1 West 30 th Street – Kenner, Louisiana 70065 – 1610 Rev. Richard
Wilson Dr. – Kenner, Louisiana 70062
Office 504-468-7292 – Facsimile 504-468-6661
E. BEN ZAHN, III JOANNE L. MASSONY MAYOR DIRECTOR
April 5, 2021
Dear Prospective Bidder:
The City of Kenner Wastewater Department is seeking bids for
improvements to Sylvaner Sewer Lift Station, as per the
specifications provided. The bid must be submitted to the Finance
Department by Friday, April 9, 2021 at 4:00 PM. The bids may be
delivered to the Finance Department attn: Netty Orellana at 1610
Rev. Richard Wilson Drive, Kenner, LA.
Please email any questions to
[email protected].
Sincerely,
Gregory Carroll, Councilman District 1
Michael G. Sigur, Councilman District 2
Glenn W. Hayes, Councilman District 3
George L. Branigan, Councilman District 4
Brian Brennan, Councilman District 5
CHIEF OF POLICE
Michael J. Glaser
BID FORM
............................................................................................................................................
11-13
BID BOND
............................................................................................................................................
14-15
AFFIDAVIT
...............................................................................................................................................
16
AFFIDAVIT-EMPLOYMENT STATUS
VERIFICATIONS…………………………………………...29
3
SECTION IV.
TECHNICAL SPECIFICATIONS
SECTION 01505 MOBILIZATION………………………………………………………………………1
SECTION 16900 PROCESS INSTRUMENTATION AND
CONTROL………………………………….20
SECTION S-004 PUMP MOTOR ………………………………………………………………………….4
SECTION S-007 DUCTILE IRON PIPE AND FITTINGS
………………………………….………...….5
SECTION S-011 DETAIL SPECIFICATIONS FOR ELECTRICAL INSTALLATION
………….…… 5
SECTION S-012 BY-PASS PUMPING …………………………………………………………….….… 1
APPENDICES
B-2 QUALIFICATION OF BIDDERS
B-3 LOUISIANA LICENSE REQUIREMENTS
B-4.01. Site Conditions
B-9 CONTRACT TIME
B-11.05. Bids to Remain Open
B-12 AWARD OF CONTRACT
B-13 EXECUTION OF AGREEMENT
B-15 WORK SCHEDULING
B-18 PURPOSE AND INTENT OF PROJECT
B-19 PERFORMANCE AND PAYMENT BOND
B-20 FORMS TO BE COMPLETED
5
limitations affecting the bidding are contained in the various
contract documents, and are not necessarily
repeated in these instructions. The following is a partial list of
applicable provisions and their locations:
Availability of Land General Conditions and Division 1
Bonds and Insurance General and Supplemental Conditions
Definitions General and Supplemental Conditions
Detailed Description of the Work Division 1
Liquidated Damages Agreement
Retainage Agreement and Supplemental Conditions
Subsurface Investigations General and Supplemental Conditions
B-2 QUALIFICATIONS OF BIDDERS. Bidders may be required to submit
evidence that they
have a practical knowledge of the particular Work bid upon, and
that they have the financial resources to
complete the proposed Work.
In determining the Bidder's qualifications, the following factors
will be considered: Work previously
completed by the Bidder and whether the Bidder (a) maintains a
permanent place of business, (b) has
adequate plant and equipment to do the Work properly and
expeditiously, (c) has the financial resources
to meet all obligations incidental to the Work, and (d) has
appropriate technical experience.
Each Bidder may be required to show that former work has been
handled and that no just claims are
pending against such work. No Bid will be accepted from a Bidder
who is engaged in any work which
would impair the Bidder's ability to perform or financially manage
this Work.
B-3 LOUISIANA LICENSE REQUIREMENTS. State regulations require that
any prospective
Bidder on construction contracts of $50,000.00 or greater obtain a
Louisiana Contractor's License prior
to either acquiring bidding documents or submitting a bid. Each
prospective Bidder shall produce
evidence that the Bidder possesses the proper Louisiana
Contractor's License before the Bidder will be
allowed to acquire copies of bidding documents, all in accordance
with LSA-R.S.37:2157D.
Contractors shall have a valid current Louisiana Municipal and
Public Works
Construction Contractor License.
B-4 FAMILIARIZATION WITH THE WORK. Before submitting a Bid, each
prospective Bidder
shall become familiar with the Work, the site where the Work is to
be performed, local labor conditions
and all laws, regulations and other factors affecting performance
of the Work. The Bidder shall
carefully correlate its observations with requirements of the
Contract Documents and otherwise become
satisfied with the expense and difficulties attending performance
of the Work. The submission of a Bid
will constitute a representation of compliance by the Bidder. There
will be no subsequent financial
adjustment for lack of such familiarization.
B-4.01. Site Conditions. Each Bidder shall visit the site of the
Work and become completely informed
relative to construction hazards and procedure, the availability of
lands, the character and quantity of
surface and subsurface materials, utilities to be encountered, the
arrangement and condition of existing
structures and facilities, the procedure necessary for maintenance
or uninterrupted operation of existing
facilities, the character of construction equipment and facilities
needed for performance of the Work,
and facilities for transportation, handling, and storage of
materials and equipment. All such factors shall
be properly investigated and considered in the preparation of the
Bid.
6
B-5. INTERPRETATIONS. All questions about the meaning or intent of
the Contract Documents
shall be submitted to Design Professional in writing. Only answers
furnished by formal written
Addenda will be binding. Oral and other interpretations or
clarifications will be without legal effect.
B-6. TAXES AND PERMITS. Attention is directed to the requirements
of the General and
Supplementary Conditions regarding payment of taxes and obtaining
permits. All taxes that are lawfully
assessed against Owner or Contractor in connection with the Work
shall be paid by the Contractor. The
bid prices shall include all such taxes and the costs of all
required permits.
B-7. BID SECURITY. The amount of bid security is as stated in the
Invitation to Bid. The
required security must be in the form of a certified or bank
cashiers check or bid bond. The bid bond
must be executed by a surety meeting the requirements set forth in
General Conditions.
The bid security shall be made payable without condition to City of
Kenner, Louisiana, the Owner. The
bid security may be retained by and shall be forfeited to the Owner
as liquidated damages if the Bid is
accepted and a contract based thereon is awarded and the Bidder
should fail to enter into a contract in
the form prescribed, with legally responsible sureties, within
thirty (30) days after such award is made
by Owner.
B-8 RETURN OF BID SECURITY. The bid security of the successful
Bidder will be retained
until execution of the Agreement and furnishing of the required
Contract Security, whereupon checks
furnished as bid security will be returned; if the successful
Bidder fails to execute and deliver the
Agreement and furnish the required Contract Security within thirty
(30) days of the Notice of Award,
Owner may annul the Notice of Award and the bid security of that
Bidder will be forfeited. The bid
security of any Bidder whom Owner believes to have a reasonable
chance of receiving the award may be
retained by Owner until the seventh (7th) day after the executed
Agreement is delivered by Owner to
Contractor and the required Contract Security is furnished but
shall not exceed sixty (60) days after the
Bid opening. Checks furnished as bid security by other Bidders will
be returned within seven (7) days
of the Bid opening.
B-9. CONTRACT TIME. The Contract Time is an essential part of the
contract and it will be
necessary for each Bidder to satisfy Owner of its ability to
complete the Work within the time set forth
in the Bid Form. Provisions for delays, liquidated damages, and
extensions of time are set forth in the
General and Supplementary Conditions.
B-10. SUBCONTRACTORS. Within seven (7) days after Bids are opened,
the apparent low
Bidder, and any other Bidder so requested, shall submit a list of
all Subcontractors expected to be used
in the Work. The use of Subcontractors listed by the Bidder and
accepted by Owner prior to the Notice
of Award will be required in the performance of the Work.
B-10.01. Suppliers. The list of subcontractors shall also include
the suppliers and manufacturers of
principal items of materials and equipment the Bidder expects to
use in the work unless such suppliers
or manufacturers are named in the bid.
7
B-11. BIDS.
B-11.01. Bid Form. A separate copy of the Bid Form is provided for
purposes of submitting a bid. Bid
forms must be completed in ink. Bids by corporations must be
executed in the corporate name by the
appropriate corporate officer, accompanied by evidence of authority
to sign, and attested by the
secretary or an assistant secretary. The state of incorporation
shall be shown below the corporate name.
Bids by partnerships must be executed in the partnership name and
signed by a partner; title and the
official address of the partnership must be shown below the
signature. Bids by joint ventures shall be
signed by each participant in the joint venture or by an authorized
agent of each participant.
The names of all persons signing must be legibly printed below
their signature. A Bid by a person who
affixes to his/her signature the word "president", "secretary",
"agent", or other designation without
disclosing his/her principal may be held to be the Bid of the
individual signing. When requested by
Owner, evidence of the authority of the person signing shall be
furnished.
All blank spaces in the Bid Form shall be filled. A bid price shall
be indicated for each lump sum item
and/or unit price item listed therein. Bids received without all
items completed may be considered non-
responsive.
The Bid shall contain an acknowledgment of receipt of all Addenda,
the numbers and dates of which
shall be filled in on the Bid Form.
No alterations in Bids, or in the printed forms therefore, by
erasures, interpolations, or otherwise will be
acceptable unless each such alteration is signed and initialed by
the Bidder; if initialed, Owner may
require the Bidder to identify any alteration so initialed.
B-11.02. Bid Pricing. The Bidder shall complete the schedule of all
unit and lump sum prices included
in the Bid Form and shall accept all fixed unit prices listed
therein.
The total Bid will be determined as the sum of the products of the
estimated quantity of each item and
the unit price bid. The final Contract Price will be subject to
adjustment according to final measured,
used, or delivered quantities as provided in Division 1, and the
unit prices in the bid will apply to such
final quantities except that unit prices will be subject to change
by Change Order if quantities vary more
than twenty-five percent (25%).
B-11.03. Submission of Bids. Two copies of the bid forms must be
submitted with the Bid.
Each Bid and accompanying data shall be enclosed in a sealed opaque
envelope or wrapping, addressed
to:
Kenner, Louisiana 70062
and identified on the outside with the Bidder's name and Louisiana
Contractor's license number and with
the words Sylvaner Lift Station Improvements.
If the bid is sent by mail, the sealed envelope shall be enclosed
in a separate mailing envelope with the
notation "BID ENCLOSED" on the face thereof.
8
Bids shall be deposited at the designated location prior to the
time and date for receipt of Bids indicated
in the Invitation to Bid, or the modified time and date indicated
by Addendum. Bids received after the
time and date for receipt of Bids will be returned unopened.
Bidder shall assume full responsibility for timely delivery at the
location designated for receipt of Bids.
Oral, telephone, or telegraph Bids are invalid and will not receive
consideration.
No Bidder may submit more than one Bid. Multiple Bids under
different names will not be accepted
from one firm or association.
B-11.04. Modification and Withdrawal of Bids. Bids may be modified
or withdrawn by an appropriate
document duly executed (in the manner that a Bid must be executed)
and delivered to the place where
Bids are to be submitted at any time prior to the opening of
Bids.
No Bids may be withdrawn after the scheduled closing time for
receipt of Bids, nor for at least forty-five
(45) days thereafter, except that Bids containing patently obvious
mechanical, clerical, or mathematical
errors may be withdrawn by the Bidder if clear and convincing
sworn, written evidence is furnished to
the Owner within 48 hours of the bid opening excluding Saturdays,
Sundays, and legal holidays, in
accordance with the Louisiana Public Bid Law. Under no
circumstances may a Bidder be allowed to
raise any prices as contained in the initial Bid. A Bidder who
attempts to withdraw a Bid under
provisions of this section shall be allowed to resubmit a Bid on
the same contract in the event that it is
re-advertised.
B-11.05. Bids to Remain Open. All Bids shall remain open for
forty-five (45) days after the day of the
Bid opening. Owner shall release Bids and return Bid securities as
specified in this section under
"Return of Bid Security".
B-12. AWARD OF CONTRACT. Owner shall award a contract to the Bidder
who, in Owner's
judgment, is the lowest responsive, responsible Bidder. Owner
reserves the right to reject any or all
Bids, to waive informalities, and to reject nonconforming,
non-responsive, or conditional Bids.
In evaluating Bids, Owner shall consider the qualifications of the
Bidders, whether or not the Bids
comply with the prescribed requirements, alternatives and unit
prices if requested in the Bid Form.
Owner may consider the qualifications and experience of
Subcontractors and may reject the Bid of any
Bidder who does not pass any such evaluation to Owner's
satisfaction. The rejection procedure will be
in accordance with the Louisiana Public Bid Law, LSA-R.S. 38:2212
et seq.
If the contract is awarded, Owner shall do so within forty-five
(45) days of the Bid Opening, unless the
successful Bidder has agreed in writing to hold its bid price for a
longer period.
B-13 EXECUTION OF THE AGREEMENT. No less than seventeen (17) days
after award,
Design Professional shall furnish to Contractor six (6) copies of
the Agreement and other Contract
Documents bound therewith. Within twelve (12) days, Contractor
shall execute the Agreement, insert
executed copies of the required bonds and Power of Attorney and
submit all copies to Owner, together
with required Certificates of Insurance. The date of contract on
the Agreement and Bond forms shall be
left blank for filling in by Owner. The certification date on the
power of attorney also shall be left blank
for filling in by Owner.
9
Owner shall execute the Contract Documents, insert the date of
contract on the Agreement, Bonds, and
Power of Attorney, and return copies to Design Professional for
review and distribution.
Contractor shall be responsible for filing one complete copy of the
executed Contract Documents with
the Recorder of Mortgages in Jefferson Parish, and promptly furnish
recordation information to Owner.
No payment shall be made until this requirement is fulfilled.
B-16. LOCAL MATERIALS AND FIRMS. By statutory authority, preference
is hereby given to
materials, supplies, and provisions produced, manufactured, or
grown in Louisiana, quality being equal
to articles offered by competitors outside of the State (LSA R.S.
38:2251), and preference is hereby
given to firms doing business in the State of Louisiana (LSA R.S.
38:2253).
Please refer to Supplementary Conditions, Paragraph SC-17.
B-17. WORK SCHEDULING. Because of the nature of this contract, it
may be necessary for the
Contractor to respond to emergencies immediately upon
notification.
B-18. WORK ADJACENT TO PRIVATE PROPERTY. The Contractor shall be
aware that work may
be performed adjacent to private property. The Contractor shall
notify, prior to the start of work in the
area, all property owners adjacent to and along the route of
construction by means of either a printed
circular or form letter giving the general details of the work. The
letter shall also include names and
telephone numbers for key project personnel of the Contractor so
that property owners may report
problems. These contact telephone numbers shall be given so that
appropriate personnel may be
contacted 24 hours a day, seven days a week.
B-19. USE OF POTABLE WATER. If the Contractor intends to use water
from the Parish water
system, Contractor shall first obtain a water meter from the
Jefferson Parish Department of Water. The
Contractor will be responsible for all costs incurred with water
usage.
B-20. PURPOSE AND INTENT OF PROJECT: Improvements to Sylvaner Lift
Station per below:
• Ductile iron piping & fittings removal &
replacement
• Installation of new emergency pump out
• New pump motors, skids, belts, sheaves & guards
• New duplex control panel
• Wood fencing and gate removal & replacement (Alternate)
• Existing wet well cleaning (Alternate)
B-21. PERFORMANCE AND PAYMENT BOND. The successful Bidder will be
required to furnish a
Performance Bond guaranteeing faithful performance and a Labor and
Materials Payment Bond
guaranteeing the payment of all bills and obligations arising from
the performance of the contract.
Companies providing the bonds shall have a minimum rating of A, an
A.M. Best Rating Classification.
The amount of these bonds shall be the total contract amount.
10
B-22 SUPPLEMENTARY INSURANCE. The successful Bidder will be
required to furnish insurance
that meets the requirements set out in the General and Supplemental
Conditions. A number of the
insurance requirements are contingent on certain categories of risk
being present as described
herein. While the nature of the insurable risk on the project may
change, an initial assessment of the
project shows that the contingent insurances below will be required
for this project.
a) Builder's Risk Insurance as detailed in SC-2.07 (Required)
b) Contractor’s Pollution (Owner's Protective Liability) as
detailed in SC-2.05 (Required)
c) Automobile Coverage for the Transpiration of Pollutants as
detailed in SC-2.02(e)
(Required)
e) Maritime Liability (Not Currently Required)
f) Umbrella Liability Policy as detailed in SC-2.04 (Not Currently
Required)
END OF SECTION
TO: _City of Kenner______________________________
_Kenner, LA 70062___________________________ (Owner to provide name
and address of owner)
BID FOR: _Sylvaner Lift Station Improvements_________
__________________________ ________________________
____________________________ ______________________
(Owner to provide name of project and other identifying
information)
The undersigned bidder hereby declares and represents that she/he:
a) has carefully examined and understands the Bidding
Documents, b) has not received, relied on, or based his bid on any
verbal instructions contrary to the Bidding Documents or
any addenda, c) has personally inspected and is familiar with the
project site, and hereby proposes to provide all labor,
materials, tools, appliances and facilities as required to perform,
in a workmanlike manner, all work and services for the
construction and completion of the referenced project, all in
strict accordance with the Bidding Documents prepared by:
Digital Engineering & Imaging, Inc. and dated: March, 2021
(Owner to provide name of entity preparing bidding
documents.)
Bidders must acknowledge all addenda. The Bidder acknowledges
receipt of the following ADDENDA: (Enter the number
the Designer has assigned to each of the addenda that the Bidder is
acknowledging _______________________________________ .
TOTAL BASE BID: For all work required by the Bidding Documents
(including any and all unit prices designated “Base
Bid” * but not alternates) the sum of:
Dollars ($ )
ALTERNATES: For any and all work required by the Bidding Documents
for Alternates including any and all unit prices
designated as alternates in the unit price description.
Alternate No. 1 (Owner to provide description of alternate and
state whether add or deduct) for the lump sum of:
Clean Existing Wet Well Dollars ($ )
Alternate No. 2 (Owner to provide description of alternate and
state whether add or deduct) for the lump sum of:
Remove and Replace Fence Dollars ($ )
)
Alternate No. 3 (Owner to provide description of alternate and
state whether add or deduct) for the lump sum of:
N/A Dollars ($
NAME OF AUTHORIZED SIGNATORY OF BIDDER:
TITLE OF AUTHORIZED SIGNATORY OF BIDDER:
SIGNATURE OF AUTHORIZED SIGNATORY OF BIDDER **:
EMAIL ADDRESS:
___________________________________________________________________________________
DATE: _______________________
THE FOLLOWING ITEMS ARE TO BE INCLUDED WITH THE SUBMISSION OF THIS
LOUISIANA
UNIFORM PUBLIC WORK BID FORM: * The Unit Price Form shall be used
if the contract includes unit prices. Otherwise it is not required
and need not be included with the
form. The number of unit prices that may be included is not limited
and additional sheets may be included if needed.
** A CORPORATE RESOLUTION OR WRITTEN EVIDENCE of the authority of
the person signing the bid for the public work as
prescribed by LA R.S. 38:2212(B)(5).
BID SECURITY in the form of a bid bond, certified check or
cashier’s check as prescribed by LA R.S. 38:2218(A) attached to and
made a
part of this bid.
UNIT PRICE FORM
TO: City of Kenner BID FOR: Sylvaner Lift Station Improvements
_________
Finance Department ____________________________
_____________________
Kenner, LA 70065
(Owner to provide name and address of owner) (Owner to provide name
of project and other identifying information)
UNIT PRICES: This form shall be used for any and all work required
by the Bidding Documents and described as unit prices. Amounts
shall be stated in figures and only in figures.
DESCRIPTION: Mobilization & Construction Layout Base Bid or
Alt.# ___
REF. NO. QUANTITY: UNIT OF MEASURE: UNIT PRICE UNIT PRICE EXTENSION
(Quantity times Unit Price)
1 1 Lump Sum
DESCRIPTION: New Duplex Control Panel (240V, 3 phase) with wiring,
conduits & disconnect Base Bid or Alt.# ___
QUANTITY: UNIT OF MEASURE UNIT PRICE UNIT PRICE EXTENSION (Quantity
times Unit Price)
2 1 Lump Sum
DESCRIPTION: Install New Pump Motors, Skids, Belts, Sheaves &
Guards Base Bid or Alt.# ______
REF. NO. QUANTITY: UNIT OF MEASURE UNIT PRICE UNIT PRICE EXTENSION
(Quantity times Unit Price)
3 1 Lump Sum
DESCRIPTION: Install Emergency Pump Out Base Bid or Alt.# ___
REF. NO. QUANTITY: UNIT OF MEASURE UNIT PRICE UNIT PRICE EXTENSION
(Quantity times Unit Price)
4 1 Lump Sum
DESCRIPTION: Ductile Iron Pipe & Fittings, and Miscellaneous
Parts Base Bid or Alt.# ___
REF. NO. QUANTITY: UNIT OF MEASURE UNIT PRICE UNIT PRICE EXTENSION
(Quantity times Unit Price)
5 1 Lump Sum
DESCRIPTION: Level Controls, Backup Float & Electrical Conduits
(Include Cables & Wiring) Base Bid or Alt.# ___
REF. NO. QUANTITY: UNIT OF MEASURE UNIT PRICE UNIT PRICE EXTENSION
(Quantity times Unit Price)
6 1 Lump Sum
DESCRIPTION: By-Pass Pumping Base Bid or Alt.# ___
REF. NO. QUANTITY: UNIT OF MEASURE UNIT PRICE UNIT PRICE EXTENSION
(Quantity times Unit Price)
7 1 Lump Sum
Wording for “DESCRIPTION” is to be provided by the Owner. All
quantities are estimated. The contractor will be paid based upon
actual quantities as verified by the Owner.
13
UNIT PRICE FORM
TO: City of Kenner BID FOR: Sylvaner Lift Station Improvements
_________
Finance Department ____________________________
_____________________
Kenner, LA 70065
(Owner to provide name and address of owner) (Owner to provide name
of project and other identifying information)
UNIT PRICES: This form shall be used for any and all work required
by the Bidding Documents and described as unit prices. Amounts
shall be stated in figures and only in figures.
DESCRIPTION: Clean Existing Wet Well Base Bid or Alt.# _1__
REF. NO. QUANTITY: UNIT OF MEASURE: UNIT PRICE UNIT PRICE EXTENSION
(Quantity times Unit Price)
8 1 Lump Sum
DESCRIPTION: Remove and Replace Fence Base Bid or Alt.# _2__
REF. NO. QUANTITY: UNIT OF MEASURE. UNIT PRICE UNIT PRICE EXTENSION
(Quantity times Unit Price)
9 41 Linear Feet
Wording for “DESCRIPTION” is to be provided by the Owner. All
quantities are estimated. The contractor will be paid based upon
actual quantities as verified by the Owner.
14
KNOW ALL MEN BY THESE PRESENTS that we, the undersigned,
_____________________
as PRINCIPAL, and as SURETY, are held and firmly bound
unto the City of Kenner, State of Louisiana, acting herein by and
through the City Council, the
governing authority for said City, hereinafter called the "OWNER",
in the penal sum of:
DOLLARS ($ ) lawful money
of the United States, for the payment of which sum well and truly
to be made, we bind ourselves,
our heirs, executors, administrators, successors, and assigns,
jointly and severally, firmly by these
presents.
THE CONDITION OF THIS OBLIGATION IS SUCH, that whereas the
Principal has submitted
the accompanying Bid dated _________________, _______, for Sylvaner
Lift Station
Improvements
NOW, THEREFORE, if the Principal shall not withdraw said Bid within
the period specified
herein after the opening of the same or, if no period be specified,
within sixty (60) days after the
said opening, and shall within the period specified therefor or, if
no period be specified, within
twelve (12) days after the prescribed forms are presented to him
for signature, enter into a written
Contract with the OWNER in accordance with the Bid as accepted, and
give bond with good
sufficient surety and sureties, as may be required, for the
faithful performance and proper
fulfillment of such Contact; or in the event of the withdrawal of
said Bid within the period
specified, or the failure to enter into such Contract and give such
bond within the time specified,
if the Principal shall pay the OWNER the difference between the
amount specified in said bid and
the amount for which the OWNER may procure the required work or
supplies, or both, if the latter
be in excess of the former, then the above obligation shall be void
and of no effect, otherwise, to
remain in full force and virtue.
IN WITNESS WHEREOF, the above bounded parties have executed this
instrument under
their several seals this day of , , and these presents signed by
its
undersigned representative, pursuant to authority of its governing
body.
In Presence of:
________________________________
______________________________
ATTEST:
BY:__________________________
State of :______________________________
*Power-of-Attorney for person signing for surety company must be
attached to bond.
16
_________________________________________________________________________________
(Name)
who after being by me duly sworn and deposed said that he is the
fully authorized ______________
(Title)
(Name of Bidder)
submitted a bid for Sylvaner Lift Station Improvements
was received by City of Kenner on _________________ , 2021 and said
affiant further said:
(1) The bidder employed no person, corporation, firm, association,
or other organization, either directly or indirectly, to
secure the public contract under which he received payment, other
than persons regularly employed by the bidder
whose services in connection with the construction of the public
building or project or in securing the public contract
were in the regular course of their duties for bidder, and
(2) That no part of the contract price received by bidder was paid
or will be paid to any person, corporation, firm,
association, or other organization for soliciting the contract,
other than the payment of their normal compensation to
persons regularly employed by the bidder whose services in
connection with the construction of the public building
or project were in the regular course of their duties for
bidder.
(3) Said bid is genuine and the bidder has not colluded, conspired,
or agreed, directly or indirectly, with any other bidder
to offer a sham or collusive bid.
(4) Said bidder has not in any manner, directly or indirectly,
agreed with any other person to fix the bid price of affiant
or any other bidder, or to fix any overhead profit or cost element
of said bid price, or that of any other bidder, or to
induce any other person to refrain from bidding.
(5) Said bid is not intended to secure an unfair advantage of
benefit from the Parish of Jefferson or in favor of any
person
interested in the proposed contract.
(6) All statements contained in said bid are true and
correct.
(7) Neither affiant nor any member of his company has divulged
information regarding said bid or any data relative
thereto any other person, firm, or corporation.
SWORN TO AND SUBSCRIBED
20__. (Authorized Signature)
SAMPLE CORPORATE RESOLUTION
___________________________________________________________
HELD ON , , A QUORUM BEING THERE PRESENT, ON MOTION DULY
MADE AND SECONDED, IT WAS RESOLVED THAT ________________________,
BE AND IS
HEREBY APPOINTED, CONSTITUTED AND DESIGNATED AS AGENT AND
ATTORNEY-IN-
FACT OF THE CORPORATION WITH FULL POWER AND AUTHORITY TO ACT ON
BEHALF OF
THIS CORPORATION IN ALL NEGOTIATIONS, BIDDING, CONCERNS AND
TRANSACTIONS
WITH THE CITY OF KENNER OR ANY OF ITS AGENCIES, DEPARTMENTS,
EMPLOYEES OR
AGENTS, INCLUDING BUT NOT LIMITED TO, THE EXECUTION OF ALL BIDS,
PAPERS,
DOCUMENTS, AFFIDAVITS, BONDS, SURETIES, CONTRACTS AND ACTS AND TO
RECEIVE
AND RECEIPT THEREFOR ALL PURCHASE ORDERS AND NOTICES ISSUED
PURSUANT TO
THE PROVISIONS OF ANY SUCH BID OR CONTRACT, THIS CORPORATION
HEREBY
RATIFYING, APPROVING, CONFIRMING AND ACCEPTING EACH AND EVERY SUCH
ACT
PERFORMED BY SAID AGENT AND ATTORNEY-IN-FACT.
I HEREBY CERTIFY THE FOREGOING TO BE A TRUE AND
CORRECT COPY OF AN EXCERPT OF THE MINUTES OF
THE ABOVE DATED MEETING OF THE BOARD OF
DIRECTORS OF SAID CORPORATION, AND THE SAME
HAS NOT BEEN REVOKED OR RESCINDED.
____________________________________________________
DATE
18
AGREEMENT
THIS AGREEMENT, made the day of ______, 20__, by and between, City
of Kenner,
Jefferson Parish, Louisiana, referred to in these Contract
Documents as "Owner" acting through
its Mayor, and
_______________________________________referred
WITNESSETH:
THAT WHEREAS: in accordance with law, Owner has caused Contract
Documents to be
prepared and an Invitation to Bid to be published, for and in
connection with Sylvaner Lift Station
Improvements; and,
WHEREAS, Contractor, in response to the Invitation to Bid, has
submitted to Owner, in the
manner and at the time specified, a sealed Bid in accordance with
Instructions to Bidders; and
WHEREAS, Owner, in the manner prescribed by law, has publicly
opened, examined, and
canvassed the Bids submitted, and has determined Contractor to be
the lowest and best Bidder for
the Work and duly awarded to Contractor a contract therefore, for
the sum or sums named in
Contractor's Bid.
NOW, THEREFORE, in consideration of the compensation to be paid to
Contractor and of the
mutual agreements herein contained, the parties to these presents
have agreed and hereby agree,
Owner for itself and its successors, and Contractor for itself,
himself, or themselves, and its, his,
or their successors and assigns, and its, his, or their executors
and administrators, as follows:
ARTICLE I. All notices, letters, and other communication directed
to Owner shall be delivered or
addressed and mailed, postage prepaid to:
City of Kenner
Kenner, Louisiana 70062
The business address of Contractor given in the Bid Form and
Contractor's office in the vicinity
of the Work are both hereby designated as the places to which all
notices, letters, and other
communication to Contractor will be mailed or delivered.
Contractor may change his address at any time by written
notification to Owner.
ARTICLE II. The Contractor shall perform all Work, including the
assumption of all obligations,
duties and responsibilities necessary to the successful completion
of the contract and the furnishing
of all materials and equipment required to be incorporated in and
form a permanent part of the
Work; tools, equipment, supplies, transportation, facilities,
labor, superintendence and services
required to perform the Work; and Bond, insurance and submittals;
all as indicated or specified in
the Contract Documents to be performed or furnished by Contractor
for the Work included in and
19
covered by Owner's official award of this contract to Contractor,
such award being based on the
acceptance by Owner of Contractor's Bid.
ARTICLE III. That owner shall pay to Contractor for performance of
the Work embraced in this
contract, and Contractor shall accept as full compensation
therefore, the sum (subject to adjustment
as provided in the Contract Documents) of
________________________________________________________________________dollars
($ _________________) for all Work covered by and included in the
contract
award and designated in the foregoing Article I; payment thereof to
be made in current funds in
the manner provided in the Contract Documents.
ARTICLE IV. That Contractor shall complete all Work within 120
calendar days, after the
commencement of Contract Time (as defined in General
Conditions).
ARTICLE V. Time is an essential condition of the contract. Should
Contractor fail to perform
the Work within the Contract Time stipulated herein, Contractor
shall pay to Owner, as liquidated
damages and not as a penalty, 0.1% of the contract amount including
change orders per calendar
day of default, or $500.00 per day, whichever is greater, unless
the Contract Time is extended by
Owner.
After ENGINEER and OWNER conduct a Final Inspection of the Work, a
Punch List of
outstanding items to be completed, if any, will be issued to the
CONTRACTOR. CONTRACTOR
shall have thirty (30) calendar days to complete any outstanding
items of Work remaining to be
completed or corrected as detailed as a result of the Final
inspection. If upon expiration of said
thirty (30) calendar days the aforementioned outstanding items of
Work have not been completed,
liquidated damages in the amount of 0.1% of the contract amount
including change orders per day
will be reinstated for every day in which the outstanding items of
Work have not been completed.
In case of joint responsibility for delay in the final completion
of the Work, where two or more
separate contracts are in force at the same time and cover related
work at the same location,
liquidated damages assessed against any one Contractor will be
based upon the individual
responsibility of that Contractor for the delay as determined by,
and in the judgment of, Design
Professional.
The expiration of the Contract Time shall ipso facto constitute a
putting in default where
Contractor has failed to perform the Work, and Owner need not
formally place the Contractor in
default. Contractor hereby waives any and all notices of
default.
ARTICLE VI. Pursuant to LSA-R.S. 38:2248 (Public Contract Law),
Owner shall retain the
following percentages of each progress payment until payment is due
under the terms and
conditions governing substantial completion or final payment.
CONTRACT AMOUNT RETAINAGE
20
ARTICLE VII. That the Contract Documents which comprise the
contract between Owner and
Contractor, attached hereto and made a part of the documents listed
in Table of Contents, and the
documents identified below.
Information submitted by Contractor prior to the time Owner
issues
Notice of Award including the following:
Notice to Proceed.
Any Modifications (as defined in General Conditions) duly delivered
after execution of this
Agreement.
The Contract Drawings consist of 1 sheet and are attached to the
Contract Documents as an
Appendix. In addition, each sheet bears the following general
title:
Sylvaner Lift Station Improvements
Notices of Final Completion and Acceptance.
ARTICLE VIII. In order to induce Owner to enter into this
Agreement, and to the extent of their
applicability to the work, Contractor makes the following
representations,
1.Contractor has familiarized himself with the nature and extent of
the Contract Documents,
Work, locality, and with all local conditions and federal, state,
and local laws, ordinances, rules,
and regulations that in any manner may affect cost, progress of
performance of the Work.
2.Contractor has studied carefully all reports of investigations
and tests of subsurface and latent
physical conditions at the site or otherwise affecting cost,
progress or performance of the Work
which were relied upon by Design Professional in the preparation of
the Drawings and
Specifications and which have been identified in the Supplementary
Conditions.
3.Contractor has made or caused to be made examinations,
investigations and tests and studies
of such reports and related data in addition to those referred to
in paragraph 2 as he deems
necessary for the performance of the Work at the Contract price,
within the Contract Time and in
accordance with the other terms and conditions of the Contract
Documents; and no additional
examinations, investigations, tests, reports, or similar data are
or will be required by Contractor
for such purposes.
4.Contractor has correlated the results of all such observations,
examinations, investigations,
tests, reports, and data with the terms and conditions of the
Contract Documents.
21
5. Contractor has given Design Professional written notice of all
conflicts, errors, or
discrepancies that he has discovered in the Contract Documents and
the written resolution
thereof by Design Professional is acceptable to Contractor.
ARTICLE IX. EQUAL OPPORTUNITY CLAUSE: 40 CFR PART 8.
During the performance of this contract, the contractor agrees as
follows:
(1) The contractor will not discriminate against any employee or
applicant for employment
because of race, color, religion, sex, or national origin. The
contractor will take
affirmative action to ensure that applicants are employed, and that
employees are
treated during employment, without regard to their race, color,
religion, sex, or national
origin. Such action shall include, but not limited to, the
following: Employment,
upgrading, demotion, or transfer; recruitment or recruitment
advertising; layoff or
termination; rates of pay or other forms of compensation; and
selection for training,
including apprenticeship. The contractor agrees to post in
conspicuous places, available
to employees and applicants for employment, notices to be provided
by the contracting
officer setting forth the provisions of this equal opportunity
clause.
(2) The contractor will, in all solicitations or advertisements for
employees placed by or
on behalf of the contractor, state that all qualified applicants
will receive consideration
for employment without regard to race, color, religion, sex, or
national origin.
(3) The contractor will send to each labor union or representative
of workers with which
he has a collective bargaining agreement or other contract, or
understanding, a notice
to be provided by the agency contracting officer, advising the
labor union or worker's
representative of the contractor's commitments under this equal
opportunity clause, and
shall post copies of the notice in conspicuous places available to
employees and
applicants for employment.
(4) The contractor will comply with all provisions of Executive
Order No. 11246 of
September 24, 1965, and of the rules, regulations, and relevant
orders of the Secretary
of Labor.
(5) The contractor will furnish all information and reports
required by Executive Order No.
11246 of September 24, 1965, and by the rules, regulations, and
orders of the Secretary
of Labor, or pursuant thereto, and will permit access to his books,
records, and accounts
by the contracting agency and the Secretary of Labor for purposes
of investigation to
ascertain compliance with such rules, regulations, and
orders.
(6) In the event of the contractors noncompliance with the equal
opportunity clause of this
contract or with any of the said rules, regulations, or orders,
this contract may be
canceled, terminated, or suspended, in whole or in part, and the
contractor may be
declared ineligible for further Government contracts in accordance
with procedures
authorized in Executive Order No. 11246 of September 24, 1965, and
such other
sanctions may be imposed and remedies invoked as provided in
Executive Order No.
22
11246 of September 24, 1965, or by rule, regulation, or order of
the Secretary of Labor,
or as otherwise provided by law.
(7) The contractor will include the portion of the sentence
immediately preceding
paragraph (1) and the provisions of paragraph (1) through (7) in
every subcontract or
purchase order unless exempted by rules, regulations, or orders of
the Secretary of
Labor issued pursuant to section 204 of Executive Order No. 11246
of September 24,
1965, so that such provisions will be binding upon each
subcontractor or vendor. The
contractor will take such action with respect to any subcontract or
purchase order as
the contracting agency may direct as a means of enforcing such
provisions, including
sanctions for noncompliance: Provided, however, that in the event
the contractor
becomes involved in, or is threatened with, litigation with a
subcontractor or vendor as
a result of each direction by the contracting agency, the
contractor may request the
United States to enter into such litigation to protect the
interests of the United States.
ARTICLE X. HISTORICAL PRESERVATION CLAUSE: 36 CFR PART 800
The contractor agrees that, should evidence of historical or
archeological sites be discovered
during construction, all work in the area will cease immediately
and the owner will be informed
of the discovery. The owner will, in turn, promptly notify the
Municipal Facilities Division of the
Louisiana Department of Environmental Quality (DEQ).
After consulting with the appropriate State and Federal agencies,
the DEQ will advise the owner
of any protective measures that may be required.
ARTICLE XI. ENDANGERED SPECIES CLAUSE: ENDANGERED SPECIES ACT OF
1973,
AS AMENDED
The contractor agrees that, should plants or animals belonging to
either endangered or threatened
species be discovered in the area of construction or adjacent
areas, all work in the area will cease
immediately, and the owner will be informed of the discovery. The
owner will, in turn, promptly
notify the Municipal Division of the Louisiana Department of
Environmental Quality (DEQ).
After consulting with the appropriate State and Federal agencies,
the DEQ will advise the owner
of any protective measures that may be required.
ARTICLE XII. PRESIDENTIAL EXECUTIVE ORDERS
The contractor is required to comply with the following
Presidential Executive Orders:
(1) 11625, 12138, and 12434 - Women's and Minority Business
Enterprise;
(2) 12549 - Debarment and Suspension
(3) 11246 - Equal Employment Opportunity.
IN WITNESS WHEREOF, the parties hereto have executed this Agreement
on the date first
23
_____________________
HOLD HARMLESS AGREEMENT
If _____________________________________________ (hereafter
“CONTRACTOR”)
is the successful bidder for, Sylvaner Lift Station Improvements
then, to the fullest extent
permitted by law, CONTRACTOR shall indemnify and hold harmless the
City of Kenner,
including its elected and appointed officials, employees, servants,
volunteers, and agents,
specifically the firm of Digital Engineering & Imaging, Inc.
(collectively, “OWNER”) from
against any and all claims, demands, suits, costs, liabilities or
judgments for sums of money, and
fines or penalties asserted by any party, firm or organization for
loss of life or injury or damages
to person or property, growing out of, resulting from, or by reason
of any negligent acts, errors,
and/or omissions, by CONTRACTOR, its agents, servants or employees,
while engaged upon or
in connection with the work required to be performed by
CONTRACTOR.
Further, CONTRACTOR hereby agrees to indemnify OWNER for all
reasonable expenses
and attorneys’ fees incurred by or imposed upon OWNER in connection
therewith for any loss,
damage, injury or other casualty pursuant to this section.
CONTRACTOR further agrees to pay
all reasonable expenses and attorneys’ fees incurred by OWNER in
establishing the right to
indemnity pursuant to the provision of this Agreement.
The above indemnification shall not apply to those claims, demands,
and/or causes of
action arising out of the negligence of OWNER.
Accepted By: ________________________________________________
Company Name: ______________________________________________
That we, , (Name of Contractor) a , hereinafter called Principal,
and
, hereinafter called the "Surety", are (Name of Surety)
held and firmly bound unto the City of Kenner, Louisiana,
hereinafter called "Owner”, in the
penal sum of
_________________________________________________________________
Dollars ($ ) in lawful money of the United States, for the payment
of which
sum well and truly to be made, we bind ourselves, our heirs,
executors, administrators, and
successors, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION is such that Whereas, the
Principal entered
into a certain contract with the Owner, dated the day of , , a
copy
of which is hereto attached and made apart hereof for the
construction of:
Sylvaner Lift Station Improvements
NOW, THEREFORE, if the Principal shall well, truly and faithfully
perform its duties, all the
undertakings, covenants terms, conditions, and agreements of said
contract during the original
term thereof, and any extensions thereof which may be granted by
the Owner, with or without
notice to the Surety, and if he shall satisfy all claims and
demands incurred under such contract,
and shall fully indemnify and save harmless the Owner from all
costs and damages which it may
suffer by reason of failure to do so, and shall reimburse and repay
the Owner all outlay and expense
which the Owner may incur in making good any default in connection
with the construction of
such work, and all insurance premiums on said work, whether by
subcontractor or otherwise, then
this obligation shall be void; otherwise to remain in full force
and effect.
PROVIDED, FURTHER, that the said Surety, for value received, hereby
stipulates and agrees
that no change, extension of time, alteration or addition to the
terms of the contract or to the work
to be performed thereunder or the specifications accompanying the
same shall in any way affect
its obligation on this bond, and it does hereby waive notice of any
such change, extension of time,
alteration or addition to the terms of the contract or to the work
or to the specifications.
PROVIDED, FURTHER, that no final settlement between the Owner and
the Contractor shall
abridge the right of any beneficiary hereunder, whose claim may be
unsatisfied.
IN WITNESS WHEREOF, this instrument is executed in counterparts,
each one of which
shall be deemed an original, this the day of , .
26
WITNESSES:
By: _____________________________________
(Principal)
(Address)
NOTE: Date of Bond must not be prior to date of Contract. If
Contractor
is Partnership, all partners should execute bond.
27
KNOW ALL MEN BY THESE PRESENTS: that
, a ______________________________________ (Name of Contractor -see
Note 1) (Entity - see Note 2)
______________________________________________________________________________
(Address of Contractor) hereinafter called Principal, and:
_____________________________________________________________________________
(Name of Surety - see Note 3)
_____________________________________________________________________________
(Address of Surety)
hereinafter called Surety, are held and firmly bound unto the City
of Kenner, State of Louisiana,
acting herein by and through the Kenner City Council, the Governing
Authority for said City,
hereinafter called Owner, in the penal sum of Dollars
($ ) in lawful money of the United States, for the payment of which
sum well and truly
be made, we bind ourselves, successors, and assigns, jointly and
severally, firmly by these
presents.
THE CONDITION OF THIS OBLIGATION is such that whereas, the
Principal entered into a
certain contract with the Owner, dated the day of , , a copy of
which is
hereto attached and made a part hereof for the construction
of:
Sylvaner Lift Station Improvements
NOW, THEREFORE, if the Principal shall promptly pay all persons,
firms, subcontractors, and
corporations furnishing materials for or performing labor in the
prosecution of the work provided
for in such contract, and any authorized extension or modification
thereof, including all amounts
due for materials, lubricants, oil, gasoline, coal and coke,
repairs on machinery, equipment and
tools, consumed or used in connection with the construction of such
work, and all insurance
premiums on said work, and for all labor, performed in such work
whether by subcontractor or
otherwise, then this obligation shall be void; otherwise to remain
in full force and effect.
PROVIDED, FURTHER, that the said Surety, for value received, hereby
stipulates and agrees
that no change, extension of time, alteration or addition to the
terms of the contract or to the work
to be performed thereunder or the specifications accompanying the
same shall in any way affect
its obligation on this bond, and it does hereby waive notice of any
such change, extension of time,
alteration or addition to the terms of the contract or to the work
or to the specifications.
PROVIDED, FURTHER, that no final settlement between the Owner and
the Contractor shall
abridge the right of any beneficiary hereunder, whose claim may be
unsatisfied.
28
IN WITNESS WHEREOF, this instrument is executed in counterparts,
each one of
which shall be deemed an original, this the day of , .
WITNESSES:
(Surety)
BY:_____________________________________
(Attorney-in-fact)
NOTE: Date of Bond must not be prior to date of Contract.
1. Correct name of Contractor
2. A Corporation, A partnership, or an Individual
3. Correct Name of Surety
29
AFFIDAVIT
BEFORE ME, the undersigned authority, personally came and
appeared,
_____________________________, who after being duly sworn, deposed
and said that he/she is
the fully authorized ________________________ of
___________________________________
(hereinafter referred to as bidder), the party who submitted a bid
for______________________,
Bid Number ______________________ and said bidder further
said:
(1) That bidder is registered and participates in a status
verification system to verify that all
employees in the State of Louisiana are legal citizens of the
United States or are legal aliens.
(2) That bidder shall continue, during the term of the contract, to
utilize a status verification
system to verify the legal status of all new employees in the state
of Louisiana.
(3) That bidder shall require all subcontractors to submit to the
bidder a sworn affidavit verifying
compliance with statements (1) and (2).
_______________________________________
ATTESTATION CLAUSE REQUIRED BY
LA. R.S. 38:2227 (PAST CRIMINAL CONVICTIONS OF BIDDERS)
Appearer, as a Bidder on the above-entitled Public Works Project,
does hereby attest that:
A. No sole proprietor or individual partner, incorporator,
director, manager, officer, organizer,
Or member who has a minimum of a ten percent (10%) ownership in the
bidding entity Name below has been convicted of, or has entered a
plea of guilty or nolo contendere to Any of the following state
crimes or equivalent federal crimes:
(a) Public bribery (R.S. 14:118) (c) Extortion (R.S. 14:66)
(b) Corrupt influencing (R.S. 14:120) (d) Money Laundering (R.S.
14:23)
B. Within the past five years from the project bid date, no sole
proprietor or individual partner,
incorporator, director, manager, officer, organizer, or member who
has a minimum of a ten
percent (10%) ownership in the bidding entity named below has been
convicted of, or has
entered a pleas of guilty or nolo contendre to any of the following
state crimes or equivalent
federal crimes, during the solicitation or execution of a contract
or bid awarded pursuant to the
provision of Chapter 10 of Title 38 of the Louisiana Revised
Statutes:
(a) Theft (R.S. 14:67) (f) Bank fraud (R.S. 14:71.1)
(b) Identity Theft (R. S. 14:67.16) (g) Forgery (R. S. 14:72)
(c) Theft of a business record (h) Contractors; misapplication
of
__________________________________
_______________________________________
__________________________________
_______________________________________
____________________________________________
SC - 1
SUPPLEMENTARY CONDITIONS List of Subjects SC-1 SCOPE SC-2 INSURANCE
SC-2.01 Workers Compensation and Employer's Liability SC-2.02
Comprehensive Automobile Liability SC-2.03 Comprehensive General
Liability SC-2.04 Umbrella Liability Policy SC-2.05 Owner's
Protective Liability SC-2.06 Installation Floater (Property
Insurance) SC-2.07 Builder's Risk Insurance SC-2.08 Deductibles
SC-2.09 Indemnity SC-2.10 Settlement of Insurance Claims SC-3 BID,
PERFORMANCE AND PAYMENT BONDS SC-4 OVERTIME WORK SC-5 CORRECTION
PERIOD SC-6 PAYMENT OF LIQUIDATED DAMAGES SC-7 DOCUMENTATION TO
ACCOMPANY APPLICATIONS FOR PAYMENT SC-7.01 Material and Equipment
SC-7.02 Schedules and Data SC-7.03 Documentation for Final Payment
SC-8 SPECIFICATIONS SC-9 RESPONSIBILITY FOR PAYMENT SC-10
UNDERGROUND INSTALLATIONS SC-11 HISTORICAL OR ARCHAEOLOGICAL
DEPOSITS SC-12 CONTRACT TIME SC-12.01 Delays and Damages SC-12.02
Time Extensions for Weather Conditions SC-13 SUBSTANTIAL COMPLETION
SC-14 ORDER OF PRECEDENCE SC-15 ASSIGNMENT SC-16 PREFERENCE AND
PRIORTY TO LOUISIANA RESIDENT CONTRACTOR SC-17 EMERGENCY PERSONNEL
REQUIREMENTS SC-18 COORDINATION OF WORK
SC - 2
SC-19 COOPERATION BETWEEN CONTRACTORS SC-20 PRE-CONSTRUCTION
CONFERENCE SC-21 SCHEDULE OF VALUES AND PROJECT WORK SCHEDULE SC-22
SHOP DRAWINGS AND SAMPLES SC-23 ACCEPTANCE OF INSURANCE
3
SUPPLEMENTARY CONDITIONS
SC-1 SCOPE. These Supplementary Conditions amend or supplement the
General Conditions (EJCDC No. C-700, 2002 Edition), and amend or
supplement other provisions of the Contract Documents. All
provisions not so amended or modified remain in full force and
effect. SC-2 INSURANCE. The insurance requirements in Article 5 of
the General Conditions are as modified herein. All liability and
property insurance shall be purchased and maintained by Contractor
as set forth herein. Section 2.01 of the General Conditions is
revised to require that the valid certificates of insurance showing
the required waivers be submitted with the Contract when the
Contractor returns the contract for signature by the Mayor of the
City of Kenner. The Contractor shall purchase in its name and
maintain at its sole cost and expense such liability and other
insurance as set out herein. This insurance will provide primary
coverage for claims and/or suits which may arise out of or result
from the Contractor’s performance and furnishing of the Work,
whether it is performed by the Contractor, any sub-contractor,
partner, supplier, or by anyone directly or indirectly employed by
any of them to perform or furnish any of the Work, or by anyone for
whose acts any of them may be liable. If applicable, the Contractor
shall require all sub-contractors to maintain, in limits equal to
or greater than Contractor’s, the same insurance coverage for Work
performed or materials provided for the Work. Contractor shall
insert this requirement in all contracts or agreements written
and/or oral with all entities and/or persons who perform any Work
under this contract. At no time shall Contractor allow any
sub-contractors to perform Work without the required types and
limits of insurance coverage. All insurance shall include a waiver
of subrogation in favor of the Owner and any principals for whom
the Owner is working, including any and all co-lessors of such
principal, and shall be subject to the approval of the Owner.
Insurance provided for Commercial General Liability, Commercial
Automobile Liability, and Umbrella Liability shall name the Owner
as an additional insured and shall be primary to any insurance
carried by the Owner. Contractor shall furnish the Owner with
certificates of insurance as evidence of the above insurance. If
Owner has any objections to the coverage afforded by or other
provision of the insurance required to be purchased and maintained
by the Contractor in accordance with Section 5.04 of the General
Conditions on the basis of its not complying with the Contract
Documents, Owner will notify Contractor in writing thereof within
thirty (30) calendar days of the date of delivery of such
certificates to Owner in accordance with Section 2.01 of the
General Conditions. SC-2.01 Workers’ Compensation and Employer's
Liability Insurance. The Contractor shall purchase in its name, and
maintain during the life of this contract, Worker's Compensation
Insurance for all his employees in any way engaged in this project.
If any Subcontractor does not carry Workers' Compensation
Insurance, such coverage must be included under the Contractor's
policy. The policy shall provide coverage at least equal to the
requirements of the State of Louisiana and shall include Employer's
Liability Coverage. If any of the Work is above, on, or alongside
bodies of water, U S Longshoreman & Harbor Workers insurance in
equal amounts ($1,000,000) is to be included in the policy. Policy
limits and endorsements shall be as follows:
SC - 4
a. State Act- Louisiana Statutory Requirements; Provide Other
States coverage, if applicable;
b. Employer’s Liability with Minimum limits of
$1,000,000/1,000,000/1,000,000; and c. Waiver of Subrogation to
include written contracts in favor of The City of Kenner,
its elected and appointed officials, agents, directors, servants,
employees, volunteers, and any other entities who may require
waivers by specific contract.
SC-2.02 Commercial Automobile Liability Insurance. The Contractor
shall purchase in its name, and maintain during the life of this
contract, Commercial Automobile Liability Insurance to protect the
Owner, Contractor and Subcontractors performing work under this
contract from claims arising from any operations or work in
connection with this contract. The Commercial Automobile Liability
Insurance coverage is to be on an occurrence basis, with minimum
limits and endorsements as follows:
a. Minimal acceptable limit: $1,000,000 Combined Single Limit; b.
Liability coverage to be provided for Any Auto or for all Owned
Autos and Hired and Non-owned Autos. If Contractor owns no
vehicles, then a Hired and Non-
owned Auto Liability policy is required; c. Additional Insured
endorsement in favor of The City of Kenner, its elected and
appointed officials, agents, directors, servants, employees, and
volunteers; d. Waiver of Transfer of Rights of Recovery Against
Others to Us to include written
contracts in favor of The City of Kenner, its elected and appointed
officials, agents, directors, servants, employees, and volunteers;
and
e. If transporting any pollutants, the policy is to include the
Broad Form Transportation Pollution Form CA 99 48, or the most
current form available. SC-2.03 Commercial General Liability
Insurance. The Contractor shall purchase in its name, and maintain
during the life of this contract, Commercial General Liability
Insurance, including Products and Completed Operations Insurance to
protect the Owner, Contractor and Subcontractors performing work
under this contract from claims arising from any operations or work
in connection with this contract. The policy shall provide the
following limits and endorsements:
a. Commercial General Liability Form CA 00 01 or pre-approved
equivalent; b. Minimal acceptable limits: $1,000,000 per
occurrence; $2,000,000 general
aggregate, $2,000,000 products/completed operations aggregate; c.
Amendment-Aggregate limits of insurance (per project), the most
recent edition in
use in Louisiana or pre-approved equivalent; d. Additional Insured
endorsement in favor of The City of Kenner, its elected and
appointed officials, agents, directors, servants, employees and
volunteers on CG 20 10 Form B (edition 07 04) or approved
equivalent; and
e. Waiver of Transfer of Rights of Recovery Against Others to Us to
include written contracts in favor of The City of Kenner, its
elected and appointed officials, agents, directors, servants,
employees, and volunteers.
SC-2.04 Umbrella / Excess Liability Coverage. The Contractor shall
purchase in its name, and maintain during the life of this
contract, a policy of Umbrella / Excess Liability Coverage in
excess of the General Liability, Automobile Liability and
Employer’s Liability coverages above, following form thereof:
a. Minimum acceptable limits of $5,000,000
SC - 5
SC-2.05 Contractor’s Pollution, if applicable. If the Work involves
pollutants of any kind, in any manner, including cleanup, this
section applies. The Contractor shall purchase in its name, and
maintain during the life of this contract, a pollution liability
policy covering losses caused by pollution conditions that arise
from the operations of the Contractor. The policy shall provide the
following limits and endorsements:
a. Minimum acceptable limits: $1,000,000 each incident; $2,000,000
aggregate; b. Broad Form Named Insured endorsement; c. Fines,
penalties and punitive damages to be included; d. Clean up costs to
be included; e. Additional Insured endorsement in favor of The City
of Kenner, its elected and
appointed officials, agents, directors, servants, employees, and
volunteers; f. Waiver of Transfer of Rights of Recovery Against
Others to Us to include written
contracts in favor of The City of Kenner, its elected and appointed
officials, agents, directors, servants, employees, and
volunteers;
h. If claims-made coverage is accepted, the retroactive date, if
any, must precede the commencement of the performance of the
contract; and
i. Any retrospective date applicable to coverage will be maintained
or an extended discovery period will be exercised for a period of
three (3) years beginning when the Contract is completed or
terminated.
SC-2.06 Builder's Risk Insurance, if applicable. If the
construction project involves a structure of any kind, this section
applies. The Contractor shall purchase and maintain Builder’s Risk
insurance upon the entire Work which is the subject of the
Contract, at the site, to the full insurable value thereof. The
Contractor shall purchase the policy with the Owner as the First
Named Insured and maintain an “all risk” builder’s risk insurance
on the entire Work. If the Contractor has a blanket Builder’s Risk
policy, it shall be endorsed to include the Work, with the Owner
listed as a Named Insured with regard to the Work. These policies
must at a minimum cover for such amount of the Work as is
determined by the Engineer and/or Architect. This insurance shall
include, the Contractor, any Subcontractors and/or vendors deemed
appropriate by the Contractor shall also be Named Insureds.
The policy shall insure against the perils of fire, flood, and
extended coverage and shall include, "all risk", insurance for
physical damage including, without duplication of coverage: theft;
testing as appropriate for the type of project; debris removal;
damage to any Work-related property stored in the open, resulting
from a non-excluded peril; and vandalism. If not covered under the
"all risk" insurance or otherwise provided in the Contract, the
Contractor shall effect and maintain similar insurance on portions
of the Work stored off the site when such portions of the Work are
to be included in any applications for payment and such procedures
have been approved by the Owner.
The Builder’s Risk insurance shall be written and provided such
that any portions of a building or site vacated by the Owner to
accommodate the Work are protected and covered by the terms of the
insurance. The insurance shall not be cancelled or permitted to
lapse because of such vacancy. Coverage is to provide for use
and/or occupancy, without qualification, of any and all portions of
the Work, or the premises where the Work is being conducted,
whether the Work has been accepted by the Owner or not. The policy
shall remain in full force and effect until all work has been
accepted by the Owner and no repairs, remediation or operations of
any type are required from the Contractor, as determined by the
Owner. Coverage for Builder’s Risk Soft Costs is to be
included.
SC - 6
SC-2.07 Deductibles / Self-Insured Retentions. No insurance
required under this contract shall include a deductible or Self
Insured Retention in excess of $25,000.00 unless approved by the
Owner. The cost of all deductible or retained amounts shall be
borne by the Contractor. SC-2.08 Indemnity. To the fullest extent
permitted by law, Contractor agrees to protect, defend, indemnify
and save the Owner, its agents, officials, employees, or any firm,
company, organization, or individual, or their contractors, or
subcontractors for whom the Owner may be contracted to, harmless
from and against any and all claims, demands, actions, and causes
of action of every kind and character including but not limited to
claims based on negligence, strict liability, and absolute
liability which may arise in favor of any person or persons on
account of illness, disease, loss of property, services, wages,
death or personal injuries resulting from operations contemplated
by this contract. Specifically indemnified is the firm of Principal
Engineering, the same as the Owner. Further, Contractor hereby
agrees to indemnify all parties above for all reasonable expenses
and attorneys' fees incurred by or imposed upon the Owner in
connection therewith for any such loss, damage, injury or other
casualty. Contractor further agrees to pay all reasonable expenses
and attorneys' fees incurred by the Owner in establishing the right
to indemnity. SC-2.09 Settlement of Insurance Claims. Losses
insured under policies that include Owner as a named insured shall
be adjusted with the Owner and made payable to the Owner as trustee
for the Insureds, as their interests may appear. SC-3 Bid,
Performance, and Payment Bonds. All Bonds shall be in the form
prescribed by the Contract except as provided otherwise by
applicable Laws or Regulations and shall be executed only by
sureties meeting the requirements and qualifications set forth
herein. If the surety on any Bond furnished by the Contractor is
declared bankrupt, becomes insolvent, loses its right to do
business in any state where any part of the Project or Work is
located, or ceases to meet the requirements of paragraphs 3.1, 3.2,
and/or 3.3 C below, the Contractor shall within twenty (20) days
thereafter substitute another Bond and surety, both of which shall
comply with the requirements herein. SC-3.1 Bid Bond / Evidence of
Good Faith - The Contractor’s Bid shall be accompanied by a
certified check, cashier’s check or bid bond in an amount equal to
five percent (5%) of the Contractor’s Bid as an evidence of good
faith. If a Bond is used the surety or insurance company must be
currently on the U.S. Department of Treasury Financial Management
Service list of approved bonding companies which is published
annually in the Federal Register, or by a Louisiana domiciled
insurance company with at least an A- rating in the latest edition
of the A. M. Best’s Key Rating Guide. SC-3.2 Performance and
Payment Bonds - The Contractor shall purchase and furnish
performance and payment bonds each in an amount at least equal to
one hundred percent (100%) of the Contract price, including but not
limited to, the obligations for actual damages and liquidated
damages in accordance with the provisions in the Contract,
regarding delay in completion of the Work within the contract times
as security for faithful performance and payment of all
Contractor’s obligations under the Contract. Contractor shall also
furnish such other Bonds as are required by the Contract. Separate
Performance and Payment Bonds shall be provided. A combined
Performance and Payment Bond will not be acceptable. SC-3.3
Qualification of Surety – Performance and Payment Bonds - Any
surety Bond written for Owner shall be written by a surety or
insurance company currently on the U.S. Department of Treasury
Financial Management Service list of approved bonding companies
which
SC - 7
is published annually in the Federal Register, or by a Louisiana
domiciled insurance company with at least an A- rating in the
latest edition of the A. M. Best’s Key Rating Guide to write
individual Bonds up to ten percent (10%) of policy holders’
surplus, or by a surety company that complies with the requirements
of LSA-R.S. 38:2219.
SC-3.4 Resident Agent Required - No surety will be accepted from a
bondsman that does not have a permanent agent or representative in
the State of Louisiana upon whom notices referred to in the General
Conditions may be served. Service of said notice on said agent or
representative in the State shall be equal to service of notice on
the president of the surety, or such other officer as may be
concerned. Should the Contractor’s surety, even though approved and
accepted by the Owner subsequently remove its agency or
representative from the State or terminate its residency or license
in the State or become insolvent, bankrupt, or otherwise fail, the
Contractor shall immediately furnish a new Bond from another
company approved by the Owner at no additional cost to the Owner.
The new Bond shall be executed upon the same terms and conditions
as the original Bond.
SC-3.5 Alternative Security – The Owner, may, at its discretion
accept alternative security pursuant to the requirements set forth
in the Louisiana Public Contract Law (LSA-R.S. 38:2211 et
seq.)
SC-3.6 Scope of the Bond and Obligation of the Surety - The
Contractor’s surety shall obligate itself to all the terms and
covenants of the Contract covering the Work to be performed there
under. The Owner reserves the right to order extra work or to make
changes by altering, adding to, or deducting from the Work under
the conditions and in the manner herein described without notice to
the Contractor’s surety and without in any manner affecting the
liability of the bondsman or releasing it from any of its
obligations hereunder.
The Bond shall also secure for the Owner the faithful performance
of the Contract in strict accordance with the plans and
specifications of the Contract. It shall protect the Owner against
all lien laws of the State and shall provide for payment of
reasonable attorney’s fees for enforcement of the Contract and
institution of concursus proceedings, if such proceedings become
necessary. Likewise it shall provide that if the Engineer is put to
labor or expense by enforcement of the Contract and institution of
concursus proceedings or through delinquency or insolvency of the
Contract he shall be equitably paid for such extra expense and
services involved.
The surety of the Contractor shall be and does hereby declare and
acknowledge itself by acceptance to be bound to the Owner as
guarantor jointly and in solido with the Contractor for fulfillment
of the foregoing items including, but not limited to any provisions
for actual or liquidated damages. SC-4 OVERTIME WORK. No work shall
be done between 6:00 p.m. and 7:00 a.m. nor on Saturdays, Sundays
or legal holidays without permission of Owner. However, emergency
work may be done without prior permission. Night work may be
undertaken as a regular procedure with the permission of Owner;
such permission, however, may be revoked at any time by Owner if
Contractor fails to maintain adequate equipment and supervision for
the proper prosecution and control of the work at night. Regular
working hours shall not exceed a maximum of 40 hours per week.
Requests to work during other than regular working hours as
established by Contractor must be submitted to the Design
Professional at least 72 hours in advance of the period proposed
for such overtime work and shall set forth the proposed schedule
for work to give the Design Professional ample time to arrange for
his personnel to be at the site of the work.
SC - 8
The Contractor shall pay for all additional engineering charges to
the Owner on account of the overtime work which may be authorized
as stated above. Such engineering charges shall be a subsidiary
obligation of the Contractor and no extra payment shall be made by
the Owner on account of such overtime work. Design Professional
overtime charges shall be assessed in accordance with the terms of
the Design Professional's Agreement with the Owner. SC-5 CORRECTION
PERIOD. Section 13.07 of the General Conditions is hereby modified
so that the correction period is one year after the date of City
Council Acceptance. Nothing in the General Conditions Article 13
concerning the correction period shall establish a period of
limitation with respect to any other obligation which Contractor
has under the Contract Documents. The establishment of time periods
relates only to the specific obligations of the Contractor to
correct the work, and has no relationship to the time within which
his obligations under the Contract Documents may be commenced to
establish his liability with respect to his obligations other than
to specifically correct the work. SC-6 PAYMENT OF LIQUIDATED
DAMAGES. Article 14 of the General Conditions is hereby modified to
include provisions for collecting liquidated damages. When
Contractor is in default for nonperformance within the stipulated
contract time (as set forth in the Liquidated Damages paragraph),
Owner shall deduct the liquidated damages amount from the
Contractor's payment request. SC-7 DOCUMENTATION TO ACCOMPANY
APPLICATIONS FOR PAYMENT. In addition to the provisions set forth
in GC-14.02 and 14.07, the Contractor's Applications for Payment
shall be accompanied by the documentation specified in SC 7.01,
7.02 and 7.03. SC-7.01 Materials and Equipment. If payment is
requested for materials and equipment not incorporated in the work,
but delivered and suitably stored at the site or at another
location agreed to in writing, the Application for Progress Payment
shall be accompanied by such data, satisfactory to the Owner, as
will establish the Owner's title to the material and equipment and
protect his interest therein, including applicable insurance.
Payments for such materials and equipment shall be based only upon
the actual cost of the materials and equipment to the Contractor
and shall not include any overhead or profit to the Contractor. The
Contractor shall be cognizant of the fact that other work may be
under construction at the same time that this Contract is active.
There shall be complete cooperation with any other contractor in
the area, and any unavoidable conflicts shall be immediately
brought to the Design Professional's attention. SC-7.02 Schedules
and Data. Each Application for Progress Payment shall be
accompanied by the Contractor's updated schedule of operations, or
progress report, with such shop drawings, schedules, procurement
schedules, value of material on hand included in application, and
other data specified in Division 1 or reasonably required by the
Design Professional. With each pay request the Contractor shall
submit a breakdown of pay items by work order site, listing
location, description of work and cost supported by foreman's
report; and a standard A.I.A. billing form indicating bid items,
unit prices bid, current quantities installed, value of current
work installed, previous quantity installed and total quantity and
cost to date. SC-7.03 Documentation for Final Payment. Contractor's
Application for Final Payment shall be accompanied by consent of
the Surety to final payment and clear lien and privilege
certificates issued by the Clerk of Court and Ex-Officio Recorder
of Mortgages for Jefferson Parish.
SC - 9
SC-8 SPECIFICATIONS. The specifications which govern the materials
and equipment to be furnished and the work to be performed under
this contract are listed in the Table of Contents at the beginning
of this volume. SC-9 RESPONSIBILITY FOR PAYMENT. Except for items
specifically identified as provided by the Owner, Contractor shall
pay for all labor, materials, and other costs incurred under this
Contract. SC-10 UNDERGROUND INSTALLATIONS. Active underground
pipelines and utilities are indicated on the Drawings only to the
extent such information was made available to or discovered by
Design Professional in preparing drawings. There is no guarantee as
to the accuracy or completeness of such information, and all
responsibility for the accuracy and completeness thereof is
expressly disclaimed by the Owner and the Design Professional.
Service connections are not indicated on the Drawings. Contractor
shall be responsible for discovery of all existing underground
installations, in advance of excavating or trenching, by contacting
all local utilities, and by prospecting. SC-11 HISTORICAL OR
ARCHAEOLOGICAL DEPOSITS. If, during the course of construction,
evidence of deposits of historical or archaeological interest is
found, Contractor shall cease operations affecting the find and
shall notify Owner who shall notify the State Historic Preservation
Officer. No further disturbance of the deposits shall ensue until
Contractor has been notified by Owner that he may proceed. Owner
will issue a notice to proceed only after the state official has
surveyed the find and made a determination to the Owner.
Compensation to Contractor, if any, for lost time or changes in
construction to avoid the find, shall be determined in accordance
with changed conditions or change order provisions of the Contract
Documents. SC-12. CONTRACT TIME. SC-12.01 Delays and Damages.
Contractor shall accept the risk of any delays caused by the rate
of progress of the work performed under this contract or other
contract. In the event the Contractor is delayed in the prosecution
and completion of the work because of such conditions, the
Contractor shall have no claim against the Owner for damages or
contract adjustment other than an extension of contract time and
the waiving of liquidated damages during the period occasioned by
the delay. Time limitations required by the Owner shall be for the
benefit of the Owner and contractors, under other contracts, who
have entered into such contracts with the Owner in reliance on the
time limitations set forth in these Contract Documents. Any claim
by the Contractor for damages due to delay by another contractor
shall be asserted against that Contractor. SC-12.02 Time Extensions
for Weather Conditions. The Contractor shall note that weather
conditions shall not be an automatic cause for time extension. The
contract time specified in the bidding documents and contract
agreement include an allowance for inclement weather. In order to
document and claim days lost to inclement weather conditions, the
Contractor shall, on a semi- monthly basis submit a report to the
Design Professional, stating the time lost to inclement weather,
within seven (7) days of the end of the report period. The Design
Professional will review the report and make recommendations for
either acceptance or rejection of each claimed time period lost to
inclement weather. The Owner will then instruct the Design
Professional to approve or reject the report.
SC - 10
The report for lost days due to inclement weather shall account for
all days during the reporting period, including weekends and
holidays. Claims for lost days on either weekends or holidays will
not be considered unless the Contractor can show that the inclement
weather affected work production on the following work day. The
reporting periods shall be from the first day of the month through
and including the fifteenth day of the month and from the sixteenth
day of the month through and including the last day of the month.
Lost time accounting shall be in one-half day increments. Lost time
shall be considered only if the weather occurrence is in excess of
the normal weather patterns as established by the nearest office of
the National Weather Service, U.S. Department of Commerce. When the
Contract utilizes critical path method scheduling (C.P.M.), the
Design Professional will determine if the days lost due to weather
conditions actual affected the critical path activities then no
time extension will be granted. SC-13 SUBSTANTIAL COMPLETION.
Section 14.04 of the General Conditions is hereby deleted entirely,
and the following is substituted: When the Contractor considers the
work 100% complete, the Contractor shall declare in writing to the
Owner and the Design Professional that the work has been completed
in accordance with the plans and specifications, and shall request
a Final Inspection of the work. Upon receipt of such notification
the Design Professional shall , as quickly as practical, schedule
and conduct a Final Inspection of the work and shall prepare and
furnish to the Contractor a Punch List of outstanding items to be
completed or corrected, all in accordance with Section 14.06 of the
General Conditions. Upon completion of the Punch List items and
verification by the Design Professional and the Owner as acceptable
and complete, the City Council will, by Resolution, accept the
project as complete for purposes of commencement of the statutory
lien period. Until completion of the Punch List, however, the
contract time will continue to run. SC-14 ORDER OF PRECEDENCE. In
the event of an inconsistency in the Contract Documents, the order
or precedence shall be as follows:
a) Agreement b) Addenda/Change Orders/Written Amendment c)
Contractor's Bid d) Supplementary Conditions e) Instructions to
Bidders f) General Conditions g) Technical Specifications h)
Referenced Standard Specifications i) Drawings
With reference to the drawings, the order of precedence is as
follows: Figures govern over scaled dimensions; detail drawings
over general drawings; addenda/change order drawings govern over
standard drawings and shop drawings. SC-15 ASSIGNMENT. Neither
party to this contract shall assign or sublet his interest in this
contract without written consent of the other, nor shall Contractor
assign any monies due or to become due him under this contract
without previous written consent of Owner, nor without the consent
of the Surety unless the Surety has waived its right to notice of
assignment. The Contractor shall perform at least fifty percent
(50%) of all work covered in the Contract Documents. Contractor
shall not employ any subcontractor, other personnel or
organization, Whether initially or at any time during the contract
time, to assist the Contractor in the execution of the Contractor’s
fifty percent (50%) of the work.
SC - 11
SC-16 PREFERENCE AND PRIORITY TO LOUISIANA RESIDENT CONTRACTORS. By
statutory authority, certain preference and priority is given to
Louisiana Resident Contractors in the award of public work
contracts (LSA-R.S. 38:2225). If applicable, Bidder must make
request in writing, to accompany bid submission. SC-17 EMERGENCY
PERSONNEL REQUIREMENTS. The work demands of this contr