3/14/2003 Implementation Review 2
Goals for Database Architecture Changes
Simplify hardware architecture Improve performance Improve system reliability Provide better capabilities for full load testing in
development environment Improve capacity planning ability
3/14/2003 Implementation Review 3
Current Database Architecture
Independent Sun Servers 2 Operational Database Servers
Pipeline Processing/Archive Ingest/ Distribution 4 cpu server with MTI RAID Array
Archive Catalog Browsing 2 cpu server with MTI RAID Array
3/14/2003 Implementation Review 4
Current Database Architecture
2 Development/Test Database Servers Original DADS dev/test server
2 cpu server with JBOD (Just a Bunch of Disks)
Original OPUS dev/test server 2 cpu server with JBOD
3/14/2003 Implementation Review 8
Current Storage Issues
MTI RAID Arrays – Operations Starting to age – had planned to start replacing MTI
with more current technology Poor tools for performance monitoring
JBOD (Just a Bunch of Disks) - Development Much slower than RAID No fault tolerance
3/14/2003 Implementation Review 9
Current Server Issues
Sparc Servers Highly reliable Lack redundant hardware components Unable to perform throughput tests on development
systems since they are undersized compared to the operational servers.
No good performance monitoring tools
3/14/2003 Implementation Review 14
Current Database Backup Strategy
Full database backups to local DLTs Tran Log dumps to local disks Operator Intensive
3/14/2003 Implementation Review 15
New Database Architecture
Consolidate 4 servers to 3 domains on Sun Fire 15K Domain 1 – Data Processing/ Archive Ingest/ Distribution
8 CPUs – EMC Should provide significantly improved performance
• Doubles the number of CPUs• Significantly more memory• Faster RAID
Anticipate extra performance will be needed to handle:• New Instruments• Object catalogs• New MAST catalogs
3/14/2003 Implementation Review 16
New Database Architecture
Consolidate 4 servers to 3 domains on Sun Fire 15K Domain 2 – Archive Catalog Browsing
4 CPUs – EMC Should provide significantly improved performance
• Doubles the number of CPUs• Significantly more memory• Faster RAID
Anticipate extra performance will be needed to handle:• New Instruments• Object catalogs• New MAST catalogs
3/14/2003 Implementation Review 17
New Database Architecture
Consolidate 4 servers to 3 domains on Sun Fire 15K Domain 3 – Development/Test
4 CPUs - EMC Should provide improved performance
• Faster CPUs
• Significantly more memory
• RAID Improved performance will be needed to allow more thorough
throughput testing
• Domains can be reconfigured to provide 8 cpu test environment for full up test
3/14/2003 Implementation Review 19
New Database Architecture
SUN FIRE 15K Domain Config
Opus/Archive
To Test andDevelopmentEnvironment
7 Dynamically Re-Configurable Domains
EMC
EMC
EMC
EMC
EMC
EMC
OPUS/Archive OPS
EMC
Databases OPS
Databases OPS
Code Development
System Test
Database Test
OS/Security Test
3/14/2003 Implementation Review 21
New Storage Benefits
EMC RAID used for both Development, Test, Ops Same Performance across domains EMC storage easier to configure for both System
Administrators and Database Administrators Better performance monitoring tools EMC switch will allow failover of disks to an alternate
domain
3/14/2003 Implementation Review 22
New Storage Benefits
EMC allows for new database backup strategies Timefinder Snapshot Backup to Centralized tape
system May facilitate snapshot refreshes of database to
development/test server
3/14/2003 Implementation Review 23
New Server Benefits
Consolidation of Database servers Simplifies management for both SAs and DBAs
Redundant hardware systems should reduce downtime
Better performance monitoring tools Domains can be reconfigured to provide extra
resources on demand
3/14/2003 Implementation Review 24
Database Transition Plans
Storage EMC Training Underway Testing EMC with loaner Sun 4800
How to layout database partitions Database backup strategies Snapshot refreshes Backup recovery from tape
3/14/2003 Implementation Review 25
Database Transition Plans
Sun Fire 15K Server System Administrator Training Underway Testing with loaner Sun 4800
Need 64 bit Sybase to utilize >4GB Memory
• ST-ECF had experienced problems with initial release of 64 bit Sybase under v12.0
• They report having no problems with Sybase v12.5
• We will run full regression test with this version.
3/14/2003 Implementation Review 26
Database Transition Plans
Sun Fire 15K Server Testing with Sun Fire 15K
Will set up initial configuration of Dev/Test Server using database configuration parameters that are similar to existing servers.
• This will allow us to duplicate current performance requirements.
We then plan to test the benefit of large amounts of memory within the database server and to further tune configuration parameters.
• This tuning work will not impact the rollout of the other servers, since they can be brought on-line with the initial tuning configuration.
3/14/2003 Implementation Review 27
Database Transition Plans
Order of Migration Development Server (Opus Dev Server) Merge in 2nd Development/Test Server (Archive Dev
Server) onto same domain Archive Catalog Browsing Server Data Processing/ Archive Ingest/ Distribution Server
3/14/2003 Implementation Review 28
Database Contingency Plans
Original hardware will be kept available should it be necessary to roll back No trade in required for this equipment
Roll back would consist of a simple database load onto the original server Roll back will be tested.