Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
DESIGN AND TECHNO-ECONOMIC ANALYSIS
OF A GRID-CONNECTED
PHOTOVOLTAIC POWER SYSTEM
AT
FIJI NATIONAL UNIVERSITY SAMABULA CAMPUS
by
Ravinesh Tendra Nand
A supervised research project submitted in partial fulfillment of the requirements for
the degree of Master of Science in Physics
Copyright©2010 by Ravinesh Tendra Nand
Division of Physics
School of Engineering and Physics
Faculty of Science, Technology and Environment
The University of the South Pacific
Suva, Fiji Islands
November, 2010
i
ii
DEDICATION
THIS WORK IS DEDICATED TO MY FATHER LATE MR SHANTI NAND WHO
ALWAYS PROVIDED THE RESOURCES FOR MY EDUCATION AND ALWAYS
ENCOURAGED AND INSPIRED ME AS A CHILD.
iii
ACKNOWLEDGEMENTS
I express my gratitude first and foremost to God Almighty for helping me throughout
this project.
My profound thanks go to my mother Mrs. Deo Mati Nand and my siblings for their
unwavering support and encouragement during the duration of my studies.
I thank my supervisor Dr. Atul Raturi, Head of School of Engineering and Physics
for his professional guidance and support throughout the duration of this study. I am
also indebted to Rajneel Prasad and the numerous staff at the University of the South
Pacific Physics department for assisting in collecting the solar data and giving timely
advice and suggestions. I also acknowledge with thanks the financial help given to
me in the preparation of this thesis by the University of the South Pacific.
My thanks also go to Mr Amit Singh of CBS Power Solutions for providing
quotations and other valuable information about the available solar technology. I also
acknowledge Mr Ravendra Chand for his advice on electrical wiring aspects of the
power system.
I appreciate the words of encouragement from my brother Rohitendra Nand, uncle
Satya Nand and my colleagues at the Fiji National University.
iv
ABSTRACT
Grid-connected photovoltaic systems are becoming attractive due to the continuing
decrease in the cost of PV modules and through the possibilities of integration of
renewable resources generated power into the traditional power systems. The heavy
dependence on expensive imported diesel for power generation in the Pacific Island
Countries (PICs) makes renewable energy based systems more viable.
For large buildings where electricity demand is high and the lighting and other energy
needs are provided mainly by fossil fuel based grid delivered electricity, grid-tied
building-integrated photovoltaics should be examined carefully to assess their
technical and economic potential.
This research was undertaken to design and carry out a techno-economic analysis of a
5 kWp grid-tied PV system for the C block of the Fiji National University Samabula
campus. The system design was done using the software PVSYST and then techno-
economic analysis was carried out using HOMER. The net present cost of energy was
estimated to be $0.69/kWh. The PV array production would meet 31 % of the
electricity demand at C block at FNU. On a yearly basis, this system could feed in
1347 kWh of electricity, thus saving $469 on electricity bill at current rates.
This project also outlines the many aspects of grid connected solar power system and
the benefits of using PV generated electricity over conventional forms of electricity
generation. However, economically it is not a viable option at current electricity
tariffs.
v
SYMBOLS
iA Beam radiation transmittance
� Absorptance
p� Temperature coefficient of power
β Slope of surface
f Horizon brightening factor
pvf PV derating factor
� Solar declination angle
oG Extraterrestrial solar radiation incident on a horizontal surface
oG Average extraterrestrial solar radiation incident on a horizontal
surface
TG Global radiation incident on the PV array surface
NOCTTG , Solar radiation at defined NOCT
γ Azimuth of surface
c� Cell efficiency
mp� Maximum power point efficiency
STCmp,� Maximum power point efficiency under standard test
conditions
θ Angle of Incidence
Z� Zenith angle
RP Rated power
g� Ground reflectance
� Solar transmittance of PV cover surface
aT Ambient temperature
NOCTaT , Ambient temperature at defined NOCT
cT Cell temperature
ct Civil time in hours
NOCTcT , Cell temperature at defined NOCT
vi
STCcT , Cell temperature at standard test conditions
STCcT , Cell temperature at standard test conditions
LU Coefficient of heat transfer to the surroundings
� Hour angle
Longitude
vii
ABBREVIATIONS
AC Alternating Current
BOS Balance of System
CDM Clean Development Mechanism
CER Certified Emission Reductions
CO2 Carbon dioxide
COE Cost of Energy
CRF Capital Recovery Factor
DC Direct Current
E Equation of time
EIA Energy Information Administration
eV Electron Volt
EVA Ethylene Vinyl Acetate
FCC Fiji Commerce Commission
FCR Fixed Charge Rate
FEA Fiji Electricity Authority
FiTs Feed-in-Tariffs
Gb Direct or beam radiation
Gd Diffuse radiation
GDP Gross Domestic Product
GMT Greenwich Mean Time
Gn Extraterrestrial normal radiation
Gsc Solar constant
GWh Giga Watt hour
GWP Global Warming Potential
HOMER Hybrid Optimization model for Electric Renewables
IEA-PVPS International Energy Agency’s Photovoltaic power systems
IGBT Insulated Gate Bipolar Transistor
IPCC Intergovernmental Panel on Climate Change
IPP Independent Power Producers
KT Clearness index
kW kilo Watt
viii
kWh kilo Watt hour
MOSFET Metal Oxide Semiconductor Field Effect Transistor
MPPT Maximum Power Point Tracker
MW Mega Watt
MWh Mega Watt hour
n Day of a year
NOCT Nominal Operating Cell Temperature
NOx Nitrous Oxides
NPC Net Present Cost
NPV Net Present Value
O&M Operation and Maintenance
PICs Pacific Island Countries
Pnom Nominal power
PV Photovoltaic
PVSYST Software for photovoltaic systems
SFF Sinking Fund Factor
STC Standard Test Conditions
UV Ultraviolet
V Voltage
Vmpp Maximum power point voltage
Wp Peak Watts
Zc Time zone in hours East of Greenwich Mean Time
ix
TABLE OF CONTENTS PAGE
Declaration i
Dedication ii
Acknowledgements iii
Abstract iv
Symbols v
Abbreviations vii
List of tables xii
List of figures xiii
CHAPTER 1 INTRODUCTION
1.1 Research background 1
1.2 Energy Needs of Fiji 2
1.3 Electricity Consumption in Fiji 5
1.4 Objectives 6
1.5 Outline of Thesis 7
CHAPTER 2 LITERATURE REVIEW
2.1 Global Solar PV Trends 8
2.2 Grid Connected PV systems in the Pacific 9
2.3 Roof Mounted Grid Connected PV systems 10
2.4 Carbon Emissions and Climate Change 11
2.5 Sustainable Energy Development 12
2.6 Solar Energy Principles 13
2.6.1 Solar Radiation at top of the Earth’s atmosphere 16
2.6.2 Solar Radiation at the bottom of the Earth’s atmosphere 16
2.6.3 Global Radiation incident on PV 17
2.6.4 PV Operation Principle 18
2.6.5 PV array power output 19
2.6.6 PV cell Temperature 20
2.6.7 Economic Analysis 21
CHAPTER 3 METHODOLOGY
3.1 Solar Resource Data 24
3.2 Software used for the project 25
x
3.2.1 Software for Photovoltaic Systems (PVSYST) 25
3.2.2 Hybrid Optimization Model for Electric Renewables (HOMER) 26
3.3 Design of PV System 27
3.3.1 Preliminary Design 27
3.2.2 Project Design Strategy 28
3.3.2.1 Selection of project site 28
3.3.2.2 Selection of Inverter 28
3.2.2.3 Selection of PV module 29
3.4 Array Sizing 30
3.5 HOMER Techno-Economic Analysis method 31
3.6 Economic Analysis methods 33
CHAPTER 4 RESULTS
4.1 PV system results 35
4.2 HOMER Techno-Economic Results 41
4.3 Inverter Output 47
CHAPTER 5 ANALYSIS
5.1 PV system analysis 49
5.2 PV Array sizing 50
5.3 Economic Analysis 52
5.4 Simple Payback Period Analysis 56
5.5 Cost of Energy Analysis 58
5.6 Life Cycle Cost (LCC) Analysis 59
CHAPTER 6 SYSTEM WIRING
6.1 Introduction 62
6.2 Wiring layout of PV system components 62
6.3 Cable Sizing 64
6.3.1 Cable sizing for PV array series connection 64
6.3.2 Cable sizing from DC Busbar to Inverter 66
6.3.3 Cable sizing from Inverter to main distribution panel 66
6.3.4 Cable selection for wiring 67
6.4 Sizing of circuit breakers 68
6.4.1 Sizing circuit protection between PV array and Inverter 68
6.4.2 Sizing circuit protection between Inverter and Grid 69
6.4.3 AC Isolation/Disconnect 69
xi
6.4.4 Earth and Lightning Protection 70
CHAPTER 7 DISCUSSION
7.1 Introduction 71
7.2 HOMER Optimization 71
7.3 HOMER Simulations 73
7.4 Selection of PV modules and Inverter 74
7.5 Outline of Inverter technology 75
7.6 Incentives and Subsidies for PV 76
7.7 Issues with Feed-in Tariffs 78
7.8 Climate Change Mitigation 79
CHAPTER 8 CONCLUSION and RECOMMENDATIONS
8.1 Conclusions 81
8.2 Recommendations 82
BIBLIOGRAPHY 83
APPENDIX 88
xii
LIST OF TABLES
PAGE
Table 1.1 Electricity Generation in Fiji excluding IPPs 3
Table 1 .2 Electricity Generation and Projections 4
Table 2.1 Grid connected PV capacity 9
Table 3.1 Recorded solar data 24
Table 3.2 PVSYST PV array designs 30
Table 3.3 HOMER input details 32
Table 4.1 HOMER Techno-Economic results 43
Table 4.2 Net present costs (NPC) for 5 kW PV and 3 kW Inverter system 43
Table 4.3 Net present costs for 5 kW PV and 5 kW Inverter system 44
Table 4.4 Annualized costs for 5 kW PV and 5 kW Inverter system 44
Table 4.5 Annualized costs for 5 kW PV and 3 kW Inverter system 45
Table 4.6 Monthly electricity budget for 5 kW PV and 3 kW Inverter 45
Table 4.7 Monthly electricity budget for 5 kW PV and 5 kW Inverter 46
Table 5.1 Comparison of 5 kW PV system with 3 kW and 5 kW inverter 52
Table 5.2 Comparison of nominal and discounted cash flows of system I
and system II 53
Table 6.1 Copper cable characteristics- Dicksmith 65
Table 6.2 Copper cable characteristics- Olex 66
Table 7.1 Net Present Cost of electricity 72
xiii
LIST OF FIGURES
PAGE
Figure 1.1 Electricity consumption trend 5
Figure 1.2 Aerial view of the project site 7
Figure 2.1 PV installations in IEA member countries 8
Figure 2.2 Carbon dioxide emissions from fossil fuel
consumption in Fiji 11
Figure 2.3 Earth revolving around the sun 14
Figure 2.4 Schematic of a solar cell 18
Figure 3.1 Efficiency graph of Energrid Inverter 29
Figure 3.2 PVSYST design of 9 x 3 PV array 30
Figure 3.3 PVSYST design for 10 x 3 PV array 31
Figure 3.4 HOMER schematic of grid connected PV system 33
Figure 4.1 Graph showing the average daily radiation data 35
Figure 4.2 Solar paths at FNU - Samabula. 35
Figure 4.3 Graph showing the load profile for a weekday 36
Figure 4.4 Graph showing the load profile for weekend 36
Figure 4.5 Graph showing the average monthly load profile 37
Figure 4.6 I-V curve of Conergy, P 180M 37
Figure 4.7 Efficiency vs. Cell temperature graph of Conergy 180M 38
Figure 4.8 PVSYST design of 5 kW PV system 38
Figure 4.9 Graph showing the average electricity
generation and grid purchases 39
Figure 4.10 HOMER graph showing Global solar radiation vs. PV power 40
Figure 4.11 HOMER optimization results after sensitivity analysis 42
Figure 4.12 Graph showing the 5 kW Inverter output power 47
Figure 4.13 Graph showing the power output of 3 kW inverter 48
Figure 5.1 PV Array sizing 50
Figure 5.2 Summing the voltage and current of each PV module 51
Figure 5.3 Graph comparing nominal and discounted cash
flows of system I and system II 54
Figure 5.4 Graph comparing PV system II having 5 kW
Inverter with system I using 3 kW Inverter 55
xiv
Figure 5.5 Graph showing net present cost summary by components 55
Figure 5.6 Graph showing net present cost by cost type 56
Figure 6.1 Wiring layout of grid connected PV components 62
Figure 6.2 Wiring layout of PV modules and the inverter 63
Figure 6.3 Block diagram of grid connected PV system 63
Figure 6.4 Diagram of 5A ATC blade fuse and holder 68
Figure 6.5 Wiring diagram for the solar panels to the inverter 69
1
CHAPTER 1 INTRODUCTION 1.1 Research Background
Electricity generation is one issue that continues to occupy the minds of many
researchers, policy makers, planners and governments. Considering the depleting
petroleum resources and the costs involved, it is necessary for any country to
diversify its sources of energy and at the same time lower the carbon dioxide content
of electricity generation.
Electricity can be generated from various energy sources which include hydro,
nuclear, wind, solar, biomass, wave, tidal, geothermal and thermal. The different
sources of electrical energy can be grouped into two main categories; renewable and
non-renewable. Renewable energy is infinite and naturally regenerative while non-
renewable energy sources are unrecoverable once depleted or replaced very slowly
through natural processes. The choice of a particular source of energy depends on a
number of factors such as; availability of resources, cost of generation and
environmental effects.
With the global CO2 emissions rising at an exponential rate the world today is facing
twin energy related threats. Firstly, that of environmental harm caused by consuming
too much of non-renewable fuels and secondly that of not having adequate and
secure supplies of energy at affordable prices. While the use of renewable energy
helps mitigate effects of climate changes by stabilizing green house gas (GHG)
concentrations, its use is crucial for the sustainable development of any country.
Solar photovoltaic (PV) energy is the conversion of the solar energy into direct
current (DC) electricity through a phenomenon called the photovoltaic effect.
Photovoltaic energy utilization can be divided into three broad categories of
standalone systems, grid connected systems and PV pumping systems. Unlike PV
pumping systems, standalone PV systems usually have battery backup. The
utilization of solar PV energy offers many benefits over other energy sources
including securing energy supplies in both the long term and short term.
2
1.2 Energy Needs of Fiji
A vital part of economic and social development for any country is the availability of
energy which is associated with several aspects of daily life. Of the different forms of
energy, electricity is the high-quality secondary energy and an important material
base of industrial production and people’s life.
The Fiji Islands Bureau of Statistics-Key Statistics report 2010 reports that since
1990, there had been a 12 % increase in total national electricity production. For the
same period, the population growth rate had been 7 % and the Gross Domestic
Product (GDP) growth rate had ranged between -2.7 % and 8.7 %.
The energy sector in Fiji has undergone significant changes with total electricity
consumption growing from 202.8 GWh in 1980 to 715.3 GWh in 2009, an increase
of 252.9%. With this change, our dependency on non renewable energy sources has
now reached an unprecedented level. This dependency is making our country
vulnerable to external shocks. Fiji is losing substantial amount of money in importing
fossil fuels (Reddy, 2010).
According to the Fiji Census of population and housing report, 2008 the increased
demand for electricity in Fiji is due to factors such as expanding economy with the
growing population, urbanisation and introduction of modern and new electrical
appliances. Fiji’s population was 588,068 in 1976, 715,375 in 1986, 775, 077 in 1996
and 837, 271 in 2007. It is projected to reach one million just after 2030.
Fiji’s present renewable energy based power plants operated by the Fiji Electricity
Authority are Wailoa hydro, Wainiqeu hydro, Wainikasau hydro, Nagado hydro and
Butoni wind farm. In addition to these, FEA operates many thermal generators
especially to power the outer islands and also to meet the power demands during
times of low outputs from the hydro power plants.
3
Table 1.1 Electricity Generation (MWh) excluding IPPs (FEA Annual Report 2009, pg 60)
Year Hydro Thermal Wind Solar Total FEA
generation
% Hydro
contribution
% Thermal
contribution
1999 449,850 78,611 - 9 528,470 85 15
2000 414,383 109,511 - 11 523,905 79 21
2001 462,957 106,517 - 14 569,488 81 19
2002 450,198 153,501 - 10 603,709 75 25
2003 343,729 284,621 - 9 628,359 55 45
2004 367,357 282,189 - 6 649,552 57 43
2005 338,739 346,032 - 2 684,773 49 51
2006 341,255 394,363 - 4 735,622 46 54
2007 508,486 255,989 3,351 1 767,827 66 33
2008 495,090 269,745 4,604 0 769,439 64 35
2009 460,192 309,924 7,211 0 777,327 59 40
In the last decade while the population grew by slightly over 62000 (8%), the total
FEA generation had increased by 147%. For the same period, as shown in table 1.1,
thermal based generation increased by almost four folds while the total electricity
generated from renewable based resources dominated by hydro had not experienced
any significant increases.
Since 2007, combined contribution of wind and solar had remained constant at 1 %
of the total electricity generation although wind generation continued to increase
after its commissioning in 2007. But electricity generation from the only grid
connected PV system kept decreasing from 2001 to 2007, except 2006 and then
stopped since 2008.
The increasing demand and the delays in harnessing additional renewable energy
resources into Fiji’s electricity sector, has resulted in significant increases in fossil
fuel imports for electricity generation. For 60:40 ratio of renewable sources to fossil
fuel electricity generation, FEA spends around $70 to $90 million in fuel bill in a
year (Natuva, Fiji Sun 12/11/2010).
4
Table 1.2 Electricity Generation and Projections (GWh), 2008 – 2015
Year 2008 2009 2010 2011 2012 2013 2014 2015 Total Generation required made of: 774.6 785.6 820.4 898.9 968.7 1035.1 1096.8 1150.5
Wailoa (FEA) 400.0 400.0 360.0 400.0 400.0 400.0 400.0 400.0 Nagado (FEA) 18.0 18.0 18.0 18.0 18.0 18.0 18.0 18.0
Wainikasau (FEA) 18.0 18.0 18.0 18.0 18.0 18.0 18.0 18.0
Waniqeu (FEA) 2.2 2.2 2.2 2.2 2.2 2.2 2.2 2.2 FSC Lautoka
(IPP) 15.0 15.0 15.0 15.0 15.0 40.0 40.0 40.0 FSC Labasa (IPP) 7.0 7.0 7.0 7.0 15.8 15.8 15.8 15.8
Tropik Drasa (IPP) 0.0 0.0 24.0 72.0 72.0 72.0 72.0 72.0
Nadarivatu (FEA) 0.0 0.0 0.0 0.0 101.0 101.0 101.0 101.0 Vuda Biomass
(IPP) 0.0 0.0 0.0 0.0 71.0 141.9 141.9 141.9 Wainisavulevu
(FEA) 0.0 0.0 0.0 0.0 7.0 7.0 7.0 7.0 Labasa Biomass
(IPP) 0.0 0.0 0.0 0.0 15.8 15.8 31.5 31.5 Savusavu
Geotherm (IPP) 0.0 0.0 0.0 0.0 0.0 15.8 31.5 31.5 Wailoa
Downstream (FEA) 0.0 0.0 0.0 0.0 0.0 0.0 35.6 35.6
Qaliwana (FEA) 0.0 0.0 0.0 0.0 0.0 0.0 43.8 43.8 FSC Rarawai
(IPP) 0.0 0.0 0.0 0.0 0.0 0.0 0.0 87.6 VLIS Biomass
(IPP) 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Diesel & HFO
(FEA) 314.4 325.4 376.2 366.7 233.1 187.7 138.4 104.6
Renewable Energy - - 444.2 532.2 735.7 847.4 958.3 1045.9
Non Renewable Energy 376.2 366.7 233.1 187.7 138.4 104.6 % of Non
Renewable Energy 37.0 43.0 45.9 40.8 24.1 18.1 12.6 9.1
% of Renewable Energy 63.0 57.0 54.1 59.2 75.9 81.9 87.4 90.9
(Source: Fiji Commerce Commission Press release 21/10/2010)
The data in table 1.2 indicates that with the entry of independent Power Producers
(IPPs) at the planned times, FEA could reach its target of using 90 % renewable
5
sources for electricity generation by 2015. The magnitude of electricity generation
and the entry of IPPs into the energy market are expected to increase strongly given
the revised electricity tariff structure by the Fiji Commerce Commission (FCC)
setting minimum tariff for IPPs at $0.27/kWh. The upward revision of electricity
tariff from 8 – 13 cents before June 2010 to $0.23/kWh thereafter and then setting
the minimum rate of $0.27/kWh applicable from 21/10/2010 provides a good
stimulus for the growth in the renewable energy sector in Fiji. At the same time the
FCC is encouraging FEA to consider higher tariff rates for investors in the high cost
areas such as the outer islands.
1.3 Electricity Consumption in Fiji
Fiji’s electricity consumption is mainly divided into three main sectors namely
Domestic/ Residential
Commercial
Industrial
Figure 1.1 Electricity consumption trend (source: FEA annual report 2009)
The graph shows an overall increase in electricity consumption of all three sectors
but the industrial sector consumption had been the greatest. In 2003 the electricity
consumption declined in all sectors but then increased steadily until 2006 and
thereafter there has been a gradual increase in consumption. In 2009 the industrial
6
sector consumed almost three times the amount of electricity consumed by the
residential sector and about 1.5 times the commercial sector.
The Fiji Department of Energy (DOE) together with FEA is undertaking demand
side management by advising consumers to become more energy efficient by
providing; technical advice, energy saving tips and billing data. Energy audits are
also carried out providing in-depth knowledge of energy consumption and
recommendations for reducing the electricity bills.
1.4 Objectives
This study is undertaken to investigate the technical, economic and environmental
suitability of installing a grid connected PV system at the C–Block at Fiji National
University Samabula campus, Suva, Fiji Islands. The C-Block has 6 classrooms, 3
science laboratories, and 4 staff rooms. The current electricity supply is from the
main power lines of the Fiji Electricity Authority (FEA) but there is also a backup
diesel generator for times of power shutdown by the FEA. The electrical appliances
used are one hundred sixty 36W fluorescent lights, forty 51W electric fans, twenty
five 40W computers, six 1000W air conditioners and some laboratory apparatus as
per use.
The specific objectives of the research are to:
i. Design a grid connected PV system using the software PVSYST (version
5.21).
ii. Carry out a techno-economic analysis of the PV system designed using the
software HOMER (version 2.68).
iii. Determine the cost of energy using different economic analysis methods and
compare the costs of electricity.
iv. Outline wiring and installation procedures for the PV system designed.
v. Undertake an environmental comparative analysis between grid connected
PV and thermal based electricity generation.
vi. Identify the various policies, incentives and initiatives for integration of
renewable energy into the existing national electricity grid in Fiji.
7
Figure 1.2 Aerial view of the project site (source: Google Earth)
1.5 Outline of Thesis
A brief structure of this thesis is as follows:
(a) Chapter 1 presents the research background, energy needs of Fiji, electricity
consumption trend in different sectors in Fiji and the research objectives.
(b) Chapter 2 is the review of literature and it presents the, global status of grid
connected PV systems, PV systems in the pacific, carbon emissions scenario
and sustainable development energy plans for Fiji. Some mathematical
formulas used for energy calculations and economic analysis are also
discussed.
(c) Chapter 3 presents the methodology adopted for the research. It includes
methods of solar data collection, selection of inverter and PV modules,
PVSYST preliminary and project design of grid connected PV system and
the use of HOMER for techno-economic analysis.
(d) The results of the research are presented in chapter 4.
(e) Chapter 5 presents the analysis of the results.
(f) Chapter 6 is about the wiring of the PV system. It presents type and size of
cables to be used for connecting different components of the system and also
includes sizing of fuses and circuit breakers.
(g) Chapter 7 is a general discussion of the research. It explores scenarios at
different electricity tariffs, outlines the inverter technology, benefits of using
solar energy and the various incentives and subsidies relevant to PV systems.
(h) Finally the conclusions and suggestions for future work are presented in
Chapter 8.
8
CHAPTER 2 LITERATURE REVIEW 2.1 Global Solar PV Trends
The use of photovoltaics technology for electricity generation differs substantially
from country to country. This is due to different energy policies and public support
programmes for renewable energy projects and especially photovoltaics, as well as
the varying grades of liberalization of domestic electricity markets. According to the
European Union PV Status report, (2009), between 2001 and 2008, installations of
PV systems in the European Union increased more than ten times and reached 9.5
GW cumulative installed capacity at the end of 2008. In 2009 alone, 4590 MW of
new PV capacity was constructed which were majority grid-tied.
Figure 2.1 PV installations in IEA member countries (IEA PVPS status
report, 2009)
These figures are indicative of the progress in the photovoltaic industry in terms of
research and development, support measures for PV projects by governments and the
much wider agreement and acceptance by people that renewable energy is part of the
solution for sustainable development.
Foster, (2008) states that “for the past decade photovoltaics have enjoyed an average
of 30 % growth across the global spectrum with certain hot spots in Europe, the
United States and Japan.” This has been mainly due to prudent government policies,
the fluctuations in fossil fuel prices and decrease in availability, and also
enhancements in the technology due to research and development. Thus, the market
development of solar energy is strongly dependent on the policy, technology
development and transfer, and economics of solar energy products.
Tota
lIns
talle
dPV
Pow
er
9
2.2 Grid Connected PV systems in the Pacific
While small PV stand-alone systems are common in the Pacific Islands, grid-
connected PV power systems are very few. The main determinant factor for
implementation of grid connected PV power projects in the Pacific Islands is the lack
of financial support for the energy sector. High capital costs of PV technologies
compared with non-renewable based technologies often limit investments in PV
systems unless funded by donor agencies e.g. the European Union Development
Fund multi-country initiative ACP-EU (REP–5) five Pacific Island countries (PICs)
has resulted in the installation of over 300 kWp of PV systems. Through the REP 5
programme, Niue, Nauru, Federated States of Micronesia (FSM) and Palau have grid
connected PV systems except Marshall Islands where off grid PV systems range
from 6 to 13 kWp for a total of 55.6 kWp.
Table 2.1 Grid connected PV capacity
(Source: www.rep5.eu/Project_Countries)
Similarly through the ‘Tuvalu e8 solar power project’ funded by the Italian
government, a total of 86 kWp of grid connected PV systems were installed in
Tuvalu; 40 kWp at Funafuti soccer stadium roof and the surrounding area and 46 kWp
system at Vaitapu Secondary school. Tokelau also has a 10 kWp PV system integrated
to the diesel supplied grid at Fakaofo which was jointly funded by UNESCO, UNDP
and the governments of New Zealand and France. Likewise, Fiji has a 10 kWp grid
connected PV project at Navutu, Lautoka funded by the Australian government and a
Japanese government funded hybrid mini-grid, 37.4 kWp solar PV and 536 kWp wind
turbines at Nabouwalu. However, due to a variety of reasons both the PV projects in
Fiji are currently non-functional. Overall, all PIC’s has shown strong interest in
Country Total cumulative installed
capacity (kW)
Niue 52
Federated States of Micronesia 52.5
Nauru 40
Palau 100
10
shifting their energy policies and energy sector initiatives towards the promotion of
renewable energy resources and diversification of the electricity production mix.
2.3 Roof Mounted Grid Connected PV systems
Solar photovoltaic systems mounted on buildings are becoming increasingly popular
as prices decrease and the installation infrastructure becomes increasingly mature.
The integration of large scale renewable energy projects into the main grid can
therefore bring down the cost of electricity and provide some financial relief to the
consumers.
Natano (2009) argues that as the cost of solar power technology, which has not
reached an optimal competitive level yet, continues to decrease over the next decade,
the spread of grid-connected power systems holds the potential to improving local
communities’ access to clean and reliable energy services. This in turn could
considerably contribute to improving the standards of living in the long run.
Siegfried, (2009) stresses that in the long term, an ecologically sustainable energy
supply can only be guaranteed by the integration of renewable resources. The
objective of a forward looking energy supply policy must therefore be to utilize the
existing grid as well as possible for the supply of clean, cheap and reliable power.
The traditional concepts of centralized power stations and very long distance
transmission of energy coupled with energy losses and high costs associated with
transmission lines needs to be reconsidered. Masters (2004), “there are compelling
reasons to believe that the traditional system of large, central power stations
connected to their customers by hundreds or thousands of miles of transmission lines
will likely need to be supplemented and eventually replaced with cleaner, smaller
plants located closer to their loads. Not only do such generation systems reduce
transmission losses and costs, but the potential to capture and utilize waste heat on
site greatly increases their overall efficiency and economic advantages.” Building
integrated generation systems offer increased reliability and reduced threat of
massive and widespread power failures.
11
Thus, there are huge opportunities for solar photovoltaic power systems especially
grid-tied PV systems but people need to overcome barriers such as perceptions,
regulatory frameworks, limitations of the existing transmission and distribution
structures and the biggest barrier of high PV capital cost.
2.4 Carbon Emissions and Climate Change
Increasing amounts of carbon emissions to the atmosphere and the changes in
climate, arising in great part from energy-producing processes, demand the reduction
of ever-increasing environmentally damaging emissions. The generation of
electricity, particularly by the use of renewable energy offers considerable scope for
the reduction of such emissions. Boxwell, (2009) emphasizes that in the context of
climate change, the immense potentials of solar and wind energy, in addition to the
world wide use of hydro, are of great importance.
Figure 2.2 Carbon dioxide emissions from fossil fuel consumption in Fiji.
(Source: Energy Information Administration (EIA) CO2 scenario, US DOE)
Figure 2.2 shows that between 1980 and 1990, on average one million metric tonnes
of CO2 per year was emitted to the atmosphere. However, the emissions had
drastically increased since 1998. In 2004 the CO2 emissions were slightly over 2.5
million metric tonnes compared with 1 million metric tonne in 1994. Emissions
declined slightly from 2004 to 2006 but then continued to increase with 2008 being
the year of highest carbon emissions in the past 28 years. The carbon emissions do
12
not only harm the environment but the use of fossil fuel results in great import bills
for Fiji, adding external pressure on our economy.
As instability in the world's oil producing countries increases, it is becoming ever
more important for nations to reduce reliance on fossil fuels. Of the sustainable
energy technologies that currently exist, solar power has the most potential for
growth in the long term, and if it is adopted at considerable levels, solar power could
have significant impact on the reduction of CO2 emissions and increased energy
security (Bradford, 2006).
Foster, (2008), “as climate change is emerging as a manageable and predictable
global problem, several industries are shifting the focus of their business to include
the reduction of greenhouse gasses. This is seen in most power generation
technologies, but solar PV systems have shown the most sustained level of growth.
Year over year the photovoltaic industry continues to expand tremendously.”
2.5 Sustainable Energy Development
The bewildering array of new options available today for sustainable energy
production offers great promise, but also an increasingly difficult challenge in
deciding how much to invest in which technologies, how to integrate these
technologies, and how to optimize the overall new energy economy. Our success as a
society, in addressing fundamental issues such as climate change and economic and
environmental sustainability in general, may well depend on our ability to meet this
challenge (Luce et. al, 2008). This suggests that for sustainable energy development,
every country should reduce their carbon footprints and effectively engage all sectors
in low carbon economic growth, while fostering inclusive economic development.
Masters, (2004) shares similar views on sustainable development in Renewable and
Efficient Electric Power Systems. “Engineering for sustainability is an emerging
theme for the twenty-first century and the need for more environmentally benign
electric power systems is a critical part of this new thrust. Renewable energy systems
that take advantage of energy sources that won’t diminish over time and are
13
independent of fluctuations in price and availability will be playing an ever
increasing role in modern power systems”.
For the sustainable development of the Fiji energy sector, the FEA policy in line with
the government policy is that by 2015, 90 % of the total electricity generated in Fiji
should be from renewable resources.
2.6 Solar Energy Principles
The global solar radiation recorded for this project was on a horizontal surface but to
calculate the power output from PV modules, solar radiation incident on the PV
surface should be considered. The Orientation of a PV array can be described using
two important parameters;
Tilt angle or slope (β). This is the angle formed between the panel and the
horizontal surface.
Azimuth (γ). It is the angle measured clockwise from North towards the
projected sunlight path on local horizontal plane. At solar noon, the sun is
directly south in the northern hemisphere and directly north in the southern
hemisphere. At sunrise it corresponds to 900 and 2700 at sunset. Thus for this
project azimuth was taken as 1800 which corresponds to north facing PV
modules.
Angle of Incidence (θ) is the angle between the beam radiation to the surface of the
PV array and the normal to that surface. When the earth revolves around the sun its
axis remains fixed in space at an angle 00 45.23�� away from the normal (figure
2.3) to the plane of revolution. (Twidell and Weir, 2006).
14
Figure 2.3 Earth revolving around the sun.
HOMER uses equation 2.1 to calculate the solar declination angle ( )� , the latitude at
which the sun's rays are perpendicular to the earth's surface at solar noon (Duffie and
Beckman, 1991).
�
���
����
��� �
�365
284360sin45.23 00 n� 2.1
Where; n is the day of a year.
The location of the sun in the sky at any time is described by the hour angle ),(� the
angle through which the earth has rotated since solar noon. Since the earth makes one
revolution in average time interval of 24 hours; ./1524360 0
0
hh�
� �hth s 12150
��� 2.2
Where; st is the solar time in hour. HOMER uses the convention whereby the hour
angle is negative before solar noon, zero at solar noon, and positive after solar noon.
Electrical load data and solar radiation data which are both time dependent are
considered as data in the local standard time or the civil time. However, HOMER
uses equation 2.3 to calculate the solar time for the respective time-dependent datas.
EZh
tt ccs ����/150
2.3
Where:
ct is the civil time in hours corresponding to the midpoint of the time step(h).
is the longitude ( 0 )
15
Zc is the time zone in hours East of Greenwich Mean Time, GMT (h)
E is the equation of time (h)
West longitudes and time zones west of GMT are taken as negative. The equation of
time accounts for the effects of obliquity (the tilt of the earth's axis of rotation
relative to the plane of the ecliptic) and the eccentricity of the earth's orbit. HOMER
calculates the equation of time as follows:
�
���
���
���
BBBB
E2sin04089.02cos014615.0
sin032077.0cos001868.0000075.082.3 2.4
B is given by: � �365
13600 ��
nB
Where: n is the day of a year.
The angle between the incident beam and the PV collector surface i.e. angle of
incidence (θ) (Duffie and Beckman, 1991) is calculated using
���������������������
sinsinsincoscoscossinsincoscoscoscoscoscossincossincossinsincos
�����
2.5
Where: θ is the angle of incidence ( 0 )
� is the slope of the surface ( 0 )
� is the azimuth of the surface ( 0 )
� is the latitude ( 0 )
� is the solar declination ( 0 )
� is the hour angle ( 0 )
The zenith angle � �Z� and the elevation/altitude angle are also important to consider
with the angle of incidence. Zenith angle is the angle formed between the vertical
and the suns ray and is zero when the sun is overhead and 900 when the sun is at the
horizon. Zenith and elevation angle are complementary.
� �elevationZ �� 090� 2.6
16
Using equation 2.5 and taking slope as zero )0( �� for a horizontal surface:
������ sinsincoscoscoscos ��z 2.7
2.6.1 Solar Radiation at top of the Earth’s atmosphere
The solar radiation striking the top of the earth’s atmosphere varies with time
because of the changes in distance between the Earth and the Sun due to the
eccentricity of the earths orbit. At mean distance of the earth from the sun, the solar
radiation striking a surface oriented perpendicular to the sun’s rays is called the solar
constant. It has a value of 1367 W/m2 but fluctuates during a year. Thus to calculate
the extraterrestrial normal radiation (Gn) at the top of the atmosphere equation 2.8 is
used.
���
��� ��
365360cos033.01 nGG scn 2.8
Where: Gsc is the solar constant
n is the day of the year.
The extraterrestrial solar radiation incident )( 0G on a horizontal surface is given by:
znGG �cos0 � 2.9
To calculate the average value of extraterrestrial solar radiation incident )( 0G on a
horizontal surface, equation 2.9 is integrated because HOMER does time step by step
analysis with the solar resource data.
� � � �� �
��� �
��� �����
�����
sinsin180
sinsincoscos12 12120 nGG 2.10
Where; 1� is the hour angle at the beginning of the time step and 2� at the end.
2.6.2 Solar Radiation at the bottom of the Earth’s atmosphere
Solar data for projects are normally collected at a horizontal surface on the ground or
calculated using the clearness index (KT) which is as a ratio of surface radiation )(G
to the extraterrestrial radiation )( 0G . Monthly clearness index values were calculated
in this project.
17
0GGKT � 2.11
Solar data recorded at the earth’s surface usually referred as global solar radiation
(G) has two main components. It is the sum of diffuse (Gd) and direct or beam (Gb)
radiation.
db GGG �� 2.12
However, when calculating the solar radiation incident on an inclined surface, the
effect of the surface inclination on beam and diffuse radiations are considered. Beam
component is affected the most because it is incident from one direction only at a
particular time whereas diffuse radiation is multidirectional. Thus, the diffuse
fraction calculated as a function of the clearness index (Duffie and Beckman, 1991)
follows:
2.13
80.022.08.0;165.0
336.12638.16388.41604.09511.0
22.0;09.00.1432 !
"#
"$
%
&'����
�
� T
T
TTTT
TTd K
KforKKKK
KforK
GG
2.6.3 Global Radiation incident on PV
The global radiation incident on the PV array surface is calculated using the
following equation. 2.14
� � � � ���
��� �
��
���
����
�����
��
��� �
����2cos1
2sin1
2cos11 3 ����
gidbidbT GfAGRAGGG
Where:
g� is the ground reflectance.
zbR
��
coscos
� is the ratio of beam radiation on tilted surface to horizontal surface.
0GGA b
i � is the anisotropy index, a measure of beam radiation transmittance
GGf b� is the horizon brightening factor to account for the majority diffuse
radiation from the horizon in the sky.
18
2.6.4 PV Operation Principle
Photovoltaic is a technology that converts solar energy into electricity. The
individual photovoltaic elements, named cells are made of semiconductor materials.
The choice of semiconductor material for photovoltaic applications depends mainly
on its band gap and absorption coefficient. However, other important factors are
contact resistance, abundance of material, stability of junctions and materials,
toxicity of materials and radiation resistance. The greatest efficiencies for absorption
of solar energy and conversion into electrical energy are for those semiconductors
that have band gap near the infrared region of around 1.5 eV. The most commonly
used semiconductor material is Silicon with band gap of 1.1 eV and absorption
coefficient of 14101 �( cm at room temperature (Zeghbroeck, 2007).
In its pure state, crystalline silicon is a poor conductor at low temperatures, due to the
fact that all of the electrons in the outer orbit are bonded and cannot move freely. To
change this behaviour, pure silicon has to go through a process called ‘doping’. In
this process some “impurities” (eg. As, B) are added to the material (Zweibel, 1990).
Semiconductors are classified as p-type or n-type depending on the type of doping.
When energy applied to the free electrons in the valence band, exceeds the band gap
of the material, the electrons move to the conduction band where they start
conducting electricity. The energy required for this transition of electrons is provided
by sunlight or particles of sunlight known as photons.
Figure 2.4 Schematic of a solar cell (Source: Luque, 2002)
19
Figure 2.4 illustrates the photovoltaic process when a solar cell is exposed to
sunlight. The incident solar energy is absorbed by the electrons in the valence band
and if the solar energy provided by the photons is more than the band gap, the
electrons migrate to the conduction band. The electrons in the excited state are
collected by the n-type semiconductor and driven to an external circuit to generate
electricity. Then through a return circuit using a p-type semiconductor, the electrons
are restored in the lower energy valence band. When the energy provided by the
photons is lower than the band gap, it is absorbed as heat by the solar cells. This
results in rise in cell temperature and thus decreases the efficiency of the electricity
generation process. The voltage at which electrons are delivered to the external
circuit is slightly lower than the band gap and for materials with band gap of around
1 eV, the output per cell is usually in the range of 0.5 – 0.7 V. Thus, multiple cells
are connected together and encapsulated to form a PV module.
2.6.5 PV array power output
Real power output from PV panels is generally lower than their rated power because
in real life applications they hardly operate at standard test conditions. This is called
the derating factor ( pvf ) and it usually ranges from 0.8 to 0.9 for modern PV panels
over their lifetime of 20 to 25 years.
PV power output is also dependent on the cell temperature and the output decreases
with increase in cell temperature. The temperature coefficient of power ( p� ) is
usually around -0.5 % / 0C. Thus, taking the derating factor and the cell temperature
into consideration, the actual power output of PV array is:
� �) *STCccpSTCT
TpvRpv TT
GGfPP ,
,1 �����
����
�� � 2.15
Where:
RP is the rated power of the panel.
cT is the cell temperature.
STCcT , is the cell temperature at standard test conditions
20
p� is the temperature coefficient of power
TG is the global radiation incident on the PV array surface
2.6.6 PV cell Temperature
PV cell temperature is calculated using the energy balance of a PV panel from Duffie
and Beckman (1991), solar energy absorbed equals the sum of electrical output and
the heat loss to the surroundings.
� �acLTcT TTUGG ������ 2.16
Where:
� is the solar transmittance of PV cover surface (%)
� is the absorptance of the PV cover surface (%)
c� is the electrical conversion efficiency of the PV (%)
LU is the coefficient of heat transfer to the surroundings [kW/m2°C]
aT is the ambient temperature [°C]
From equation 2.16, it follows that; ���
��� ����
����
���
����� c
LTac U
GTT 1 2.17
However, PV manufactures usually report the Nominal Operating Cell Temperature
(NOCT) instead of cell temperature. NOCT refers to the surface temperature that a
PV cell would reach if exposed to 800 W/m2 of solar radiation at a surrounding
temperature of 200C, wind speed of 1 m/s and at no load ( c� = 0). Thus, substituting
these values into equation 2.17 yields;
NOCTT
NOCTaNOCTc
L GTT
U ,
,, ��
�� 2.18
Where: NOCTaT , is the ambient temperature at which the NOCT is defined [20°C]
NOCTTG , is the solar radiation at which the NOCT is defined [0.8 kW/m2]
NOCTcT , is the cell temperature at which the NOCT is defined [200C].
Substituting equation 2.18 into 2.17;
21
���
��� ����
����
� ���
���c
NOCTT
NOCTaNOCTcTac G
TTGTT 1
,
,, 2.19
Assuming that majority of the time the PV array operates at its maximum power
point, then cell efficiency is equal to maximum power point efficiency, mpc �� � .
Thus cell temperature ���
����
���
��
����
� ���
���mp
NOCTT
NOCTaNOCTcTac G
TTGTT 1
,
,, 2.20
However, mp� is dependent on cT because efficiency of PV array decreases with
increase in cell temperature. Thus, HOMER uses the following linear relationship:
� �) *STCccSTCmpmp TTp ,, 1 ��� ��� 2.21
Where:
STCmp,� is the maximum power point efficiency under standard test conditions [%]
p� is the temperature coefficient of power [%/ 0C]
STCcT , is the cell temperature under standard test conditions [25 0C]
Substituting 2.21 into 2.20 and solving for cell temperature, cT (K) yields:
� � � �
� � ���
����
����
����
���
�
���
� ���
��
����
���
�
����
����
STCmp
NOCTT
TNOCTaNOCTc
STCcSTCmp
NOCTT
TNOCTaNOCTca
c pG
GTT
pTG
GTTTT
,
,,,
,,
,,,
1
11
2.22
2.6.7 Economic Analysis
The annual interest rate is related to annual inflation rate and the nominal interest
rate and is given by:
ffii
��
�1
'
2.23
22
Where:
i = real interest rate 'i = nominal interest rate or the rate at which loan is secured
f = annual inflation rate
Capital recovery factor (CRF) is used to calculate the present value of a series of
annual cash flows and is given by:
1)1()1(),(��
�� N
N
iiiNiCRF 2.24
Where: i = real interest rate and N = number of years.
The future value of a series of annual payments is calculated using the Sinking Fund
Factor (SFF) and is given by the equation:
1)1(),(
��� Ni
iNiSFF 2.25
Annualized capital cost over the project life time is calculated from the initial capital
cost as follows:
),(, projcapcapa RiCRFCC (� 2.26
Where:
capC is the initial capital cost of a component
),( projRiCRF is the capital recovery factor with real interest rate i , and project
lifetime ., projR
The value of a system component remaining at the end of a project lifetime is called
the salvage value, S and is given by:
���
����
��
comp
remrep R
RCS 2.27
Where:
�repC replacement capital cost of a component
�compR component lifetime.
�remR Remaining life of a component at the end of project lifetime and is given by;
� �repprojcomprem RRRR ��� .
23
The replacement cost duration, repR , is calculated using the equation;
���
����
�(�
comp
projcomrep R
RINTRR . INT is the integer function, returning the integer portion
of a real value.
HOMER calculates the Annualized replacement cost using the equation:
� � � �) *projcomprepreparep RiSFFSRiSFFfCC ,, (�((� 2.28
Where: � �+ � � 0,,/, &� reprepprojrep RRiCRFRiCRFf and 0�repf for 0�repR .
24
CHAPTER 3 METHODOLOGY 3.1 Solar Resource Data
Solar data used for this research was the recorded global horizontal radiation at
Laucala bay area for 2008 and 2009. The research project site is less than 3 km away
from the data collection site and thus the data collected is a fair representation of the
solar data at the project site.
The scaled annual average irradiation was 3.94 kWh/m2/day and the scaled annual
average temperature was 25.8°C. The global meteorological coordinate for the
project site is:
� Latitude: 18.1 degrees South
� Longitude: 178.3 degrees East
� Time zone: GMT +12:00
Month
Clearness
Index
Average Daily
Radiation
(kWh/m2/d)
Average
Temperature
(°C)
January 0.381 4.38 27.1 February 0.448 4.98 27.6
March 0.447 4.56 27.4 April 0.459 4.08 26.8 May 0.326 2.49 24.8 June 0.347 2.43 25.0 July 0.453 3.29 24.4
August 0.402 3.34 25.0 September 0.422 4.07 25.1
October 0.411 4.42 26.0 November 0.388 4.41 26.1 December 0.422 4.88 27.2
Table 3.1 Recorded solar data
(Source: University of the South Pacific Energy Laboratory)
25
3.2 Software used for the project
3.2.1 Software for Photovoltaic Systems (PVSYST)
PVSYST is useful for designing PV systems for applications such as grid connected,
standalone, pumping and DC grid. It has three step design process comprising of a
preliminary system design, project design and tools menu.
The preliminary design offers a basic and quick way to determine PV component
sizes by defining the location for the project and system parameters. In the pre-sizing
process, PVSYST evaluates the monthly production and performances using a few
general system characteristics and provides a rough estimate of the costs of the PV
system. For building integrated grid connected systems, the design is architect
oriented as the input requirements are; available roof area, desired nominal power or
the desired energy yield. Other features like mounting of the solar modules and
ventilation are also considered.
Project design mode, is engineer oriented and offers a large database for PV
components, locations and meteorological sites. However, other meteorological data
can also be used. It has tools for adjusting the orientation of PV modules and the user
only has to choose a PV module, inverter and desired nominal power. PVSYST
provides the number of inverters and possible array layouts. It takes into account the
number of modules in series that would provide the maximum power point voltage
compatible with the inverter and also displays warnings if PV system configuration
is not satisfactory. It also has three dimensional (3-D) feature to analyze effects of
near and far shading on PV modules.
The tools menu of PVSYST has meteorological database for over 330 sites over the
world and also allows user to import meteorological data from other sources such as
Meteonorm, NASA-SSE and RETScreen etc. It holds components data of over 1750
PV modules, 650 inverters and data about many pumps, batteries and regulators. The
tool menu provides many graphical and tabular forms of results under various
conditions and offers features to extensively study the solar resource geometry, PV
array behavior and helps optimize the operating voltage. Thus, PVSYST is used for
detailed technical designs of PV systems.
26
3.2.2 Hybrid Optimization Model for Electric Renewables (HOMER)
HOMER is a micro power optimization model, which simplifies the task of
evaluating designs of both grid-connected and off-grid power systems for a variety
of applications. Homer’s optimization and sensitivity analysis algorithms make it
easier to evaluate many possible system configurations and to identify the most
economical power system (Lilienthal, 2005).
HOMER performs three principal tasks: simulation, optimization, and sensitivity
analysis. In the simulation process, HOMER models the performance of a particular
micro power system configuration for each hour of the year to determine its technical
feasibility and life-cycle cost. In the optimization process, HOMER simulates many
different system configurations in search of the one that satisfies the technical
constraints at the lowest life-cycle cost. In the sensitivity analysis process, HOMER
performs multiple optimizations under a range of input assumptions to gauge the
effects of uncertainty or changes in the model inputs.
Optimization determines the optimal value of the variables over which the system
designer has control such as the mix of components that make up the system and the
size or quantity of each. Sensitivity analysis helps assess the effects of uncertainty or
changes in the variables over which the designer has no control, such as the average
wind speed, average solar radiation or the future fuel price etc.
HOMER models a particular system configuration by performing an hourly time
series simulation of its operation over one year. HOMER steps through the year one
hour at a time, calculating the available renewable power, comparing it to the electric
load, and deciding what to do with surplus renewable power in times of excess, or
how best to generate (or purchase from the grid) additional power in times of deficit.
When it has completed one year’s worth of calculations, HOMER determines
whether the system satisfies the constraints imposed by the user on such quantities as
the fraction of the total electrical demand served, the proportion of power generated
by renewable sources, or the emissions of certain pollutants.
27
HOMER also computes the quantities required to calculate the system’s life-cycle
cost, such as the annual fuel consumption, annual generator operating hours,
expected battery life, or the quantity of power purchased annually from the grid. The
quantity HOMER uses to represent the life-cycle cost of the system is the total net
present cost (NPC). This single value includes all costs and revenues that occur
within the project lifetime, with future cash flows discounted to the present.
The total NPC includes the initial capital cost of the system components, the cost of
any component replacements that occur within the project lifetime, the cost of
maintenance and fuel, and the cost of purchasing power from the grid. Any revenue
from the sale of power to the grid reduces the total NPC.
3.3 Design of PV System
The grid connected PV system was designed using the software for photovoltaic
systems, PVSYST. The software has features of preliminary system design and
project design.
3.3.1 Preliminary Design
PVSYST preliminary design could be done in three different ways using the array
specification features of:
� Active area (m2)
� Annual yield (MWh/y)
� Nominal power (kWp)
Firstly a grid connected PV system was designed using the total available north
facing roof area of approximately 320 m2. A 75 kW PV system was required to cover
the whole roof area but this design was not economically viable as it would have
required huge capital investments.
Therefore, a grid connected PV system was designed by specifying the desired
nominal power as 5 kWp because the daily power demand which was greatest during
28
weekdays was 4.5 kW. This design was based on a standard monocrystalline Silicon
cell technology solar module mounted on tilted roof with free ventilation properties.
The total roof area required for a 5 kW system was 36 m2. Following the preliminary
system design, a 5 kW grid connected PV system was designed using the ‘project
design’ feature of PVSYST.
3.3.2 Project Design Strategy
The meteorological and project site data were first specified under the ‘project
design’ tool of PVSYST. The values used were; 18.10 South latitude, 178.30 East
longitude and site elevation above the sea level as 64 m. PV module orientation was
specified as; fixed tilted plane at 180 from the horizontal and at an azimuth of 1800.
Following that, in the ‘system’ tool of PVSYST, 180Wp 30 V Conergy PV module
and Energrid El 5000 pure sine wave 5 kWp inverter were selected.
3.3.2.1 Selection of Project Site
The building proposed to be used for this project has a north facing gable roof with
pitch angle of 15 degrees, making it suitable for installation of solar panels. The
building is a 3 storey concrete structure and the roofing profile is also quite strong,
capable of withstanding addition weight of the PV modules. The project site (C-
block) is also free of any shading effects from the surrounding structures and plants.
3.3.2.2 Selection of Inverter
A Tenesol manufactured Energrid El 5000 model grid connect inverter was selected
for this project. Its features include; Maximum Power Point (MPP) voltage range of
150 to 450 V, absolute maximum PV voltage of 540 V, nominal MPP voltage of 270
V, nominal AC power of 5 kW, maximum AC power of 5.24 kW, nominal AC current
of 22 A, maximum AC current of 27.2 A, maximum efficiency of 95.6 % and
monophased output on AC grid side at frequency of 50 Hz.
29
P in (DC) [kW]
Figure 3.1 Efficiency curve of Energrid Inverter
(Source: Energrid El 5000 technical data sheet - PVSYST)
The efficiency curve indicates that there is very little decrease in efficiency when the
DC input power decreases from 5 kW to 1 kW making the inverter highly suitable
for periods of both high radiation levels and low radiation levels.
3.3.2.3 Selection of PV module
The PV modules selected were silicon monocrystalline technology based 30 V
Conergy P180M model which has 72 cells in series. Its nominal power at STC is 180
Wp. At reference temperature of 25 0C and reference solar radiation of 1000 W/m2,
the short circuit current is 5.20 A and open circuit voltage is 45 V. The maximum
power point (MPP) voltage is 36 V with MPP current of 5 A.
Basic model parameters include; 900 Ω shunt resistance, 0.134 Ω series resistance
(model), 0.60 Ω series resistance (apparent), 37 nA diode saturation current, 1.30
diode quality factor, voltage temperature coefficient of CmV 0/3.142� and
temperature coefficient for power = C0%/5.0� . Each module dimension is 1580
mm x 808 mm x 45 mm with an area of 1.277 m2 and module mass of 15 kg.
There are 4 by-pass diodes per module with reverse characteristics of -0.7 V diode
direct voltage, quadratic factor of 2/2.3 VmA and absorptivity coefficient for
temperature of 0.9.
30
3.4 Array Sizing
The optimum array configuration was determined using ‘design the array’ feature of
PVSYST which provided the different possibilities of number of modules and strings
and the array power at different operating conditions. After selecting the PV
modules, inverter and specifying other parameters such as orientation of modules
and site solar resource data, a PV array design of 4 parallel strings, each with 7
modules in series, occupying maximum roof area of 36 m2 was obtained (figure 4.8).
The maximum operating power from a 7 x 4 array was 4.6 kW. The maximum power
point voltage of the 7 x 4 PV array at average cell temperature of 20 0C (Vmpp = 268
V) and at the highest possible cell temperature of 60 0C (Vmpp = 227 V) are within
the inverter input voltage range of 150 – 450 V.
Figure 3.2 PVSYST design of 9 x 3 PV array.
Other possible configurations of the PV array which had between 6 and 10 modules
in series was modeled in PVSYST and the maximum power point voltage and
maximum operating power of each array design was compared with the 7 x 4 array
design. A 9 x 3 PV array design (figure 3.2) yielded the closest nominal power to a 7
x 4 PV array but the inverter was marginally oversized with respect to PV array.
Modules in series
No. of strings
Vmpp at 20 0C (V)
Vmpp at 60 0C (V)
Pmax (kW) Pnom (kW)
7 4 268 227 4.6 5.0 8 4 307 260 5.3 5.8 9 4 345 292 5.9 6.5 7 3 268 227 3.5 3.8 9 3 345 292 4.4 4.9 10 3 383 324 4.9 5.4
Table 3.2 PVSYST PV array designs
31
Increasing the PV modules in each series string to 8 resulted in the array nominal
power exceeding the desired nominal array power of 5 kW (table 3.2). Similarly,
when each series string had 9 PV modules with 4 in each parallel string, the array
nominal power exceeded the desired nominal array power by 1.5 kW and also the
array ( Pmax = 5.9 kW) was oversized with respect to the inverter.
Figure 3.3 PVSYST design for 10 x 3 PV array. PV array configuration of 10 x 3 yielded maximum operating power of 4.9 kW,
closest of all designs but the nominal power exceeded by 0.4 kW. Moreover, a
technically challenging and difficult task in this particular design was to integrate 3
strings from the PV array with only 2 maximum power point tracking inputs of the
inverter.
After sizing the different PV array configurations and comparing its compatibility
with the inverter, the optimum design achieved for a 5 kW grid connected PV system
had an array of 4 parallel strings with 7 modules in series. Further analysis based on
the technology and economics was carried out using HOMER.
3.5 HOMER Techno-Economic Analysis method
Firstly, a new file was created under HOMER and a schematic was built which
consisted of primary load, photovoltaic panel, converter and AC / DC bus. Then the
hourly load details for each month and the component details such as technology
options, component costs, and the sizes and numbers of each component (Inverter
and solar panels) that HOMER used for simulations was specified.
32
Table 3.3 HOMER input details
Photovoltaic Modules
Slope = 180 Azimuth = 1800
Lifetime = 25 years
O&M cost = $10/y
Capital cost = $12/W
Replacement cost = $10/W
Tracking system: none (fixed)
Derating factor = 90 %
Efficiency at STC = 15 %
Ground reflectance = 20 %
Coefficient of power = -0.5 % /0C
NOCT = 45 0C
Sizes to Consider (kW) = 0.02, 0.03,
0.04, 1.0, 2.0, 3.0, 4.0, 5.0, 6.0, 7.0, 10,
13, 16, 17, 20, 25, 40, 41, 42, 70, 75, 80,
85
Grid No Interconnection cost
Purchase capacity (kW) = 10, 11, 12, 13,
14, 15
Net metering: monthly accumulation
C02 emissions factor = 632 g/kWh
S02 emissions factor = 2.74 g/kWh
NOx emissions factor = 1.34 g/kWh
Power price = $0.3484/kWh
Sellback rate = $0.27/kWh
Demand rate = $0.3484/kWh
Rates applicable – Jan to Dec- All week
00:00-24:00
Sale capacity (kW) = 5, 10, 11, 12, 13,
14, 15, 16, 17, 18, 19, 20, 25, 30, 40, 50,
60, 70, 80, 85
Inverter
O&M cost = $10/y
Lifetime = 15 years
Capital cost = $1700/kW
Replacement cost = $1600/kW
Efficiency at full load = 95.6 %
Rectifier capacity relative to inverter =
100 %
Rectifier efficiency = 97.7 %
Sizes to consider (kW) = 0.05, 0.1, 0.2,
1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 16, 19,
20
Economics
Annual real interest rate = 6 %
Project lifetime = 25 years
System fixed capital cost = $1000
System fixed O&M cost = $200/y
Capacity shortage penalty = $0/kWh
Constraints
Maximum annual capacity shortage =
10, 15, 20 %
Minimum renewable fraction = 30, 40,
50, 60, 70, 80 %
Operating reserve as percentage of solar
power output - 100 %
Operating reserve as percentage of
hourly load - 100 %
33
Figure 3.4 HOMER schematic of grid connected PV system.
The recorded solar resource detail for every hour of the year including two year
monthly average ambient temperatures were input as HOMER data. The average
value of solar irradiation obtained was 3.94 kWh/m2/d. The cost of buying electricity
($0.3484/kWh) from FEA grid and the selling price to the grid ($0.2700/kWh) was
also specified into HOMER. The software used these inputs to simulate different
configurations of system components and generated results that were viewed as a list
of feasible solutions sorted by net present cost. HOMER also displayed simulation
results in tables and graphs that helped compare configurations and evaluate them on
their economic and technical merits.
HOMER simulations were done using the sensitivity variables of; minimum
renewable energy contribution (30, 40, 50, 60, 70 and 80 %), maximum capacity
shortage of (10, 20 and 30 %), grid sale capacity of (5 kW to 75 kW) and finally an
optimum solution was achieved. From the list of feasible solutions, a 5 kW grid
connected PV system contributing 31 % renewable energy to the electric load at a
cost of $0.698/kWh was obtained.
3.6 Economic Analysis methods
A detailed economic analysis of the 5 kW PV system designed was carried out
manually with the following economic analysis methods:
1. Simple payback period analysis
2. Cost of energy analysis
3. Life-cycle costing analysis
34
Hence, the production cost of a unit of electricity ($/kWh) from the solar system
designed was compared with the present cost of a unit of electricity supplied by the
Fiji Electricity Authority.
Energy policies of the Fiji government and various incentives for the integration of
grid connected renewable energy technologies are also studied. Finally, the
environmental impacts of the use of solar power systems were discussed and a report
was compiled as the mini-thesis.
35
CHAPTER 4 RESULTS 4.1 PV system Results
Figure 4.1 Graph showing the average daily radiation data.
The results show that the average daily global horizontal radiation for the first four
months is 4.50 kWh/m2/d, 2.89 kWh/m2/d for the months of May to August and 4.45
kWh/m2/d for the last four months of a year. The average daily irradiation over a year
is 3.94 kWh/m2/d whereas from September to April the average is 4.47 kWh/m2/d.
Overall the available solar resource at this site is not very good as on average the
solar irradiation is below 5 kWh/m2/d.
Figure 4.2 Solar paths at FNU - Samabula.
Aver
age
Dai
ly R
adia
tion
(kW
h/m
2 /d)
36
The solar path diagram is for latitude 18.10 South, longitude 178.30 East at an altitude
of 64 m. From January (path 6) to June (path 1) the Sun moves towards the North and
then back towards path (7) in December. It shows that majority of the time the solar
radiation is received towards the equator, hence the solar modules to be mounted
would be equator facing and tilted at 180 above the horizontal.
Figure 4.3 Graph showing the load profile for a weekday.
The graph shows that there is actually very low demand for power from 7 pm to 7
o’clock in the morning but the demand is about 4.5 kW from 8 am to 7 pm in the
evening. This is because of the normal teaching hours at the Fiji National University
(FNU) campus whereby almost all the six classrooms, the staff room, computers and
the three laboratories are in use. The electric fans would normally be used during the
hot hours of a day (depending on the weather) but its usage is taken as an average
over a day. The power demand is still 4.5 kW from 5 pm to 7 pm because of the
evening classes at the campus. The low demand of about 0.5 kW from 7 pm to 7
o’clock in the morning is because of the exterior lights that are switched on around
the building.
Figure 4.4 Graph showing the load profile of weekend.
37
The demand for electricity in the weekends is low but some students and staff
members come and work in the C-Block, usually during day times of Saturdays and
Sundays. The load of 0.5 kW from 6 pm to 6 am represents the lighting needs during
the dark hours.
Figure 4.5 Graph showing the average monthly load profile.
The results show that except for the months of June and December, every other
month the maximum daily electrical load is around 4 kW and the average load for
each day of every month is about 2 kW. These values indicate that the average power
demand is reasonably constant over a year except for June and December due to the
semester breaks. The scaled annual average is 40 kWh/d or 1.67 kW and the peak
load is 8.09 kW with a load factor of 0.206. Day-to-day electrical load variation of
15 % was considered for HOMER optimization.
Figure 4.6 I-V curve of Conergy, P 180M.
(Source: Technical data sheet Conergy P 180M module-PVSYST)
38
The power output of PV modules is dependent on the cell temperature as well as the
incident irradiation. At the project site the average recorded irradiation was 3.94
kWh/m2/d, which corresponds to power density of 394 W/m2 at 10 hours of radiation
per day. Hence each module would produce on average 60 W (figure 4.6). For the
solar modules temperature effects were also taken into account with nominal
operating cell temperature (NOCT) of 45 oC and temperature coefficient of power as -
0.5 % / oC.
Figure 4.7 Efficiency vs. Cell temperature graph of Conergy, P 180M.
(Source: Technical data sheet Conergy P 180M module-PVSYST)
The rated efficiency of Conergy P 180M modules at STC is 14.5 % but efficiency
decreases with increase in PV cell temperature. Therefore, an efficiency of 13 % was
considered for calculations at NOCT of 45 0C.
Figure 4.8 PVSYST design of 5 kW PV system. The optimum array size of the 5 kW PV system designed using PVSYST, consisted of
7 modules in series and 4 parallel strings, providing maximum operating power of 4.6
39
kW without any overload losses. There was only one possibility for the number of
strings (4 in parallel) but it was possible to have between 6 and 10 modules in series.
However, for other possibilities of the number of modules in series except 7, the PV
array maximum operating power was lower than 4.6 kW in each case (table 3.2).
The maximum power point operating voltage (Vmpp) for each module was 32.4 V at
60 0C and the open circuit voltage (Voc) at -10 0C was 49.9 V. Thus for the PV array,
Vmpp at 60 0C was 227 V and 268 V at 20 0C (figure 4.8) i.e. the PV output decreases
with the increase in cell temperature. Since each series string had 7 modules the array
Voc was 350V. The roof area needed for the optimum array size of 28 solar modules
was 36 m2 and the total weight of the panels would be 420 kg i.e. 11.67 kg/m2.
Figure 4.9 Graph showing the average electricity generation and grid purchases. For every month of a year, majority of the power demand is met from the grid. The
minimum energy productions from the PV system are during the months of May and
June, generally the cooler months of a year. It also corresponds to the lowest clearness
index values for the solar resource during these months.
Annual PV production based on the average daily irradiation of 3.94 kWh/m2/d
(assuming 10 hours of radiation) was 6135 kWh/y while the grid purchases are
13,674 kWh/y. The PV array production would meet 31 % of the electricity demand
of C Block at FNU. Of the total renewable energy generated from the PV system, 92
% would be consumed and the remaining could be sold to the FEA grid.
40
The PV array output is usually lower than the rated output due to the power losses
during DC to AC conversion, decrease in efficiency of PV modules with increase in
temperature and also because of losses arising from system wirings and connections.
Figure 4.10 HOMER graph showing Global solar radiation vs. PV power.
For solar radiation values around 1000 Wm-2 (figure 4.10), the maximum operating
PV power as calculated by HOMER is slightly less than 4.5 kW which is less than the
rated power of 5 kW. This is because for Conergy modules the nominal operating cell
temperature is 45 0C and the temperature coefficient of power is -0.5 %/ oC. Therefore
a 25 oC temperature rise from STC corresponds to 12.5 % (0.625 kW) decrease in PV
power. Cell temperature rise above 45 0C during periods of low wind speeds coupled
with high irradiation values account for further power losses. Therefore, proper
ventilation for solar modules is an integral part of the design process.
41
4.2 HOMER Techno-Economic Results
HOMER techno-economic analysis was done using sensitivity variables of grid sale
capacity, maximum annual capacity shortage and minimum renewable fraction.
Annual capacity shortage is the ratio of the total capacity shortage and the total
electrical load. Specifying a capacity shortage value means that the power system is
designed not to meet peaks which occur over short times. Otherwise, the system
designed would include large and expensive equipments which would remain unused
majority of the time but increase the system total cost. An annual capacity shortage
factor enables HOMER to design a smaller and less expensive power system to meet
all loads except the peak. Generally, power systems with higher capacity shortage
are considered infeasible.
Grid sale capacity is the amount of electricity that can be fed into the power utility
grid and it was taken as 5 kW to 75 kW to allow for any future expansion of the PV
project. The Net Present Cost (NPC) which considers time value of money is the sum
of present values of all cash-flows associated with a project and is strongly
dependent on the discount rate. Thus, for this project a discount rate of 6 % over 25
year period was used for HOMER simulations.
The optimum solution achieved was a 5 kW grid connected PV power system (fig
4.11) with renewable energy contribution of 31 %. The list of feasible solutions had
many different configurations of the PV and inverter sizes. Based on the lowest cost
of energy of $0.678/kWh the optimum solution was a 5 kW PV system utilizing a 3
kW inverter. The NPC for this system was $126,627.00. This was considered as the
base case system.
However, to ensure that inverter and PV were neither under nor over sized relative to
each other, the optimum solution for the power system was 5 kW PV with 5 kW
inverter i.e. the current system. The cost of energy was $0.698/kWh, which was
$0.02/kWh higher than the base case system and the NPC was $130, 211.00.
42
Figure 4.11 HOMER optimization results after sensitivity analysis.
As shown in figure 4.11, the grid sale capacity does not have any effect on the cost
of energy. Similarly, when the annual capacity shortage sensitivity values of 10 %,
20 % and 30 % were used in HOMER simulations, the capacity shortage was always
zero as shown in the list of feasible solutions in figure 4.11. This is because the PV
system is grid connected and even at times of high peak load, the demand would be
met from the FEA grid.
Results for simulations with the sensitivity variable of minimum renewable energy
fraction are summarized in table 4.1
43
Renewable
Fraction
PV System
Size (kW)
Initial
Capital
Cost ($)
Operating
Cost
($/y)
Total NPC
($)
COE
($/kWh)
0.31 5 69,500 4749 130,211 0.698
0.40 7 96,900 4137 149,790 0.803
0.53 10 138,000 2971 175,979 0.943
0.62 13 177,400 1755 199,834 1.071
0.71 17 232,200 437 237,786 1.274
0.81 25 335,000 -1326 318,050 1.704
Table 4.1 HOMER Techno-Economic results
The operating cost of the PV system decreases as the system size increases because
of higher grid sales with bigger power systems. For PV systems with renewable
energy contribution of 71 % and less, the operating cost represents annual electricity
bill payment to FEA whereas the operating cost for 25 kW system represents the
revenue generated from annual grid sales of electricity. The NPC of a 25 kW system
is lower than the initial capital cost as a result of revenue generated from grid sales.
Component
Capital
($)
Replacement
($)
O&M
($/y)
Salvage
($/y)
Total
($/y)
PV 60,000 0 639 0 60,639
Grid 0 0 55,662 0 55,662
Inverter 5,100 2,003 38 -373 6,768
Other 1,000 0 2,557 0 3,557
System 66,100 2,003 58,897 -373 126,627
Table 4.2 Net present costs (NPC) for 5 kW PV and 3 kW Inverter system.
The capital cost of the power system represents 52 % of the NPC. Grid O&M cost is
reasonably high in comparison with O&M of other components because HOMER
calculates grid O&M costs as difference of the cost of purchasing electricity from the
grid and the revenue generated from grid sales.
44
Component
Capital
($)
Replacement
($)
O&M
($/y)
Salvage
($/y)
Total
($/y)
PV 60,000 0 639 0 60,639
Grid 0 0 54,734 0 54,734
Inverter 8,500 3,338 64 -621 11,281
Other 1,000 0 2,557 0 3,557
System 69,500 3,338 57,994 -621 130,211
Table 4.3 Net present costs for 5 kW PV and 5 kW Inverter system.
Comparing the base case system with the current PV system utilizing 5 kW inverter
shows that although the initial capital cost increases, the grid operation and
maintenance cost decreases. The grid O&M cost for a system using 5 kW inverter is
$903.00 lower than a system using 3 kW inverter because a 5 kW inverter would be
able to feed more electricity into the FEA grid and hence generate more revenue.
Component
Capital
($/y)
Replacement
($/y)
O&M
($/y)
Salvage
($/y)
Total
($/y)
PV 4,694 0 50 0 4,744
Grid 0 0 4,282 0 4,282
Inverter 665 261 5 -49 882
Other 78 0 200 0 278
System 5,437 261 4,537 -49 10,186
Table 4.4 Annualized costs for 5 kW PV and 5 kW Inverter system
It can be deduced from table 4.4 that the operation and maintenance cost of the solar
panels, inverter, and the balance of system (BOS) is $255.00/y or only 5.6 % of the
system annual O&M costs. When the grid operation and maintenance costs of
$4282.00/y are included then the system O&M cost increases to $4537.00. The total
annualized cost is $4749.00 greater than the annualized capital cost because this
system will not meet the full electricity demand of the building.
45
Component
Capital
($/y)
Replacement
($/y)
O&M
($/y)
Salvage
($/y)
Total
($/y)
PV 4,694 0 50 0 4,744
Grid 0 0 4,354 0 4,354
Inverter 399 157 3 -29 529
Other 78 0 200 0 278
System 5,171 157 4,607 -29 9,906
Table 4.5 Annualized costs for 5 kW PV and 3 kW Inverter system
The O&M cost of using 3 kW inverter (table 4.5), excluding the grid O&M cost is
$253.00/y i.e. $2.00 less than a system utilizing 5 kW inverter. When grid O&M
costs is included the system O&M cost increases by $70.00 because a 3 kW inverter
would feed less electricity to the FEA grid than a 5 kW inverter for the same PV
array output hence increase in electricity bill.
Month
Energy
Purchased
(kWh)
Energy
Sold
(kWh)
Net
Purchases
(kWh)
Peak
Demand
(kW)
Energy
Charge
($)
Jan 1,320 100 1,220 7 425
Feb 1,126 123 1,004 8 350
Mar 1,293 130 1,162 8 405
Apr 1,241 100 1,141 7 397
May 1,275 83 1,193 7 415
Jun 605 82 523 4 182
Jul 1,266 84 1,182 8 412
Aug 1,405 94 1,311 7 457
Sep 1,197 111 1,085 8 378
Oct 1,304 116 1,189 7 414
Nov 1,235 130 1,105 7 385
Dec 503 194 309 3 108
Annual 13,770 1,347 12,424 8 4,326
Table 4.6 Monthly electricity budget for 5 kW PV and 3 kW Inverter system.
46
Table 4.6 assumes that FEA prices for buying and selling electricity do not change
over the project life. It can be interpreted from the results in table 4.6 that on yearly
basis the PV system can feed-in a total of 1347 kWh of electricity to the FEA grid
which would be savings of $469.29/y in terms of the electricity bill. This generally
accounts for the weekends when the power demand for the building is low compared
with the weekdays and hence the PV electricity generated is fed into the grid.
On the other hand, the PV system alone cannot meet the average annual power
demand and hence 13,770 kWh of electricity needs to be purchased from the FEA
grid. The difference between the demand and surplus corresponds to 12,424 kWh of
net purchases from the FEA grid. In economical terms it translates to the FNU
paying the FEA $4326.00/year as the total cost of its electricity bill for the C-Block.
The lowest values for the net energy purchases are during the months of December
(309 kWh) and June (523 kWh) because of the semester breaks during these months.
Month
Energy
Purchased
(kWh)
Energy
Sold
(kWh)
Net
Purchases
(kWh)
Peak
Demand
(kW)
Energy
Charge
($)
Jan 1,320 108 1,212 7 422
Feb 1,112 134 978 8 341
Mar 1,285 140 1,145 8 399
Apr 1,231 104 1,127 7 392
May 1,275 88 1,187 7 413
Jun 605 90 515 4 179
Jul 1,245 88 1,158 8 403
Aug 1,398 102 1,296 7 451
Sep 1,189 121 1,068 8 372
Oct 1,295 125 1,169 7 407
Nov 1,215 145 1,071 7 373
Dec 503 214 290 3 101
Annual 13,674 1,459 12,215 8 4,253
Table 4.7 Monthly electricity budget for 5 kW PV and 5 kW Inverter system.
47
The peak demand of electricity ranges from 3 kW to 8 kW (table 4.7). The results
show that a PV system utilizing 5 kW inverter can feed-in a total of 1459 kWh of
electricity to the FEA grid; 112 kWh more compared with 1347 kWh if a 3 kW
inverter is used. Using 5 kW inverter in the PV system would reduce the electricity
bill from $4326.00 to $4253.00 per annum; a reduction in the electricity bill by
$73.00/y. However, the initial capital cost of having a 5 kW inverter will be
$3400.00 more than a 3 kW inverter but it will ensure the available solar energy is
fully harnessed by the PV system.
The highest grid sales of 214 kWh is in December and the lowest grid sales are in the
months of May (88 kWh), June (90kWh) and July (88kWh), generally the cooler
months of a year.
4.3 Inverter Output
At 10 h/d of operation for the 5 kW inverter, yearly mean output is 0.67 kW. This is
due to the generally poor solar resource. The maximum output is 4.41 kW and at full
capacity it operates for 1278 hours in a year. The capacity factor which is the ratio of
average output to the nominal output is 13.4 % and losses account for 110 kWh/y
(4.4 %) of the total energy input of 2495 kWh/y.
Figure 4.12 Graph showing the 5 kW Inverter output power.
The optimum solution provided by HOMER with lowest cost of energy of $0.678/kWh
was a 5 kW PV system with 3 kW inverter (figure 4.11).
48
Figure 4.13 Graph showing the power output of 3 kW inverter.
If 3 kW inverter is used then the capacity factor is 20 % with mean output of 0.6 kW.
It would operate for 1251 hours per year and the energy output will be 2176 kWh/y
with energy losses accounting for 100 kWh/y (4.4 %). However, if 3 kW inverter is
used then the PV system will be undersized relative to the PV array capacity during
times of good solar irradiation.
49
CHAPTER 5 ANALYSIS 5.1 PV system analysis
There are several characteristics of PV power systems which bear considerable
examination because they have direct impacts on how an investor values the worth of
the technology. Three such basic analyses of investment in PV systems include; the
system capital cost, cost per kW and cost per unit area. The total capital cost of the 5
kW PV system designed was $69,500.00.
./00.900,13$5
00.500,69$ kWkWPowerRated
CostCapitalkWperCostSystem ���
./56.1930$36
00.500,69$ 22 m
mAreaArrayPVCostPowerRatedAreaunitperCost ���
Despite the availability of renewable energy equipments at duty free rates in Fiji, PV
system capital costs in common with other countries are quite high and do not
compare favourably with the capital costs of fossil fuel based power systems of
similar power ratings. The high costs are because PV modules and inverters are not
manufactured locally and therefore the prices are driven by overseas market prices
and freight costs associated with the supply of equipments.
Apart from the technological and economic aspects of PV systems, their performance
analysis is heavily dependent on the local climatic conditions. Thus, two technical
terms of interest are the specific yield and the specific output both of which are a
function of the energy produced annually.
./42.17036
6135Pr 22 mkWh
mkWh
AreaArrayPVoductionEnergyAnnualYieldSpecific ���
loadfullatoperationofhours
kWkWh
PowerRatedoductionEnergyAnnualOutputSpecific
1277
56135Pr
�
��
%1587601277
,��hh
yearainhoursoutputspecificfactorcapacitysystemPV
50
5.2 PV Array sizing
Figure 5.1 shows how the inverter maximum power point (MPP) input voltage range
(150 – 450) V and the maximum DC power curve constraint the maximum array
size. At STC temperature of 25 0C, the inverter DC power curve and the I-V curve
for the array are closest (at maximum inverter efficiency) to each other at a nominal
MPP voltage (VmppNom) less than 270 V.
Figure 5.1 PV array sizing
At the maximum annual ambient temperature of 29 0C, the open circuit voltage of the
PV array would be close to 315 V and the VmppNom will be between 250 - 270 V with
the maximum power point current (Impp) close to 20 A. Thus, the number of PV
modules needed in series was determined by taking the average (260V) of the
nominal maximum power point voltage and dividing by the MPP voltage (Vmpp) of
36 V for the Conergy PV modules. The result was 7.2; therefore the optimum
PVSYST design was 7 modules in series (figure 5.2).
51
For the series string of 7 modules, the open circuit voltage (Voc) was 285 V, short
circuit current (Isc) was 4.2 A, Vmpp was 250 V and Impp = 4 A. Thus the maximum
power output from each series string is 1000 W.
Figure 5.2 Summing the voltage and current of each PV module
The series string of 7 solar modules provides the PV array output voltage compatible
with the minimum inverter input voltage of 150 V but results in increase of the series
resistance of the circuit. Therefore, to increase PV power production and to reduce
losses due to circuit resistance, 3 other parallel strings were added. Thus the PV array
consists of 7 modules in each of the 4 parallel strings and the open circuit voltage of
the array is 285 V with short circuit current of 16.8 A.
52
5.3 Economic Analysis
PV
(kW) Inverter.
(kW) Grid (kW)
Initial Capital
Total NPC
System I 5 3 10 $66,100 $126,627 System II 5 5 10 $69,500 $130,211
Table 5.1 Comparison of 5 kW PV system with 3 kW and 5 kW inverter.
The optimum solution obtained from HOMER analysis for 30 % renewable energy
penetration was 5 kW PV array with 3 kW inverter but the inverter would be
undersized relative to the PV array. Therefore, a power system with 5 kW PV array
and 5 kW inverter was designed.
The present worth, which is the difference between the net present costs of system I
and system II is -$3584.00
Present Worth = $126,627.00 - $130,211.00 = - $3584.00.
The negative sign of the present worth indicates that system II doesn’t compare
favourably as an investment option with system I. It indicates that system II would
cost more money over the project lifetime compared with system I.
Annual worth is the product of the present worth and the capital recovery factor
(CRF). At interest rate 6( �i %) and system lifetime )25( �N years;
1)1()1(),(��
�� N
N
iiiNiCRF
0782.01)06.01(
)06.01(06.0)25,06.0( 25
25
���
��CRF
Annual worth = (CRF present worth
y/00.280$27.28000.3584$0782.0 �,���(�
53
Nom
inal
Cas
h Fl
ows
Dis
coun
ted
Cas
h Fl
ows
Yea
r
Syst
em II
Sy
stem
I D
iffer
ence
Sy
stem
II
Syst
em I
Diff
eren
ce
Ann
ual
($)
Cum
ulat
ive
($)
Ann
ual
($)
Cum
ulat
ive
($)
Ann
ual
($)
Cum
ulat
ive
($)
Ann
ual
($)
Cum
ulat
ive
($)
Ann
ual
($)
Cum
ulat
ive
($)
Ann
ual
($)
Cum
ulat
ive
($)
0 -6
9,50
0 -6
9,50
0 -6
6,10
0 -6
6,10
0 -3
,400
-3
,400
-6
9,50
0 -6
9,50
0 -6
6,10
0 -6
6,10
0 -3
,400
-3
,400
1
-4,5
37
-74,
037
-4,6
07
-70,
707
71
-3,3
29
-4,2
80
-73,
780
-4,3
46
-70,
447
67
-3,3
33
2 -4
,537
-7
8,57
3 -4
,607
-7
5,31
5 71
-3
,259
-4
,038
-7
7,81
8 -4
,100
-7
4,54
7 63
-3
,271
3
-4,5
37
-83,
110
-4,6
07
-79,
922
71
-3,1
88
-3,8
09
-81,
627
-3,8
68
-78,
415
59
-3,2
11
4 -4
,537
-8
7,64
7 -4
,607
-8
4,52
9 71
-3
,118
-3
,593
-8
5,22
0 -3
,649
-8
2,06
5 56
-3
,155
5
-4,5
37
-92,
183
-4,6
07
-89,
136
71
-3,0
47
-3,3
90
-88,
610
-3,4
43
-85,
508
53
-3,1
03
6 -4
,537
-9
6,72
0 -4
,607
-9
3,74
4 71
-2
,976
-3
,198
-9
1,80
8 -3
,248
-8
8,75
6 50
-3
,053
7
-4,5
37
-101
,257
-4
,607
-9
8,35
1 71
-2
,906
-3
,017
-9
4,82
5 -3
,064
-9
1,82
0 47
-3
,006
8
-4,5
37
-105
,793
-4
,607
-1
02,9
58
71
-2,8
35
-2,8
46
-97,
672
-2,8
91
-94,
710
44
-2,9
62
9 -4
,537
-1
10,3
30
-4,6
07
-107
,566
71
-2
,765
-2
,685
-1
00,3
57
-2,7
27
-97,
437
42
-2,9
20
10
-4,5
37
-114
,867
-4
,607
-1
12,1
73
71
-2,6
94
-2,5
33
-102
,890
-2
,573
-1
00,0
10
39
-2,8
80
11
-4,5
37
-119
,403
-4
,607
-1
16,7
80
71
-2,6
23
-2,3
90
-105
,280
-2
,427
-1
02,4
37
37
-2,8
43
12
-4,5
37
-123
,940
-4
,607
-1
21,3
87
71
-2,5
53
-2,2
55
-107
,535
-2
,290
-1
04,7
27
35
-2,8
08
13
-4,5
37
-128
,477
-4
,607
-1
25,9
95
71
-2,4
82
-2,1
27
-109
,662
-2
,160
-1
06,8
87
33
-2,7
75
14
-4,5
37
-133
,014
-4
,607
-1
30,6
02
71
-2,4
11
-2,0
07
-111
,668
-2
,038
-1
08,9
25
31
-2,7
44
15
-12,
537
-145
,550
-9
,407
-1
40,0
09
-3,1
29
-5,5
41
-5,2
31
-116
,899
-3
,925
-1
12,8
50
-1,3
06
-4,0
49
16
-4,5
37
-150
,087
-4
,607
-1
44,6
17
71
-5,4
70
-1,7
86
-118
,685
-1
,814
-1
14,6
64
28
-4,0
22
17
-4,5
37
-154
,624
-4
,607
-1
49,2
24
71
-5,4
00
-1,6
85
-120
,370
-1
,711
-1
16,3
75
26
-3,9
95
18
-4,5
37
-159
,160
-4
,607
-1
53,8
31
71
-5,3
29
-1,5
89
-121
,960
-1
,614
-1
17,9
89
25
-3,9
71
19
-4,5
37
-163
,697
-4
,607
-1
58,4
38
71
-5,2
58
-1,4
99
-123
,459
-1
,523
-1
19,5
12
23
-3,9
47
20
-4,5
37
-168
,234
-4
,607
-1
63,0
46
71
-5,1
88
-1,4
15
-124
,874
-1
,437
-1
20,9
48
22
-3,9
25
21
-4,5
37
-172
,770
-4
,607
-1
67,6
53
71
-5,1
17
-1,3
34
-126
,208
-1
,355
-1
22,3
03
21
-3,9
05
22
-4,5
37
-177
,307
-4
,607
-1
72,2
60
71
-5,0
47
-1,2
59
-127
,467
-1
,279
-1
23,5
82
20
-3,8
85
23
-4,5
37
-181
,844
-4
,607
-1
76,8
68
71
-4,9
76
-1,1
88
-128
,655
-1
,206
-1
24,7
88
18
-3,8
67
24
-4,5
37
-186
,380
-4
,607
-1
81,4
75
71
-4,9
05
-1,1
20
-129
,775
-1
,138
-1
25,9
26
17
-3,8
49
25
-1,8
70
-188
,250
-3
,007
-1
84,4
82
1,13
7 -3
,768
-4
36
-130
,211
-7
01
-126
,627
26
5 -3
,584
Ta
ble
5.2
C
ompa
rison
of n
omin
al a
nd d
isco
unte
d ca
sh fl
ows o
f sys
tem
I an
d sy
stem
II.
54
System II minus System I
Figure 5.3 Graph comparing nominal and discounted cash flows of system I and
system II.
Both the nominal and the discounted cash flow values show significant increases in
cumulative cash flows in year 15 because of the cost of replacing the inverter which
has a lifetime of 15 years. The nominal cost increases from $2411.00 in year 14 to
$5541.00 in year 15 whilst the discounted cash flow increases from $2744.00 to
$4049.00 respectively. The increases are by 129.8 % and 147.5 % respectively. Over
the project lifetime of 25 years, the cumulative nominal and discounted cash flows
were at its lowest values in year 14. Although the cash flow would continuously
improve after the inverter replacement, the costs at the end of project lifetime are
higher than the costs before inverter replacement. But overall the cash flow over the
lifetime improves from $3400.00 initially to $3768.00 for nominal cost and $3584.00
for discounted cost.
The return on investment (ROI) calculated using the cumulative nominal cash flows is:
� �) * blifetimebaROI --��
Where: a is cumulative nominal cash flow in final year.
b is cumulative nominal cash flow in year zero.
� �) * 43.000.3400$2500.3400$00.3768$ ���--����ROI %.
55
The discount factor over the project lifetime is given by:
� �2329.0
06.011
)1(1
25 ���
�� Nd i
f . i.e. The nominal cash flow of $3768.00 in the
25th year has a present value of $877.57
System II Compared with System I - Discounted
Figure 5.4 Graph comparing PV system II having 5 kW Inverter with system I
using 3 kW Inverter.
For system II utilizing 5 kW inverter, the change in cash flow from the 14th to the
15th year is large and abrupt compared with system I utilizing 3 kW inverter because
of the higher cost of replacement of 5 kW inverter. The initial difference between the
current and the base case power system is $3400.00 but at the end of 25 years the
difference increases to $3584.00. The nominal costs of system II increases from
$69,500.00 to $130,211.00 over the 25 year period.
Figure 5.5 Graph showing net present cost summary by components.
56
High capital cost of $60,000.00 for the PV modules and the O & M costs of $639.00
represent 47 % of the total net present cost (NPC) of $130,211.00 for the PV power
system. The net present costs for the inverter represents 8.7 % of the total while the
balance of system (BOS) costs of $3557.00 represent 3 %. The grid NPC of
$57,734.00 is the difference between the cost of buying and selling electricity from
the FEA grid.
Figure 5.6 Graph showing net present cost by cost type.
The high capital cost of the PV system in common with high initial capital costs of
most of renewable energy technologies represents 53 % of the total NPC. The
replacement cost of the inverter is $3338.00 with a salvage cost of $621.00. The
O&M cost of all system components including the grid is $57,994.00 and excluding
the grid O&M costs is $3260.00 i.e. 2.5 % of the total NPC of $130,211.00.
5.4 Simple Payback Period Analysis This calculation compares revenue with costs and determines the length of the time
required to recoup the initial investment. The payback period in years is equal to the
total capital cost divided by the average annual return from the power produced.
� � � �� �AARturnAnnualAverage
CcCostCapitalSPPeriodPaybackSimpleRe
�
The current cost of buying electricity from FEA grid is $0.3484/kWh for domestic
households, educational institutes and faith based energy customers e.g. churches and
57
temples. The government however provides a subsidy of $0.1425/kWh towards
electricity bills of all primary and secondary schools but tertiary institutes like Fiji
National University pay $0.3484/kWh.
Simple Payback Period @ $0.3484/kWh
� �
43.2137$3484.0$6135
cosPr
�(�
(�
kWh
kWpertAEPoductionEnergyAnnualAAR
yearsSP 5.3243.2137$00.500,69$
��
It would take 32.5 years to recover the initial investment on the PV system against
the system lifetime of 25 years. Thus, the investment will not be a viable one to
consider.
Simple Payback Period @ $0.2700/kWh
� �
45.1656$2700.0$6135
cosPr
�(�
(�
kWh
kWpertAEPoductionEnergyAnnualAAR
yearsSP 4296.4145.1656$00.500,69$
,��
The minimum tariff payable to Independent Power producers (IPPs) feeding into the
FEA grid is $0.2700/kWh. If separate meters are used for grid sales and grid
purchases instead of using net-metering then the simple payback period of the project
is 42 years.
The simple payback period analysis ignores several factors such as loan costs,
depreciation in capital costs, operational and maintenance costs and variation in the
value of delivered electricity over time. All these factors have direct influence on the
economics of any energy generation system. Thus, at the current electricity tariffs,
investment on grid connected PV power system would not be a viable investment
because the payback period is more than the system lifetime.
58
5.5 Cost of Energy Analysis This analysis is based on a fixed charge rate over the loan period and it neglects the
most important factor of economics i.e. the time value of money. The fixed charge
rates used are 6 % and 13 % to account for the average loan interest rates charged by
development bank and commercial banks respectively.
The cost of energy (COE) is defined as the unit cost to produce energy (in $/kWh)
from the solar energy system.
oductionEnergyAnnualtsOperatingEnergyofCost
Prcos
�
� �tsMORateeChFixedtCapitaltsOperating cos&argcoscos �(�
Fixed Charge Rate (FCR) = 6 % O&M costs = $255.00/year
Case 1: Half of the capital cost is financed at FCR of 6 %.
FCR only applies to ($69,500.00 ÷ 2) = $34,750.00
� � � �) * kWhkWh
COE /38.0$6135
00.255$06.000.750,34$�
�(�
Case 2: Half of the capital cost is financed at FCR of 13 %.
FCR only applies to ($69,500.00 ÷ 2) = $34,750.00
� � � �) * kWhkWh
COE /78.0$6135
00.255$13.000.750,34$�
�(�
Case 3: If the total capital cost is financed at FCR of 6 %.
� � � �) * kWhkWh
COE /72.0$6135
00.255$06.000.500,69$�
�(�
59
Case 4: If the total capital cost is financed at FCR of 13 %.
� � � �) * kWhkWh
COE /51.1$6135
00.255$13.000.500,69$�
�(�
In all of the four cases above, the cost of energy is greater than the cost at which the
FEA provides the electrical energy ($0.3484 / kWh).
5.6 Life Cycle Cost (LCC) Analysis
This analysis is more comprehensive and is more realistic in evaluating the
feasibility of renewable energy projects. It includes the net present value of money
( cNPV ) and calculates the levelized cost of energy ).(COEL
oductionEnergyAnnualCRFNPV
COEL c
Pr(
�
Levelizing is a method for expressing costs or revenues that occur once or in
irregular intervals as equivalent equal payments at regular intervals. The net present
value is generally used as a measure of economic value when comparing different
investment options in the life cycle costing analysis.
���
�����
����
����
�� LriYfCN
rYPPNPV mocadc ,
11,
11
&
� � � � 1;1
,1
.��
��
kk
kkxkYx
Using: Loan interest rate b = 6 %
Discount rate r = 5 %
System lifetime L = 25 years
Period of loan N = 20 years
Down payment on the system �dP = $34,750.00 (i.e. 50 % of cC )
Capital cost cC = $69,500.00
Annual Operation and maintenance cost, O&M = $255.00
60
Assumption: The general inflation and energy inflation rates, ( i ) are constant at 2 %
over the system lifetime.
The capital recovery factor (CRF) based on the loan interest rate, ( b ) rather than
discount rate ( r ) is used to determine the amount of each future payment required to
accumulate a given present value when the discount rate and the number of payments
are known.
� �) * 0;11
.��
� � rr
rCRF N CRF for loan = � �) * 0872.0
06.01106.0
20 ��� �
CRF based on system lifetime = � �) * 0709.0
05.01105.0
25 ��� �
Annual payment on system costs, � � CRFPCP dca (��
� �20.3030$
0872.000.750,34$00.500,69$�
(��
For payment
���
�����
��
����
����
����
20,06.1120,
06.011,
11 YYN
rY �
���
����
���
�����
��
���
�
�
06.111
06.11
06.11 120
5.1967
For system lifetime
5278.17
05.102.11
05.102.1
05.102.1
25,05.102.125,
05.0102.01,
11
125
����
����
���
�����
��
���
����
�����
��
�����
����
�����
�
YYLriY
Annual operation and maintenance cost fraction, 3& 1066.3
00.500,6900.255$ �(��mof
61
� � � �
59.955,54$
55.4458$04.747,15$00.750,34$
5278.171066.300.500,69$1967.520.3030$00.750,34$
,11,
11
3
&
�
���
(((�(��
���
�����
����
����
��/
�
LriYfCN
rYPPNPV mocadc
kWhoductionEnergyAnnual
CRFNPVCOEL c /64.0$
61350709.059.955,54$
Pr�
(�
(�
The life cycle cost of $0.64/kWh is almost double the current cost at which FEA
provides the electricity. Though the environmental value of PV generated electricity
is great, economically it is not a viable option at current electricity tariffs.
HOMER came up with the cost of energy as $0.69/kWh which is slightly greater than the
Life Cycle Cost analysis of $0.64/kWh. The difference is because HOMER assumes the
loan is paid over the 25 year period whereas the LCC analysis considered loan repayment
in 20 years.
62
CHAPTER 6 SYSTEM WIRING 6.1 Introduction
Wiring of the different components of a PV system is equally important as the design
of the PV system itself because poor wiring usually results in significant power
losses and can lead to system failures. This chapter outlines the many wiring aspects
of each system component; the length of cables, diameter of cables, power losses in
each segment of wiring, suitable sizes of fuses and circuit breakers. The general
layout of the system and earthing and lightning protection is also discussed.
6.2 Wiring layout of PV system components
A thorough knowledge of the PV system circuit wiring is vital to ensure connections
are correct and that system components do not get electrically damaged. The overall
PV system wiring is divided into three main sections comprising of the PV array, the
inverter and the user load with the grid backup.
Figure 6.1 Wiring layout of grid connected PV system with its components.
63
The PV array consists of 28 Conergy P180M solar modules. There are 4 parallel
strings and 7 PV modules are connected in each series string. Output from each
parallel string is connected separately to a common DC busbar from which only a
single negative and positive connection is made to the inverter. The DC busbar
incorporates a blocking diode which ensures that the PV array does not draw current
from the grid during non sun hours.
Figure 6.2 Wiring layout of PV modules and the inverter.
The arrows in the block diagram below indicate the generation and flow of electricity
through the various components of the grid connected PV system.
Figure 6.3 Block diagram of grid connected PV system.
5 kW PV Array with
DC fuse
Single Phase 5 kW Inverter With double
MPPT
Main distribution panel with
meter
Loads
Grid
AC
dis
conn
ect
Switc
h
64
6.3 Cable Sizing
Accurate sizing and selection of cables for component wirings is important to ensure
safe current handling capacity of cables is not exceeded and the performance of any
component is not compromised.
Ohm’s law states that the voltage drop across the ends of any conductor is equal to the
product of resistance and the current through it. i.e. .RIV � The resistance is given
by:
AR ��� 6.1
Where: �� resistivity of the cable / conductor � �m0
�� Length of the cable � �m
�A Cross sectional area of the cable � �2m
Thus, the voltage drop is given by: .IA
V (��� 6.2
Multiplying the length of the cable by 2 to account for the total loop wiring and
making cross sectional area, A, the subject of the equation yields:
� �V
IAIA
V (((�'(
(�
�� �� 2.2 6.3
Technical Information
� Copper cable resistivity, m0(� �8107.1�
� Standard maximum allowable voltage drop across cables in grid-tied systems
= 5 %
� Standard maximum allowable current for PV circuit = 125 % of the short
circuit current.
6.3.1 Cable sizing for PV array series connection
The following information was used for cable sizing:
� Nominal voltage rating of each Conergy module = 24 V DC.
� Short circuit current, .20.5 AIsc �
� Maximum cable length, 1�� m.
65
Maximum possible current .5.620.525.1 AA �(�
Maximum allowable voltage drop VV 2.124100
5�(�
Therefore the minimum cross sectional area required for the cable interconnecting the
PV modules is:
.18.01084.12.1
5.61107.122 2278
mmmV
IA �(�((((
�(((
� ����
However, cables with such low minimum cross sectional area and high current
carrying capacity are expensive as these are normally used in electronics. Therefore,
DC electrical cables for this project were selected using the table given below.
Number & Size of Strands
Conductor Area (sq.mm)
Current Rating (Amps)
Resistance per metre
(Ohms 35 0C)
Nearest Equivalent
AWG (B & S) 10 x 0.12 0.11 1.1 0.17 27 7 x 0.16 0.14 1.4 0.13 26 1 x 0.5 0.20 2.0 0.10 24
14 x 0.14 0.22 2.2 0.088 24 7 x 0.2 0.22 2.2 0.086 24 1 x 0.6 0.28 2.8 0.067 23 1 x 0.7 0.38 3.8 0.049 21
14 x 0.2 0.44 4.4 0.043 21 10 x 0.25 0.49 4.9 0.039 20 63 x 0.10 0.49 4.9 0.039 20 50 x 0.12 0.55 5.0 0.035 20 60 x 0.12 0.68 6.8 0.028 19 89 x 0.1 0.70 7.0 0.027 19 24 x 0.2 0.75 7.5 0.025 18
112 x 0.10 0.88 8.8 0.022 18 30 x 0.2 0.94 9.4 0.02 17 1 x 1.13 1.0 10.0 0.019 17 32 x 0.2 1.0 10.0 0.019 17
512 x 0.05 1.0 10.0 0.019 17 168 x 0.1 1.32 13.0 0.014 16
7 x 0.5 1.4 14.0 0.014 16 30 x 0.25 1.5 15.0 0.013 15 26 x 0.3 1.8 17.0 0.010 15
168 x 0.12 1.9 18.0 0.010 14 26 x 0.32 2.1 19.0 0.0091 14 7 x 0.67 2.5 22.0 0.0077 13 1 x 1.78 2.5 22.0 0.0076 13
252 x 0.127 3.2 29.0 0.0059 12 41 x 0.32 3.3 30.0 0.0057 12
315 x 0.12 3.6 30.0 0.0053 12 630 x 0.12 7.13 50 0.0027 9
1666 x 0.12 18.84 120 0.0010 5 Table 6.1 Copper cable characteristics
(Source: Dicksmith Electronics Annual catalogue 2009, pg 350)
66
Thus, for the series connection of the PV panels, 268.0 mm copper cable would be
used because it has current carrying capacity of 6.8 A, which is a slightly higher value
than the maximum possible current of the array.
6.3.2 Cable sizing from DC Busbar to Inverter
Cable sizing was done using the following information:
� Maximum cable length, 10�� m.
� Inverter voltage input range = 180 - 450 V DC
The maximum possible current from an the array of 28 PV modules (7 x 4) =
.26420.525.1 A�((
Average of the inverter input voltage range (180 – 450 V) = 315 V. Thus, maximum
voltage drop = 75.15315100
5�( V V
2278
56.01061.575.15
2610107.122 mmmV
IA �(�((((
�(((
� ����
Thus, a 22.3 mm cable would be used for the wiring from the DC Busbar to the
inverter because it has current carrying capacity of 29 A, which is a slightly higher
value than the maximum possible current of 26 A from the array.
6.3.3 Cable sizing from Inverter to main distribution panel
Alternating current cables are needed for wiring this section of the PV circuit. Thus,
Olex electrical data and current ratings as given in the table below were used.
Table 6.2 Copper cable characteristics
(Source: Olex Electrical handbook 2009, pg 72)
67
Cable sizing was done using the following information:
� Maximum cable length, 10�� m.
� Inverter rating = 5 kVA single phase.
When the inverter operates at full load, the maximum current .83.20240
5 AkVA��
Maximum allowable voltage drop VV 12240100
5�(�
Therefore the minimum cross sectional area required for the cable from the inverter to
main junction box interfacing the inverter, grid and the load is:
.59.01090.512
83.2010107.122 2278
mmmV
IA �(�((((
�(((
� ����
Thus, a 24 mm cable would be used for the wiring from inverter to main distribution
panel because in PVC circular form that is the appropriate size having current
carrying capacity of 25 A, which is also higher than current carrying capacity (20.83
A) of the cable needed.
The voltage drop rating of this cable isAmmV12 . Thus, for 20m of cable the voltage
drop would be ,6202512 VmAAmmV
�(( which is within the voltage drop limit as
%5.21002406
�(V
V .
6.3.4 Cable selection for wiring
The length, cross sectional area, temperature effects on resistance and insulation and
the current carrying capacity are some important factors to consider in selecting the
right cables for wiring the different components of the PV circuit. Generally, the
current carrying capacity of the cables selected should be slightly more than the over
current protection devices rating to ensure non burning or melting of the cables which
can result in fire.
68
6.4 Sizing of circuit breakers
Circuit breakers used in grid connected PV systems are bi-directional which provide
protection against over current. The standard current rating of the fuse must be
maximum of 125 % of the nominal current flowing in the cable.
6.4.1 Sizing circuit protection between PV array and Inverter
The four parallel strings from the PV array could be connected with circuit breakers
in two different ways.
Option 1
A fuse/circuit breaker could be installed on each string before the cable is connected
to the inverter.
Option 2
All four parallel strings could be fused together and then a circuit breaker installed
before the fused output is connected to the inverter.
Due to the simplicity and ease of circuit breaker connection in each parallel string, the
first option is used for this project.
Maximum possible current .50.620.525.1 AA �(� The lowest rated DC fuses
commonly available are 5 A and the next is 8 A. Therefore, a 5A fuse would be used
for each parallel string.
Figure 6.4 Diagram of 5A ATC blade fuse and holder.
(Source: www.digikey.com)
69
Figure 6.5 Wiring diagram for the solar panels to the inverter
6.4.2 Sizing circuit protection between Inverter and Grid
This circuit breaker would be part of the main distribution panel providing circuit
protection to the grid from the single phase output of the inverter in an over current
situation.
For the inverter operating at full load, the maximum current .83.20240
5 AkVA��
Therefore, the current rating for the bi-directional AC circuit breaker would be 20 A.
This circuit breaker would be protecting the inverter from over current situations
resulting from the grid as well as it will ‘trip’ in case of any over current situations
from the inverter to the grid.
6.4.3 AC Isolation/Disconnect
The disconnect switch would be placed between the inverter and the main distribution
box allowing provision for isolating the PV system from the grid during system
maintenance times or to rectify some faults in the circuit operation. The rating for the
70
disconnect switch can be the same or slightly greater than the rating for circuit
protection between the inverter and the grid i.e. 20 A.
6.4.4 Earth and Lightning protection
Grounding or earth is important in PV systems for electrical safety as well as
lightning protection. Improper earthing of PV systems could cause catastrophic
failures of PV systems and its components. Therefore, to provide the easiest path for
lightning to get to ground, all PV panel frames and the mounting structures would be
grounded through a single earth rod (~ 2.5 m) long. The ground for the earth rod
would be salted with copper oxide to improve conductivity.
.
71
CHAPTER 7 DISCUSSION 7.1 Introduction
Economic viability of grid connected PV systems depends mainly on electricity
generation potential of PV projects and electricity tariffs applicable for generating
renewable energy. Thus, HOMER analysis was carried out using grid sale tariff of
$0.27/kWh and $0.3484/kWh at average daily irradiation value of 3.94 kWh/m2/d.
7.2 HOMER Optimization
Case 1
Demand rate =$0.3484/kWh
Grid power price = $0.3484/kWh
Grid sales price = $0.27/kWh.
For a 5 kW grid connected PV system, five different configurations of PV power
system were obtained as feasible solutions i.e. with five different inverter sizes
ranging from 1 kW to 5 kW. The net present cost of energy (NPC), for the inverter
sizes from 1 kW up to 5 kW was: $0.683/kWh, $0.679/kWh, $0.678/kWh,
$0.686/kWh and $0.698/kWh respectively.
Based on the lowest NPC, HOMER optimization provided a base case optimum
system consisting of 5 kW PV array with 3 kW inverter. The inverter capacity was
undersized relative to the PV array capacity because HOMER calculates the
optimum size based on the average daily irradiation values. To account for
irradiation levels during the bright sun hours of a day, when the irradiation values are
usually more than the average value of 3.94 kWh/m2/d, a 5 kW PV array with 5 kW
inverter was considered despite the COE being higher than the base case system.
This power system would meet 31 % of the electricity needs of the C block at FNU.
The current grid sale tariff in Fiji, set by the Fiji Commerce Commission is a
minimum of $0.27/kWh. It is an incentive for IPPs to consider energy projects in
72
outer islands but for an IPP operating on any of the two main islands, the grid sale
tariff applicable is fixed at $0.27/kWh.
.
Case 2
Demand rate =$0.3484/kWh
Grid power price = $0.3484/kWh
Grid sales price = $0.3484/kWh
All educational and religious institutions in Fiji, connected to the FEA grid were
supplied electricity at special tariff of $0.2059/kWh until 21/10/2010 when it was
revised to $0.3484/kWh effective from 01/11/2010. Following the tariff alignment by
the Fiji Commerce Commission, the government announced that it will subsidise the
increases for primary and secondary schools but tertiary institutes. Thus, HOMER
analysis was performed considering the grid sale tariff is set equal with the grid
purchase tariff of $0.3484/kWh, which could be an incentive for IPPs.
The optimization results of a 5 kW PV system were five feasible solutions of
different inverter configurations with sizes ranging from 1 kW to 5 kW. The NPC of
energy, for the inverter sizes from 1 kW up to 5 kW were: $0.683/kWh, $0.679/kWh,
$0.679/kWh, $0.686/kWh and $0.698/kWh respectively. Other PV system sizes and
their contribution to the electricity demand is summarised in table 7.1
PV system
size (kW)
Renewable
Fraction
NPC($/kWh) @
grid sellback rate
= $0.27/kWh
NPC($/kWh) @
grid sellback rate
= $0.3484/kWh
5 0.31 0.698 0.698
7 0.40 0.803 0.803
10 0.53 0.943 0.941
13 0.62 1.071 1.055
17 0.71 1.274 1.257
25 0.81 1.704 1.651
Table 7.1 Net Present Cost of electricity
73
Comparison of case 1 and 2, shows that higher tariff for grid sales would only have
any significant impact on the PV cost of energy when larger PV systems are
developed. For the PV project to have any significant impact on the electricity
consumption of the C block at FNU, it was decided that the solar system must
contribute at least 30 % of the total electricity demand. The cost of energy in all the
different PV system sizes obtained from HOMER is more than the present cost of
supply from FEA ($0.3484 / kWh). The unit cost of electricity increases with the
increase in the PV system size mainly due to the following reasons.
� Prices of PV modules, inverters, cables and the balance of system
components are unreasonably high compared with fossil fuel based electricity
generators.
� Project site has a poor solar resource, resulting in the maximum capacity of
the system not fully realized.
� HOMER does not consider a discount rate in the initial capital costs when
systems with larger power ratings are considered.
The high capital costs and low irradiation levels, creates an economic imbalance
between the installed capacity of the system and the actual power output. Thus, when
larger systems are installed, the economic imbalance is having a multiplying effect
and hence the cost of energy increases.
7.3 HOMER Simulations
From the HOMER analysis it was calculated that the energy production from the PV
system was 6135 kWh/y while total purchases from the FEA grid was 13,674 kWh/y.
The mean output from the panels was 0.7 kW or 7 KWh/d. The mean output is really
low compared with the rated capacity of 5 kW for the PV panels and hence it
translates to a low capacity factor of 15 %. The PV system would operate for a total
of 2555 h/y. However, the total energy provided over a year from the PV system
accounts for 31% of the demand from the building i.e. renewable energy contribution
of 31%.
74
The initial cost of the complete system would be $69,500.00 and the net present cost
(NPC) after a system lifetime of 25 years of $130,211.00. The levelized cost of
energy came to a value of $0.698/kWh which is quite high compared with the cost of
electricity supplied by the Fiji Electricity Authority. i.e. $0.3484 / kWh.
Although the cost is quite high, a major advantage of having PV power system is
that it produces totally green energy i.e. 100% renewable energy. The annual
operation and maintenance cost of the system excluding the O&M of the grid was
$255.00/y with system fixed O&M cost of $200/y.
Some of the assumptions made for HOMER techno-economic analysis were:
� grid is available majority of the time
� loan interest rate remains constant at 6 %
� energy and real inflation rate is constant at 2 %
� electrical load variation is not more than 15 %
� inverter is expected not to produce very significant harmonic distortions.
HOMER performed a total of 2484 simulations with 324 sensitivities. The sensitivity
variables were maximum capacity shortage, minimum renewable energy fraction and
energy sale capacity of the power system.
7.4 Selection of PV modules and Inverter
Conergy P180 model solar panels were selected because it is designed especially for
large electrical power requirements and the 72 monocrystalline cells of each module
are embedded in ethylene vinyl acetate (EVA) which ensure long term performance
with high efficiency. Presence of solar glass on the front side of Conergy modules
raises ultraviolet (UV) resistance and improves insulation. The Aluminium frames
provide high resistance from corrosion and other metallic reactions when exposed to
the environment. Conergy modules are provided with general 5 year warranty with
12 year warranty on 90 % of the minimum power and 25 year warranty on 80 % of
the minimum power. The modules also have power tolerance of 31 %.
75
Inverter selection was made from 3 common inverter models; Energrid, Sunny mini
central and Sunny boy. 5 kW Sunny boy was only available with 60 Hz output but
one with 50 Hz rating was required. Based on PVSYST designs, Energrid was
technically better option than Sunny mini central because for different array
configurations the maximum operating power was greater than Sunny mini central.
In addition to that, Energrid has DC input voltage range (180 – 450) V with
maximum voltage input of 500 V compared with Sunny mini central input voltage
range (246 - 480) V and maximum input voltage of 540 V. The lower bound for the
input voltage of Energrid would enable the conversion of solar energy to electrical
energy even during not much bright hours of a day. The inverter weight is 32 Kg
(410mm x 180mm x 510 mm) and can provide output at frequency of either 50 Hz or
60 Hz. It has 4 DC inputs suitable to cater for any future expansion of the PV array.
7.5 Outline of Inverter technology
In grid-connected photovoltaic power systems, the DC output power for the
photovoltaic array has to be converted into the AC power of the utility power system.
Under this condition, an inverter to convert DC power into AC power is required.
The two main types of inverter technology available are line commutated and self
commutated inverters.
A line commutated inverter uses a switching device like a commutating thyristor that
can control the timing of turn-on while it cannot control the timing of turn-off by
itself. Turn-off should be performed by reducing circuit current to zero with the help
of supplemental circuit or source. Conversely, a self-commutated inverter is
characterized in that it uses a switching device that can freely control the ON-state
and the OFF-state, such as Insulated Gate Bipolar Transistor (IGBT) and Metal
Oxide Semiconductor Field Effect Transistor (MOSFET).
Self-commutated inverters can freely control the voltage and current waveform at the
AC side, and adjust the power factor and suppress the harmonic current, and is
highly resistant to utility system disturbance. Due to advances in switching devices,
most inverters for distributed power sources such as photovoltaic power generation
now employ a self-commutated inverter.
76
Self-commutated inverters include voltage and current types. The voltage type is a
system in which the DC side is a voltage source and the voltage waveform of the
constant amplitude and variable width can be obtained at the AC side. The current
type is a system in which the DC side is the current source and the current waveform
of the constant amplitude and variable width can be obtained at the AC side. In the
case of photovoltaic power generation, the DC output of the photovoltaic array is the
voltage source, thus, a voltage type inverter is employed.
The voltage type inverter can be operated as both the voltage source and the current
source when viewed from the AC side, only by changing the control scheme of the
inverter. When control is performed as the voltage source (the voltage control
scheme), the voltage value to be output is applied as a reference value, and control is
performed to obtain the voltage waveform corresponding to the reference value.
Pulse width modulation (PWM) control is used for waveform control. This system
determines the switching timing by comparing the waveform of the sinusoidal wave
to be output with the triangular waveform of the high-frequency wave, leading to a
pulse row of constant amplitude and a different width. In this system, a waveform
having less lower-order harmonic components can be obtained.
A self commutated inverter was selected for this project so that the PV system can
continue to operate in isolation even if the grid is down. Its features include 240V
single phase AC output at 50 Hz, 2 maximum power point tracking (MPPT) high
frequency converters followed by a rectifier, capacitor storage, a DC link and a DC
to AC grid connected output stage.
Finally, though the inverter technologies nowadays are very advanced, the capital
cost is an important element when considering the economics of PV power systems.
7.6 Incentives and Subsidies for PV
Feed-in-tariffs (FiTs) which have fueled many energy markets over the world in the
recent years is an explicit monetary reward for producing PV electricity. It is a
77
payment for electricity which is greater than the standard price paid to non-
renewable resource based electricity generators.
In Germany, the “Feed-in-Law” of 2004 permits customers to receive preferential
tariffs for solar generated electricity depending on the nature and size of the
installation. The feed-in-law fixes tariff over a 20 year period from commissioning
of a project and for roof mounted grid connected PV systems it was initially 0.481
€/kWh in 2004. The FiT is based on annual reduction and for roof mounted PV
electricity it is a 5 % reduction per annum whereas for grounded mounted PV
systems it is 6.5 % per year (European Union PV Status report 2009).
Similarly, according to European Union PV Status report 2009, French government’s
intention to increase the use of solar generated electricity 400 times by 2020 to a
total installed capacity of 5.4 GW has resulted in general feed-in tariffs remaining at
0.30 €/kWh for the next 20 years. In addition to that, for building-integrated PV
installations, there is a supplement of 0.25 €/kWh. If similar incentives are provided
for the building-integrated PV projects in Fiji, then significant growth in the grid-tied
PV power systems can be anticipated. However, the FiT incentive does not help
directly with high capital costs of PV systems but it guarantees electricity tariff
above the standard tariff over a number of years and FiTs can be used in proposals to
more easily secure funding for PV projects.
FiTs in Fiji’s energy sector can be applied in different contexts. It can be applied to
all power produced by the PV system or only applied to any additional power above
the needs of the customer. FiT can also be based on the benefits that PV will add to
the FEA grid, peak demand of electricity or line support. For larger grid connected
PV systems government should even consider a standard reward that could be a
certain multiple of the retail electricity price, either fixed for few years or could be
based on annual reduction of the tariff.
The FiT itself can be funded sustainably, whereby it is paid by a tax levied to all
electricity users instead of being sourced from government budgets, which can
change subject to government policy changes and priorities. In this way, the FiTs will
not be a burden for the tax payers.
78
Introducing attractive FiTs based on reducing tariff amount over time e.g. Germany,
could well be a temporary mechanism to stimulate growth in electricity generation
from grid connected PV systems. But if prices for PV system components do not
come down as the technology expands, or if the subsidy program itself is not directly
helping the local economy and instead PV system equipments are bought from
overseas countries, then not much progress in PV system installation could be
realized.
On the other hand, annual reduction of FiTs will encourage investors to invest early
and will ensure that PV systems are of high quality and perform well since funding
for the system is guaranteed. It will also force PV power producers to improve
overall power system efficiency as the annual reduction of the benefit will encourage
investors to acquire the best technology that will give them the greatest return. This
incentive may be targeted at commercial entities and large scale IPPs.
To attract groups with limited capital flow such as households, community based
organisations, schools particularly tertiary institutes and small businesses to invest in
renewable energy projects, the government can consider FiT combined with some
direct capital subsidy. Alternatively, government can decide to use direct capital
subsidies, renewable portfolio standards, green electricity schemes, tax breaks or
some combination instead of the FiT. Generally, using a type of subsidy other than
the FiT, progress in the industry would generally be slow but more constant and
predictable e.g. Germany, Italy, Korea, France, Portugal, Spain and Netherlands.
7.7 Issues with Feed-in Tariffs
The issue of where exactly to set the FiT is a major problem. Setting the FiT too high
will result in overheated markets and if it is set too low the investment in PV will be
negligible. This had been the case in Fiji before June 2010 when the tariff offered to
IPPs was between 8 to 13 cents per unit only. However, the current tariff structure
allows a minimum tariff of $0.27/kWh and also provides the incentive to encourage
investments away from the usual business centres and where higher tariffs could be
offered by FEA.
79
Even with higher tariffs now offered to IPPs, the market share of grid connected PV
generated electricity in Fiji is not expected to change significantly because the capital
costs remain unchanged. One way to increase PV installations could be offering
higher FiT to a specific market segment such as grid-tied PV at the beginning, and
then later expand to other segments such as hydro and wind.
Furthermore, even high levels of FiT rewards may not be proportional to market size,
but are rather sensitive to an incentive threshold that investors can be comfortable
with. Other important features in a sound FiT plan should include longevity and
stability i.e. there should not be mistrust between the investor and the government,
regarding the support for a PV subsidy, especially because of the high initial cost and
predicted length of operation of PV system.
7.8 Climate Change Mitigation
Global carbon emissions are rising at an exponential rate and there is a need for a
shift in energy supply from fossil fuels to renewable energy. Uses of renewable
energy helps in mitigating effects of climate changes by stabilizing green house gas
(GHG) concentrations in the atmosphere. The principle GHGs are water vapor
(H2O), carbon dioxide (CO2), methane (CH4), nitrous oxide (N2O) and sulphur
dioxide (SO2). Water vapor behaves rather differently from other GHGs and is better
regarded as part of the climate than an outside influence on it. Other less significant
GHGs include chlorofluorocarbons (CFCs), halocarbons (HFCs) and
perfluorocarbons (PFCs).
Carbon dioxide is the most abundant GHG but its Global Warming Potential (GWP)
is lower than other GHGs. Each tonne of CH4 contributes 21 times as much to
global warming as each tonne of CO2 i.e. GWP of methane is 21. The GWP of N2O
is 310 and for SO2 and other Sulphur fluorides e.g. Sulphur hexa fluorides (SF6) the
GWP is above 23900 (IPCC 4AR WG1 TS sec.TS2).
Thus, comparing this 5 kW PV project with a diesel generator, it would help
decrease carbon dioxide emissions to the environment by 7720 kg/y, sulphur dioxide
80
by 33.5 kg/y and nitrous oxides by an amount of 16.4 kg/y. The total reduction per
annum would be 7759.43 kg CO2eq per annum.
This project would provide emission reductions against what would otherwise occur
if a diesel generator is used and hence could qualify to earn Certified Emission
Reduction (CER) credits under the Clean Development Mechanism (CDM) projects
as defined in article 12 of the Kyoto protocol. Thus considering the value of 1 tonne
of CO2eq as USD30.00 (adapted from: http://cdm.unfccc.int/about/index.html), the
value of carbon credits from this PV project would amount to US$23.28 per annum.
This is indicative of the scope in Fiji for generating funds for the mitigation of
climate change under the CDM.
81
CHAPTER 8 CONCLUSION and RECOMMENDATIONS 8.1 Conclusions
Accurate and long term solar resource data is vital for assessing the site potential for
photovoltaic applications. The findings in this project are based on 2008 and 2009
solar data with an average irradiation of 3.94 kWh/m2/day. The software used for
design was PVSYST while HOMER was used for evaluating the techno-economic
viability of PV systems.
The optimum size of the power system for the C-Block at Fiji National University
Samabula Campus was a 5 kW grid-connected photovoltaic system at a cost of
$0.698/kWh. The power output from this 5 kW PV system represents 31 % of
renewable energy contribution to the total power demand of the building. The simple
payback period is 32.5 years, which is greater than the system lifetime of 25 years
because of the low feed-in-tariffs for renewable energy projects in Fiji. Therefore, it
is not an economically viable investment to consider.
Economic analysis of the PV system was also done using the net present cost of
energy (NPC) analysis method, cost of energy (COE) and cost of energy levelized
(COEL) method which yielded $0.698/kWh, $0.64/kWh and $0.72/kWh
respectively. The unit costs of electricity from all the three economic analysis
methods are similar and almost double the cost of electricity supplied by the FEA. In
common with other renewable energy sources the cost of electricity generated from
the PV system is dominated by the capital cost of the system making it non-
competitive with the present conventional forms of electricity generation.
The PV array designed has 7 modules in series and 4 parallel strings, occupying total
roof area of 36 m2. The weight of these 28 modules would be 420 kg i.e. 11.67 kg/m2.
Thus, the C block can withstand this weight as well as the additional weight of other
mounting structures. The solar panels will be facing north and mounted at 180 tilt to
optimise the use of available solar resource and also to control the economic costs
associated with maintenance of tracking mechanisms.
82
Finally, one of the major obstacles affecting the progress in the use of renewable
resources for power generation is the high capital costs of the technologies despite it
being available without any duty charges in Fiji. However, with the technological
advances of PV systems coupled with the escalating fossil fuel prices, grid tied PV
systems are becoming increasingly viable option for electricity generation. Thus, as
the era of cheap oil draws to a close with the global need to reduce carbon emissions,
other energy options must be developed which are sustainable and have minimum
ecological impact.
8.2 Recommendations
From the design and techno-economic analysis undertaken, the researcher
recommends that the implementation of grid connected PV systems should be
genuinely pursued in Fiji and research needs to be done on the electrical effects of
connecting small power producers directly to the FEA grid. It is also recommended
that further research be done on the introduction of feed-in tariffs and its impact on
the energy sector in Fiji.
83
BIBLIOGRAPHY
Arnulf, J. 2009. PV Status Report 2009. Research, Solar Cell Production and Market
Implementation of Photovoltaics. European Commission, DG Joint Research Centre,
Institute for Energy, Renewable Energy Unit Via Enrico Fermi; TP 450 I – 21027
Ispra (VA), Italia
Asian Development Bank Report, 2009. ADB and Fiji Islands fact sheet, pg 1- 4.
Suva, Fiji.
Bradford, T. Solar Revolution - The Economic Transformation of the local Global Energy
Industry, Cambridge, Massachussetts: The MIT Press, 2006.
Boxwell, M. 2009. Solar Electricity handbook. A simple practical guide to using
electric solar panels and designing and installing photovoltaic solar PV systems.
Code Green Publishing, UK.
B.Marion, J.Adelstein, K. Boyle etal. Performance Parameters for Grid-Connected
PV Systems. Conference paper prepared for the 31st IEEE Photovoltaics Specialists
Conference and Exhibition, Lake Buena Vista, Florida, January 3-7, 2005.
Communication from the Commission to the Council and the European Parliament;
Renewable Energy Road Map – Renewable energies in the 21st century: building a
more sustainable future; COM (2006) 848final (07.01.2007), {SEC (2006) 1719;
SEC (2006) 1720; SEC (2007) 12}. http://europa.eu/ (accessed 2 March 2010)
Country Energy Data of fuel consumption in Fiji. Energy Information Administration
(EIA) CO2 scenario, Department of Environment, USA.
http://www.eia.doe.gov/country/country_energy_data.cfm?fips (accessed 12 October 2010)
Dicksmith Electronics Annual catalogue, 2009. Wire and Coaxial cable specification,
pg 350. Australia.
84
Duffie, J.A and Beckman, W. A. 1991. Solar Engineering of Thermal Processes. John
Wiley & sons Ltd. London.
European Photovoltaic Industry Association, Global Market Outlook for
Photovoltaics until 2013, 2009. http://europa.eu/ (accessed 5 March 2010)
European Renewable Energy Council, “Renewable Energy Targets for Europe: 20%
by 2020” http://europa.eu/ (accessed 4 March 2010)
European Union (EU), Support to the energy sector in five ACP pacific Island
Countries. http://www.rep5.eu/(accessed 7 March 2010)
Fiji Commerce Commission press release. http://www.commcomm.gov.fj/press.html
(accessed 21 November 2010)
Fiji Electricity Authority Annual Reports. 2003- 2009.
http://www.fea.com.fj/pages.cfm/downloads/annual-reports.html (accessed 2
November 2010)
Fiji Islands Bureau of Statistics-Key Statistics report 2010.
http://www.statsfiji.gov.fj/economic/gdp_summary.htm (accessed 11 October 2010)
Fiji Islands Bureau of Statistics, 2008. Fiji Census of population and housing report,
No 45. http://www.statsfiji.gov.fj/Census2007/census07_index2.htm (accessed 11
October 2010)
Foster, S. 2008. Global Solar Photovoltaic Industry Analysis with Focus on the
Chinese Market. Department of Public Technology. Malardalen University, Sweden.
Grid-Connected Solar PV Project Final Report-Fiji Islands. Energy Unit of the
South Pacific Applied Geoscience Commission (SOPAC), Suva, Fiji. 1999
http://cdm.unfccc.int/about/index.html (accessed 5 March 2010)
85
http://www.digikey.com (accessed 20 November 2010)
http://www.rep5.eu/Project_Countries (accessed 20 November 2010)
http://www.solarbuzz.com/FastFactsGermany.htm (accessed 20 November 2010)
Intergovernmental Panel on Climate Change, 4th Assessment Report (2007). Working Group 1, TS sec.TS2.
International Energy Agency, World Energy Outlook 2008, ISBN-13:978 92 64
04560-6. http://www.iea-pvps.org. (accessed 4 March 2010)
International Energy Agency PV status report, 2009. http://www.iea-pvps.org.
(accessed 4 March 2010)
Kitamura, A., Demonstration Test Results for Grid Interconnected Photovoltaic
Power Systems, Report. IEA PVPS (International Energy Agency Implementing
Agreement on Photovoltaic Power Systems) T5-02, pp.17-27, 1999.
Lilienthal, P. 2005. Micro Power system Modelling with HOMER. National
Renewable Energy Laboratory, US Department of Energy.
Luque, A and Hegedus, S. 2002. Handbook of Photovoltaic Science and
Engineering, S. John Wiley & Sons, London.
Manwell, J. F, McGowan, J,G and Rogers, A, L. 2002. Wind Energy Explained. John
Wiley & sons Ltd, London.
Masters, M.G. 2004. Renewable and Efficient Electric Power Systems. John Wiley
& Sons, New Jersey, USA.
Natano, K. 2009. The Tuvalu Solar Power Project. Decreasing reliance on fuel and
enhancing Renewable Energy-Based Electrification in the small Island State of
Tuvalu. e8 secretariat, Montreal, Canada.
86
Natuva, P. Minister salutes State move. Fiji Sun 12/11/2010.
Olex Electrical handbook, 2009. PVC Aerial cable specification, pg 72. Australia.
http://storage.baselocation.com/olex.com.au/Media/Docs/Olex-Handbook-2009-
1092f313-0d63-4f89-bfcf-0a2336b67b5d.pdf . (accessed 15 November 2010)
Reddy, M. 2010. Determination of Fiji Electricity Authority Tariff Rates Phase II.
Press release 21 October, 2010. http://www.commcomm.gov.fj/press.html (accessed
21 October 2010)
Reliability Study of Grid Connected PV Systems. Task 7- Report IEA-PVPS T7-
08:2002. March 2002.
Siegfried, H. 2009. Grid Integration of Wind Energy Conversion Systems. John
Wiley & Sons, London.
Twidell, J and Weir, T. 2006. Renewable Energy Resources. Spon press, New York.
United Nations Development Programme Pacific Centre Annual report 2009.
http://www.undppc.org.fj/_resources/article/files/Pacific%20Centre%202009%20An
nual%20Report. (accessed 25 October 2010)
Verhoeven, B., Utility Aspects of Grid Connected Photovoltaic Power systems,
Report IEA PVPS International Energy Agency Implementing Agreement on
Photovoltaic Power Systems) T5-01, pp.12-23, 1998.
Wenham, S.R etal 2006. Applied Photovoltaics (2nd edition). UNSW centre for
photovoltaic engineering, NSW, Australia.
Wiring Rules. 2007. Australia and New Zealand Electrical Installations. Standards
Australia, Sydney and Standards New Zealand, Wellington.
Zweibel, K. 1990. Harnessing Solar Power: The Photovoltaics Challenge, Plenum
Press, New York and London.
87
Zeghbroeck, B.V. 2007. Principles of Semiconductor Devices.
http://ece.colorado.edu/~bart/book/.
88
APPENDIX PVSYST Array Designs
Tenesol Inverter