D2 Subway Status

Planning and Capital Programs Committee

May 12, 2020

Steve Salin, AICP

Vice President, Capital Planning

- ®

Page 2: D2 Subway Status - Dallas Area Rapid Transit · D2 Subway Status Planning and Capital Programs Committee May 12, 2020 ... Key Comments 10 • Key topics at April 16, 2020 meeting

D2 Subway Alignment

2

0 A - -Miles

DART kt&pa . •

. . . . West Transfer 'i Center .~

West End ~ 1

.. ..,. .•·····Gt·········· • • ......... -- • •• Commerce

Station

D,d,

East Transfer Center

. .. ........ ... -·

! . . . :

~ , CBD East

Station

UveOak Station Baylor

Proposed 02 Alignment

= AtGrade

Below Grade

c:J Tunnel Portal

D2 Station

Existing system

LRT Alignment

D LRT Station

TRE Commuter Rail

McKinney Ave Trolley

Dallas Streetcar

i;J CBD Transfer Center

Page 3: D2 Subway Status - Dallas Area Rapid Transit · D2 Subway Status Planning and Capital Programs Committee May 12, 2020 ... Key Comments 10 • Key topics at April 16, 2020 meeting

• The purpose of today’s briefing is to provide an overview of:

– Updated SDEIS schedule

– Service Plan amendment process and proposed schedule

– Public and agency involvement activities

o Urban Design Peer Review Panel feedback

o Coordination on I-345 issues (TxDOT, City of Dallas)

– Update on Capital Investment Grant (CIG) approach and potential decision points under new financial conditions

Today’s Briefing

3

Page 4: D2 Subway Status - Dallas Area Rapid Transit · D2 Subway Status Planning and Capital Programs Committee May 12, 2020 ... Key Comments 10 • Key topics at April 16, 2020 meeting

SDEIS and Service Plan Amendment Schedule

Page 5: D2 Subway Status - Dallas Area Rapid Transit · D2 Subway Status Planning and Capital Programs Committee May 12, 2020 ... Key Comments 10 • Key topics at April 16, 2020 meeting

SDEIS Schedule

5

Date Agency Action

April 7 to 24 FTA Review/Comment

April 27 to May 5 DART Revise, based on FTA comments and return to FTA

May 8 FTA Upload to Federal website

May 8 to 15 DART Distribute to Elected Officials, Stakeholders,Public Libraries (mostly electronically)

May 15 FTA Notice of Availability (Federal Register)

May 15 to June 29 FTA/DART 45-day Comment Period

June 11 DART Public Hearings (may be virtual)

Page 6: D2 Subway Status - Dallas Area Rapid Transit · D2 Subway Status Planning and Capital Programs Committee May 12, 2020 ... Key Comments 10 • Key topics at April 16, 2020 meeting

• The current Service Plan does not include the proposed D2 Subway alignment and stations as contained in the SDEIS and 20% design plans

• Service Plan is typically amended prior to a Final EIS and Record of Decision

• The process requires a public hearing with notification to adjacent property owners

• New fixed guideway alignments not already on Service Plan must be approved by the municipality

Service Plan Amendment Process

6

Page 7: D2 Subway Status - Dallas Area Rapid Transit · D2 Subway Status Planning and Capital Programs Committee May 12, 2020 ... Key Comments 10 • Key topics at April 16, 2020 meeting

Proposed Service Plan Amendment Schedule

7

Tentative Date Agency Action

June 15 or August 17 Dallas City Council Transportation and Infrastructure Committee

Briefing/Action

July 7 DART Planning and Capital Programs Committee

Call for Public Hearing

August 11 DART Committee-of-the-Whole Call for Public Hearing

September 16 Dallas City Council Approval

September 22 DART Board Public Hearing and Approval Consideration

Page 8: D2 Subway Status - Dallas Area Rapid Transit · D2 Subway Status Planning and Capital Programs Committee May 12, 2020 ... Key Comments 10 • Key topics at April 16, 2020 meeting

Recent and Upcoming Meetings

Page 9: D2 Subway Status - Dallas Area Rapid Transit · D2 Subway Status Planning and Capital Programs Committee May 12, 2020 ... Key Comments 10 • Key topics at April 16, 2020 meeting

• April 16 – TxDOT, City of Dallas, NCTCOG meeting

• April 24 – Urban Design Peer Review Panel

• April 29 – Feasibility Study kick-off with east portal property owner

• May/June - City staff, stakeholder meetings and SDEIS public hearings

• June 4 – Park and Recreation Board briefing and action

– Call for Chapter 26 hearing for proposed park easements

• June – Landmark Commission briefing (historic resources)

• June – Arts & Cultural Advisory Commission briefing (public art)

Recent and Upcoming Meetings

9

Page 10: D2 Subway Status - Dallas Area Rapid Transit · D2 Subway Status Planning and Capital Programs Committee May 12, 2020 ... Key Comments 10 • Key topics at April 16, 2020 meeting

• Maintain a unified identity for the entire alignment while also encouraging unique individual characteristics of each station

• Explore partnering with private developers to develop air rights above all proposed stations while also ensuring station design can accommodate future development

• Try to reduce escalator runs and distance to Commerce Station platform

• Design Pegasus Plaza headhouse to be minimalist in style and design the headhouse and park as one space to minimize impact on the park

• Explore developing the East Transfer Center as a future development site

• Design of the space at Swiss/Good Latimer wye junction with landscaping and public art to prevent it from becoming a purely utilitarian space

Urban Design Peer Review PanelKey Comments

10

Page 11: D2 Subway Status - Dallas Area Rapid Transit · D2 Subway Status Planning and Capital Programs Committee May 12, 2020 ... Key Comments 10 • Key topics at April 16, 2020 meeting

• Key topics at April 16, 2020 meeting included:

1. Review D2 Subway current design

2. Discussion of two City of Dallas ideas for alignment and roadway modifications if the D2 Subway portal was to move into downtown to allow for at-grade crossing under I-345

3. Review early concepts for I-345 below-grade options to understand how they would interface with D2 Subway and city streets

4. Discuss next steps to advance both projects in coordinated manner

TxDOT/City of Dallas/NCTCOGI-345 Coordination

11

Page 12: D2 Subway Status - Dallas Area Rapid Transit · D2 Subway Status Planning and Capital Programs Committee May 12, 2020 ... Key Comments 10 • Key topics at April 16, 2020 meeting

City of Dallas Concept #1D2 Subway At-Grade under I-345

DART •

Page 13: D2 Subway Status - Dallas Area Rapid Transit · D2 Subway Status Planning and Capital Programs Committee May 12, 2020 ... Key Comments 10 • Key topics at April 16, 2020 meeting

DART Review of City of Dallas Concept #1 Pacific Portal (Plan)

13

DART

Page 14: D2 Subway Status - Dallas Area Rapid Transit · D2 Subway Status Planning and Capital Programs Committee May 12, 2020 ... Key Comments 10 • Key topics at April 16, 2020 meeting

• Actual length of portal would raise Elm Street about 5 feet

• Profile under Commerce Street is raised by about 14 feet

– Cut-and-cover through Main Street Garden, along Commerce for station and likely for entire alignment given short length of mined sections (including cut-and-cover through Belo Garden)

• Requires displacement of two Elm Street Parking Garages with long standing opposition of property owners and businesses who use garages

• Undesirable at-grade crossing of major arterial at portal exit location due to reconstruction of Cesar Chavez Boulevard & Pearl Street

• Bisects DART East Transfer Center potential development site

DART Review of Concept #1

14

Page 15: D2 Subway Status - Dallas Area Rapid Transit · D2 Subway Status Planning and Capital Programs Committee May 12, 2020 ... Key Comments 10 • Key topics at April 16, 2020 meeting

City of Dallas Concept #2 Elm Portal

15

DART •

... ~,,. ~ · --

-

Page 16: D2 Subway Status - Dallas Area Rapid Transit · D2 Subway Status Planning and Capital Programs Committee May 12, 2020 ... Key Comments 10 • Key topics at April 16, 2020 meeting

DART Review of Concept #2

16

Page 17: D2 Subway Status - Dallas Area Rapid Transit · D2 Subway Status Planning and Capital Programs Committee May 12, 2020 ... Key Comments 10 • Key topics at April 16, 2020 meeting

• New vertical profile developed from portal placed east of Cesar Chavez along Elm

• Actual length of portal extends under I-345

• Portal would impact I-345 columns and northbound I-345 ramp to Elm

• Station within Elm Street would close Elm and create tight station platforms along sidewalk (Epic access eliminated)

• Double track LRT within Elm would possibly allow for one lane on Elm

• Undesirable 10 mph curve at Elm/Good Latimer to be able to place junction within Marquis apartments

• Station under Elm Garages would require displacement and relocation of garage to nearby site like Concept #1

DART Review of Concept #2

17

Page 18: D2 Subway Status - Dallas Area Rapid Transit · D2 Subway Status Planning and Capital Programs Committee May 12, 2020 ... Key Comments 10 • Key topics at April 16, 2020 meeting

• TxDOT is still in feasibility study phase but developed several concepts that appear to work with current design of D2 Subway

• There would be a requirement for a pump station, ongoing operating costs of pump station, and infrastructure for taller walls due to deeper facility

– Opportunity for cost-sharing of agencies as contingency program for future facility

TxDOT I-345 Options

18

Page 19: D2 Subway Status - Dallas Area Rapid Transit · D2 Subway Status Planning and Capital Programs Committee May 12, 2020 ... Key Comments 10 • Key topics at April 16, 2020 meeting

Path Foward

19

• Agencies will continue to meet bi-weekly especially related to I-345 options and city street interface

• DART will continue to advance project as currently contained in 20% and in SDEIS

• Potential schedule changes to both D2 Subway and TxDOT Feasibility Study may allow more time for collaboration and resolution of details

• City of Dallas may want to present the D2 Subway alternatives at future meetings as part of process and documentation

Page 20: D2 Subway Status - Dallas Area Rapid Transit · D2 Subway Status Planning and Capital Programs Committee May 12, 2020 ... Key Comments 10 • Key topics at April 16, 2020 meeting

CIG Program Status

Page 21: D2 Subway Status - Dallas Area Rapid Transit · D2 Subway Status Planning and Capital Programs Committee May 12, 2020 ... Key Comments 10 • Key topics at April 16, 2020 meeting

Capital Investment Grant (CIG) Status Update

21

• Staff are continuing to coordinate with FTA towards a Core Capacity submittal in August/September timeframe

– Submittal will include 6-month advance notice to request entry into Engineering phase

• It is unknown if FTA will be changing process due to the COVID-19

• DART staff is coordinating internally on required readiness documents that need to be complete before FTA would authorize DART into Engineering

• Project schedule changes will factor into the decision to advance project past this Project Development phase into Engineering

Page 22: D2 Subway Status - Dallas Area Rapid Transit · D2 Subway Status Planning and Capital Programs Committee May 12, 2020 ... Key Comments 10 • Key topics at April 16, 2020 meeting

Project Decision Tree

22

• Decision chart

NO

YES

ACQUIRE AND HOLD

ACQUIRE AND HOLD

Page 23: D2 Subway Status - Dallas Area Rapid Transit · D2 Subway Status Planning and Capital Programs Committee May 12, 2020 ... Key Comments 10 • Key topics at April 16, 2020 meeting

Project Decision Tree

23

• Decision chart

ADJUST PROJECT

NO

NO ENTER ENG

YES

FFGA

Page 24: D2 Subway Status - Dallas Area Rapid Transit · D2 Subway Status Planning and Capital Programs Committee May 12, 2020 ... Key Comments 10 • Key topics at April 16, 2020 meeting

D2 Board Schedule

Page 25: D2 Subway Status - Dallas Area Rapid Transit · D2 Subway Status Planning and Capital Programs Committee May 12, 2020 ... Key Comments 10 • Key topics at April 16, 2020 meeting

Future Briefings/Board Goals

25

Board/Committee Meeting Topic/Action

January 28 Planning ✓ Corridor preservation progress✓ Status of TxDOT coordination✓ Progress on LONP to FTA for pre-award authority✓ Progress on FTA Review of SDEIS Chapters✓ Review of key issues

February 25 Planning ✓ Review 20% design submittal/key issues✓ Progress on advance notice to request entry into Engineering✓ Proposed date for Federal Register notice on SDEIS✓ Proposed dates for SDEIS Public Hearings✓ FTA Funding Review (covered in other briefing)

March 10 Planning & Capital Programs

✓ Process for 20% design review✓ Schedule update

April 14 Planning & Capital Programs

✓ Review 20% design submittal cost methodology✓ SDEIS 45-day public and agency review timeline

May 12 Planning & Capital Programs

Service Plan Amendment schedule (briefing)Update on potential refinements to 20% designDiscussion of Capital Investment Grant (CIG) core capacity submittal schedule/approach and FY2021 Financial Plan assumptionsStatus of SDEIS review/key issues

DART --- - ,,.- ·

Page 26: D2 Subway Status - Dallas Area Rapid Transit · D2 Subway Status Planning and Capital Programs Committee May 12, 2020 ... Key Comments 10 • Key topics at April 16, 2020 meeting

Future Briefings/Board Goals

26

Board/Committee Meeting Topic/Action

June 9, 2020 Planning & Capital Programs

Entry into Engineering progressSummary of SDEIS comments to dateDevelopment of Mitigation Monitoring Program (MMP)

July 7, 2020 Planning & Capital Programs

Progress on FEIS/ROD developmentProgress on 30% design submittalCall for Public Hearing on Service Plan Amendment (action)

August 11, 2020 COTW/Board Call for Public Hearing on Service Plan Amendment (action)

August 11, 2020 Planning & Capital Programs

Status of 30% design submittalStatus of CIG submittal (typically due in Aug/Sept)Status of FEIS/ROD

September 8, 2020 Planning & Capital Programs

Status of CIG submittal (typically due in Aug/Sept)Proposed date for Federal Register notice on FEIS/ROD

September 22, 2020 FY2021 Financial Plan approvalApproval of Service Plan Amendment

FUTURE FY2021 Negotiation of Full Funding Grant Agreement

Page 27: D2 Subway Status - Dallas Area Rapid Transit · D2 Subway Status Planning and Capital Programs Committee May 12, 2020 ... Key Comments 10 • Key topics at April 16, 2020 meeting

27DART

®