17
1 ENGINEERS IRELAND __________________________________________________________________________________ DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS _________________________________________ Michael Looby, Director, Byrne Looby Partners. Dr. Mike Long, Senior Lecturer, University College Dublin. Paper first presented to a meeting of the Geotechnical Society of Ireland at Engineers Ireland, 22 Clyde Rd, Dublin 4, on 11 th December 2007. Photograph shows Westgate 14 m deep excavation in June 2006 SYNOPSIS A number of Deep Excavations up to 23m in depth have recently been completed in Dublin. Different approaches including propped and unpropped, Secant and Contiguous Pile Wall Solutions have been employed on various projects. The paper updates a database for propped and cantilevered wall supported excavations in Glacial Tills. A comment and interpretation of recorded wall movement versus retained heights and wall stiffness is provided. Modelled predications are also discussed. A number of case histories of deep basement excavations including Spencer Dock in the Docklands, 14m excavation at Westgate (Heuston Square) and other projects are presented and discussed.

DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS · DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS ... Secant and Contiguous Pile Wall Solutions have been ... deep basement construction

Embed Size (px)

Citation preview

Page 1: DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS · DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS ... Secant and Contiguous Pile Wall Solutions have been ... deep basement construction

1

ENGINEERS IRELAND

__________________________________________________________________________________ DEEP EXCAVATIONS IN DUBLIN

RECENT DEVELOPMENTS

_________________________________________

Michael Looby, Director, Byrne Looby Partners.

Dr. Mike Long, Senior Lecturer, University College Dublin.

Paper first presented to a meeting of the Geotechnical Society of Ireland at Engineers Ireland, 22 Clyde Rd, Dublin 4, on 11th December

2007.

Photograph shows Westgate 14 m deep excavation in June 2006

SYNOPSIS

A number of Deep Excavations up to 23m in depth have recently been completed in Dublin. Different approaches including propped and

unpropped, Secant and Contiguous Pile Wall Solutions have been employed on various projects. The paper updates a database for propped

and cantilevered wall supported excavations in Glacial Tills. A comment and interpretation of recorded wall movement versus retained

heights and wall stiffness is provided. Modelled predications are also discussed. A number of case histories of deep basement excavations

including Spencer Dock in the Docklands, 14m excavation at Westgate (Heuston Square) and other projects are presented and discussed.

Page 2: DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS · DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS ... Secant and Contiguous Pile Wall Solutions have been ... deep basement construction

2

1. INTRODUCTION

The recent period of sustained economic

growth in Ireland has led to an increase in the

use of underground space, with some

development now including 4 underground

levels. This period has also seen the

development of marginal sites, for example

areas of Dublin docklands, which previously

would have been considered unsuitable for

deep basement construction.

The purpose of this paper is to provide an

update on recent developments in deep

excavations in the Dublin area. Specifically

the paper will:

• Briefly review the background geology

• Summarise the situation as existed up to

about 2002

• Present recent developments in the use of

cantilever retaining walls.

• Review the lessons learned from deep

open cuts.

• Present current approaches for the

analysis, design and construction of deep

excavations by reference to some case

histories namely:

→ 7 m cantilever wall at Ballycullen Rd.

where monitoring information for

some 140 weeks is available

→ 14 m excavation at Westgate

supported by a single row of anchors

→ 7 m deep excavation in complex

ground conditions at Spencer Dock in

Dublin docklands.

Finally some issues related specifically to

construction will be discussed and some

recommendations given for future works.

2. BACKGROUND GEOLOGY

Bedrock in the Dublin area is a thin to

medium interbedded homogenous grey

argillaceous limestone and calcareous shale.

Over much of the city, it is overlain by

glacial deposits, known colloquially as

Dublin boulder clay (DBC). This is hard

lodgement till which was deposited beneath

the ice sheet that covered much of Ireland

during the Pleistocene period. It was known

that the ice thickness in Dublin was

approximately 1 km and that several

advances and retreats of the glaciers occurred

in the area. The grinding action of this sheet

as it eroded the underlying rocks coupled

with its loading effect resulted in the

formation of a very dense / hard low

permeability deposit, which contains pockets

of lenses of coarse gravel, particularly at

depth. Oxidiation of the clay particles in the

top 2 m to 3 m has resulted in a change in

colour from black to brown and a lower

strength material.

With the construction of the Dublin Port

Tunnel, a clearer understanding of the

detailed geology of these deposits has

emerged, see Skipper et al. (2005). The

details of the engineering properties and

engineering behaviour of DBC has been

reported by Farrell and Wall (1990), Long

and Menkiti (2007a and 2007b)

Geological conditions in the Dublin

docklands are complex and comprise a series

of estuarine clays, slits, sands and gravels.

The situation in the docklands area is

complicated by the presence of a pre-glacial

channel just north of the River Liffey which

was identified by Farrington (1929). It

diverges from the present channel of the

River Liffey near Connolly Station and

returns near the mouth of the river. It is not

clear whether widely varying sea levels,

tectonic movements or some weakness in the

underlying rock gave rise to the channel.

However from an engineering point of view,

it has significant importance in that is it

generally filled with deposits of glacial and

fluvio-glacial gravels. A study of the deposits

in this area is currently being carried out at

UCD (Research student Brian Kearon).

Useful information can also be found on the

website of the Geological Survey of Ireland

(www.gsi.ie).

Figure 1. Dáil Eireann 6 m excavation

adjacent to (a) Senate chamber and (b)

Trinity College

3. SITUATION UP TO 2002

Up to about five years ago, basements in

Dublin generally comprised two underground

levels and were often constructed within

lightly supported contiguous or secant piled

retaining walls. Some typical examples of

these projects are the 6 m deep excavation at

Dáil Eireann, see Figure 1A and the 7.4m

excavation at Trinity College (see Figure 1B)

(Brangan, 2007)

A possible exception to these early

developments was that of the Jervis St.

shopping centre, where the secant piled

retaining wall had to be designed for an 8 m

deep dig and to support large loads from the

old Jervis St. hospital façade and the adjacent

Marks and Spencer store on Mary St., see

(Dougan et al., 1996).

In general these retaining systems behaved

very well. Lateral wall movements were very

small and prop forces were less than

traditional design approaches would predict

in boulder clay. At Jervis St and the Dáil

some attempts were made to monitor the prop

forces and they were found to be dominated

by temperature effects. Loading resulting

from the excavation was close to zero.

Brangan and Long (2001) (see also Brangan,

2007 and Long 2002b provided a summary

of the situation up to that time and included

data from 9 propped or anchored walls and 3

cantilever walls. All of these sites were

underlain by competent glacial deposits.

Page 3: DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS · DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS ... Secant and Contiguous Pile Wall Solutions have been ... deep basement construction

3

Figure 2. (a) Mespil Rd (b) Tallaght

Town Centre

The conclusions of this work were:

• The support systems behaved in a very

stiff manner with displacements and prop

forces being much lower than for world

wide stiff soil cases,

• In general traditional wall designs are

conservative,

• In order to properly model the behaviour

soil parameters such as the coefficient of

in situ horizontal stress (K0), the

variation in stiffness with strain and the

undrained shear strength (su) are very

important,

• The pore pressure behaviour during

excavation is poorly understood and it is

likely that high negative pore pressures

(suctions) develop.

Figure 3. Dublin glacial till database

for propped walls (a) δδδδh versus H (b) δδδδh

/ H versus EI/γγγγws4

4.0 UPDATED DATABASE FOR

PROPPED WALLS

The database of Brangan and Long (2001) /

Brangan (2007) and Long (2002b) for

propped walls in competent glacial deposits

is reproduced in Table 1 below and has been

augmented by data from eight other sites

including the 14 m deep Westgate excavation

and data from the Dublin Port Tunnel project

where excavation depths were up to 25 m

(see Figure 4).

A plot of maximum measured lateral

movement (δh) versus retained height (H) is

shown on Figure 3a. Except for the project in

Tallaght (see Figure 2B) all δh values are less

than 10 mm. There does appear to be some

weak tendency for an increase in δh with H.

The stiff behaviour of the very deep Westgate

and Dublin Port Tunnel excavations are

particularly worthy of note.

Also shown on Figure 3a are lines

representing normalised movement (δh/H) of

0.18% and 0.4%. The former relationship

was obtained by Long (2001) for an average

of 169 case histories worldwide where there

was stiff soil at dredge level. The behaviour

of the Dublin projects is significantly stiffer

than the worldwide average. The 0.4% line

represents a typical design value as

recommended by CIRIA report C580 (Gaba

et al., 2003) and clearly this relationship is

very conservative for the Dublin cases.

0 5 10 15 20 25Excavation depth, H (m)

0

10

20

30

40

Ma

x.

late

ral w

all

mo

ve

me

nt,

δh (

mm

)

δh/H = 0.18%

169 world casesLong (2001)

δh/H = 0.4%

typical designGaba et al. (2003)

DPT - WA2DPT

W'gate

DPT

0.1 1 10 100 1000Clough et al. (1989) system stiffness (EI/γws4)

0

0.1

0.2

0.3

0.4

0.5

δh /

H (

%)

δh/H = 0.18%

δh/H = 0.4%

Tallaght

Page 4: DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS · DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS ... Secant and Contiguous Pile Wall Solutions have been ... deep basement construction

4

Figure 4. Shaft WA2 – Dublin Port

Tunnel Project - 56 m diameter 25m

deep diaphragm wall shaft with single

ring beam support (Photo courtesy Dr.

Chris Menkiti, GCG)

The data shown on Figure 3a takes no

account of the retaining wall type, its

stiffness nor the prop / anchor configuration.

In order to attempt to include these factors,

the data are replotted on Figure 3b in the

normalised form of δh/H against Clough et

al. (1989) system stiffness. This is defined as:

4s

EIstiffnessSystem

wγ=− (1)

where:

EI = wall stiffness

γw = unit weigh of water (required to make

expression unit less)

s = support spacing

Lateral movements appear to be independent

of stiffness. This suggests that a more flexible

(an hence a more economic) wall may

perform adequately in many cases. These

data confirm the findings of the earlier work

that design of retaining wall systems in

Dublin glacial deposits are very conservative.

5. RECENT DEVELOPMENTS IN

CANTILEVER WALLS

5.1 General

Cantilever walls form ideal temporary or

permanent works. The site remains free of

internal props or struts allowing construction

to continue without obstacles. In particular

perimeter works such as drainage can

proceed without hindrance. Difficulties

associated with ground anchorages, such as

obtaining wayleaves or proof testing are also

avoided. Soil mechanics textbooks suggest

cantilever walls are only suitable for modest

excavations up to about 4.5 m retained

height. However throughout the world and

more recently in Ireland cantilever walls have

been used to retain excavations significantly

greater than 4.5 m. In the following sections

the performance of cantilever walls

worldwide and in Ireland will be reviewed

and attempts will be made to explain why the

behaviour of these structures surpasses that

suggested by conventional soil mechanics.

5.2 Cantilever walls worldwide

A summary of the case histories used is given

on Table 2. Note this table is an expanded

version of the one given by Long (2001) and

only those references not quoted in this latter

paper are given here. Figure 5a shows the

maximum measured lateral movement of the

walls (δh) versus retained height (H). The

data have been sub-divided into two groups,

those where there was stiff soil at the bottom

of the excavation (dredge) and where there

was soft soil at dredge. For the stiff soil at

dredge cases, surprisingly, the δh values are

confined to a relatively narrow band certainly

up to a retained height of about 9 m. δh

values are on average about 15 mm. Beyond

H = 9 m, there is a tendency for increasing δh.

For the limited number of cases with soft soil

at dredge level, the movements are greater,

especially for the case of the 10 m deep

excavation in San Francisco.

Data are presented in normalised δh/H versus

H form on Figure 6a. Again the δh/H values

are confined within a relatively narrow band

and seem independent of H, certainly up to H

= 10 m to 11 m. Average δh/H is about

0.25%.

The normalised movement data are

furthermore plotted against Clough et al.

(1989) system stiffness on Figure 7a, in an

attempt to examine the influence of the

retaining system on the movement. Here the

support spacing s is taken to be either the

retained height (H) or H + fixity. Typically s

is taken as 1.4 H. Beyond a Clough et al.

(1989) system stiffness value of 1 (equivalent

to a sheet pile of average size), the lateral

movements appear to be independent of

stiffness. This suggests that a more flexible

(an hence a more economic) wall may

perform adequately in many cases. World-

wide design practice of cantilever walls,

especially where there is stiff soil at dredge

level, may therefore be conservative.

5.3 Cantilever walls in Dublin

A summary of Dublin case histories is also

shown on Table 2. Relatively high cantilever

walls have been used for some time. Use of

these walls was based on the practical

experience of open cuts in the glacial tills

being able to stand unsupported at very steep

angles. Some examples of contiguous piles

retaining walls from Intel in Leixlip and

Charlemont Place, in Ranelagh, Dublin are

shown on Figure 8 (Long, 1997).

More recently cantilever walls of 7.5 m or so

are being used regularly. An example of the

7.5 m high cantilever 600 mm diameter

contiguous pile wall at Hunters Wood,

Ballycullen Rd. is shown on Figure 9. The

design, construction and performance of this

structure will be discussed in more detail in a

later section of the paper.

56m diameter Diaphragm Wall TBM Launch Shaft56m diameter Diaphragm Wall TBM Launch Shaft

Page 5: DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS · DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS ... Secant and Contiguous Pile Wall Solutions have been ... deep basement construction

5

Figure 5. Cantilever retaining walls δδδδh

versus H (a) world-wide case histories,

(b) Dublin

Figure 6. Cantilever retaining walls

δδδδh/H versus H (a) world-wide case

histories, (b) Dublin

Figure 7. Cantilever retaining walls

δδδδh/H versus Clough et al. (1989) system

stiffness (a) world-wide case histories,

(b) Dublin

2 4 6 8 10 12Excavation depth, H (m)

0

50

100

150

200

250

Ma

x.

late

ral m

ove

., δ

h (

mm

)

Stiff soil at dredge

Soft soil at dredge

World-wide case histories

2 4 6 8 10 12Excavation depth, H (m)

0

50

100

150

200

250

Ma

x.

late

ral m

ove

., δ

h (

mm

)

Stiff soil at dredge

Soft soil at dredge

Dublin case histories

Trendline from world-widecase histories

2 4 6 8 10 12Excavation depth, H (m)

0

0.5

1

1.5

2

2.5

Norm

alis

ed m

ax. la

tera

l m

ove

., δ

h / H

Stiff soil at dredge

Soft soil at dredge

World-wide case histories

2 4 6 8 10 12Excavation depth, H (m)

0

0.5

1

1.5

2

2.5

No

rmals

ied m

ax. la

tera

l m

ove.,

δh

/ H

Stiff soil at dredge

Soft soil at dredge

Dublin case histories

Trendline from world-widecase histories

0.01 0.1 1 10 100 1000

Clough et al. (1989) system stiffness = EI/γwh4

0

0.5

1

1.5

2

2.5

Norm

alis

ed m

ax.

late

ral m

ove

., δ

h / H

Stiff soil at dredge

Soft soil at dredge

World-wide case histories

0.01 0.1 1 10 100 1000

Clough et al. (1989) system stiffness = EI/γwh4

0

0.5

1

1.5

2

2.5

No

rma

lsie

d m

ax. la

tera

l m

ove

., δ

h /

H

Stiff soil at dredge

Soft soil at dredge

Dublin case histories

Trendline from world-widecase histories

Page 6: DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS · DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS ... Secant and Contiguous Pile Wall Solutions have been ... deep basement construction

6

Figure 8. Cantilever retaining walls at

Intel, Leixlip (6.8 m max.) and (b)

North Wall Quay (7.5 m max.) Sept

2007

Figure 9. 7.5 m high cantilever wall at

Ballycullen Rd. (a) during construction

in June 2005 and (b) in service

September 2007

Plots of δh versus H, δh/H versus H and δh/H

versus Clough et al. (1989) system stiffness

for the Dublin case histories are shown on

Figures 5b, 6b and 7b respectively. In each

case the best-fit trendline from the worldwide

database of cantilever walls are also shown.

The Dublin walls have performed very well,

with values falling in general well below the

trendlines. Average δh and δh/H values are

about 5 mm and 0.08% respectively. An

exception is the Thorncastle St. case history

(Long et al., 2002) where there was soft

alluvial soil at dredge level.

Again it seems that lateral movement is

independent of system stiffness and once a

sufficiently stiff system is provided the walls

will behave well. Again it seems Irish

practice is conservative and perhaps even

more conservative than that worldwide.

Based on these data it seems there is scope

for the use of higher cantilever walls, at least

for temporary work s purposes.

5.4 Behaviour with time

The data presented above omit one very

important factor, i.e. how does the lateral

movement vary with time. This has important

implications as to whether these walls can be

used for permanent work as well as

temporary works and also in the temporary

case how long is the useful life span.

Data from five sites in Dublin, Ballycullen

Rd., Cork St., New St. and the Dublin Port

Tunnel all in glacial till and Thorncastle St.

in soft alluvial soils are shown on Figure 10a.

The data for Ballycullen Rd is of particular

interest as it spans a period of some 140

weeks (2.7 years). In most of the projects,

after a relatively short time, the retaining wall

was encorporated into the permanent works

meaning it was no longer acting as a

cantilever. The Ballycullen Rd site is unusual

as the wall forms the permanent works, see

Figure 9b. On Figure 10b the data for the

first 40 weeks is shown in more detail.

It can be seen that in all cases there is a

gradual development of movement increasing

with time. For the glacial till cases the rate of

increase of lateral displacement is relatively

slow. However for the soft alluvial soils case

at Thorncastle St the development of

movement is rapid.

Page 7: DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS · DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS ... Secant and Contiguous Pile Wall Solutions have been ... deep basement construction

7

Figure 10. Cantilever retaining wall

movement with time

The reason for this behaviour is the gradual

dissipation of negative pore pressures

(suctions) and the build up of positive pore

pressure. This will be discussed in the

following sections.

6. LESSONS LEARNED FROM

STEEP UNSUPPORTED CUTS IN

DBC

6. 1 Natural slopes

There are several examples of natural steep

slopes in glacial tills in the Dublin area.

Hanrahan (1977) and Long et al. (2003)

describe near vertical slopes of up to 33 m

high in Howth (north of Dublin), Killiney

(south), Greystones (south of Dublin in Co.

Wicklow) and Chapelizod (west). There are

similar high natural cuts along the River

Dodder, in the south of the city

Figure 11(a) Glacial till sea cliffs at

Greystones, Co. Wicklow, (b) man made

6 m cut in Rathfarnham, south Dublin.

A view of the cliffs at Greystones is shown

on Figure 11a. Local instability can be seen,

for example when the slope was undercut by

sea erosion.

6.2 Man made temporary cuts

Temporary cuts of significant thickness,

made for engineering works, can stand

unsupported for relatively long periods, see

Figure 11b for example. Groundwater level

(as recorded by piezometers) was at about 2

m depth. The cut was made during the

summer time and is mostly in the weathered

upper brown boulder clay (UBrBC). No

ground water control system was used within

the excavation and no cracks were observed

at the slope crests, for a period of several

months. The authors have seen other near

vertical 8 m deep cuts in central Dublin stand

unsupported, adjacent to heavily trafficked

roads, for periods of several months.

6.3 Instability in steep cuts

Some instances of instability of cuts in

Dublin boulder clay have been reported. For

example Hanrahan (1977) discusses failures

caused by water bearing granular layers in

slopes in Glencullen, south Dublin. During

December 2000, the railway line adjacent to

the sea cliffs at Killiney had to be closed on

three occasions due to landslides. These were

due to surface slips in the upper (weathered)

portion of the till which occurred after

periods of high rainfall. Some local

instability can be seen in the slope beneath

the Martello tower at Howth, Co. Dublin.

This failed in December 2002 following a

period of heavy rain and caused the road

underneath to be blocked.

Long et al. (2003) describe some minor

failures in an 8 m high steep open cut in

north Dublin.

0 40 80 120 160Time (weeks)

0

5

10

15

20

25

Maxim

um

late

ral w

all

dis

pla

cem

en

t (m

m)

0 10 20 30 40Time (weeks)

0

5

10

15

20

25

Thorncastle 2

Thorncastle 4

Ballycullen 1

Ballycullen 2

Cork St. 1

Cork St. 2

New St. 3

New St. 5

DPT - DP79

Page 8: DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS · DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS ... Secant and Contiguous Pile Wall Solutions have been ... deep basement construction

8

Menkiti et al. (2004) describe the failure at

the trial trench excavated for the Dublin Port

Tunnel project.

The failures typically occur after periods of

high rainfall, at the location of granular

lenses and are characterized by the slip of

thin flakey wedges.

The behaviour of these natural and man made

cuts should give some clues as to the

surprisingly stiff behaviour of the Dublin

retaining walls.

6.4 Possible reasons for stable steep cuts

The possible reasons why steep cuts in

Dublin glacial till can stand unsupported for

significant time periods are discussed in

detail by Long et al. (2003). Possible

explanations for this observed behaviour are:

• The till possesses a high drained

cohesion (c') component.

• The particles are cemented together.

• Pore water suctions.

Long and Menkiti (2007a and 2007b) have

explained why the depositional nature of the

till and its particle size distribution have

resulted in it having a curved rather than the

normally assumed linear failure surface with

c' = 0. Evidence from scanning electron

microscope photographs has confirmed no

appreciable cementation exits between the

soil particles. Therefore pore water suction

must perform a significant role in the

observed behaviour of the material. This is

consistent with the failure of the material in

the presence of granular lenses and high

rainfall.

Figure 12. Pore water pressure

reduction in cut slopes

6.5 Pore water suctions

The pore water pressure conditions in the

slope before and after excavation are shown

diagrammatically on Figure 12. Before

excavation the pore water pressure (u) is

simply given by the hydrostatic head below

the groundwater table, which is at about 2 m

depth, i.e.

zu wγ= (2)

The change in u caused by the excavation can

be determined (approximately at least) from

Skempton’s (1954) classical equation for

pore water pressure change:

( )[ ]313 σσσ ∆−∆+∆=∆ ABu (3)

In this case both the all round pressure (∆σ3)

and the deviator stress (∆σ1-∆σ3) reduce due

to the excavation-induced stress relief. This

means that u reduces and, depending on its

initial value, could become negative. If u

reduces then the effective stress increases,

thus improving, in the short term, the

stability of the slope. The length of time over

which this reduced pore water pressure can

be sustained is a complex issue and depends

on the soil type, its fabric, permeability, the

sequence of construction, slope protection,

weather, etc.

As well as increasing the strength of the soil,

from the point of view of retaining wall

design the net effect is that there will be none

or at least very low pore water pressure

acting on the wall. Normally designers

assume hydrostatic water pressures, which

can be higher than soil pressures.

As can be seen from Skempton’s formula

above it is necessary to determine ∆σ3 and

∆σ1-∆σ3 in order to calculate the pore water

pressure after excavation. This is not a trivial

matter. Some elastic based solutions exist. In

the Dublin Port Tunnel project use was made

of the finite element approach. Further details

of these analyses can be found in Menkiti et

al. (2004) and Kovacevic et al. (2007). This

work was carried out by the Geotechnical

Consulting Group (GCG), who made use of

the Imperial College, London, geotechnical

finite element code called ICFEP. Some

typical output for the Dublin Port Tunnel

trial trench excavation is shown on Figure

13.

6.6 Some examples of measured pore water

suctions

The techniques used for measuring pore

water suctions on the Dublin Port Tunnel

project are described in detail by Long et al.

(2004). This includes a description of the

special piezometers used and the method

used to seal them into the ground.

A typical example for a piezometer at about

5.5 m depth in the trial trench is shown on

Figure13b. It can be seen that the measured

suction of about –30 kPa is very similar to

that predicted by the finite element analysis.

To the authors knowledge there has been no

measurements made of pore water suctions

behind retaining walls in Dublin boulder

clay. Such data would be of significant

practical use in the future design of these

systems.

12 mfor DPT

Groundwater table at 2 m

Before excavation pore pressure, u = γw x z

After excavationstress relief reduces

u and it possibly becomes negative (i.e suction)

z

Slope angle 70 to 80 deg. for DPT

Before excavation After excavation

Page 9: DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS · DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS ... Secant and Contiguous Pile Wall Solutions have been ... deep basement construction

9

Figure 13a. Predicted pore water

pressures for Dublin Port Tunnel trial

trench and (b) typical measured value

for piezometer at 5.5 m (Long et al.,

2004)

7. OTHER SOIL FACTORS

INFLUENCING RETAINING WALL

BEHAVIOUR

In addition to the role of pore water suctions

there are other significant factors influencing

the very stiff behaviour of retaining walls in

Dublin boulder clay. These are best

illustrated by examining a series of high

quality isotropically consolidated (CIUC)

triaxial tests (carried out by NMTL Ltd. for

ARUP Consulting Engineers) for a site in the

south city centre. The tests were carried out

on GeoBore-S rotary cores.

From the test results it can be seen:

• The material is very strong with

undrained shear strength (su) typically

between 400 kPa and 500 kPa

• It is ductile with peak strength being

developed at relatively high strains. (This

is advantageous from the point of view of

steep slopes or retaining wall moments as

the signs of incipient failure will be seen

some time before failure occurs).

• It is highly dilatant with negative pore

pressures developing during shear.

• Stiffness is highly non linear.

• Stiffness values are very high. Shear

modulus (G, as measured by local sample

mounted transducers) varies between 400

to 600 MPa at strains of 5x10-4 % to less

than 100 MPa at 0.01%.

• Stiffness measured by local strain

transducers in the laboratory is consistent

with very small strain stiffness measured

in situ using MASW surface wave

techniques (Donohue et al., 2003)

Figure 14. CIUC triaxial test

results for Dublin boulder clay

(Courtesy NMTL Ltd. And

ARUP Consulting Engineers)

Scale10m0

-75kPa-50kPa

-25kPa 0kPa

125kPa

100kPa

75kPa

50kPa

25kPa

-40.00

-30.00

-20.00

-10.00

0.00

10.00

20.00

30.00

40.00

2/23/02 3/5/02 3/15/02 3/25/02 4/4/02 4/14/02 4/24/02

Po

re P

res

su

re (

kP

a)

Piezometer 3B - 5.5 m - Trial trench

Excavation

Page 10: DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS · DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS ... Secant and Contiguous Pile Wall Solutions have been ... deep basement construction

10

8.0 DESIGN APPROACH

The previous sections have shown that low

level displacement has occurred for a number

of various types of retaining walls, primarily

in boulder clay soils. From a practitioners

point of view in order to understand why low

level deflections are occurring it is important

we understand the background to retaining

wall design. The following section briefly

outlines the general pile design approach and

the issues critical to wall movement.

As with any structure the design approach for

basement retaining structures commences

with the overall design philosophy and

proceeds through to detailed numerical

design. Assuming that the site investigation

has been completed, the initial considerations

will include the following issues which are

separated into those critical to movement and

other issues:

Movement Related Issues:

• Allowable movements

• Ground Model - Cohesive or

Cohesionless

• Quality of Site Investigation

• Depth of required excavation

• Prevailing groundwater conditions

• Retained structures and services –

surcharges

• Propped/cantilevered

• Temporary/Permanent retention

Other Issues:

• Space limitations/available plant

• Budget and programme

• Vertical load carrying requirement

• Recovery of material (e.g. sheet

piles)

• Working space (single vs. double

sided shutters for permanent RC

walls)

Once the broad requirements, based on the

above criteria, have been established then the

design can proceed to the numerical design

stage.

8.1 Limit States

Simpson and Driscoll (1998) define limit

state design as a procedure in which attention

is concentrated on avoidance of limit states,

i.e. states beyond which the retaining wall no

longer satisfies the design performance

requirements. This relates to the possibility

of damage, economic loss or unsafe

situations.

Retaining walls should be designed for

Ultimate Limit States (ULS) and

Serviceability Limit States (SLS).

8.2 Ultimate Limit States

Ultimate limit states are those associated with

collapse or with other similar forms of

structural failure. They are concerned with

the safety of people and the safety of the

structure.

The following should be considered:

• Loss of equilibrium of the structure

• Failure by rotation or translation of

the wall

• Failure by lack of vertical

equilibrium of the wall

• Failure of a structural element such as

wall, anchor, prop or wailing beam

• Movements of the retaining structure

that may cause collapse of the

structure, nearby structures or

services which rely upon it

• Failure caused by fatigue or other

time-dependent effects.

The ULS design involves carrying out a

Limit Equilibrium Analysis. Appropriate

Factors of Safety are applied and earth

pressure diagrams are derived, using classical

earth pressure theory in which full “Active”

and “Passive” conditions are assumed.

Computer programmes allow rapid analyses

to be carried out and readily allow for

changes to geometry, stratigraphy, soil

parameters etc.

This type of analysis will produce a set of

bending moments and shear forces in the wall

along with calculated propping forces. These

forces may or may not be the actual design

forces and hence cannot be used to predict

deflection.

8.3 Serviceability Limit States

Serviceability limit states correspond to

conditions beyond which specific service

performance requirements are no longer met,

for example pre-defined limits on the

amounts of wall deflections.

The permissible movements specified in the

design should take into account the tolerance

of nearby structures and services to

displacement.

It is worth remembering that the overall

stability analysis was carried out using full

“Active” and “Passive” soil conditions with

factored soil and surcharge parameters.

The next stage of the analysis procedure is to

calculate the actual wall, ground and building

movements along with the forces in the wall

in the “serviceability condition”. Soil

generally does not exist in the ground, pre-

development, at either it’s active or passive

limit and generally will not fully reach its

passive limit during the works, as appropriate

factors of safety will have been employed.

Importantly, the soil may not reach its active

limit either and therefore the soil load on the

wall in the SLS condition may be greater

than in the ULS condition.

As stated above bending moments, shear

forces and prop loads were calculated based

on the soil model presented in the ULS

analysis. However if the soil does not fully

reach its passive (or active) limit then this

model will not be accurate and an alternative

model or models are required.

Before construction activities occur soil

exists in-situ at “At-rest” or “Ko” (co-

efficient of earth pressure at rest) conditions,

see Figure 15. As soil cannot strain laterally

as it is being compressed during its

formation, lateral stresses are generated. This

subject has generated a vast amount of

research but for the purpose of this paper a

simple example will be used.

Figure 15 Earth Pressure at Rest Ko

As an excavation proceeds, see Figures 16,

the earth pressures move from the Ko

condition towards either the Ka or Kp

condition. The magnitude and distribution of

the shift and the “serviceability” pressures on

the wall are based on numerous factors,

however the stiffness of the various soil strata

have a significant influence.

Figure 7 Notional SLS Earth Pressures

Figure 16 – Ko Condition

It is therefore apparent that the SLS pressures

are different in magnitude and shape to those

in the ULS model. Therefore the ULS model

cannot be used to accurately predict the

displacement of the wall.

Page 11: DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS · DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS ... Secant and Contiguous Pile Wall Solutions have been ... deep basement construction

11

Modern SLS analyses are normally carried

out using finite element (FE) or finite

difference (FD) techniques and there are

many computer packages available to carry

out these. An example from the PLAXIS

package is presented in Figure 17 below.

Figure 17 - Example of PLAXIS

Output

The serviceability analyses are carried out

using unfactored soil parameters with no

over-dig allowance.

8.4 Modelling Method/Approach

After horizontal or vertical unloading

theoretical soil and groundwater pressures in

cohesive soils can be significantly less than

zero and can sometimes provide no active

load on a retaining wall. This will be further

discussed below. For a number of reasons

this is not an acceptable design approach as

set out below:

• Tension cracks can develop to the

rear of the wall. The relevant code

(CIRIA 580) requires the use of a

Minimum Equivalent Fluid

Pressure (MEFP) for tension cracks

• Sand and gravel lenses which are a

common occurrence in the Dublin

boulder clay can supply sufficient

groundwater to allow hydrostatic

groundwater pressures develop to

the rear of the wall

• Potential unidentified pockets of

sand and gravel could provide

loading conditions and failure

modes that tend towards effective

stress conditions. (This condition

applies to the passive side also).

In order to account for the above criteria in

retaining wall design BLP currently use one

of the following approaches (a key factor in

which approach is employed is the level of

the groundwater for the particular project).

• Effective stress conditions with a

low Ka value

• Undrained soil parameters with a

minimum equivalent fluid pressure

employed in the analysis as per

CIRIA C580.

• Undrained soil parameters with full

hydrostatic groundwater pressures

• A combination of the above criteria

The above paragraphs outline conditions that

can occur and the relevant design criteria. In

reality, full hydrostatic water pressures,

MEFF conditions or effective stress

conditions may not exist and actual loading

conditions on the wall could be closer to the

undrained or partially undrained conditions

where complex (incl. negative) pore

pressures exist. This results in low or zero

lateral pressures on the wall. Obviously the

deflection predictions from the analysis with

undrained parameters will be significantly

less than any of the design approaches

discussed above.

The use of undrained parameters in

conjunction with the observational approach

may be considered for reducing predicted

deflections to simplify the construction

sequence and reduce costs. (In addition to

this, how we model groundwater with time

post excavation should also be considered

but is not addressed as part of this paper).

This approach should also only be considered

where the predicted deflections using

traditional approaches are within defect limits

to prevent the possibility of damage,

economic loss or unsafe situations. The risk

associated with the decision should be clearly

assessed in terms of understanding of the site

geology, type and condition of structures to

the rear of the pile wall and the quality of

monitoring procedures put in place. This

decision to use undrained parameters will

have a large impact on predicted deflections

as discussed above.

The benefits of using undrained parameters

are not so much that pile sizes will be

reduced but that more cost effective overall

solutions can be employed in more areas. It

seems there is scope for the greater use of

cantilever walls and also greater retained

heights at least for temporary works

purposes.

Similar design issues arise in relation to

undrained soil parameters on the passive side

of the wall and undrained analysis can

potentially allow for very shallow

embedment depths. In order to allow for the

possibility of unknown gravel layers,

effective stress parameters are often used to

determine the overall stability requirements.

However the serviceability analysis may

require the benefit of using undrained

material on the passive side in order to more

accurately predict deflection.

8.5 Quality of Site Investigation Data

As with all geotechnical applications, quality

of site investigation is critical to accurately

predict movements. The results of recent

consolidated triaxial tests presented in

Section 7.0 are consistent with monitored

pile deflections in boulder clay, in that they

suggest that we are currently significantly

under estimating the stiffness parameters of

the glacial tills. Higher quality laboratory

testing on larger projects should be

considered.

Investigations should accurately establish the

static groundwater profile at the site. As

noted previously, to the author’s knowledge

there have been no measurements made of

pore water suctions behind retaining walls in

Dublin boulder clay. Such data would be of

significant practical use in the future design

of these systems.

8.6 Critical Issues for Movement

A summary of the critical issues in relation to

retaining wall deflections and predictions are

as follows:

• Cohesive or Cohessionless model –

in conjunction with how we model

groundwater with time

• Continuous Wall (Secant/sheet pile)

or contiguous

• Surcharge

• Propped/Cantilevered

• Groundwater conditions

• Soil parameters – quality of

investigation

• Attitude to risk

9.0 CASE HISTORIES

The design and monitoring of 3 No. deep

basements are described in the following

sections. All projects were completed in the

past three years. The projects include

Spencer Dock Development at North Wall

Quay Wall, the Westgate (now called

Heuston Square) project and a residential

development in Dublin 24.

Page 12: DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS · DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS ... Secant and Contiguous Pile Wall Solutions have been ... deep basement construction

12

Figures 18/19 - Spencer Dock and

Westgate

The projects were selected to compare the

performance of permanent and temporary,

propped and cantilevered walls in various

soils types and the accuracy of predicted

deflections.

9.1 Westgate

The Westgate Development (see Figure 19) is

a combined commercial and residential

development, adjacent to Heuston Station,

south of the Liffey. Topographical levels on

the site vary between 14m OD at the south

end of the site and 6m OD at the north.

Basement formation was 0m OD resulting in

a 14m retained height at the southern end.

Ground stratigraphy consisted of stiff to hard

glacial till interlayered with dense gravel.

The gravel layers were intermittent and did

not exist consistently across the site. A

geological x–section of the site is provided in

Figure 20. Soil parameters employed for the

different strata are as indicated in Table 3.

A monitoring programme indicated that

groundwater levels varied between +8m OD

of the southern boundary and 0.9m OD at the

northern boundary. The variable levels were

due to groundwater flow towards the River

Liffey.

Construction Sequence

The construction sequence was as follows:

• Install 900mm φ “Secant” Soft-Hard

Pile wall to 20m bgl at 0.7m cc to

achieve overlap. Piles were

constructed with a 30 Tonne metre

Torque CFA Rig. The male piles were

• `

reinforced with 18 No. T32’s over the

central third of the pile and 10 No.

T32’s over the top and bottom third of

the pile and were constructed with

• C35 Concrete.

• Construct a reinforced capping beam.

• Install, test and pre-stress 700 kN SWL

anchors @ 2.25m cc through the

capping

• Complete excavation in staged manner

with a detailed monitoring programme.

Table 3 - Westgate Soil Parameters

Figure 21 illustrates a typical x-section

through the pile wall.

A key aspect of the retaining wall design

was the use of the “Observational

Approach” to monitor the movement of the

wall as excavation proceeded. 6 No.

inclinometers were installed at key locations

across the site to measure pile wall

deflection. Inclinometer monitoring was

carried out by BLP in-house with

monitoring being carried out at critical

stages of the excavation.

“Trigger level” lateral movement criteria was

established prior to the works commencing

for the different stages of excavation. The

original design analysis predicted pile

deflections of 50mm, the pile was structurally

designed to resist the bending moment that

reflected this profile. The maximum trigger

level value of 35mm for complete excavation

was selected to ensure that excessive

deflections did not have an impact on the

existing listed boundary wall to the rear of

the pile wall.

The following protocol was agreed if the

monitored deflection exceeded the trigger

value.

1. Excavation works would cease.

2. A second set of readings would be

taken the following day.

3. If further movements were

observed the wall would be

partially backfilled.

4. If the wall had stabilised, a second

layer of the tie-back anchors

would be installed.

Recorded Movement

Figure 21 illustrates a typical x-section

showing the original predicted deflection and

the recorded pile inclinometer data. The

original analysis included modelling the soil

stratigraphy with drained parameters using

both FREW and PLAXIS analyses. In the

PLAXIS analyses the made ground and

glacial soils were assumed to behave as

elastic perfectly plastic materials with failure

defined by Mohr Coulomb using drained

parameters. The analyses gave reasonably

consistent predictions within 20% of each

other.

Maximum recorded pile deflections were

12mm. The modelled movements are

significantly different. It is noted also that

while the original Site Investigation

suggested that significant gravel layers may

be present, inspection of the bulk excavation

at the southern end of the site indicated the

soil was predominantly a clay material.

Stratum Depth

m bgl

E

MPa

Ko φφφφ (o) Cu C

Fill 0- 1 50 .5 30 - -

Dense

Gravel

1-25 150 1 38 - -

Stiff

Brown

Clay

1-25 150 1 35 - -

Page 13: DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS · DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS ... Secant and Contiguous Pile Wall Solutions have been ... deep basement construction

13

Figure 20 Westgate Geological Section

For the purposes of this paper an analysis of

the wall with undrained soil parameters and a

static water level 7m OD was carried out

using FREW. Predicted pile deflections were

20mm suggesting that the undrained

parameters would model actual pile

deflections more accurately. Figure 21 also

indicates the predicted pile deflection profile

using the drained parameters. The

introduction of a consolidation stage in the

analysis to model groundwater pressures with

time may further improve predictions.

9.2 Spencer Dock

Spencer Dock (see Figure 18) is located in

the Dublin Docklands and is 2km east of the

city centre adjacent to the River Liffey.

Topographical level at the site is +2.5m OD.

The site is bounded to the west by the

Spencer Dock canal and the south by the

River Liffey.

Figure 22 illustrates the typical geology of

the site.

The water table on the site is 0m OD and is

not significantly influenced by the tidal cycle.

The upper made ground consists of brick and

masonry in a clay matrix. Due to the variable

depositional environment in this section of

the site close to the river, the alluvium

stratum is a complex mixture of soil types

typical of the docklands. The upper 3.5m

comprises a loose to medium dense sand and

gravel. This is underlain by a soft clay and

silt with organic material.

N-values in the soft clay layer vary from 2 to

7. The underlying glacial deposits consist of

2 to 3m of dense gravel overlying a hard till.

Construction Sequence

A 900mm φ soft/hard secant pile wall was

employed. Tie back anchors were employed

at approximately 2.5m bgl rather than at

capping beam level. The construction

sequence therefore involved an initial

cantilevered stage of 2.5m.

Piles were extended to 16m bgl to include a

2m embedment into boulder clay to achieve

groundwater cut-off. As with the Westgate

project a detailed inclinometer monitoring

programme was implemented to monitor pile

movement.

Movement

FREW was employed to carry out the

original pile wall analysis and indicated that

predicted pile deflections would be in the

range of 35mm to 40mm. A sensitivity

analysis was carried out at the time of the

design varying the stiffness and strength

characteristics of the soils as well as

modelling the layer with drained and

undrained parameters for the soft alluvium

layer.

Inclinometer readings over the course of the

construction stage recorded the deflection

profile as being reasonably consistent with

modelled deflections, approximately 15%

less as per Figure 22, illustrating that the

model may be better at predicting movements

in the cohesionless soil layers and low

strength strata’s as encountered.

9.3 Ballycullen Road

The Ballycullen Road project was a

residential development located in the

Knocklyon area of Dublin 24 (see Figure 23).

The development consists of a number of

apartment blocks constructed over a double

level basement. Datum level at the site was

Figure 21 Westgate Pile Section.

107 mAD and basement formation was

99.5mAD providing a 7.5m effective retained

height. The wall was installed in January

2005 and excavation was carried out in

February 2005.

Groundwater monitoring at the site indicated

that static water levels were below excavation

level.

The basement directly bounds a public access

road to the residential estate necessitating the

requirement for the retaining wall.

The geology of the site consisted

predominantly of glacial till. A brown Firm

to Stiff boulder clay was noted to overlay

Hard Black Boulder Clay as per Figure 23.

The brown and black boulder clay layers

were modelled with effective stress

parameters of 35 and 37 degrees respectively.

The deeper boulder clay layers were

modelled with stiffness parameters of

120,000kPa and 80,000kPa in the temporary

and permanent conditions respectively.

Construction Sequence

The pile wall was required to provide both

permanent and temporary retention (see

Figure 9a & 9b). A 600mm diameter

contiguous pile wall solution was chosen

based on the geology of the site and the

retained height. The construction sequence

was as follows:

• Install 600mm diameter hard piles at

750mm cc to a total depth of 14m below

ground level. Piles were constructed

with a 24 Tonne metre Torque CFA Rig.

The piles were reinforced with 8 No.

T32 over the full height of the pile wall.

Page 14: DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS · DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS ... Secant and Contiguous Pile Wall Solutions have been ... deep basement construction

14

Figure 22 Spencer Dock Pile Section

• Construct the reinforced capping beam.

• Complete excavation in a staged manner

with detailed monitoring.

• Install a basement concrete slab to

provide a low level prop/restraint.

Prior to construction commencing a number

of design criteria were established including

the following:

• If local gravel layers were encountered

they would be shotcreted to prevent loss

of ground between piles. If more

significant gravel layers were

encountered a Secant Pile Wall solution

would be installed.

• If movement levels in the construction

sequence exceeded a trigger level of

25mm, tie-back anchors would be

installed. The original design analysis

employed drained conditions to the rear

of the wall in the temporary stage.

Predicted pile deflections were 40mm

and 45mm respectively in the temporary

and permanent conditions. The trigger

values were selected to ensure that long

term deflections would not be excessive

in order to avoid damage to the adjacent

road.

Recorded Movement

2 No. inclinometers were installed at key

locations on the pile wall for measuring pile

wall deflections. These have been left in

place to allow monitoring on an ongoing

basis to be carried out and this has been done

over the past 2 years.

Recorded pile deflections during the

construction stage and post construction to

November 2007 (22 Months) were 10mm

and 17mm respectively. Recorded

deflections to date are significantly less that

predicted the deflections of 45mm. An

analysis with undrained parameters was

carried out for this paper which indicated

deflections in the temporary condition of

17mm which is in line with those recorded to

date.

10. CONCLUSIONS

1. Case history data confirms retaining wall

behaviour in Dublin glacial till is

extremely stiff. This applies to

excavations up to 25 m deep.

2. It appears that current approaches over

predict walls deflections and the use of

overall current design practice is clearly

conservative.

3. The use of undrained parameters in

conjunction with the observational

approach may be considered for reducing

predicted deflections to simplify the

construction sequence and reduce costs.

4. This approach should also only be

considered where the predicted

deflections using traditional approaches

are within defect limits to prevent the

possibility of damage, economic loss or

unsafe situations.

5. Cantilever walls have been successfully

constructed up to 7.5 m high. These walls

show smaller movements than expected,

though the development of movement

with time is very important.

6. It seems there is scope for the greater use

of cantilever walls and possibly also

higher retained heights, at least for

temporary works purposes.

7. Important insights into the above can be

gained from observations of steep slopes

in Dublin boulder clay, where pore water

suction plays an important role.

Figure 23 Ballycullen Rd Pile Section

8. Laboratory testing on high quality

samples of the material confirm that it is

stronger and stiffer than normally

assumed in design.

9. Measurement of Pore Water Pressure to

rear of walls should be carried out.

10. The analysis employed accurately

predicted deflections in the boulder clay.

ACKNOWLEDGMENTS

Dr. Chris Menkiti and Dr. George Milligan

for input from DPT project, Dr. Carl

Brangan, former PhD student at UCD. Mr.

Tony O’Dowd, PJ Edwards & Co., Mr. Pat

Fox, Murphy International Ltd and Mr.

Douglas Cook, FK Lowry Piling Contractors.

REFERENCES

1. Bentler, J.G. and Labuz, J.F. (2006).

“Performance of a cantilever retaining

wall”. ASCE Journal of Geotechnical and

Geoenvironmental Engineering, Vol.

132, No. 8, August, pp 1062 - 224.

2. Brangan, C. and Long, M. (2001).

“Behaviour of buildings adjacent to deep

excavations in Dublin glacial till”. Proc.

Int. Conf. Response of Buildings to

Excavation Induced Ground Movements,

Imperial College, London, 17 – 18 July

2001, CIRIA Special Publication No.

199, pp 209 – 216

3. Brangan, C. (2007). “Retaining walls in

Dublin boulder clay” PhD thesis,

University College Dublin, November.

4. Byrne, J. (2007). “Deep Basement

Design and Construction”, The

Institution of Structural Engineers in

association with The Dept. of Civil &

Page 15: DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS · DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS ... Secant and Contiguous Pile Wall Solutions have been ... deep basement construction

15

Structural Engineering, Dublin Institute

of Technology.

5. Cabarkapa, Z., Milligan, G.W.E, Menkiti,

C.O., Murphy J. and Potts D. M. (2003).

“Design and performance of a large

diameter shaft in Dublin Boulder Clay”.

British Geotechnical Association

International Conference on Foundations,

Dundee, Thomas Telford: 175 – 185.

6. Clough, G.W., Smith, E.M. and

Sweeney, B.P. (1989). “Movement

control of excavation support systems by

iterative design”. Proc ASCE Foundation

Eng: Current Principles and Practices;

2; pp 869-884.

7. Curtis, P. and Doran, J. (2003).

“Retaining wall behaviour at the Dublin

Port Tunnel”. BE Project, UCD.

8. Donohue, S., Gavin, K, Long, M. and

O’Connor, P. (2003). “Gmax from

multichannel analysis of surface waves

for Dublin boulder clay”. Proc. 13th.

ECSMGE, Prague, Vanicek et al., Eds.,

Vol. 2, pp 515 – 520. Published by

CGtS, Prague.

9. Dougan, I, Long M.M. and Byrne J.J.B.

(1996). “The Geotechnical Aspects of the

Deep Basement for the Jervis St.

Shopping Centre”. Trans. Institution of

Engineers of Ireland, Vol. 120, 1996 /

1997, pp 49 - 70.

10. Farrell, E. R. and Wall, D. (1990). “The

soils of Dublin”. Transactions of the

Institution of Engineers of Ireland, 115:

78-97.

11. Farrington, A. (1929). The pre-glacial

topography of the Liffey basin. Proc.

Royal Irish Academy,1929, 38, B, 9. 12. Gaba, A.R., Simpson, B., Powrie, W. and

Beadman, D.R. (2003). “Embedded

retaining walls – Guidance for economic

design”. CIRIA report C580.

13. Hanrahan, E.T. (1977). “Irish glacial till -

origin and characteristics”. RC 164 An

Foras Forbartha, Dublin, 1977.

14. Kovacevic, N., Milligan, G.W.E., Long,

M., and Potts, D.M. (2007). "Finite

element analyses of steep man-made cuts

in Dublin Boulder Clay". Accepted for

publication in Canadian Geotechnical

Journal, July 2007.

15. Long, MM (1997). “Design and

Construction of Deep Basements in

Dublin, Ireland” Proc XIV Int. Conf. on

Soil Mech. and Foundation Engineering,

Hamburg, Germany , September 1997,

Vol. 2, pp 1377-1380.

16. Long, M (2001). “A database for

retaining wall and ground movements

due to deep excavations”. ASCE Journal

of Geotechnical and Geoenvironmental

Engineering, Vol. 127, No. 3, March, pp

203 - 224. See also closure to discussion

on this paper by M. Long in Vol. 128,

No. 6, pp 536 – 537.

17. Long, M., Brangan, C. and Gavin, K.

(2002). “Behaviour of cantilever

retaining walls”. Geotechnical Aspects of

Underground Construction in Soft

Ground (IS-Toulouse 2002), Toulouse,

France, October. Published by

Spécifique, Lyon, ISBN 2-9510416-3-2,

pp 471 – 476.

18. Long, M. (2002a). “Observations of

ground and structure movements during

site re-development in Dublin”.

Institution of Civil Engineers Journal of

Geotechnical Engineering, Vol. 155, No.

4, October, pp 229 – 242. See Also

Discussion in Vol. 156, No. 3, p165.

Published by Thomas Telford Ltd.

19. Long, M. (2002b). “Review of behaviour

of basement excavations in Dublin glacial

till”. Proc. Workshop on Advanced

Laboratory Testing of Geomaterials,

NTU Singapore, Dec., pp 1 –22.

Published by Nanyang Technical

University. Also presented to IEI

Seminar on Basement Design and

Construction, 14 Nov.

20. Long, M., Menkiti, C. O., Kovacevic, N,

Milligan, G. W. E., Coulet, D. and Potts,

D. M. (2003). “An observational

approach to the design of steep sided

excavations in Dublin glacial till”.

Underground Construction 2003, London

UK , September, Published by

Hemmings, pp 443 – 454.

21. Long, M., Menkiti, C.O. and Follet, B.

(2004). “Some experience in measuring

pore water suctions in Dublin glacial

till”. Geotechnical News / Geotechnical

Instrumentation News (GIN), Vol. 22,

No. 3, Sept. 2004, pp 21 – 27. 22. Long, M. and Menkiti, C.O. (2007a).

“Geotechnical properties of Dublin

boulder clay”. Géotechnique, Vol 57, No,

7, September, 595 - 611.

23. Long, M. and Menkiti, C.O. (2007b).

Characterisation and engineering

properties of Dublin Boulder clay.

Proceedings 2nd International Workshop

on Characterisation and Engineering

Properties of Natural Soils (“Natural

Soils 2006”). NUS Singapore, November

/ December, Eds. Tan, T.S. et al.

Published by Taylor and Francis Group,

London, Vol. 3, pp 2003 - 2045.

24. Menkiti, C. O., Long, M., Kovacevic, N,

Edmonds, H., Milligan, G. W. E. and

Potts, D. M. (2004). “Trial excavation for

cut and cover tunnel construction in

glacial till- a case study from Dublin”.

Skempton Memorial Conference,

Imperial College London, March,

Advances in Geotechnical Engineering,

Eds. Jardine et al., Published by Thomas

Telford, Vol. 2, pp 1090 - 1104.

25. Skempton, A.W. (1954). “The pore

pressure coefficients A and B”.

Géotechnique, 4, No. 4, pp 153 - 173.

26. Skipper, J., Follett, B., Menkiti, C., Long,

M, Clarke – Hughes, J. (2005). “The

engineering geology and characterisation

of Dublin Boulder Clay”. Quarterly

Journal of Engineering Geology and

Hydrogeology (QJEGH), 38, pp 171 –

187, August.

Page 16: DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS · DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS ... Secant and Contiguous Pile Wall Solutions have been ... deep basement construction

h Soft H s

Stiff

Table 1. Summery of Case Histories - Propped Walls in Dublin Glacial Deposits

Case Location Soil at Soil strength H (m) h (m) Support s* (m) Wall type EI (kN/m2) Del. h (mm) Del. v (mm) Referencehistory dredge lev. su (kPa) configuration

26 Jervis St. Shopping Cen. DBC SPT N = 50+ 9.7 3 Single prop 8.5 Secant 1254800 3 0 Dougan et al. (1996)27 Clarendon St. carpark DBC N = 50+ 6.2 1 Single prop 5 Soldier pile 3895 7 0 Long (1997)28 M&S Grafton St. DBC N = 50+ 7.2 3 Single prop 6 Sheet piles 58500 5 2 Long (1997)39 Dáil Eireann DBC N = 50 to 100 6 0 Single prop 6 Secant 381700 3 0 Brangan (2007)40 Hilton Hotel, College St. Gravel over wth rock N = 50+ 6.3 4 Single prop 6.3 Secant 1254800 1.2 0 Long (2002a)41 ESAT, Grand Canal DBC 4 2 Single anchor 3.5 Secant 347000 5 ?? UCD files42 TCD - Lecky Gravel over DBC N = 30 to 100 7.2 0 3 anchors 2.5 Secant 347000 5 ?? Brangan (2007)43 TCD - Nassau Gravel over DBC N = 30 to 100 8.6 0 2 anchors 3.5 Secant 347000 7 ?? Brangan (2007)44 Ely Place DBC N = 47 to 100 3.5 0 Single prop / anchor 3.5 Secant 201300 3 ?? Brangan (2007)45 Harcourt St. Gravel over DBC N = 28 to 100 4.5 0 Single prop 3 Secant 381700 4.7 ?? Brangan (2007)46 Kings Inn St Gravel over DBC N = 30 - 45 5.7 3.9 Single prop 5.7 Secant 381700 5.5 ?? Brangan (2007)47 Balbriggan Gravel over stiff clay Med dense / stiff 5.7 2.5 Single anchor 5.7 Secant 644126 9 ?? BLP files36 Clancy Barracks Gravel over DBC Dense / hard 5.4 1.5 Single anchor 5.4 Secant 644126 1.5 ?? BLP files in progress48 Westgate Gravel over DBC N = 20 to 100 14 2 Single anchor 14 Secant 644126 7 ?? BLP files49 Tallaght Centre DBC N = 20 to 100 11 1.5 Single anchor 6 Contiguous 293620 18 ?? BLP files50 TCD - Sports Centre Gravel over DBC N = 30 to 100 6.9 1 2 to 3 anchors 3.5 Secant 644126 9.5 ?? BLP files51 DPT Northern C&C - DP8 DBC N = 30 to 100 12 1 Single prop 10.2 Diaphragm 4320000 4.5 ?? Curtis and Doran (2003)52 DPT Northern C&C - DP36 DBC N = 30 to 100 17 1 Two props 5.5 Diaphragm 4320000 8.5 ?? Curtis and Doran (2003)53 DPT - Shaft WA2 DBC N = 30 to 100 25 1 Single ring beam 12 Diaphragm 8437500 8.5 ?? Cabarkapa et al. (2003)

Page 17: DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS · DEEP EXCAVATIONS IN DUBLIN RECENT DEVELOPMENTS ... Secant and Contiguous Pile Wall Solutions have been ... deep basement construction

h Soft H s

Stiff

Table 2. Summery of Case Histories - Cantilever Walls

Case Location Soil at Soil strength H (m) h (m) s* (m) Wall type EI (kN/m2) Del. h (mm) Del. v (mm) Referencehistory dredge lev. su (kPa)

Stiff soil at dredge

1 Benwell Rd. London clay Stiff 4.5 ? 6.3 Contiguous 100661 11 ? Fernie and Sukling (1996)2 A329-Reading London clay 80 (UU) 6.9 1 9.66 Diaphragm 2500000 18 ? Carder and Symons (1989)3 Leith House London clay Stiff 3.7 6.6 5.18 Contiguous 465950 0.7 ? Thompson (1991)4 Sanct Bld London clay Stiff 5.3 2 7.42 Diaphragm 1280000 4 ? Thompson (1991)5 Newport Crt London clay 180 (UU) 3.7 4.8 5.18 Diaphragm 1280000 8 ? Wood and Perrin (1984)6 Putney Centre London clay Stiff 4.8 0 6.72 Diaphragm 1280000 3.3 ? Thompson (1991)7 British Library London clay Stiff 4 3 5.6 Secant 2571750 20* 20 Raison (1985)8 Bell Common London clay 130 (UU) 5.2 4 7.28 Secant 2330250 10 18 Tedd et al (1984)9 Dunton Green London clay 70 (UU) 8 0 11.2 Contiguous 4385400 38 ? Garrett and Barnes (1984)

10 Broadgate 5 London clay 200 (UU) 9 6 12.6 Contiguous 465950 8 ? Ove Arup & Ptns Files11 Broadgate 9/10 London clay 200(UU) 7.2 6 10.08 Contiguous 465950 10 ? Ove Arup & Ptns Files12 Nat Gal Ext London Clay Stiff 2.3 4.2 3.22 Secant 618000 3 ? Long (1989)13 Bentalls KuT London clay Stiff 6.5 2 9.1 Secant 2855000 12 ? Sherwood et al (1989)14 Waitrose KuT London clay Stiff 3.5 2 4.9 Contiguous 1132800 8 ? Ground Engineering (1985)

15 Swindon Kimmeridge Stiff 4.5 ? 6.3 Contiguous 179600 12 ? Fernie and Sukling (1996)16 Channel Tunnel Gault 60 (UU) 2.7 0 3.78 Sheet 73500 11* ? Young and Ho (1994)17 Cheltenham Lias 120 (UU) 10.6 0 14.84 Contiguous 4141760 40* ? Ford et al (1991)18 Batheaston Lias Very stiff /hard 8.5 0 11.9 Diaphragm 1280000 16 ? La Masurier (1997)19 Finchley Boulder clay 200 (UU) 5.2 1 7.28 Contiguous 1198500 11 0 Brookes & Carder (1996)

20 Manchester Sandstone ? 5 ? 7 Contiguous 254250 11 ? Fernie and Sukling (1996)21 Manchester Sandstone ? 5 ? 7 Contiguous 254250 11 ? Fernie and Sukling (1996)22 Edinburgh Coal Meas ? 6 ? 8.4 Contiguous 245400 6 ? Fernie and Sukling (1996)

23 Salzburg Gravel, clay ? 11.5 ? 16.1 Soldier Piles 1280000 100 30 Breymann (1992)24 Konstanz Gravel, clay ? 7.2 ? 10.08 Secant 639000 26 29 Goldscheider and Gudehus (1988)28 Bloomington, Minn Fill Stiif 7.9 ? 11.06 RC 1055000 4.5 ? Bentler and Labuz (2006)

29 Ship St., Dublin DBC, grav V. stiff / dense 3 2 4.2 Secant 95426 2 ? UCD files30 Intel, Leixlip Till V. stiff / dense 6.8 0 9.52 Contiguous 27600 2 ? Long (1997)31 Schoolhouse Lane DBC V. stiff / dense 5.5 0 7.7 Contiguous 190850 2 ? Long (1997)32 Hammond Lane Gravels Dense 4 2 5.6 Secant 381700 1.5 ? Brangan (2007)33 Parnell St DBC, grav V. stiff / dense 4 2 5.6 Contiguous 190850 2.5 ? BLP Files34 New St. DBC, lmst V. stiff / dense 5.5 2 7.7 Secant 282740 11 ? BLP Files35 North Wall Quay Complex Estuarine 7.5 2 10.5 Secant 644125 2 ? BLP files in progress36 Clancy Barracks DBC, grav V. stiff / dense 7 2 9.8 Secant 260870 1 ? BLP files in progress37 Cork St DBC V. stiff 6 2.5 8.4 Contiguous 238550 7 ? BLP Files38 Ballycullen Rd. DBC V.stiff 7 0 9.8 Contiguous 282740 18 ? BLP Files

51/52 DPT Northern C&C DBC V. stiff / hard 7 1 9.8 Diaphragm 4320000 3.2 ? Curtis and Doran (2003)

Soft soil at dredge

25 UOB Singapore Soft clay 30 (vane) 3 32 4.2 Diaphragm 4320000 10* Wallace et al (1992)26 San Francisco Soft clay soft 10 ? 23.5 Sheet ? 61000 220* ? Clough ??27 Thessaloniki Soft clay 30-40 (vane) 6.5 11.5 9.1 Diaphragm 14000 62* ? Hadjigogos and Avdelas (1998)39 Thorncastle Soft clay SPT 10 4 13 5.6 Secant 381700 23.5 ? Long et al. (2002)

* s = H or H + fixity