12
Harrisburg Overpass Construction Update December 1, 2015

December 1, 2015 - ride METRO...•We have produced 5,000 flyers ( English/Spanish) •Posters printed and distributed •Banners – facilities will install •Radio Buys with Univision

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: December 1, 2015 - ride METRO...•We have produced 5,000 flyers ( English/Spanish) •Posters printed and distributed •Banners – facilities will install •Radio Buys with Univision

Harrisburg Overpass Construction Update December 1, 2015

Page 2: December 1, 2015 - ride METRO...•We have produced 5,000 flyers ( English/Spanish) •Posters printed and distributed •Banners – facilities will install •Radio Buys with Univision

Utilities Completed 3,800 LF

% Completed Installed Total

55% 2095 LF

All Utility Work East of Union Pacific Railroad

Page 3: December 1, 2015 - ride METRO...•We have produced 5,000 flyers ( English/Spanish) •Posters printed and distributed •Banners – facilities will install •Radio Buys with Univision

Utilities Remaining to be Relocated East of Union Pacific Railroad

Page 4: December 1, 2015 - ride METRO...•We have produced 5,000 flyers ( English/Spanish) •Posters printed and distributed •Banners – facilities will install •Radio Buys with Univision

Concrete Paving East of Union Pacific Railroad

Page 5: December 1, 2015 - ride METRO...•We have produced 5,000 flyers ( English/Spanish) •Posters printed and distributed •Banners – facilities will install •Radio Buys with Univision

Current Sidewalk Detour Plan

5

Page 6: December 1, 2015 - ride METRO...•We have produced 5,000 flyers ( English/Spanish) •Posters printed and distributed •Banners – facilities will install •Radio Buys with Univision

All Utility Work West of Union Pacific Railroad

Utilities Completed 4,150 LF

% Completed Installed Total

73% 3,210 LF

Page 7: December 1, 2015 - ride METRO...•We have produced 5,000 flyers ( English/Spanish) •Posters printed and distributed •Banners – facilities will install •Radio Buys with Univision

Utilities Remaining to be Relocated West of Union Pacific Railroad

Page 8: December 1, 2015 - ride METRO...•We have produced 5,000 flyers ( English/Spanish) •Posters printed and distributed •Banners – facilities will install •Radio Buys with Univision

Concrete Paving West of Union Pacific Railroad

Page 9: December 1, 2015 - ride METRO...•We have produced 5,000 flyers ( English/Spanish) •Posters printed and distributed •Banners – facilities will install •Radio Buys with Univision

Progress and Planned Activities • Pavement Operations are beginning in the Northeast Quadrant

• McCarthy will maintain driveways by adding crushed stone as required

• Relocated Street Lighting during construction to be maintained and illuminate along new roadway

• METRO/McCarthy are working to adjust schedule activities to keep the project on schedule • Select construction activities will be built concurrently with major bridge activities during the third phase of

construction

• McCarthy will be working extended hours to expedite completion of roadway pavement • The placing, finishing, curing, and saw cutting new pavement requires extended work hours

• Utility crews started 12 hour days instead of 10 hours

• To make up time due to rain, McCarthy chose to work on one Sunday in November

• McCarthy plans to work extra shifts during the drilling of the 6 major bridge bents in Phase II of the project • Weather permitting, this work will begin in January 2016

9

Page 10: December 1, 2015 - ride METRO...•We have produced 5,000 flyers ( English/Spanish) •Posters printed and distributed •Banners – facilities will install •Radio Buys with Univision

30 Day Look Ahead

10

West of UPRR

Complete 24” Storm east of Caylor

Water line and Sanitary Sewer Service Taps

Rough grade, lime stabilize subgrade, fine grade, erect forms, place steel reinforcement, place

concrete, cure, and saw cut for new roadway, intersection and driveway pavement

Install curbs and sidewalks

Install underground conduit for bridge lighting

Install temporary asphalt transitions from existing roadway to new concrete pavement

East of UPRR

Complete all storm sewer lines

Complete 8” waterlines

Complete Sanitary sewer lines

Wet connects for water services

Clear and grub right of way for new roadway pavement

Rough grade, lime stabilize subgrade, fine grade, erect forms, place steel reinforcement, place

concrete, cure, and saw cut for new roadway, intersection and driveway pavement

Traffic control switch from south to north side of Harrisburg to complete utility work in southeast

quadrant

Page 11: December 1, 2015 - ride METRO...•We have produced 5,000 flyers ( English/Spanish) •Posters printed and distributed •Banners – facilities will install •Radio Buys with Univision

Marketing Update for East End Businesses

• Collaborated with the EEMD, the EECOC, Business Owners, and Residential Stakeholders

• Final Product is the East End Calendar of Events scheduled to start on Wednesday, December 2 • We have produced 5,000 flyers ( English/Spanish) • Posters printed and distributed • Banners – facilities will install • Radio Buys with Univision ( Estereo Latino) • Print ads with two week run of the front cover and two page spread due December 2

– (Que Onda) • Foam Arrows for business visibility • Individual Store flyers • Direct Mail/Door hangers

11

Page 12: December 1, 2015 - ride METRO...•We have produced 5,000 flyers ( English/Spanish) •Posters printed and distributed •Banners – facilities will install •Radio Buys with Univision

Radio Spots

12