Upload
scot-richardson
View
212
Download
0
Embed Size (px)
Citation preview
Decommissioning Rules & Funds
for Renewable Energy Facilities
RenewElec WorkshopOctober 21, 2010
Jonathan VoegeleResearch AssociateInstitute for Energy and the EnvironmentVermont Law School
What is Decommissioning?
Controlled process to safely retire an electric generation facility. Deactivation Defueling Dismantling Site Remediation
2
Decommissioning Goals
Restoration to original environment Footprint reduction: removal of all structures Hazardous materials remediation
Avoiding environmental disturbances Noise, dust, water quality, impact on local
wildlife and vegetation.3
Dedicated funds Site-specific bonds or letters of credit Regulatory requirement but no contribution Local zoning ordinances with or without
dedicated funds requirements No requirement
4
Decommissioning Requirements
Decommissioning Implementation
State Lands Statute PUC Approval Processes or Orders Energy Facility Siting Evaluation Commissions
(EFSECs) Local Ordinances
Federal Lands Controlling Agency Regulations 5
State Implementation: Statute Specific statutes requiring PUC to adopt rules
governing site restoration Addresses specific renewable energy projects,
typically large wind facilities. Example: Minnesota
MN statute requires PUC to promulgate regs specifying decommissioning and restoration requirements for LWECS, including a valuation method mandating contribution levels. 6
State Implementation: PUCs
Utility commissions use approval processes and agency orders to impose requirements. Certificates of Public Good Siting Approval
Example: Vermont VT PSB conditions Certificate of Public Good
– a generation facility requirement – on decommissioning fund establishment. 7
State Implementation: EFSECs
One-stop licensing committees that provide centralized evaluation and oversight of large energy facilities and infrastructure. Jurisdiction triggered by project capacity rating
Broad public interest authority with varying degrees of standards.
Decommissioning imposed through siting certificate conditions. 8
State Implementation: EFSECs
Example: Oregon 35MW+ geothermal, solar or wind projects. Must find that a site “can be restored adequately to a
useful, non-hazardous condition following permanent cessation of construction or operation of the facility.”
Applicant must propose site restoration plan and expense estimate.
OREFSC reviews and imposes mandatory condition requiring bond or letter of credit prior to facility construction. 9
State Implementation: Zoning Absent statewide requirements, local zoning ordinances
regulate of decommissioning requirements (majority). Also used when projects do not meet nameplate capacity
for PUC jurisdiction. Example: South Dakota
SDPUC jurisdiction for100 MW wind farms Less than 100MW, SDPUC encourages local zoning
boards to impose requirements SDPUC “model ordinance” requires plan and financial
assurance after tenth operating year. 10
Federal Implementation Dept. of Interior: BOERME (MMS
successor). Projects in the outer-continental shelf (OCS)
• All non-hydrokinetic facilities.
• Hydrokinetic facilities prior to FERC licensing. Case-by-case basis at amount based on
anticipated costs of decommissioning. Requires financial assurance through bond or
letter of credit. 11
Federal Implementation
Bureau of Land Management Renewable projects sited on public lands. Requires decommissioning plan development
& approval prior to right-of-way authorization. $10,000 bond for each turbine on public lands,
subject to periodic review for funds adequacy.
12
Analysis
No correlation between state decommissioning rules and funds for renewable and non-renewable generation. Some states govern irrespective of resource. Others impose contingent on facility type.
13
Recommendations Statewide decommissioning regulations
Explicit PUC/EFSEC findings requirement that a site can be restored.
Requirement for decommissioning plans Requirement for financial assurance for the plan’s total cost.
Objectives Alleviate environmental and aesthetic considerations which
hinder large-scale renewable development. Offset risks for states with ambitious renewable portfolio
standards.14