Energy - Decommissioning 2002-4

Embed Size (px)

Citation preview

  • 7/29/2019 Energy - Decommissioning 2002-4

    1/58

    Offshore Decommissioning 2002

  • 7/29/2019 Energy - Decommissioning 2002-4

    2/58

    OffshoreDecommissioning

    Opportunities for Scottish BasedBusinesses

    2001

    (Including Update at March 2002)

    Prepared by Eric Faulds Associates on behalf of

  • 7/29/2019 Energy - Decommissioning 2002-4

    3/58

    1

    Index Page

    1.0 Introduction 2

    2.0 Executive Summary and Recommendations 3

    3.0 Decommissioning Background 8

    4.0 Numbers, types, locations and weights of offshore 10installations.

    5.0 Market Drivers. 14

    6.0 Business Sectors. 18

    7.0 Steel Platforms 19

    8.0 Concrete Gravity Based Structures. 34

    9.0 Subsea installations. 37

    10.0 Drill cuttings 38

    11.0 Pipelines 41

    12.0 Well Plug and Abandon 44

    13.0 Reuse of Offshore Installations 46

    Internet References 50

    Appendix A 51

    All rights reserved. No part of this publication may be reproduced, stored in aretrieval system, or transmitted in any form or by any means, electronic,

    mechanical, photocopying, recording or otherwise, without the prior writtenpermission of the publisher.

  • 7/29/2019 Energy - Decommissioning 2002-4

    4/58

    2

    1.0 Introduction

    During the next couple of decades decommissioning of offshore structures will be

    another major opportunity for Scotland. It is vitally important that we understand the

    size and nature of the opportunity and develop the appropriate strategy to maximise

    the economic impact to Scotland.

    Scottish Enterprise Energy has commissioned this study as a first step in identifying

    the opportunities and informing the industry of the same. Our next task will be

    engaging other public sector partners as well as industry in appropriate dialogue to

    determine the future course of action.

    The focus of this report is on the decommissioning of offshore platforms. In addition

    the report will cover other decommissioning sectors such as pipeline

    decommissioning and drill cuttings where the information and knowledge available is

    somewhat limited. Re-use of installations for new purposes will also be considered.

    There is a paucity of reliable information on which to base predictions regarding the

    development of the North Sea decommissioning market. This is in part due to the fact

    that there has been very little experience of decommissioning to date and no

    experience of removing very large offshore structures in any part of the world. In

    addition, there are no regulations in place regarding aspects such as drill cuttingsand pipeline decommissioning. History has shown us that the predictions of likely

    costs of major new engineering projects, where there is no previous experience, are

    likely to be seriously underestimated. It is reasonable to expect the same situation

    will occur in decommissioning, particularly for the early decommissioning projects.

    A variety of public domain information as we ll as proprietary data have been used in

    the preparation of this study. There is some lack of consistency in the data due to

    the different sources but despite this we believe it is sufficiently reliable for the

    purposes of this report.

    Scottish Enterprise hope that this study would make a valuable contribution to the

    subject of decommissioning of offshore facilities, and it would lead to maximisation of

    economic benefits from this opportunity, to Scotland.

  • 7/29/2019 Energy - Decommissioning 2002-4

    5/58

    3

    2.0 Executive Summary

    The offshore decommissioning market is still in its infancy and as a result there are

    uncertainties regarding what the total market requirements may be and how the

    market might develop. However, there are also a number of certainties. The cost of

    decommissioning will be very high. We estimate that the total for the entire North Seais unlikely to be less than 20 billion and could easily be 30 billion. This expenditure

    will be spread over a period of some 20 to 30 years and most importantly, it is a

    market that is absolutely ce rtain to occur and it will occur on Scotlands doorstep.

    We also believe that the underlying commercial drivers behind the decommissioning

    market will ensure that it will be a relatively predictable market without the cyclical

    swings in demand experienced in the development of the North Sea.

    In terms of potential decommissioning market value, the tonnage of platforms to be

    removed provides a good indication of the likely cost. In terms of tonnes of steel

    contained in the offshore platforms, the approxima te split between countries is shown

    in the pie chart below:

    England

    10%

    Scotland

    43%

    Norway

    38%

    DK

    2%NL

    7%

  • 7/29/2019 Energy - Decommissioning 2002-4

    6/58

    4

    The total decommissioning market can be broken down into a number of distinct

    activities. Whilst there is no North Sea track record for decommissioning it is difficult

    to be precise about the total value of the market. The chart below gives the order of

    magnitude of the UK Sector Costs.

    Order of Magnitude UK Sector

    Decommissioning Costs

    02,0004,0006,0008,000

    10,00012,00014,00016,000

    Total

    Pipe

    lines

    SteelPla

    tforms

    WellP

    &A

    ConcretePla

    tforms

    DrillCuttings

    million

    Cost estimate range

    It is generally not recognised that plugging and abandoning wells will account for a

    substantial part of the cost of decommissioning an offshore production platform. This

    will be a significant expanding market that will require an increase in specialist

    expertise and equipment. We envisage that companies already operating in Scotland

    will be able to expand to meet these requirements and lead the way in developing

    lower cost and more reliable techniques. There may also be opportunities for new

    players.

    The requirements for dealing with drill cutting waste deposited on the sea bed

    beneath many of the installations off the Scottish Coast have not yet been

    determined but there is little doubt that there will be significant market opportunities

    for companies in the removal, handling and treatment of both drill cuttings and the

    associated contaminated water.

    There is likely to be a significant market in pipeline decommissioning which will be

    dominated by the need for offshore marine equipment and diving services. However,

    until the decommissioning requirements are better defined there are no obvious near

    term business opportunities apart from the removal of small diameter flowlines and

    cables associated with the decommissioning of subsea installations.

  • 7/29/2019 Energy - Decommissioning 2002-4

    7/58

    5

    The greatest near term market opportunities will be associated with the

    decommissioning of fixed offshore platforms. The key question is how can Scottish

    business ensure that it secures a large slice of this cake?

    Approximately sixty to seventy percent of the cost of removing an offshore platform is

    associated with the offshore heavy lift contractor and currently the heavy lift

    equipment is owned and operated by Dutch and Italian companies. The vesselstypically operate out of The Netherlands or Norway. If the status quo remains then

    Scotlands slice of the cake for platform removal will be limited to the supply of

    offshore labour, diving vessels and onshore disposal.

    The worldwide market for heavy lift vessels is increasing and with the additional

    requirements of North Sea decommissioning, demand is likely to exceed supply and

    apply upward pressure on prices. There is a perceived need for additional

    competition in this market and this is expected to come from the development of a

    new generation of heavy lift vessels aimed at the decommissioning market but also

    capable of competing for new installation work. These new designs are being

    developed in Norway and The Netherlands but there is a unique opportunity for

    companies with a Scottish base not only to build these new vessels but, more

    importantly, to operate them. If these new vessels can be based in Scotland then

    Scotlands share of the market will be greatly enhanced since the vessels base not

    only influences its maintenance and direct support activities it also influences the

    operation of associated cargo barges, fabrication of necessary steelwork as well as

    engineering design and project management work. The recently announced plan by

    Phillips Petroleum in Norway to use the new technology vessels on the first two

    removals of Ekofisk installations make it virtually certain that at least one of these

    new generation vessels will be built and operated. We estimate that if one of the new

    generation vessels could be based in Scotland then the value of steel platform

    removal work coming to Scotland could amount to 4.5 billion and there is the

    additional potential of income from the worldwide platform installation market.

    Without a vessel based in Scotland the value of removal work coming to Scotland

    may be as low as 1.5 billion. It will take both political and corporate initiatives to win

    this prize.

    There is now a general realisation that the onshore dismantling of offshore

    installations will not create many jobs. Industry estimates suggest approximately 150

    to 200 jobs per annum on average will be required in the UK. We anticipate that there

    will be a requirement for about three decommissioning yards in the UK. Able UK,

    based in Teesside is well established to dominate the Southern North Sea market

  • 7/29/2019 Energy - Decommissioning 2002-4

    8/58

    6

    and the deep water in Shetland along with its proximity to the Northern North Sea

    fields will give the Shetland Decommissioning Company a distinct advantage over its

    UK competitors. We believe however that the market could support an additional

    yard located in Scotland.

    A feature of decommissioning to date has been the continual slippage in the market

    getting effectively underway. This has caused problems where a number ofcompanies have invested in the development of new technology only to find the start

    of the market has slipped. There is no doubt that there will be a tendency for this

    slippage to continue but there are a number of events planned to occur in 2001 which

    are likely to be significant.

    The Maureen (1) platform will be removed in mid summer and taken to

    Norway. Whilst benefit to the UK may be limited it will raise awareness of the

    decommissioning challenge.

    It is expected that Phillips Petroleum in Norway will commence the

    prequalification procedure for 3 of the Ekofisk installations in July this year

    (2001). For two of the installations new technology lift equipment will have to

    be used. It is expected these critical contracts will be awarded in Spring 2002.

    TotalFinaElf(3) are due to publish their decommissioning plan for the Frigg

    Field in the very near future. This will be a major decommissioning

    programme and will include the first large platforms to be decommissioned in

    the UK sector.

    These events will arguably bring a renewed focus on decommissioning and with the

    expectation of prequalification activities commencing this will require contractors to

    seriously consider their position and plans for entry into the market.

    The above summary has focussed on the major activities but given the enormous

    size of the market a very small slice of the cake will represent a large volume of

    business for many specialist companies.

    Although the reuse of offshore facilities and equipment in newlocations has received

    considerable attention and effort by decommissioning specialists, without much

    success to date, the potential economic benefits suggest that this is not an aspect

    that should be dismissed. There is a need to identify what markets, if any, could

    utilise redundant North Sea installations.

  • 7/29/2019 Energy - Decommissioning 2002-4

    9/58

    7

    In addition, a number of offshore structures have been reused for new purposes with

    the reuse of Brent Spar in Norway to form a new quay structure a prime example.

    There have been suggestions that offshore installations could be used not only for

    coastal engineering projects but also for offshore aquaculture and power generation

    utilising wind and wave power. We believe that these ideas require study to

    determine their merits.

    It should not be forgotten that the UK government bears a significant part of the cost

    of decommissioning (up to 60 to 70% in some instances) through tax rebates to the

    oil companies. The use of redundant platforms to provide wealth creating

    infrastructure improvements such as quaysides etc may help offset this charge on

    the UK economy.

    In conclusion, 2001 and 2002 is likely to see significant developments in the

    Norwegian sector and investment in new technology lifting vessels. Early action is

    required if Scottish based companies are to obtain a significant foothold in the

    market. In particular there are new opportunities to build and operate new heavy lift

    vessels, to take a lead in developing low cost well plugging technology, to develop

    sea bed waste handling technology and to utilise offshore installations for renewable

    energy and aquaculture purposes. All of these business areas have worldwide

    applications. If business initiatives are not put in place, there is the likelihood that

    Norwegian and Continental based companies will gain the lions share of the

    decommissioning market in UK waters.

  • 7/29/2019 Energy - Decommissioning 2002-4

    10/58

    8

    3.0 Decommissioning Background.

    The footings referred to above are the large heavy sections at the base of steel

    jackets where the jacket is connected to the foundation piles. The maximum number

    of steel installation footings that could be left partially in place under these

    regulations is 34 out of approximately 600 in the North Sea.

    The application of these new regulations has yet to be put to th e test although

    Phillips Petroleum in Norway have proposed that derogation should be sought toleave the Ekofisk Concrete Tank structure in place.

    3.1 Decommissioning Process.

    The decommissioning process in the UK is governed by the requirements of the

    Petroleum Act 1998. The process is clearly set out in guidance notes (14) published

    by the DTI. In summary the process is as follows:

    Stage 1. The Operator of the installation undertakes preliminary discussions with the

    DTI. This will typically take place 3 to 5 years in advance of the expected

    decommissioning date. The Operator will outline the likely timetable of future events.

    Stage 2. Detailed discussions of a draft decommissioning proposal. For

    straightforward cases where installations are being totally removed this is likely to be

    Topsides

    DEROGATION?

    Must leave 55metres

    water column above

    remaining items

    Must provide

    navigation markings

    YES

    NO

    NO

    YES

    YES

    YES

    UK REQUIREMENTSINSTALLATION

    Steel Jacket10,000tonnes

    Can dump or leave part

    or whole in place

    Can leave footings

    Remove

    Remove

    Exceptional case

    damage etc

    Can dump or leave part

    or whole in place

    Can dump or leave part

    or whole in place

  • 7/29/2019 Energy - Decommissioning 2002-4

    11/58

    9

    a straightforward process. However if the installation is large and has the potential to

    be considered for derogation then the OSPAR requirements will have to be taken into

    account.

    Stage 3. Consultation with interested parties.

    Stage 4. Formal submission of the decommissioning proposal and approval by theSecretary of State.

    Stage 5.Execution of the work.

    Stage 6.Monitoring of the site if applicable.

    Particular points to note from the above process are that the Operator of the

    installation drives the process and the regulator is the DTI who will make the final

    decision regarding an Operators proposals. Although the regulations set out by the

    OSPAR Convention are significant for a small number of large installations the

    OSPAR Convention is not a regulator and has no decision making role in the

    process. It is also relevant to note that both the OSPAR regulation and the DTI

    Guidance notes require Operators to cooperate and share information on

    decommissioning matters.

    ALL CASES

    Secretary of State

    calls for formal

    Submission

    ADDITIONAL

    ACTIVITIES

    REQUIRED FOR

    DEROGATION

    Up to three

    years before

    decommission

    Maximum of 32 weeks

    for OSPAR consultation

    process

    Detailed

    submission

    and

    consideration

    of draft

    programme

    Consultation

    with

    interested

    parties

    Formal

    submission

    and approval

    of

    programme

    Commence

    main works

    and undertake

    site surveys

    Monitoring

    of

    site

    Preliminary

    discussions

    with

    Government

    Departments

    Consultation

    with OSPAR

    Contracting

    Parties

    Assessment

    of

    options in

    accordance

    with

    OSPAR

  • 7/29/2019 Energy - Decommissioning 2002-4

    12/58

    4.0 Numbers, types, locations and weights of offshore installations

    There are approximately 600 platforms located in the North and Irish Seas. The exact

    number quoted by various sources varies, as there is no consistency in how

    platforms are counted. For example some sources regard two platforms linkedtogether by a bridge as one platform whilst others count these as two platforms.

    The platforms are located mainly in UK, Norwegian, Dutch and Danish waters.

    The great majority of installations are fixed platforms comprising a steel jacket fixed

    to the seabed with piles along with a topsides structure containing drilling, process

    and living facilities. Approximately 4% of the total numbers are very large concrete

    gravity based substructures. There are also a number of floating installations and

    subsea installations

    The table below shows the location of installations by type and by country.

    Country SteelJacket

    ConcreteSubstructure

    Subsea

    Floating Total

    UK (UK) 227 12 56 17 312

    Norway (N) 69 13 54 9 145

    The Netherlands (NL) 118 2 7 127

    Denmark (DK) 39 39

    Germany (D) 1 1 2Total 454 28 117 26 625

    It can be seen that the UK has 50% of the total number of North Sea installations

    located in its controlled waters.

    The cost of removing a platform increases with size and weight and therefore, for the

    decommissioning market, the tonnage of materials to be disposed of is more

    significant than installation numbers. Platforms tend to get larger and heavier as the

    water gets deeper.

    The table below gives the total weight in millions of tonnes of offshore platforms by

    sector and type. Concrete substructures have been excluded.

  • 7/29/2019 Energy - Decommissioning 2002-4

    13/58

    11

    UK N NL DK D Total

    Topsides(steel jacket platforms)

    1.11 0.75 0.28 0.09

  • 7/29/2019 Energy - Decommissioning 2002-4

    14/58

    12

    England

    10%

    Scotland

    43%

    Norway38%

    DK

    2%NL

    7%

    National Tonnages

    Sector Map showing number of steel platformsand total tonnage of steel

  • 7/29/2019 Energy - Decommissioning 2002-4

    15/58

    13

    The above analysis has looked at the distribution of offshore installations. There is a

    lack of good data on other aspects of decommissioning such as pipelines and the

    treatment of drill cuttings. As a general guide however, the UK and Scotland in

    particular has the greatest share of the volume of each aspect of decommissioning.

  • 7/29/2019 Energy - Decommissioning 2002-4

    16/58

    14

    5.0 Market Drivers.

    5.1 Timing.

    The fundamental driver influencing an Operator when considering decommissioning

    is that it is a very high cost outlay with no associated income.

    A prime objective of both Operator and government is to maximise the production

    from any field and combined with the financial penalty of decommissioning at the

    end of field life there is every incentive to delay cessation of production for as long as

    possible. This may be done by introducing cost saving measures in the production

    and operating processes and could include selling the asset to a lower cost Operator

    or by utilising new drilling and production technology or by a combination of all of

    these measures.

    An excellent example of field life extension is Shells Auk field, which was installed in

    1974 with a life expectancy of no more than 7 years the latest prediction is that it

    could produce until 2010.

    Ultimately however fields will become uneconomic either through falling production

    levels or through a drop in oil price. Both well production and oil price are difficult to

    predict accurately and hence cessation of production dates may change from time to

    time with a tendency for dates to recede.

    It should be noted that a low oil price does not necessarily lead to early

    decommissioning of installations since, in this instance, the Operators will be cash

    constrained and will be extremely reluctant to spend money on activities that do not

    generate income. Although high oil prices will tend to delay the cessation of

    production of oil fields high oil prices may accelerate the cessation of production from

    gas fields as consumers maximise their use of lower cost gas in preference to oil. It is

    also important to note that cessation of production and decommissioning dates are

    not necessarily closely linked. There may be many years between production

    shutdown and the start of decommissioning.

    There are however other drivers that may, in certain circumstances, tend to

    accelerate decommissioning. Delaying a number of decommissioning projects could

    build up a significant cash flow problem in the years ahead. Tax offsets will be

  • 7/29/2019 Energy - Decommissioning 2002-4

    17/58

    15

    generated and it may suit an Operator to optimise its tax position by

    decommissioning earlier rather than later. Some Operators may also have fears

    regarding the financial strength of some of their partners and would prefer not to

    delay. It should be noted that all partners in a field are held liable for

    decommissioning costs. In addition, the Government will not wish to see undue delay

    which could increase financial risks if some licence owners ceased trading and there

    will be pressure from fishermen and others to see the sea bed cleared of installations

    as soon as practically possible.

    Nevertheless, the overall trend is likely to be a delay decommissioning and this has

    certainly been the experience to date.

    5.2 Cooperation

    With all Operators having to face the loss making business of decommissioning and

    combined with the fact that it is not core business there is the basis for a much more

    cooperative approach between Operators compared to new field development. In

    addition, OSPAR regulation requires cooperation and DTI Guidance Notes state:

    The Government is keen to encourage Industry co-operation and collaboration at the

    decommissioning stage.

    5.3 PoliticsAlthough different fiscal regimes exist in Norway and the UK the net effect of both isthat the Governments have to contribute a significant amount to the

    decommissioning costs either directly in the case of Norway or indirectly through tax

    relief in the UK.

    An important consequence therefore, is that both Government and Operator

    objectives are aligned as far as reducing decommissioning costs are concerned.

    On environmental issues however there is the potential for divergence in that

    Operators would generally prefer to see environmental issues evaluated on the basis

    of sound science whereas Governments will tend to be more sensitive to emotionally

    based public opinion. However, in reality, environmental considerations, although

    important, are unlikely to have a further significant effect on the installation removal

    market. The same cannot be said about the removal of drill cuttings and pipelines

  • 7/29/2019 Energy - Decommissioning 2002-4

    18/58

    16

    from the sea bed. Environmental issues will continue to play a significant role in

    establishing the extent of these particular markets.

    To date there has been limited political interest in ensuring that the UK maximises its

    opportunities in this large new market. Most new business development has been

    Norwegian based and without political pressure we will probably see Norway taking a

    disproportionate amount of the North Sea decommissioning business.

    Although EU trading rules do not permit Norway and the UK to protect their

    decommissioning markets the Basel Convention on the export of waste which, in

    essence, requires each country to dispose of its own waste could arguably be

    applied to offshore decommissioning. There is therefore an expectation that although

    Norway will tend to have an advantage in special situations such as Brent Spar and

    Phillips Maureen, where deep water is particularly significant, the vast majority of UK

    offshore installations will be decommissioned in the UK.

    5.4 Effects of Drivers

    It is important to appreciate that the market drivers in decommissioning are distinctly

    different from new field development. Although both are high cost activities new field

    development costs are offset by income to be generated from the investment.

    Decommissioning costs must be met from cash available at the time of

    implementation and any overrun in expenditure will have an immediate effect on a

    companys annual profit. In new field development, time is normally a critical factor,

    particularly once project development gets underway. In decommissioning, time will

    be relatively unimportant and this is likely to have a significant influence in the way

    the market develops. Generally, the longer a project is delayed the better the

    financial return for the Operator in terms of net present value. The need to get a new

    project completed on time tends to minimise cooperation between projects, even

    within the same company. Decommissioning is likely to see much more cooperation

    between companies.

    The fundamental driver of high cost no income for the Operator will arguably lead

    to a strong drive to create an industry with the greatest overall efficiency and hence

    lowest possible cost consistent with safe and environmentally acceptable practices.

    An efficient offshore decommissioning industry will require the following features:

  • 7/29/2019 Energy - Decommissioning 2002-4

    19/58

    17

    The best possible technology available when needed.

    Competition.

    Innovation.

    Equipment and human resources available when needed. A predictable and smooth workflow without boom and bust periods.

    The greatest single problem to date with respect to developing new technology has

    been the trend for decommissioning start dates to continually slip. The development

    of new heavy lift vessels has been particularly hampered in this respect with several

    companies commencing development aiming for a market commencing in 2001 only

    to find that it will not commence until 2003 at the earliest. Maintaining a development

    team for an additional two years is clearly a significant burden.

    The flexibility of decommissioning timing should however bring benefits in that it will

    be feasible to delay a decommissioning start whilst a particular piece of technology is

    developed if it can be shown that this will reduce cost. Another advantage arising

    from the potential to delay is the expectation that it will be easier, compared to new

    field development, to obtain contractual commitments from a client prior to a

    developer investing capital in new hardware.

    The oil industry is fully committed to the belief that competition drives down costs by

    focussing on efficiency and encouraging innovation. There is no reason to believe

    that the decommissioning business will be any different.

    We believe that boom and bust periods will be less likely in the decommissioning

    market. Our expectation is that contracts will generally be let on a multi-project basis

    spread over a number of years and that the combination of timing flexibility and a

    determination to keep costs down will smooth out the work flow. If a peak in demand

    arises and is driving up costs then the projects will simply be delayed until supply and

    demand are back in balance.

  • 7/29/2019 Energy - Decommissioning 2002-4

    20/58

    18

    6.0 Business Sectors.

    6.1 General

    Offshore decommissioning can be broken down into a number of distinct business

    sectors comprising the decommissioning of steel platforms, concrete gravity based

    platforms, sub-sea installations, drill cuttings, pipelines and well plug and

    abandonment.

    An indication of the order of magnitude costs of potential decommissioning costs for

    each of these sectors is shown in the chart below. (Subsea decommissioning is

    excluded as it is small in comparison to the other sectors)

    Order of Magnitude UK Sector

    Decommissioning Costs

    0

    2,000

    4,000

    6,000

    8,000

    10,000

    12,000

    14,000

    16,000

    Total

    Pipelin

    es

    SteelP

    latform

    s

    WellP

    &A

    ConcretePlatf

    orms

    DrillC

    uttings

    million

    Cost estimate range

    It must be emphasised that the above numbers can only be regarded as rough

    estimates but they do give an indication of the relative size of each sector.

  • 7/29/2019 Energy - Decommissioning 2002-4

    21/58

    19

    7.0 Steel Platforms.

    7.1 Cost Breakdown

    The estimated decommissioning cost of this sector, excluding the cost of

    plugging and abandoning wells, is in the order of 4 to 7 billion for the UK

    sector.

    From our cost database we can derive the breakdown shown below of the

    major business sectors within the steel platform decommissioning market.

    Materials &

    Fabrication

    15%

    Onshore

    scrapping

    4%

    Design &

    management

    10%

    Offshore

    Support

    10%

    Offshore

    Preps

    10%

    Marine

    HLV

    30%

    Marine support

    contracts21%

    Onshore

    29%

    Each sector will be discussed below:

  • 7/29/2019 Energy - Decommissioning 2002-4

    22/58

    20

    7.1.1 Heavy Lift Vessel (HLV).

    Virtually all offshore platforms were installed using heavy lift crane vessels such as

    shown below. Similar vessels will be required for the removal of the installations

    These specialist vessels with their unique lifting capacity up to 12,000 tonnes are, not

    surprisingly, expensive pieces of equipment with costs ranging from typically

    350,000 to 500,000/day and higher for exceptional lifts.

    The heavy lift vessel will be the key resource during the offshore removal process.

    7.1.2 Marine Support Contracts.

    The heavy lift vessel will need the support of other specialist services. In particular

    diving support, underwater cutting equipment, tugs, supply boats and cargo barges.

    7.1.3 Offshore Preparation.

    Before the heavy lift vessel can remove the topsides a considerable amount of

    preparation work will have to be carried out prior to lifting. For example the facilities

    will have to be cleaned of residual hydrocarbons where necessary and pipework,

    ductwork, cables, structural steel etc. will have to be cut to release each section

    being lifted. In addition, the lifted sections will require a thorough inspection and are

    likely to need new lifting eyes to be attached to the structure which also may require

    strengthening. All this work will require an offshore labour team.

    7.1.4 Offshore Support.

    Although some of the offshore preparation work may be able to be carried out while

    the platform has adequate safety and life support facilities it is likely to reach a stage

  • 7/29/2019 Energy - Decommissioning 2002-4

    23/58

    21

    where a flotel (accommodation vessel) is required to provide the necessary support

    to the labour team. In addition crew changing, equipment and supplies, catering, etc.

    will be required to be provided via helicopter and supply boat.

    7.1.5 Design and Management.

    Clearly, a major decommissioning project will require an onshore team of engineers

    to design a safe and efficient removal method and will need a team onshore and

    offshore to manage the project.

    7.1.6 Materials and Fabrication.

    It is often not appreciated that there is likely to be a substantial amount of fabricated

    steel required to ensure that the various platform sections can be safely lifted and

    supported during transport to shore. This work will be heavy structural steel

    fabrication. It is expected that this work will create many more jobs than those

    created with onshore d isposal work.

    7.1.7 Onshore Disposal.

    Although onshore scrapping and waste disposal is perhaps perceived as a major part

    of decommissioning it is in fact a relatively small part of the work as far as costs and

    jobs are concerned.

    When steel structures are removed they will either have to be reused, which is

    considered to be an unlikely occurrence in most cases, or brought to shore for

    dismantling and disposal. The basic requirements for an onshore decommissioning

    site are that it must have a strong quayside with a water depth of around 9m, and

    ideally over 20m, along with adequate space to layout the offshore facilities. In

    addition, hard standings with a closed drain system will be required and there will be

    a need for craneage and cutting plant. Existing technology will be capable of dealing

    with onshore disposal.

    The amount of hazardous wastes such as asbestos, radioactive material, etc. which

    will come ashore with the structures will be very small relative to the total amount of

    materials. However, these wastes will clearly need to be treated and disposed of in

    accordance with regulations. Existing technology is capable of dealing with these

    wastes. The disposal of low-level radioactive waste known as Low Specific Activity

    (LSA) scale which forms on some pipework will need careful consideration by both

  • 7/29/2019 Energy - Decommissioning 2002-4

    24/58

    22

    contractors and authorities. In the UK there are a limited number of sites which are

    licensed to remove the scale material and the UK depository for low level wastes at

    Drigg does not have sufficient capacity under its current licence to take all of the

    North Sea waste.

    7.2 Steel Installation Technology Issues.

    7.2.1 Conventional Heavy Lift Vessels.

    The offshore steel platforms were generally installed by first transporting a steel

    jacket structure on a barge, see photo below,launching the jacket into the sea and

    pinning it to the sea bed using steel piles.

    The topsides structures were placed in position using a heavy lift vessel such as the

    one shown below:

    In principle, it should be feasible to reverse the topsides installation process simply

    by utilising a heavy lift vessel to remove the sections in the same sequence as they

  • 7/29/2019 Energy - Decommissioning 2002-4

    25/58

    23

    were originally installed. For the majority of offshore installations this should be

    technically straightforward. There are however two problem areas worth noting.

    1. The preparation of the offshore structures to make them safe to lift could be

    extensive. Over the years many modifications may have taken place, such as

    the installation of additional fire and blast walls following the Piper Alpha

    disaster, which make the sections too heavy to lift without removing the

    excess weight. Additionally all the interconnecting structural, electrical and

    mechanical interconnections between each section will have to be cut taking

    into account that the pipework may contain hydrocarbon residues. Efficient

    cold cutting techniques will therefore be required.

    2. Whilst it is feasible to lift a very large deck of up to 12,000 tonnes from a

    cargo barge using two cranes acting in tandem as in the photo above, it willbe difficult to reverse the process in anything other than flat calm sea

    conditions since placing a large deck structure onto a moving barge could

    result in serious damage to the barge. In these cases the large decks may

    have to be cut into smaller pieces or alternatively new stronger barges or

    shock absorbing technology will have to be introduced.

    The jacket installation process of launching the structures into the sea utilising gravity

    clearly cannot be reversed for removal. Current technology requires the jackets to be

    cut into lift size pieces for removal by a heavy lift crane vessel. The following issuesarise with the larger jacket structures:

    A large number of underwater cuts of structural members will be required.

    This could be several hundred for a large structure.

    Very thick steels, up to 75mm and potentially greater, will have to be cut.

    Efficient underwater cutting technology will be required.

    Some jacket sections, the pile clusters in particular, will be extremely heavy

    and will require complex lifting arrangements to ensure a safe lift.

    Great care will be required to ensure that, as the structure is progressively

    removed, the remaining structure remains stable.

  • 7/29/2019 Energy - Decommissioning 2002-4

    26/58

    24

    7.2.2 New Technology Lift Vessels.

    There are a number of companies actively developing a new generation of heavy lift

    vessels. The objective of the new vessels is to lift off the topsides of offshore

    installations in a single lift and a number of the vessels also aim to remove jackets in

    a single piece for transport to shore. The lifting capacity of these new vessels will be

    up to 20,000 tonnes and potentially higher. The vessels will equally be able to be

    used for offshore installation as well as removal.

    These vessels can be compared to giant floating forklift trucks where the forks fit

    under the deck and by deballasting the vessel the deck can be lifted from the

    substructure.

    Graphic impressions of the Pieter Schelte being designed by Excalibur Engineering

    bv (6)are shown below. The picture sequence indicates how the topsides and jacket

    of a large installation can be removed in two large lifts and transported to shore.

    Installation of a new platform would simply reverse this process.

  • 7/29/2019 Energy - Decommissioning 2002-4

    27/58

    25

    A similar sequence is shown below for the Marine Shuttle (7) being designed in

    Norway. There are a number of other vessels being developed essentially along

    similar principles to the vessels indicated to the Pieter Schelte and the Marine

    Shuttle.

    The oil companies are currently studying the technical issues associated with these

    vessels. However, to date no commitments have been made to use these vessels.

  • 7/29/2019 Energy - Decommissioning 2002-4

    28/58

    26

    7.3 Steel Installation Market Development.

    The removal of the steel installations will be the most significant activity in the

    decommissioning market and has received the greatest amount of study and

    consideration to date. Nevertheless, as stated previously, there is virtually no

    experience of the market in the North Sea and although a considerable amount of

    decommissioning has taken place in the Gulf of Mexico the amount of learning that

    can be transferred is limited. This is primarily due to the much greater size and

    weight of the North Sea installations, particularly those in Scottish waters. The

    following development predictions must therefore be treated as speculative.

    The development of the North Sea construction market has been characterised by

    cyclic activity where there has been an overheating of the market driving up prices

    and equally there have been slack periods when there has been an overprovision of

    resources.

    Although there have been a number predictions of decommissioning dates and work

    flow such as the one shown below showing jobs forecast published by the North Sea

    Decommissioning Group (8), part of the Government/Industry Pilot Task Force.

    NSDG Jobs Forecast

    Decommissioning Jobs - SpreadDecommissioning Jobs Ear ly-Late Spread

    -

    500.00

    1,000.00

    1,500.00

    2,000.00

    2,500.00

    3,000.00

    3,500.00

    2000

    2001

    2002

    2003

    2004

    2005

    2006

    2007

    2008

    2009

    2010

    2011

    2012

    2013

    2014

    2015

    2016

    2017

    2018

    2019

    2020

    2021

    2022

    2023

    2024

    2025

    2026

    2027

    2028

    2029

    2030

    2031

    2032

    2033

    2034

    2035

    Onshore Decommissioining

    Onshore Preparation

    Design

    Offshore Deconstruction

    Well Abandonment

    HLV

    DS V

  • 7/29/2019 Energy - Decommissioning 2002-4

    29/58

    27

    The above would seem to predict a similar boom and bust pattern for

    decommissioning. However the reader will note that the activity peaks occur at 2005,

    10,15, 20 25 and 30. These round number peaks are almost certainly a reflection on

    the inaccuracy of the predicted cessation of production date for each field. The fact

    that decommission dates need not closely follow cessation of production is ignored.

    We are firmly of the opinion that the above pattern of decommissioning will not

    happen in practice because of the common goal of driving down cost and the fact

    that timing is not a significant issue in decommissioning projects. If a boom period is

    developing and tending to drive up prices, then projects will simply be delayed until a

    better balance of supply and demand is reached. A good example of this smoothing

    in practice is the published plan for the decommissioning of 14 platforms in the

    Ekofisk field in the Norwegian sector. Phillips original plan to spread the

    decommissioning work over four campaigns stretching from 2003 to 2015 (2). (This is

    currently under review with work not now expected to commence until 2004) We

    believe a more realistic pattern of decommissioning activity is indicated in the chart

    below.

    Potential shape of UK platform Decommissioning

    Market

    0

    2

    4

    6

    8

    10

    12

    2000

    2002

    2004

    2006

    2008

    2010

    2012

    2014

    2016

    2018

    2020

    2022

    2024

    2026

    2028

    2030

    2032

    2034

    2036

    2038

    2040N

    umberofplatformsdec

    ommissione

    perannum

    As far as the near term market is concerned the prospects are as follows:

    Maureen (1) A contract has already been awarded to Aker to remove this installation

    in the summer of 2001 and to dismantle the installation in Norway. Like Spar,

    Maureen is a unique type of structure where the deep water of Norway has highly

    significant advantages compared to UK sites for decommissioning. The fact that

  • 7/29/2019 Energy - Decommissioning 2002-4

    30/58

    28

    Maureen will go to Norway for decommissioning should not be seen as an indicator

    for future decommissioning of steel platforms.

    Ekofisk (2).A huge field in the Norwegian sector where 15 installations are now

    redundant. Two of the insta llations are in UK waters although they come under

    Norwegian regulation. The platforms are in approximately 70 meters of water and are

    typically 8,000 tonnes total weight although there are significant differences above

    and below this figure. The field is operated by Phillips who have submitted

    decommissioning plans to the Norwegian Government for approval. The need to

    decommission these platforms is largely driven by subsidence of the reservoir and

    the sea bed which has resulted in the topsides of the installations being at risk of

    being damaged by storm waves. The decommissioning programme is therefore not

    directly driven by production levels or oil price. The current intention is that Phillips

    will formally commence the tendering process in July 2001 with an invitation to

    contractors to prequalify for the decommissioning of the two installations in the UK

    sector with the proviso that new lifting technology must be used and in addition they

    will seek contractors for the decommissioning of the concrete tank storage

    installation. It is expected that contracts will be let in Spring 2002. The requirement to

    use new technology for the two UK installations and the need to build the new lift

    vessels means that offshore removal is not likely to commence until 2004 o r 2005.

    Frigg (3) This is another major decommissioning project consisting of 5 large

    platforms plus a wrecked jacket structure. Three of the platforms are in the UK Sector

    and two are in the Norwegian Sector. Three of the platforms are Concrete Gravity

    Base Structures. It is anticipated that production in the field will cease in 2003 which

    would suggest the earliest decommissioning date is likely to be 2005. The Frigg Field

    installations will be the first large steel jacket and concrete installations to be

    decommissioned in the UK Sector and must be a key target for UK companies

    wishing to enter the decommissioning market.

    Hutton TLP (13) This is another unique structure with an early decommissioning

    date. The tension leg configuration makes this platform an excellent candidate for

    reuse at other locations throughout the world and it is expected that the unit will be

    sold in the near future and removed from the field in 2002 or 2003. There will also bea requirement to remove a seabed template and anchorages.

    North West Hutton. This platform was expected to be an early decommissioning

    project but the current high oil price has given it an extended period of economic life.

    Subject to the oil price remaining high it is thought unlikely that decommissioning of

    this installation will commence before 2005.

  • 7/29/2019 Energy - Decommissioning 2002-4

    31/58

    29

    7.4 Steel Installation - Market Opportunities

    7.4.1 Heavy lift vessel.

    Of all the business sectors the heavy lift vessel market is the most dominant. The

    heavy lift vessel is the key piece of equipment required for removal of an offshoreinstallation and therefore has tended to take on the role of main contractor with other

    sectors such as marine support, material and fabrication, onshore scrapping and

    design and project management being subcontracts or part of a joint venture. The

    heavy lift contractor will therefore have a strong influence over 60 to 70% of the

    platform decommissioning costs.

    It is important to understand the market requirements of these key players in the

    decommissioning market. These are:

    1. A deep water port. These extremely large lifting vessels have a minimum

    draught of about 20 metres. There are no ports on the UK East coast that

    meet this requirement. This limits their home port to either Rotterdam or a

    number of locations in Norway. Rotterdam is the favoured location

    particularly for Heerema which is a Dutch company. The choice of home port

    is important since it tends to be the focus of all activities associated with the

    operation of the vessel.

    2. Cargo barge berths. Cargo barges to carry the structures either to or from

    the installation site are an essential part of the lift vessel equipment spread.

    The heavy lift companies own a fleet of these barges with additional barges

    being hired from specialist supply companies when required. The company

    owned barges tend to be moored in locations close to the operations centre of

    the heavy lift vessels themselves which is of course outside the UK.

    3. Steelwork fabrication. It is not generally appreciated that for removal (or

    installation) of large offshore platforms several thousand tonnes of temporary

    steelwork will have to be fabricated. These are special lifting aids and grillage

    steelwork that must be installed on the cargo barges to both spread the load

    on the barge and to facilitate removal of the structures from the barge. The

    fact that the grillage steel needs to be installed on the cargo barge and the

    lifting aids need to be available on the lifting vessel means that fabricators in

    the vicinity of the vessel and barges home port tend to have an advantage.

  • 7/29/2019 Energy - Decommissioning 2002-4

    32/58

    30

    4. Diving and underwater vehicle support. The removal of the underwater

    elements of offshore platforms will require the steel legs and bracings to be

    cut. The number of cuts could amount to several hundred. Scottish based

    companies are already well placed to meet this market.

    5. Offshore preparations for lifting. There will be a considerable amount of

    labour required to prepare the platform topsides for lifting. Modules will have

    to be cleaned, the interconnecting structural, electrical and mechanical

    systems will have to be cut, lifting points will have to be fitted, etc., etc.. Some

    or all of this work may be undertaken by contractors already on the

    installation as part of an Integrated Services Contract or it may have to be

    supplied entirely by the Heavy Lift Contractor. Either way the existing

    Aberdeen based service companies are extremely well placed to get this

    work.

    6. Engineering and Project Management. There will be a considerable

    amount of engineering work required to ensure that the offshore dismantling

    process undertaken by the Heavy Lift Contractor is undertaken in a safe way.

    The requirement will primarily be for structural engineers. Currently this work

    is undertaken by Heerema in their Leiden office and by Saipem in their

    London office. There is no reason to believe that this pattern will change and

    therefore there will be limited opportunity for Scottish Companies. Similarly

    the contractors project management team will normally be based at the

    contractors head office.

    It can be seen from the above that as things stand today there is limited opportunity

    for major involvement by Scottish companies to contribute to the heavy lift contractor

    activities which in turn account for 60 to 70% of the platform removal market. The

    supply of offshore labour and underwater vehicles and equipment will be the most

    significant contributions from Scotland.

    Can this situation by remedied? In our view this will not be easy. Even if a quay with

    20 metres water depth were to be built it is difficult to envisage the vessels relocatingfrom their well established bases. Particularly now that the heavy lift market is

    becoming increasingly more global.

    There will be a greater opportunity for barge mooring and the associated structural

    fabrication to be ba sed in Scotland particularly when decommissioning becomes an

    established business and if cargo barges become dedicated to decommissioning

  • 7/29/2019 Energy - Decommissioning 2002-4

    33/58

    31

    work. The onshore decommissioning yards themselves will be an obvious possibility

    to attract this business since the barges will be delivering their cargo to these yards.

    There is also potential benefit for both the onshore disposal contractor and heavy lift

    contractor if barges with cargo are over-wintered at the dismantling yard and the

    dismantling work carried out on the barge. In this way the onshore disposal company

    would save the considerable expense of taking the structures off the barge and in

    return the heavy lift contractor would save on mooring costs.

    Scotland is well placed to supply the necessary underwater services but to maintain

    this position it is critical that the Scottish companies keep ahead of technology

    development, particularly with respect to underwater cutting technology.

    A more speculative but potentially much more rewarding approach for Scottish

    business would be to attract one or more of the new technology lifting vessels.

    Firstly there is the potential to build or fit out these new vessels in Scotland but more

    significantly, as far as sustainable business is concerned, there is the opportunity to

    have these vessels based in Scotland not only to serve the North Sea

    decommissioning market but also the world wide installation market. By having the

    vessels based in Scotland there is the potential to attract the full range of support

    activities as well as the direct jobs associated with the heavy lift vessel and its

    management.

    In most cases these new vessels are being developed by design houses or

    development companies without the necessary expertise to operate the new vessels.

    They must link up with established construction companies before they can become

    a credible force. There is clearly an opportunity for established Aberdeen based

    offshore construction companies to link with the providers of the new vessels.

    7.4.2 Onshore Disposal.

    We believe tha t the myth that decommissioning would be the saviour of the Scottish

    fabrication yards has largely been dispelled. However we consider it important to

    emphasise that the value and jobs potential of onshore decommissioning is relatively

    small. In a recent study as part of the Pilot Task Force (8) it was estimated that

    onshore disposal would provide only 8% of the total decommissioning jobs

    associated with platform decommissioning. This is the equivalent of 150 jobs per

  • 7/29/2019 Energy - Decommissioning 2002-4

    34/58

    32

    annum in the UK averaged over a 25-year period. Given that there will be a ramp up

    and tail off of jobs then a peak job requirement of perhaps 200 can be envisaged.

    Even if these estimates are doubled the prediction is still a very low number of jobs

    compared to the numbers involved in fabrication. These estimates have recently

    been supported by Aker in Norway who are predicting a requirement for 100 jobs on

    average and a requirement for two decommissioning yards to serve the Norwegian

    sector. (The Norwegian market is approximately two thirds the size of the UK

    market).

    We estimate that the UK could support 3 onshore decommissioning yards. The

    established Able UK yard on Teesside is well placed for the Southern half of the

    North Sea and the proposed facility in Shetland is particularly well placed for the

    larger Northern facilities. The access to sheltered deep water gives Shetland a

    particular advantage over other UK sites. There is perhaps potential for another yard

    to be located in Scotland. The existing fabrication yards such as Nigg, Ardersier or

    Methil are obvious candidates but there are a number of factors acting against them

    in their current fabrication mode. Namely, overheads, high labour costs compared to

    the demolition industry and management with a fabrication mind set. In short the

    existing facilities are too sophisticated to be competitive. In the event that one of the

    existing fabrication yards ceases trading as a fabricator then it would be feasible to

    reinstate the yard for onshore decommissioning. With the UK likely to have an

    overcapacity in onshore decommissioning capability for some time, possibly 10

    years, we would not recommend investment at this time unless it is part of a

    diversified development with alternative income streams.

    7.4.3 Other areas

    As explained previously the decommissioning market is potentially very large and

    there will be opportunities for small and medium sized enterprises to play a

    significant role. Examples are given below:

    Weight engineering. Before an old structure can be lifted it will be necessary

    to accurately check the actual weight to be lifted. This estimate will have to

    take into account the many modifications that are likely to have taken place

    over the life of the installation. It is quite conceivable that structures will have

    to be reduced in weight before they can be lifted. There will therefore be a

  • 7/29/2019 Energy - Decommissioning 2002-4

    35/58

    33

    requirement for engineers to accurately check weights and to calculate

    centres of gravity.

    Structural Engineering. There will be a considerable amount of structural

    engineering calculation required to enable these installations to be safely

    removed.

    NDT Inspection. As well as checking the weight of structures it will be

    essential to check that the load bearing members of the structure are still

    sound and that corrosion or other defects are not compromising the safety of

    the lift.

    Environmental assessment. The media attention given to Shells Brent Spar

    proposal has created an impression that there are significant environmental

    hazards associated with the decommissioning of offshore structures. Brent

    Spar was a unique type of installation and cannot be used as a guide for the

    decommissioning of typical offshore platforms. Whilst environmental

    management will be important and there will be an ongoing requirement for

    specialist support in this area it should not be regarded as a major element of

    typical decommissioning projects.

    Equipment reuse. The difference between a successful onshore disposal

    contractor and an unsuccessful one may prove to hinge around success in

    maximising the sale of reusable equipment rather than simply scrapping it.

    There is a huge difference in value between resale and recycle but it requires

    specialists to identify the markets for surplus equipment.

  • 7/29/2019 Energy - Decommissioning 2002-4

    36/58

    34

    8.0 Concrete Gravity Based Structures. (GBS)

    8.1 General

    There are relatively few concrete GBS platforms in the North Sea with 12 in the UK

    and 13 in Norway.

    Whilst regulations require that the topsides of concrete platform must be removed

    and brought to shore or re -used the regulations recognise that it may be extremely

    difficult to remove the concrete substructures of these platforms. The regulations

    therefore permit exceptions or derogations to be permitted from the general rule of

    complete removal.

    Although the offshore removal of the topsides from the concrete platforms may bemore challenging compared to the steel platforms we do not see significantly different

    technologies or equipment being required. There may be a greater requirement for

    temporary lifting aids relative to the steel platforms but given the relative ly small

    number of concrete GBS platforms this will not be significant in the overall market

    place.

    The more significant issue is the feasibility of removing the concrete substructures

    from their offshore location and bringing them inshore for breaking up. Although a

    Norwegian study carried out in 1998 concluded that it would be feasible to remove

    concrete structures their work considered a second generation structure with

    systems built-in to assist the refloatation. Even for the second generation platforms

    the risks are not inconsiderable and there is a general belief within the industry that

    whilst it may be feasible to refloat the concrete structures the risks to both personnel

    and environment will generally be unacceptably high. This view has been reinforced

    by Phillips Norway concluding that they wish to leave the concrete tank installation in

    place in the Ekofisk field.

    There are no reliable published estimates of the costs of decommissioning the

    concrete GBS structures but if the platforms are removed from the field there is no

    doubt that the costs will be extremely high. Even the leave in place option will have

    significant costs associated with it. Not only for the removal of the topsides but also

    for the cleaning of the oil storage tanks.

  • 7/29/2019 Energy - Decommissioning 2002-4

    37/58

    35

    8.2 Concrete Platform Technology Issues

    Studies are underway to assess the viability of removing these platforms but to date

    little has been published.

    The generally recognised problems associated with removal are:

    1. Restoration of buoyancy. Many penetrations through the concrete walls and

    base slab will have to be plugged to restore buoyancy to the structure. The

    feasibility of establishing reliable plugs is questionable.

    2. Release of the soil suction. The soil beneath the base of the installation will

    have to be pressurised to release the natural suction that will exist between

    structure and soil.

    3. Grout and soil may adhere to the underside of the structure when the

    structure is refloated. The consequences of this heavy mass suddenly

    detaching itself from the base will have to be assessed.

    4. Many of the pipework systems used for installation will have corroded and

    become unserviceable.

    5. The structures may have suffered in-service damage and deterioration which

    will be difficult to measure.

    An alternative to total removal would be to take off the deck from the platform and to

    leave the concrete legs sticking out of the water with suitable navigation warnings.Removal of the deck section should be relatively straightforward using conventional

    heavy lift vessels. However there are question marks regarding how clean the oil

    storage cells need to be before the structure is abandoned and what methods can be

    used to clean them given that access is extremely limited. It seems likely that the

    tank cleaning process could produce large quantities of contaminated sea water

    which will have to be cleaned before returning the treated water to the sea.

    Rather that leave the legs protruding above the sea surface it has been suggested

    that the legs should be cut off underwater. International guidelines requires the cut to

    be made at least 55 metres below the sea surface. This option will require the

    development of underwater concrete cutting technology and will require a detailed

    engineering assessment to determine the viability of the idea.

  • 7/29/2019 Energy - Decommissioning 2002-4

    38/58

    36

    Some platforms will however be easier to remove than others and any that are

    brought inshore for demolition will require a suitable deepwater site and nearby

    drydock. Loch Kishorn is an obvious candidate for consideration in Scotland.

    8.3 Concrete Platform Market Development.

    This is a particularly difficult market to predict. The picture should become clearer in

    the next few months when TotalFinaElfs plans for the decommissioning of the three

    concrete platforms in the Frigg field are published. (Two of the three platforms are in

    the UK sector with the other being in the Norwegian sector).

    If as expected, the majority of the installations remain in place then the market

    development will be limited to cleaning and monitoring activities.

    Like the steel platform decommissioning market, we see no reason to believe that

    decommissioning of concrete installations will not be spread over a number of years

    to minimise peaks and troughs.

    8.4 Concrete Platform Market Opportunities.

    If some or all are brough t inshore for decommissioning then there will be a need to

    reopen a dry dock facility such as Kishorn and there will be a high number of jobs incomparison to the steel structure decommissioning activity. We estimate that it could

    take two to three years at an inshore location to demolish a concrete GBS whose

    weight may be as great as 350,000 tonnes.

    Assuming the majority of the concrete platforms remain in place then opportunities

    will exist for companies to provide the technology and the services to clean the

    storage cells before the structures are left to decay naturally which may take several

    hundred years. Given the difficulty in accessing the storage cells it is not clear what

    the best methods of cleaning will be but there is little doubt that this activity will be

    time consuming and expensive. Disposal of the waste hydrocarbons and cleaning

    fluids is also a potentially expensive operation.

    There will be a requirement for ongoing monitoring of the platforms if they are left in

    place.

  • 7/29/2019 Energy - Decommissioning 2002-4

    39/58

    37

    9.0 Subsea installations.

    9.1 General

    The market for the removal of subsea installation is relatively small in comparison to

    the overall market. The work will be undertaken almost exclusively by diving and

    ROV specialists.

    9.2 Technical Issues.

    We do not believe that there are any significant technology issues associated with

    the removal of subsea installations.

    9.3 Market Development.

    This is a relatively small market sector and we believe that the technology and

    capability is in place to undertake this work. Like the other markets, there will be

    timing flexibility and it therefore seems likely that these smaller projects will be used

    to smooth the utilisation of personnel and equipment between larger

    decommissioning projects.

    9.4 Market Opportunities

    We do not envisage any significant new market opportunities other than an eventual

    expansion of existing capabilities as the decommissioning of subsea activities

    increases.

  • 7/29/2019 Energy - Decommissioning 2002-4

    40/58

    38

    10.0 Drill cuttings.

    10.1 General

    Beneath many of the installations in the Central and Northern North Seas there are

    accumulations of rock cuttings deposited on the sea bed as a result of the drilling of

    wells. These cuttings are contaminated by oils used to make up the drilling fluids and

    are potentially toxic if disturbed. There is estimated to be over 1 million cubic metres

    of cuttings on the sea bed in the UK sector.

    The industry has initiated a wide ranging study along with other interested parties to

    determine the Best Environmental Practice and Best Available Techniques with

    respect to these cuttings piles. All reports completed to date are published on the

    UKOOA website (9).

    At this point in time it is not clear if the best solution will be to leave the cuttings in

    place or to remove them.

    With so much uncertainty, it is not feasible to give a reliable estimate of the value of

    this market but if the majority of the piles have to be removed from the UKCS then

    the cost is likely to be over a 1 billion and could be significantly greater.

    10.2 Technical Issues

    The basic issues are:

    From an environmental standpoint is it better to leave the cuttings undisturbed

    on the sea bed to naturally degrade over time or is the best overall solution to

    remove them?

    If the answer is to remove some or all of the cuttings what is the best

    technology to develop to undertake this task with minimum environmental

    impact?

    Are there alternative solutions to removal such as covering the cuttings or

    perhaps using biotechnology methods to accelerate natural degradation?

    If the cuttings are removed there will be considerable quantities of

    contaminated water brought to the surface. Tests to date have had a

    water/cuttings ratio as high as 10/1. How and where can this water be

    treated?

  • 7/29/2019 Energy - Decommissioning 2002-4

    41/58

    39

    If the cuttings are removed how are they to be disposed of? The ideal would

    be to identify an economic reuse for the material since the cuttings do not

    make good land fill material.

    All of the above issues are being studied in the UKOOA research and development

    project.

    10.3 Market Development

    Until the current research and development programme is complete it is not clear

    how this market will develop.

    It seems likely that there will be a need to remove some drill cuttings the minimum

    will be that required to get access to remove the platform structure and the maximum

    could be the removal of all drill cuttings.

    Waste regulations will tend to dictate that all UK sector cuttings return to the UK and

    all Norwegian cuttings return to Norway for disposal.

    The removal of cuttings will require the development of specialist equipment and

    processes. It seems likely that an integrated solution will be required combining the

    removal method, the water and cuttings handling process and the onshore disposal

    processes. If we assume that the removal requirement will be greater than the

    minimum then there will be a requirement for at least two companies offering

    competitive solutions.

    10.4 Market Opportunities

    This is a potentially large market in which there are no current players. There will be

    significant opportunities for innovative solutions and technology development. We

    believe the important areas to consider are:

    In-situ measuring and monitoring equipment.

    Development of leave-in-place solutions.

    Development of underwater suction pumps to remove the material from deep

    water.

    On-ship water treatment equipment.

  • 7/29/2019 Energy - Decommissioning 2002-4

    42/58

    40

    Onshore water receiving and treatment plants.

    Onshore cuttings cleaning.

    Re-use of cuttings material.

    Companies interested in this market should keep abreast of the UKOOA initiative andshould consider having solutions developed for the Ekofisk and Frigg

    decommissioning projects.

  • 7/29/2019 Energy - Decommissioning 2002-4

    43/58

    41

    11.0 Pipelines

    11.1 General

    According to DTI figures there are 10,430 km of offshore pipelines in the UK. Like

    drill cuttings the decommissioning requirements for pipelines are unclear. There are

    no international rules or guidelines available. The guidelines issued by the DTI

    indicate that decisions will be taken in the light of individual circumstances and with

    little pipeline decommissioning having been undertaken to date there are no

    precedents on which to base any predictions of the likely size and shape of the

    pipeline decommissioning market.

    The Norwegian Ministry of Oil and Energy has taken a lead in researching the

    possible options and has recently published the results of their studies (10).

    It would seem that the final outcome will include a number of solutions including

    leaving in place, trenching and burying or totally removing. It is impossible to predict

    at this stage the mix of solutions that will be applied and combined with the fact that

    there are no reliable cost estimates for each of these solutions it is not possible to

    give a reliable cost estimate for this market. Using the range of costs quoted in the

    Norwegian study and adjusting for the greater length of UK pipelines then a low

    estimate based on trenching only of 325 million is obtained with a high estimate of

    3.8 billion for complete removal. Allowing for a range of different solutions then a

    cost range of 1 billion to 3 billion could be considered reasonable given the current

    uncertainties.

    These costs will be totally dominated by the cost of specialist marine construction

    equipment.

    11.2 Technical Issues.

    Pipelines associated with offshore oil and gas production can either be buried, lie inopen trenches or simply lie on the sea bed.

    The key decommissioning issue is the cost and environmental effects of removing

    the pipelines versus the environmental effect of leaving them to decay in situ

    particularly the effect it may have on fishing activities. The larger diameter export

    pipelines have a heavy coating of concrete surrounding the pipe that makes them

  • 7/29/2019 Energy - Decommissioning 2002-4

    44/58

    42

    more difficult to remove and recycle compared to the smaller infield pipelines which

    have less heavy coatings and can often be removed from the sea bed by reeling up

    onto a ship.

    Leaving buried pipelines in place in areas where the sea bed is stable would

    arguably not pose significant problems for fishermen. However, some of the

    Southern North Sea areas are prone to the movement of sand waves which can

    alternately bury and uncover pipelines. There will be arguments that these pipelines

    should be removed.

    For pipelines lying on the sea bed, research suggests that trenching the line will be a

    significantly lower cost option compared to complete removal.

    For unburied lines it would be feasible to dump rocks over the lines to provide cover

    but there are strong objections to this solution from fishermen.

    The final solution may well be a mix of removal, trenching and covering but at this

    point in time no firm predictions can be made.

    If lines are to be left in place then clearly they will need to be flushed and cleaned.

    11.3 Market Development

    There is little doubt that there will be an ongoing market for the removal of small

    diameter lines and cables which are not buried. This market can be served by the

    existing capability in underwater services.

    There is also likely to be a requirement for trenching of pipelines since this appears

    to be one of the favoured decommissioning options. There is also likely to be a

    requirement for the total removal of pipelines in some areas where trenching or

    leaving on the sea bed are not acceptable in the long term. In either event, there will

    be a need for specialist marine equipment.

    11.4 Business Opportunities

    The near term market is likely to be limited to the removal of relatively small lines and

    cables which can be accommodated by the existing contracting market.

  • 7/29/2019 Energy - Decommissioning 2002-4

    45/58

    43

    Longer term opportunities need to await further research, dialogue between

    interested parties and regulator guidance. At the present time there are no

    indications of any early activity with respect to research or regulatory developments.

    However the market is potentially large.

  • 7/29/2019 Energy - Decommissioning 2002-4

    46/58

    44

    12.0 Well Plug and Abandon

    12.1 General.

    Interest in decommissioning has, to date generally been concerned with onshore

    disposal of structures which is in fact one of the smallest sectors in the market and

    little attention has been paid to well abandonment which is likely to account for

    almost a third of the cost of decommissioning a production platform.

    Well abandonment cost estimates are highly variable ranging from the cost of

    straightforward platform based wells, the cost of difficulties arising from corrosion of

    the well tubulars through to the costs associated with complex high temperature high

    pressure wells and to subsea wells. There are reportedly 2,400 wells to be plugged

    and abandoned in the UK sector and we estimate that the total cost of this activitycould be in the order of 1 billion to 1.5 billion.

    12.2 Technical Issues.

    This is a highly specialised activity which will typically be carried out by specialist

    contractors for both platform and subsea wells. It is likely that platform wells will be

    abandoned in a phased manner during the final years of production. In this way the

    associated overhead costs can be shared with other installation activities.

    With the cost of well abandonment being a major element of field decommissioning

    there is obviously an interest from oil companies in new technology to help reduce

    these costs. Techniques using coiled tubing are now being utilised and no doubt

    further research and development work will be needed to tackle the challenge of

    reducing costs whilst at the same time increasing reliability.

    A conference sponsored by Robert Gordon University in Aberdeen on 28th

    and 29th

    March 2001 is believed to be the first of its kind to focus on North Sea well plug andabandonment issues and is a sign that greater attention is now being paid to this

    important subject.

  • 7/29/2019 Energy - Decommissioning 2002-4

    47/58

    45

    12.3 Market Development

    In the Gulf of Mexico well plug and abandonment is generally undertaken by

    specialist contractors using techniques that do not require the use of a drilling rig. It

    seem likely that similar developments will occur in the North Sea although it remains

    to be seen whether rigless techniques will be suitable in all cases in the North Sea.

    In the UK there are already companies developing specialist equipment and

    expertise for the North Sea market. The size of the future market suggests that there

    will be further openings for specialist operators and equipment developers.

  • 7/29/2019 Energy - Decommissioning 2002-4

    48/58

    46

    13.0 Reuse of Offshore Installations

    13.1 General

    Much of international and national environmental legislation on waste is based on the

    waste hierarchy that says, in order of importance:

    1. Minimise the creation of waste.

    2. Reuse assets rather than create new.

    3. Recycle materials rather than use new resources.

    4. Dispose of the material in landfill or by incineration.

    Whilst close to 100% of the material in offshore platforms can be recycled it is clearly

    more desirable if the assets can be reused.

    There are two distinct aspects to the reuse of redundant offshore platforms. Namely

    reuse in whole or in part for hydrocarbon production or for reuse for non-oil and gas

    related purposes.

    1.2 Reuse for oil and gas production.

    In the Gulf of Mexico reuse of redundant platforms is a well established process. In

    the North Sea area, several oil companies have put considerable time and effort into

    trying to find a buyer for their installations but to date there has been no success. We

    believe the reasons for the lack of success are a combination of the following:

    Limited number of North Sea assets decommissioned to date.

    North Sea is a mature area that is almost exclusively using subsea and

    floating production technology to develop remaining reserves. Therefore there

    is not a market within the North Sea for old platforms.

    The ageing North Sea structures and their large size are not well suited to

    new developing areas in the world

    There is an attitude amongst designers that new is best.

    Whilst there will no doubt be reuse of the more versatile of the North Sea structures

    such as the Hutton TLP and the FPSO installations it is difficult to envisage a reuse

    market developing on the scale of the Gulf of Mexico.

  • 7/29/2019 Energy - Decommissioning 2002-4

    49/58

    47

    Nevertheless, there is a very significant financial prize on offer if a platform can be

    sold rather than scrapped and we therefore anticipate that efforts will continue to be

    made to sell installations.

    We are not aware of any studies having been undertaken to identify where potential

    reuse markets might lie. If they do exist, then we would expect them to be located in

    developing areas such as China, Far East, Eastern Europe, Asia and West Africa. A

    study of these markets could be considered to determine if there is scope for reuse of

    North Sea assets.

    An essential ingredient of being able to reuse installations is to be able to match

    sellers with potential buyers. A Dutch company, The Web Platform Brokers (11), has

    been set up to undertake this function with the aid of the world wide web.

    The sale of a complete platform including jacket and topsides to a new owner such

    that the facility is a close fit to the new requirements is unlikely. In particular the

    jacket structures will be difficult to reuse without the new water depth being very

    close to the original North Sea location. A more realistic reuse is to take the topsides

    of a North Sea installation and place it on a new support structure. It is even more

    realistic to envisage particular sections of a topsides structure such as the living

    quarters, drilling rig, power generation modules etc. being used in new locations.

    Ultimately there will be an overlap with the onshore disposal industry which will also

    be aiming to sell as much reusable equipment as possible.

    If markets can be identified and buyers matched with sellers then there could be a

    limited but profitable business in removing, modifying and reinstalling North Sea

    platforms.

    13.3 Reuse for non-oil and gas purposes.

    13.3.1 Reuse offshore

    It is important to regard a redundant platform as an asset rather than an industrial

    relic destined for the scrap heap. The challenge, therefore, is to identify the best use

    of these assets in position in the North Sea. It is a mistake to believe that structurally

    these installations are nearing the end of their life. Indeed the concrete structures are

    likely to survive for several hundred years without maintenance and the challenge of

  • 7/29/2019 Energy - Decommissioning 2002-4

    50/58

    48

    finding a new use for old concrete installations is particularly relevant since many of

    them are unlikely to be moved.

    There have been many reuse ideas put forward in the past such as prisons, hotels,

    casinos etc. most of which have no likelihood of being financially viable.

    There are however two generic areas which we believe merit further study to

    determine if there is any prospect of viability.

    Power Generation.

    There is an abundance of wind and wave power at the offshore platform locations.

    Whilst there may be limited space available to mount wind turbines we feel there may

    be opportunities to harness considerable quantities of wave power. One of the

    serious proposals considered by Shell for the reuse of Brent Spar was the use of

    Spar as a hub for an array of wave power generation buoys using a novel technology

    being developed by Ocean Power Technologies Inc in the United States. The

    proposal was to generate 15 MW of power using Spar. A large offshore platform

    would clearly be capable of generating a much greater output.

    If the legs of the concrete platforms are opened to the sea then it may be viable to

    generate power from the resultant oscillating air column in the legs using the same

    principles as being put into practice by Wavegen (12).

    Lastly, an idea brought to our attention by a Norwegian environmental pressure

    group, Bellona, is to use offshore platforms to generate large power outputs from gas

    turbines but rather than discharge the exhaust gases to the atmosphere the gases

    would be injected into underground reservoirs. In this way large amounts of fossil fuel

    power could be generated without atmospheric emissions.

    Question marks have been raised regarding the economics of laying power cables

    from offshore to land but it is interesting to note that BP are planning to lay cables

    from land to some of their offshore installations so that power can be supplied from

    onshore stations. These same cables could presumably be used in the opposite

    direction.

  • 7/29/2019 Energy - Decommissioning 2002-4

    51/58

    49

    An alternative suggestion to exporting electricity from an offshore installation is to use

    the offshore power for the electrolysis of seawater to produce hydrogen the fuel for

    cars of the future.

    The viability of the above and similar ideas is clearly highly questionable but we

    believe that there is sufficient merit to justify a serious investigation to determine if

    the ideas should be discarded or developed.

    Aquaculture.

    We have been advised by fish farming specialists that there is a desire in the fish

    farming industry to move away from inshore areas to more exposed offshore

    locations. This would open up new disease free areas and opportunities to raise

    different species.

    Suggestions put forward are to have fish cages that can be lowered below the wave

    zone for much or the year but raised during the summer period for harvesting.

    Other ideas have suggested using platforms as nursery areas for development of

    young fish which would eventually be released to the wild.

    We are not competent to judge the merits of these ideas but given the current

    pressure on fish stocks there is an argument for looking more closely at these ideas.

    It is conceivable that both power generation and aquaculture could occur at the same

    location.

  • 7/29/2019 Energy - Decommissioning 2002-4

    52/58

    50

    Internet References.

    1. http://www.phillips66.com/maureen/default.htm

    2. http://phillips.netpower.no/3. http://www.totalfinaelf.no

    4. http://www.shell.com/uk-en/directory/0,4010,25268,00.html5. http://www.ospar.org6. http://www.excalibur-engineering.com

    7. http://www.msoinc.com8. http://www.pilottaskforce.co.uk

    9. http://www.ukooa.co.uk10. http://odin.dep.no/oed/norsk/html/rapporter/14/#_Toc47586188711. http://www.web-platform-brokers.com

    12. http://www.wa