33
DESIGN OF PAVEMENT BY USING GEO POLYMER CONCRETE BLOCKS IN AUTT CAMPUS Guided by Mr. S. SURESH Visiting faculty Department of Civil Engineering Anna university Presented by N.Dhileeban(011081 11016) V.Harikrishnan(011 08111028) S.Jaisankar(011081

Design of Pavement by Using Geo Polymer

Embed Size (px)

Citation preview

Page 1: Design of Pavement by Using Geo Polymer

DESIGN OF PAVEMENT BY USING GEO POLYMER CONCRETE BLOCKS IN AUTT

CAMPUS

Guided by Mr. S. SURESH Visiting faculty Department of Civil Engineering Anna university of technology, Tiruchirappalli-24

Presented byN.Dhileeban(01108111016) V.Harikrishnan(01108111028) S.Jaisankar(01108111029) K.Kalirajan(01108111034)

Page 2: Design of Pavement by Using Geo Polymer

The traditional system of bituminous pavements is widely used in our country.

Bitumen is a by product of petroleum which is depleting day by day.

Locally available cement concrete is a better substitute to bitumen.

Concrete – Low Impact and Abrasion Resistance .

Portland cement responsible for upward 85% of energy and 90% of carbon dioxide emission.

The perfect solution would be GEO POLYMER CONCRETE BLOCK PAVEMENTS.

Introduction

Page 3: Design of Pavement by Using Geo Polymer

Objective

We have planned to prepare geo polymer concrete blocks and design a pavement by using these blocks in AUTT campus.

Different aspects in planning , designing and cost analysing of pavement will be included.

Page 4: Design of Pavement by Using Geo Polymer

MethodologyGeo polymer concrete

preparation

Geo polymeration(60-80oC 6-12 hours open atm)

Aggregate storage(Open air atm)

Alkaline activator (NaOH + Na2SiO3)( Na2O 6- 10%, w=0.30 – 0.40,M=8)

Fly ash

Page 5: Design of Pavement by Using Geo Polymer

Mix Proportion

10 Molarity calculation:-Specific gravity of flyash = 2.52Design Compressive strength = 45 MpaDensity of concrete = 2400 kg/m3

 Weight of the aggregate = 75% of 2400 = 1800 kg/m3

70% of Coarse aggregate = 1260 kg/m3

Fine aggregate (sand) = 1800 – 1260 = 540 kg/m3

Page 6: Design of Pavement by Using Geo Polymer

cont...

Alkaline liquid (Sodium hydroxide + Sodium silicate)Alkaline liquid to flyash ratio by mass = 0.45 = 0.45Mass of flyash and liquid = 2400 – 1800= 600 kg/m3

 Mass of flyash = 600/(1+0.45)= 413 kg/m3

Mass of alkaline liquid = 600 – 413= 186 kg/m3

Page 7: Design of Pavement by Using Geo Polymer

Cont...

Ratio of sodium silicate to sodium hydroxide = 2.5  Alkaline liquid requirement:Mass of NaoH = 186/(1+2.5) = 53.2 kg/m3

Mass of sodium silicate = 133 kg/m3

Page 8: Design of Pavement by Using Geo Polymer

Curing

Ambient CuringHot curing

Ambient Curing was done by keeping the specimens including the moulds in Room temperature for 5 days after it will be demoulded.

In Hot Curing the specimens including the moulds were kept in a hot air oven or in micro-oven at 60oC for 24 hours after it will be demoulded.

Page 9: Design of Pavement by Using Geo Polymer

Economy of Gpc Vs ordinary cement concrete

Ordinary concrete for M30: cement content = 340 kg/m3

cost = Rs. 2500 Geopolymer concrete for M30:  NaoH requirement 31 Kg cost = Rs. 1147 sodium silicate requirement 109 kg cost = Rs. 1144.50 Total cost = Rs. 2291.50 No CO2 emission

Page 10: Design of Pavement by Using Geo Polymer

Test values

Specific Gravity: Fly ash = 2.47 Sand =2.68 Coarse aggregate =2.83 Soil test: Plastic limit = 21% Liquid limit =22.5% Optimum moisture content =10% Bulk density = 1.93 g/cc Dry density =1.75 g/cc

Page 11: Design of Pavement by Using Geo Polymer

Cont...

Fineness of flyash = 90% Aggregate crushing value =1.93% Fineness modulus of c.a = 7.68 Fineness modulus of f.a = 2.507 CBR value = 9%

Page 12: Design of Pavement by Using Geo Polymer

Molarit

y of

NaOH

Specimen Compressive strength

7day

s

N/

mm2

14da

ys

N/

mm2

28days

N/mm2

 

12 M

A 17.9 20.6 24.2

B 18.1 21.1 24.1

C 17.3 20.9 24.4

 

10 M

A 15.2 19.7 22.5

B 14.6 19.8 22.1

C 15.3 20.2 22.3

 

8 M

A 13.8 19.2 21.5

B 13.1 18.7 21.6

C 14.2 19.1 21.4

Page 13: Design of Pavement by Using Geo Polymer
Page 14: Design of Pavement by Using Geo Polymer
Page 15: Design of Pavement by Using Geo Polymer

EDA calculation

Effective number of days per year = 300 Days/ yearGrowth factor = (1+r)n -1 / loge(1+r)

= (1+0.02)20 – 1 / loge(1+0.02)

= 24.5Design EDA = no of vehicle per day x load factor x effective no of day x growth factor = [(190 x 0.5)+(58 x 1)+(15 x 3)] x 300 x 24.5 = 1.45 x 106 EDA.

Page 16: Design of Pavement by Using Geo Polymer

Total thickness chart

Page 17: Design of Pavement by Using Geo Polymer

Base course thickness

Page 18: Design of Pavement by Using Geo Polymer

Paving block thicknessDesign traffic (EDA) Recommended paving

blocks

Shape Thicknes

s (mm)

Laying

pattern

Up to 3x104 Any 60 or 80 H,B or S

3x104 or more Capable of

herringbon

e pattern

80 H only

Page 19: Design of Pavement by Using Geo Polymer

Pavement Design

Thickness Design : Sub base course = 150 mm Base course = 140 mm Bedding Sand = 30 mm Pavement Block = 80 mm Joint = 3 mm Laying pattern : Herringbone Laying pattern

Page 20: Design of Pavement by Using Geo Polymer

Herringbone Laying pattern

Page 21: Design of Pavement by Using Geo Polymer

Pavement Structure

Page 22: Design of Pavement by Using Geo Polymer

Campus Road layout

Page 23: Design of Pavement by Using Geo Polymer

Construction of pavement

The following steps are followed in the construction of pavement, Setting out Drainage and subgrade construction Compaction Sub base/ base course construction Planning the paving operation Placing and screeding sand bedding Edge restraints Laying the paving block

Page 24: Design of Pavement by Using Geo Polymer

Maintenance WEED CONTROL The sanded joints ultimately acquire a content of dust which may

permit germination of airborne seeds. Traffic should control weed growth in many situations. If,however weed growth does become apparent spraying with a herbicide will be necessary.

JOINTS Once filled and after dust has time to accumulate the joints

should remain filled. Joints sand can sometimes be lost by rain on steep slopes or vigorous hosing ,particularly in the early life of the pavement. If there is evidence of sand loss the affected joints should be topped up by sand brooming and vibration.

CLEANING Block pavements can generally be cleaned with normal

equipment.The exceptions are vacuum equipment. And water blasting which may remove joint sand.In the course of time dust acts as a binder in the joints and vacuum equipment. May be used.

The block surfaces can become stained with oil or food stuffs. Commercially available concrete cleaning compounds can be used but care is needed when hosing them off.

Page 25: Design of Pavement by Using Geo Polymer

Item

no

Particul

ates of

items

and

details

of

works

No Leng

th

m

Breadt

h

m

Thickn

ess

m

Quantity

Cu.m

1 Earth

work

excavati

on

1 4609.

38

7.2 0.24 7965

2 Subgrad

e filling

1 4609.

38

7.2 0.15 4978.13

3 Base

course

filling

1 4609.

38

7.2 0.09 2986.88

4 Bedding

sand

1 4609.

38

7.2 0.03 995.63

5

Paveme

nt block

12485

90

0.19 0.139 0.08 2655

6 Edge

restraint

s

2 4609.

38

0.15 0.15 207.42

7 Joint

filling

sand

12485

90

- 0.015 0.08 1498.3

Page 26: Design of Pavement by Using Geo Polymer

Abstract of cost

Item

no

Particulate

s of items

and details

of works

Quantity

Cu.m

Per Rate

Rs.

p.

Amount

Rs.

p.

1 Earth work

excavation

7965 Cu.m 25.50 203107.50

2 Subgrade

filling

4978.13 Cu.m 365.00 1817017.4

5

3 Base course

filling

2986.88 Cu.m 400.00 1194752.0

0

4 Bedding

sand

995.63 Cu.m 110.00 109519.30

5 Pavement

block

2655 Cu.m 2991.50 7942432.5

0

6 Edge

restraints

207.42 Cu.m 2991.50 620496.93

Total

11887325.

68

Add 3% for contingencies 356619.77

Add 2% for work charged

established

237746.51

Grand total

12481691.

96

Page 27: Design of Pavement by Using Geo Polymer

Comparision between GPC&OPC

Item no Particulates

of items

and details

of works

Quantity

Cu.m

Per Rate

Rs.

p.

Amount for

GPC

Rs. p.

Amount

for OPC

Rs p.

1 Earth work

excavation

7965 Cu.m 25.50 203107.50 203107.50

2 Subgrade

filling

4978.13 Cu.m 365.00 1817017.45 1817017.4

5

3 Base course

filling

2986.88 Cu.m 400.00 1194752.00 1194752.0

0

4 Bedding sand 995.63 Cu.m 110.00 109519.30 109519.30

5 Pavement

block GPC

2655 Cu.m 2991.50 7942432.50 --

6 pavement

block OPC

2655 Cu.m 3200.00 -- 8496000

7 Edge

restraints

GPC

207.42 Cu.m 2991.50 620496.93 --

8 Edge

restraints

OPC

207.42 Cu.m 3200.00 -- 663744.00

Total 11887325.68 12484140.

25

Add 3% for contingencies 356619.77 374524.21

Add 2% for work charged

established

237746.51 249682.81

Grand total

12481691.96 13108347.

27

Page 28: Design of Pavement by Using Geo Polymer

conclusion

Through this project the following results were obtained Mix design procedure for geopolymer concrete. Compressive strength has been varying with

respect to the change in molarity of NaOH solution.

Economy in GPC production when compared to Ordinary cement concrete.

And also we are concluded that by using this type of pavements in our campus will be most economical. At the same time natures gift of wonderful World is protected from Global warming problem. Thus this project will be most economically and ecofriendly also.

Page 29: Design of Pavement by Using Geo Polymer
Page 30: Design of Pavement by Using Geo Polymer

TURN POLLUTION INTO SOLUTION

Page 31: Design of Pavement by Using Geo Polymer

Suggestions for future Research

The bond between geopolymer concrete and steel reinforcements needs to be studied for the practical use of this material.

The interaction of geopolymer concrete and reinforcements is to be studied to develop codal provisions for practical design purposes.

A detailed study is needed to minimize the amount of heat energy required for polymerization of geopolymer concrete.

It is obvious that durability of geopolymer concrete is to studied in details for long term performance of such concrete.

Page 32: Design of Pavement by Using Geo Polymer

References

Davidovits, J (1988) “Soft Mineralogy and Geopolymers”, Proceedings of the of Geopolyemer 88 International Conference, the Université de Technologie, Geopolymer Compiègne, France.

Dutta, B.N., “Estimating and Costing in Civil Engineering”, UBS

Malhotra, V. M. (1999). "Making Concrete "Greener" With Fly Ash." ACI Concrete International 21(5): 61-66.

Tait, J.B(1987) “Interlocking Concrete Block paving” National Roads board, RRU Technical Recommendation TR10.

PWD Schedule Rates for 2011-2012. Shackle, B(1978) “An Experimental Investigation

of the Response of Interlocking Block pavements to Simulated Traffic Loading”. Australian Road Reasearch Board. ARR 90. 

Page 33: Design of Pavement by Using Geo Polymer