Design FMEA (DFMEA) Tutorial In this tutorial, you will learn: Completing the Design FMEA Form: Identifying the Product Function Identifying Potential Failure Modes Identifying Potential Failure Effects Determining the Severity of the Effect Identifying Potential Cause(s) of the Failure Mode Determining the Probability of Occurrence of the Failure Mode Identifying Design Verifications for the Causes Determining the Probability of Non-Detection of the Failure Mode Using the Completed DFMEA Form: calculating the Risk Priority Number (RPN) determining Corrective and Preventive Actions prioritizing Actions Based on the RPN What Is A Design FMEA? * FMEA is a method for identifying potential or known failure modes and providing corrective and preventive actions. * The Design FMEA is a disciplined analysis of the part design with the intent to correct or prevent the design- based failure modes prior to the first production run. The FMEA Process: * Identify potential or known failure modes * Identify the effects and causes of each failure mode * Prioritize the identified failure modes based on the frequency of occurrence, the severity of the failure mode, and the likelihood of detection * Provide for follow-up corrective and preventive actions * Follow up

Design FMEA

  • Upload
    pierors

  • View
    25

  • Download
    2

Embed Size (px)

DESCRIPTION

Design FMEA

Citation preview

Design FMEA (DFMEA) TutorialIn this tutorial, you will learn:Completing the Design FMEA Form: Identifying the Product Function Identifying Potential Failure Modes Identifying Potential Failure Effects Determining the Severity of the Effect Identifying Potential Cause(s) of the Failure Mode Determining the Probability of Occurrence of the Failure Mode Identifying Design Verifications for the Causes Determining the Probability of Non-Detection of the Failure ModeUsing the Completed DFMEA Form: calculating the Risk Priority Number (RPN) determining Corrective and Preventive Actions prioritizing Actions Based on the RPNWhat IsADesignFMEA?* FMEA is a method for identifying potential or known failure modes and providing corrective and preventive actions.* The Design FMEA is a disciplined analysis of the part design with the intent to correct or prevent the design-based failure modes prior to the first production run.The FMEA Process:* Identify potential or known failure modes* Identify the effects and causes of each failure mode* Prioritize the identified failure modes based on the frequency of occurrence, the severity of the failure mode, and the likelihood of detection* Provide for follow-up corrective and preventive actions* Follow upDesignFMEAProcess Flow

These steps of the FMEA will be discussed and explained later in detail,but it is helpful to see the overall flow, at this overview level, for now. Try to match the additional following examples to this flow to give you a feel for how Design FMEAs can be used.

For this abbreviated example, there are 4 basic functions of the car door. One way (failure mode) the door could potentially fail to perform the last 2 basic functions listed is by the interior lower door panels becoming corroded.The failure mode could potentially lead to deteriorated door panel life (a failure mode effect of door panel corrosion), resulting in poor appearance and impaired function of the interior door hardware.Note: it is acceptable to break down the effect in a chain of events as shown if it better describes the problem being worked on.The effect is described from the perspective of the customer, although the description need not be in the customers language. The severity of the deteriorated door life effect is rated asa 6 here.There are 4 potential design-based root causes of the door panel corrosion (the failure mode here) listed.Note that while these causes may show up in fabrication or assembly, they are design-based, that is, the designers specify their values or settings.Each cause receives its own probability of occurrence rating score, based on the likelihood of the cause happening and its resulting in the failure mode.The only design verifications (DVs) presently in place are the Design groups phase design reviews.The ability of the design reviews to prevent the design-based cause (or detect the potential failure mode) from happening is assessed for each of the causes listed.Then the RPN is calculated for each cause so that their corrective/preventive actions can be prioritized. The highest scores become the highest priorities.The fact that none of the scores is close to the maximum possible score (1000) does not mean anything.Just the relative scores are meaningful.

The Design FMEA (DFMEA) needs to be done early in the product design cycle, after the design concept has been selected since it needs detailed part functions; it should be continually updated as the program develops. FMEA can be applied as a supporting method as part of the Concurrent Engineering development process. Try for some concurrency between the Design and Process FMEAs.

The information developed from the DFMEA will provide excellent input for the earlier phases of the Concurrent Engineering or Integrated Product Development processes, and vice versa. Having some timing overlap (concurrency) between the DFMEA and the PFMEA will further reduce the Time to Market.If an existing design, on which there is already a DFMEA, is applied in a different environment or usage, then the FMEA should be focused on the impact of the new environment or application.

The DFMEA process will be explained and demonstrated using the numbering scheme shown on the preceding blank DFMEA form. You may want to periodically refer back to this blank form as each step and column of the process is described. There will also be a flowchart that progressively develops in sequence with the numbered steps.Function of the Part The function of the part is the task that it must perform to meet its design intent. it should be described in away that is concise, exact andclear to all participants and users Use a verb-noun formatExamples: Isolate electrical data signals Provide mating surface to part B Provide dielectric material for impedance Provide engaging tab for cam Last for 40,000 cycles Operate within specified environmental conditions Be manufactured at specified productivity and quality rates Right about now in the FMEA process would be a good time to perform the Fault Tree Analysis FTA.Then you would transfer the information to theFMEA form as you go through the steps.Note that you will likely adding to that information, but it is an excellent way to make the FMEA more thorough.

Although the DFMEA assumes the part will be manufactured to the design intent, it should still take into account realistic limitations of the manufacturing and assembly processes, e.g., clearances for tooling, achievable tolerance capabilities, realistic parts/hour rates, etc.Design FMEA Use this blank form to develop your own example.

FMEA Process Flow Failure Mode and Effect of Failure ModePotential Failure Mode of the Function* The ways in which the part could fail to perform its intended design function.. it should be described in a negative way.* Stress how the part could fail, not whether it will fail, to conform to the design specification* Try asking what could happen to cause a loss of function: How could this part fail?,or Could it break, deform, wear, corrode, bind, leak, short, open, etc.?

*Examples of failure modes: Isolate electrical data signals loss of dielectric Provide mating surface to part B worn mating surface Provide dielectric material for impedance loss of signal transmission integrity Provide engaging tab for cam bent tab Corrosion Cannot assemble Over-deflectionAssumethat the failure could occurfor now.Later we will deal with the likelihood of its occurrence. Refer back to the list of functions when asking the What If questions.Also refer back to the FTA to help ensure completeness here.List each potential failure mode forthe part.Note that for these examples, the failure modes are shown following the parts basic functions (optional).Other possible failure modes could be a part oxidizing, fracturing, sticking, loosening, not transferring a force, not assembling readily with a mating part, drift, disengaging during operation, etc.FMEA Process Flow Effect of FailureMode

PotentialEffect(s) of the Potential Failure Mode* The outcome of the occurrence of the failure mode on the part or assembly (system).* Describe the effect of the failure specifically, and in terms of customer reaction:What does the customer (external or internal) experience as a result of the failure mode ofor Will the component or assembly be inoperative, intermittently operative, noisy, not durable, etc.?* Consider whether the effect can also impact other functionsor parts.Examples of effects:* Loss of dielectric low withstanding voltage assembly shorts out* Bent tab cannot assemble mating part* Worn mating surface mating part does not engage* Loss of signal transmission integrity incorrect data transmission* Tab edge does not engage cam auxiliary bolt sticks* Cannot assemble lost time and wasted costs in Final Assembly* Corrosion part loses yield strength, with a lower MTBF

The loss of dielectric is an example of a failure mode resulting in a low withstanding voltage, which in turn results in the assembly sorting out (the effect).Using a chain of events is a good technique if it helps you better explain the failure modes and their effects. Look for the outcomes or consequences of the failure mode on the part, assembly, other parts, end-user, etc. You should also include safety or regulatory non-compliance outcomes.Other examples include unpleasant odor, unstable, regulatory non-compliance, intermittent operation, or poor appearance.Assuming that the failures have occurred, give specific descriptions of the ways in which customers could observe each failure.Use the perspective of the external or internal customer, but it isnt necessary to use the customers terminology here.Note that there could be more than one effect for a given failure mode, or, an effect could be the result of several failure modes.Dont forget to refer back to your FTA. Note: MTBF stands for mean time between failures.The severity or estimated consequence of the effect on a 1 to 10 scale, where a 1 is a minor nuisance and a 10 indicates a severe total failure of the system.When weighing the consequence (effect) ofthe failure, ask How serious would the effect of this failure be to the customer, assuming it has appended?To reduce the severity of the effect of a product failure mode, a part design action is usually required.The part design action to reduce a high rating may include design additions or revisions that mitigate the resultant severity of the failure, e.g., seat belts in a car. Severity is the first of the 3 Risk Priority Numbers (RPN) rating criteria.Think of the estimated consequence orseriousness of the effect, assuming it does exist*, on the external and/or internal customer. If the effect is critical, the severity is probably high.*Do not consider the likelihood that the defect will occur in scoring this criterion; this will be evaluated in the second criterion (Occurrence).A sample of a Severity ranking scale is shown here:Severity RankingRankingDescription

1The effect of the failure is of such a minor nature as to be undetectable by the customer.For example, the part may be out ofspecification on a non-key quality characteristic but not have any noticeable effect on the system.

2-3The failures effect is of a minor nature, although it is detectable by the customer, it causes only slight annoyance without any noticeabledegradation in the system performance.

4-6The failures effect causes some customer dissatisfaction and some system degradation.

7-9The failures effect causes major customer dissatisfaction and major system degradation. serious safety/legal implications.

10Sudden, catastrophic failure without any prior warning. very serious legal implications.

Thecompany should adopt these sample ratings towhat is appropriate to their industry. This table of a Severity ranking scale provides guidance for assigning criteria values to the failure mode effects on a consistent basis.It is only a sample and should not be used without adaptation to the industry and company. The project team should evaluate each effect and reach a consensus on their ranking values. The idea is to find comparative differences among the effects so that their associated causes can later be prioritized. Failure modes with a severity rank of 1probably do not need to be analyzed further.It is an indication of a design weakness, the consequence of which is the failure mode. Consider the possible design mechanisms and/or causesof each failure mode.Analyze what conditions can help bring about the failure modes.

Make sure the list of causes is thorough. This helps point the way toward preventive/corrective actions for all pertinent causes. Consider the difference between effects, contributing causes, and root causes.Examples of causes:* Wrong polymer specified moisture absorption loss of dielectric* Excess annealing malleable base material alloy bent tab* Maximum material condition stack-up worn mating surface* Insufficient gold plating specified loss of signal transmission integrity* Least material condition stack-up gap Tab edge does not engage camHere you are looking for the potential design-based root causes of the potential failure modes.This includes causes that occur in production but are due to the design.Do not include causes that are due strictly to errors or flaws in the production process save these for the PFMEA. Again, refer to the completed FTA to help ensure the list of causes is as thorough as possible, and that the root causes are identified. Otherpossible causes could include improper material specified for process or end-use operating environment, incorrect algorithm, incorrect software specification, insufficient re-lubrication capability, incorrect cam path, etc. Other possible failure mechanisms could include creep, fatigue, wear, galvanic action, EMI (electromagnetic interference), etc.* The probability that the cause will happen, and that it will result in the failure mode, on a 1 to 10 scale. A 1 reflects a remote possibility of it happening and a 10 indicates a high probability of the cause and its failure occurring in major proportions.* AskHow likely to happen is the cause? and then How likely is it to result in the potential failure mode?* Generally, to reduce the probability of the failure mode happening, a design change will be required.Occurrenceis the second of the 3 Risk Priority Numbers (RPN) rating criteria.Think of the relative likelihood or probability of the cause actuallyhappening during the design life of the part andthen resulting in the failure mode.One possible source of reference data is the reject and service history for similar components. A sample of a Probability of Occurrence ranking scale is shown below:Probability OfOccurrence RankingRankingDescription

1Remote possibility of happening.Where similar parts have been used for similar functions in previous design or processes, failures have been non-existent.

2-3Low failure rate with similar parts having similar functions in previousdesigns or processes.

4-6Moderate failure rate with similar parts having similar functions in previous designs or processes.It is generally a failure that had occurred occasionally in the past but not in major proportions

7-9Frequent failure rate with similar parts having similar functions in previous designs or processes.

10High probability of failure.

The company should adopt these sampling ratings totheir industry and include specific probability values. This table of a Probability of Occurrence ranking scale provides guidance for assigning criteria values to the causes and their failure modes on a consistent basis.It is only a sample and should not be used without adaptation to the industry and company.

The project team should evaluate the likelihood of each cause and its associated failure mode and reach a consensus on their ranking values. The idea is to find comparative differences among the causes so they can later be prioritized (with the total RPN scores).* The design verification steps that have been or are being used with the same or similar designs.* List all current design controls which are intended to prevent the specific design-based causes(s) of the potential failure modes from occurring, or are intended to detect the design-based causes(s) of the potential failure or the resultant failure mode.

Examples: design checklists, peer reviews, reliability analysis, variation stack-up analysis, FEA, rapid prototyping, handoff checklists, environmental stress analysis, etc. Design controls are intended to assure the design adequacy for the failure mode and/or cause under consideration.Asuggested technique when listing the Design Controls in their column is to add the prefix p to DVs which are intended to prevent the failure mode cause or the prefix d to DVs which are intended to detect the failure mode or its cause. It is not uncommon for a company just beginning to use FMEA to find that it does not have many DVs.Detectability or Probability of Detection of the Potential Failure Mode* The probability that the failure mode caused by the design would be detected by the DV before the part is released to production on a 1 to 10 scale, where a 1 indicates a high probability and a 10 indicates a low probability.* Ask If there is a design weakness, how likely is it to be detected by our current DVs before the part is released to production?

Detectability is the third of the 3 Risk Priority Number (RPN) rating criteria.It is an assessment of the ability of the DV program to identify a potential design weakness before release to production. It is a relative ranking (within the FMEA) of the ability of the DV to assure the design adequacy for the failure mode and/or cause or failure mechanism under study.A high score means a low probability of detection, and a low score indicates a high probability of detection.Because of this possible confusion, some users call this criterion the Probability of Non-Detection.A sample of a Probability of Detection ranking scale is shown on the next page.RankingDescription

1-2There is a very high probability that the design weakness, when it exists, will be detected before the part is released to production, usually bythe DV program.A very low probability of non-detection.

3-4High probability that the design-based cause of the failure will be detected before the parts release to production, usually by the DV program.A low probability of non-detection.

5-6Moderate probability that the design-based cause of the failure will be detected before the parts release to production, usually by the DV program.A moderate probability of non-detection

7-8Low probability that the design-based cause of the failure will be detected before the parts release to production.High probability ofnon-detection.

9-10Very low probability that the design-based failure will be detected before the parts releaseto production.Very high probability of non-detection.

The company should adopt these sample rankings to their industryand include specific probability values. A low score means that there is a low probability that the failure mode or defect based on a design weakness, when the failure mode does exist*, will escape the DV controls before the design is released to Production and the defect has a chance to reach the customer. *Do not consider the likelihood that the defect will occur in scoring this criterion; this was evaluated in the second criterion (Occurrence).A high score for Detectability means that there is a high probability that the failure mode or defect, when it exists, will escape the DV controls before the design is released to Production. If there is more than one design control that could prevent or detecta given failure mode or its cause under study, consider in the scoring the one that would provide the best prevention or detection.Quantifying FMEA: Risk Assessment

This is an alternate set of rating guidelines.Customized guidelines should be developed for your industry and company.This summary of alternate ranking criteria can also be used as a guideline for developing your own standardized set of values. In the table, P refers to the Probability of an event.For example, for a rank of 6 in Occurrence, the probability of the cause and the failure mode happening is approximately 1 in 80.

At a level of 6 in Severity (of the failure modes effect), there would be some customer dissatisfaction, starting to approach a high level with someinteroperability of the part. For a rank of 6 in Detectability, the probability of missing the failure mode would be somewhere around 1 in 100.These probability values might be appropriate for some industries but not for others.FMEA Risk Priority Number* The Risk Priority Number (RPN) is calculated by multiplying together the values of the severity, occurrence, and detection risk assessmentcriteria.* The RPN provides an indicator of the relative seriousness and priority of each failure mode.The higher the RPN, the more relatively serious is the failure mode.FMEA Risk Priority Number FormulaRPN=Severity x Occurrence xDetectionAlthoughsome FMEA instruction manuals say the RPN values are used to rank and compare the seriousness of failure modes, the scoring is actually done for each cause.The Corrective/Preventive Actions will be generated for the higher priority causes. The purpose of generating the RPN scores is to prioritize for which causes there should be Corrective and/or Preventive Actions developed and completed.Note: the absolute values of the RPN do not mean anything.As long as you are consistent in applying the criteria, then their RPN scores can be usedfor relative ranking and prioritizing of the causes and their actions within the project.It is notadvised to compare/rank actions between projects from separate FMEAs unless the teams followed the same ranking criteria scales, and did so very consistently.

Recommended Corrective/Preventive Action* The Recommended Corrective/Preventive Actions for the root causes of the prioritized failure modes should be described specifically andbriefly.* The intent of any recommended action is to reduce the severity, occurrence, and then detection rankings.* It should be stated in a positive way, e.g., Increase spring wire diameter by .001 in. or Conduct trials to identify the optimum annealing method or Develop a more robust engagement tab design.

To reduce a severity ranking, a design revision will be required.A design revision will also be required to reduce an occurrence rating, by removing or controlling one or more of the failure modes causes.Increasing DV actions only is not as desirable since it does not address the severity or occurrence of the failure mode.The solutions should either be based on data, or they should call for a trial or investigation to generate the necessary data for determining the best solution(s) to solve the root causes.One of the risks in the FMEA process is for the team to generate Corrective/Preventive Actions that are not proven with observed data.The Actions should end up calling for revised tolerances, specifications, etc.Responsibility Information for the Corrective/Preventive Action The Recommended Corrective/Preventive Actions should eachshow the person or department responsible for resolution, and the EstimatedCompletion Date. The action items should be reported on and monitored. The actual actions taken later are described.The severity, occurrence, and detection criteria are re-evaluated after the actions are taken, then a new RPN is then calculated.The responsible party should usually be someone on the project team, even though the person(s) actually doing the tasks may be someone else.DFMEA Quiz1.In the DFMEA process, the potential or known failure modes areidentified, then the causes are identified, and then the effects are identified.Answer:Incorrect. The effects are identified before the causes in the DFMEA process.2. A DFMEA would normally contain the causes that occur in production but are due to the design and causes that are due to errors or flaws in aproduction process that was called out by the designer.Answer:Incorrect. A DFMEA should not include causes that are due to execution errors or flaws in a production process (unless the product cannot be economically/reasonably manufactured by the process called out by the designer).3. It is a good idea to start the PFMEA before the DFMEA is finished.Answer: correct4. The following would be good examples of a part function for a light bulb no out-of-box failures and provide bright light.Answer:Incorrect. Better examples would be to provide 99.7% defect-free turn-on reliability, and to provide 75 watts of light for 450 hours. These are more exact, and clearer to the DFMEA team.5. Asking What does the customer experience as a result of the failure mode oforWill the component or assembly be inoperative,intermittently operative, noisy, not durable, etc.? are examples of questions asked in the step in which the effects are determined.Answer: Correct

6. Asking what could happen to cause a loss of function, such asHow could this part fail?, orCould it break, deform, wear, corrode, bind, leak, short, open, etc.? are examples of questions asked in the step in which the causes are determined.Answer: Incorrect. These questions should be asked in the step in which failure modes are identified.7. When describing the effects, it is important to use the customers terminology.Answer: Incorrect. Use the perspective of the external or internal customer, but it isnt necessary to use the customers terminology here.8. Do not consider the likelihood that the defect will occur in scoring the severity rating criterion.Answer: Correct.9. In the DFMEA process, the potential or known failure modes are identified, then the causes are identified, and then the effects are identified.Answer: Incorrect. The effects are identified before the causes in the DFMEA process.10.Generally, to reduce the probability of the failure mode happening, better design verifications/controls will be required.Answer: Incorrect. Generally, to reduce the probability of the failure mode happening, a design change will be required.11.For the Occurrence rating, a 1 reflects a remote possibility of it happening and a 10 indicates a high probability of the cause and its failure occurring in major proportions.Answer: Correct12. If none of failure mode causes are rated high, e.g., none have RPN scores over 500 or 600, then there is a good chance you missed some key failure modes or causes.Answer: Incorrect.The absolute RPN scores do not mean anything.The relative ranking provides prioritization of the causes preventive/corrective action.