Bank Station Capacity Upgrade Safely together Delivering the Bank Station Capacity Upgrade Project Innovation through Collaboration Cate Anthony (Dr. Sauer & Partners) and John Comins (Dragados)

Delivering the Bank Station Capacity Upgrade Project ... Delivering BSCU...Oct 10, 2018  · Bank Station Capacity Upgrade Triple escalators provide direct link from Central line to

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Delivering the Bank Station Capacity Upgrade Project ... Delivering BSCU...Oct 10, 2018  · Bank Station Capacity Upgrade Triple escalators provide direct link from Central line to

Bank Station Capacity UpgradeSafely together

Delivering the Bank StationCapacity Upgrade Project

Innovationthrough

CollaborationCate Anthony

(Dr. Sauer & Partners)and

John Comins(Dragados)

Page 2: Delivering the Bank Station Capacity Upgrade Project ... Delivering BSCU...Oct 10, 2018  · Bank Station Capacity Upgrade Triple escalators provide direct link from Central line to

Bank Station Capacity UpgradeSafely together

Agenda• Bank Station Capacity Upgrade

• Collaboration at Bank• Combined Lining Design• Pile Load Transfer Structures• SCL Replacing Squareworks• Option A Joint

• Construction Progress• Challenges and Successes on Site• Productivity• Resources and Equipment• Current and Upcoming Works

Page 3: Delivering the Bank Station Capacity Upgrade Project ... Delivering BSCU...Oct 10, 2018  · Bank Station Capacity Upgrade Triple escalators provide direct link from Central line to

Bank Station Capacity UpgradeSafely together

Bank Station Capacity Upgrade

Page 4: Delivering the Bank Station Capacity Upgrade Project ... Delivering BSCU...Oct 10, 2018  · Bank Station Capacity Upgrade Triple escalators provide direct link from Central line to

Bank Station Capacity UpgradeSafely together

Bank Station Capacity Upgrade

Triple escalators providedirect link from Centralline to Northern line level

Former southbound Northern lineplatform tunnel re-used to increasecirculation and interchange spacefor customers

Moving walkway in new tunnelprovides greater capacity whilstreducing walking distances andinterchange times

New entrance to Bank station onCannon Street. Lifts and tripleescalators from street to Northernline and DLR

New Southbound railway tunneland platform for Northern line tocreate more space for customercirculation

Page 5: Delivering the Bank Station Capacity Upgrade Project ... Delivering BSCU...Oct 10, 2018  · Bank Station Capacity Upgrade Triple escalators provide direct link from Central line to

Bank Station Capacity UpgradeSafely together

Design Philosophy – Tier 2 Engagement

Sketch Draft Design Compliance SubmissionIDC IFC

SCL DETAILED DESIGNSCL DETAILED DESIGN

Final Design

Joseph GallagherTier 2

TunnelsDr Sauer

Tunnel Designer

DragadosTier 1

LondonUnderground

Page 6: Delivering the Bank Station Capacity Upgrade Project ... Delivering BSCU...Oct 10, 2018  · Bank Station Capacity Upgrade Triple escalators provide direct link from Central line to

Bank Station Capacity UpgradeSafely together

Combined Lining Design

• Approximately 15% saving in lining thickness

Page 7: Delivering the Bank Station Capacity Upgrade Project ... Delivering BSCU...Oct 10, 2018  · Bank Station Capacity Upgrade Triple escalators provide direct link from Central line to

Bank Station Capacity UpgradeSafely together

SCL Replacing Squareworks

Page 8: Delivering the Bank Station Capacity Upgrade Project ... Delivering BSCU...Oct 10, 2018  · Bank Station Capacity Upgrade Triple escalators provide direct link from Central line to

Bank Station Capacity UpgradeSafely together

SCL Replacing Squareworks

Existing assets

Construction sequence

New SCL tunnels

Page 9: Delivering the Bank Station Capacity Upgrade Project ... Delivering BSCU...Oct 10, 2018  · Bank Station Capacity Upgrade Triple escalators provide direct link from Central line to

Bank Station Capacity UpgradeSafely together

SCL Replacing SquareworksMechanised Excavation and SupportFaster and Safer

Larger Working Envelope

ImprovedWaterproofing

Page 10: Delivering the Bank Station Capacity Upgrade Project ... Delivering BSCU...Oct 10, 2018  · Bank Station Capacity Upgrade Triple escalators provide direct link from Central line to

Bank Station Capacity UpgradeSafely together

Option A Joint

Page 11: Delivering the Bank Station Capacity Upgrade Project ... Delivering BSCU...Oct 10, 2018  · Bank Station Capacity Upgrade Triple escalators provide direct link from Central line to

Bank Station Capacity UpgradeSafely together

Construction Progress so far

Start AST shaft sinking November 2016

Start Tunnelling May 2017

Page 12: Delivering the Bank Station Capacity Upgrade Project ... Delivering BSCU...Oct 10, 2018  · Bank Station Capacity Upgrade Triple escalators provide direct link from Central line to

Bank Station Capacity UpgradeSafely together

Construction Progress so far – Central & WBS

Page 13: Delivering the Bank Station Capacity Upgrade Project ... Delivering BSCU...Oct 10, 2018  · Bank Station Capacity Upgrade Triple escalators provide direct link from Central line to

Bank Station Capacity UpgradeSafely together

Challenges and Successes – Site Establishment

Page 14: Delivering the Bank Station Capacity Upgrade Project ... Delivering BSCU...Oct 10, 2018  · Bank Station Capacity Upgrade Triple escalators provide direct link from Central line to

Bank Station Capacity UpgradeSafely together

Challenges and Successes – AST Shaft Sinking

Page 15: Delivering the Bank Station Capacity Upgrade Project ... Delivering BSCU...Oct 10, 2018  · Bank Station Capacity Upgrade Triple escalators provide direct link from Central line to

Bank Station Capacity UpgradeSafely together

Resources and Equipment - Excavation

Page 16: Delivering the Bank Station Capacity Upgrade Project ... Delivering BSCU...Oct 10, 2018  · Bank Station Capacity Upgrade Triple escalators provide direct link from Central line to

Bank Station Capacity UpgradeSafely together

Resources and Equipment – Concrete Supply

Page 17: Delivering the Bank Station Capacity Upgrade Project ... Delivering BSCU...Oct 10, 2018  · Bank Station Capacity Upgrade Triple escalators provide direct link from Central line to

Bank Station Capacity UpgradeSafely together

Resources and Equipment – Dust & Ventilation

Page 18: Delivering the Bank Station Capacity Upgrade Project ... Delivering BSCU...Oct 10, 2018  · Bank Station Capacity Upgrade Triple escalators provide direct link from Central line to

Bank Station Capacity UpgradeSafely together

ProductivityTunnel Dia Shift m/day

(ave.)Comment

NL RT & pilot 4.9m 12hr

8hr

2.0

2.7

FullFace

Including initial plant chamber

NL Platform 9.8m 12hr

8hr

1.2

1.5

TH -INV

Enlargement from pilot

CP3 8.2m 1.3 TH -INV

CL-MW 7.7m 1.8 TH -INV

Page 19: Delivering the Bank Station Capacity Upgrade Project ... Delivering BSCU...Oct 10, 2018  · Bank Station Capacity Upgrade Triple escalators provide direct link from Central line to

Bank Station Capacity UpgradeSafely together

Current Works – Waterproofing

• PVC and Mapelastic spray membranes• 2 layer system• Mapelastic is water based, supplied premixed

and dust free• Waste is minimised and it is simple to spray

Page 20: Delivering the Bank Station Capacity Upgrade Project ... Delivering BSCU...Oct 10, 2018  · Bank Station Capacity Upgrade Triple escalators provide direct link from Central line to

Bank Station Capacity UpgradeSafely together

Upcoming works

Page 21: Delivering the Bank Station Capacity Upgrade Project ... Delivering BSCU...Oct 10, 2018  · Bank Station Capacity Upgrade Triple escalators provide direct link from Central line to

Bank Station Capacity UpgradeSafely together

Thank you for your attention