Upload
pablo-castro
View
55
Download
0
Embed Size (px)
Citation preview
PHA , Hazards Identification & Risk Analysis by Nigel Hyatt
HAZOP Procedure for company
RISK = CONSEQUENCE (IMPACT) x FREQUENCY ( LIKELIHOOD) OF OCCURRENCE
A measure of the consequence of a hazard and the frequency with which is likely to occur.
PHA , Hazards Identification & Risk Analysis by Nigel Hyatt
HAZOP Procedure for company
WHAT ?HAZOP is Hazard and Operability Analysis
WHEN ?Hazop can be used at practically any stage. It is so widely used that almost any form of process hazards analysis is referred to as “ HAZOP”
ADVANTAGE ?HAZOP is very thorough , because you force yourself to examine most aspect
DISADVANTAGE?HAZOP is very time consuming and costly. If not setup correctly and managed properly , it can be ineffective. Needs leadership by an Expert in the field of Hazop
PHA , Hazards Identification & Risk Analysis by Nigel Hyatt
HAZOP Procedure for company
A hazard and Operability ( HAZOP) analysis is the systematic identification of every credible deviation in the system or process , usually a chemical manufacturing process from the design intent. This method was used UK Imperial Chemical Industries in the 1960’s
The purpose of a Hazop is to review a process or operation systematically to identify whether deviations from the desired practices could lead to undesirable consequences
Hazop is usually requires a series of meeting during which the team , using process drawings , systematically evaluates the impact of the deviations from the desired practices
The risks of deviations are assessed and if deemed unacceptable , the a set of recommended action is determined
Definition“a system to identify, assess & mitigate potential hazards to a tolerable level by addressing not only technology but also facility and human using specific tools”
Objective : To ensure that an adequate assessment of risk is carried out in order to
meet thefollowing :1. To identify hazards and operability problems2. To identify the consequences and evaluate the risk of hazard events3. To analyse the adequacy of existing safeguards4. To recommend additional safeguards to reduce the risks if necessary
What Is PHA ?
Hazard and Operability study (HAZOP) Failure Mode and Effect Analysis (FMEA) Hazard Identification (HAZID) Hazard Analysis (HAZAN) Structured What-if Technique (SWIFT) Safety Integrity Level Assessment (SIL) Layers of Protection Analysis (LOPA) Quantitative Risk Assessment (QRA)
Which technique?
It depends on:
The type of work you are doing and
The type of potential hazards
PHA Tools
Hazard & Operability Problems
• PEOPLE - Fatality, injury• ENVIRONMENT - air, water, land, ecological• ASSET: Equipment, asset damage/loss• REPUTATION: Loss of business, national impact
Consequence & Hazard Risk
Existing Safeguards
Additional safeguards & recommendations
• Highly explosive fuel gas• Electric power• High pressure steam of 54 bar• High temperature superheated steam • N2, O2, Argon• Chemicals Tray collapsedTubes leak, not properly weldValve passing
• Procedure• Alarm & operator intervention • Interlock, LSHH, PSHH• Lab analysis• Scheduled DOSH inspection• Preventive Maintenance
• Proper training program for new staff?• Additional transmitter or alarm?• Verification checklist?• Review inventory of critical spare part?
HAZOP Process
Method Selection
CAUSEDEVIATION
CONSEQUENCEFault Tree Analysis (FTA)
HAZOP
Failure Mode & Effect Analysis (FMEA)
What-If Checklist
Examples of PHA Applications
What If/Checklist
FMEA HAZOP FTA
Conceptual
Basic
Design
Detailed
Existing process
Process change
Decommissioning
The Process Flow…
Process Hazard Analysis (PHA)
Managing Recommendations & Tracking
Prioritized?Review/challenge?Assign action partyFollow-up/trackCommunicate to employees
Hazard ReviewTo cover Technology, Human
Errors, Facility Siting & Inherent Safer Process
• To select the suitable tools e.g. What-If?,HAZOP, FMEA, FTA,IPF
AssuranceCompliancy & Review
Communicate any findings to affected employee
Hazard Identification (HazId)
Field tour Previous MOC & Incident? Previous HazOp report?
Consequences Analysis
• Identify the potential source of leakages Type of event – F, E,TR
• Size of release
• Effect to PEAR
Planning • Identify area of study/set
boundary
• Select Team comprises of PHA leader, scribe & members
SupportingElements
Site visit for verification, ergonomics study, fire safety review,
Up-to-date Information and Documentatione.g. P&ID, O&M, MSDS, Area Classification
Resources –PHA practitioners & cross-functional subject matter expert
Facilities Data through PIMS, SAP records, e-HSEMS, e-CPA
start
What is HAZOP?
HAZOP comes from the phrase “HAZard and OPerability study”
It is a systematic method (team-based) for examining complex
facilities or processes to find actual / potentially hazardous
procedures / operation. These hazards shall be eliminated or
mitigated to a tolerable level (ALARP)
Identification & assessment of hazards related to process deviation
or changes in process operating envelope
Importance of HAZOP
How can we operate plants safety if we do not know the hazards? How can we control the hazards if we don’t understand their potential of release and
impacts. How can we be confident that we are controlling the hazards if we don’t know how we
expect our controls to perform? How can we improve on the safeguards to ensure that the hazards are adequately
mitigated?
General way of doing HAZOP
By considering the plant on section-by-section, line-by-line and item-by-item; develop suitable node
By defining ‘normal operation’
By considering deviations from ‘normal operation
By using a keyword matrix to initiate discussion
General assumptions while doing HAZOP study
One failure at a time (no double jeopardy) unless It has the potential to happen It has happened before
The system will perform as the design intent The system is operated and maintained in line with the design intentProtective systems/safeguarding are functioning as designed
Outline of HAZOP Technique
HAZOP systematically review deviations from design intent The study shall consists of a team of knowledgeable and experience personnel Use guidewords to stimulate creative thinking Identify significant consequences and reasonable causes (reject small, unimportant issues e.g. small release from valve
packing) Review the available safeguards Develop recommendations to manage risks Proceed to the next deviation Put risk ranking for each of the cause (preferably later)
Outline of HAZOP Technique
The results are qualitative in nature (quantitative assessment
is available by using QRA) Effective duration is 4-5 hours per day depending on the team Further study may be required more in-depth analysis (i.e.
quantitative method) and it should be noted
Deviation List Causes
Possible?
Consequence?
Proposed OptionExisting
SAFEGUARD sufficient?
Divide system into nodes and state design intent
No
No
NoYes
Yes
Yes
For each node, select parameter
HAZOP Process
HAZOP Process Flow DetailHAZOP Process Flow Detail
Identify a Node
Describe design intent & operating condition
Consider first or next Guide Word
Identify all Causes and record
Identify all Consequences and record
List existing Safeguards and record
Identify the Risk Ranking and record
Provide any recommendations and record
Take a new Node
Last Guide Word?No
Yes
HAZOP Process FlowHAZOP Process Flow
1. Identify a Node2. Describe design intent and operating condition
A node is defined as a segment of the system which have distinct
design intent The boundary of the node should be selected such that it is
manageable for the team to analyze
Typical node: One major equipment (vessel/column/storage tank etc),
associated minor equipment (pumps/valves etc), instrumentation and other
ancillary equipment Team must understand the design intent of the node – specific information
on how the node is operated under design conditions (specific pressure,
temperature, flow etc)
HAZOP Process FlowHAZOP Process Flow
Normally, a node follows the process flow Start at an isolation point (valve or equipment item) of where the
line enters the node being analyzed (INLET BOUNDARY) Continue to the next change of design intent
OR
Continue to where a critical parameter (e.g. flow, pressure, temperature)
changes
OR
Continue to the next equipment item
The point of where the node stops is known as OUTLET BOUNDARY
Practical Tips for Node SelectionPractical Tips for Node Selection
Aim for nodes which is planned to take no more than 1 – 2 hours to
study Aim for not more than 5 causes for the first Guide Word If the team needs to analyze the node in parts, then break the node
into smaller nodes HAZOP Leader and Scribe may choose the nodes before the study session
starts. The proposed nodes shall be agreed by the team members Be prepared to change the nodes if the team is struggling to analyze it
Example of Selection of Node: HAZOP Study on MOC
The following are nodes/area of study for HAZOP: Node 1: Line from V6-0204 to AGI Node 2: Line from V6-0207 to AGI Node 3: AGI
PV-1100
From V6-0204
AGI
From V6-0207
From Glycol
From LP fuel
gas
Node No:1
Node No: 2
Node No: 3Replacement of PV-1100
HAZOP Process FlowHAZOP Process Flow
3. Consider Guide Word
Guide Word Process Deviation Definition
NO, NOT or NONE
The complete negation of the design or operating intent
No part of the intention is achieved
MORE OF Quantitative increase of the parameter
More of the intention occurs or is achieved
LESS OF Quantitative decrease of the parameter
Less intention occurs or is achieved
AS WELL AS Qualitative increase of the parameter
All the intention is achieved with some addition
PART OF Qualitative decrease of the parameter
Only some of the intention is achieved
REVERSE Logical opposite of the design intent The reverse of the operating intention occurs
OTHER THAN Something else happens No part of the intention occurs
Deviations obtained by using Guide WordsDeviations obtained by using Guide Words
Parameter Guide Word DeviationFlow No/Less No/Less Flow
Flow More More Flow
Flow Reverse Reverse Flow
Pressure More High Pressure
Pressure Less Low Pressure
Temperature More High Temperature
Temperature Less Low Temperature
Level More High Level
Level Less Low Level
Reaction More More Reaction
Reaction Other Other Reaction
Composition Other Off-specification
Contamination Other Contamination
Relief Other Relief
Sampling Other Sampling
Service No Power Failure
Service No Instrument Air Failure
Service No Cooling Water Failure
Service No Steam Failure
Service No Nitrogen Failure
Service No No Flushing Oil
Maintenance Other Maintenance
Consider other modes of operationConsider other modes of operation
Normal Operation
Reduced Throughput / Turndown
Routine Start Up
Routine Shutdown
Commissioning
Emergency
Special Modes of Operation
Other Guide WordsOther Guide Words
Phase : Gas / liquid / solid
Composition : Two phase / changes with time / slugging / additives
Testing : Equipment / hydrocarbon streams / effluents / sampling points
Operation : Operability / maintainability
Electrical : Area classification / isolation / earthing
Instrument : Sufficient for control / too many / correct location / consistent philosophy / separate tapping for alarm and IPF
Global Guide WordsGlobal Guide Words
Toxicity Commissioning / start up Shutdown (isolation / purging) Breakdown (including services and utility failures) Effluent Noise Fire / explosion Safety equipment Materials of construction Quality, consistency & reliability Efficiency and reliability Ignition
Engineering issues
Corrosion / erosion
Previous precaution
Accessibility
Orientation
Safety/ ESD
Environmental
Viscosity
HAZOP Process FlowHAZOP Process Flow
The Causes identified must be within the Node It must be a credible scenario Typically done using a brainstorming technique without considering
the Consequences It is possible that there are none or no new Cause identified for a
specific Deviation
4. Identify all Causes
HAZOP Process FlowHAZOP Process Flow
Wrong routing Blockage Incorrect blind plate insertion Isolation in error Burst pipe Large leakage Incorrectly installed check valve Equipment failure (fail-close valve, pump, filter etc) Incorrect pressure differential
Examples of Causes for NO FLOW
Examples of Causes for NO FLOW
HAZOP Process FlowHAZOP Process Flow
Surge problems Thermal overpressure Isolation of relief devices Positive displacement pump running Failed open PCV Incorrect design pressure Gas breakthrough (inadequate venting) Connection to high pressure system Specification of pipes, vessels, fittings & instruments
Examples of Causes for MORE PRESSURE
Examples of Causes for MORE PRESSURE
HAZOP Process FlowHAZOP Process Flow
Phase change Settling of slurries Leaking isolation valves, exchanger tubes Incorrect feedstock specification Process control upsets Uncontrolled reaction by intermediate or by-products
Examples of Causes for OTHER COMPOSITION
Examples of Causes for OTHER COMPOSITION
HAZOP Process FlowHAZOP Process Flow
Wrong relief philosophy (process / fire etc) Unsuitable type of relief device, blocking Unsuitable relief device location Multi-phase flow Effect of debottlenecking on relief capacity Effect of inlet/outlet piping & manifold configuration
Examples of Causes for RELIEFExamples of Causes for RELIEF
HAZOP Process FlowHAZOP Process Flow
Wrong control philosophy Wrong fail-safe philosophy Unsuitable instrument location and response time Time available for operator intervention Panel arrangement and location Fire protection Unsuitable set points of alarms, trips and authorization of changes Alarm and trip testing, auto/manual switches and human error
Examples of Causes for INSTRUMENTATIONExamples of Causes for INSTRUMENTATION
HAZOP Process FlowHAZOP Process Flow
Failure of Instrument air, steam, water & nitrogen Hydraulic power, electric power Telecommunications, computer and interfaces Heating and ventilation
Contamination of Instrument air, steam, nitrogen
Examples of Causes for SERVICE FAILUREExamples of Causes for SERVICE FAILURE
HAZOP Process FlowHAZOP Process Flow
Purging Flushing Start up Normal shutdown Emergency operation Emergency shutdown Inspection of operating machines
Examples of Causes for ABNORMAL OPERATION
Examples of Causes for ABNORMAL OPERATION
HAZOP Process FlowHAZOP Process Flow
Grounding arrangement Insulated vessel/equipment Low conductance fluids Two liquid phases Splash filling of vessel Insulated components Dust and powder handling Electrical area classification Flame arrestors Hot work and hot surfaces Auto-ignition and pyrophoric materials
Examples of Causes for IGNITION SUPPRESSION
Examples of Causes for IGNITION SUPPRESSION
HAZOP Process FlowHAZOP Process Flow
Fire and gas detection Testing of emergency equipment Emergency shutdown First aid, medical resources Fire fighting response time Effluent disposal Emergency plan & training Hazards created by others Toxic and hazardous properties of process materials
Examples of Causes for SAFETY EQUIPMENTExamples of Causes for SAFETY EQUIPMENT
HAZOP Process FlowHAZOP Process Flow
Consequences shall be linked to the cause identified Safeguards is not considered in Consequences determination
(assume the safeguards fail) Consequences can be within the Node or outside of the Node
(upstream and downstream) One Cause can lead to many Consequences (list all of them) Can be listed under People, Environment, Asset and Reputation Meaningful and significant Can be listed one by one starting from not-so-worse consequence
until the worst case scenario
5. Identify all Consequences
Examples of consequencesExamples of consequences
People
First aid injury, minor injury, major injury, fatality
Environment
Local spillage, effluent discharge to river, black smoke
Asset
Equipment crack, valve damage, fire/explosion on storage tank
Reputation
Media attention, public inquiry, disrepute to international image
HAZOP Process FlowHAZOP Process Flow
It is the designed system or administrative controls to prevent,
detect or mitigate the Consequences May list the safeguards based on the Causes Something to think about:
i. Does an indicator or a gauge being considered as a safeguard?
ii. Does working procedure being considered as a safeguard?
6. List existing Safeguards
HAZOP Process FlowHAZOP Process Flow
Safeguards for any system could be listed based on the system’s
Layers of Protection theory.
HAZOP Process FlowHAZOP Process Flow
The Risk Ranking for each Consequence shall be identified by
utilizing the PGB Risk Matrix Consequence vs. Probability = Risk Ranking In general, there are three levels of Risk Ranking i.e. HIGH
MEDIUM and LOW The “Consequence” rating shall take into consideration of the
detection and mitigation safeguards available The “Probability” rating shall take into consideration of the
prevention safeguards available
7. Identify the Risk Ranking
Sample of Risk MatrixSample of Risk Matrix
CONSEQUENCE INCREASING LIKELIHOOD ------>
People (P) Environment (E)Assets
Loss (A) Reputation (R)
A B C D ENever heard of in the industry
Has happened in the industry.
Has happened once in the company
Has happened several times per year in the company.
Has happened several times per year in company
Negligible 1 time in > 20 years
1 time between 4 to 20 years
1 time between 6 months to 4 years
1 time in < 6 months
P0No injury
E0No effect
A0No loss
R0No Impact L L L L L
P1Slight Injury
E1Slight effect
A1Slight loss
R1Slight Impact
L L L L L< 10k
P2Minor Injury
E2Minor Effect
A2Minor Loss
R2Limited Impact
L L L M M10k ~ 100k
P3Major Injury
E3Localised effect
A3Local Loss
R3
Considerable Impact L L M M H 100k ~ 0.5 M
P4Fatalities
E4Major effect
A4Major Loss
R4
National Impact L M M H H 0.5M ~ 10M
P5Fatalities
E5Massive effect
A5Extensive
Loss R5
International Impact M M H H H> 10 M
HAZOP Process FlowHAZOP Process Flow
If the team decided that the existing Safeguards are inadequate to
prevent, detect or mitigate the Consequences, they may recommend
additional safeguards to protect the system The Recommendations must address the issue and bring the risk to
an acceptable level i.e. LOW The Recommendations must be clear and use 3Ws – WHAT, WHY
and WHERE A further study may also be recommended because HAZOP is not a
tool to solve safety issues in detail Cost of the recommendations SHALL NOT be an issue for the HAZOP
analysis team
8. Provide any Recommendations
HAZOP Team SelectionHAZOP Team Selection
The team shall consist ofo HAZOP leader – to facilitate the study
o Scribe – to record the study
o Operation personnel
o Multi-disciplinary members, depending on the scope of
the study (e.g. instrument, electrical, mechanical,
inspection, piping, civil, HSE)
Balance of skills, knowledge and experience Willing contributors, able to express thoughts clearly
Process Engineer & Operation Personnel’s ResponsibilitiesProcess Engineer & Operation Personnel’s Responsibilities
Provide simple description of the system Provide design intention for each process unit Provide information in process conditions and design conditions Provide operational specialist input to the analysis
Check design for operational issues Ensure design compatibility with existing work practices Check design for operating procedure and training requirements
Provide details of process chemistry Provide details of process hazards
Typical information requiredTypical information required
As built / latest P&ID of the plant PFD and material balances Design parameters: temperature, pressure, flow etc Operating parameters: temperature, pressure, flow etc
Equipment data sheet / drawing Marked up P&ID / drawing of the system as reference Operating procedures Schedule of alarm/trip setting Cause & effect matrix Interlock logic chart Properties and hazards of process materials
HAZOP Team dynamicsHAZOP Team dynamics
Everyone shall be involvedo Encourage quiet people, manage loud people
Maintain attention and motivationo Concentrate on the task
Appropriate paceo Not too rush or too drawn out
Appropriate orientationo Primarily process rather than content oriented
PHA , Hazards Identification & Risk Analysis by Nigel Hyatt
HAZOP Procedure – Existing Plant
Occupational Safety & Health Administration( OSHA) process safety management ( PSM) regulation 29 CFR 1910.119 -Requires company to update or revalidate their PHA at least every 5 years
-In addition , the US Environment Protection Agency’s (EPA) risk management program rule , 40 CFR Part 68 requires companies to performe quatitative off-site consequences analysis
Scheduled hazard study on existing plant
Risk assessment in this context is the process of quantifying the level of risk associated with the operation of the equipment / machine
It should be a structured and systematic process that answers the following 4 specifics questions:-
i)How severe are potential injuries?
ii)How frequently are employees exposed?
iii)What is possibility of avoiding the hazards if it does occur?
iv)What is the likelihood of an injury should a safety control system fail ?
PHA , Hazards Identification & Risk Analysis by Nigel Hyatt
Pilot Plant & Operational Lab
Pilot Plant & Operational Lab
HAZOP – GROUP PRESENTATION
HAZOP – GROUP PRESENTATION
PHA , Hazards Identification & Risk Analysis by Nigel Hyatt
How to perform HAZOP process ?
1. Preparation P&ID PFD plus material and energy balances Equipment specifications Layout drawing
2. Facilitator and Process Engineer
Break P&ID down into nodes
Nodes are equipment items If nodes are too small you can loose sense of analysis and incur excessive
repetition
If nodes are too large , hard to handle and becomes confusing
How to perform HAZOP process ?
3. Prepare HAZOP outline with List of Deviations
4. Assemble HAZOP team
5. Facilitators ExplainsThe facilitator or one of the team members explains the purpose and scope of theHAZOP and sets the rules of the study
6. Process Engineer ExplainsProcess in generalImmediate Node being Hazoped
7. HAZOP Each Node Using Deviation Listed in Outline Working Through the P&ID
Produce Hazop worksheet recording the following : Cause Consequence Safeguards Action & recommendation Remarks
PHA , Hazards Identification & Risk Analysis by Nigel Hyatt
How to perform HAZOP process ?
8.At the End of HAZOP , the Facilitators Issues Preliminary HAZOP Report consisting ofAttendanceOutlineDetail reportAction/ recommendation Register.
9. Issues Final Report Giving Full Details
From BFW Header
Steam drum
Water drum
PI 7810
FT 7810
FC 7810
NC
NC
Demin Water
TI 7801
TI 7801
PT 7801
PI 7801
PI 7802
FV 7810
NC
FC 7810
LT 7810
LC 7810A
FY 7810
TW-1"-7801-A1031-H(N20A)
BW-3"-7801-D6103-H(N20B)
LT 7809
LA 7809
LSLL 7809
LALL 7809
Economizer
BV
BV BV
Boiler Feed Water for F4- 781
BV
Example of Single Node on Boiler System
NODE 1
NODE 1
Design intent: Replacement of B/Valve at D/ Stream & U/ Stream FV 7801
GUIDE DEVIATION
CAUSES CONSEQUENCES
SAFEGUARDS
REMARKS & RISK RANKING
ACTION BY/ DATE: STATUS
WORD RECOMMENDATIONS P E A R
More More Pressure BV at
Economizer partially close
1.Increased backpressure on Steam turbine2.ST tripped
PI 7801 , PI 7802 and PI 7810 (indication only
To install vibration sensor to all ST pump
L L M L 1. MTA( Q3 Fy 2010/11)
No Pressure
BV at U/stream or D/ Stream FV 7810 is fully close
1.,No water supply to steam drum leading to low level2.Boiler tripped 3.Slow down the process
LSLL 7809 To implement “ Tagging system “ to critical valve
L L M L 1.POA ( 1st May 2010 )
Less Less pressure
NA
HAZOP Worksheet