Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Revision 0 – 16-Nov-2017Prepared for – Taylor Construction Group – ABN: 00
Proposed Industrial WarehouseDevelopment - ChulloraTaylor Construction Group16-Nov-2017
DA Cost Estimate ReportChullora Logistics Park - Building 1 and 4
AECOM Proposed Industrial Warehouse Development - ChulloraDA Cost Estimate Report – Chullora Logistics Park - Building 1 and 4
Revision 0 – 16-Nov-2017Prepared for – Taylor Construction Group – ABN: 00
DA Cost Estimate ReportChullora Logistics Park - Building 1 and 4
Client: Taylor Construction GroupABN: 00
Prepared byAECOM Australia Pty LtdLevel 21, 420 George Street, Sydney NSW 2000, PO Box Q410, QVB Post Office NSW 1230, AustraliaT +61 2 8934 0000 F +61 2 8934 0001 www.aecom.comABN 20 093 846 925
16-Nov-2017
Job No.: 00
AECOM in Australia and New Zealand is certified to ISO9001, ISO14001 AS/NZS4801 and OHSAS18001.
© AECOM Australia Pty Ltd (AECOM). All rights reserved.
The Report and the information within it is confidential and may be privileged. If you have received the Report in error please notify AECOMimmediately. You should not copy it for any purpose, or disclose its contents to any other person. The Report is qualified in its entirety by andshould be considered in the light of AECOM’s Terms of Engagement and the following:
1. The Report is provided solely for your use and benefit unless expressly permitted and then only in connection with the purpose in respect ofwhich the Report is provided. Unless required by law, you shall not provide the Report to any third party without AECOM’s prior writtenconsent, which AECOM may at its discretion grant, withhold or grant subject to conditions. Possession of the Report does not carry with itthe right to commercially reproduce, publish, sale, hire, lend, redistribute, abstract, excerpt or summarise the Report or to use the name ofAECOM in any manner without first obtaining the prior written consent of AECOM.
2. AECOM has used its reasonable endeavours to ensure that the data contained in the Report reflects the most accurate and timelyinformation available to it and is based on information that was current as of the date of the Report.
3. The Report is based on estimates, assumptions and other information developed by AECOM from its independent research effort, generalknowledge of the industry and consultations with you, your employees and your representatives. No warranty or representation is made byAECOM that any of the projected values or results contained in the Report will actually be achieved. In addition, the Report is based uponinformation that was obtained on or before the date in which the Report was prepared. Circumstances and events may occur following thedate on which such information was obtained that are beyond our control and which may affect the findings or projections contained in theReport. We may not be held responsible for such circumstances or events and specifically disclaim any responsibility therefore.
4. AECOM has relied on information provided by you and by third parties (Information Providers) to produce the Report and arrive at itsconclusions. AECOM has not verified information provided by Information Providers (unless specifically noted otherwise) and we assumeno responsibility and make no representations with respect to the adequacy, accuracy or completeness of such information. Noresponsibility is assumed for inaccuracies in reporting by Information Providers including, without limitation, by your employees or yourrepresentatives or for inaccuracies in any other data source whether provided in writing or orally used in preparing or presenting the Report.
5. In no event, regardless of whether AECOM’s consent has been provided, shall AECOM assume any liability or responsibility to any thirdparty to whom the Report is disclosed or otherwise made available.
6. The conclusions in the Report must be viewed in the context of the entire Report including, without limitation, any assumptions made anddisclaimers provided. The conclusions in this Report must not be excised from the body of the Report under any circumstances.
7. Without the prior written consent of AECOM, the Report is not to be used in conjunction with any public or private offering of securities orother similar purpose where it might be relied upon to any degree by any person other than you.
8. All intellectual property rights (including, but not limited to copyright, database rights and trade marks rights) in the Report including anyforecasts, drawings, spreadsheets, plans or other materials provided are the property of AECOM. You may use and copy suchmaterials for your own internal use only.
AECOM Proposed Industrial Warehouse Development - ChulloraDA Cost Estimate Report – Chullora Logistics Park - Building 1 and 4
Revision 0 – 16-Nov-2017Prepared for – Taylor Construction Group – ABN: 00
Table of Contents1.0 Executive Summary i2.0 Basis of the Estimate i3.0 Project Cost Summary 14.0 Budget Reconciliation 35.0 Specific Inclusions and Assumptions 36.0 Specific Exclusions 37.0 Information Used 4
Architectural Drawings 4Civil Drawings 4Hydraulic Drawings 5Landscape Drawings 5
8.0 Cost Estimate 6
Appendix 7A - Building 1 Detailed Estimate 7B - Building 4 Detailed Estimate 7
AECOM Proposed Industrial Warehouse Development - ChulloraDA Cost Estimate Report – Chullora Logistics Park - Building 1 and 4
Revision 0 – 16-Nov-2017Prepared for – Taylor Construction Group – ABN: 00
i
1.0 Executive Summary
This DA cost estimate has been prepared by AECOM Australia Pty Ltd in their capacity as Quantity Surveyors to
Taylor Construction Group for the proposed Chullora Logistics Park – Building 1A, 1B, 4A and 4B at Chullora,
NSW.
This cost estimate is based on the documentation referred to in Section 7 of this report. All assumptions and
exclusions are under section 5 and 6.
The estimate has been priced at current day rates and prices with separate allowance made for lump sum items,
no escalation has been allowed.
It is recommended that the Client maintains a suitable construction contingency to cover any additional
unforeseen costs arising during the construction phase of the project. No allowance has been included in the
estimate for construction contingency at this stage.
2.0 Basis of the Estimate
This estimate reflects the project scope as defined in the architectural, civil, landscape and hydraulic drawingsprovided. The rates have been benchmarked against similar Chullora projects.
The cost estimate has been compiled by:
- Measurement, on an elemental basis by the Australian Institute of Quantity Surveyor (AIQS)
- Inclusion of monetary allowances based on a cost per square metre basis
- Design and construction contingency has been excluded.
- Builder’s preliminaries and margin have been included in 5.5% and 3.75% of trade costs.
- Professional fees and authority fees and charges have been included in 3.5% and 0.85% ofconstruction costs
- The Goods and Services Tax (GST) has been included in 10%.
Earthwork has been excluded in this report as which is included under the earthwork package.
AECOM Proposed Industrial Warehouse Development - ChulloraDA Cost Estimate Report – Chullora Logistics Park - Building 1 and 4
Revision 0 – 16-Nov-2017Prepared for – Taylor Construction Group – ABN: 00
1
3.0 Project Cost Summary
Summary of the DA estimates for Building 1 and 4 prepared is as follows:
Building 1 Total
Substructure 684,275
Columns 277,098
Upper Floors 207,576
Staircases 25,400
Roof 1,053,575
External Walls 1,107,781
Windows 99,110
External Doors 134,450
Internal Walls 297,555
Internal Screens 6,800
Internal Doors 60,100
Wall Finishes 102,471
Floor Finishes 101,811
Ceiling Finishes 115,246
Fitments 137,948
Hydraulic Services 203,630
Mechanical Services 302,804
Fire Services 381,090
Electrical Services 394,820
BWIC 20,000
Roads and Pavements 769,307
Outbuilding 27,750
Landscaping, Fencing, Etc 495,770
External Services 928,100
Preliminaries – 5.5% 436,396
Margin – 3.75% 313,907
Total of Construction Cost 8,684,771
Professional fees – 3.5% 303,967
Authority fees and charges – 0.85% 76,404
Project Cost (Excl GST) 9,065,142
GST 906,514
Building 1 - Total Project Cost (incl GST) 9,971,656
AECOM Proposed Industrial Warehouse Development - ChulloraDA Cost Estimate Report – Chullora Logistics Park - Building 1 and 4
Revision 0 – 16-Nov-2017Prepared for – Taylor Construction Group – ABN: 00
2
Building 4 Total
Substructure 1,191,678
Columns 283,026
Roof 1,816,443
External Walls 931,255
Windows 36,040
External Doors 119,080
Internal Walls 254,675
Internal Screens 3,300
Internal Doors 16,300
Wall Finishes 71,886
Floor Finishes 52,140
Ceiling Finishes 35,812
Fitments 104,951
Hydraulic Services 171,810
Mechanical Services 190,448
Fire Services 459,430
Electrical Services 528,240
BWIC 20,000
Roads and Pavements 1,107,655
Outbuilding 27,750
Landscaping, Fencing, Etc 352,675
External Services 965,375
Preliminaries – 5.5% 480,698
Margin – 3.75% 345,775
Total of Construction Cost 9,566,441
Professional fees – 3.5% 334,825
Authority fees and charges – 0.85% 84,161
Project Cost (Excl GST) 9,985,427
GST 998,543
Building 4 - Total Project Cost (incl GST) 10,983,970
AECOM Proposed Industrial Warehouse Development - ChulloraDA Cost Estimate Report – Chullora Logistics Park - Building 1 and 4
Revision 0 – 16-Nov-2017Prepared for – Taylor Construction Group – ABN: 00
3
4.0 Budget Reconciliation
Details of the project budget are not applicable
5.0 Specific Inclusions and Assumptions
· Construction trade works
· Structural works assumed
· External works
· Outbuilding assumed
· Landscape works
· External services assumed unless specified
· Contractor preliminaries, supervision and margin
· Professional fees
· Authority fees & charges
· GST
6.0 Specific Exclusions
· Escalation beyond November 2017
· Design and construction contingencies
· Demolition works
· Earthworks
· Racking in warehouse
· Loose furniture, fixtures and equipment
· Gas supply
· Land and legal costs
· Work outside the site boundary
· Out of hours works
· Latent conditions
· Survey and setting out costs
· Traffic control and / or temporary fencing during construction
· Maintenance costs
· Finance costs and interest charges
· Other Client costs, e.g. marketing and sales costs
· Costs associated with legislative changes
AECOM Proposed Industrial Warehouse Development - ChulloraDA Cost Estimate Report – Chullora Logistics Park - Building 1 and 4
Revision 0 – 16-Nov-2017Prepared for – Taylor Construction Group – ABN: 00
4
7.0 Information Used
Architectural DrawingsBuilding 1
2523981-GA-DA-001-D 03-Nov-2017 Cover
2523981-GA-DA-002-F 03-Nov-2017 Master Site Context Plan
2523981-L1-DA-101-G 03-Nov-2017 Site and Roof Plan
2523981-L1-DA-301-E 03-Nov-2017 Ground Floor Plan
2523981-L1-DA-311-D 03-Nov-2017 Office 1A Detail; Ground and First Floor Plans
2523981-L1-DA-312-D 03-Nov-2017 Office 1B Detail; Ground and First Floor Plans
2523981-L1-DA-401-D 03-Nov-2017 Master Elevations
2523981-L1-DA-402-D 03-Nov-2017 Office 1A Detailed Elevations
2523981-L1-DA-403-B 03-Nov-2017 Office 1B Detailed Elevations
2523981-L1-DA-501-D 03-Nov-2017 Sections
2523981-L1-DA-801-D 03-Nov-2017 3D Perspectives
2523981-L1-DA-802-C 03-Nov-2017 Exterior Material and Finishes
Building 4
2523981-L4-DA-101-G 03-Nov-2017 Site and Roof Plan
2523981-L4-DA-301-G 03-Nov-2017 Ground Floor Plan
2523981-L4-DA-311-E 03-Nov-2017 Office 4A and 4B Detail; Ground Floor Plans
2523981-L4-DA-401-F 03-Nov-2017 Master Elevations
2523981-L4-DA-402-E 03-Nov-2017 Office 4A Detailed Elevations
2523981-L4-DA-403-C 03-Nov-2017 Office 4B Detailed Elevations
2523981-L4-DA-501-E 03-Nov-2017 Sections
2523981-L4-DA-801-D 03-Nov-2017 3D Perspectives
2523981-L4-DA-802-C 03-Nov-2017 Exterior Material and Finishes
Civil DrawingsBuilding 1
C012891.05-DA-10-A 29-Sept-2017 Drawing List & General Notes
C012891.05-DA-20-A 29-Sept-2017 Erosion & Sediment Control Plan
C012891.05-DA-25-A 29-Sept-2017 Erosion & Sediment Control Details
C012891.05-DA-40-A 29-Sept-2017 Stormwater Drainage Plan
C012891.05-DA-45-A 29-Sept-2017 Stormwater Drainage Details
C012891.05-DA-50-A 29-Sept-2017 Finished Level Plan
AECOM Proposed Industrial Warehouse Development - ChulloraDA Cost Estimate Report – Chullora Logistics Park - Building 1 and 4
Revision 0 – 16-Nov-2017Prepared for – Taylor Construction Group – ABN: 00
5
Building 4
C012891.06-DA-10-B 29-Sept-2017 Drawing List & General Notes
C012891.06-DA-20-B 29-Sept-2017 Erosion & Sediment Control Plan
C012891.06-DA-25-B 29-Sept-2017 Erosion & Sediment Control Details
C012891.06-DA-40-B 29-Sept-2017 Stormwater Drainage Plan
C012891.06-DA-45-B 29-Sept-2017 Stormwater Drainage Details – Sheet 1
C012891.06-DA-46-B 29-Sept-2017 Stormwater Drainage Details – Sheet 2
C012891.06-DA-50-B 29-Sept-2017 Finished Level Plan
Hydraulic DrawingsBuilding 1
2016130-H-01-P7 05-Oct-2017 Master Site Plan
2017105-FH-01-P01 05-Oct-2017 Proposed Fire Hydrant Coverage
2017105-FHR-01-P01 05-Oct-2017 Proposed Fire Hose Reel Coverage
Building 4
2017104-FH-01-P01 05-Oct-2017 Proposed Fire Hydrant Coverage
2017104-FHR-01-P01 05-Oct-2017 Proposed Fire Hose Reel Coverage
Landscape DrawingsBuilding 1
Hort-01-LS-100-A October-2017 Index Plan
Hort-01-LS-200-A October-2017 Landscape Plan
Hort-01-LS-201-A October-2017 Landscape Plan
Hort-01-LS-202-A October-2017 Landscape Plan
Hort-01-LS-203-A October-2017 Landscape Plan
Hort-01-LS-300-A
Building 4
October-2017 Plant Schedule and Details
Hort-01-LS-100-A October-2017 Index Plan
Hort-01-LS-200-A October-2017 Landscape Plan
Hort-01-LS-201-A October-2017 Landscape Plan
Hort-01-LS-202-A October-2017 Landscape Plan
Hort-01-LS-203-A October-2017 Landscape Plan
Hort-01-LS-300-A October-2017 Plant Schedule and Details
AECOM Proposed Industrial Warehouse Development - ChulloraDA Cost Estimate Report – Chullora Logistics Park - Building 1 and 4
Revision 0 – 16-Nov-2017Prepared for – Taylor Construction Group – ABN: 00
6
8.0 Cost Estimate
See Appendix A – Building 1 Detailed Estimate.Appendix B – Building 4 Detailed Estimate
AECOM Proposed Industrial Warehouse Development - ChulloraDA Cost Estimate Report – Chullora Logistics Park - Building 1 and 4
Revision 0 – 16-Nov-2017Prepared for – Taylor Construction Group – ABN: 00
7
Appendix
A – Building 1 Detailed Estimate
B – Building 4 Detailed Estimate
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Item Description Quantity Unit Rate Total
Revision : PROJECT SUMMARY
DA Estimate - Building 1
A
Construction Costs
1 Building 1 Warehouse Facility m27,772 735.14 5,713,541
External Works and Services 2,220,927
Sub-total 7,934,468
Preliminaries
2 Preliminaries %5.50 436,396
3 Margin %3.75 313,907
Sub-total 750,303
Total of Construction Costs 8,684,771
Project Costs
4 Professional fees %3.50 303,967
5 Authority fees and charges %0.85 76,404
Sub-total 380,371
GST
6 GST %10 906,514
TOTAL END COST 9,971,656
AECOM Project No. 60539394 Page 116-Nov-2017
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Revision : Building 1 Warehouse Facility
DA Estimate - Building 1
A
Item Description Elemental Qty Unit Elemental Rate Total $/m² GFA
Construction Costs
Substructure 684,275
Columns 277,098
Upper Floors 207,576
Staircases 25,400
Roof 1,053,575
External walls 1,107,781
Windows 99,110
External doors 134,450
Internal walls 297,555
Internal screens 6,800
Internal doors 60,100
Wall finishes 102,471
Floor finishes 101,811
Ceiling finishes 115,246
Fitments 137,948
Hydraulic services 203,630
Mechanical services 302,804
Fire services 381,090
Electrical services 394,820
Transport services Excl
Bwic 20,000
5,713,541TOTAL NET CONSTRUCTION COST
Page 216-Nov-2017AECOM Project No. 60539394
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Revision : Building 1 Warehouse Facility
DA Estimate - Building 1
A
Item Description Quantity Unit Rate Total
SUBSTRUCTURE
Detailed excavation
1 Detailed excavation to pad footing m370 45.00 3,150
2 Backfilling with excavated material to workingspace
m312 15.00 180
3 Disposal of excavated unsuitable material andtopsoil
m358 38.00 2,204
Pad footings
4 1200 x 1200 x 500 deep reinforced concrete padfootings :[80 no]
m358 260.00 15,080
5 Side formwork to pad footings Incl192 0
6 Reinforcement to pad footings (80Kg/m3) t4.64 2,200.00 10,208
Slab on grade
7 150 thick reinforced concrete ground slab,including attached/edge beams :[7,038 m2]
m31,056 250.00 264,000
8 Edge formwork to ground slabs not exceeding250mm high
m436 25.00 10,900
9 Formwork to setdown m101 20.00 2,020
10 Formwork sundries m27,038 5.00 35,190
11 Mesh reinforcement in two layers m27,038 20.00 140,760
12 Surface finish m27,038 4.00 28,152
13 Concrete sundries / joints m27,038 5.00 35,190
14 50mm sand blinding m27,038 4.00 28,152
15 Vapour barrier m27,038 4.00 28,152
16 100 thick base course m27,038 11.50 80,937
Termite treatment
17 Allowance for termite system - to slab perimeters Excl436 0
684,275Total - Substructure
COLUMNS
Steel columns
18 C1 - 410 UB 54 :[13 no] t9.65 4,800.00 46,334
19 C2 - 200 UC 60 :[14 no] t11.55 4,800.00 55,440
20 C3 - 250 UC 73 :[18 no] t18.07 4,800.00 86,726
21 Assume 150 SHS to offices - (from Level 1 to roof):[11 no]
t2.27 4,800.00 10,901
22 Allow for anchor bolt no224 35.00 7,840
23 Allowance for structural steel connections Incl 0
24 Allowance for surface finish Incl 0
Page 316-Nov-2017AECOM Project No. 60539394
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Revision : Building 1 Warehouse Facility
DA Estimate - Building 1
A
Item Description Quantity Unit Rate Total
25 Internal painting to steel columns Incl777 0
Concrete Columns
From Footing to Level 1
26 Concrete to 600x600mm columns :[36 no] m339 260.00 10,140
27 Formwork to sides of columns m2312 120.00 37,440
28 Allowance for formwork sundries m2312 2.00 624
29 Reinforcement to columns (assume 200kg/m3) t8.42 2,200.00 18,533
30 Internal painting to concrete columns m2312 10.00 3,120
277,098Total - Columns
UPPER FLOORS
Reinforced concrete
31 200 thick reinforced concrete suspended slab andattached beams
m3206 260.00 53,560
32 Surface finish m2835 4.00 3,340
33 Concrete sundries m2835 5.00 4,175
34 Allowance for joints m2835 5.00 4,175
Formwork
35 To soffit of slab m2835 80.00 66,800
36 To sides of slab soffit n.e 200mm thick m225 50.00 11,250
37 To sides of beams m2130 80.00 10,400
Reinforcement
38 To suspended concrete slab (110Kg/m3) t18.37 2,000.00 36,730
39 To attached beams (220Kg/m3) t8.57 2,000.00 17,146
207,576
207,576Total - Upper Floors
STAIRCASES
Steel Staircase
Internal Staircase - office 1A
40 1200mm wide structural steel staircase to FirstFloor
m/r4 2,650.00 10,600
41 Metal Handrail and balustrade incl
42 Extra over for soffit paint m/r4 75.00 300
43 Extra over for safety nosing m/r4 450.00 1,800
Internal Staircase - office 1B
44 1200mm wide structural steel staircase to FirstFloor
m/r4 2,650.00 10,600
45 Metal Handrail and balustrade incl
46 Extra over for soffit paint m/r4 75.00 300
Page 416-Nov-2017AECOM Project No. 60539394
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Revision : Building 1 Warehouse Facility
DA Estimate - Building 1
A
Item Description Quantity Unit Rate Total
47 Extra over for safety nosing m/r4 450.00 1,800
Subtotal 25,400
25,400Total - Staircases
ROOF
Structural steelwork
Warehouse Roof
48 Roof structural steelwork including connection andsurface finish
m26,610 60.00 396,595
Office Roof
49 Roof structural steelwork including connection andsurface finish
m2842 60.00 50,520
50 Allow for structural steelwork to metal pergola m29 200.00 1,800
Warehouse Awning
51 Roof structural steelwork including connection andsurface finish
m2878 60.00 52,680
Metal sheet roofing
Warehouse Roof
52 RF01 - Profiled clip fixed metal sheet roofing(colour:Zincalume) with 2.5 degree pitch andincluding flashing, capping and the like
m26,610 38.00 251,180
53 Extra over RF02 - - Profiled clip fixed metal sheetroofing (colour: Translucent white opal)
m2988 15.00 14,820
54 Wire safety mesh to roof m26,610 2.00 13,220
55 Double sided aluminum foil vapour barrier m26,610 2.00 13,220
56 75mm thick roof insulation m26,610 7.50 49,575
57 Roof safety and access system m26,610 5.00 33,050
Office Roof
58 RF03 - Colourbond "Kliplock" metal sheet roofingwith 2.5 degree pitch and including flashing,capping and the like
m2842 38.00 31,996
59 Wire safety mesh to roof m2842 2.00 1,684
60 Double sided aluminum foil vapour barrier m2842 2.00 1,684
61 75mm thick roof insulation m2842 7.50 6,315
62 Roof safety and access system m2842 5.00 4,210
Warehouse Awning
63 RF01 - Profiled clip fixed metal sheet roofing(colour:Zincalume) with 2.5 degree pitch andincluding flashing, capping and the like
m2878 38.00 33,364
64 Fc sheeting to awning soffit m2878 42.00 36,876
65 External painting to Fc soffit m2878 12.00 10,536
Roof plumbing
Page 516-Nov-2017AECOM Project No. 60539394
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Revision : Building 1 Warehouse Facility
DA Estimate - Building 1
A
Item Description Quantity Unit Rate Total
Warehouse Roof
66 Allow for roof plumbing m26,610 5.00 33,050
Office Roof
67 Allow for roof plumbing m2842 10.00 8,420
Warehouse Awning
68 Allow for roof plumbing m2878 10.00 8,780
1,053,575Total - Roof
EXTERNAL WALLS
Precast concrete wall panels
Warehouse
69 CN01 - Precast concrete Dado panel, includingframing
m2707 175.00 123,725
70 External texture acrylic paint finish colour:colourbond@windspray
m2707 15.00 10,605
Main Office and showroom - 1A
71 CN01 - Precast concrete Dado panel, includingframing
m27 175.00 1,225
72 External texture acrylic paint finish colour:colourbond@windspray
m27 15.00 105
Alucobond cladding system
Main Office and showroom - 1A
73 Structural wall framing m2701 80.00 56,080
74 CD01 - Alucobond@PE wall cladding with darkgrey metallic colour finish; including insulation,mesh and sislation
m2642 280.00 179,760
75 300mm thick aluminium wall fin with alucobondfinish system
m259 550.00 32,450
Main Office and showroom - 1B
76 Structural wall framing m2521 80.00 41,680
77 CD01 - Alucobond@PE wall cladding with darkgrey metallic colour finish; including insulation,mesh and sislation
m2203 280.00 56,840
78 CD01 Parapet wall - Alucobond@PE wall cladding( to both side ) with dark grey metallic colour finish;:[7 m]
m213 600.00 7,800
79 CD02 - Alucobond@PE wall cladding with smokesiliver metallic colour finish; including insulation,mesh and sislation
m2235 280.00 65,800
80 300mm thick aluminium wall fin with alucobondfinish system
m270 400.00 28,000
Metal wall cladding
Warehouse
Page 616-Nov-2017AECOM Project No. 60539394
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Revision : Building 1 Warehouse Facility
DA Estimate - Building 1
A
Item Description Quantity Unit Rate Total
81 Structural wall framing m23,565 80.00 285,200
82 CD03- Profiled metal wall cladding with horizontal /vertical profile, including insulation and mesh-Colourbond@shale grey
m22,950 50.00 147,500
83 CD04- Profiled metal wall cladding with horizontal /vertical profile, including insulation and mesh-Colourbond@Monument
m2615 50.00 30,750
84 Allow for external logo "Corporate" fixed to externalwall - at North elevation - Grid 1H
No1 6,000.00 6,000
85 Allow for external logo "Corporate" fixed to externalwall - at North elevation - Grid 1B
No1 3,000.00 3,000
86 Allow for external logo "Corporate" fixed to externalwall - at North elevation - Grid 1.2-1.3
No1 3,000.00 3,000
Damp proof course
87 Allow for damp proof course to perimeter ofbuilding
m436 15.00 6,540
Miscellaneous and sundry works
88 Miscellaneous and sundry works %2.0 1,086,060.00 21,721
1,107,781Total - External walls
WINDOWS
Aluminum framed windows
Main Office - 1A
89 Aluminum frame window, with powder coatedfinish, double glazed
m284 450.00 37,800
Main Office - 1B
90 Aluminum frame window, with powder coatedfinish, double glazed :[19 no]
m2103 450.00 46,350
Window furnishing
Main Office 1A and 1B
91 Allow for window roller blind m2187 80.00 14,960
99,110Total - Windows
EXTERNAL DOORS
Aluminum framed glazed doors
Glazed Doors
Main Office - 1A
92 Aluminum framed glazed single doors no1 1,800.00 1,800
93 Allow for safety decals m1 50.00 50
Hardware
94 To single door no1 450.00 450
95 Extra over for overhead door closer no1 200.00 200
Page 716-Nov-2017AECOM Project No. 60539394
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Revision : Building 1 Warehouse Facility
DA Estimate - Building 1
A
Item Description Quantity Unit Rate Total
Main Office - 1B
96 Aluminum framed glazed double doors no3 2,150.00 6,450
97 Allow for safety decals m6 50.00 300
Hardware
98 To double door no6 900.00 5,400
99 Extra over for overhead door closer no6 200.00 1,200
Glazed folding door
Main Office - 1A
100 Aluminum framed folding glazed doors to outdoorarea :[1 no]
m212 850.00 10,200
101 Allow for safety decals m6 50.00 300
Automatic glazed sliding door
Main Office - 1A
102 Glazed double sliding door to lobby no1 8,500.00 8,500
103 Allow for safety decals m2 50.00 100
104 Extra over for automatic system no1 5,000.00 5,000
Timber door and frame
Doors
105 Single timber fire door and frame to warehouse no6 800.00 4,800
Hardware
106 To single door no6 450.00 2,700
Paint
107 To single door no6 250.00 1,500
Roller shutter doors
Warehouse
108 RSD - 3000 x 4500mm high motorized roller shutterdoor
no4 4,750.00 19,000
109 RSD - 6000 x 5800 high motorized roller shutterdoor
no7 9,500.00 66,500
134,450Total - External doors
INTERNAL WALLS
Precast concrete wall panels
Main Office and showroom - 1A
110 150 thick precast concrete wall panels, includingframing to lift shaft walls
m260 175.00 10,500
Main Office - 1B
Page 816-Nov-2017AECOM Project No. 60539394
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Revision : Building 1 Warehouse Facility
DA Estimate - Building 1
A
Item Description Quantity Unit Rate Total
111 150 thick precast concrete wall panels, includingframing to lift shaft walls
m257 175.00 9,975
Reinforced blockwork
Main Office and showroom - 1A
112 190 thick reinforced concrete blockwork wall m2348 150.00 52,200
113 Allow for bond beam m10 50.00 500
114 Allow for movement and control joints m2348 10.00 3,480
Main Office - 1B
115 190 thick reinforced concrete blockwork wall m2158 150.00 23,700
116 Allow for bond beam m3 50.00 150
117 Allow for movement and control joints m257 10.00 570
Warehouse
118 Inter-tenancy wall - 190 thick reinforced concreteblockwork wall
m2302 150.00 45,300
Plasterboard lining and partitions
Main Office and showroom - 1A
119 Plasterboard on furring channels to internal skin ofexternal walls
m2299 40.00 11,960
120 Plasterboard on furring channels to block andconcrete walls
m2390 40.00 15,600
121 Plasterboard on furring channels to Lift shaft wall m260 40.00 2,400
122 Metal stud partition with plasterboard each side,including insulation
m2409 105.00 42,945
123 Extra over for moisture resistant plasterboard m2274 15.00 4,110
124 Allow for noggings m21,158 10.00 11,580
Main Office - 1B
125 Plasterboard on furring channels to internal skin ofexternal walls
m2209 40.00 8,360
126 Plasterboard on furring channels to block andconcrete walls
m2130 40.00 5,200
Plasterboard on furring channels to Lift shaft wall 57 40.00 2,280
127 Metal stud partition with plasterboard each side,including insulation
m2209 105.00 21,945
128 Extra over for moisture resistant plasterboard m2130 15.00 1,950
129 Allow for noggings m2605 10.00 6,050
Toilet partitions
Main Office and showroom - 1A
GF
Page 916-Nov-2017AECOM Project No. 60539394
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Revision : Building 1 Warehouse Facility
DA Estimate - Building 1
A
Item Description Quantity Unit Rate Total
130 Set of 2 toilet/shower cubicles comprising 1 xdivision panel + 2 doors + 1 front panels + 2 nibpanels + aluminum head rails + feet and channels+ gravity hinges + indicator bolt
No1 2,400.00 2,400
131 Set of 3 toilet /shower cubicles comprising 2 xdivision panels + 3 doors + 2 front panels + 2 nibpanels + aluminum head rails + feet and channels+ gravity hinges + indicator bolts
No1 3,600.00 3,600
Level 1
132 Set of 2 toilet cubicles comprising 1 x division panel+ 2 doors + 1 front panels + 2 nib panels +aluminum head rails + feet and channels + gravityhinges + indicator bolt
No2 2,400.00 4,800
Main Office - 1B
GF
133 Set of 1 toilet cubicles comprising 1 x division panel+ 1 doors + aluminum head rails + feet andchannels + gravity hinges + indicator bolt
No2 1,200.00 2,400
Level 1
134 Set of 2 toilet cubicles comprising 1 x division panel+ 2 doors + 2 front panels + 2 nib panels +aluminum head rails + feet and channels + gravityhinges + indicator bolt
No1 2,400.00 2,400
135 Set of 1 toilet cubicles comprising 1 x division panel+ 1 doors + aluminum head rails + feet andchannels + gravity hinges + indicator bolt
No1 1,200.00 1,200
297,555Total - Internal walls
INTERNAL SCREENS
Internal windows
Main Office and showroom - 1A
136 Aluminium framed glazed internal fixed windows :[5no]
m28 500.00 4,000
Glazed partitions
Main Office - 1A
137 Internal glazed screen to meeting m26 450.00 2,700
138 Safety decal m2 50.00 100
6,800Total - Internal screens
INTERNAL DOORS
Timber door and frame
Doors
Main Office and showroom - 1A
GF
139 Single timber fire door and frame no3 800.00 2,400
140 Single timber door and frame no6 650.00 3,900
Page 1016-Nov-2017AECOM Project No. 60539394
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Revision : Building 1 Warehouse Facility
DA Estimate - Building 1
A
Item Description Quantity Unit Rate Total
141 Double timber fire door and frame no1 1,500.00 1,500
Level 1
142 Single timber fire door and frame no1 800.00 800
143 Single timber door and frame no12 650.00 7,800
144 Double timber door and frame no1 1,200.00 1,200
Main Office - 1B
GF
145 Single timber fire door and frame no1 800.00 800
146 Single timber door and frame no2 650.00 1,300
Level 1
147 Single timber door and frame no7 800.00 5,600
Hardware
148 To single fire door no5 550.00 2,750
149 To single door no27 450.00 12,150
150 To double fire door no1 1,100.00 1,100
151 To double door no1 900.00 900
Paint
152 To single door no32 250.00 8,000
153 To double door no2 350.00 700
Internal Glazed doors
Main Office - 1A
154 1500 x 2100mm high glazed single sliding door tobreakout area
no1 3,500.00 3,500
155 1800 x 2100mm high glazed double swing door toshowroom
no1 5,500.00 5,500
156 Allow for safety decals m4 50.00 200
60,100Total - Internal doors
WALL FINISHES
Ceramic wall tiles
Main Office and showroom - 1A
157 Ceramic wall tiles to WCs and cleaner m2211 100.00 21,100
Main Office - 1B
158 Ceramic wall tiles to WCs and cleaner m2100 100.00 10,000
Waterproofing
Main Office and showroom - 1A
159 Waterproofing to shower walls m240 40.00 1,600
Main Office - 1B
160 Waterproofing to shower walls m28 40.00 320
Page 1116-Nov-2017AECOM Project No. 60539394
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Revision : Building 1 Warehouse Facility
DA Estimate - Building 1
A
Item Description Quantity Unit Rate Total
Wall Rendering
Main Office and showroom - 1A
161 To 190 thick reinforced concrete blockwork wall -ond side
m2348 35.00 12,180
Main Office - 1B
162 To 190 thick reinforced concrete blockwork wall -one side
m2158 35.00 5,530
Warehouse
163 Internal rendering to blockwalls - 2 sides m2603 35.00 21,105
Paint
Main Office and showroom - 1A
164 To rendered wall m2348 12.00 4,176
165 To plasterboard walls m2939 12.00 11,268
Main Office - 1B
166 To rendered wall m2158 12.00 1,896
167 To plasterboard walls m2505 12.00 6,060
Warehouse
168 To rendered wall m2603 12.00 7,236
102,471Total - Wall finishes
FLOOR FINISHES
Recessed door mats
Main Office and showroom - 1A
169 Recessed door mat to main door entrance no3 1,500.00 4,500
Main Office - 1B
170 Recessed door mat to main door entrance no2 1,500.00 3,000
Carpet
Main Office and showroom - 1A
171 Carpet tiles m2482 50.00 24,100
172 Aluminium skirting m321 15.00 4,815
Main Office - 1B
173 Carpet tiles m2365 50.00 18,250
174 Extra over Feature tiling to reception / waiting area m230 125.00 3,750
175 Aluminium skirting m178 15.00 2,670
Vinyl flooring
Main Office and showroom - 1A
176 Non-slip vinyl flooring m266 50.00 3,300
Page 1216-Nov-2017AECOM Project No. 60539394
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Revision : Building 1 Warehouse Facility
DA Estimate - Building 1
A
Item Description Quantity Unit Rate Total
177 Coved skirting m62 25.00 1,550
Main Office - 1B
178 Non-slip vinyl flooring m272 50.00 3,600
179 Coved skirting m64 25.00 1,600
Ceramic tiling
Main Office and showroom - 1A
180 Ceramic tiling m293 100.00 9,300
181 Extra over Feature tiling to reception / waiting area excl 80.00
Main Office - 1B
182 Ceramic tiling m255 100.00 5,500
183 Extra over Feature tiling to reception / waiting area excl 80.00
Waterproofing
Main Office and showroom - 1A
184 Waterproofing to wet areas m289 40.00 3,560
185 Waterproofing membrane upturn to floortermination
m120 15.00 1,800
Main Office - 1B
186 Waterproofing to wet areas m255 40.00 2,200
187 Waterproofing membrane upturn to floortermination
m76 15.00 1,140
Concrete sealer
Main Office and showroom - 1A
188 Show room m2196 6.00 1,176
Warehouse
189 Concrete sealer to warehouse Excl6,373
Ducted skirting
Warehouse
190 Ducted skirting Excl414
Tactile tiles
Main Office and showroom - 1A
191 Allow for stainless steel tactile tiles m23 1,000.00 3,000
Main Office - 1B
192 Allow for stainless steel tactile tiles m23 1,000.00 3,000
101,811Total - Floor finishes
CEILING FINISHES
Page 1316-Nov-2017AECOM Project No. 60539394
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Revision : Building 1 Warehouse Facility
DA Estimate - Building 1
A
Item Description Quantity Unit Rate Total
EXTERNAL CEILING
Main Office - 1B
193 Allow for 6mm FC lining to soffit of balcony m212 95.00 1,140
Paint to ceiling
Main Office - 1B
194 Painting to FC ceiling m212 10.00 120
195 Allow paint to external concrete soffit m2246 10.00 2,460
INTERNAL CEILING
Suspended ceiling
Main Office and showroom - 1A
196 Prefinished acoustic tiled ceiling includingsuspended framing system
m2552 45.00 24,840
197 13mm flush set plasterboard ceiling, includingsuspended framing
m2285 65.00 18,525
198 Extra over for moisture resistant plasterboard inwet areas
m289 5.00 445
199 Acoustic ceiling insulation m2837 15.00 12,555
200 EO above for bulkheads - say 10% of ceiling ares m284 150.00 126
201 Shadowline m550 12.00 6,600
202 Allowance for access panels to ceilings no6 300.00 1,800
Main Office - 1B
203 Prefinished acoustic tiled ceiling includingsuspended framing system
m2437 45.00 19,665
204 13mm flush set plasterboard ceiling, includingsuspended framing
m244 80.00 3,520
205 Extra over for moisture resistant plasterboard inwet areas
m244 5.00 220
206 Acoustic ceiling insulation m2481 25.00 12,025
207 EO above for bulkheads - say 10% of ceiling ares m248 150 72
208 Shadowline m317 12.00 3,804
209 Allowance for access panels to ceilings no6 300.00 1,800
Paint to ceiling
Main Office and showroom - 1A
210 To plasterboard ceiling m2285 12.00 3,420
211 To plasterboard bulkhead m284 12.00 1,004
Main Office - 1B
212 To plasterboard ceiling m244 12.00 528
213 To plasterboard bulkhead m248 12.00 577
115,246Total - Ceiling finishes
Page 1416-Nov-2017AECOM Project No. 60539394
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Revision : Building 1 Warehouse Facility
DA Estimate - Building 1
A
Item Description Quantity Unit Rate Total
FITMENTS
Glazed Balusterade
Main Office and showroom - 1A
214 Assume 1200mm high glazed balustrde at level 1void
m11 950.00 10,450
Splashback
Main Office and showroom - 1A
215 600mm high glass splashback above sinkcupboard
m5 450.00 2,250
Main Office and showroom - 1A
216 600mm high glass splashback above sinkcupboard
m10 450.00 4,500
Joinery
Office 1A
217 Kitchen sink cupboard with overhead storagecupboard :[3 no]
m11 1,200.00 13,200
218 Kitchen island cupboard with benchtop :[1 no] m4 1,500.00 6,000
219 Full height cupboard m3 1,200.00 3,600
Office 1B
220 Reception counter :[1 no] m6 1,200.00 7,200
221 Kitchen sink cupboard with overhead storagecupboard :[2 no]
m9 1,200.00 10,800
Urinal Panel
Office 1A
222 Wall mounted urinal panel no4 250.00 1,000
Office 1B
223 Wall mounted urinal panel no3 250.00 750
Sanitary fittings
Office 1A
224 Toilet paper holder no9 50.00 450
225 Hand dryer no5 250.00 1,250
226 Soap dispenser no10 150.00 1,500
227 Coat hooks no13 20.00 260
228 Grab rails no2 350.00 700
229 Soap dish no3 100.00 300
230 Stainless steel fixed shelf no1 100.00 100
231 Shower folding seat no1 450.00 450
Page 1516-Nov-2017AECOM Project No. 60539394
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Revision : Building 1 Warehouse Facility
DA Estimate - Building 1
A
Item Description Quantity Unit Rate Total
232 Shower curtain no1 250.00 250
233 Mirror no10 450.00 4,500
Office 1B
234 Toilet paper holder no6 50.00 300
235 Hand dryer no3 250.00 750
236 Soap dispenser no1 150.00 150
237 Coat hooks no6 20.00 120
238 Grab rails no1 350.00 350
239 Soap dish no1 100.00 100
240 Stainless steel fixed shelf no1 100.00 100
241 Shower folding seat no1 450.00 450
242 Shower curtain no1 250.00 250
243 Mirror no7 450.00 3,150
Bollards
244 Allow for 800mm high concrete bollard with yellowcolour safety paint
Item1 15,000.00 15,000
Metalwork
245 Access ladder to roof (allowance) no2 2,750.00 5,500
246 Metal angles to dock edge m54 175.00 9,450
247 Internal column protection to warehouse Item1 10,000.00 10,000
Dock Bumper
248 3000mm long resilient laminated rubber dockbumper; horizontal
no4 600.00 2,400
249 6000mm long resilient laminated rubber dockbumper; horizontal
no7 1,000.00 7,000
Building and Statutory Signage
250 Offices and amenities m21,399 5.00 6,995
251 Warehouse m26,373 1.00 6,373
Miscellaneous and sundry works
252 Loose furniture Excl
137,948Total - Fitments
HYDRAULIC SERVICES
Hydraulic services with sanitary ware
253 To office area m21,399 100.00 139,900
254 To warehouse m26,373 10.00 63,730
Page 1616-Nov-2017AECOM Project No. 60539394
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Revision : Building 1 Warehouse Facility
DA Estimate - Building 1
A
Item Description Quantity Unit Rate Total
203,630Total - Hydraulic services
MECHANICAL SERVICES
Air conditioning
255 To offices m21,399 180.00 251,820
Smoke extraction and ventilation system
256 To warehouse m26,373 8.00 50,984
302,804Total - Mechanical services
FIRE SERVICES
Sprinklers
257 To offices m21,399 85.00 118,915
258 To warehouse m26,373 25.00 159,325
Fire hydrants
259 Fire hydrants item1 25,000 25,000
Fire hose reels
260 Fire hose reels item1 25,000 25,000
Dry fire services
261 To offices m21,399 15.00 20,985
262 To warehouse m26,373 5.00 31,865
381,090Total - Fire services
ELECTRICAL SERVICES
Electrical/Communications and security
263 To offices m21,399 100.00 139,900
264 To warehouse m26,373 40.00 254,920
394,820Total - Electrical services
TRANSPORT SERVICES
Dock Levellers
265 Dock Leveller to dock Excl1 0
ExclTotal - Transport services
BWIC
266 Bwic item1 20,000 20,000
20,000Total - Bwic
Page 1716-Nov-2017AECOM Project No. 60539394
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Revision : External Works and Services
DA Estimate - Building 1
A
Item Description Elemental Qty Unit Elemental Rate Total $/m² GFA
Roads and pavements 769,307
Outbuilding 27,750
Landscaping, fencing etc 495,770
External services 928,100
2,220,927TOTAL NET CONSTRUCTION COST
Page 1816-Nov-2017AECOM Project No. 60539394
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Revision : External Works and Services
DA Estimate - Building 1
A
Item Description Quantity Unit Rate Total
ROADS AND PAVEMENTS
Concrete hardstanding area
1 150 thick reinforced concrete pavement (heavyduty) on 150 thick base course
m24,580 95.00 435,100
2 Extra over for truck loading ramp down area m2522 120.00 62,640
Open car park
3 30 thick asphalt pavement (light duty) on 150 thickbase course
m21,589 68.00 108,052
4 Road kerb m859 65.00 55,835
5 Wheelstops no49 100.00 4,900
Concrete footpaths
6 100 thick reinforced concrete pavement on 150thick base course
m2496 85.00 42,160
7 Kerb ramp no2 1,500.00 3,000
Paver
8 Concrete paver to outdoor area m2231 120.00 27,720
Line marking
9 Carpark no49 100.00 4,900
10 Directional arrow item1 5,000.00 5,000
Road signage
11 Road signage item1 5,000.00 5,000
Vehicular crossover
12 Vehicular crossover no3 5,000.00 15,000
769,307Total - Roads and pavements
OUTBUILDING
Outbuilding
13 Pump house - base building m237 750.00 27,750
27,750Total - Outbuilding
LANDSCAPING, FENCING ETC
Soft landscaping
14 300 thick topsoil m23,692 10.00 36,920
15 MD - white Feather Honey Myrtle - 100L no4 250.00 1,000
16 MD - white Feather Honey Myrtle - 45L no52 120.00 6,240
17 EF - Red Ironbark - 45L no40 120.00 4,800
18 AD - Black wattle - 45L no4 120.00 480
19 Mn - Ball Honey Myrtle - 5L (3 no. / m2) no759 20.00 15,180
20 Shrubs & ground covers - 130mm (3 no. /m2) no9,558 5.00 47,790
21 50mm mulch m23,692 5.00 18,460
22 Establishment and maintenance item1 10,000 10,000
Irrigation system
Page 1916-Nov-2017AECOM Project No. 60539394
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Revision : External Works and Services
DA Estimate - Building 1
A
Item Description Quantity Unit Rate Total
23 Irrigation system item1 25,000 25,000
Quartz gravel mulch
24 Geo fabric material under pebble mulch m229 5.00 145
25 75mm thick selected pebble mulch m229 25.00 725
26 Galvanised patio tubing nailed and stabalized withspicks
m21 10.00 210
Hard landscaping
27 Tree-tie with jarrah stake no100 45.00 4,500
28 Bike rack item1 2,500.00 2,500
29 Security kiosk to car entry / exit (allowance) no1 5,000.00 5,000
Fencing
30 Fence (Type 1) - '2400 high black anodisedpalisade security fencing
m341 270.00 92,070
31 Fench (Type 2) - 2100 high chainwire fence with 3x strands of barbed wire above
m193 50.00 9,650
32 Extra over for single security gate to fence type 1 no1 3,500.00 3,500
33 Car entry and exit gates no4 7,500.00 30,000
34 Automatic tracked palisade operated gate no1 20,000.00 20,000
Retaining Walls
35 Average 1300mm high retaining block wallsincluding capping, footings, waterproofing,aggragate drain and the likegranular backfilling, :[98 m]
m2127 500.00 63,500
36 Extra over for safety barrier to top of retaining wall m98 200.00 19,600
37 Average 2000mm high retaining block wallsincluding capping, footings, waterproofing,aggragate drain and the likegranular backfilling, :[123 m]
m2245 300.00 73,500
Signage
38 Pylon sign no1 5,000.00 5,000
495,770Total - Landscaping, fencing etc
EXTERNAL SERVICES
Electrical
39 Connection to existing services item1 20,000.00 20,000
40 External lighting item1 75,000.00 75,000
41 HV cabling and associated works item1 200,000.00 200,000
42 Padmount power kiosk no1 50,000.00 50,000
43 Sub-station - included in building 3 Note
Communications
44 Connection to existing services item1 15,000.00 15,000
Water
45 Connection to existing services item1 15,000.00 15,000
Page 2016-Nov-2017AECOM Project No. 60539394
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Revision : External Works and Services
DA Estimate - Building 1
A
Item Description Quantity Unit Rate Total
Fire
46 Connection to existing services item1 15,000.00 15,000
47 10.18m dia fire sprinkler tank and pump allowance item1 100,000.00 100,000
Sewer
48 Connection to existing services item1 20,000.00 20,000
Stormwater
49 SW - stormwater drainage m489 250.00 122,250
50 RW - roof water drainage m319 150.00 47,850
51 GD - Grated drain m56 250.00 14,000
52 SGGP - Single grated gully pit no14 2,500.00 35,000
53 SJP - Sealed junction pit no12 3,500.00 42,000
54 GPT no2 10,000.00 20,000
55 Connection to existing services item1 25,000.00 25,000
56 4.85m dia rainwater tank no1 12,000.00 12,000
57 OSD underground tank no2 50,000.00 100,000
928,100Total - External services
Page 2116-Nov-2017AECOM Project No. 60539394
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Item Description Quantity Unit Rate Total
Revision : PROJECT SUMMARY
DA Estimate - Building 4
A
Construction Costs
1 Building 4 Warehouse Facility m212,411 506.53 6,286,513
External Works and Services 2,453,455
Sub-total 8,739,968
Preliminaries
2 Preliminaries %5.50 480,698
3 Margin %3.75 345,775
Sub-total 826,473
Total of Construction Costs 9,566,441
Project Costs
4 Professional fees %3.50 334,825
5 Authority fees and charges %0.85 84,161
Sub-total 418,986
GST
6 GST %10 998,543
TOTAL END COST 10,983,970
AECOM Project No. 60539394 Page 116-Nov-2017
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Revision : Building 4 Warehouse Facility
DA Estimate - Building 4
A
Item Description Elemental Qty Unit Elemental Rate Total $/m² GFA
Construction Costs
Substructure 1,191,678
Columns 283,026
Roof 1,816,443
External walls 931,255
Windows 36,040
External doors 119,080
Internal walls 254,675
Internal screens 3,300
Internal doors 16,300
Wall finishes 71,886
Floor finishes 52,140
Ceiling finishes 35,812
Fitments 104,951
Hydraulic services 171,810
Mechanical services 190,448
Fire services 459,430
Electrical services 528,240
Transport services Excl
Bwic 20,000
6,286,513TOTAL NET CONSTRUCTION COST
Page 216-Nov-2017AECOM Project No. 60539394
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Revision : Building 4 Warehouse Facility
DA Estimate - Building 4
A
Item Description Quantity Unit Rate Total
SUBSTRUCTURE
Detailed excavation
1 Detailed excavation to pad footing m387 45.00 3,915
2 Backfilling with excavated material to workingspace
m315 15.00 225
3 Disposal of excavated unsuitable material andtopsoil
m372 38.00 2,736
Pad footings
4 1200 x 1200 x 500 deep reinforced concrete padfootings :[100 no]
m372 260.00 18,720
5 Side formwork to pad footings Incl240 0
6 Reinforcement to pad footings (80Kg/m3) t5.76 2,200.00 12,672
Slab on grade
7 150 thick reinforced concrete ground slab,including attached/edge beams :[12,507 m2]
m31,877 250.00 469,250
8 Edge formwork to ground slabs not exceeding250mm high
m519 25.00 12,975
9 Formwork to setdown m103 20.00 2,060
10 Formwork sundries m212,507 5.00 62,535
11 Mesh reinforcement in two layers m212,507 20.00 250,140
12 Surface finish m212,507 4.00 50,028
13 Concrete sundries / joints m212,507 5.00 62,535
14 50mm sand blinding m212,507 4.00 50,028
15 Vapour barrier m212,507 4.00 50,028
16 100 thick base course m212,507 11.50 143,831
Termite treatment
17 Allowance for termite system - to slab perimeters Excl519 0
1,191,678Total - Substructure
COLUMNS
Steel columns
18 C1 - 410 UB 54 :[20 no] t11.34 4,800.00 54,432
19 C2 - 200 UC 60 :[21 no] t17.26 4,800.00 82,858
20 C3 - 250 UC 73 :[26 no] t22.97 4,800.00 110,237
21 Assume 150 SHS to offices :[33 no] t4.48 4,800.00 21,499
22 Allow for anchor bolt no400 35.00 14,000
23 Allowance for structural steel connections Incl 0
24 Allowance for surface finish Incl 0
25 Internal painting to steel columns Incl1,190 0
Page 316-Nov-2017AECOM Project No. 60539394
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Revision : Building 4 Warehouse Facility
DA Estimate - Building 4
A
Item Description Quantity Unit Rate Total
283,026Total - Columns
ROOF
Structural steelwork
Warehouse Roof
26 Roof structural steelwork including connection andsurface finish
m212,448 60.00 746,870
Office Roof
27 Roof structural steelwork including connection andsurface finish
m2470 60.00 28,200
East and West Warehouse Awning
28 Roof structural steelwork including connection andsurface finish
m21,531 60.00 91,860
Metal sheet roofing
Warehouse Roof
29 RF01 - Profiled clip fixed metal sheet roofing(colour:Zincalume) with 2.5 degree pitch andincluding flashing, capping and the like
m212,448 38.00 473,024
30 Extra over RF02 - - Profiled clip fixed metal sheetroofing (colour: Translucent white opal)
m21,492 15.00 22,380
31 Wire safety mesh to roof m212,448 2.00 24,896
32 Double sided aluminum foil vapour barrier m212,448 2.00 24,896
33 75mm thick roof insulation m212,448 7.50 93,360
34 Roof safety and access system m212,448 5.00 62,240
Office Roof
35 RF03 - Colourbond "Kliplock" metal sheet roofingwith 2.5 degree pitch and including flashing,capping and the like
m2470 38.00 17,860
36 Wire safety mesh to roof m2470 2.00 940
37 Double sided aluminum foil vapour barrier m2470 2.00 940
38 75mm thick roof insulation m2470 7.50 3,525
39 Roof safety and access system m2470 5.00 2,350
East and West Warehouse Awning
40 RF01 - Profiled clip fixed metal sheet roofing(colour:Zincalume) with 2.5 degree pitch andincluding flashing, capping and the like
m21,531 38.00 58,178
41 Fc sheeting to awning soffit m21,531 42.00 64,302
42 External painting to Fc soffit m21,531 12.00 18,372
Roof plumbing
Warehouse Roof
43 Allow for roof plumbing m212,448 5.00 62,240
Office Roof
Page 416-Nov-2017AECOM Project No. 60539394
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Revision : Building 4 Warehouse Facility
DA Estimate - Building 4
A
Item Description Quantity Unit Rate Total
44 Allow for roof plumbing m2470 10.00 4,700
East and West Warehouse Awning
45 Allow for roof plumbing m21,531 10.00 15,310
1,816,443Total - Roof
EXTERNAL WALLS
Precast concrete wall panels
Warehouse
46 CN01 - Precast concrete Dado panel, includingframing
m2854 175.00 149,450
47 External texture acrylic paint finish colour:colourbond@windspray
m2854 15.00 12,810
Alucobond cladding system
Main Office
48 Structural wall framing m2386 80.00 30,880
49 CD01 - Alucobond@PE wall cladding with darkgrey metallic colour finish; including insulation,mesh and sislation
m2123 280.00 34,440
50 CD02 - Alucobond@PE wall cladding with smokesilver metallic colour finish; including insulation,mesh and sislation
m2263 280.00 73,640
51 300mm thick aluminum wall fin with alucobondfinish system
m243 550.00 23,650
Metal wall cladding
Warehouse
52 Structural wall framing m24,163 80.00 333,040
53 CD03- Profiled metal wall cladding with horizontal /vertical profile, including insulation and mesh-Colourbond@shale grey
m22,725 50.00 136,250
54 CD04- Profiled metal wall cladding with horizontal /vertical profile, including insulation and mesh-Colourbond@Monument
m21,438 50.00 71,900
55 Allow for external logo "Corporate" fixed to externalwall
no2 9,000.00 18,000
External glazed screen
Main Office
56 GL01 - Full height aluminum framed glazed wall(super blue 40)
m247 450.00 21,150
Damp proof course
57 Allow for damp proof course to perimeter ofbuilding
m519 15.00 7,785
Page 516-Nov-2017AECOM Project No. 60539394
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Revision : Building 4 Warehouse Facility
DA Estimate - Building 4
A
Item Description Quantity Unit Rate Total
Miscellaneous and sundry works
58 Miscellaneous and sundry works %2.0 912,995.00 18,260
931,255Total - External walls
WINDOWS
Aluminium framed windows
Main Office
59 Aluminium frame window, with powder coatedfinish, double glazed :[3 no]
m268 450.00 30,600
Window furnishing
Main Office
60 Allow for window roller blind m268 80.00 5,440
36,040Total - Windows
EXTERNAL DOORS
Aluminum framed glazed doors
Glazed Doors
Main Office
61 Aluminum framed glazed double doors no2 2,150.00 4,300
62 Allow for safety decals m4 50.00 180
Hardware
63 To double door no2 900.00 1,800
64 Extra over for overhead door closer no4 200.00 800
Timber door and frame
Doors
Warehouse
65 Single timber fire door and frame no5 800.00 4,000
Hardware
66 To single door no5 450.00 2,250
Paint
67 To single door no5 250.00 1,250
Roller shutter doors
Warehouse
68 3000 x 4500mm high motorized roller shutter door no6 4,750.00 28,500
69 6000 x 5800mm high motorized roller shutter door no8 9,500.00 76,000
119,080Total - External doors
INTERNAL WALLS
Page 616-Nov-2017AECOM Project No. 60539394
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Revision : Building 4 Warehouse Facility
DA Estimate - Building 4
A
Item Description Quantity Unit Rate Total
Reinforced blockwork
Main Office
70 190 thick reinforced concrete blockwork wall m2230 150.00 34,500
71 Allow for bond beam m6 50.00 300
72 Allow for movement and control joints m2230 10.00 2,300
Warehouse
73 Inter-tenancy wall - 190 thick reinforced concreteblockwork wall
m21,055 150.00 158,250
Plasterboard lining and partitions
Main Office
74 Plasterboard on furring channels to internal skin ofexternal walls
m2155 40.00 6,200
75 Metal stud partition with both side plasterboard,including insulation
m2260 105.00 27,300
76 Extra over for moisture resistant plasterboard m2245 15.00 3,675
77 Allow for noggings m2415 10.00 4,150
Warehouse
78 Furring channels with 2 layers fire resistantplasterboard lining to internal face of external walls
Excl 0
Toilet partitions
Main Office
79 Set of single toilet cubicle comprising 1 x sidepanel + 1 door + 2 nib panels + aluminum head rail+ feet and channel + gravity hinges + indicator bolt
No1.00 1,200.00 1,200
80 Set of 4 toilet / shower cubicles comprising 3 xdivision panels + 4 doors + 3 front panels + 2 nibpanels + aluminum head rails + feet and channels+ gravity hinges + indicator bolts
No2.00 4,800.00 9,600
81 Set of 3 toilet cubicles comprising 2 x divisionpanels + 3 doors + 2 front panels + 2 nib panels +aluminum head rails + feet and channels + gravityhinges + indicator bolts
No2.00 3,600.00 7,200
254,675Total - Internal walls
INTERNAL SCREENS
Glazed partitions
Main Office
82 Internal glazed screen to meeting m27 450.00 3,150
83 Safety decal m3 50.00 150
3,300Total - Internal screens
INTERNAL DOORS
Timber door and frame
Page 716-Nov-2017AECOM Project No. 60539394
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Revision : Building 4 Warehouse Facility
DA Estimate - Building 4
A
Item Description Quantity Unit Rate Total
Doors
Main Office
84 Single timber fire door and frame no2 800.00 1,600
85 Single timber door and frame no8 650.00 5,200
86 Single timber service door and frame no2 450.00 900
Hardware
87 To single fire door no2 550.00 1,100
88 To single door no10 450.00 4,500
Paint
89 To single door no12 250.00 3,000
16,300Total - Internal doors
WALL FINISHES
Ceramic wall tiles
Main Office
90 Ceramic wall tiles to WCs and cleaner m2191 100.00 19,100
Waterproofing
Main Office
91 Waterproofing to shower walls m215 40.00 600
Wall Rendering
Main Office
92 Internal rendering to blockwalls m2230 35.00 8,050
Paint
Main Office
93 To plasterboard walls m2484 12.00 5,808
94 To rendered wall m2230 12.00 2,760
Warehouse
95 To concrete walls - internal face m2854 12.00 10,248
96 To - Intertenancy wall - 190 thick reinforcedconcrete blockwork wall
m22,110 12.00 25,320
71,886Total - Wall finishes
FLOOR FINISHES
Recessed door mats
Main Office
97 Recessed door mat to main door entrance no2 1,500.00 3,000
Carpet
Main Office
Page 816-Nov-2017AECOM Project No. 60539394
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Revision : Building 4 Warehouse Facility
DA Estimate - Building 4
A
Item Description Quantity Unit Rate Total
98 Carpet tiles m2401 50.00 20,050
99 Aluminium skirting m228 15.00 3,420
Vinyl flooring
Main Office
100 Non-slip vinyl flooring m29 50.00 450
101 Coved skirting m16 25.00 405
Ceramic tiling
Main Office
102 Feature tiling to reception / waiting area (5.5 x 6) m233 150.00 4,950
103 Ceramic tiling to WCs and cleaner m288 100.00 8,800
Waterproofing
104 Waterproofing to wet areas m288 40.00 3,520
105 Waterproofing membrane upturn to floortermination
m103 15.00 1,545
Concrete sealer
Warehouse
106 Concrete sealer to warehouse Excl11,881
Ducted skirting
Warehouse
107 Allow Ducted skirting Excl467
Tactile tiles
Main Office
108 Allow for stainless steel tactile tiles m26 1,000.00 6,000
52,140Total - Floor finishes
CEILING FINISHES
Suspended ceiling
Main Office
109 Prefinished acoustic tiled ceiling includingsuspended framing system
m2442 45.00 19,890
110 Extra over for moisture resistant plasterboard inwet areas
m288 5.00 440
111 Acoustic ceiling insulation m2530 15.00 7,950
112 EO above for bulkheads - say 10% of ceiling ares m253 150.00 80
113 Shadowline m330 12.00 3,960
Page 916-Nov-2017AECOM Project No. 60539394
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Revision : Building 4 Warehouse Facility
DA Estimate - Building 4
A
Item Description Quantity Unit Rate Total
114 Allowance for access panels to ceilings no6 300.00 1,800
Paint to ceiling
Main Office
115 To plasterboard ceiling m288 12.00 1,056
116 To plasterboard bulkhead m253 12.00 636
35,812Total - Ceiling finishes
FITMENTS
Splashback
Main Office
117 600mm high glass splashback above sinkcupboard
m7 450.00 3,150
Joinery
Main Office
118 Reception counter with side table :[2 no] m8 1,200.00 9,600
119 Kitchen sink cupboard with overhead storagecupboard :[2 no]
m7 1,200.00 8,400
120 Kitchen linen cupborad no2 750.00 1,500
Urinal Panel
121 Wall mounted urinal panel no6 250.00 1,500
Sanitary fittings
Main Office
122 Toilet paper holder no16 50.00 800
123 Hand dryer no6 250.00 1,500
124 Soap dispenser no12 150.00 1,800
125 Coat hooks no16 20.00 320
126 Grab rails no2 350.00 700
127 Soap dish no2 100.00 200
128 Stainless steel fixed shelf no2 100.00 200
129 Shower folding seat no2 450.00 900
130 Shower curtain no2 250.00 500
131 Mirror no12 450.00 5,400
132 Mop holder no2 150.00 300
Bollards
133 Allow for 800mm high concrete bollard with yellowcolour safety paint
Item1 15,000.00 15,000
Page 1016-Nov-2017AECOM Project No. 60539394
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Revision : Building 4 Warehouse Facility
DA Estimate - Building 4
A
Item Description Quantity Unit Rate Total
Metalwork
134 Access ladder to roof (allowance) no2 2,750.00 5,500
135 Metal angles to dock edge m66 175.00 11,550
136 Internal column protection to warehouse Item1 10,000.00 10,000
Dock Bumper
137 3000mm long resilient laminated rubber dockbumper; horizontal
no6 600.00 3,600
138 6000mm long resilient laminated rubber dockbumper; horizontal
no8 1,000.00 8,000
Building and Statutory Signage
139 Offices and amenities m2530 5.00 2,650
140 Warehouse m211,881 1.00 11,881
Miscellaneous and sundry works
141 Loose furniture Excl
104,951Total - Fitments
HYDRAULIC SERVICES
Hydraulic services with sanitary ware
142 To office area m2530 100.00 53,000
143 To warehouse m211,881 10.00 118,810
171,810Total - Hydraulic services
MECHANICAL SERVICES
Air conditioning
144 To offices m2530 180.00 95,400
Smoke extraction and ventilation system
145 To warehouse m211,881 8.00 95,048
190,448Total - Mechanical services
FIRE SERVICES
Sprinklers
146 To offices m2530 85.00 45,050
147 To warehouse m211,881 25.00 297,025
Fire hydrants
148 Fire hydrants item1 25,000 25,000
Fire hose reels
149 Fire hose reels item1 25,000 25,000
Dry fire services
150 To offices m2530 15.00 7,950
Page 1116-Nov-2017AECOM Project No. 60539394
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Revision : Building 4 Warehouse Facility
DA Estimate - Building 4
A
Item Description Quantity Unit Rate Total
151 To warehouse m211,881 5.00 59,405
459,430Total - Fire services
ELECTRICAL SERVICES
Electrical/Communications and security
152 To offices m2530 100.00 53,000
153 To warehouse m211,881 40.00 475,240
528,240Total - Electrical services
TRANSPORT SERVICES
Dock Levellers
154 Dock Leveller to dock Excl1 0
ExclTotal - Transport services
BWIC
155 Bwic item1 20,000 20,000
20,000Total - Bwic
Page 1216-Nov-2017AECOM Project No. 60539394
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Revision : External Works and Services
DA Estimate - Building 4
A
Item Description Elemental Qty Unit Elemental Rate Total $/m² GFA
Roads and pavements 1,107,655
Outbuilding 27,750
Landscaping, fencing etc 352,675
External services 965,375
2,453,455TOTAL NET CONSTRUCTION COST
Page 1316-Nov-2017AECOM Project No. 60539394
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Revision : External Works and Services
DA Estimate - Building 4
A
Item Description Quantity Unit Rate Total
ROADS AND PAVEMENTS
Concrete hardstanding area
1 150 thick reinforced concrete pavement (heavyduty) on 150 thick base course
m27,329 95.00 696,255
2 Extra over for truck loading ramp down area m2822 120.00 98,640
Open car park
3 30 thick asphalt pavement (light duty) on 150 thickbase course
m22,030 68.00 138,040
4 Road kerb m1,168 65.00 75,920
5 Wheelstops no50 100.00 5,000
Concrete footpaths
6 100 thick reinforced concrete pavement on 150thick base course
m2560 85.00 47,600
7 Kerb ramp no2 1,500.00 3,000
Paver
8 Concrete paver to outdoor area m2110 120.00 13,200
Line marking
9 Carpark no50 100.00 5,000
10 Directional arrow item1 5,000.00 5,000
Road signage
11 Road signage item1 5,000.00 5,000
Vehicular crossover
12 Vehicular crossover no3 5,000.00 15,000
1,107,655Total - Roads and pavements
OUTBUILDING
Outbuilding
13 Pump house - base building m237 750.00 27,750
27,750Total - Outbuilding
LANDSCAPING, FENCING ETC
Soft landscaping
14 300 thick topsoil m22,950 10.00 29,500
15 MD - white Feather Honey Myrtle - 100L no45 250.00 11,250
16 EF - Red Ironbark - 45L no13 120.00 1,560
17 AD - Black wattle - 45L no4 120.00 480
18 Mn - Ball Honey Myrtle - 5L (3 no. / m2) no873 20.00 17,460
19 Shrubs & ground covers - 130mm (3 no. /m2) no7,101 5.00 35,505
20 50mm mulch m22,950 5.00 14,750
21 Establishment and maintenance item1 10,000 10,000
Irrigation system
22 Irrigation system item1 25,000 25,000
Page 1416-Nov-2017AECOM Project No. 60539394
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Revision : External Works and Services
DA Estimate - Building 4
A
Item Description Quantity Unit Rate Total
Quartz gravel mulch
23 Geo fabric material under pebble mulch m2120 5.00 600
24 75mm thick selected pebble mulch m2120 25.00 3,000
25 Galvanised patio tubing nailed and stabalized withspicks
m51 10.00 510
Hard landscaping
26 Tree-tie with jarrah stake no62 45.00 2,790
27 Bike rack item1 2,500.00 2,500
28 Security kiosk to car entry / exit (allowance) no1 5,000.00 5,000
Fencing
29 Fence (Type 1) - '2400 high black anodisedpalisade security fencing
m76 270.00 20,520
30 Fench (Type 2) - 2100 high chainwire fence with 3x strands of barbed wire above
m575 50.00 28,750
31 Extra over for single security gate to fence type 1 no1 3,500.00 3,500
32 Car entry and exit gates no3 7,500.00 22,500
33 Automatic tracked palisade operated gate no1 20,000.00 20,000
Retaining Walls
34 Average 1300mm high retaining block wallsincluding capping, footings, waterproofing,aggragate drain and the likegranular backfilling, :[115 m]
m2149 500.00 74,500
35 Extra over for safety barrier to top of retaining wall m90 200.00 18,000
Signage
36 Pylon sign no1 5,000.00 5,000
352,675Total - Landscaping, fencing etc
EXTERNAL SERVICES
Electrical
37 Connection to existing services item1 20,000 20,000
38 External lighting item1 100,000 100,000
39 HV cabling and associated works item1 100,000 100,000
40 Padmount power kiosk no1 50,000.00 50,000
41 Sub-station - included in building 3 Note
Communications
42 Connection to existing services item1 15,000 15,000
Water
43 Connection to existing services item1 15,000 15,000
Fire
44 Connection to existing services item1 15,000 15,000
45 10.18m dia fire sprinkler tank and pump allowance item1 100,000.00 100,000
Sewer
Page 1516-Nov-2017AECOM Project No. 60539394
Taylor - Chullora Logistics ParkProject :
Cost Plan :
Revision : External Works and Services
DA Estimate - Building 4
A
Item Description Quantity Unit Rate Total
46 Connection to existing services item1 20,000 20,000
Stormwater
47 300mm dia stormwater pipe m47 215.00 10,105
48 375mm dia stormwater pipe m152 250.00 38,000
49 450mm dia stormwater pipe m154 280.00 43,120
50 525mm dia stormwater pipe m86 320.00 27,520
51 600mm dia stormwater pipe m107 370.00 39,590
52 675mm dia stormwater pipe m57 420.00 23,940
53 825mm dia stormwater pipe m10 550.00 5,500
54 RW - roof water drainage m319 150.00 47,850
55 GD - Grated drain m33 250.00 8,250
56 SGGP - Single grated gully pit no35 2,500.00 87,500
57 SJP - Sealed junction pit no4 3,500.00 14,000
58 GPT no1 10,000.00 10,000
59 Connection to existing services item1 25,000.00 25,000
60 OSD underground tank no1 150,000.00 150,000
965,375Total - External services
Page 1616-Nov-2017AECOM Project No. 60539394