Demolition and Rebuild Structure Work Programme

Embed Size (px)

Citation preview

  • 8/18/2019 Demolition and Rebuild Structure Work Programme

    1/1

    ID Task Name Duration Start Finish Predecessors

    1   Construction of  CBP Wall 6  218 days Mon 16/11/15Tue 2/8/16

    2   CH 0 ‐ 150 (1000mm Dia) 218 days Mon 16/11/15Tue 2/8/16

    3   Setting out

     alignment

     2 days Mon

     16/11/15 Tue

     17/11/15

    4   Temporary sheet pile  15 days Wed 18/11/15 Fri 4/ 12 /1 5 3

    5   Excavation and Transport Extra Over 

    Earth

    20 days Mon 30/11/15 Tue 22/12/15 4FS‐5 days

    6   Preparing Platform 3 days Wed 23/12/15 Mon 28/12/15 5

    7   Boring & Concreting (140 nos) 99 days Tue 29/12/15 Tue 26/4/16 6

    8   Hacking Pile 60 days Sat 20/2/16 Fri 29/4/16 7FF+3 days

    9   Capping Beam 60 days Thu 3/3/16 Wed 11/5/16 8FF+10 days

    10   Cantilever Slab and Retaining 

    Structure

    50 days Thu 12/5/16 Fri 8/7/16 9

    11   Backfilling 18 days Wed 13/7/16 Tue 2/8/16 10,21FF

    12   Ch 150 ‐ 205 (600mm Dia) 84 days Wed 27/4/16 Tue 2/8/16

    13   Setting out alignment  2 days Wed 27/4/16 Thu 28/4/16 7

    14   Temporary sheet pile  10 days Fri 29/4/16 Tue 10/5/16 13

    15   Excavation and Transport Extra Over 

    Earth

    15 days Thu 5/5/16 Sat 21/5/16 14FS‐5 days

    16   Preparing Platform 1 day Mon 23/5/16 Mon 23/5/16 15

    17   Boring & Concreting (64 nos) 32 days Wed 27/4/16 Thu 2/6/16 7

    18   Hacking Pile 15 days Mon 23/5/16 Wed 8/6/16 17FS‐10 days

    19   Capping Beam 10 days Mon 6/6/16 Thu 16/6/16 18FS‐3 days

    20   Cantilever Slab and Retaining 

    Structure

    25 days Fri 17/6/16 Fri 15/7/16 19

    21   Backfilling 15 days Sat 16/7/16 Tue 2 /8 /1 6 2 0

    22   Finish 0 days Tue 2 /8 /1 6 Tu e 2 /8 /1 6 1 1

    23   Demolition and Reconstruct Existing 

    KPKT's Structure

    121 days Wed 2/3/16 Wed 20/7/16

    24   Method statement approval 1 day Wed 2/3/16 Wed 2/3/16

    25   Preparation works  30 days Thu 3/3/16 Wed 6/4/16 24

    26   Hacking of  structure 30 days Thu 7/4/16 Wed 11/5/16 25

    27   Rebuild of  existing structure 60 days Thu 12/5/16 Wed 20/7/16 26

    2 Boring points per day

    2/8

    6 22 8 24 9 25 10 26 13 29 14 30 16 1 17 3 19 4 20

    25/10 29/11 3/1 7/2 13/3 17/4 22/5 26/6 31/7

    21/11/15 1/2/16 11/4/16 21/6/16 1/

    MSPR6 ‐ Work Programme for Construction of  CBP Wall 6

    Page 1