CLIENT
PROJECT
M. P. AUDYOGIK KENDRA VIKAS NIGAM (I) LTD. INDORE
CONSTRUCTION OF RAU- PITHAMPUR ROAD, MP.
DETAIL DESIGN OF HIGH LEVEL BRIDGE ACROSS
GAMBHIR RIVER AT CH. 6+456.
8/10/2019 D1 Hydr Ghambir.pdf
http://slidepdf.com/reader/full/d1-hydr-ghambirpdf 2/7
GAMBHIR RIVER Hydraulic design Rau - Pithampur road.
Data:-
1 Catchment area = 90.43 Sqkms
2 HFL = RL 550.300 m
3 Slope of river = 0.0020
1.Discharge calculation :-
a) By area velocity method:-
( i ) At C/L OF PROPOSED BRIDGE SITE
HFL = 550.300 mChain.
(m)
Bed level
(R.L.)
Depth
below HFL
(m)
Average
depth (m)
Distance
(m)
Diff. in
depth (m)
Area
(sq. m)
A
Wetted
perimeter
(m) P72.668 550.300 0.000 0.000 0.0 0.000
83.523 550.251 0.049 0.024 10.9 0.049 0.266 10.855
95.964 550.139 0.161 0.105 12.4 0.112 1.306 12.442
104.999 550.055 0.245 0.203 9.0 0.084 1.834 9.035
108.514 549.863 0.437 0.341 3.5 0.192 1.199 3.520
112.204 549.671 0.629 0.533 3.7 0.192 1.967 3.695
116.03 549.479 0.821 0.725 3.8 0.192 2.774 3.831
119.548 549.287 1.013 0.917 3.5 0.192 3.226 3.523
123.055 549.095 1.205 1.109 3.5 0.192 3.889 3.512127.122 548.589 1.711 1.458 4.1 0.506 5.930 4.098
130.123 548.084 2.216 1.963 3.0 0.505 5.892 3.043
133.86 547.578 2.722 2.469 3.7 0.506 9.227 3.771
137.585 547.072 3.228 2.975 3.7 0.506 11.082 3.759
143.651 543.430 6.870 5.049 6.1 3.642 30.627 7.075
145.259 543.023 7.277 7.073 1.6 0.407 11.374 1.659
150.714 541.931 8.369 7.823 5.5 1.092 42.674 5.563
154.453 541.644 8.656 8.512 3.7 0.287 31.828 3.750
158.475 541.163 9.137 8.896 4.0 0.481 35.782 4.051
162.292 541.135 9.165 9.151 3.8 0.028 34.929 3.817
165.78 541.594 8.706 8.935 3.5 0.459 31.167 3.518167.992 542.505 7.795 8.250 2.2 0.911 18.250 2.392
169.85 543.792 6.508 7.151 1.9 1.287 13.287 2.260
175.108 545.686 4.614 5.561 5.3 1.894 29.240 5.589
179.365 548.274 2.026 3.320 4.3 2.588 14.133 4.982
185.005 548.941 1.359 1.692 5.6 0.667 9.55 5.679
193.005 549.803 0.497 0.928 8.0 0.862 7.42 8.046
200.005 549.996 0.304 0.400 7.0 0.193 2.80 7.003
207.279 550.300 0.000 0.152 7.3 0.304 1.11 7.280
Avg BL 546.755 361.66 130.47
DETAILED DESIGN OF HIGH LEVEL BRIDGE ACROSS GAMBHIR
RIVER AT CH. 6+456.
Road name - Rau - Pithampur road.
M. P. AUDYOGIK KENDRA VIKAS NIGAM (I) LTD. INDORE
Ch-
HYDRAULIC DESIGN
6+456
8/10/2019 D1 Hydr Ghambir.pdf
http://slidepdf.com/reader/full/d1-hydr-ghambirpdf 3/7
GAMBHIR RIVER Hydraulic design Rau - Pithampur road.
H.M.D. R = A/P = 2.772 m Here A= C/S area in sq. m
Slope S = 0.00200 P= Wetted perimeter
From manning's formula :- V = (1/n) x (R)2/3
x (S)1/2
Where
V = Velocity in m/sec.
n = Rugosity const. Here n = 0.035(Table 5.1 of IRC SP-13
R = hydraulic mean depth in m
V = 2.521 m/sec.
Discharge Q = V x A in cumec.
Where A = C/S area in sq. m
Q = 912 Cumec
( ii ) At 578.0 M U/S (FROM PROPOSED BRIDGE SITE)
HFL = 548.250 m
Chain.
(m)
Bed level
(R.L.)
Depth
below HFL
(m)
Average
depth (m)
Distance
(m)
Diff. in
depth (m)
Area
(sq. m)
A
Wetted
perimeter
(m) P60.560 548.250 0.000 0.000 0.0 0.000
66.81 546.926 1.324 0.662 6.3 1.324 4.137 6.389
73.652 544.482 3.768 2.546 6.8 2.444 17.420 7.265
78.582 542.601 5.649 4.709 4.9 1.881 23.213 5.277
95.71 542.638 5.612 5.630 17.1 0.037 96.439 17.128
100.369 542.847 5.403 5.507 4.7 0.209 25.659 4.664
106.27 544.355 3.895 4.649 5.9 1.508 27.434 6.091
112.171 545.862 2.388 3.142 5.9 1.507 18.538 6.090
120.473 546.362 1.888 2.138 8.3 0.500 17.750 8.317
130.313 546.836 1.414 1.651 9.8 0.474 16.246 9.851135.954 546.505 1.745 1.580 5.6 0.331 8.910 5.651
142.351 546.173 2.077 1.911 6.4 0.332 12.225 6.406
152.912 545.950 2.300 2.188 10.6 0.223 23.113 10.563
158.702 545.980 2.270 2.285 5.8 0.030 13.230 5.790
162.117 546.153 2.097 2.183 3.4 0.173 7.457 3.419
171.284 546.495 1.755 1.926 9.2 0.342 17.656 9.173
180.358 546.837 1.413 1.584 9.1 0.342 14.373 9.080
100 548.250 0.000 0.707 80.4 1.413 56.773 80.370
400.57 201.53
H.M.D. R = A/P = 1.988 m
Slope S = 0.0020
V = 2.020 m/sec.
Q = 809.15 Cumec
( iii ) At 363.0 M D/S (FROM PROPOSED BRIDGE SITE)
HFL = 550.600 m
8/10/2019 D1 Hydr Ghambir.pdf
http://slidepdf.com/reader/full/d1-hydr-ghambirpdf 4/7
GAMBHIR RIVER Hydraulic design Rau - Pithampur road.
Chain.
(m)
Bed level
(R.L.)
Depth
below HFL
(m)
Average
depth (m)
Distance
(m)
Diff. in
depth (m)
Area
(sq. m)
A
Wetted
perimeter
(m) P103.073 550.600 0.000 0.000 0.0 0.000
109.757 549.920 0.680 0.340 6.7 0.680 2.273 6.719
114.713 546.018 4.582 2.631 5.0 3.902 13.039 6.308
118.232 543.026 7.574 6.078 3.5 2.992 21.388 4.619
123.369 541.395 9.205 8.390 5.1 1.631 43.097 5.390125.647 541.597 9.003 9.104 2.3 0.202 20.739 2.287
128.463 541.655 8.945 8.974 2.8 0.058 25.271 2.817
130.776 541.673 8.927 8.936 2.3 0.018 20.669 2.313
139.982 543.033 7.567 8.247 9.2 1.360 75.922 9.306
144.402 546.627 3.973 5.770 4.4 3.594 25.503 5.697
148.181 547.451 3.149 3.561 3.8 0.824 13.457 3.868
155.571 548.579 2.021 2.585 7.4 1.128 19.103 7.476
160.467 549.053 1.547 1.784 4.9 0.474 8.734 4.919
164.946 549.527 1.073 1.310 4.5 0.474 5.867 4.504
168.461 549.459 1.141 1.107 3.5 0.068 3.891 3.516
174.571 549.545 1.055 1.098 6.1 0.086 6.709 6.111180.521 549.630 0.970 1.013 5.9 0.085 6.024 5.951
184.602 549.637 0.963 0.967 4.1 0.007 3.944 4.081
189.875 549.644 0.956 0.960 5.3 0.007 5.059 5.273
193.12 549.680 0.920 0.938 3.2 0.036 3.044 3.245
202.111 549.745 0.855 0.888 9.0 0.065 7.980 8.991
208.347 550.600 0.000 0.428 6.2 0.855 2.666 6.294
334.38 102.96
H.M.D. R = A/P = 3.248 m
Slope S = 0.0020
V = 2.802 m/sec.Q = 936.97 Cumec
b) By Dickens formula:-
Q = C x M(3/4)
Where C = 18.0 (Article 4.1 of IRC SP-13)
M = Catchment area =
Q = 18.0 x 90.4(3/4)
Q = 527.85 Cumec
2. Design Discharge :-
The flood discharge is calculated by empirical formula and
also by rational method. The values are as given below :-Emperical formula :-
Dicken formula = 527.85 Cumec
Rational method :-
Area velocity method
At D/S = 936.97 Cumec
At U/S = 809.15 Cumec
At C/L = 912 Cumec
Max. in above three = 937.0 Cumec
90.43 sqkm
8/10/2019 D1 Hydr Ghambir.pdf
http://slidepdf.com/reader/full/d1-hydr-ghambirpdf 5/7
GAMBHIR RIVER Hydraulic design Rau - Pithampur road.
Therefore take the Design Discharge Q = 937.0 Cumec
( Maximum of above )
% increase over design discharge for scour level
as per cl. 703.1.1 of IRC:78-2000 = 253 CumecTotal Design Discharge Q' For Scour level = 1190 Cumec
3. Area of the flow at C/L of bridge = 361.66 sqm
4. Mean Design velocity V = Q/A = 2.521 m/sec.
Say 2.52 m/sec.
5. Linear water way :-
i) By Area Velocity method :-
Avg. Depth = HFL - avg. bed level
Avg. bed level = 545.984 m
Avg. Depth = 4.32 m
Design dishrage = 937 Cumec
Velocity = 2.52 m/sec
L = Q/VxD = 86.09 m
ii) Actual Water spread at Bridge = 130.0 m
6. Spans :- HFL spread is very shallow depth on one side of bank & one side is
solid high bank. So following arrangement is proposed -
Proposed High level bridge of Spa = 21.0 m
No. of spans = 4 Nos.
Proposed Length of Bridge = 84.0 m
7. Calculation of scour depth :- As per cl. 703.2 & 703.3 of IRC 78-2000
Mean depth of scour dsm = 1.34 x [ Db / Ksf ]
Q' = 1190 Cumec
Eff. availeble linear water-way L = 75.7 m
Db = Q' / L = 15.72 Cumec/m
Ksf = 1.25
Mean depth of scour dsm = 7.81 m
8. Foundation & Scour level at pier :-
Depth of scour from HFL at pier = 2 x dsm = 15.61 m
Foundation below scour level = 5.20 m
Foundation level for pier = 529.48 m ie at grip length.
Rock level = 538.000 m
Foundation level for pier = 536.000 m ie 2 m below Rock lev
Proposed foundation level for pier = 536.00
Scour level at pier = 538.000 m ie. at Rock Level
8/10/2019 D1 Hydr Ghambir.pdf
http://slidepdf.com/reader/full/d1-hydr-ghambirpdf 6/7
GAMBHIR RIVER Hydraulic design Rau - Pithampur road.
9. Foundation & Scour level at abutment :-
Depth of scour from HFL = 1.27 x dsm = 9.91 m
Foundation below scour level = 3.30 m
Foundation level = 537.08 m ie at grip length.
Rock level = 540.000 m
Foundation level = 538.00 m ie 2 m below Rock lev
Proposed foundation level = 538.00Scour level = 540.386 m
10. Afflux
BY Molesworth Formula Ha = [{V2/17.88} + 0.015]x[{A/a}
2 - 1]
Where Ha - Afflux in m
V - Velocity in m/sec = 2.52 m/sec
A - Area of Water way natural at HFL= 361.66 m2
Avg. bed level in bridge length = 545.984 m
Avg. Depth in bridge length = 4.316 m
a - Area of Water way under Bridge = 326.75 m2
Modified velocity at bridge C-S (design Q/a) = 2.868 m/sec
Ha = 0.107
say 0.150 m
11. Sofffit Level :-
As per cl. 106.2.1 of IRC - 5 : 2000
Vertical clerance = 1.200 m
Soffit level = HFL + Afflux + Vertical clearance
= RL 551.650 m Say
12. Formation level :-
Slab thickness = 2.000 m
Wearing coat thickness = 0.065 m
Camber = 0.274 mFormation level = Soffit level + Slab thickness + Wearing coat thickness
RL 553.989 m
However considering road FRL adopt the Formation level RL 555.665 m
& Soffit level at RL 553.326 m
13. Pile cap level :-
Pier Pile cap top RL 546.000 m RL 544 for P2
Abut. Pile cap top RL 549.500 m
8/10/2019 D1 Hydr Ghambir.pdf
http://slidepdf.com/reader/full/d1-hydr-ghambirpdf 7/7
GAMBHIR RIVER Design Parameter Rau - Pithampur road.
GENERAL DETAILS
1 Bridge Ch. -
2 Name of River - GAMBHIR RIVER
3 Name of Road - Rau - Pithampur road.
4 District Name - INDORE
5 Contractor - M/s RAU- PITHAMPUR INFRASTRUCTURE PVT .LTD.
6 Client - M. P. AUDYOGIK KENDRA VIKAS NIGAM (I) LTD. INDORE
HYDRAULIC & DESIGN PARAMETER
1 Type of Bridge - High level
2 Length of Bridge - 4 Spans of 21 m
3 Overall width - 12.9 m
4 Carriageway - 10.5 m
5 Formation level - m
6 Soffit level - m
7 HFL - m
8 LWL - m
9 Design Discharge - cum/sec
10 Max. mean velocity - m/sec
11 Afflux - mm
12 Catchment area - sqkm
13 Seismic zone - II
14 SBC - 60 t/m2
15 Foundation level A - m
P - m
16 Scour level A -
P -
17 Foundation type - Pile
18 Substructure type - RCC box type Abutment M-30 & RCC Circular Pier M-30
19 Superstructure type - RCC T-girder M-30
20 Design loading - IRC Class 70R+Ax1 or Class Ax3 lane whichever produces Severe eff
21 Wearing coat - RCC M-30 75 mm thick as per MORTH.
22 Railing - RCC Railing with kerb & median
23 Drainage spout - As per M.O.R.T.H. STD. DRG. NO. SD/103
24 Length of Abutment - 5.0 m
6+456
540.386
538.000
553.326
550.30
541.135
936.97
2.868
150
90.43
538.000
536.000
84.000
555.665