Upload
wan-azri
View
215
Download
0
Embed Size (px)
Citation preview
8/18/2019 Demolition and Rebuild Structure Work Programme
1/1
ID Task Name Duration Start Finish Predecessors
1 Construction of CBP Wall 6 218 days Mon 16/11/15Tue 2/8/16
2 CH 0 ‐ 150 (1000mm Dia) 218 days Mon 16/11/15Tue 2/8/16
3 Setting out
alignment
2 days Mon
16/11/15 Tue
17/11/15
4 Temporary sheet pile 15 days Wed 18/11/15 Fri 4/ 12 /1 5 3
5 Excavation and Transport Extra Over
Earth
20 days Mon 30/11/15 Tue 22/12/15 4FS‐5 days
6 Preparing Platform 3 days Wed 23/12/15 Mon 28/12/15 5
7 Boring & Concreting (140 nos) 99 days Tue 29/12/15 Tue 26/4/16 6
8 Hacking Pile 60 days Sat 20/2/16 Fri 29/4/16 7FF+3 days
9 Capping Beam 60 days Thu 3/3/16 Wed 11/5/16 8FF+10 days
10 Cantilever Slab and Retaining
Structure
50 days Thu 12/5/16 Fri 8/7/16 9
11 Backfilling 18 days Wed 13/7/16 Tue 2/8/16 10,21FF
12 Ch 150 ‐ 205 (600mm Dia) 84 days Wed 27/4/16 Tue 2/8/16
13 Setting out alignment 2 days Wed 27/4/16 Thu 28/4/16 7
14 Temporary sheet pile 10 days Fri 29/4/16 Tue 10/5/16 13
15 Excavation and Transport Extra Over
Earth
15 days Thu 5/5/16 Sat 21/5/16 14FS‐5 days
16 Preparing Platform 1 day Mon 23/5/16 Mon 23/5/16 15
17 Boring & Concreting (64 nos) 32 days Wed 27/4/16 Thu 2/6/16 7
18 Hacking Pile 15 days Mon 23/5/16 Wed 8/6/16 17FS‐10 days
19 Capping Beam 10 days Mon 6/6/16 Thu 16/6/16 18FS‐3 days
20 Cantilever Slab and Retaining
Structure
25 days Fri 17/6/16 Fri 15/7/16 19
21 Backfilling 15 days Sat 16/7/16 Tue 2 /8 /1 6 2 0
22 Finish 0 days Tue 2 /8 /1 6 Tu e 2 /8 /1 6 1 1
23 Demolition and Reconstruct Existing
KPKT's Structure
121 days Wed 2/3/16 Wed 20/7/16
24 Method statement approval 1 day Wed 2/3/16 Wed 2/3/16
25 Preparation works 30 days Thu 3/3/16 Wed 6/4/16 24
26 Hacking of structure 30 days Thu 7/4/16 Wed 11/5/16 25
27 Rebuild of existing structure 60 days Thu 12/5/16 Wed 20/7/16 26
2 Boring points per day
2/8
6 22 8 24 9 25 10 26 13 29 14 30 16 1 17 3 19 4 20
25/10 29/11 3/1 7/2 13/3 17/4 22/5 26/6 31/7
21/11/15 1/2/16 11/4/16 21/6/16 1/
MSPR6 ‐ Work Programme for Construction of CBP Wall 6
Page 1