Secateur (+12% CST)  2 no.  396.00           792.00

   ii) Sprayer  2 no.  1500.00 3,000.00

   iii) Water storage tank  3000 lts  8.00  24,000.00

   iv) PVC Pipe  L.S  L.S        8,000.00 

   v) P.P. measures  L.S  L.S        4,000.00 

   vi) Pruning  14 MD  132.00  1848.00

   vii) Weeding  100 MD  132.00        13,200.00 

   viii) Organic manure  10 qtls.  1200.00       12,000.00 

   Total of  2nd Year          66,840.00  

   G. Total of I+II        2,50,000.00  

         

 

 

 

 

Bamboo  1,20,000.00 (+) 1,20,000.00

Vegetable garden  15,650.00 I9,719.00 (+)4,069.00

Poultry  16,180.00 33,800.00 (+)17,620.00

Piggery  14,090.00 33,050.00 (+)18,960.00

Sub Total  45,920.00  1,80,650.00  (+) 1,34,730.00 

Page 64: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 63 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

COST­BENEFIT ANALYSIS: 

1.  1st Year 

  i) Expected yield / ha.            =  175 qtls. 

  ii) Returns from sale of 175 qtls. @ Rs. 1,000/qtl.     =  Rs. 1,75,000.00 

2.  2nd Year 

  i) Expected yield/ha            =  250 qtls. 

  ii) Returns from sale of 250 qtls. @ Rs. 1,000/qtl.    =  Rs. 2, 50,000.00 

3.  Gross income upto 2nd Year          =  Rs. 4,25,000.00 

   Income will be stabilized from 3rd year onwards @ 500 qtls Per Unit.  

 

Table No.  36: Per Unit Cost­benefit analyses for Arecanut Cultivation 

 

Unit Area    :   2 Hectares. Unit Cost    :   Rs. 2,50,000.00 

Sl. No. 

Particulars  Quantity  Rate (Rs.)  Amount (Rs.) 

I.  First Year           

i)  Arecanut seedlings  3200 nos.  8.00  25,600.00

ii)  Birds eye chilli  4kg.  300.00           1,200.00 

iii)  Water Storage Tank  3000 lts  8.00  24,000.00

iv)  PVC Pipe  L.S.  L.S.        12,000.00 

v)  Organic manure  16 qtls.  1,200.00        19,200.00 

vi)  Pit digging, planting & broad casting  160 MD  132.00        21,120.00 

vii)  Irrigation  80 MD  132.00  10,560.00

viii)  Weeding  90 MD  132.00  11,880.00

ix)  Transportation  L.S.  L.S.        4,000.00 

   Total of 1st year            1,29,560.00  

II.  Second Year          

i)  Organic manure  16 qtls.  1,200.00        19,200.00 

ii)  Plant Protection Measures  L.S.  L.S.        4,000.00

iii)  Plant nutrients  L.S.  L.S.        5,000.00 

Page 65: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 64 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

iv)  Sprayer  2 no.  1,500.00  3,000.00 

v)  Irrigation  80 MD  132.00  10,560.00

vi)  Weeding  90 MD  132.00  11,880.00

vii)  Application of Plant Protection measures  & Plant nutrients  60MD  132.00       7,920.00

viii)  Transportation  L.S.  L.S        2,000.00 

   Total of 2nd Year            63,560.00  

III.  Third Year         

i)  Organic manure  20qtls.  1,200.00      24,000.00

ii)  Irrigation  80 MD  132.00  10,560.00

iii)  Weeding  90 MD  132.00  11,880.00

iv)  Application of Plant Protection measures  & Plant nutrients  60MD  132.00       7,920.00

v)  Transportation  L.S.  L.S  2,520.00

   Total of 3rd Year        56,880.00 

   G. Total of I+II+III        2,50,000.00 

      COST­ BENEFIT ANALYSIS: 

1.  1st Year ‐ 6th Year   i) Expected yield        =   40 qtls. (Dried)                      (Birds eye chilli each year)   ii) Expected returns @ Rs. 8,000 per qtl.   =   Rs. 3, 20,000.00  2.  7th Year   i) Expected yield @ 250 nuts/ tree    =  6, 40,000.00 nuts   ii) Expected returns @ Rs. 0.75 per nut.  =  Rs. 4, 80,000.00  3.  Gross Income       =  Rs. 8, 00,000.00      Yield will be stable from 8th year @ Rs. 4, 00,000 nos. of nuts/ha. 

 

 

 

Page 66: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 65 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

Table No.  37: Per Unit Cost analyses for Greenhouse farming 

 

Green House Area           :        1000 sq.mt. 

Crop                                       :         Vegetables/ Flowers 

Unit Cost                              :  Rs. 2, 50,000.00 

 Main Trade: 

Sl. No. 

Particulars  Quantity Rate (Rs.) 

Amount (Rs.) 

1  U.V. film for roof  1650 sqm.  50.00      82,500.00 

2  Shade net for side wall  960 sqm.  45.00      43,200.00 

3  Materials like local timbers and bamboo for structures  L.S  L.S      69,000.00 

4  Nails, strings etc.  L.S  L.S   3,500.00 

5  Construction of Green House   55 MD  132.00        7,260.00 

6  Land development and preparation of  beds  25 MD  132.00        3,300.00 

7  Manures (FYM)  700 tins  15.00        10,500.00 

8  Seeds/ Plants  L.S  L.S        6,600.00 

9  Operational Cost  80 MD  132.00        10,560.00 

10  Transportation of Inputs  L.S  L.S        13,580.00 

 Total  

2,50,000.00 

 

 

 

 

 

 

Page 67: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 66 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

7.3.5: Activities under Livelihood Production System   

The main activities  to be  taken up under Livelihood Production  System are  specifically 

aimed at those who are asset less. Trainings will be provided to all proposed beneficiaries before 

provision  of  funds.  They  will  be  assisted  either  in  groups  (after  formation  of  SHGs)  or  as 

individuals.  The  Project  will  provide  funds  upto  a  maximum  of  Rs.2.50  Lakhs  per  SHG  and 

Rs.25000.00 per individual. Initially, each SHG and individual will be provided one Unit of each 

activity/Trade.  Additional  units  will  be  provided  upon  performance  to  deserving  groups  and 

individuals. Main activities proposed to be taken up under Livelihood Production System are as 

follows:‐  

• Dairy farming 

• Poultry farming (Layer) 

• Poultry farming (Broiler) 

• Hill cattle/Methuen rearing 

• Goat/Sheep rearing 

• Pig rearing 

• Aquaculture 

• Vermin‐Composting 

• Electronic goods Servicing 

• Carpentry 

• Petty Trade 

• Tailoring 

The  list of activities  is not exhaustive. SHGs/Individuals may  take up other activities as 

per its interest and capacities.  

 Table No. 38: Per Unit Cost­Benefit Analyses for Dairy Farming 

Unit Size      :   4 Cross – Bred Cows Unit Cost                           :   Rs. 2, 50,000.00 

     Sl.No  Particulars  Unit  Total A.  CAPITAL EXPENDITURE : 

1)  Cost of construction of Byre ( Cowshed) –          60 sqft per cow @ Rs.250 /‐ per sqft ( i.e             60 x 4 = 240 sqft)  for 4 cows  2)  Cost of equipments like Allmn. Bucket for        milking , Allmn. Dekchi and  milk can etc. 3)  Water Storage Tank @ Rs.8/‐ per Litre.                            

   L.S 2750 Lits capacity

Rs.60,000.00

Rs.   4,000.00

Rs.22,000.00

    TOTAL :  Rs. 84,000.00

Page 68: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 67 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

B.  RECURRING EXPENDITURE : 1) Cost of 4‐ Dairy Cows @ Rs. 35,000/‐,per       cow including transportation cost. 2) Cost of feeds up to 1 months @ 3kg per        cow per day @ Rs. 10/‐ per kg  of feeds 3) Insurance premium @ Rs. 6.5% of original       cost for 4 cows ( i.e. 4 x 2600.00) 4) Veterinary Aids including Vaccines and       Medicines etc. @Rs.500/‐per cow 

       L.S 

Rs.1,40,000.00

Rs.  3,600.00

Rs.  10,400.00

Rs.   2,000.00 

    TOTAL  Rs1,56,000.00C.    Land preparation for Kitchen gardening    Rs. 8,000.00  Total Unit Cost (A+B+C+D)    Rs. 2,50,000.00  COST­BENEFIT ANALYSIS:  E.  GROSS INCOME FOR ONE YEAR 

 1) Sale of 5400 lits of milk. Average 10 lits Per cow per day for 270 days @ Rs. 25/‐ per lit 2) Sale of manure ( cow dung)  

    L.S 

Rs. 2,70,000.00

Rs. 10,000.00

    TOTAL  Rs. 2,80,000.00 

F.  EXPENDITURE FOR ONE YEAR :  1) Cost of feeds  for 365 days @ 3kg.cow/  day @ Rs. 10/‐ per kg of feeds 2) Insurance  premium @ Rs. 6.5% of original cost 3) Veterinary Aids & Medicine and Vaccines etc 

      L.S 

Rs.43,800.00

Rs.10,400.00

Rs.   2,000.00     TOTAL   Rs. 56,200.00   NET INCOME FOR ONE  YEAR 

( i.e. E­ F ) Rs. 2,80,000 – 56,200.00    

Rs.2,23,800.00 

 

 

 

 

 

 

 

 

 

Page 69: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 68 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

Table No.  39: Per Unit Cost­benefit analyses for Poultry farming (Layer) 

 Unit Size        :    400 Nos  Unit Cost                                    :    Rs: 2, 50,000.00 

  A. 

 CAPITAL EXPENDITURE:  i) Construction of layer house with locally available       materials with tin roofing @ 1.02 sqft per bird      (i.e 1.02 sqft x 400 birds) = 408 sqft at the rate of     Rs. 150/‐ per sqft. ii)Cost of feeding trough & water trough etc. 

       L.S 

Rs. 61,200.00

 Rs. 10,000.00

    Sub­Total 

Rs.71,200.00 

 B. 

 RECURRING EXPENDITURE :  i)   Cost of Day –old chicks  @ Rs. 35/‐ per chick   For 400 chicks.  ii)   Cost of feed upto 8 months: Chick mash: 0 – 8  weeks (2 months)  @ 45gm/chick/day at the rate of Rs. 13.00 per kg  Grower Mash 8 – 20 weeks (3 months) @ 100gms/chick/day at the rate of  Rs. 13.00 per kg Layer mash 20 – 32 weeks (3 months) @ Rs.140gm/bird/day at the rate of Rs. 13.00 per kg iii)   Vety Aids including vaccine & medicines etc.  @ Rs. 20/‐ per bird 

 

Rs. 14,000.00 

 Rs. 14,040.00

 Rs. 46,800.00

Rs. 65,520.00  

Rs. 6,000.00

    Sub­Total  

Rs. 1,46,360.00 

C.  Land Development for Kitchen gardening  

L.S  Rs.12,440.00

D.  Electrification of layer house etc.  

  Rs. 4,000.00

E.  Water harvesting facilities @ Rs. 8/‐ per lit  2000 lit Capacity 

Rs. 16,000.00

   GRAND TOTAL INVESTMENT COST  

(i.e A+B+C+D+E) 

 Rs. 2,50,000.00 

Page 70: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 69 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

       .  

 COST­BENEFIT ANALYSIS:   GROSS INCOME FOR THE FIRST ONE – YEAR 1) Sale of eggs – 180 eggs per bird @ Rs.5.00 per egg (i.e 180X400 birds) = 72,000 eggs 

 

 Rs. 3,60,000.00

  TOTAL  Rs. 3,60,000.00 

EXPENDITURE FOR THE FIRST YEAR  1) Cost of feeds : a)  Chick mash ‐ @ 2.7kg per bird ( 0‐8) weeks )  @ Rs.13/‐ per kg b) Grower mash ‐ @ 9kg per bird ( 8‐20 weeks)  @ Rs.13/‐ per kg c) Layer mash ‐@ 12.6kg per bird ( 24‐32) weeks) @ Rs.13/‐ per Kg 2) Veterinary Aids including Vaccines and Medicines etc @ Rs.20/‐ per bird 

  

Rs. 14,040.00 

Rs. 46,800.00

Rs. 65,520.00

Rs   8,000.00

  TOTAL  Rs. 1,34,360.00  

 NET INCOME FOR ONE YEAR : Rs. Rs. 3,60,000.00 ‐ Rs. 1,34,360.00 

 Rs.2,25,640.00 

   

Table No. 40: Per Unit Cost­benefit analyses for Poultry farming (Broiler) 

    Unit Size        :   400 Broilers     Per Unit                                    :   Rs: 2, 50,000.00 

    A. 

 CAPITAL EXPENDITURE  i) Construction of layer house with locally available materials with tin roofing @ 1.02 sqft per bird ( i.e 1.02 sqft x 400 birds) = 204 sqft at the rate of Rs. 150/‐ per sqft. ii) Cost of feeding trough & water trough etc.  

       L.S 

Rs. 61,200.00

Rs. 15,000.00

    TOTAL  Rs. 72,200.00  

 B. 

 RECURRING EXPENDITURE :  i)   Cost of Day –old chicks  @ Rs. 35/‐ per chick   For 400 chicks. 

 

Rs. 14,000.00 

Page 71: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 70 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

 ii)   Cost of feed upto 8 months: Chick mash: 0 – 8  weeks (2 months)  @ 45gm/chick/day at the rate of Rs. 13.00 per kg  Grower Mash 8 – 20 weeks (3 months) @ 100gms/chick/day at the rate of  Rs. 13.00 per kg Layer mash 20 – 32 weeks (3 months) @ Rs.140gm/bird/day at the rate of Rs. 13.00 per kg iii)   Vety Aids including vaccine & medicines etc.  @ Rs. 20/‐ per bird 

   

Rs. 14,040.00

 Rs. 46,800.00

Rs. 65,520.00   

Rs. 6,000.00

    Sub­Total  

Rs. 1,46,360.00 

 C. 

 Land Development for Kitchen gardening 

 L.S  Rs. 10,500.00

 D. 

 Electrification of layer house etc. 

 LS  Rs. 8,050.00

E.  Water harvesting facilities @ Rs. 8/‐ per lit  2000 lit  Rs. 16,000.00

  TOTAL INVESTMENT COST   (A+B+C+D+E) 

  Rs.2,50,000.00  

 F. 

 COST­BENEFIT ANALYSIS;  GROSS INCOME FOR THE FIRST CYCLE   

1) Sale of 370 broilers @ Rs.200.00 per kg     One broiler attains 3 kg at 3 months    (370 x 3 kg x Rs. 200.00) 

   

 Rs.2,22,000.00  

  TOTAL  Rs.2,22,000.00

Income for 1 Year (4Cycles) =4x2,22,000  

G.TOTAL  Rs .8,88,000.00

Page 72: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 71 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

 G. 

 EXPENDITURE FOR THE FIRST CYCLE 1)   Cost of Day –old chicks  @ Rs. 35/‐ per chick   For 400 chicks.  2) Cost of feeds : a)  Chick mash ‐ @ 1.8kg per bird ( 0‐4) weeks ) @ Rs.13/‐ per kg b) Grower mash ‐ @ 3.6kg per bird (4‐8 weeks)  @ Rs.13/‐ per kg c) Finisher mash ‐@ 6.6kg per bird (8‐12) weeks)  @ Rs.13/‐ per Kg 3) Veterinary Aids including Vaccines and Medicines etc @ Rs.30/‐ per bird 

  

14,000.00

Rs. 9,360.00 

Rs. 18,720.00 

Rs. 34,320.00

Rs. 12,000.00

  TOTAL  Rs. 84,400.00

  Expenditure for 1 Year (4Cycles) =4x84,400 

G.TOTAL   Rs. 3,45,600.00

  NET INCOME FOR ONE YEAR : (i.e. F‐G ) Rs .8,88,000.00 ­ 3,45,600.00   

 TOTAL 

    Rs . 5,42,400.00 

 

 

 

 

Table No. 41: Per Unit Cost­benefit analyses for Hill cattle/Methuen rearing 

 

 Unit Size            :  8 FEMALE + 2 MALE UNITS  Cost Per Unit                                      :   Rs. 2, 50,000.00 

 A.  CAPITAL EXPENDITURE : 

1) Construction of cattle  shed for night shelter. Half 

wall, Tin roofing with locally available  materials. 

(25’ x 12’ )  

  L.S  Rs. 38,000.00

    TOTAL :  Rs. 25,000.00

B.  RECURRING EXPENDITURE : 

1) Cost of 20 local cattle of average 6 months old @ 

Rs. 8,000/‐ (2 male + 18 female cattle ) 

 

Rs. 1,60,000.00

    TOTAL  Rs. 1,60,000.00

C.  Land Development for Kitchen gardening  L.S  Rs. 12,000.00

Page 73: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 72 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

D.  Construction of watering trough @ Rs. 8/‐ per lit  3000litres 

Rs. 24,000.00

E.  Veterinary Aids casting   L.S  Rs. 6,000.00

F.   Cost of Min. Mixture, casting  rope, farm implements 

etc.  

L.S  Rs. 10,000.00

  TOTAL  INVESTMENT COST 

(A+B+C+D+E+F) 

  Rs. 2,50,000.00 

   COST­BENEFIT ANALYSIS:   GROSS INCOME Sale of 20 cattle at the end of the 1st year attaining 120 kg body wt at 18 months,   @ Rs. 150/‐ kg of meat  

 

Rs. 3,60,000.00

  TOTAL  Rs. 3,60,000.00

RECURRING EXPENDITURE  (To be borne by  beneficiary from income of  1st year) 1)  cost of 20 local cattle of average 6 months old @ Rs. 8000/‐ per cattle as replacement stock. 2)  cost of mineral mixtures, vaccines and vitamins @ Rs. 500/‐ per cow 3) Veterinary aids, medicines etc @ Rs. 300/‐ per animal 

    

 

 Rs. 1,60,000.00

Rs. 10,000.00

Rs. 6,000.00    TOTAL   Rs, 1,76,000.00

  NET INCOME FOR ONE YEAR  (Rs. 3,60,000.00  ‐ Rs. 1,76,000.00) : 

    Rs. 1,84,000,00 

 

 

 

 

 

 

 

Page 74: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 73 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

Table No. 42: Per Unit Cost­benefit analyses for Goat/Sheep rearing 

 

    Unit Size       :     96 FEMALE + 4 MALE     Per Unit                                    :     Rs. 2, 50,000.00 

     A.  CAPITAL EXPENDITURE : 

 1) Construction of House for night shelter with locally available materialist 4sqft / goat = 400sqft @ with tin roofing.  

   L.S 

Rs. 40,000.00

    TOTAL :  Rs. 40,000.00 B.  RECURRING EXPENDITURE : 

 1) Cost of  foundation  stock 96 female goat + 4 male goat of 3 months old @ Rs. 800/‐ per kg live weight   2) purchase of Minerals & Vets lick  3) Veterinary Aids including Vaccines and Medicines etc 

      L.S  L.S 

 Rs. 80,000.00

Rs. 6,000.00

Rs. 5,000.00

    TOTAL :  Rs. 91,000.00 C.  Land Development for Kitchen gardening  L.S  Rs. 15,000.00

D.  Construction of watering trough @ Rs. 8/‐ per lit  3000 Lits  Rs. 24,000.00

E.  Fencing with Barbed wire  L.S  Rs. 80,000.00

  TOTAL INVESTMENT COST  (i.e. A+B+C+D+E) 

  Rs. 2,50,000.00 

   COST­BENEFIT ANALYSIS:  

GROSS  INCOME FOR THE FIRST YEAR :  

1) Sale of 200 nos. of young goats assuming 50% of goat kidded  twice a year and the goat has attained 5kgs live weight per kid @ Rs. 800/‐ per kid 

 

Rs. 1,60,000.00 

 G.  TOTAL  Rs. 1,60,000.00EXPENDITURE FOR THE FIRST YEAR :  

1) Veterinary Aids including vaccination and medication 2) Purchase of Mineral mixture & vets licks etc  

    

Rs. 5,000.00

Rs. 6,000.00  H.  TOTAL   Rs. 11,000.00  NET INCOME  FOR THE FIRST – YEAR 

 

( i.e. G ‐ H = Rs. 1,60,000 – Rs.11,000 )  

Rs.1,49,000.00 

 

 

Page 75: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 74 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

Table No. 43: Per Unit Cost­benefit analyses for Pig rearing 

 

 Unit Size          : 4 SOWS + 10 FATTENERS Cost Per Unit         : Rs. 2, 50,000.00  

Sl.No. 

Particulars  Unit  Total 

A.  CAPITAL EXPENDITURE : 1)  Cost of construction of 4 Farrowing   Pen        (i.e. 12’ x 6’ x2) = 144 sqft. with locally available            materials @ Rs. 200/‐   per sqft. 2) Cost of construction of 10 fatteners sty        (i.e. 16’.02 x 6’x 2)  = 192.2 sqft with locally  available      Materials @ Rs. 200/‐ per sqft. 3) Cost of construction of piglets box. 4) Cost of utensils like Allmn. Bucket / Dekchi 

       

             L.S L.S 

Rs. 28,800.00

Rs. 38,440.00 

Rs. 4,000.00Rs. 8,000.00

    TOTAL  Rs. 77,240.00 B.  RECURRING EXPENDITURE : 

1)  Cost of foundation stock of 14nos. of      piglets ( 4 female + 10 male for fatteners )            of 2 months old @ Rs. 3500 /‐ per piglet 2) Cost of conc feed upto 6 months for         fatterners @ 3 qtls./ Pig at the rate of            Rs. 12/per kg of feeds. 3)  Cost of conc. feed upto 12 months for 4 Sow @      Rs. 5.70 qtls./ sow @ Rs. 12/‐   per kg of feeds.     4) Veterinary Aids including purchase of        vaccines & medicines, A.I & boar Service                            

       

Rs.49,000.00

Rs. 50,400.00

Rs. 27,360.00

Rs. 5,000.00    TOTAL  Rs. 1,31,760.00 

C.  Land Development for Kitchen Gardening  L.S  Rs. 15,000.00D.  Water Harvesting Facility @ Rs. 8/‐ per lit.  3000 lit. Cap.  Rs. 24,000.00  TOTAL INVESTMENT COST (A+B+C+D)    Rs. 2,50,000.00 

  COST BENEFIT ANALYSIS GROSS INCOME FOR THE FIRST ONE YEAR  1) Sale of 10 nos of fatteners ; assuming 90kgs/ fattener @ Rs.200/‐ per kg of pork 2) Sale of 36 piglets @ Rs. 3500/‐ per piglet  EXPENDITURE FOR ONE YEAR :  

1) Cost of Conc.  feeds  2) Veterinary Aids including vaccines & medicines, A.I. & Boar Service charge  NET INCOME  FOR ONE YEAR :  ( Rs. 3,06,000.00  ‐ . 80,760.00) 

   

Rs.1,80,000.00  

 Rs. 1,26,000.00     

Rs. 77,760.00  

    Rs. 3,000.00 

Rs. 3,06,000.00           Rs. 80,760.00 

Rs. 2,25,240.00

 

Page 76: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 75 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

Table No. 44: Per Unit Cost­benefit analyses for Aquaculture 

 

Unit Area      :  2 Hectares.  Unit Cost      :  Rs. 2, 50,000.00  A. Capital Investment 1) Construction of 2.0 ha of new pond (1.8 ha main pond and 0.2 ha 

rearing pond) as per unit cost of FFDA (GOI).  

2) Nets and gears (1 dragnet, 2 hand nets) 

Rs.2,00,000.00    Rs.     8,000.00 

Sub­total ‘A’:­  Rs.2,08,000.00  B. Annual Recurring Expenditure 1) Slaked lime 500kg/ha for 2 Ha – 1000kg @ Rs.4.780/Ha

 2) Fish  seed  (fry  for  raising  15,000  to  20,000nos  of  100mm  size 

fingerling in the rearing tank to stock the main pond) 30,000nos of fry per unit @ Rs.160.00 per 1000nos 

3) Organic manure – Raw cowdung at a dose of 10 M.T/Ha for 2Ha‐20 M.T @ Rs.0.40/kg 

4) Inorganic Fertilizer:‐ 1) Urea – 300kg/ha @ Rs.10.00/kg for 600kg 2) SSP – 240kg/ha @ Rs.9.00/kg for 480kg 3) Micro nutrient – 12kg/ha @ Rs.150.00/kg for 24kg 

 5) Fish  feed  –  Concentrated/Palleted  at  a  dose  of  700kg/unit  @ 

Rs.1500/qtl  

Rs.     4,780.00  Rs.     4,800.00    Rs.   8,000.00  Rs.     6,000.00 Rs.     4,320.00 Rs.     3,600.00  Rs.   10,500.00    

Sub­total ‘B’:­  Rs.   42,000.00 TOTAL A+B:­  Rs.2,50,000.00 

 C. Economic Return of the Unit 1. Gross Return 

i) Production of table size fish @ 2000kg/ha from 2.0 Ha ii) Gross  annual  sale  proceed/income  from  4000kg  of  fish  @ 

Rs.120/kg 2. Investment 

i) Capital investment per unit ii) Annual recurring expenditure iii) Depreciation  of  capital  investment  presuming  lifetime  at  15 

years iv) Cost on Annual repair on 3rd, 6th and 9th year, 10% of capital 

investment v) Total of ARE, Depreciation and Annual repair (ii+iii+iv) 

 3. Net Annual Revenue/Profit 4. BCR of the Unit at NPV 

4000kg Rs.4,80,000.00  

 Rs.2,08,000.00 Rs.   50,000.00 Rs.   20,800.00  Rs.   62,400.00  Rs.1,33,200.00  Rs.3,46,800.00 2.30  

   

Page 77: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 76 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

Vermi­composting :   

If  farmers  realise  the  benefits  of  compost  and  vermicompost  in  particular,  the 

productivity  of  their  land  can  increase  manifold.  As  part  of  direct  livelihood  support,  the 

villagers  (mainly  land  less)  are  going  to  receive  cows,  buffaloes  and  small  ruminants.  These 

animals in turn will produce waste, which can be used to prepare Vermicompost. It  is planned 

that  a  vermicompost unit  by one  SHG would be  supported by  the project. The  SHG members, 

with  the  help  of  hired  manpower,  can  collect  animal‐dung.  They  will  process  this  dung  to 

prepare vermicompost and sell it to the farmers in the village or outside, as per demand.  

The  process  of  composting  crop  residues  using  earthworms  comprise  spreading  the 

agricultural wastes and cow dung in layers of 1.5 m wide and 0.9 m high beds of required length. 

Earthworms are introduced in between the layers @ 350 worms per m3 of bed volume. The beds 

are maintained at about 40 ‐ 50% moisture content and a temperature of 20 ‐ 30o C by sprinkling 

water over the beds. The earthworms being voracious eaters consume the biodegradable matter 

and give out a part of the matter as excreta or vermi‐castings. Vermi compost has more nutrient 

compare  to  other  manures  and  fertilizer;  so,  by  the  use  of  vermicompost  use  of  chemical 

fertilizer can be reduced. Vermicompost not only supply nutrient but also  improve quantity of 

hormones for plant growth, improves the soil structure leading to increase in water and nutrient 

holding capacities of soil.  

 

Components of a commercial unit:   1. Sheds:  

Sheds  can be made  by  the  use  of  concrete  pillars. While  designing  the  sheds  adequate 

room has to be left around the beds for easy movement of the labourers attending to the filling 

and harvesting the beds.  

2. Vermi­beds:  An ideal bed size is 75 cm ‐ 90 cm thick depending on the provision of filter for drainage 

of excess water. The whole bed area should be above ground. The bed should have a uniform 

height over  the entire width  to  the extent possible  to avoid  low production owing  to  low bed 

volumes. The proper bed width should not be more that 1.5 m to allow easy access to the centre 

of the bed.  

3. Land:  About 125 square meter of land will be required to set up a vermin compost production 

unit. It should have at least 2‐3 sheds each of about 180‐200 sq.ft. It should have a good watering 

arrangement and other equipments as required because moisture is essential for vermicompost 

production.  

Page 78: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 77 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

4. Seed Stock:  This is very important thing because worms multiply at the rate of 350 worms per m3 of 

bed space over a period of 6 month to a year.  

 Estimate for a vermicompost unit:   

• Requirement of nitrogen for 1 hectare sorghum fodder production=90 kg.  

•  1.6% N available in vermin compost.  

•  90 kg N fulfill by the use of 90/1.6*100= 5625 kg vermicompost (5.5 ton).  

•  Need  of  vermicompost  to  fulfill  the  requirement  of  nitrogen  for  15  hectare 

5.5*15 =82.5 (80 ton).  

• 45 kg phosphorus required for 1 hectare sorghum fodder production.  

• Requirement of phosphorus for 15 hectare fodder production 15*45=675 kg.  

• Supply of phosphorus through vermin compost 0.7/100*80000=560 kg.  

• Remaining requirement of phosphorus 675‐560=115 kg.  

• Remaining dose of phosphorus will be supplied by rock phosphate.  

• 8  cycles  of  45  days  each  will  be  required  for  80  ton  vermin  compost 

production.  

 

Table No. 45: Model Cost Estimation for A Vermi­Compost Unit 

 

S. No  

Particulars   Quantity  Rate (Rs.)  

Amount (Rs.) 

1   Wooden ballies (3 m long)   20   50   1000 2   Wooden (4 m long)   25   60   1500 3   Shade mats for covering the roof   125   25   3125 4   Binding wire for tying wooden ballies & mats   20 Kg   50   1000 5   Labour charges for erection of sheds   35MD   132   4620 6   Shovels, spades, crowbars, iron baskets,       2500 7   Weighing scale (100 kg capacity)   1   2000   2000 8   Cow dung   10 ton   800   8000 9   Worms @ 3 kg per ton   30 kg   80   2400 10   Formation of vermin bed with agro‐waste, cow 

dung and worms 20 bed   250   5000 

11   Miscellaneous        

  Total cost       31,250  

  Cost for 8 cycles       2,50,000  

Page 79: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 78 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

Cost­benefit Analysis:  Benefits  

1. Sale of vermin compost of 80 tones @ Rs.3750/‐per ton   80*3500     =  Rs. 3,00,000  

2. Sale of worms @ 5 kg per ton of compost and Rs. 60 per kg  400*60        =  Rs. 24,000  

Total                              Rs. 3,24,000  

Net benefit   Rs. 3,24,000 ­ Rs.2,50,000                           = Rs. 74,000  

  

Table No. 46: Per Unit Cost­benefit analyses for Electronic Goods Servicing 

 Per Unit Cost:  Rs. 25, 000.00 

 A. Capital expenditure: 

 1) Land and Building            :   Self Owned 

2) Plant and Machinery           

a) Welding Transformer        :  Rs.   5,000.00 

b) Digital Millimetre          :  Rs.   3,000.00 

c) Soldering pump etc.          :  Rs.  3,500.00 

3) Fixture and Furniture 

a) Table, Chair, Bench, Tools box, etc.      :    Rs.   1,500.00 

Total      :          Rs. 13,000.00 

B. Recurring Expenditure For The Month  

1) Raw materials 

a) Welding Rod etc.          :  Rs.   3,000.00 

2) Other Expenditures 

a) Advertisement, Electricity,  

Stationery, water etc.        :  Rs.    1,000.00 

Total      :  Rs.   4,000.00 

3) Staff 

a) Manager  :  Proprietor self        :   Nil 

b) Mechanic/Welder          :  Rs.   6,000.00 

c) Helper 1 No. @ Rs. 2,500/‐        :  Rs.    2,000.00 

Total        :  Rs.    8,000.00 

4) Total of recurring expenditure        :  Rs. 12,000.00 

Page 80: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 79 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

  

C. COST OF THE PROJECT 

1) Towards fixed Assets          :  Rs. 13,000.00 

2) Towards working capital        :  Rs. 12,000.00 

Total        :  Rs. 25,000.00 

 

 

Table No. 47: Per Unit Cost­benefit analyses for Carpentry 

 Per Unit Cost:  Rs. 25, 000.00 

  A. Capital expenditure:  

1) Land and Building            :   Self Owned 

2) Tools & Equipments           

a) 2 Sets of carpentry tools @ Rs. 4,500.00    :  Rs.     9,000.00 

b) Pre operative expenses like installation of power:  Rs.     1,500.00 

Total      :          Rs.   10,500.00 

B. Working Capital  

1) Raw materials 

a) Sawn wood 20cft @ 250.00        :  Rs.   5,000.00 

b) Nails, Fevicol, Plywood, Ply board, Nuts & Bolts, etc.:  Rs.   2,500.00 

Total      :  Rs.  7,500.00 

2) Staff 

a) Manager              :    Self     

b) Semi Skill @ Rs. 4,500.00        :  Rs.     4,500.00 

c) Helper @ Rs. 2,500.00        :  Rs.     2,500.00 

Total      :  Rs.     7,000.00 

3) Total of recurring expenditure        :  Rs.  14,500.00  C.  Cost of The Project 

1) Towards fixed Assets          :  Rs. 10,500.00 

2) Towards working capital        :  Rs. 14,500.00 

Grand Total      :  Rs. 25,000.00 

 

 

Page 81: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 80 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

Table No. 48: Per Unit Cost­benefit analyses for Petty Trade 

 Per Unit Cost:  Rs. 25, 000.00 

  A.   Furnishing of Shop 

 1) Furniture (Table, Rack, Almirah)    :  Rs.     5000.00 2) Skilled Laborer Charge (Carpenter)  :  Rs.     1000.00 3) Unskilled Laborer charge (Helper)    :  Rs.        600.00  

Sub Total­I    :  Rs.     6600.00 

B. Working Capital Per Month  

1) Food Items (Dal, Salt, Sugar, etc.)  :  Rs.      10000.00 2) Sweets, Gums, etc.  :  Rs         4000.00 3) Others (Shop, Tooth Brush, etc.)  :  Rs         4400.00                                                Sub­Total­II   :  Rs.   18400.00   

                          Grand Total {(I+II) = Rs. (6600 + 13400)} :  Rs.   25000.00  

 C.          Expected Production Per Month:  

  1) Food Items (Dal, Salt, Sugar, etc.)  :  Rs.      12200.00   2) Sweets, Gums, etc.  :  Rs         5290.00   3) Others (Shop, Tooth Brush, etc.)  :  Rs         5910.00 

                                                              Total                :  Rs.   23400.00  

D.         Net Profit per Month C‐B = Rs. (23400 – 18400)  :  Rs.     5000.00 

 E.          Expected expenditure for the 1st year 

Rs. 6600 + Rs. (18400x 12)  :  Rs. 227400.00  

F.          Expected Production for the 1st Year Rs. 23400 X 12  :  Rs. 280800.00 

G.          Net Profit For The 1st Year F– E = Rs. (Rs. 280800 – 227400)  :  Rs.   53400.00 

 H.          Net Profit from 2nd Year Onwards  :  Rs.   60000.00      

Page 82: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 81 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

Table No. 49: Per Unit Cost­benefit analyses for Tailoring 

 Per Unit Cost:  Rs. 25, 000.00 

 1  CAPITAL EXPENDITURE:           

  Land and Building             

  Plant and Machinery             

  a)  Foot Sewing machine  :  Rs.  8,500.00 

  b)  Hand Sewing machine  :  Rs.  5,500.00 

  c)  Embroidery  :  Rs.  10,000.00 

    Total  :  Rs.  24,000.00 

                 

2  FIXTURE & FURNITURE         

  a)  Table, Chair, Bench, etc.  :    Self Owned 

  b)  Electric Iron  :  Rs.  700.00 

  c)  Measuring tape, Scissor  :  Rs.  300.00 

    Total  :  Rs.  1,000.00 

                 CAPITAL EXPENDITURE + FIXTURE & FURNITURE 

=    TOTAL EXPECTED EXPENDITURE  :  Rs.  25,000.00 

                 EXPECTED PROJECT INCOME           

Daily Income @ Rs.150.00/Finished clothes  :  Rs.  450.00 

Monthly Income        :  Rs.  11,250.00 

Total Income for 1 year        :  Rs.  135,000.00 

                 

EXPECTED PROFIT (Within 1 Year)         

NET INCOME ­ TOTAL EXPENSES  = PROFIT       

  Rs.  135,000.00  ‐  Rs.  25,000.00  =    110,000.00  

  

Page 83: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 82 

IWMP: Lunglei – III Watershed Project                                                                PIA: BDO, Lungsen 

 Chapter 8:  Project Phasing and Year­Wise Action Plan 

 The project will be implemented in a phased manner and will be completed in four to seven 

years  depending  on  the  need.  All  institutional  structures  viz.  Watershed  Development  Teams 

(WDTs), Watershed Committees (WCs) User Groups (UGs) etc. will be established in first year itself 

and staff will be recruited and trained. Entry Point Activities (EPA) will be completed within the 

first year and watershed works will also be taken up from the first year onwards. Skill up gradation 

trainings and capacity building of Watershed Development Teams (WDTs), Watershed Committees 

(WCs)  Self  Help  Groups,  Individuals  and User  Groups will  continue  over  the  project  period  and 

placement  facilities  services will  be  completed within  the project  period.  Coverage of  families  is 

phased  over  a  period  of  four  years.  Consolidation  of  project  components  and  interventions will 

begin during the sixth and seventh year. Table No. 54 and Table No. 55 below depicts the phasing 

strategy and year wise action plan for Community Institution building and project interventions.  

The classification of activities in yearly/annual phases must not be understood in a rigid 

manner.  Many  of  the  later  activities may  even  start  during  the  first  year  or  third  year  itself. 

Phasing of activities has an internal logic and integrity that  flow through the entire action plan 

which  depended  on  a  host  of  factors  such  as  the  prevailing  initial  conditions,  needs  and 

possibilities  in  each  village,  response  of  the  community  etc.  Flexibility  is  built  into  the  action 

plan  reflect  the  distinguishing  feature  of  the  Common  Guidelines. Project phasing strategy and

Year-wise Action Plan is tabulated as below:

Page 84: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 83 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

 TABLE NO. 50: PROJECT PHASING STRATEGY 

 (Financial Figures are in Rupees Lakhs) 

Sl. No 

Component 

1st Year  2nd Year  3rd Year  4th Year  5th Year  6th Year  7th Year  Total 

Phy (No) 

Fin (Rs) 

Phy (No) 

Fin (Rs) 

Phy (No) 

Fin (Rs) 

Phy (No) 

Fin (Rs) 

Phy (No) 

Fin (Rs) 

Phy (No) 

Fin (Rs) 

Phy (No) 

Fin (Rs) 

Phy (No) 

Fin (Rs) 

1 Entry Point Activities (4%)  16  30.00  ‐  ‐  ‐  ‐  ‐  ‐  ‐  ‐  ‐  ‐  ‐  ‐  16  30.00 

2 Institution & Capacity Building (5%) 

‐  12.00  ‐  10.00  ‐  8.00  ‐  7.50  ‐  ‐  ‐  ‐  ‐  ‐  ­  37.50 

Productivity Enhancement (13%) 

10  25.00  10  25.00  10  25.00  9  22.50  ‐  ‐  ‐  ‐  ‐  ‐  39  97.50 

4 Livelihoods for Asset less (10%) 

‐  ‐  15  10.50  20  23.00  20  23.00  9  13.50  2  5.00  ‐  ‐  66  75.00 

Natural Resource Management (50%) 

1818  48.805  1871  100.752  1872  101.172  1837  76.386  1778  47.885  ‐  ‐  ‐  ‐  9176  375.00 

6 Consolidation phase (5%)  ‐  ‐  ‐  ‐  ‐  ‐  ‐  ‐  ‐  15.00  ‐  15.00  ‐  7.50  ­  37.50 

7 Administration (10%)  ‐  12..50  ‐  12.50  ‐  12.50  ‐  11.00  ‐  10.00  ‐  9.00  ‐  7.50  ­  75.00 

TOTAL  1844  128.305  1896  158.752  1902  169.672  1866  140.386  1787  86.385  2  29.00  ­  15.00  9297  727.50 

 

 

Page 85: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 84 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

TABLE NO. 51: YEAR WISE ACTION PLAN  

A). COMPONENT: ENTRY POINT ACTIVITIES  

Sl. No 

Sub‐Component 

1st Year  2nd Year  3rd Year  4th Year  5th Year  6th Year  7th Year  Total 

Phy (No) 

Fin (Rs) Phy (No) 

Fin (Rs Lakh) 

Phy (No) 

Fin (Rs) Phy (No) 

Fin (Rs) 

Phy (No) 

Fin (Rs) 

Phy (No) 

Fin (Rs) 

Phy (No) 

Fin (Rs) 

Phy (No) 

Fin (Rs) 

1  Water Harvest Tank  3  9                          3  9 

2  Urinal Shed  6  1.50                          6  1.50 

3  Waiting Shed  3  4.50                          3  4.50 

4  Agri Link Road  4km  15.0                          4km  15.0 

TOTAL  16  30.00                          16  30.00 

  B). COMPONENT: INSTITUTION AND CAPACITY BUILDING  

Sl. No 

Sub‐Component 

1st Year  2nd Year  3rd Year  4th Year  5th Year  6th Year  7th Year  Total 

Phy (No) 

Fin (Rs) Phy (No) 

Fin (Rs Lakh) 

Phy (No) 

Fin (Rs) Phy (No) 

Fin (Rs) 

Phy (No) 

Fin (Rs) 

Phy (No) 

Fin (Rs) 

Phy (No) 

Fin (Rs) 

Phy (No) 

Fin (Rs) 

1 Institution and Capacity Building 

  12.00    10.00    8.00    7.50                37.50 

TOTAL    12.00    10.00    8.00    7.50                37.50 

   

Page 86: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 85 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

  C). COMPONENT: PRODUCTIVITY ENHANCEMENT/FARM PRODUCTION SYSTEM 

(All financial figures are in Rs lakhs) 

Sl. No 

Sub‐Component 

1st Year  2nd Year  3rd Year  4th Year  5th Year  6th Year  7th Year  Total 

Phy (No) 

Fin (Rs) Phy (No) 

Fin (Rs) Phy (No) 

Fin (Rs) Phy (No)  Fin (Rs) 

Phy (No)

Fin (Rs) Phy (No) 

Fin (Rs)  Phy (No) 

Fin (Rs) Phy (No) 

Fin (Rs) 

1 Rubber Cultivation 

5  12.50  3  7.50  3  7.50  1  2.50              12  30.00 

2 Passion Fruit Cultivation 

    1  2.50  2  5.00  5  12.50              8  20.00 

3 Arecanut Cultivation 

5  12.50  3  7.50  2  5.00                  10  25.00 

4 Bamboo Cultivation 

    2  5.00  3  7.50  2  5.00              7  17.50 

5 Greenhouse Farming 

    1  2.50      1  2.50              2  5.00 

TOTAL  10  25.00  10  25.00  10  25.00  9  22.50              39  97.50 

  

Page 87: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 86 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

  

D). COMPONENT: LIVELIHOOD FOR ASSETLESS/LIVELIHOOD MANAGEMENT SYSTEM  

(All financial figures are in Rs lakhs) 

Sl. No 

Sub‐Component 

1st Year  2nd Year  3rd Year  4th Year  5th Year  6th Year  7th Year  Total 

Phy (No) 

Fin (Rs) 

Phy (No) 

Fin (Rs) 

Phy (No) 

Fin (Rs) 

Phy (No) 

Fin (Rs) Phy (No) 

Fin (Rs) 

Phy (No) 

Fin (Rs)  Phy (No) 

Fin (Rs) 

Phy (No) 

Fin (Rs) 

1  Dairy Farming          1  2.50  1  2.50              2  5.00

2  Poultry Farming (Layer)                  1  2.50  1  2.50      2  5.00

3  Poultry Farming (Broiler)          1  2.50  1  2.50              2  5.00

4  Hill Cattle Rearing              1  2.50  1  2.50          2  5.00 

5  Goat Rearing          2  5.00  2  5.00  2  5.00          6  15.00 

6  Pigrearing      2  5.00  2  5.00  2  5.00              6  15.00 

7  Aquaculture          1  2.50  1  2.50  1  2.50  1  2.50      4  10.00 

8  Vermicomposting      1  2.50  1  2.50                  2  5.00 

9  Electronic Goods Servicing      3  0.75  3  0.75 3  0.75 1  0.25          10  2.50 

10  Carpentry      3  0.75 3  0.75 3  0.75 1  0.25         10  2.50 

11  Petty Trade      3  0.75 3  0.75 3  0.75 1  0.25         10  2.50 

12  Tailoring      3  0.75 3  0.75 3  0.75 1  0.25         10  2.50 

TOTAL  ­  ­  15  10.50  20  23.00  20  23.00  9  13.50  2  5.00  ­  ­  66  75.00 

  

Page 88: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 87 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

  

E). COMPONENT: NATURAL RESOURCES MANAGEMENT    

Sl. No 

Sub‐Component 

1st Year  2nd Year  3rd Year  4th Year  5th Year  6th Year  7th Year  Total 

Phy (No) 

Fin (Rs) 

Phy (No) 

Fin (Rs Lakh) 

Phy (No) 

Fin (Rs) Phy (No) 

Fin (Rs) 

Phy (No) 

Fin (Rs) 

Phy (No) 

Fin (Rs) 

Phy (No) 

Fin (Rs) 

Phy (No) 

Fin (Rs) 

1  Stone Bund  600  13.13  600  13.13  600  13.13  600  13.13  600  13.13          3000  65.6382 

2 Staggered Contour Trench 

1118  24.505  1118  24.505  1118  24.505  1118  24.505  1118  24.505          5590  122.52156 

3 Bordered Contour Trench 

60  10.25  60  10.25  60  10.25  60  10.25  60  10.25          300  51.2505 

4  Afforestation      40  14.297  40  14.297  20  7.15              100  35.74219 

5  Check Dam Type A      2  13.61                      2  13.61326 

6  Check Dam Type B          2  10.26  3  15.39              5  25.65 

7  Check Dam Type C      2  7.54  3  11.31  1  3.77              6  22.62 

8  Earthen Bund  40  0.92  40  0.92  40  0.92  30  0.691              150  3.4458 

9  Agri Link Road      4  15.0  4  15.0                  8  30.00 

10  Farm Pond      5  1.5  5  1.5  5  1.5              15  4.51855 

TOTAL  1818  48.805  1871  100.752  1872  101.172  1837  76.386  1778  47.885          9176  375.00 

  

Page 89: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 88 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

Chapter 9:  Consolidation and Withdrawal Mechanism  

In  this  phase  the  resources  augmented  and  economic  plans  developed  in  the  earlier 

phases  will  be  made  the  foundation  to  create  new  nature‐based,  sustainable  livelihoods  and 

raise  productivity  levels.  The  main  objectives  under  this  phase  will  be  to  consolidate  and 

complete  various works,  building  the  capacity  of  the  community  based organizations  to  carry 

out  the new agenda  items during post project period, sustainable management of  (developed) 

natural resources and up‐scaling of successful experiences regarding farm production systems / 

off‐farm  livelihoods. List of various activities  to be performed during Consolidation period are 

given below: 

A) Consolidation of various works: 

a). Preparation of project completion report with details about status of each 

      Intervention; 

b). Documentation of successful experiences and lessons learnt for future use. 

B) Management of developed natural resources 

a). Improving the sustainability of various interventions under the project; 

b). Formal allocation of users right over Common Property Resources (CPRs); 

c). Collection of user charges for CPRs; 

d). Repair, maintenance and protection of CPRs; 

e). Sustainable utilization of developed natural resources; 

f). Involvement of Village Councils/corresponding institutions (as a governance 

                                body) in addressing the above aspects. 

C) Intensification of farm production systems/off‐farm livelihoods 

a). Up scaling of successful experiences related to above aspects through  

revolving fund under the project as well as credit and technical support from  

external institutions; 

b). Promotion of agro‐processing, marketing arrangements of produce and 

      similar off – farm and informal sector enterprises. 

c). Farmers may also be encouraged to develop non pesticidal management, 

      low cost organic inputs, seed farms and links with wider markets to fetch  

      competitive price. 

D) Project management related aspects 

a). Participatory planning, implementation and monitoring of activities to be 

                                  carried out during consolidation phase; 

b). Terminal evaluation of project as per the expected outcomes. 

Page 90: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 89 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

Self Help Group Federation (SHGF): 

Self Help Group Federations (SHGF) will be formed in each village to support economic 

activities  at  scale.  These would  further  strengthen  and  activate  the  linkages  established with 

external  resource  agencies  for  knowledge,  credit,  input  procurement,  sale  of  local  produce, 

carrying  on  processing  activities  to  the  point  of  exports.  In  these  activities,  bankability  of 

activities will be attempted. The executive committee will have 10‐15 members with sufficient 

women  participation.  The  ex‐officio  secretary  of  the  executive  committee  will  be  will  be 

nominated by the Block Development Officer. In the non‐economic sphere activities will raising 

various social  issues of non  inclusion of  the poor, gender participation, establishing norms  for 

social accountability, and conflict resolution within and across SHGs.  

  Viable business activities will be identified and linked with a wider market to provide the 

poor  with  sustainable  opportunities  for  increasing  their  household  incomes.  The  project  will 

also  facilitate  SHGs  to  federate  into  higher‐level  organizations  (namely  producer 

companies/cooperatives  etc.)  to  access  higher  level  services  by  leveraging  on  economies  of 

scale.  A  federation  will  start  with mature  SHGs  and  in  a  size  that  is  economically  viable.  An 

established  federation  would  later  invite  other  SHG  members  from  the  area  to  join  as  the 

groups’ capacities and interests grow. Such livelihoods federations will legally take the form of 

either  Producer  Companies  or  Cooperative  Societies  where  the  individual  SHGs  engaged  in 

specific  livelihoods  will  become  shareholders  or  cooperative  members  under  the  livelihood 

federation.  The  project  will  provide  an  initial  grant  in  the  form  of  working  capital  to  each 

federation  upon  approval  of  its  business  plan.  The  federation will  subsequently  leverage  the 

grant money to raise additional funding from commercial banks on commercial terms.  

Linkages:  

  These organizations may seek services of technical resource organizations/persons 

for business interventions. The project will develop package of practices that is first demonstrated 

in a local agro‐ecological zone and help for tie ups with private sector especially for marketing; for 

example, with food retail chains.  

 

 

 

 

Page 91: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 90 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

EXIT PROTOCOL:  

Since the beginning of this project the community members are being facilitated to adopt 

operational  strategies  in  capacity  building.  In  the  last  year  of  the  project,  the  Watershed 

Committee/Watershed  Association  will  be  converted  in  to  a  self‐sufficient,  independent 

institution which will be able to maintain post project activities on its own. The convergence and 

harmonization  of  resources  of  different  flagship  scheme  and  programmes  will  be  channelled 

through  this  project.  At  the  end  of  the  project  (after  saturation)  the  concerned  PIA  /  Block 

Development  Officer  shall  hand  over  the  assets  created  during  the  project  period, 

responsibilities  and  post  project  management  etc.  to  the  Watershed  Committee/Association 

through a memorandum of agreement depicted below:‐ 

   The Memorandum of Agreement (MOA) between Watershed Committee (WC) 

& Block Development Officer (PIA)   

This  Memorandum  of  Agreement  is  executed  on  this___________  day  of  _________  month 

____________year  &  between  Watershed  Committee,_________________________________  Village, 

represented by its President herein after called and referred to as the Committee and the PIA . 

IN FAVOUR OF 

PIA under Lunglei III IWMP Lunglei district, handing over the post management responsibilities 

&  sustainability  to  the  President  &  the  authorized  person,  on  behalf  of WC  to  undertake  the 

responsibilities  of  ongoing  development within  the  project  area  as  per  terms  and  conditions. 

Now this document witnesses as follows: 

  

The terms and conditions in respect of Memorandum of Agreement between Watershed Association and PIA 

  1.   An exhaustive list of assets (structures, amount in cash and in the bank accounts) created 

(under EPA, NRM, FPS & LSS) in all the matured and saturated watersheds under IWMP 

should be prepared by the respective Watershed Committees and handed over to the PIA 

through WDT,  retaining  one  copy  of  the  same with  them  for  post  project maintenance 

and regular audit at the watershed level by the Chartered Account. 

2.   The amount lying as on closing date of the project, Watershed Project account should be 

audited and transferred to the Watershed Development Fund (WDF) Account in the Bank. 

 

Page 92: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 91 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

3.   For  sustainability  of  the  programme  beyond  the  project  period,  the  Watershed  (WC) 

should  believe  in  rotational  leadership  and  is  authorized  to  operate  only  one  Bank 

Account i.e. WDF Account. 

4.   Yearly auditing of the accounts by Competent Authority is mandatory and to be adhered 

strictly. 

5.   The  office  bearers  of Watershed  Committee  (WC)  shall  not  involve  in  any  political  or 

religious activities. 

6.   The office bearers of Watershed Association and Watershed Committee shall  involve all 

the communities irrespective of caste, creed and religious. 

7.   In case of any embezzlement of fund, the Administrative system shall proceed according 

to existing Rules & Laws. 

8.   The appropriate officials shall have the liberty to inspect and carry out checks on works 

under  progress,  completed works,  documents,  reports,  vouchers,  accounts,  Cash  Book, 

physical  verification  of  assets  created  under  IWMP  at  any  time  and  can  take  any 

administrative action against the defaulter/s. 

9.   The community assets shall be divided into three categories : (a) Those which are to be 

used by the same families on a regular basis (e.g. water tanks, field drains etc.) ; (b) Those 

which annually auctioned (e.g. fishing right, biomass from the common land etc.) and (c) 

Common assets like irrigation sources, WHS, canals, watershed office, tanks/ponds etc. 

10.   Separate list of beneficiaries shall be prepared for assets under category (a), (b) and (c) 

as applicable. 

11.   The  Watershed  Association  shall  have  the  right  to  decide  the  service  charges  to  be 

collected  from  the beneficiaries  associated with  the  first  category  (a) of  structures  and 

also  collect  the  amount  through;  auction  regarding  use  of  assets  under  second  (b) 

category  of  structures  and  shall  be  deposited under  the Watershed Development  Fund 

account. 

12.   The  WDF  account  will  primarily  run  in  the  nature  of  revolving  Fund.  No  individual 

beneficiary should be granted any sorts of grant, financial assistance in any form. 

13.   Only  the SHG/UG  formed during  the  implementation phase  shall have  the eligibility  to 

take loans. For sustainability of the programme beyond the project period, all groups i.e. 

Self Help Groups  and User Groups  should  be  converted  into  income  generating  groups 

and should have rotational leadership. 

14.   New groups (SHG/UG) may be formed during post‐project phase. These groups may also 

be entitled to have such loan subject to the fulfilment of maturity criterion. 

 

Page 93: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 92 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

15.   The Watershed Committee  (WC) may engage one Para‐worker on regular or part basis 

depending upon the need and financial resources available (for maintenance of accounts, 

records, registers etc.) 

16.   The existing rate of interest shall be continued uniformly for all the lending groups and 

repayment  of  loans  should  be  made  within  one  year  with  maximum  12  (twelve) 

instalments. 

17.   The WC may collect the financial assistance from any other sources to augment the WDF 

fund. All donations, interests, fines, fees etc. shall be deposited in the WDF account. 

18.   All  the  group  representatives  (at  lease  one  from  each  group)  shall  be  ensured  in  the 

Watershed Committee. 

19.   The  decisions  approved  and  resolved  in  the  General  Body  Meeting  of  Watershed 

Association, will only be executed / implemented by the Watershed Committee. 

20.   Any  change  in Watershed  Committee  shall  be  made  once  it  is  resolved  in  the  Annual 

General Meeting (AGM) of Watershed Association. 

21.   Bi‐monthly Meeting of Watershed Association is mandatory. 

22.   The  WDF  shall  have  interest  bearing  account  in  any  Nationalized  Bank  /Corporative 

Bank. 

23.   The  WDF  shall  be  jointly  operated  by  the  President  and  the  Secretary  and/or 

unauthorized  person  duly  resolved  in  WA.  During  the  post  project  period,  the  Block 

Development Officer  i.e.  the WDT Leader, will also be a part of Bank Account of WA,  to 

assure the proper utilization of WDF and no depletion of WDF may take place. 

24.   Any  withdrawal  of  money  from  WDF  account  shall  be  resolved  in  WC  meeting  with 

proper records and purpose. 

25.   The SHG shall take loan maximum up to double the amount of their common fund and the 

UG shall be restricted to the equal amount of their savings as usual. However, maximum 

amount to be given to one SHG/UG at a time shall not exceed Rs.25000/‐ (Rupees twenty‐

five thousand) only. 

26.   The peer group pressure shall be kept functional for successful recovery of loan. 

 27.   50% of interest earned by way of lending shall be retained by the respective groups 

 (SHGs / UGs) and rest 50% will go to WDF. 

28.   The Watershed association are also at their liberty to start new profit making ventures by 

utilizing the corpus fund (WDF) as security deposit and the profit earned should go to the 

WDF. 

 

Page 94: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 93 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

29.   The details  of  account  of  income and  expenditure  shall  be  presented  in  the meeting of 

Watershed Association and put it on the notice board of WA and Panchayat also on half 

yearly basis. 

30.   In  the  event  that  WA  becomes  defunct,  the  community  assets  and  WDF  fund  will  be 

transferred to the Village Council/ Government. 

 

In  witness  thereby,  the  Memorandum  of  Agreement  is  executed  on  the__________ 

day____________ month And _____________year. 

 

 

 Handing over          Taking over 

 

 

 

 

Project Implementing Agency       1) ____________________________ President 

 

 

2) ______________________________Authorized 

 Person of Watershed Association 

 

 

DEPONENTS 

 

Witnessed by, 

 

1) _____________________________________________ 

 

 

2) _____________________________________________ 

 

    

Page 95: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 94 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

 Chapter 10:  Expected Outcomes 

 8.1 Expected Outcomes   8.1.1 Drinking water  

As a result of the watershed activities, it is expected that the quantity and quality of 

drinking water would improve as given in the table below.  

 

 Table No. 50: Status of drinking water 

 

Sl.No Name of Village 

Availability of drinking water   (No. of month in a year) 

Quality of drinking water 

Pre­ Project Expected post 

project Pre­ Project 

Expected post project 

1  Phairuangkai Through every village has access to drinking water, existing sources of water are inadequate due to increasing  population 

Unexplored natural sources of water will be tapped and greater thrust on rain water harvesting will improved the condition significant 

Satisfactory. However, external pollutants tend to make the water turbid especially during the monsoons 

Condition will improve with required intervention through the programme 

2  Rotlang ‘W’ 

3  Runtung 

   8.1.2. Migration  

 On account of  agriculture  and animal husbandry providing only part  time employment 

for  some  part  of  the  year,  the  people  migrate  for  a  better  half  of  the  year  for  wage  labour. 

Employment opportunities in the local area as mentioned above will ensure lessening seasonal 

migration from the area.  

 

Table No.51:   Migration from the Project Area  

Sl.No  Name of Village 

No.of persons migrating 

No. of days per year of migrating 

Major reasons for migrating 

Expected reduction in No. of persons migrating 

1  Phairuangkai  64  Data not available 

In search of better livelihood 

13 2  Rotlang ‘W’  28  6 3  Runtung  11  2 

Page 96: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 95 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

 8.1.3 Crops  

Agriculture primarily depends upon water; but this is what is lacking. All this can change 

with  the  integrated  land  and  water  management  during  the  watershed  project.  The  planned 

earthen  bunds would  help  percolate  sweet water  underground,  and  preserve moisture  in  the 

soil. This will help in additional area coming under cultivation and increasing productivity too. 

The  farmers  can  then  take more  than one  season of  crops. Different  varieties  of  crops  can be 

taken.  

   

Table No. 52:  Major crops grown and their productivity in the Project Areas   

Sl.No  Name of Crop  Current Status  Expected post Project status 

    Area (Ha)  Productivity (Kg/Ha)  Area (Ha)  Productivity 

(Kg/Ha) 1  Rice  20  1000  90  1500 

2  Mize  10  1000  70  1200 

3  Sugarcane  10  1000  50  1200 

4  Oil Seed  5  1000  30  1000    8.1.4 Vegetative cover  

There  is negligible  area under  tree  cover. The village has  a  forest  area of 524ha which 

consists of only Juliflora Prosopis (ganda babool). Trees like Neem and _Alianthus_are seen just 

here and there, not concentrated in any area.  

It is planned that 15 ha land to be covered under new plantation.  

 

8.1.5 Livestock  

The  interventions  like  provision  of  good  quality  cows  and  buffaloes  and  other  such 

related activities would spur up the dairy development in the village. It is expected that the post 

project period would see a substantial increase in livestock population and yield from them.  

 

8.1.6Linkages 

The direct livelihood activities need good forward and backward support. Without such 

support  system  the  activities  may  fail  to  deliver  the  desired  results.  These linkages would 

involve credit, machinery, input supply, marketing, etc. 

Page 97: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 96 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

 8.1.7 Employment   

Employment has always been a problem in the Project Area. The principal occupations of 

the people are shifting cultivation, animal husbandry and casual labour work. However, rain fall 

being very  limited and erratic, agriculture suffers,  i.e.  at best  they can  take only a  single crop, 

which keeps them partially engaged for about 4 months. Lack of fodder makes animal husbandry 

very difficult too. So, animal husbandry does not keep them engaged full time. Thus the people 

mainly depend upon casual labour, either in the village itself or outside it. The project plans for 

creation  of  both  wage  employment  and  self  employment  opportunities.  Wage  employment 

would be created by engaging people in watershed physical works like construction of earthen 

bunds, farm bunds, village pond, plantation, etc. Self employment would be created by providing 

the people with cash support  in  the  form of direct  livelihood activities  like agriculture, animal 

husbandry and enterprise development.  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 98: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 97 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

 

Table No. 53: Employment Generation  

Sl.No  Name of Village 

Wage employment  Self employment 

No. of mandays  No. of beneficiary 

    SC  ST  Others Women  Total  SC ST  Others Women  Total  SC  ST Others  Woman  Total 

1  Phairuangkai    223698    17208  240905    260    20  280    15   10  25 

2  Rotlang ‘W’    98943    8604  107547    115    10  125    15   5  10 

3  Runtung    30113    4302  34415    35    5  40    5    5  10 

    8.1.8 Ground water table   

Rainfall has been scanty but demand for ground water has been increasing all the time. The ground water table thus has depleted over 

the years. Presently it stands at 28 m. Proper water harvesting structures and percolation tanks would go a long way in increasing water table 

depth from 28 m in the pre‐project level to 25 m in the post project period.  

 

 

 

 

Page 99: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 98 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

 

Table No. 54: Ground Water Table depth in the Project Area.    

Sl.No  Name of  Village  Source  Pre­Project level  Expected Post project level 

1  2  3  4  5 

1  Phairuangkai 

Surface Water, Rain Water Harvesting 

Depletion  during  the  dry  season  and  also due  to  extensive  exploitation  of  ground water 

Ground water will be recharged through a forestation and recharge pits to increase soil moisture and to maintain the water 

table level 

2  Rotlang ‘W’ 

3  Runtung 

 

Page 100: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 99 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

CHAPTER 11:  LOGICAL FRAMEWORK ANALYSIS  

Logical Framework Analysis:  

Components  Activities  Outputs  Effect  Impact 1  2  3  4  5 

 Village Institution Formation 

• Formation of Watershed Committees • Formation of Self Help Groups •  Formation of User Groups 

• One Watershed Committee for each village 

• Number of Self Help Groups and User Groups depending on the coverage of particular intervention 

• Project can be implemented in a democratic and participatory manner ensuring equity 

• Unity and prosperity in the village management. 

• People participation • Positive perception of the programme 

 

 Strengthening Village Institutions   

• Organise training and awareness programmes for village institutions 

• Capacity building workshops and exposure visits of Watershed Committees, SHGs and User Groups 

• Facilitating and monitoring the functioning of WCs, SHGs and UGs 

• Strengthen linkages between WCs, SHGs and UGs 

• Gender sensitization of WCs , UGs and SHGs to increase inclusiveness of decision making 

• Sensitize  village communities to involve youth in development 

• Awareness Camps to be organised 

• Training and exposure visits of WCs, SHGs and UGs to be held 

• Capacity building workshops to be organised 

• Federation of SHGs and UGs to be formed 

• Quality of   management of resources to be improved 

• Quality of     distribution of benefits between people to be improved 

• Increased awareness of women about village resources 

•  Women Participation enhanced 

• Participation of youth in development increased 

 Fund Management   • Improve management and utilization 

of funds by UGs, SHGs and WCs • Prepare communities to explore other sources of income 

• operating Bank Accounts and managing funds on their own

• Federation of SHGs and UGs creating credit linkages with banks  

• Purpose frequency and volume and use of the fund enhanced 

• Volume of funds generated for UGs and WCs  from other sources  

      Increased  

Page 101: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 100 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

 Ecological Restoration 

• Protection treatment and regeneration of common and private lands 

• Protection treatment and regeneration of forest lands 

• Plantation of fruits and forest species 

• Identification of non‐timber forest produce based income generation activities 

 

• Common and private lands to be brought under new plantations and agro‐horti forestry 

• Forest lands to be brought under new plantation and protection 

• Income generation intervention promoted 

• Accessibility to common and forest land increased with removal  of encroachments and resolution of conflicts 

• Fodder availability from common and private lands increased 

 • Better ecological balance 

• Increase in the proportion of households having more security of fodder 

 Rainfed Area Development 

• Treatment of land through improved soil and moisture conservation practices 

• Promotion of good agricultural practices 

• Promotion of organic farming practices 

• Identification of agri‐produce based income generating practices like processing 

• Promotion of better irrigation practices like drip irrigation 

 • Land to  be brought under improved soil moisture conservation practices 

• Good agricultural practices to be promoted 

• Organic farming to be promoted 

• Agriculture based livelihood income generation activities too be promoted 

• Water harvesting structures to be constructed 

• Training, exposure visits and meetings to be organized for communities, village volunteers and staff  

• Improved productivity of treated land 

• Increased availability of water in wells  

• Farmers adopt organic farming practices 

• Increase availability of water for 9 to 12 months  

• Increased availability of water for livestock 

• Availability of irrigation water established  

• Farmers take two crops in a year 

 

 • Increase in proportion of households having more security of food 

•  Increase in contribution of agricultural income to the household income 

 

Page 102: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 101 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

 Women’s Socio­political and economic empowerment 

 • Formation & Strengthening of women’s SHG groups 

• Capacity building of womenfolk • Capacity building of SHG leaders and accountants 

• Linking SHGs with external financial institutions   

   

 • Women’s SHG groups to be formed 

•  Federation of Women’s SHGs to be formed 

• Trainings to be conducted for preparation of woollen products from sheep and goats   

   

 • Enhanced capacities of leaders of women's group in taking initiatives to solve problems at different levels. 

• Improved access to credit for livelihood purposes. 

• Increased household income   

   

 • Position of women in household, community, society (politically, socially and economically) as perceived by women and community at large 

• Performance enhancement of SHGs in terms of participation, decision‐making, leadership and fund management.  

• Equality & Equity in gender relations at home (decision making, expenditure, children’s education, health)    

Page 103: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 102 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

CHAPTER 12:  MONITORING AND EVALUATION 

 

  As enshrined in the project core values and based on the non‐negotiable principles of 

the project , monitoring and evaluation of the project will adhere to the principles of transparency, 

participation, and accountability. The degree of success of a project depends on monitoring to a 

great  extent.  Therefore,  a  comprehensive monitoring  system will  be  designed  for  the  project. 

Monitoring Committees will be created at each level of administration namely Village, Block and 

District and their working modalities spelt out.  

  There will be a Village Monitoring Committee at each village to monitor the working of 

SHGs and other stakeholders. The Monitoring committee members will be elected by the Gram 

Sabha and will be chaired by a person who is not the member of SHG. This Committee will verify 

the working of every Self Help Group every three months and submit their report to the PIA. 

   Apart from this, social audit will be conducted every six months to review the working of 

Self Help Groups. The Gram Sabha will  form Social audit  forum who will conduct all  the social 

audit processes. The success of the Forum depends upon the open and fearless participation of 

all  people,  particularly  potential  beneficiaries  of  the  project.  Effective  public  participation 

requires adequate publicity about the Forum as well as informed public opinion. It will require 

that people have prior access to information from the Chairman of the Watershed Committee 

 The date, time, agenda, importance and sanctity of the Forum will be widely publicized so as to 

ensure  maximum  participation.  All  the  relevant  documents,  including  complete  files  of  the 

works or copies of them will be made available for inspection. The checklist below will help in 

reviewing whether the norms and provisions of the project are being observed. 

  a) Whether the process of formation of SHG was conducted in a transparent manner: 

  b) Whether there is a manipulation of already sanctioned development works  

  c) Whether there is a diversion or under‐execution of development works 

  d) Whether there is problem in credit flows 

  e) Whether SHGs really took up the work for which they received 

  f) Whether the work done are commensurate with the sanctioned amount.  

All  the  proposals  and  query  raised  in  the  Social  audit  will  be  submitted  to  the  for  further 

necessary action. 

  Similarly, monitoring committees will be formed at the Block and District levels. 

 

 

 

Page 104: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 103 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

Evaluation: 

    The objective of IWMP is to improve capacity and opportunities for the rural poor to 

achieve  sustainable  livelihoods).  Investments made  are  expected  to  generate  employment  and 

purchasing  power,  raise  economic  productivity,  promote  women’s  participation  in  the 

workforce,  strengthen  the  rural  infrastructure  through  the  creation  of  durable  assets  and 

contribute  to  the  regeneration  of  natural  resources.  Thus,  outlays  for  the  project  have  to  be 

transformed into outcomes. Regular evaluations and sample surveys of specific works should be 

conducted  to assess outcomes. District‐wise studies  should be  conducted or  commissioned by 

the State level agency.. Project‐wise evaluation studies should be conducted or commissioned by 

the District Project Manager. 

    The District Unit should develop its own evaluation system in collaboration with 

research  institutions  of  repute  and  review  evaluations  conducted  by  other  agencies.  The 

evaluation studies should also throw light on particular innovations in planning, monitoring or 

implementation.  

Management Information System:  

    The State/District Unit will adopt Creation of a Management Information System 

(MIS) with a database on all  the activities  taken up under  the  project,  resource  requirements, 

registered SHGs, funds received and expended at different levels, and all other related matters. 

The  full  possible  applications  of  IT  to  the  implementation  of  the  project will  be  explored  and 

appropriate modules developed into a comprehensive system to be continuously up‐graded as 

required. IT experts will be engaged to deal with this MIS and  through this all the information 

pertaining to the implementation of the project will be given to higher authorities every month 

on‐line.   

  The introduction of MIS will facilitate – 

   (a) The efficiency and transparency of operational processes  

  (b) Digitization of Registration and other important documents; 

  (c) Financial Management Systems: The fund transfer from the Ministry, States,  Districts 

and PIA may be entered on‐line. 

  (d) Communication and access to information; 

  (e) Grievance‐redressal systems; etc. 

   

 

 

 

 

Page 105: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 104 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

Chapter 13:  Mapping  

 

 

Page 106: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 105 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

 

 

 

 

Page 107: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 106 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

       

Page 108: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 107 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

 

Page 109: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 108 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

 

Page 110: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 109 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

Page 111: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 110 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

Page 112: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 111 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

Page 113: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 112 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

Page 114: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 113 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

       

Page 115: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 114 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

 

Page 116: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 115 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

Page 117: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 116 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

Page 118: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 117 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

Page 119: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 118 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

Page 120: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 119 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

Page 121: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 120 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

      

Page 122: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 121 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

  

Page 123: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 122 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

 

Page 124: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 123 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

Page 125: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 124 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

Page 126: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 125 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

Page 127: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 126 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

Page 128: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 127 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

    

Page 129: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 128 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

 

Page 130: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 129 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

Page 131: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 130 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

Page 132: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 131 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

Page 133: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 132 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

Page 134: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 133 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

Page 135: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 134 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

        

Page 136: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 135 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

      

Page 137: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 136 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

         

Page 138: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 137 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

         

Page 139: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 138 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

 

Page 140: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 139 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

          

Page 141: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 140 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

        

Page 142: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 141 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

Annexure­I 

 

Page 143: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 142 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

 

 

 

 

Page 144: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 143 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

 

 

 

Page 145: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 144 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

Annexure II    

    

Page 146: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 145 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

      

Page 147: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 146 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

Annexure III  

 

 

Page 148: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 147 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

  

  

Page 149: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 148 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

Annexure IV   

  

Page 150: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 149 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

  

   

Page 151: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 150 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

Annexure V  

MODEL RULES AND REGULATIONS OF A SOCIETY  1.    Name of the Society 

Name of the Society shall be ...................................................................................  

2.    Membership The membership  of  the  Society  is  open  to  any  person  who  has  attained  the  age  of 

maturity and fulfills the terms and conditions of the Society but subject to the approval of the Governing Body. If any Government servant is desirous of becoming a member of the Society, he/she will have to  inform the appropriate authority  in the Government prior to  joining the society. If the membership is not approved by the Governing Body, the reason of refusal shall be communicate to the person/applicant concerned. 

3.    Admission Fee & Subscription The Admission Fee and the Subscription shall be as under unless otherwise revised by 

the Governing Body.  

(a) Admission Fee Rs. ______________________ at the time of admission. 

(b) Subscription Rs. ______________________________ per month. 

4.    Termination or Cessation of Membership The Governing Body of the Society shall have the powers to expel/terminate  

a member or/and members, from the membership of the society, on the following  grounds: (a) On death. 

(b) On written resignation. 

(c) If found to be involved in any anti‐social activities. 

(d) If adjudged by any court of law to be a criminal offender. 

(e) If found guilty by means of anti propaganda of the Aims & Objects of the  

  society 

(f) If fails to pay the subscription contribution or contribution for three months. 

(g) If has not attended three consecutive meetings. 

(h) If disregards Rules & Regulations or disobey the decisions of the Governing 

  Body.  The  decision  of  the  Governing  Body  shall  be  communicated  to  the  member        

concerned. 

5.  Re‐Admission   In case, any member of the Society is expelled by the Governing Body on any    ground of section 4(b), (e), (f), (g) & (h) of Rules & Regulations, he can be    readmitted, Provided the Governing Body permitted his/her readmission. 

  

Page 152: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 151 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

6.  Registration of members and facilities  The society shall maintain a register of its members and shall entre therein the name, address, date of enrolment and date of termination of a members. 

7.  General Body Defined   All members of the society will constitute the General Body of the society. 

8.  General Body a. Notice:‐ Minimum__________ days notice shall be given  to  the members, before  in  the 

date of General Body Meeting, enclosing agenda specifying date, time, place and issue to be discussed.  

b. Meeting:‐ General Body Meeting shall be held at least once in every year. c. Quorum:‐  The quorum of General Body Meeting  shall be  2/3rd  (two‐third) of  the  total 

strength of the General Body members of the society. 9.  Rights & Privileges of Members 

All and every member of the society. a. Shall be entitled   to participate  in meetings cultural/educational  functions and other 

lawful gatherings, call/arranged by the society. b. Have  right  to  collect  the  Identity Card  after  depositing  the  required/prescribed  fee 

(fixed by the Governing Body of the Society from time to time) 10.  Duties of the Members 

All and every member of the society shall: a. Elect the Governing Body of the society, b. Attend the General Body meetings regularly c. Give  the  Necessary  information  to  the  society,  pertaining  to  any matter  which  is 

necessary to be known by the society. d. Not indulge in activities which are prejudial to the Aims and Objects and/or the Rule & 

Regulations of the Society. 11.  Governing Body: 

a. Strength:‐   The Strength of Governing Body (Including office bearers and executive member) shall not be less than ___________ and not more than _________________ 

b. Term:‐   Term of every Governing Body shall be ___________years. c. Notice:‐  Minimum  ____________days  notice  but  urgent  Governing  Body  

Meeting can be called  by 24 hours notice. d. Quorum:‐  Quorum of every Governing Body Meeting shall be ________________ 

of the total strength of the Governing Body. e. Meeting:‐  Governing  Body Meeting  shall  ordinarily  be  held  once  in  3 months 

regularly but shall be held at least once every year. f. Emergent Meeting:‐  The Emergent Governing Body Meeting may be called by the 24 

hours notice but quorum  for  the  same  Emergent Governing Body Meeting  shall be 2/3rd  of the total strength of the Governing Body of the Society.  

12.  Composition of the Governing Body:‐    The Composition of the Governing Body shall be as under: 

a. President / Chairman      One 

b. Vice President/ Chairman    One 

Page 153: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 152 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

c. General Secretary      One 

d. Assistant Secretary      One 

e. Treasurer        One 

f. Financial Secretary      One 

g. Executive Members      From ……………………. to ……………………… 

13.  Termination of Members of Governing Body:‐   Any member of the Governing Body can be terminated from the office on the    same grounds of article 4. 

14.  Functions and Powers of Governing Body:‐ a. Governing Body  shall be  responsible  for  the management  and  administration of  all 

affairs of  the  society, and  is also authorized  to appoint any office bearer, executive 

member to look after any particular activity.  

b. All the decisions shall be taken by the majority votes. 

c. The  Governing  Body  shall  have  the  powers  as  are  the  powers  of  the  Society, 

mentioned in the memorandum of the society and in these rules and regulations. 

The Governing Body shall have also the following powers: 

(i) To prepare plans, Projects and Programmes. 

(ii) To appoint election officers and his / her powers. 

15. Restriction on Holding office:‐   No  persons who  is  an  undercharged  insolvent  or who  has  been  convicted  of  any offence  under  the  law  shall  be  entitled  to  be  a  member  of  a  Governing  Body. Permission/sanction  from  the  prescribed  authority  shall  be  obtained  by  the  Government Servant holding an elective office in the society. 

16. Powers and Duties of office Bearers: A. President/Chairman 

a. President/Chairman shall preside over all the meetings of the society. 

b. At the time of voting on any matter/ subject (except election), if the total votes of the 

groups of members happen to be equal in number the President has the power to cast 

an extra vote to decide the matter / subject 

c. President/Chairman shall have the power to allow inclusion of any subject/ matter in 

agenda for the discussion in the course of proceeding/ meeting. 

d. President/Chairman  will  sign  all  the  papers/letters,  on  behalf  of  the  society,  to 

conduct its correspondence. 

B. Vice President/Vice Chairman   The Vice  President/ Vice  Chairman  of  the  society  shall  enjoy  all  the  powers  of  the President/Chairman in his/her absence.   

Page 154: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 153 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

C. General Secretary. a. General Secretary will  summon and attend  the meeting of  the Governing Body and 

General Body b. General  Secretary will  prepare  the membership  register  as well  as  the  proceeding 

register to record the minutes of the proceedings of the Governing Body Meeting and have them duly signed by the members who attend the meetings. 

D. Secretary                    The Secretary shall enjoy all the powers of General Secretary in his/ her absence.  

E. Treasurer a. All funds of the society shall remain under the care and management of Treasurer. b. Treasurer shall maintain the accounts of all money which  is received and/or paid by 

him/her on behalf of the society. c. Treasurer  shall make  disbursement  in  accordance with  the  direction  of  Governing 

Body. F. Financial Secretary. 

a. He  shall  keep  account  book  of  the  Society’s  fund  and  shall  record  all  receipts  and 

expenditure. 

b. All monetary transactions shall be made through her/ him 

c. He/she  shall  be  responsible  with  the  Treasurer  for  the  proper  accounting  of  the 

Society’s fund. 

17.  Filling up of Casual Vacancies Any casual vacancy amongst the Governing Body, shall be filled by the resolution passed by the Governing  Body.    Such  appointment(s)  shall  be  confirmed  by  the General  Body  in  its coming General Body Meeting. 

18.  Appeals All the appeals shall be preferred to the Governing Body of the society and the decision of the Governing Body shall be final. 

19.  Election General Body in its Annual Meeting will elect its President/Chairman and all the office bearers 

and also  the Executive Members of  the Governing Body, after every __________________ 

years by secret ballot papers or by show of hands as the Election Officer may decide, voting 

by proxy will be  allowed/will not be  allowed.  Simple majority of  vote  shall be declared  as 

elected accepted. 

20.  Sources of Income All the income of the society shall be utilized only for the promotion and uplift me of the Aims and Objects of the society. Sources of income of the society are as under:  

a. Admission fee : Subscription from the members of the society. b. Donations and special contributions. 

  

Page 155: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 154 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

21.  Property of a Society   All property belonging to a society shall vest in the Governing Body of the Society but  

shall  be  referred  to  as  the  property  of  the  society.  The  society  shall maintain  register  for recording details of the properties.  

22.  Gift   Any kind of gift received from any person for a specific purpose shall not be used for  

any other purpose without the consent of the donors of Registrar, Firms & Society.  

23. Financial Year   Financial Year of Society shall start from 1st April to 31st March, every year.  

24. Audit The accounts of  society  shall be audited by  the qualified auditor  (Chartered Accountant or Persons approved by the Registrar, Firms & Societies) every year.  

25. Management of Funds & Accounts Operation Bank Accounts shall be operated by  joint signatures of ___________________________ the society  shall  keep  proper  books  of  accounts  in which  all  sums  of money  received,  source thereof, expenditure and object or purpose, the assets and  liabilities of the society shall be entered.  

26. Inspection of accounts and of the proceedings of meetings All  the  members  of  the  society  shall  have  the  right  to  inspect  Books  of  accounts  and proceedings of the meetings of the society if and when required.  

27. Submission of annual reports/returns One  in every year a  list of  the Governing Body of  the current year, annual activities  report certified  by  the  President  and  Secretary  and  auditor’s  report  and  balance  sheet  for  the previous  year  duly  audited  and  signed  by  the  qualified  auditors  shall  be  in  office  of  the Registrar,  Firms  &  Societies,  Mizoram,  Aizawl  as  it  is  required  under  section  18  of  the Mizoram Societies Registration Act. 2005.  

28. Dissolution If the society needs to be dissolved, it shall be dissolved as per provisions laid down under the Section 25 & 28 of the Mizoram Societies Registration Act. 2005.  

29. Legal Proceedings Society may sue and/or be used in the name of the President, the Society or any office bearer authorized by the Governing Body in this behalf.    

Page 156: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 155 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen 

30. Amendment   Any amendment in memorandum and Rules & Regulations will be carried out in  

accordance with Section 9 of the Mizoram Societies Registration Act. 2005.  

31. Application of the Act.   All the provisions under all the section of the Mizoram Societies Registration Act.  

2005 shall be applicable to this society. Certified that this is the correct copy of the Rules & Regulations of the society. 

    

Secretary                                                                    Chairman   

…………………………………………..... Watershed Committee ................................... Lui  

 

                          

Page 157: DETAILED PROJECT REPORTmizorural.nic.in/file/IWMP/ACTION PLAN/Action Plan... · INTEGRATED WATERSHED MANAGEMENT PROGRAMME (IWMP) DETAILED PROJECT REPORT OF LUNGLEI – III (LOWER

Detailed Project Report | 156 

IWMP: Lunglei – III Watershed Project                                                                                           PIA: BDO, Lungsen