48
Presented by: Stantec & Golder Associates February 2, 2016 Department of National Defence B-Jetty Reconstruction CFB Esquimalt, BC

Department of National Defence B-Jetty Reconstruction · Department of National Defence B-Jetty Reconstruction ... Design Considerations 5 Structural Pile Considerations 6 ... •

Embed Size (px)

Citation preview

Presented by:

Stantec &

Golder Associates

February 2, 2016

Department of National Defence B-Jetty Reconstruction CFB Esquimalt, BC

Agenda

1 B-Jetty Project Background

2 Distinguishing Project Features

3 Structural Schemes Considered

4 Design Considerations

5 Structural Pile Considerations

6 Analysis

7 Dredging and Soil Remediation

VICTORIA

ESQUIMALT

Project Background

DND B-Jetty Reconstruction Stantec I Golder Associates

Existing B-Jetty

•  Finger pier constructed in early 1940’s •  Reconstructed in 1956 •  Timber pile/pile cap structure with pre- cast

concrete deck panels •  Original design vessel – 2000 tons •  About 190 m long and 18 m wide •  Fixed crane

DND B-Jetty Reconstruction Stantec I Golder Associates

B-Jetty Replacement Project •  To accommodate the next class of offshore

patrol vessels, frigates and supply vessels (JSS, AOPS, CSC, Subs)

•  Design vessel - 20,000 Tonnes displacement •  Finger pier About 270 m long and 26 m wide •  Rail mounted crane •  Services tunnel around jetty perimeter

“Stub” section to align with future A-Jetty replacement project

A JETTY

B JETTY

C JETTY

DRYDOCK

A JETTY

B JETTY

C JETTY

DRYDOCK

Distinguishing Project Features

DND B-Jetty Reconstruction Stantec I Golder Associates

Geotechnical Field Investigations

•  Geophysical and geotechnical investigations were undertaken to obtain information on subsurface conditions

•  Geophysical investigations consisted of multi-beam (high resolution) bathymetry survey and sub-bottom profiling of an area comprising both B- and A-Jetties

•  Geotechnical investigations consisted of cone penetration tests and samples boreholes with rock coring and sampling to depths varying from 10 to 20 m

•  Geophysical televiewer surveys were also carried out in the rock core holes

DND B-Jetty Reconstruction Stantec I Golder Associates

Geotechnical Results – Geophysical Surveys (Non-intrusive)

Inferred Glacial Till/Bedrock Surface

Inferred Seabed Surface

DND B-Jetty Reconstruction Stantec I Golder Associates

Geotechnical Borehole Investigation

Area-3

Area-1

Area-2

DND B-Jetty Reconstruction Stantec I Golder Associates

Geotechnical Subsurface Conditions

•  Shallow bedrock near shore •  Bedrock slopes sharply down in seaward direction •  Marine sediments vary from non-existent near

shore to 10 m thick offshore •  Marine sediments are underlain by Victoria Clay

to depths in excess of 70 m from seabed •  Clay underlain by thin till layer and bedrock •  Bedrock quality varies with severe fracturing/

jointing and low intact strength in upper 1 – 9 m

DND B-Jetty Reconstruction Stantec I Golder Associates

Soil Stratigraphy - B Jetty

DND B-Jetty Reconstruction Stantec I Golder Associates

Geotechnical Shear Strength Profile Victoria Clay and Marine Sediments

DND B-Jetty Reconstruction Stantec I Golder Associates

Earthquakes

DND B-Jetty Reconstruction Stantec I Golder Associates

Earthquake Loading (2010 NBCC)

DND B-Jetty Reconstruction Stantec I Golder Associates

Earthquake Loading (2010 NBCC)

DND B-Jetty Reconstruction Stantec I Golder Associates

Tsunami

Cause and Effects of a Tsunami

•  M9 megathrust earthquake •  Mike 21 modelling package •  Water level rise 1.6 m to 1.8 m •  Time of arrival after EQ ~ 90 minutes •  Current speed ~ 6 m/s •  Wave hits broadside to finger pier •  Run-up

DND B-Jetty Reconstruction Stantec I Golder Associates

Tsunami

DND B-Jetty Reconstruction Stantec I Golder Associates

Tsunami B  Jetty

0  m 50  m 100  m

NAD83  UTM Zone   10  Projection

DND B-Jetty Reconstruction Stantec I Golder Associates

Tsunami

DND B-Jetty Reconstruction Stantec I Golder Associates

Tsunami

DND B-Jetty Reconstruction Stantec I Golder Associates

Tsunami

Computed Run-Up (Shaded)

Structural Schemes Considered

DND B-Jetty Reconstruction Stantec I Golder Associates

Structural Schemes Steel Sheet Piles and Concrete Caissons •  Apply sustained loads to weak and compressible

overburden soils •  Would result in large, on-going total and

differential settlements •  Not acceptable Steel Pipe Piles •  Vertical loads transferred to bedrock •  No settlement •  Pile lengths vary from less than 5 m near shore to

more than 90 m at the seaward end

DND B-Jetty Reconstruction Stantec I Golder Associates

Preferred Structural Scheme

Steel Pipe Piles •  Rock anchored steel pipe piles •  Reinforced concrete pile caps, support beams

and deck •  But still a significant challenge to construct due to

thick overburden and deep bedrock at seaward end

Design Considerations

DND B-Jetty Reconstruction Stantec I Golder Associates

Geotechnical •  Shallow bedrock at shoreward end, very deep

bedrock at seaward end •  Bedrock quality varies with severe fracturing/

jointing and low intact strength in upper 1 – 9 m

Vessels & Operational Loads •  Water depth 11.5 m max (varies) •  20,000 Tonnes Displacement max •  Deck live load – 30 kPa •  Rail mounted crane •  Berthing loads, Mooring loads (60 knots)

DND B-Jetty Reconstruction Stantec I Golder Associates

Earthquakes •  2,475 year return period (NBCC) •  Importance Factor 1.5 (Post-Disaster) •  Analyses based on both National Building Code

of Canada and Canadian Highway Bridge Design Code

Tsunami •  Current speed ~ 6 m/s •  Wave hits broadside to finger pier •  Current force on berthed Joint Supply Ship (JSS) •  Governs over earthquakes loads

Structural Pile Configurations

DND B-Jetty Reconstruction Stantec I Golder Associates

Concept 1

•  Mix of battered and vertical piles •  Battered piles provide lateral

bracing •  Challenge to install in deep

bedrock zones

DND B-Jetty Reconstruction Stantec I Golder Associates

Concept 2

•  All vertical piles •  More lateral movement under high

loads (EQ, Tsunami) than battered piles

•  Challenge to install in deep bedrock zones – but less than for battered piles

DND B-Jetty Reconstruction Stantec I Golder Associates

Preferred Configuration •  Concept 2 – All Vertical piles •  Main Consideration - Constructability

Analysis

Analysis – SAP 2000

Classic Line Diagram

Solid Surface Diagram

DND B-Jetty Reconstruction Stantec I Golder Associates

Displacement (Tsunami)

SOIL INTERACTION

TSUNAMI FORCE

LINEAR SPRINGS AT DISCRETE POINTS, BUT NON-LINEAR ALONG THE LENGTH OF PILE

Governing load combination generally due to Tsunami Forces

DND B-Jetty Reconstruction Stantec I Golder Associates

Jetty Deflection – Tsunami West to East (Incoming)

TSUNAMI

180 mm

DND B-Jetty Reconstruction Stantec I Golder Associates

Required: •  1067 mm dia, rock anchored, concrete filled pipe piles

•  Post-tensioned longitudinal beams and deck

Stresses - Tsunami

Dredging and Soil Remediation

DND B-Jetty Reconstruction Stantec I Golder Associates

Dredging and Soil Remediation Contaminated Soil Remediation •  Significant effort to remove contaminated harbor

sediment •  Remediated areas to be capped with a 300 mm

thick layer of sand (Residual Management Cover). •  RMS Cover 14,000 m2

Soft Sediment Dredging •  For soil remediation and for water depth at berths •  Estimated Quantity 40,000 m3

•  All dredged material to be barged to offsite offload location for land disposal

DND B-Jetty Reconstruction Stantec I Golder Associates

Dredging and Soil Remediation

Bedrock Dredging •  For infrastructure installation •  For water depth at vessel berths •  For rock removal adjacent to Future A-Jetty location •  Estimated Quantity 6,500 m3

Limits of Dredging

NON-REMEDIATED

REMEDIATED

DND B-Jetty Reconstruction Stantec I Golder Associates

Limits of Dredging

SOFT  SEDIMENT  DREDGING  TO  BEDROCK  

SOFT  SEDIMENT  DREDGING  TO  DEPTH  (REMEDIATED)  

SED  TO  BR  

SED  TO  BR  

-­‐13.9  m  

-­‐13.7  m  

-­‐12.2  m  

-­‐15  m  

SLOPE  UP  TO  -­‐4  m  REMOVE  1  TO  2.2  m  

DND B-Jetty Reconstruction Stantec I Golder Associates

Limits of Dredging

SOFT  SEDIMENT  DREDGING  TO  DEPTH  (NON-­‐REMEDIATED)  

BEDROCK  DREDGING  

-­‐13.4  m  

-­‐11.9  m  

-­‐13.7  m  

-­‐12.2  m  

DND B-Jetty Reconstruction Stantec I Golder Associates

Bedrock Dredging/Blasting

•  Bedrock removal both onshore and within the harbor, required for infrastructure installation and for water depth at vessel berths

•  Must be carried out near existing historic structures including buildings, quay wall and drydock

•  Mitigating effects on local marine mammals are also an important consideration for the blasting program

•  Blasting program includes low yield charges, bubble curtain, marine life exclusion zone

DND B-Jetty Reconstruction Stantec I Golder Associates

Questions?