Upload
junwhan-kim
View
222
Download
2
Embed Size (px)
Citation preview
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
1/60
Pressure PipeInstallation Manual
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
2/60
02
03
04
06
08
09
1316
22
23
23
24
25
27
28
30
ContactInformation
General
Pipe
Information
TheSteelBellandSpigotJoint
Shipping
Weights
and
Dimensions
Laying
Length
PipeMarkings
Pipe
Dimensions
for
Lined
and
Embedded
Cylinder
Pipe
JointDeflection
Bevel
Adaptors
Field
Installation
HealthandSafety
Unloading
the
Pipe
DiggingtheTrenchandPreparingtheBedding
Handling
the
Pipe
Preparing
the
Pipe
Ends
QuantitiesofLubricant&GroutforJoints
TABLE OF CONTENTS
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
3/60
31
3234
36
37
38
39
40
4142
46
48
50
51
54
55
56
57
Making
the
Joints
Installing
FittingsChecking
the
Gaskets
Grade
and
Line
Changes
Protecting
the
Joints
Backfilling
InstallingwithaTrenchBox
Testing
Restrained
Joints
Snap
Ring
Restrained
Joint
Welded
Restrained
Joint
HarnessClampRestrainedJoint
Closures
Emergency
Closures
Pressure
Tapping
Wall
Pieces
Pipe
OrientationField
Services
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
4/60
DECAST Ltd.8807 County Road 56
Utopia, ON L0M 1T0
1.800.461.5632
705.734.2892
Engineering Fax: 705.734.2270
Shipping Fax:
705.734.9373
WEB
www.decastltd.com
0
l
4
416.605.7374Rob Micieli
Vice President, Sales
647.500.3789Mauro DeFranco, P.Eng.Technical Sales Engineer
416.520.2779
905.302.1062
705.796.8868
Benoit Tanguay, ing, P.Eng. 514.209.318(Eastern Canada)
Martin Fischer
Sales
John Pozzobon, C.E.T.
Sales
Frank Mazza, C.E.T.Sales
ENGINEERING
CONTACT INFORMATION
% John Siervogel 705.623.726Field Services
CONTACTS!
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
5/60
GENERAL PIPE
INFORMATION
DECAST concrete pressure pipe and fittingsare manufactured to ANSI/AWWA C301standards in sizes from 400 mm to 3600mm with working pressures to 1720KPa and higher
For specialized applications DECAST canalso manufacture concrete pressure
pipe to ANSI/AWWA C300 and C302specifications.
DECAST concrete pressure pipe isrugged, durable and long-lasting. Thepipe has self-centering steel joint rings andrubber gaskets that ensure water-tightness and joint flexibility.
Concrete pressure pipe can be installedeasily, rapidly and economically because itssteel bell and spigot joint, which ismanufactured to close tolerances,permits a quickly-made watertightconnection.DECAST provides pipelinelayout drawings that show thesequence of installation for all pipe and
fittings it manufactures.
This installation manual providesinstructions for laying, joining andbackfilling pipe. It is provided as a guideonly. DECAST assumes no responsibilityor liability by reason of supplying thismanual.
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
6/60
THE STEEL BELL
AND SPIGOT JOINT
The bell and spigot joint consists of a steel spigot on which a rubber gasket is placed. During installation, the spend is pushed into the steel bell to form a watertight joint.
Prestressed Lined Cylinder Pipe Ready for Joining Prestressed Embedded Cylinder Pipe Ready for J
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
7/60
The following diagrams show the completed joint for a prestressed lined cylinder pipe and a completed jointfor a prestressed embedded cylinder pipe.
Completed Joint for a Prestressed Lined Cylinder Pipe Completed Joint for a Prestressed Embedded Cy
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
8/60
SHIPPING WEIGHTS AND
DIMENSIONS
TABLE 1: SHIPPING WEIGHTS AND DIMENSIONS OF
LCPAND ECP
DECAST supplies lined cylinder pipe (LCP)and embedded cylinder pipe (ECP) in thefollowing diameters.
Nominal Pipe
Diameter(mm)
Bell
O.D.(mm)
Barrel
O.D.(mm)
Approx.
Weight(Kg/m)
Core
Length(m)
LCP 400 572 508 230 6.096
450 629 565 270 6.096
500 686 622 300 6.096
600 800 737 380 6.096
750 972 908 560 6.096
900 1143 1080 710 6.096
1050 1302 1251 970 6.096
1200 1473 1422 1230 6.096
1350 1667 1594 1460 6.096
1500 1838 1765 1640 6.096
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
9/60
ECP 1050 - 1295 1120 6.096
1200 - 1473 1340 6.096
1350 - 1626 1490 6.096
1500 - 1803 1680 6.096
1650 - 1981 2240 6.096
1800 - 2159 2650 6.096
1950 - 2337 3070 6.096
2100 - 2518 3560 6.096
2250 - 2670 3780 6.096
2400 - 2822 4020 6.096
2550 - 2975 4320 6.096
2700 - 3140 4690 6.096
2850 - 3311 5140 6.096
3000 - 3483 6030 4.877
3150 - 3686 6260 4.877
3300 - 3826 6780 4.877
3550 - 3997 7370 4.877
3600 - 4169 7970 4.877
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
10/60
LAYING LENGTH
TABLE
2:
LAYING
LENGTHThe
nominal
lay
length
of
a
standardlengthpipeis6.106mor
4.887m. Thenominallaylengthis
basedona10mmjointgap.Actual
laylengthcanvaryasshowninthe
followingtable:
Nominal PipeDiameter
(mm)
Min. LayingLength
(m)
AverageLaying Length
(m)
Max. LLen
(m
LCP 400 through to 1200 6.096 6.106 6.1
1350 6.096 6.106 6.1
1500 6.096 6.106 6.1
ECP 1050 & 1200 6.096 6.106 6.1
1350 6.096 6.106 6.1
1500 6.096 6.106 6.1
1650 6.096 6.106 6.1
1800 6.096 6.106 6.1
1950 6.096 6.106 6.1
2100 6.096 6.106 6.1
2250 & 2400 6.096 6.106 6.1
2550 through to 2850 6.096 6.106 6.1
3000 through to 3600 4.877 4.887 4.9
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
11/60
PIPE MARKINGS
The bell end inner concrete lining of thepipe surface is stenciled with:
DECAST
Date of manufacturing
Mark No.
Cylinder gauge, if other than 16 Gauge
Job No.
Serial No.CSA / NSF 61
AWWA Designation
Inspector's stamp
Concrete pressure pipe is an engineeredproduct. Prior to repositioning any pipe orfitting contact the Engineering Department atDECAST
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
12/60
PIPE MARKINGS
Pipe Size(in)
Nominal PipeDiameter
(mm)
Pipe Size(in)
NominaDiam
(m
16 400 78 19
18 450 84 21
20 500 90 22
24 600 96 24
30 750 102 25
36 900 108 27
42 1050 114 28
48 1200 120 30
54 1350 126 31
60 1500 132 33
66 1650 138 34
72 1800 144 36
Cylinder gauge (if other than 16 Ga)
Restrained joint (A) Snap Ring Bell, (W)
welded joint
Class of pipe (CL 12)
Pipe size, see Table 3
Lined (L), Embedded (E)
L 48 - 12 A - 14G TABLE
3:
PIPE
MARKING
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
13/60
A pipe that differs from a standard pipe ismarked with a coloured stripe.
A Y LLOWSTRIP indicates that the pipe has arestrained bell end.
A PINK STRIP indicates that the pipe has a
threaded or flanged outlet and is painted atthe outlet.
A LU STRIP indicates that the pipe has abevelled spigot.
Pipe Markings
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
14/60
PIPE MARKINGS
TABLE 4:
SPIGOT
COLOUR
CODPipe
with
cylinder
thickness
greater
than
16
Gauge
are
speciallymarkedbyaddingapaintpatchonthespigot
end. The colour code system is according to the
followingchart: U.S GaugeNumber
Steel Sheet Thickness MaCo
(mm) (in)
16 1.52 0.0598 N
14 1.90 0.0747 O
12 2.66 0.1046
10 3.42 0.1345 G
8 4.18 0.1644 Y
6 4.94 0.1943 P
N/A 6.35 0.2500
N/A 7.37 0.2900 Blue/
N/A 7.62 0.3000 Blu
N/A 7.94 0.3125 Blu
N/A 12.7 0.5000 Blue
N/A 15.88 0.6250 Red
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
15/60
PIPE DIMENSIONS FOR LINED AND
EMBEDDED CYLINDER PIPE
LinedCylinderPipe EmbeddedCylinderPipe
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
16/60
PIPE DIMENSIONS FOR LINED AND
EMBEDDED CYLINDER PIPE
TABLE
5:
LINED
CYLINDER
PIPE
DIMENSIONS
Nominal PipeDiameter
(mm)
PipeI.D.
(mm)
CoreThickness
(mm)
Std. JointDepth(mm)
JointDiameter
(mm)
BellO.D.
(mm)
BarrelO.D.
(mm)
CoreLength
(m)
400 406 25 114 470 572 508 6.096
450 457 29 114 527 629 565 6.096
500 508 32 114 584 686 622 6.096
600 610 38 114 699 800 737 6.096
750 762 48 114 870 972 908 6.096
900 914 57 114 1041 1143 1080 6.096
1050 1067 67 114 1200 1302 1251 6.096
1200 1219 76 114 1372 1473 1422 6.096
1350 1372 86 121 1565 1667 1594 6.096
1500 1524 95 124 1738 1838 1765 6.096
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
17/60
Nominal PipeDiameter
(mm)
PipeI.D.
(mm)
CoreThickness
(mm)
Std. JointDepth(mm)
JointDiameter
(mm)
BarrelO.D.
(mm)
CoreLength
(m)
1050 1067 89 114 1143 1295 6.096
1200 1219 102 114 1302 1473 6.096
1350 1372 102 130 1467 1626 6.096
1500 1524 114 133 1622 1803 6.096
1650 1676 127 137 1781 1981 6.096
1800 1829 140 114 1944 2159 6.096
1950 1981 152 143 2095 2337 6.096
2100 2134 165 114 2255 2518 6.096
2250 2286 165 149 2410 2670 6.096
2400 2438 165 149 2569 2822 6.096
2550 2591 165 152 2715 2975 6.096
2700 2743 171 152 2873 3140 6.096
2850 2896 181 152 3064 3311 6.096
3000 3048 190 152 3216 3483 4.877
3150 3200 200 152 3369 3686 4.877
3300 3353 210 152 3521 3826 4.877
3450 3505 219 152 3673 3997 4.877
3600 3658 229 152 3826 4169 4.877
TABLE 6: EMBEDDED CYLINDER PIPE DIMENSIONS
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
18/60
JOINT DEFLECTION
After
the
joint
is
in
place,
the
pipe
can
be
deflected within the tolerable limits that are
shownintheTables7,8,9and10.
DeflectionofStandardPipe
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
19/60
TABLE 7: JOINT DEFLECTION OF LINED CYLINDER PIPE
Nominal PipeDiameter
(mm)
Max. JointOpening
(mm)
AverageLaid
Length(m)
Max.Deflection
Angle
Max. Offsetfor Std.Length(mm)
Min. CurveRadius for
Std. Length(m)
JointDepth
(mm)
JointDiameter
(mm)
400 44 6.106 5 - 24 ' 574 64 114 470
450 44 6.106 4 - 49 ' 512 72 114 527
500 44 6.106 4 - 21 ' 462 80 114 584
600 44 6.106 3 - 38 ' 387 95 114 699
750 44 6.106 2 - 55 ' 311 119 114 870
900 44 6.106 2 - 26 ' 259 142 114 1041
1050 44 6.106 2 - 7 ' 225 164 114 1200
1200 44 6.106 1 - 51 ' 197 188 114 1372
1350 41 6.106 1 - 30 ' 160 231 121 1565
1500 44 6.106 1 - 27 ' 155 238 124 1738
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
20/60
JOINT DEFLECTION
Nominal PipeDiameter
(mm)
Max. JointOpening
(mm)
AverageLaid
Length(m)
Max.Deflection
Angle
Max. Offsetfor Std.Length(mm)
Min. CurveRadius for
Length(m)
JointDepth
(mm)
JointDiamete
(mm)
400 13 6.106 1 - 32 ' 164 225 114 470
450 13 6.106 1 - 22 ' 146 253 114 527
500 13 6.106 1 - 14 ' 132 280 114 584
600 13 6.106 1 - 2 ' 110 335 114 699
750 13 6.106 0 - 50 ' 88 417 114 870
900 13 6.106 0 - 41 ' 74 499 114 1041
1050 13 6.106 0 - 36 ' 64 576 114 1200
1200 13 6.106 0 - 31 ' 56 658 114 1372
1350 13 6.106 0 - 27 ' 49 751 121 1565
1500 13 6.106 0 - 25 ' 44 833 124 1738
TABLE 8: JOINT DEFLECTION OF LINED CYLINDER PIPE WITH MECHANICAL RESTRAINED JOINTS
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
21/60
TABLE 9: JOINT DEFLECTION OF EMBEDDED CYLINDER PIPE
Nominal PipeDiameter
(mm)
Max. JointOpening
(mm)
AverageLaid
Length(m)
Max.Deflection
Angle
Max. Offsetfor StdLength(mm)
Min. CurveRadius for
Std. Length(m)
JointDepth
(mm)
JointDiamete
(mm)
1050 44 6.106 2 - 13 ' 236 156 114 11431200 44 6.106 1 - 57 ' 208 178 114 1302
1350 48 6.106 1 - 51 ' 197 187 130 1467
1500 51 6.106 1 - 47 ' 190 194 133 1622
1650 54 6.106 1 - 44 ' 184 201 137 1781
1800 31 6.106 0 - 56 ' 99 373 114 1944
1950 60 6.106 1 - 38 ' 175 211 143 2095
2100 31 6.106 0 - 48 ' 85 432 114 2255
2250 67 6.106 1 - 35 ' 168 220 149 2410
2400 67 6.106 1 - 29 ' 158 234 149 2569
2550 63 6.106 1 - 20 ' 142 260 152 2715
2700 63 6.106 1 - 15 ' 134 275 152 2873
2850 63 6.106 1 - 11 ' 126 294 152 3064
3000 63 4.887 1 - 7 ' 96 247 152 3216
3150 63 4.887 1 - 4 ' 91 258 152 3369
3300 63 4.887 1 - 1 ' 87 270 152 3521
3450 63 4.887 0 - 59 ' 84 282 152 3673
3600 63 4.887 0 - 57 ' 80 293 152 3826
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
22/60
JOINT DEFLECTION
TABLE 10: JOINT DEFLECTION OF EMBEDDED CYLINDER PIPE WITH MECHANICAL RESTRAINED JOINTS
Nominal PipeDiameter
(mm)
Max. JointOpening
(mm)
AverageLaid
Length(m)
Max.Deflection
Angle
Max. Offsetfor Std.Length(mm)
Min. CurveRadius for
Std. Length(m)
JointDepth
(mm)
JoiDiam
(m
1050 13 6.106 0 - 38 ' 67 548 114 11
1200 13 6.106 0 - 33 ' 59 624 114 13
1350 13 6.106 0 - 29 ' 52 704 130 14
1500 13 6.106 0 - 26 ' 47 778 133 16
1650 13 6.106 0 - 24 ' 43 854 137 17
1800 13 6.106 0 - 22 ' 39 932 114 19
1950 13 6.106 0 - 20 ' 36 1005 143 20
2100 13 6.106 0 - 19 ' 34 1082 114 22
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
23/60
2250 13 6.106 0 - 18 ' 32 1156 149 24
2400 13 6.106 0 - 16 ' 30 1232 149 25
2550 13 6.106 0 - 16 ' 28 1303 152 27
2700 13 6.106 0 - 15 ' 26 1379 152 28
2850 13 6.106 0 - 14 ' 25 1470 152 30
3000 13 4.887 0 - 13 ' 19 1235 152 32
3150 13 4.887 0 - 12 ' 18 1293 152 33
3300 13 4.887 0 - 12 ' 17 1352 152 32
3450 13 4.887 0 - 11 ' 16 1410 152 36
3600 13 4.887 0 - 11 ' 16 1469 152 38
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
24/60
BEVEL ADAPTORS
BevelAdaptor
Bevel
adaptors
may
be
used
to
make
minor
grade or line changes that are beyond the
normaljointdeflection.
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
25/60
FIELD INSTALLATION &
HEALTH AND SAFETY
HEALTH AND SAFETY
All installation procedures and operations
must be performed in accordance with local
Occupational Health and Safety Act (OHSA)
regulationsandcodes.
FIELD
INSTALLATION
The most common way to lay prestressed
concrete pipe is with a backhoe, although
other methods can be used depending on the
conditions and the size of the pipe
beinginstalled.
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
26/60
UNLOADING THE PIPE
All DECAST pipe is inspected at ourfacilities before shipping. However, thepipe should always be checked for anydamage that may have occurred duringtransit. Note any damage on the packingslip before accepting the pipe.
Before unloading the pipe, the truck andthe trailer must be parked on a level, stable
surface with brakes applied and, ifnecessary, wheels blocked. Whenunloading multi-tiered shipments, the crosstimbers must be secured to the trailer siderail on the side that is being unloaded toprevent the timbers from kicking up-wardsand dropping the rear pipe off the backside of the trailer.
When pipes are unloaded using a forklift,forks must be cushioned using rubber orwood to prevent damaging the pipe.
Pipe may also be unloaded using abackhoe or crane fitted with a cable orsling, with safe lifting capacity, that hasbeen centered on the pipe at thebalancing point. The cable or sling mustbe short enough to control themovement of the pipe. Multiple slingsmay be needed if the pipe or fittingsare large. Chains are not recommended.
Gaskets should be stored in a cool placeaway from heat, sunlight, gasolineor other materials that can damagerubber. Joint lubricants should be storedaccording to the manufacturer'sinstructions. If freezing conditions areexpected, the pipe must be set onwooden skids off the ground.
Unloadingpipeusinforklift
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
27/60
DIGGING THE TRENCH AND
PREPARING THE BEDDING
The typical trench geometry should allowfor sufficient clearance to properly installthe pipe. Pipe designs are affected by thetrench geometry, and hence the trenchgeometry should not be changed from thecontract specifications without consultingthe supervising engineer and DECAST.
Diggingatrenchforalengthofpipe
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
28/60
DIGGING THE TRENCH AND
PREPARING THE BEDDING
COVER MATERIAOVER MATERIANATIVE MATERIAATIVE MATERIA
Typical Trench Bedding
A space along the width of the pipeapproximately 200 mm deep and 400 mmlong should be made at the place where thepipe will be joined. This space allowsroom for the installation of the diaperaround the joint. To allow removal of thecable after the pipe has been laid, a spacecan also be made at the point where thesling is located.
After digging the trench, the contractormust follow the specifications that areappropriate for the type of bedding. Forany change to the specifications, thesupervising engineers should be consulted.
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
29/60
HANDLING THE PIPE
Slip
the
steel
cable
sling
under
the
pipe.
Hookoneendoftheslingonthehookofthebucket.
When you find the balancing point on the
lengthofpipe,markthebalancingpointsonthe
otherlengthsofpipe.
To achieve the best possible control over the
joining,slowlymovethebackhoetotheendof
thetrench,ascloselyasissafe.
Backhoewithsteelslingmovingpipe
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
30/60
PREPARING THE PIPE ENDS
For proper installation of the gasket priorto joining the pipe the following stepsshould be adhered to:
Clean the spigot groove and the insideof the bell. Apply lubricant on thespigot groove and the inside of the bell.See Table 11 for recommended amounts.
Apply lubricant to the rubber gasket witha clean cloth. Caution: Use only thelubricant supplied by DECAST Petroleumbased lubricants should not be usedbecause they will damage the rubbergasket.
3 Place the lubricated gasket in thegasket groove of the entire spigot ring.
When the gasket is in place, insert asmooth rod or a screwdriver between thegasket and spigot
ring and run the screwdriver/rod around the entire circumferenceof the spigot ring to ensure that thegasket is stretched evenly aroundthe spigot. This usually takes 2 to 3rotations to accomplish.
4
Coat the gasket with lubricant.
5
Do not pre-install gaskets in pipestrung out ahead of theinstallation crew because the jointlube under the gasket can dry fromthe heat of the sun or be diluted byrain water. In both of thesesituations, the gaskets ability toslide within the groove duringinstallation will be inhibited.
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
31/60
Cleanspigotgrooveandinsideofbell Applying lubricant to the spigotgroove
Applying
lubricant
to
the
gasket
with
a
cleanclothUsing
a
screwdriver
to
ensure
that
thegasket is stretched evenly around the
spigot
Applyinglubricanttotheinsidbell
Coating
the
gasket
with
lubric
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
32/60
QUANTITIES OF LUBRICANT
& G ROU T F O R JO I NT S
Quantities of lubricant shownare based on applying 1.5 mmthick layer of lubricant to thegasket, spigot groove and theinside of bell.
The amount of grout shownare based on grouting the outside
joint opening of a standard joint.
TABLE
11:
APPROXIMATEQUANTITIES
OF
JOINT
LUBR ICANT&
GROUTFOR
EXTER NALSTANDARDJO
Nominal PipeDiameter
(mm)
Approx. No.of Joints per10 Kg Pail of
Lubricant
Approx.Amount
of Grout perJoint
(cu. meter)
Nominal PipeDiameter
(mm)
Approx. No.of Joints per10 Kg Pail of
Lubricant
ApAm
of GrJ
(cu.
400 34 0.0142 1950 5 0.
450 31 0.0159 2100 4 0.
500 28 0.0176 2250 3 0.600 23 0.0211 2400 3 0.
750 18 0.0263 2550 3 0.
900 15 0.0315 2700 3 0.
1050 11 0.0363 2850 2 0.
1200 9 0.0414 3000 2 0.
1350 8 0.0473 3150 2 0.
1500 7 0.0525 3300 2 0.
1650 6 0.0650 3450 2 0.1800 6 0.0709 3600 1 0.
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
33/60
MAKING THE JOINTS
Carefully
maneuver
the
pipe
to
align
the
spigotend toward the existing bell end so that the
spigotwillenterthebellendsquarely. Ifthepipe
is properly aligned, the pipe will slide in
smoothly. If any dirt touches the lubricated
spigot ring of the pipe already in position, the
spigot ring must be cleaned and lubricated
again.
PipeJoining
PipeJoiningOptions
The following diagram shows three methods of majoints.
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
34/60
INSTALLING FITTINGS
Fitting
joints
slide
together
in
the
same
way
asjoints for straight pipe. Aswith straight pipe,
hydraulicpullersandcome-alongscanbeused
tojointhefittings.
The long and short sides of the elbow are
stenciledonthefaceofthespigot.Additionally,
fittingsaregivenatopmarkatthespigotorbell
endasrequired.
Long,ShortandTopMark
Come-alongs or hydraulic pullers canbe used to
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
35/60
Elbowmovedintopositiononthepipe
g y p
pull thejoint home while thebackhoe supports
the elbow from above.
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
36/60
CHECKING THE GASKETS
A
feeler
gauge
is
used
to
test
the
joints
for
correctgasketplacement.
LCPPIPE
Use the external feeler gauge to check the
gasketfromtheoutside.
1 Insertthefeelerintothejoint.
2
If
you
cannot
feel
the
gasket
anywherealong the full circumference, thejointis
ACCEPTABLE.
3 Ifyoufeelthegasketanywherealongthe
circumference, remake thej oint usinga
newlubricatedgasket.
THE GASKETCANNOTBE FELT
AROUND THE FULLCIRCUMFERENCE
OF JOINT, THEREFORE, THE JOINT IS
ACCEPTABLE FEELER GAUGE
RUBBER GASKET
AcceptableLCPJoint
THE GASKET IS FELT ANYWHERE, REMAKE
JOINT WITH NEW LUBRICATED GASKET
F
RUBBER GA
UnacceptableLCPJoint
EXTERNAL
FEELER GAUGE
INTERNAL
FEELER GAUGE
23 mm
68 mm
ExternalandInternalFeelerGauge
ECPPIPE
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
37/60
Inspect the gaskets using the internal feeler
gauge from the inside. Insert spacers
(12mm) between the bell and spigot ends to
allowentryofthefeelergauge.
1 Insertthefeelerintothejoint.
2 Ifthefeelergaugedoesnotfitbetweenthe
bellandthespigot,thejoint isACCEPTABLE.
3 Occasionally,thejointringsmaypermitthe
feelergaugetobeinsertedoverthespigotlip
for a certain distance along the
circumference.Attheselocations,youmust
beabletofeelthegasket. Ifyoudo,thejointis
ACCEPTABLE.
4 Ifyou do not feel the gasketwhere the
feelergaugewasinserted,thegaskethas
been rolled or is cut. Remake thejoint
usinganewgasket.
THE FEELER GAUGE FITS IN BETWEEN THE SPIGOT
AND BELL, AND THE GASKET CAN BE FELT AROUND
THE FULL CIRCUMFERENCE OF THE PIPE.
THEREFORE,THE JOINTIS ACCEPTABLE
FEELER GAUGE
RUBBER GASKET
AcceptableECPJoint
THE FEELER GAUGE FITS IN BETWEEN THE
SPIGOTAND BELL, BUTCANNOT FEEL THE
GASKET. THEREFORE, REMAKE JOINT WITH NEW
LUBRICATED GASKET
FEELERGAUGE
RUBBER GASKET
UnacceptableECPJoint
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
38/60
GRADE AND LINE CHANGES
If joint deflections are required, they shouldbe made after the pipes have beenjoined. Restrained joints must bedeflected as described in the restrainedjoint section of this manual. Pipe positionscan be checked with a laser or transit.
A level is used to check the elevation of the bell ethe pipe.
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
39/60
PROTECTING THE JOINTS
To
protect
the
joints,
a
mortar
collar
is
poured
aroundthefullcircumferenceofthejoint.
1 Placethediaperaroundthefullcircumference
of thej oint so that it straddles thejoint.
Tightenthewiresorthestraps.
2 Mix 3 parts sand to1 part cementwith
enoughwater to make a free-flowing grout.
Ensure
that
the
same
cement
that
was
used
in
thepipecoatingisusedinthegrout.
Seetable11forapproximateamountof
groutperstandardjoint.
3 Pourthegroutintothediaperononeside
until the mortar appears on the other side.
Continue pouring the grout on the other
sideuntilthediaper isfull.Trowelthegapat
thetopofthediaperwithastiffermix.
4 Mortartheinsideofthej oint. Usearatioof3:1(sa
cement) and enoughwater to make a mix tha
easily
trowelled.
Point
the
inner
joint
recess
andthesurfacesmoothwiththeinsideofthepipe.
Pouringthegroutinthediaper
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
40/60
BACKFILLING
Bulldozerbackfillingthepipe
Follow
the
contract
specifications
for
backfilling. In general, after the pipe has been
laidtothe lineandgrade,material istampedin
uniform layers not more than 200 mm in
thickness up to the spring line of the pipe.
From the spring line of the pipe to about 300
mm above the top of the pipe, selected
material is spread uniformly and compacted.
The remainder of the trench is filledwith any
readily
available
backfill
appropriate
for
the
trafficconditions.
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
41/60
INSTALLING WITH
A T REN CH BO X
Soil
conditions
and
ensuring
safety
often
requires that pipe is installedwithin a trench
box.
Afteryoupull theboxahead in the trench, it is
important tocheck thepipe tomakesure that
thepipejointshavenotpulledapart.
Installingwithatrenchbox
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
42/60
TESTING
All testing must be done in accordance withcontract specifications and procedures.DECAST can provide test bulkheads toaccommodate field test pressures on isolatedsections of the pipeline. Air testing is notrecommended.
TestBulkhead
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
43/60
RESTRAINED JOINTS
When a pipeline changes size, direction oris bulkheaded, the internal line pressurecreates a thrust condition along thepipeline. At these locations, restrainedjoints are installed to counteract thethrust. Snap Ring joints, welded jointsand Harness Clamp are the typicalrestrained joints that DECAST uses.Harness Clamp restrained joints are
normally used at the long term bulkheadlocations.
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
44/60
SNAP RING
RESTRAINED JOINT
This patented joint assembly providesrestraint for pipe diameters 400 mmthrough 1800 mm and is provided byDECAST. The Snap Ring joint assembly isused for applications requiring restraintdue to unbalanced forces (such as bends,tees, etc.), therefore eliminating theneed for thrust blocks.
The joint design eliminates the problemof point bearing and at the same timepermits deflection, for slight directionalchanges during installation. Followingassembly of the joint, the voids around thejoint are filled with a protective cement/sand grout. This grout helps to distributethe thrust load uniformly around the jointperimeter.
Registered trade name of Price Brothers Corporation
Snap RingJoint
At the same time, the grout willcompress under load to permit slight
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
45/60
compress under load to permit slightsettlement of the pipeline. The result is asuperior restrained joint with a shortinstallation time that effectivelyeliminates the chance of aninstallation error.
The Snap Ring method is a fast and easyway to make a better mechanicalrestrained joint. The joint is completely self-contained, ready to engage, and completedby tightening a 9 mm bolt. It onlyrequires one man just a few minutes tocomplete the joint using a speed wrench. Snap RingJoint Assembly
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
46/60
SNAP RING RESTRAINED
JOINT
DEFLECTINGASNAPRINGJOINT
ASSEMBLY
IfadeflectionoftheSnapRingisnecessary,
theinsertringmustbetightenedintwostages.
Stageone:Thejoint isassembledsquarelyand
the insert is tightened only enough to prevent
thepipefrompullingapartduringdeflection.
SingleBoltSnapRingJoint
Stagetwo:Oncethepipehasbeendeflectedthe
requiredamount,the insertcanbetightened to
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
47/60
SnapRingJoint
q g
the extent of the bolt travel. Hand tightening is
allthatisrequired,donotforcethebolt.
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
48/60
WELDED
RESTRAINED JOINT
Welded joints are another method used totransmit thrust as well as provide joint restraint.However, they are generally less economical thana mechanically restrained joint due to field weldingcosts. The rigidity of a welded joint coupled withextreme soil settlement will cause adjacent pipelengths to transform into one long rigid beam,subjected to bending and shear stresses. To thisend, welded type joints are used in special
applications to resist thrust and to increase the lay-length of a standard pipe.
If welded joints are used, DECAST recommendseither an internal welded joint or an externalwelded joint. Internal welded joints are utilized forpipelines 1200 mm and larger in diameter, wherewelding inside the pipeline is feasible.
This method requires a water-tight weld due tothe absence of the gasket.
Internal Field Weld
For pipelines 1050 mm and smallerin diameter, an external welded joint
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
49/60
jis recommended. This method requires afield-weld bar (rolled to joint diameter),which is wedged tightly against theassembled joint rings. The procedure iscompleted by a partial or full weld ofthe joint assembly circumference,avoiding unnecessary heat which maydamage the rubber gasket.
ExternalFieldWeld
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
50/60
HARNESS CLAMP
RESTRAINED JOINT
TheHarnessClampRestrainedJoint isnormally
used
at
locations
where
there
is
the
potential
for
future connection. It is also used where the
application dictates a higher pressure, for
exampleatabulkhead.
HarnessClampJoint
DEFLECTING A HARNESS
CLAMP JOINT
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
51/60
When deflecting a Harness Joint the two C
clamps must be assembled and tightened in
two steps:
Step one: Assemble joint tightening the two
bolts only enough to prevent the pipe frompulling apart during deflection.
Step two: Once the pipe is deflected to the
appropriate angle tighten the bolts and grout
as usual.
Harness
Clamp
Joint
CLOSURES
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
52/60
CLOSURES
Closure sections are used when a newpipeline is connected to an existingpipeline, or when a connection is requiredafter an isolated pressure test. Tomanufacture the closure section, DECASTrequires the exact dimensions of theclosure length.
If access to the pipe joints is available, the
closure should be measured as per thediagram to the right. If the bulkheadscannot be removed or if completeexcavation is not possible, DECASTTechnical Services can instruct the surveycrews on how to acquire the necessarydimensions. DECAST will manufacture theclosure to fit the existing opening. Theclosure may be installed with a coupling or
a split welding sleeve.
MeasuringforaTypicalClosure:
Closures can be manufactured for restrained o
restrainedareasofthepipeline.
EMERGENCY CLOSURES
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
53/60
InstalledClosure Installedstandardweldsleeveclosure
DECAST can provide a full range of Emergency Closuresections available in 6.096 m and 7.315 m lengths. These
sections are designed to replace standard lengths ofpipe in restrained and non-restrained areas. The
plain ends of the closure sections are suitable fowelded sleeve or mechanical coupling. Fo
information regarding Emergency Closure please contact our Engineering department.
EMERGENCY CLOSURES
PRESSURE TAPPING
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
54/60
PRESSURE TAPPING
Tapping into concrete pressure pipe isa routine application. The proceduresfor tapping concrete pressure pipe whilethe pipe is under pressure are thesame as for tapping other kinds of pipe.Weld-on tapping assemblies are notrecommended for tapping concrete pipebecause deformation may occur duringwelding to the pressurized steel cylinder.
The tapping saddle configuration shouldallow for the saddle to be securely boltedto the pipe before the prestressing wire orthe reinforcing rod from the tap openingare removed.
Tapping
machine
positioned
on
pipe
DECAST can provide a full range of tappingsaddles for concrete pressure pipe andother piping products DECAST also
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
55/60
Installed wire anchor tapping saddle
other piping products. DECAST alsoprovides a full line of tapping services. Inlined cylinder pipe 900 mm and smaller astrapless saddle tap may be used for tapsbetween 19 mm and 38 mm. The saddleanchors directly to the prestressing wireafter the mortar coating has been carefullychipped away.
This type of tapping saddle requiresno reinforcing bands or excavation underthe pipe. Encase all exposed steel in a 3:1mortar mix after the tap has been made.
Use a strap-type saddle for larger taps.The saddle shown in the photograph belowis for a 200 mm tap in a 750 mm diameterpipe.
PRESSURE TAPPING
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
56/60
PRESSURE TAPPING
The reinforcing bands of the saddle must be
torqued
and
the
space
between
the
saddle
andthebarrelofthepipegroutedbeforeanyof
the prestressing wires are cut. The space
around the saddle gland can be grouted after
the pressure test is complete but must be
done prior to tapping the pipe. In all cases
tapping concrete pressure pipe should only be
done by qualified, experienced personnel.
After
tapping
is
complete
the
saddle
should
be
protected by encasement in a cement rich
concreteormortarwithaminimumcoverof25
mmoverallsteelsurfaces.Densotapeandpaste
may also be used where concrete
placementisimpractical. Strap-typesaddleusedforlargertaps
WALL PIECES
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
57/60
WALL PIECES
WallPiece
Wall pieces are generally provided with wall
flanges
or
thrust
collars
at
the
point
at
which
thewall is to encase the piece. Ifyour project
does not incorporate this feature, internal
bracing should be used to ensure that the
pieceremainsroundduringtheconcretepour.
Wall pieces may also be providedwithwater
stops.
These
are
not
designed
for
thrust
restraint. If thrust restraint is required, joint
restraints (mechanical or welded) must be
used. If thrust flanges are incorporated in the
wall piece the longitudinal thrust must be
transmitted from the wall piece to the
chamberorathrustblock.
PIPE ORIENTATION
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
58/60
PIPE ORIENTATION
Pipe
Orientation
It is common practiceto describe pipe asif it is
being viewed from the spigot end looking
toward the bell end.
FIELD SERVICES
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
59/60
DECAST offers the assistance of highly
trained and experienced Field ServiceTechnicians who can advise your crew oninstallation procedures and repairmethods. Please see page 2 of this manualfor contact information.
7/25/2019 DECAST-CPP-Installation-Manual-2016.02.10.pdf
60/60
DECAST Ltd.
8807 County Road 5
Utopia, ON L0M 1T0
1.800.461.5632
705.734.2892
WEB
www.decastltd.com
0
4
Most extensive product linein the industry
PRESTRESSED CONCRETE CYLINDER PIPE AND FITTINGS
VALVE AND UTILITY CHAMBERS
STEEL PIPE AND FITTINGS
BRIDGE GIRDERS
DE-SPAN
BRIDGE SUPERSTRUCTURE AND SUBSTRUCTURE
TUNNEL SEGMENTSBOX CULVERTS
REINFORCED CONCRETE PIPE
MAINTENANCE HOLES &CATCH BASINS
INTEGRATED FRAME & COVER MH SYSTEM (IFC)
HEADWALLS
RAILWAY / SUBWAY TIES