_Decommissioning in the North Sea - Demand vs Capacity_low-res

Embed Size (px)

Citation preview

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    1/100

    Decommissioning inthe North SeaReview of Decommissioning Capacity

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    2/100

    2

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    Boskalis

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    3/100

    3

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    Contents

    Executive Summary 4

    1 Introduction 7

    1.1 Background and Context 8

    1.2 Drivers and Influencers 9

    1.3 The North Sea in Numbers 101.4 Decommissioning Approaches 14

    2 Analysis of Supply Chain Approach 17

    2.1 Analysis Approach 18

    2.2 Resource Breakdown Structure 19

    2.3 Programme 18

    3 Market Forecasts 23

    3.1 Market Forecasts of Expenditure 24

    3.2 Market Forecasts of Activity 30

    4 Critical Supply Chain Elements 39

    5 Well Abandonment 45

    5.1 Overview 47

    5.2 Activity 48

    5.3 Supply Chain 50

    5.4 Health Check 52

    6 Topside and Substructure Removal 55

    7.1 Overview 57

    7.2 Activity 58

    7.3 Supply Chain 60

    7.4 Health Check 63

    7 Topsides and Substructure 65

    Recycling

    7.1 Overview 67

    7.2 Activity 68

    7.3 Supply Chain 70

    7.4 Analysis 74

    8 People 77

    9 Context and Considerations 81

    Appendix A:References 87

    Appendix B:Criteria Scoring 91

    Appendix C:Resources 95

    Contents

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    4/100

    4

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    The O&G Decommissioning sector offers a significantsocio-economic opportunity in terms of job creationin the Scottish, UK and European supply chains,and an opportunity for North Sea based firms toexport expertise to other parts of the world. Thisreport, prepared by Arup and commissioned byDecom North Sea (DNS) and Scottish Enterprise,

    seeks to provide an overview of the scale andnature of the decommissioning market in the nextdecade highlighting areas where there are potentialbottlenecks in the supply chain.

    There is a need to continue to develop the existingO&G and decommissioning supply chain tomeet future increases in demand associated withDecommissioning in the North Sea. This offersa significant opportunity to the supply chain in agrowth market, and will require a range of highlyskilled and high value capability. A range of activitieswill require innovation in terms of technical andmanagement approaches to drive down the costs

    of decommissioning. There are other areas thatwill need significant growth in capacity to meet thedemands of the market.

    Executive Summary

    The analysis focuses on critical supply chainelements which are resources that are fundamentalto delivering decommissioning projects, andwhich would have the most significant effect onthe deliverability of the these projects if there werecapacity constraints. The critical supply chainelements that have been identified are:

    rigs/rigless abandonment infrastructure,

    removal vessels for topsides and substructure,

    ports/harbours/yards for recycling and

    skilled engineering and operational resourcesserving all aspects of the sector.

    These are the areas where the supply chain,operators and Government will need to work closelyto ensure that the opportunities are realised. Forother resources the supply chain is more likely tobe able to naturally respond without major external

    intervention.A capacity health check for the critical supply chainelements considers available capacity and investmentlead time, investment commitment, pressures/synergies from other industries and capability. Thestudy drew from the experience and expertise of anumber of significant firms currently operating withinthe North Sea decommissioning market. Therewas broad consensus amongst this group that theindustry needed to evolve to efficiently deliver theactivity needed over the next 40 years.

    Executive Summary

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    5/100

    5

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    A Changing Mind Set

    The approaches and philosophy of the Exploration& Production (E&P) market are currently largelyimplemented in the decision making processes ofthe decommissioning market. There is a need for themarket to evolve an approach to decommissioningthat is distinct from that of exploration and production

    activity. Recognition of the different drivers andsuccess criteria of E&P versus decommissioningshould enable the market to evolve an approach that

    is optimised for their respective projects.

    Smoothing the Peaks

    Creating accurate estimates of decommissioningexpenditure across the North Sea is challenging.Estimates have been produced in isolation by arange of organisations from the bottom up. Theseshow a broad range in expenditure on a year byyear basis and over the next decade. Operators

    are likely to have significantly more flexibility tomanage procurement and programme decisions fordecommissioning activities than in E&P, where a raceto production is imperative. Consequently, the marketis unlikely to procure services in the peaks suggestedby the predicted estimates as the cost to procureresources would increase i.e. the market will smoothout the peaks.

    Contracting and Procurement Strategy

    Rigidity in contracting and procurement structuresdeveloped to support the E&P market can inhibitoperators and the supply chain from adapting tomeet the demands of the decommissioning market.

    Adapting existing procurement strategies to reducerequirements for proof of previous experience will

    allow new entrants to the market who may introduceinnovative methods.

    Driving Innovation, Driving Down Costs and

    Regulation

    Innovation can play a role in deliveringdecommissioning in a more cost effective manner.

    The nascent market has limited experience focusingon decommissioning activities and is at a stagewhere it can incorporate lessons learnt along withdeveloping new approaches to reduce costs.

    The uncertainty in the timescales of the market

    opportunity is limiting commitment to drive and investin innovation. The supply chain cites the stop/startnature of the industry as a barrier to investment.

    Executive Summary

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    6/100

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    6

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    7/100

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    7

    1.0 Introduction

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    8/100

    8

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    The Cost

    Projected North Sea decommissioning activityestimates vary, with the most conservative estimatespredicting the market will require over 30bn ofexpenditure before 2040 in the UK Continental Shelf(UKCS) alone[1]. As ageing assets reach the end oftheir economically useful life it is expected that the

    next 5 to 10 years will see a significant increase inactivity, increasing up to an estimated annual spend

    in excess of 2.5bn per annum [1],[2],[3].

    The Opportunity

    The Decommissioning Sector offers a significantsocio-economic opportunity in terms of job creationin the Scottish, UK and European supply chains,and a foundation from which North Sea based firmscan export expertise to other parts of the world. Totake full advantage of this opportunity, the industrymust build on its existing capacity and capability

    to service the complex and demanding nature ofdecommissioning work in the North Sea.

    The Objectives

    This report, prepared by Arup and commissioned byDNS and Scottish Enterprise, seeks to provide aneasily understandable and concise overview of thescale and nature of the decommissioning market. Inparticular, highlighting areas where there are potentialbottlenecks in the supply chain which might impactdecommissioning activity levels.

    1.1 Background and Context

    The Scope

    North Sea O&G resources are extracted fromthe North Sea and proximate areas including theNorwegian Sea and Atlantic Ocean. This area iscollectively known as the North Sea within the O&Gindustry. Four countries have O&G resources rightswhich they exploit in the North Sea. These are

    the United Kingdom, Norway, Denmark, and theNetherlands, and it is this area that is the focus of thisstudy.

    The Contributors

    This report uses a number of existing sources ofinformation to assess the likely scale of demand fordecommissioning services. It then draws on Arupsknowledge of the Sector, along with the expertviews of a range of industry leaders in the field, toidentify and assess critical areas of capability andcapacity. Particular thanks go to the following for their

    invaluable insight and contributions:

    Aker Solutions

    CNR International

    Halliburton

    Marathon Oil

    Royal Boskalis Westminster N.V.

    Seaway Heavy-lifting

    Weatherford International

    Wood Group

    Introduction| Background and Context

    Note:All references can be found in Appendix A

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    9/100

    9

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    1.2 Drivers and Influencers

    The market drivers are complex and there are manytechnical, commercial and regulatory influenceswhich will affect the manner in which the market fordecommissioning activity is realised. Understandingthe opportunities and challenges presented byNorth Sea O&G decommissioning is best informedby reviewing the market as part of a much more

    extensive whole, including E&P and other competingindustries.

    Regulation

    A range of international and national legislationsimpact the North Sea Decommissioning Sector.Of these, OSPAR is particularly significant in termsof influencing decommissioning approach.

    OSPAR Decision 98/3 prohibits leaving offshoreinstallations wholly or partly in place unless furtherderogation are granted. However, it providescertain derogations to concrete structures and the

    footing of large steel jackets weighing more than10,000 tonnes, from the fundamental principlethat decommissioning should result in full removalof the installation. Derogation is not automaticallyavailable and is subject to a detailed assessmentand consultation procedure to determine if there aresignificant reasons to allow the installation (or partthereof) to remain in situ. Furthermore, no derogationis available to steel installations constructed after 9February 1999 (being the date that Decision 98/3came into force).

    As a result of the OSPAR ruling, the North Sea willlead global decommissioning practice from a totalremoval perspective.

    The Other Industries

    Decommissioning offshore installations is onecomponent of offshore industrial activities occurringin the North Sea. These include E&P, offshore wind,marine renewables, power and communicationsnetworks, and port and harbour developments.

    Understanding the opportunities and challengespresented by North Sea O&G decommissioningtherefore needs to be considered in the context of

    these wider activities.

    This broader appreciation will provide a greaterunderstanding of where it competes for resourceswith other offshore activities, and where possiblesynergies exist, notably in the area of transferableskills.

    The Global Industry

    In terms of expenditure, the North Sea representsan important but modest part of an extensive globalO&G industry, including onshore and offshore activityacross upstream, midstream and downstreamSectors.

    The resources supporting the North Sea market tendto be highly mobile and operate in a global, ratherthan local market. The cycles of the global activitywill influence the availability of certain North Searesources.

    Asset Life Cycle

    Decommissioning is the final chapter of a wholeasset lifecycle, which often stretches back manyyears to initial fabrication and installation, throughmaintenance, refurbishment and production,then into the late life asset management cycle,including cessation of production and ultimatelydecommissioning. The design and managementof the asset through its long life cycle will influencethe approach to decommissioning and providesimportant context for the market.

    Interdependent Systems

    Individual offshore O&G assets, be they platforms,pipelines, wells or utilities, often interact with andare interdependent upon one another to a greateror lesser degree. While these can introduceadditional complexities to the decommissioningprocess, they can offer opportunities to increasethe decommissioning process efficiency throughintegrated management of systems and processes.

    Introduction| Drivers and Influencers

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    10/100

    10

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    One of the main challenges in determining the supplychain requirements stems from the heterogeneity ofthe types and designs of structures present in theNorth Sea. This renders a consolidated approachto removal difficult, if not impossible. Indeed, NorthSea infrastructure varies across geographies dueto a range of factors including the nature of the

    resources being exploited, the geological conditions,water depth, the technology available and metoceanconditions.

    The Installations

    There are more than 1500 registered installations inthe North Sea including small fixed steel installationsof less than 100 tonnes, large heavy concrete gravitybase or fixed steel installations weighing up to 0.5million tonnes, floating steel, concrete installationsand subsea steel infrastructure[4].

    Excluding subsea steel, there are 715 installations

    in the North Sea: the vast majority of theseinstallations are fixed steel (83%) and locatedin the UKCS (53%)[4].

    The Age

    The North Sea has an ageing asset base, withthe first field having commenced production in1967. The peak ten year period was from 1984to 1993 when an average of 20 installations werecommissioned each year. The yearly peak occurredin 1993, with 38 commissions[4]. The average overthe last ten years has been just over 7.5 a year with

    a peak of 13 a year[4]

    .

    The average age of North Sea installation is 25years. The UKCS has the oldest average asset base,whilst Denmark owns the youngest assets. There arecurrently 245 assets over 30 years old across theNorth Sea[4].

    1.3 The North Sea in Numbers

    Denmark Netherlands Norway UK

    Installations in the North Sea

    Number

    ofInstallations

    300

    200

    100

    0

    400

    150

    50

    250

    350

    450

    Country

    Fixed Steel Floating SteelFloating Concrete

    Concrete Gravity Based Others Source: OSPAR[4]

    Others 3%

    Concrete Gravity Based 4%

    Floating Steel 11%

    Floating Concrete >1%

    Fixed Steel 82%

    North Sea Installation Types(excluding subsea steel)

    Source: OSPAR[4]

    Denmark Netherlands Norway UK

    Average age of North Sea Installations

    AverageAge 25

    23

    21

    19

    27

    22

    20

    24

    26

    28

    Country

    22

    24 24

    26

    Source: OSPAR[4]

    Introduction| The North Sea in Numbers

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    11/100

    11

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    Decommissioning

    Only 12% (88) of NorthSea installations have beendecommissioned to date,reflecting the nascent nature ofthe decommissioning market[4].

    This includes 55 fixed steelinstallations, 22 floating steel,3 concrete gravity base and 7others.

    Of the 88 installations that have

    been decommissioned, onlyseven have had derogationsgranted to allow infrastructureto remain in place. These havebeen associated with installationsin NW Hutton, Frigg andEkofisk. These were all concretegravity base infrastructure withsubstructures over 200,000tonnes. The only exceptionNW Hutton was a fixed steelinstallation where the jacket andtopside were removed and thefootings of the jacket were left insitu.

    Installations by Age. Source: OPSAR [4]

    Introduction| The North Sea in Numbers

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    12/100

    12

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    The Geographies

    UKCS Southern North Sea, Danish and Dutch Sectors aregenerally characterised by comparatively shallow water (lessthan 60 meters), relatively moderate metocean conditions,and exploit gas resources. They have comparatively lightinstallations[4].

    The Norwegian Sector and UKCS Central and northernNorth Sea have deeper water and more exposed metoceanconditions. The platforms are larger and heavier[4].

    The Norwegian Sector has proportionally larger installationsin tonnage terms compared to other countries. This is

    because the majority are large deep water installations.Norway has a larger percentage of heavy concrete gravitybase infrastructure when compared to the UKCS.

    The UKCS area contains a mix of platform sizes with lighterinstallations predominately in the southern area and heavierinstallations moving north.

    Despite having a similar number of installations to theNorwegian Sector, the Dutch Sector only has a smallproportion of the total installation tonnage, as the majorityare small installations.

    Fixed and Floating Steel Infrastructure Weightin the North Sea

    Topside3,068,000 tonnes

    Substructure1,687,000 tonnes

    UNITED KINGDOM

    Topside985,000 tonnes

    Substructure675,000 tonnes

    NORWAY

    Topside

    215,000 tonnes

    Substructure127,000 tonnes

    NETHERLANDS

    Topside155,000 tonnes

    Substructure

    87,000 tonnes

    DENMARK

    Fixed Steel FloatingConcrete

    FloatingSteel

    ConcreteGravity Based

    Others Subsea Steel

    Infrastructure Weight in the North Sea

    TotalWeight(Te)Millions

    6

    4

    2

    0

    Topside Substructure

    8

    10

    3

    1

    5

    7

    9

    Source: OPSAR[4]

    Introduction| The North Sea in Numbers

    Source: OPSAR[4]

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    13/100

    13

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    Topside Weight of Installations greater than 30 years old. Source: OSPAR[4]

    Introduction| The North Sea in Numbers

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    14/100

    14

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    The manner in which assets can be decommissioned is subject to a Comparative Assessment. This assessmentis used to make recommendations to the regulatory authority. It considers the technical feasibility, environmentaland social impact, economic and health & safety implications of all viable decommissioning approaches indetermining the optimal approach. The decommissioning approaches associated with the main infrastructureelements are influenced by the original installation design, and the strategy implemented by the operator.

    1.4 Decommissioning Approaches

    Well Abandonment

    Running, Make Safe & Preperation

    Subsea & Site Remediation

    Topsides & Substructure Recycling

    Operator Project Management & Monitoring

    Topside & Substructure Removal

    Topsides

    Several methods are used for removing installations. The main classifications include:

    Piece Small- the installation is dismantled offshore by cutting or dismantling into small sections that areshipped onshore in containers.

    Heavy-lift- whole modules are removed in the reverse of the installation sequence and loaded on to flat-topbarges or a crane vessel for transport to the decommissioning yard.

    Reverse Float Over- the topside is removed in an approach that is a reversal of a float over installationprocess. Here, the whole topside is cut from the jacket and taken ashore in one piece, with the installationpartly floating during transport.

    Single Lift- the topsides and/or jacket are removed in one piece and transported to the decommissioning

    yard.

    Introduction| Decommissioning Approaches

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    15/100

    15

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    Substructures

    The main classification of substructures includes:

    Steel Installations

    Floating Installations (concrete or steel)

    Concrete Gravity Bases

    The majority of substructures will require total removal.For platforms with the option to apply for a derogation,they can be partially removed or left in place ifapproved.

    The main classifications include: Heavy-lift [as explained in the section above]

    Reverse Installation [as explained in the sectionabove]

    Single Lift [as explained in the section above]

    Buoyancy where buoyancy tanks are installed onthe jacket legs to force the platform to the surface

    Wells

    Plugging & Abandonment (P&A) is the process bywhich a well is closed permanently, usually after

    either logs determine there is insufficient hydrocarbonpotential to develop the well, or after production hasceased. Abandonment must be done in a way thatprotects the downhole and surface environment inperpetuity.

    All wells must be plugged and abandoned accordingto regulations once no longer in use and theirconnecting platform is being decommissioned. P&Ainvolves plugging off the well generally with cementplugs and salvaging all recoverable equipment. Thestandards applied in terms of expected integrity varybetween jurisdictions. The North Sea has some ofthe worlds most stringent regulations. In this region,

    responsibilities for well integrity are enduring and anyfuture failure must be remedied by the operators.

    There is a diversity of well infrastructure in the NorthSea which is determined by a variety of technicalfactors associated with the well including type,location, status and geology. Wells are associated witha range of E&P life cycle activities including exploration(identifying resource), appraisal (determiningcommercial viability) and development (extractingresource). Wells ready to be P&A may have beensuspended through installation of a temporary cap.

    Alternatively, they may be associated with a depleted

    reservoir.

    In order to determine the manner by which a wellcan be abandoned, data is collected from the wellto determine its current condition. Depending on theage and history of the well and the quality of records,it can be challenging to accurately determine the wellstate. This creates risk in selecting the appropriateabandonment approach. An approach which canonly be operated in good conditions may reducecosts if conditions turn out to be favourable butlead to significant additional costs if conditions areunfavourable.

    PipelinesOSPAR have not made any recommendation forpipelines, and therefore there is no obligation toremove them. Agreement must be obtained fromthe regulating authority on the appropriate approachthrough consideration in a comparative assessment.Key issues to be considered are pipeline cleanliness,stability, extent of burial and impact on other users ofthe sea.

    There are diverging precedents in the North Sea.Indeed, some pipelines have been decommissionedin situ, while others have been removed to shore.

    Generally, the smaller pipelines which can be moreeasily removed without significantly disturbing theseabed are recovered. O&GUK have producedguidelines on the decommissioning of pipelines.

    Introduction| Decommissioning Approaches

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    16/100

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    16

    Boskalis

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    17/100

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    17

    2.0 Analysis of Supply Chain Approach

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    18/100

    18

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    2.1 Analysis Approach

    The approach to the analysis of the decommissioningsupply chain taken in this report is explained below.

    Market Forecasts of Expenditure Trends

    A review of existing industry estimates of overallanticipated decommissioning expenditure wasundertaken to understand the likely range of activity

    over the next 5 to 10 years in the North Sea.This information is found in Chapter 3.

    Critical Supply Chain Elements

    This involved identifying the critical supply chainelements on which the detailed assessmentwas undertaken. Critical supply chain elementsare resources that are fundamental to deliveringdecommissioning projects, and which would havethe most significant effect on the deliverability of thedecommissioning projects if there were capacityconstraints. It is on these elements that a detailed

    activity analysis was undertaken. This information isfound in Chapter 4.

    Market Forecasts of Activity Trends

    These estimated the level of activity expected foreach of the critical supply chain elements whichwas informed by the overall expenditure trends. Thisinformation is found in Chapter 3.

    Supply Chain Capacity Review

    This consisted of a detailed review of the capacity ofthe existing supply chain for the critical supply chainactivities. This information is found in Chapters 5 to 8.

    Capacity Health Check

    A capacity health check analysis was essential todetermine the critical supply chain elements. Theanalysis considered the following parameters:

    Available Capacity & Investment Lead Time - theexisting capacity of skills and resources against

    expected activity and the duration it takes tobuild any capacity shortfall.

    Investment Commitment - the progress andcommitment made by the supply chain to buildnew capacity to meet any shortfalls.

    Pressures/Synergies from other industries - theopportunity or threat of analogous industries.

    This can result from competition from resources/skills, or supporting the investment case to buildcapacity.

    Capability - the competence of the industry to

    support the decommissioning market.It is distinct from capacity as it does not relateto the volume of capable resources to meetthe predicted demand. The classification ofcapability is derived from the assessmentcommissioned by DNS and Scottish Enterprise[5].In this report, the industry and supply chain wasconsulted on their perceived capability to providedecommissioning services as per the Oil & GasUK (O&GUK) Work Breakdown Structure (WBS).

    Each critical supply chain element is attributed ascore of Low to High (Low, Low/Medium, Medium,Medium/High, High) for each parameter. The scoring

    is based on subjective criteria which are detailed inAppendix B. The capacity health check is found inChapters 5 to 8.

    Analysis of Supply Chain Approach| Analysis Approach

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    19/100

    19

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    A common language in decommissioning has been developed by O&GUK through the production of their WBS.Activities associated with the decommissioning programme have been characterised in 11 categories which aredefined.

    This report uses an aggregated version of the O&GUK WBS which focuses on the resource requirements. SomeO&GUK categories have been combined where there is commonality in the resources that support the activities.

    This categorisation has been termed in this report as the Resource Breakdown Structure (RBS) to differentiate itfrom the O&GUK WBS.

    The relationship between the 2013 O&GUK WBS and the RBS can be seen in the figure below.

    2.2 Resource Breakdown Structure

    Well Abandonment

    Facilities / PipelinesMaking Safe

    Topsides Preparation

    Topsides Removal

    Substructure Removal

    Subsea Infrastructure

    Site Remediation

    Topsides andSubstructure Recycling

    Monitoring

    Fac

    ilityR

    unn

    ing

    /Owners

    Cos

    ts(Pre

    NU/NUI)

    O

    pera

    tor

    Pro

    jec

    tManagemen

    t

    Operator ProjectManagement &

    Monitoring

    Well

    Abandonment

    Running, MakingSafe & Preparation

    Topside &Substructure

    Removal

    Subsea & SiteRemediation

    Topsides &Substructure Reuse

    & Recycling

    ArupResource Breakdown Structure

    2013 O&G UK WBS

    The resources associated with each element of the RBS aredetailed in Appendix C.

    Work Breakdown Structure

    Analysis of Supply Chain Approach| Resource Breakdown Structure

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    20/100

    20

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    21/100

    21

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    The decommissioning programme commences with the management of the asset during late life, and lasts al l theway to the monitoring of the seabed once the asset has been decommissioned. The diagram below shows theRBS activities in a programme format.

    The programme duration depends on the technical complexity of the project as well as a range of commercialconsiderations. A typical project is often carried out in parts with several periods of inactivity, rather than acontinuous activity flow and so individual project programmes can vary significantly.

    2.3 Programme

    Late Life Operations andAsset management

    Subsea Infrastructure

    Topsides & SubstructureReuse or Recycling

    Facilities Running, Owners Costs

    Well Abandonment

    Facilities, PipelinesMaking Safe

    TopsidePreparation

    TopsideRemoval

    SubstructureRemoval

    Site Remediation

    Monitoring

    HydrocarbonFree

    CoP

    Analysis of Supply Chain Approach| Programme

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    22/100

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    22

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    23/100

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    23

    3.0 Market Forecasts

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    24/100

    24

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    Available market forecasts indicate that theoverall decommissioning expenditure in theNorth Sea could be between 1.1bn and2.6bn per annum, and is estimated toreach over 17bn for the period between2014 to 2022[1], [3].

    The UKCS is likely to be the largest sector

    of the North Sea decommissioning market,although Norway is expected to contributea significant proportion of activity as the endof the decade approaches. Denmark and theNetherlands are likely to contribute a muchsmaller proportion of activity.

    3.1 Market Forecasts of Expenditure

    20222014 2015 2016 2017 2018 2019 2020 2021

    Annual Estimated North SeaDecommissioning Expenditure

    EstimatedExpenditure(M)

    1,500

    1,000

    500

    0

    OGUK Insight 2013 ReportUK

    Mackay 2013Norway

    Mackay 2013Denmark & Netherlands

    2,000

    2,500

    3,000

    Source: Oil & Gas UK[1], Mackay Consultants[3]

    Market Forecasts| Market Forecasts of Expenditure

    20222014 2015 2016 2017 2018 2019 2020 2021

    Annual Estimated North SeaDecommissioning Expenditure

    Estim

    atedExpenditure(M)

    1,200

    800

    400

    0

    1,600

    2,000

    600

    200

    1,000

    1,400

    1,800

    Source: Oil & Gas UK[1], Mackay Consultants[3]

    OGUK Insight 2013 ReportUK

    Mackay 2013Norway

    Mackay 2013Denmark & Netherlands

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    25/100

    25

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    Predicting Decommissioning Activity

    Accurate estimation of decommissioning expenditureis challenging. Forecasts have been produced by anumber of organisations to estimate the profile ofdecommissioning expenditure in the North Sea overthe next decade. These estimates are substantiallydiverse both in the short and long term.

    The estimates are underpinned by assumptionsof the costs of decommissioning activities and theprogramme in which activities are delivered. There isinherent uncertainty in both areas:

    The timing of decommissioning activities isinformed by an economic analysis whichconsiders the revenue generated from the assetin terms of productivity and market value of theresource, the costs to operate and maintainthe infrastructure and the capital costs ofdecommissioning. Current trends have seenO&G prices increase, while technology innovationhas allowed for improved extraction, increasingthe life span of ageing infrastructure

    The costs of decommissioning generally havenot to date been reliably predicted, due to the

    nascent stage of the industry. The evolvingmarket has significant potential to reduce coststhrough applying innovative approaches thatreduce costs and simplify operations.

    Data from the Norwegian, Danish, and Dutch Sectorsare significantly less detailed and less robust thandata from the UKCS. Although these Sectors havefewer installations than the UKCS, they cumulativelyrepresent almost half of the O&G infrastructure in theNorth Sea.

    Profile of Market Activity

    There are further limitations in decommissioningestimates which are built from a bottom-up analysisbased on individual operators independentlydeclaring their expected decommissioning schedule.

    These estimates suggest that activity will ramp up inthe next decade with a number of peaks and troughsin activity.

    However, the market is inherently different to that ofE&P activities. In E&P programmes, delays directlyimpact the timing of subsequent revenue flows

    and programme drivers are highly significant inprocurement decisions, resulting in an industry thathas a peaking profile.

    For decommissioning, programme delays defercapital expenditure and often have a relatively lesssignificant detrimental impact on project economics.

    As a result, operators are likely to have higherflexibility to manage procurement and programmedecisions, and are unlikely to procure in peak periodsso there will be a flattening of the peaks and troughswith the decommissioning market flexing.

    Market Forecasts| Market Forecasts of Expenditure

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    26/100

    26

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    Interaction with the Wider Supply Chain

    The vast majority of resources utilised by the decommissioning market are not wholly specialised to thoseactivities. A number of critical supply chain elements support other offshore industries such as E&P, offshore wind,subsea cabling, and marine renewables. The mobility of resources means that the impact potential of local andglobal activities on decommissioning supply should be considered. Indeed, decommissioning spend over the nextdecade is expected to be a small proportion of overall O&G market, both in the North Sea and globally. Thereforeexpenditure in this area is likely to be a key influencing factor in the delivery of North Sea decommissioning.

    Forecast Annual UKCS DecommissioningExpenditure

    EstimatedExpenditur

    e(M)

    1,500

    1,000

    500

    020222014 2015 2016 2017 2018 2019 2020 2021

    OGUK Insight 2013 Report

    Oil and Gas UK Activity Report 2014

    Kemp 2014

    Mackay 2013

    2,000

    2,500

    Forecasts of Expenditure in the UKCS

    O&GUK undertake a comprehensive surveyof estimated spend and activity in the UKCS.Their members estimate that 10.4bn ofexpenditure will be incurred by 2022[1]. This isapproximately 30% of the decommissioningcosts in the UKCS estimated to 2040[1]. Thisspend is associated with the decommissioningof 2,300km of pipelines, over 130 installationsand 800 wells[1].

    However, there is significant uncertainty withregards to the spend that will actually beincurred, due to confidence in the estimatesof both costs and timing of individual

    programmes. Comparison of O&GUKanalysis with other trend analysis showsa significant range in both the annual andaverage forecasts. The largest annual varianceis over 1.2bn and average range is over0.5bn[1],[2],[3],[6].

    Forecast Annual Average UKCS Expenditure(2014 - 2022)

    EstimatedExpenditure(M)

    1,200

    800

    400

    0

    OGUK Insight 2013 Report

    Oil and Gas UK Activity Report 2014

    Kemp 2014

    Mackay 2013

    1,600

    2,000

    600

    200

    1,000

    1,400

    1,800

    Overall Average

    Annual Average

    Source: Oil & Gas UK[1][6],Prof. Kemp[2]Mackay Consultants[3]

    Source: Oil & Gas UK[1][6], Prof. Kemp[2]Mackay Consultants[3]

    Market Forecasts | Market Forecasts of Expenditure

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    27/100

    27

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    Running, Making Safe& Preparation

    Expenditure in each of the six RBScategories is biased toward Well

    Abandonment which accounts for 46%of the average spend over the period.

    Two categories; Running, Making Safe& Preparation as well as Topside &Substructure Removal, account for afurther 40% of spend, with the remainingcategories accounting for only 14%[1].

    Within each of the RBS categories, trendsof spend proportion vary over time as theoverall projects profiles change from a

    bias to early stage activities (such as WellAbandonment), to later activities (such asmonitoring)[1].

    Estimated Annual UKCS Expenditure

    Operator ProjectManagement & Monitoring

    PercentageofTotalExpenditure

    70%

    60%

    50%

    40%

    30%

    20%

    0%20222014 2015

    Well Abandonment

    2016 2017 2018 2019 2020 2021

    10%

    Topside & Substructure Removal

    Topside & Substructure Reuse & Recycling

    80%

    90%

    100%

    EstimatedExpenditure(M)

    1,000

    800

    600

    400

    200

    0

    1,200

    1,400

    1,600

    Total Expenditure

    Resource Breakdown Structure AverageUKCS Expenditure (2014 - 2022)

    46%

    1%

    18%

    22%

    8%5%

    Well Abandonment

    Topside &Substructure Removal

    Running, Making Safe& Preparation

    Subsea & Site Remediation

    Topside & Substructure Reuse & Recycling

    Operator Project Management & Monitoring

    Source: Adapted from Oil & Gas UK[1]

    Source: Adapted from Oil & Gas UK[1]

    Market Forecasts| Market Forecasts of Expenditure

    Subsea & Site Remediation

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    28/100

    28

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    The data shows that the overall trends in peaksand troughs is not applicable to all RBS elements.

    Topside & Substructure Recycling and OperatorProject Management & Monitoring are relativelyconsistent through the period. Whereas Well

    Abandonment shows a sharp decline to 50%of its peak to 2022. Topside & SubstructureRemoval grows to a peak near the latter endof the programme. This shows that the overalltrends relating to growth and decline will not beconsistent across all elements of the RBS[1].

    Forecast of Expenditure in Norway

    Norway has 19% of the North Sea installations,and approximately a third of the number in theUKCS[4]. There is a paucity of data regarding

    the likely decommissioning expenditure for theNorwegian Continental Shelf (NCS) as comparedto the UKCS.

    The Norwegian Climate and Pollution Agency(NCPA) estimates the costs of decommissioningthe entirety of the current infrastructure in theNCS to approximate 160bn NOK (16bn)[7].

    This represents about half of the UKs estimatesto 2040. While the Norwegian Oil and Gas

    Association (NOGA) has predicted conservativeestimates up to 2018, analysis undertaken byMackay suggests a total spend of 7.3bn up to2022, which represents over 55% of the total

    NCS estimated spend[8],[3].

    This is a more front loaded profile than for theUKCS, which expects only 30% of costs incurredto 2022. The assets based in the UK are onaverage older than in the Norwegian Sector,which suggest significantly different assumptionsof asset life have been made in the two Sectors.

    2022

    Estimated Annual Norwegian Continental ShelfDecommissioning Expenditure

    NOGA

    EstimatedExpe

    nditure(M)

    1,200

    1,000

    800600

    400

    200

    02013 2014 2015 2016 2017 2018 2019 2020 2021

    Mackay 2013

    Source: Adapted from Oil & Gas UK[1]

    Source: Mackay Consultants[3], NCPA[8]

    Market Forecasts| Market Forecasts of Expenditure

    Estimated Annual UK Continental ShelfDecommissioning Expenditure

    EstimatedExpenditure(M)

    700

    600

    500

    400

    300

    200

    020222014 2015 2016 2017 2018 2019 2020 2021

    100

    Running, Making Safe& Preparation

    Operator ProjectManagement & Monitoring

    Well Abandonment

    Topside & Substructure Removal

    Topside & Substructure Reuse & RecyclingSubsea & Site Remediation

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    29/100

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    30/100

    30

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    Market expenditure provides an understandingof the likely levels of overall activities predictedin the North Sea. However, to understand therequirements of the supply chain it is necessary tounderstand the characteristics of the infrastructurethat is planned for removal in more detail.

    There is limited publically available information

    on individual installation decommissioningprogrammes. It is therefore not possible to buildthis understanding from the bottom-up. However,analysing the general characteristics of the NorthSea Sectors provides insight into the infrastructurethat could be removed in the coming decade.

    Steel Activity

    Fixed steel installations and the topsides ofconcrete gravity base installations are most likelyto require a removal vessel to decommissionthe topside and substructure either by lifting

    or reverse float over (a method where a vesselis semi-submerged and positioned under theplatform, and the lift is achieved by de-ballastingthe vessel). The remaining installations are eitherself-propelled or can be towed requiring lessonerous intervention.

    The UK and Norway have an estimated 4.5million tonnes of steel associated with fixed steelor concrete gravity base topsides which will a lleventually need to be decommissioned[4].

    The other North Sea countries account for only0.6 million tonnes or 12% of the total North Seasteel removal requirements[4].

    The largest steel substructure is the 45,300tonne YME MOPUStor installation[4]. However,the majority of substructures are significantlylighter, with 64% under 2,000 tonnes. The largesttopside for a fixed installation is the 53,000tonnes Gullfacks C[4]. Again, the majority ofsubstructures are significantly lighter with 62%under 3,000 tonnes.

    3.2 Market Forecasts of Activity

    Removal Requirements of Fixed Steel andConcrete Gravity Base Topsides in the North Sea

    Fixed Steel InstallationsSubstructures

    Weight(Te)Millions

    4.0

    3.5

    3.0

    2.5

    2.0

    1.5

    1.0

    0.5

    0Denmark Nertherlands Norway UK

    Fixed Steel and Concrete GravityBased Installations Topsides

    Source: OSPAR[4]

    Weight of Fixed Steel and ConcreteGravity Base Topsides

    South(Refers to areasbelow 55 degrees LAT)

    North(Refers to areasabove 55 degrees LAT)

    58,000

    Source: OSPAR[4]

    Source: OSPAR[4]

    Market Forecasts| Market Forecasts of Activity

    Weight of Fixed Steel Substructures

    58,000

    South(Refers to areasbelow 55 degrees LAT)

    North(Refers to areasabove 55 degrees LAT)

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    31/100

    31

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    Across the North Sea, steel decommissioning isestimated to average around 150,000 tonnes perannum up to 2019 and over 270,000 tonnes perannum between 2020 and 2022. Excluding steelassociated with floating installations, this figurecould be around 100,000 tonnes per annum up to2019 and over 150,000 beyond.

    The decade from 1984 to 1993 was theperiod when the most infrastructure by weightwas installed in the North Sea on an annualaverage basis with over 240,000 tonnes of steelinstalled every year[4]. This volume of activity is

    commensurate with estimated activity over thenext decade. This suggests decommissioningactivity could be comparable to peak installationactivity.

    In the UKCS, it is estimated that nearly 440,000tonnes of steel associated with topsides andsubstructures will be removed in the periodbetween 2014 and 2022[1]. This equatesto approximately 9% of the existing steelinfrastructure in the UKCS.

    The timing of decommissioning activit ies in theNorwegian Sector is considered more uncertain

    with limited published analysis available. TheNCPA have estimated that between 50,000 to80,000 tonnes of steel a year will be removed untilaround 2020[7]. The Agency then expects a steepincrease to around 200,000 tonnes after 2020.

    This estimate seems surprisingly high as it equatesto the removal of nearly 50% of the existing steelinfrastructure in the Norwegian Sector by 2022.

    The Dutch and Danish Sectors are even lessquantified, but likely to only contribute a smallproportion of total North Sea steel removal activity.Estimates made by Arup suggest a total removal

    of the order of 30,000 - 40,000 tonnes between2014-2022, or 5-7% of their existing infrastructure.

    Estimated Annual Steel Removalin the North Sea

    UK (North - Refersto areas above 55degrees LAT)

    Weight(Te)Thousands

    400

    350

    300

    250

    200

    150

    100

    50

    02014 to 2019

    inc. Floating

    2014 to 2019

    excl. Floating

    2020 Onwards

    inc. Floating

    2020 Onwards

    excl. Floating

    NorwayUK (South Refersto areas below 55degrees LAT)

    All Others

    Source: O&G UK[1],[9] ,NCPA[7]

    Market Forecasts | Market Forecasts of Activity

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    32/100

    32

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    Well Abandonment

    Platforms vs Subsea

    Wells are either co-located with a platform and havebeen drilled from a permanent installation to whichthe well is directly connected, or subsea and drilledfrom a mobile installation and tied back to a localplatform. Platform wells may be abandoned using theplatform as an operational base. If the original drillingrig is still present, it can be refurbished and reused toabandon the well. Alternatively, a rig can be retrofittedto the platform, or a rigless alternative can be used.

    Platform-based operations are significantly moreflexible and lower cost than their mobile alternative.Encountering unexpected conditions is also generallyless of a concern than for subsea wells, as operationsare more easily suspended.

    Subsea wells can also be abandoned using a mobilerig such as a drill ship, semi-submersible or jack-upvessel. A light-weight intervention vessel can alsobe used if a rigless methodology is opted for. Thewater depth and metocean conditions of well locationboth influence the appropriate methodology andsubsequent vessel requirements.

    Rigs vs Rigless

    Wells can be abandoned using either rig orrigless approaches. A rig based approach usesvessel or platform drilling rigs, adapted to recoverdownhole equipment and plug the wells. Riglessalternatives can be utilised for some or all partsof P&A operations to reduce the number ofexpensive rig days. However, the condition andtype of well dictates the potential to use a riglessapproach. Currently rigless operations have been

    biased towards platform based operations due totechnology constraints and operators risk appetite.Due to the limitations of rigless methodologies, costscan dramatically increase if unexpected conditionsare encountered and a rig needs to be deployed tocomplete the abandonment. Technology innovationand increased demonstration of rigless approachesis likely to reduce these risks and increase their use inthe future with consequential cost reductions for webabandonment activities.

    Market Forecasts | Market Forecasts of Activity

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    33/100

    33

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    Suspended SNS / CNS / IS

    Activity

    It is estimated that there are more than 8,200wells in the North Sea that are active orsuspended and awaiting P&A. The majority ofthese are located in the UKCS, accounting for61% of wells[9] [10] [11] [12] [13].

    There is significant publicly available datafrom the UKCS in terms of the technicalcharacteristics of well infrastructure andplanned decommissioning activity whichcan be used to inform the understandingof demands on the supply chain. The otherSectors have a paucity of data. It is thereforenecessary to make assumptions in termsof the relative activity based on known datain terms of geographical characteristics,infrastructure volume, spend and activityprofiles.

    Activity in UKCS

    It is estimated that there are close to 5,000wells requiring abandonment in the UKCSof which around 18% (more than 800) willrequire abandonment in the next

    decade[9], [1]. Approximately 80% of all wellsin the UKCS are associated with a platform,but the next decade will see a proportionatelylarger number of subsea wells to platformwells being abandoned, compared to the longterm[9].

    Of the wells expected to be decommissionedin the next decade, there is a relativelyconsistent and even split between wells inthe South and Central North Sea comparedto the Northern North Sea. This is the casefor both subsea and platform wells. This will

    influence vessel selection as water depthand metocean conditions differ across theseregions.

    Subsea Wells Platform Wells

    UKCS Wells to be Decommissioned

    Number

    ofWells

    3,000

    2,000

    1,000

    0

    4,000

    1,500

    500

    2,500

    3,500

    4,500

    Well type

    Completed NNS Suspended NNS

    Unclassified

    Total UKCS Wells tobe Decommissioned

    SubseaWells910

    Platform Wells3725

    SubseaWells258

    Platform Wells552

    Wells to beDecommissioned

    in the UKCS (2014 - 2022)

    Source: Oil & Gas UK[9]Source: Oil & Gas UK[1]

    Source: Oil & Gas UK[9]

    Market Forecasts| Market Forecasts of Activity

    Wells in the North SeaUK

    Netherlands

    Norway

    Denmark

    Source: DECC[10], NPD[11], DEA[12], NLOG[13]

    5000

    2330

    550

    375

    Completed SNS / CNS / IS

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    34/100

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    35/100

    35

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    Activity in Norway

    There are over 2,300 active wells in the NorwegianSector of which only 140 have been suspended[11].

    There is limited information regarding the planneddecommissioning programmes for these wells, or ifthey are associated with platforms or subsea.

    The nature of the Norwegian Sector water depthsmeans that the wells are likely to all be in deeperwaters, therefore requiring intervention by semi-submersible vessels or drill ships, rather than jack-upvessels.

    The Norwegian volume of activity could be assumedas roughly half of the UK activity inferred fromthe knowledge that they have only 40% of theinfrastructure, but that their spend and steel removalactivity profile suggest a more aggressive spendprofile than the UK. In the absence of publisheddata, it could be assumed that Norway has similarcharacteristics to the UK in terms of demands for rigsversus rigless solutions. However, further analysisof the characteristics of the wells may affect thoseassumptions.

    Activity in Denmark

    There are nearly 380 active wells in Danish waters[12].Denmark has been focusing on the P&A ofsuspended wells which has resulted in only a verysmall number remaining suspended, all of which haveP&A plans approved by the Danish Energy Agency(DEA). Across the Danish North Sea, only 3 subseawells exist with all remaining wells being platformbased.

    The nature of the Danish Sector water depths meansthat the wells are likely to be all in shallower watersrequiring intervention by jack-up vessels rather than

    semi-submersible vessels or drill ships.Activity in Denmark is likely to be more biasedtowards rigless approaches than the overall UK profiledue to the low number of subsea wells. However,the spend profiles combined with the proportion ofinfrastructure suggests that activity will represent lessthan 10% of the level occurring in the UKCS.

    Activity in Netherlands

    There are nearly 500 active wells in Dutch watersof which approximately 10% are suspended[13].

    There is limited information regarding the planneddecommissioning programmes for these wells, or ifthey are associated with platforms or subsea.

    The nature of the Dutch Sector water depthsmeans that the wells are likely to be all in shallowerwaters requiring intervention by jack-up vessels orlightweight intervention vessels (LWIV) rather thansemi-submersible vessels or drill ships.

    In the absence of published data, it could beassumed that the Dutch Sector would have similarcharacteristics to the UK in terms of demands forrigs versus rigless solutions. Further analysis ofthe characteristics of the wells may impact thoseassumptions.

    The spend profiles combined with the proportion ofinfrastructure suggests that activity will represent lessthan 10% of the level occurring in the UKCS.

    Market Forecasts| Market Forecasts of Activity

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    36/100

    36

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    Published Plans

    There is a paucity of published data on decommissioning dates from operators. Data published by OSPAR andthe North Sea regulators identifies a total of 32 installations likely to cease production and/or be removed in thecoming decade [4], [14], [15], [16]. These include 29 fixed steel installations and 3 concrete gravity base. 67% of theplatforms are located in the deeper and more exposed waters in the northern areas of the North Sea.

    UK Norway Denmark Netherlands

    Miller

    Brent A

    Brent B

    Brent C

    Brent D

    Goldeneye

    Kittiwake A

    Thames AV

    Thames AR

    Thames AP

    Brae A

    Brae B

    Brae EastMurchison

    Little Dotty

    Big Dotty

    Albuskjell F

    Edda

    Ekofisk A

    Ekofisk G

    Ekofisk S

    H-7

    Hod

    Huldra

    Valhall PCP

    Vest EkoFisk

    YME MOPUStor

    Cecilie

    Dagmar

    Rolf

    Svend

    Q8-B

    K10-B

    Weight of North Sea Platforms Expected tobe Decommissioned (2014 - 2022)

    TopsideWeight(Te)

    1,000,000

    100,000

    10,000

    1000

    100

    Substructure Weight (Te)

    100 1000 10,000 100,000 1,000,000

    Concrete Gravity Based Fixed Steel

    Source: OSPAR[4], NPD[14], DEA[15], DECC[16]

    The following plots show the relative topsideand substructure weights for the 32 identifiedplatforms. The larger the circle, the sooner theplatform is planned for removal.

    Market Forecasts| Market Forecasts of Activity

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    37/100

    37

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    The identified platforms equate to approximately1.2 million tonnes of infrastructure of which540,000 tonnes is fixed steel or concrete gravitybase topsides. This equates to an annualremoval of approximately 54,000 tonnes of steel.

    These figures are about two thirds of the valuesidentified by O&GUK and NCPA up to 2020.

    This suggests that there are plans for additionalplatforms to be decommissioned in the nextdecade, which are not in the public domain andthese estimates appear conservative.

    The weight distribution of these 32 installations,

    as shown in the graphs, show a broad spreadof installation sizes. This is despite the factthat the overall North Sea asset stock includesa significantly higher proportion of smallerinstallations in the more sheltered areas of thesouthern North Sea. This suggests that the earlydemands for decommissioning are going to bemore evenly spread across all the weight ranges,with a disproportionately higher demand forlarger capacity vessels depending on the removalmethod.

    Weight of Topsides for Platforms Expectedto be Decommissioned

    South North

    NumberofTopsides

    8

    7

    6

    5

    4

    3

    2

    1

    0

    Weight (Te)

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    38/100

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    38

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    39/100

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    39

    4.0 Critical Supply Chain Elements

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    40/100

    40

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    Identification of the critical supply chain elementshas been based on Arups experience and viewof the status of the industry and informed throughconsultation with the industry expert panel.

    The following critical supply chain elements havebeen established as those most likely to impacton the delivery of cost effective decommissioningprogrammes, with potential to require marketintervention to ensure their capacity is secured.

    They are parts of the supply chain which are knownto have:

    demands from other maritime and otherindustries

    known shortages either in the past or expectedin future, are specialised and not easilysubstituted by alternatives, and

    challenges in growing capacity

    The critical supply chain elements identified are showin the table referenced to the resource breakdownstructure.

    ResourceBreakdownElements

    Critical SupplyChain Elements

    Generic CriticalSupply ChainElements

    Operator ProjectManagement &Monitoring

    NoneConsideredCritical

    EngineeringSkills

    OperationalSkills

    WellAbandonment

    Drilling Rigsor Rigless

    Alternatives

    Running

    Making Safe &Preparation

    None

    ConsideredCritical

    Topside &SubstructureRemoval

    RemovalVessels

    Subsea & SiteRemediation

    NoneConsideredCritical

    Topsides &SubstructureReuse &

    Recycling

    Ports, Harboursand Yards

    Rigs and Rigless Alternatives for

    Well Abandonment

    Rigs or rigless alternatives have been identified asa fundamental aspect of the well abandonmentprocess and cannot be replicated through anotherprocess. This resource has significant pressures fromE&P activities as the same infrastructure is utilisedfor drilling activities and is mobile across the globalmarket. This market is volatile and the spot prices forthis infrastructure is vulnerable to market demand.

    The capacity floats to meet an unpredictable demandand decommissioning activity will need to competewithin this challenging market.

    Critical Supply Chain Elements

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    41/100

    41

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    Removal Vessels for Topside and

    Substructure Removal

    Removal vessels are a critical part of thedecommissioning process and their cost andavailability will have a substantial impact on the overallcosts of the process. It is likely that vessels withlift capacities of up to 500 tonnes and significantlyhigher will be utilised by the market regardless ofthe approach to removal. They are not unique to thedecommissioning market and are utilised for E&P aswell as offshore wind markets.

    The capital costs of a new vessel are significant,and vessel operators will require a substantialcommitment to invest in new capacity. The latest newspecialist heavy lift vessel, the Pieter Schelte wasover 10 years in development and was supportedby an investment case from markets other thandecommissioning. Although smaller vessels for piecesmall operations will be significantly less expensiveand quicker through the planning process, theywould need to be developed in greater volume todeliver the same level of work of the larger vessels.

    Ports, Harbours and Yards for Topsides and

    Substructure Recycling

    Although operators could potentially utilise ports,harbours and yards from the global market to carryout decommissioning activities, this would likely beat a significant cost penalty to decommissioning.

    This is not because it would impact recycling costs,which are only a small proportion of overall costs, butbecause it would impact on removal costs throughincreasing vessel costs. It would also reduce thepotential for local socio-economic benefits throughcreation of jobs in the North Sea local markets.

    The capital cost of upgrading major infrastructure can

    be substantial and generally requires high investmentcertainty to make commitment. In addition to thisthe timescales can be extremely protracted, with theduration to realise significant new infrastructure fromdesign and development to construction potentiallytaking up to a decade for a contentious development.

    Engineering and Operational Skills for all

    areas of Decommissioning

    Skills capacity is an issue that crosses all aspects ofthe decommissioning process, and was commonlycited as a potential concern and constraint. Thechallenges to grow skills capability are distinct toinvestment in a physical resource such as a vesselor port. They require a collaborative effort betweenschools, universities, operators, supply chain andGovernment.

    Other Resources

    There are a significant number of other resourcesassociated with the decommissioning processeswhich are detailed in Appendix C. These resourcesoffer a significant opportunity to the supply chainas the market grows. They will require a breadth ofhighly skilled and high value capacity and capability.

    A range of activities will require innovation in termsof technical and management approaches to drivedown the costs of decommissioning. Examplesinclude development in cutting tools, or improvedlogistics management of offshore operations. Thereare other areas that will need significant growth incapacity to meet the demands of the market, such asa growth in survey capability or support vessels.

    There will undoubtedly be constraints in supply ofmany of these resources depending on the level ofmarket demand. However these areas are of lowercapital investment and lead time when comparedto the aspects considered as critical supply chainelements. The supply chain is more likely to be ableto naturally respond to these opportunities withoutany market intervention. As such, although they areconsidered as significant opportunities, they are notassessed in detail as part of this exercise.

    A health check of the four critical supply chainelements identified above is provided in Chapters5 to 9 where each element is considered within thecontext of the expected activity and in light of currentcapacity. Engineering and operational skills areconsidered separately in Chapter 4, as these skillsare somewhat transferrable across the RBS.

    Critical Supply Chain Elements

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    42/100

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    42

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    43/100

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    43

    5.0 Well Abandonment

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    44/100

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    44

    Skills Supply ChainInfrastructure and

    Equipment

    Well and P&A ProjectManagement

    Engineering (P&A)

    Operations Support

    Rig Upgrade Capabilities

    Waste Management

    Rig and Rigless DesignServices

    Hazardous Waste Handlingand Disposal Routes

    Specialist Well Inspectionand Intervention services

    Specialist Services i.e.

    Wireline

    Rigs

    Rigless Solution

    Light Weight InterventionVessels

    Transport Vessels

    Waste and Scale Treatmentand Storage

    Abandonment Materials,Expanding Cement,Resins, Silicone Rubber

    Drilling Contractors

    Specialist Consultants andContractors

    Vessel Operators

    Rig/Rigless Contractors

    Well Abandonment

    Decom North SeaReview of Decommissioning Capacity | September 2014

    Well Abandonment

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    45/100

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    45

    Well P&A can be done using mobile rigs mountedon a vessel, platform rigs or rigless solutions on alightweight intervention vessel. These resources areall considered critical supply chain elements. The

    selected appropriate approach is dictated by thetype and condition of the well.

    There are over 8,200 active or suspended wellsin the North Sea, all of which will eventually needto be plugged and abandoned[9] [10] [11] [12] [13]. In theUKCS it is estimated that over 800 wells will beabandoned in the next decade[9]. An extrapolationof data considering infrastructure and expectedspend in Denmark, Norway and the Netherlandssuggests that there could be up to a 70% increasein activity from the other Sectors. The majority of thisadditional activity will be in the deeper waters of thenorthern areas of the North Sea.

    The number of working years required to abandonwells in the UKCS over the next decade have beenestimated. It is predicted there are;

    4.5 years which require mobile drilling rigs suchas jack-up vessel, semi-submersible or drillship.

    Approximately 10 years which require platformrigs.

    Approximately 7.5 years which require riglessplatform solutions.

    Less than 2 years of subsea rigless operationswhich require intervention vessels but notmobile drilling rigs.

    These durations are exclusive of any weather relatedor other non-productive downtime.

    Considering P&A activity in isolation the marketcapacity for mobile drill rigs appears to be adequatefor both jack-up vessels and semi-submersiblevessels/drill ships. However, there is greateruncertainty when considering platform rigs andrigless solutions, where there is more uncertaintyregarding the potential for capacity constraints.

    Mobile drilling rigs, temporary platform rigs andrigless intervention systems are all mobile resources.P&A contractors operate globally, following marketopportunities in E&P and P&A in the worldsproducing regions. Although it is expected that there

    will be sufficient supply chain capability to meetthe demands of abandonment activity in isolation,the competition for E&P resources has potentialto cause a constraint in an already highly utilisedsupply chain.

    5.1 Overview

    700

    600

    500

    400

    300

    200

    100

    0

    2014 2015 2016 2017 2018 2019 2020 2021 2022

    Estimated UKCS Expenditure

    Millionperyear

    46%

    Well Abandonment | Overview

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    46/100

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    46

    Well P&A can be done using mobile rigs mountedon a vessel, platform rigs or rigless solutions on alightweight intervention vessel. These resources allconsider critical supply chain elements.

    Currently, there are more than 8,200 wells in theNorth Sea that are either in production, injectionor that have been suspended and awaiting P&A.

    The majority of these are located in the UKCS, andaccount for 61% of wells.

    There is significant data available from the UKCSin terms of the technical characteristics of wellinfrastructure and planned decommissioning activitywhich can be used to inform the understanding ofdemands on the supply chain. The other Sectorshave a paucity of data and it is necessary to makeassumptions in terms of the relative activity based onknown data in terms of geographical characteristics,infrastructure volume, spend and activity profiles.

    5.2 Activity

    Well Abandonment | Activity

    Number of Wells in the North SeaUK

    Netherlands

    Norway

    Denmark

    Source: DECC[10], NPD[11], DEA[12], NLOG[13]

    5000

    2330

    550

    375

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    47/100

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    47

    UKCS and Other North Sea Regions

    It is estimated that there are approximately 5,000wells requiring abandonment in the UKCS ofwhich around 18% (more than 800) will requireremoval in the next decade[1].

    O&GUK estimates that it will require over 140working years of activity to abandon all the wellscurrently in the UKCS, without any workingdowntime[9]. Of this, 80 years are expectedto require rigs (based on current technologycapability). The majority of this activity (55 years)

    is associated with platform wells which may beable to utilise existing or refurbished rig capability.However, a large proportion are likely to requirea temporary rig. The remaining 25 years areassociated with subsea wells, which are morelikely to need a mobile drilling rig or LWIV.

    Using this as a basis to consider activities in thenext decade (where 18% of wells will be removed)and assuming current technical capabilities, thereare[9]:

    4.5 years which require mobile drilling rigssuch as jack-up vessel, semi-submersible or

    drill ship. Approximately 10 years which require

    platform rigs.

    Approximately 7.5 years which require riglessplatform solutions.

    Less than 2 years of subsea riglessoperations which require intervention vesselsbut not mobile drilling rigs.

    The next decade will see a larger proportion ofsubsea wells removed than platform wells.

    As such these statistics are likely to underestimate

    the number of mobile drilling rig years andoverestimate the number of platform rig years.

    In the rest of the North Sea, contribution of activityfrom the Norwegian, Dutch and Danish Sectorswill increase the demands on the supply chain.

    An extrapolation of data considering infrastructureand expected spend suggests that there couldbe up to a 70% increase in activity from the otherSectors. The majority of this additional activity willbe in the deeper waters of the northern areas ofthe North Sea. Extrapolating between the balanceof rig and rigless solutions is not possible due to a

    lack of available data.

    Total UKCS Wells tobe Decommissioned

    SubseaWells910

    Platform Wells3725

    SubseaWells258

    Platform Wells552

    Wells to be Decommissionedin the UKCS (2014 - 2022)

    Source: Oil & Gas UK[9]

    Source: Oil & Gas UK[1]

    Well Abandonment | Activity

    0

    UKCS Well P&A Durations

    20 40 60 80 100 120 140 160

    Group 1 - Rig Required

    Group 3 - Future Rigless PartialCompletion

    Group 2 - Future Rigless withEntire Completion

    Group 4 - Rigless

    Group 5 - Pluged Wellbore RequiringAnnulus Plugs

    PlatformWells Total

    Duration

    SubseaWells Total

    Duration

    Source: Oil & Gas UK[9]

    Working Years

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    48/100

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    48

    Drilling activity peaked in the decade followingthe mid-1980s with an annual of 540 wellsdrilled a year in that period. Currently drillingactivity is lower than the peak activity, but stillsubstantial with 470 wells a year or nearly 90%of peak activity[10], [11], [12], [13]. If drilling continued atthe same rate over the next decade, estimated

    abandonment activities in the same period willrepresent an increase in activity of 30%. This willput increasing pressures on the supply chain formobile and platform drilling rigs.

    Mobile Drill Rigs

    Drill ships and semi-submersible vessels areadapted to work in deep water and harshexposed environments. Jack-up vessels are alower cost option which are optimal for shallowwater and are more weather sensitive in theperiod in which they are mobilised for operations.Jack-ups for abandonment have a broader

    water depth envelope than their heavy-liftcounterparts, but are still limited to about 150meters. Generally, jack-ups are suitable for theSouthern, Central and Irish Sea in the UKCS aswell as Dutch and Danish Sectors. Drill ships andsemi-submersible vessels are usually deployedin the UKCS Northern North Sea and NorwegianSectors.

    Within the UKCS, approximately half of theworking requirements are in the Northern NorthSea, and as such there is likely to be an equaldistribution between jack-up vessels versus

    semi-submersible vessels /drill ship requirements.An increase in activity in the Norwegian Sectorwill increase the requirements on drill ships andsemi-submersible vessels. As this equates toapproximately 50% of the UKCS activity, it islikely to affect the overall availability of thesevessels. Although Dutch and Danish Sectorswill be biased towards jack-up vessels, theyhave a significantly smaller proportion of vesselrequirements. As such overall, it is assumed thereis a bias towards the need for semi-submersiblerather than jack-up vessels in terms of overallactivity.

    5.3 Supply Chain

    Historical E&P and Future P&A in the North Sea

    Total North Sea E&P

    Num

    berofWells

    800

    700

    600

    500

    400

    300

    200

    100

    020231987 1991 1995 1999 2003 2007 2011 2015 2019Pre 60 1963 1967 1971 1975 1979 1983

    E&P in Norway

    P&A UKCS

    Total North Sea P&A

    E&P in Denmark

    P&A Others

    E&P in the UKCS

    E&P in Netherlands

    North Sea Mobile Drill Rigs

    NumberofDrillRigs 60

    50

    40

    30

    20

    10

    0Drillship Jackup Semisub

    Number of Rigs Average Rated Water Depth (m)

    AverageOperatingDepth(m)

    3000

    2500

    2000

    1500

    1000

    500

    0

    Rig Type

    Source: DECC[10], NPD[11], DEA[12], NLOG[13]

    Source: Rigzone[17]

    Well Abandonment | Supply Chain

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    49/100

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    49

    Rigzone catalogues that there are 97 mobile drillrigs currently operating in the North Sea, whichrepresents around 12% of the global fleet [17]. Theseare relatively evenly split between semi-submersiblevessels and jack-ups. Even when factoring in weatherand other unproductive time, a fleet this size couldeasily support the 4.5 rig years of adandonmentrequired in the next decade from the UKCS. Theadditional estimated 70% increase of activity from theother sectors is unlikely to cause a constraint.

    However, utilisation of mobile rigs is currentlyhigh, with global utilisation of jack-ups and semi-

    submersible vessels averaging between 79 to 88%last year[18]. The incremental increase in abandonmentactivity when considered in the back drop of E&Pactivity, could potentially cause a constraint on mobilerigs, unless greater numbers of the global fleet aredeployed in the North Sea.

    Platform Rigs

    The requirement of drill rigs for platforms is estimatedto be more than double the requirement of mobiledrilling rigs in terms of working days. The capabilityof the market to refurbish existing platform rigs will

    dictate the required capacity for additional rigs tobe temporarily installed on the platform. Again, asplatform rigs are in demand for drilling activity, therewill be a competition for this resource and it has thepotential to become a constraint.

    Rigless Intervention Systems

    Rigless interventions are associated with about 40%of the total working days of all P&A activities. Riglessinterventions are estimated to mainly be associatedwith platform wells, but also with a smaller number ofsubsea wells. For these operations, the availability ofrigless systems must be considered.

    There is also a significant number of additional wellsthat could be abandoned using a rigless solution iftechnology innovation was stimulated. Indeed, riglesssolutions are significantly shorter and lower cost than

    rig-based alternatives and could offer a more costeffective alternative to operators.

    The market is likely to want to move towards usingrigless options where risk-based analysis concludesthat it is the most cost effective approach. Availablyof rigless solutions has the potential to becomea constraint in the future, especially if the marketconfidence increases in its viability.

    Well Abandonment | Supply Chain

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    50/100

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    50

    Overall Status = Red

    There is a high potential for well abandonment resources to cause a supply chainbottleneck based on the considerations detailed above.

    Investment Status = Low / Medium

    Contractors are reluctant to make commitments to new rigs and rigless systems without certaintyin terms of timing of the North Sea decommissioning market. In the Gulf of Mexico an idle iron

    policy had been implemented which places a deadline on abandonment activity. This policydecision has given market certainty and stimulated technology innovation in bringing forward

    more rigless solutions. In the North Sea further innovations are necessary to de-risk riglesssolutions.

    Capability = Low / Medium

    Accenture[5]consider well adandonment aligned with the 2011 WBS which considers P&A of wells, rig upgrades and rigless optionsamong others with an average capability for these three of 2.5 out of 5.

    Rig upgrades were rated the lowest capability with P&A and rigless options performing better.

    Accenture conclude that the market for associated well services such as drilling, completions and interventions has extensiveknowledge, tools, technology, experience and capability. Well Abandonment has been widely identified as a phase requiring focusand there are multiple organisations, events and publications that provide a forum for discussion, debate and knowledge sharing.

    The presence of global players in the UKCS provides a source of knowledge, technology and experience of complex well situationsand well abandonments from other regions.

    However, while the market for wells services is mature, the specific capability and experience for plugging & abandonment is not asstrong. The entry costs for new wells companies in the UKCS are too high, in part due to the cost of compliance to local regulations.

    Estimated volume of supply against demand = Low / Medium

    Considering P&A activity in isolation the market capacity for mobile drill rigs appears to be adequate for both jack-up vessels andsemi-submersible vessels/drill ships.

    There is more uncertainty when considering platform rigs and rig less solutions where there is more potential for capacity constraints.

    Rigless solutions are significantly shorter and lower cost than rig-based alternatives and could offer a more cost effective alternativeto operators. There are a significant number of additional wells that could be abandoned using a rigless solution if technologyinnovation is stimulated.

    The market is l ikely to want to move towards using rigless options where r isk-based analysis concludes that it is the most costeffective approach. Availably of rigless solutions has potential to become a constraint in the future if the market confidence increasesin its viability.

    The lead time to development of r ig-based solut ions is less than five years to commission and construct new capacity. For riglesssolutions, where innovation and demonstration is required this lead time could potentially be even longer.

    Pressures and/or synergies from other industries = Low / Medium

    Mobile drilling rigs, platform rigs and rigless intervention systems are all mobile resources. P&A contractors operate as a globalresource, following the market opportunities from E&P and P&A in the worlds O&G producing regions. Anecdotally well contractorsprefer to support new field development, as it is less cost driven and more programme focused than decommissioning.

    Currently drilling activity is 470 wells a year or nearly 90% of peak activity which occurred in the 1980s.

    Although there is expected to be sufficient supply chain capabili ty to meet the demands of abandonment activity inisolation the competition for E&P resources has potential to cause a constraint in an already well utilised supply chain.

    5.4 Health Check

    Well Abandonment | Health Check

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    51/100

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    51

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    52/100

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    53/100

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    53

    6.0 Topside & Substructure Removal

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    54/100

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    54

    Skills Supply ChainInfrastructure and

    Equipment

    Detailed Engineering(Topsides andSubstructures)

    Naval Architecture

    Offshore Operations

    Transportation

    Removal Vessel

    Transportation Barges

    Anchor Handling TugSupply (AHTS) Vessels

    Construction SupportVessels (CSV)

    Safety Standby Vessels(SSBVs)

    Survey Vessels

    Rock Dumping / BackfillVessels

    Heavy-Lift VesselContractors

    Support Vessel Contractors

    Engineering Consultancies

    Specialist Consultancies

    Topside & Substructure Removal

    Decom North SeaReview of Decommissioning Capacity | September 2014

    Topside & Substructure Removal

  • 7/21/2019 _Decommissioning in the North Sea - Demand vs Capacity_low-res

    55/100

    Decom North Sea

    Review of Decommissioning Capacity | October 2014

    55

    83% of installations in the North Sea are fixed steeland 4% concrete gravity base[4]. They will requirea vessel to remove the topside and substructure,either by lifting or reverse float over. The remaining

    installations are either self-propelled or can betowed requiring less onerous interventions. Theconstruction vessels utilised to remove topsides andsubstructures are considered to be critical supplychain elements.

    The market is not consolidated on a single approachto decommissioning for topsides and substructures,and the methodology is influenced by a range oftechnical and commercial factors, such as theweight and design of the installation and the marketavailability of vessels. As a result, there is a diverserange of vessel types that can be utilised by themarket. These include large heavy-lift vessels whichoperate in deep waters and exposed conditions in

    the Northern North Sea, and to sheer leg, and jack-up vessels which are more suited to the shallow andbenign waters of the Southern North Sea.

    The market peak for installation in the North Seaoccurred in the decade from 1984 to 1993[4]. In thisperiod, an approximate average of 240,000 tonnesof steel was installed every year [4]. This activity level

    is equivalent to estimates of steel removal over thenext decade, which are approximately 150,000to 260,000 tonnes a year. This suggests that thedemand for decommissioning resources in the nextten years will be comparable to the period of peakactivity which occurred 30 years ago.

    The North Sea has significantly greater numbers ofsmaller and lighter platforms than heavier and largerplatforms. However, published plans suggest thatthe early demands for decommissioning are goingto be spread more evenly across all the weightclasses with a disproportionately higher demand forlarger capacity vessels.

    The availability of suitable heavy-lift vessels todecommission the larger platforms in the northernarea is likely to create the biggest constraint. Insouthern areas, where platforms are generallysmaller, there is a larger fleet of vessels that couldremove topsides in a single lift, though this reducesfor categories above >1,600 tonnes.

    6.1 Overview

    160

    350

    300

    250

    200

    150

    100

    50

    0

    2014 2015 2016 2017 2018 2019 2020 2021 2022

    Estimated UKCS Expenditure

    Millionperyear

    22%

    Topside & Substructure Removal | Overview

  • 7/21/2019 _Decommissioning in the North Sea