Upload
truonghuong
View
213
Download
0
Embed Size (px)
Citation preview
Updated: February 23, 2007 EB-2005-0501 Exhibit D1 Tab 3 Schedule 5 Page 1 of 35
SHARED SERVICES AND OTHER CAPITAL 1
2
1.0 INTRODUCTION 3
4
Capital expenditures under the Shared Services program support the Sustainment, Development, 5
and Operations work programs of Hydro One Networks Inc. As such they consist of assets that 6
are largely shared by both the Transmission and Distribution businesses. Shared assets include 7
Information Technology installations such as applications software and computer equipment, 8
land, buildings, office equipment, transportation and work equipment (T&WE), tools, and 9
service equipment. 10
11
Shared services cost levels are fully reviewed as part of the annual business planning process 12
described in Exhibit A, Tab 14, Schedule 1. 13
14
Table 1 15
Shared Services & Other Capital Allocated to Transmission 2003-2008 ($ Millions) 16
17
Historic Bridge Test Years
Description 2003 2004 2005 2006 2007 2008
Information Technology 7.3 9.7 20.1 14.9 67.1 26.0
Facilities & Real Estate 1.6 3.1 0.8 1.5 4.0 4.2
Transport & Work Equipment 20.7 4.7 10.1 9.9 10.4 9.7
Service Equipment 2.5 1.7 1.5 1.7 3.1 2.8
Other (3.4) 1.0 3.0 6.1 0 0
Total 28.7 20.2 35.5 34.1 84.6 42.7
18
Table 1 is a summary of the Transmission portion of the Shared Services Capital over the 19
Historic, Bridge, and Test years. Exhibit C1, Tab 5, Schedule 3 outlines the appropriate cost 20
allocation drivers that have been utilized to derive the Transmission allocation of this capital.21
Updated: February 23, 2007 EB-2005-0501 Exhibit D1 Tab 3 Schedule 5 Page 2 of 35
1
The following table provides an overview of the various cost categories for the period 2003 2
through 2008, highlighting the total capital spending for Shared Services and Other Capital, as 3
well as the portion allocated to the transmission business. 4
5
Table 2 6
Total Shared Services & Other Capital ($ Millions) 7
8
Historic Bridge
Test Years Allocated to
Transmission
Description 2003 2004 2005 2006 2007 2008 2007 2008
Information Technology 14.6 20.0 39.6 34.3 131.5 48.1 67.1 26.0
Facilities & Real Estate 2.8 5.9 2.6 3.6 7.2 7.7 4.0 4.2
Transport & Work
Equipment
53.5 13.5 40.5 41.2 43.5 40.6 10.4 9.7
Service Equipment 6.4 4.9 3.1 3.9 7.3 6.5 3.1 2.8
Other (0.1) (2.2) 3.1 6.1 0 0.0 0 0
Total 77.2 42.1 88.9 89.1 189.5 102.9 84.6 42.7
9
Sections 2.0 through 6.0 detail the capital requirements which make up the Shared Services 10
Capital program. 11
12
2.0 INFORMATION TECHNOLOGY 13
14
Information Technology (“IT”) refers to computer systems (hardware, software and applications) 15
that support business processes used by employees throughout the organization. IT infrastructure 16
includes the voice and data telecommunication networks; data centre installations; and computer 17
equipment (servers, computers and printers) that enable employees to access IT systems. Staff 18
Updated: February 23, 2007 EB-2005-0501 Exhibit D1 Tab 3 Schedule 5 Page 3 of 35
access software applications from offices, and field locations using the wide are network, local 1
area networks or through virtual private network connections. 2
3
Capital programs include annual maintenance investments so that existing IT assets are kept 4
current to maintain continuity of operations and minimize risks of interruption or failure. IT 5
capital programs also include investments in newly developed projects to either replace old 6
technology or to introduce new technological processes to serve the business operations. 7
8
For accounting purposes, IT capital expenditures are defined to include software expenditures for 9
projects and programs that in total cost more than $2 million. Also included in this category are 10
minor fixed assets and hardware expenditures such as desktop computers, which are required as 11
part of ongoing refresh and replacement programs. IT investments are made in accordance with 12
approved business strategies, follow the IT Governance process described in Exhibit C1, Tab 2, 13
Schedule 5, and are subject to a formal review process. 14
15
A significant capital investment in major enterprise applications and systems was made 16
concurrently with the de-merger of Ontario Hydro in 1999 to ensure the new company would 17
have the required business systems and to ensure the de-merged systems would be Y2K 18
compliant. 19
20
Investments in enterprise applications made at or around that time were “best of breed” 21
applications and included: Customer One - customer information and billing system (1998); 22
PassPort - accounts payable, purchasing, inventory and supply management system (1999); 23
PeopleSoft - financial and human resources system (1999). Other than in 2002, when an upgrade 24
was made to the PeopleSoft system, the applications have not been upgraded. Certain of the 25
applications have undergone significant customization to provide additional functionality since 26
the date of their installation. 27
These applications have reached, or are approaching, their end of life. An application approaches 28
its end of life when the application does not provide sufficient functionality or does not have 29
Updated: February 23, 2007 EB-2005-0501 Exhibit D1 Tab 3 Schedule 5 Page 4 of 35
additional capacity to be redesigned or modified to add such functionality to meet current and 1
foreseen business needs. Additionally these older versions are no longer, or will no longer be, 2
supported by the software vendors. Work which is planned for the major application replacement 3
program (Cornerstone) in 2006, 2007 and 2008 is discussed below under the heading 4
Development Projects. 5
6
Capital work that was previously scheduled for Cornerstone in 2006 was postponed in order to 7
expand the assessment and planning of the process changes for these core applications. 8
9
Hydro One’s approach to ensuring ongoing reliability and capacity is to upgrade and/or 10
renew/replace applications and systems when required to either meet changing business needs, 11
when the software application or systems are no longer vendor supported, or to mitigate business 12
risks. Hydro One’s objective is to maintain its systems as near to a current basis as possible to 13
ensure its technology environment is vendor supported. 14
15
In addition to the replacement cycle for existing systems, organic growth and increased reliance 16
on technology requires the systems to grow to accommodate the business needs. In data storage, 17
Hydro One has observed increases averaging 30% per annum. According to a June 2006 White 18
Paper by IBM, this is in line with Industry expectations estimated at 37% per annum. Faster 19
processing speeds to address upgraded application requirements are also facilitated through 20
server and storage improvements or replacements. The increasingly heavy reliance of technology 21
in the field and at field locations has continued to place an upward demand on the IT data 22
infrastructure in terms of volume, speed, connectivity and concurrent use. Field office locations 23
are increasingly utilizing larger more complex business applications such as Passport, Customer 24
One, ArcFM and outage management applications (ORMS). Data networks (wide area and local 25
area networks) are monitored on an ongoing basis and upgrades are made as required to address 26
the business needs and to ensure that application performance is acceptable. 27
Updated: February 23, 2007 EB-2005-0501 Exhibit D1 Tab 3 Schedule 5 Page 5 of 35
2.1 Total IT Capital Expenditures 1
2
Table 3 lists the capital expenditures for programs and projects 3
. 4
5
6
Capital IT expenditures respond to the needs of three general business drivers and are undertaken 7
as projects or programs: 8
9
• Software Refresh and Maintenance Program ensures continued operations of the installed IT 10
application infrastructure 11
• Minor Fixed Assets (MFA) program ensures the continued operations of the installed IT 12
hardware infrastructure. Expenditures in this category address equipment needs which are 13
generated by the growth in demand for IT services, in addition to the replacement of end-of-14
life and under-capacity assets in IT and in the Business Telecom network. 15
• Development Projects replace or upgrade older and end-of-life applications or develop new 16
applications or processes, including those: 17
o that have become inadequate for current functional needs; 18
o that require new applications to improve Business operations 19
o that result from legislative or market driven initiatives 20
21
Bridge
Description 2003 2004 2005 2006 2007 2008 2007 2008
Software Refresh & Maintenance Program 0.7 3.0 14.2 8.6 6.6 8.3 3.7 4.7
Minor Fixed Assets Program 6.8 8.8 14.6 13.2 8.6 8.0 3.7 3.5
Development Projects 7.1 8.2 10.8 12.5 116.3 31.8 59.7 17.9
TOTAL 14.6 20.0 39.6 34.3 131.5 48.1 67.1 26.0
Table 3Total IT Capital Expenditures ($ Millions)
Historic Test Years Allocated to Transmission
Filed: September 12, 2006 EB-2005-0501 Exhibit D1 Tab 3 Schedule 5 Page 6 of 35
Software Refresh and Maintenance includes costs related to upgrading existing operating 1
systems. 2
3
MFA includes desktop computing equipment, field tablet computers, mainframe and storage 4
systems, servers, and peripherals and telecommunication infrastructure including PBX’s, 5
computerized telephony interfaces etc. Other capital items include systems applications and 6
operating systems required to operate the IT and telecommunication infrastructure hardware. 7
8
Development projects include the cost for new applications or the replacement of exiting 9
applications which are at end of life. 10
11
The following architecture principles underlie IT strategy and planning and as such will guide 12
the required application upgrades that will take place over the next 5 years: 13
14
• Applications will be “off the shelf” with built-in protocols (tested and generally used 15
throughout like industries). 16
• The system architecture will be on an open standards platform allowing systems to run on 17
any hardware platform. 18
• Middleware, interfaces and hubs, will be used as appropriate to facilitate application 19
interconnectivity. 20
• Systems architecture and chosen applications will be: 21
• robust (generally understood to mean unlikely to fail, but rapid response if it does) 22
• secure (generally understood to mean 3-tiered, fire-walled and password protected) 23
• flexible service oriented architecture (generally accepted as the most appropriate and 24
efficient IT strategy). 25
• System hardware will be upgraded as required to support the new application. 26
• Costs will be managed on a total cost of operations basis. 27
28
Updated: February 23, 2007 EB-2005-0501 Exhibit D1 Tab 3 Schedule 5 Page 7 of 35
In support of new and planned applications the current hardware infrastructure will be upgraded 1
and designed to: 2
3
• improve disaster recovery processes; 4
• improve system security; 5
• facilitate the increased application of mobile technologies; 6
• continue the transition to storage area networks that benefit from generally accepted industry 7
practices; 8
• secure improved functionality from new and expected technology. 9
10
IT capital project spending increases significantly from 2002 through 2008 and beyond as 11
existing enterprise applications are upgraded and replaced. The larger number of smaller projects 12
which had been undertaken in 2003 through 2006 will decline and be replaced by a phased series 13
of large projects. 14
15
Within projects and programs is work described as “Impact of Capital Projects”. This work is 16
included under the OM&A category called Impact of Capital Projects as discussed under Exhibit 17
C1, Tab 2, Schedule 5, Section 4.3.2. Work in this category includes business process re-18
engineering costs, such as training and change management costs required to implement and 19
train field staff when new capital IT projects are introduced, are captured and reported as OM&A 20
expenditures. These costs vary with each capital project. In accordance with Hydro One 21
accounting practices, the cost associated with this work is not capitalized. 22
23
The major planned capital projects that will be funded in 2007 and 2008 are described below. 24
Updated: February 23, 2007 EB-2005-0501 Exhibit D1 Tab 3 Schedule 5 Page 8 of 35
2.2. Software Refresh and Maintenance Program Capital Expenditures 1
2
Table 4 lists the capital expenditures for the software refresh and maintenance program. 3
4
5
6
Hydro One utilizes just over 700 commercial software programs in order to equip its employees 7
with the required technologies to perform their tasks efficiently and safely. The software refresh 8
and maintenance program provides the needed software vendors’ releases, periodic version 9
upgrades, and replacements of applications that meet the total capital threshold of $2 million 10
aggregated. 11
12
Applications are replaced or upgraded with the line of business involvement to address their 13
business needs and to ensure that applications remain compatible with current IT platforms and 14
other interfacing applications. In this manner, vendor support is maintained to help fix 15
breakdowns or other issues that may occur with the applications. Funding decisions are made 16
based on software lifecycles, vendor schedules, reliability requirements, and experience with 17
similar initiatives/projects. 18
19
In 2005-2006 work was undertaken to upgrade the Microsoft Windows operating system 20
technology from Windows NT and Windows/Office 98 to Windows XP and Office 2003 for all 21
users operating on the Hydro One system. In addition to upgrading the desktop operating system 22
Bridge
2003 2004 2005 2006 2007 2008 2007 2008
Software Refresh & Maintenance Program 0.7 1.7 2.6 1.0 6.6 6.4 3.7 3.6
Windows (O/S) 0.0 1.4 11.6 7.6 0.0 1.9 0.0 1.1
TOTAL 0.7 3.0 14.2 8.6 6.6 8.3 3.7 4.7
Historic Test Years Allocated to Transmission
Table 4Software Refresh and Maintenance Program Capital Expenditures ($ Millions)
Description
Updated: February 23, 2007 EB-2005-0501 Exhibit D1 Tab 3 Schedule 5 Page 9 of 35
and e-mail application the platform was simplified and consolidated to improve system 1
reliability, redundancy and to ensure better security. Coincident with the XP software investment 2
in 2005/2006 a significant increase in MFA investments for computers, servers and storage was 3
required to replace those operating on the old Windows NT/98 platform to retain functionality in 4
the XP/2003 environment. 5
6
The 2006 capital expense level includes the carry-over of Windows XP work related to affected 7
applications as well as the capitalization of previously accrued charges for the Windows XP 8
Upgrade. 9
10
In 2008, a further upgrade from XP/2003 to the Windows Vista application is planned. In 11
accordance with Microsoft’s planned application release schedule, the intent will be to upgrade 12
server functionality. With a significant investment already made in Windows XP and in the 13
2003 infrastructure, Hydro One’s intent is to maintain the operating systems in a current state. 14
Current indications from Microsoft are that the upgrade to the new operating system will be less 15
complex than the upgrade to XP. Even so, single point applications used in the business 16
operations will still have to be tested to ensure they are supported by the new operating system. 17
18
Other expenditures identified for 2007 and 2008 include an upgrade to the Open Market Systems 19
to utilize the functionality of the existing Company hub technology, virtualization of the Storage 20
Area Network to improve data retention and stabilize storage costs, and a number of other 21
technology investments related to intrusion detection, firewalls, and to a greater use of portal 22
technologies. 23
24
Updated: February 23, 2007 EB-2005-0501 Exhibit D1 Tab 3 Schedule 5 Page 10 of 35
2.3. Minor Fixed Assets 1
2
Table 5 lists the capital expenditures for IT Minor Fixed Assets. 3
4
5
Minor Fixed Asset investments are for IT hardware and include specific programs to refresh 6
older hardware such as computers. Equipment refresh is planned to ensure that if system 7
upgrades or applications are added over the life of the hardware that the system will continue to 8
be functional with only a minimal upgrade being required. This strategy minimizes the costs of 9
ownership, ensures operational risk is kept at an acceptable level, and maintains functionality. 10
Planned funding is based on equipment lifecycles. This work is broken down into the categories 11
discussed below for the expenditures shown in Table 5. 12
13
2.3.1 MFA: IT Mainframe, Servers and Storage Sustainment program 14
15
This investment in servers and mainframe computing capability is an ongoing infrastructural 16
obligation for Hydro One information technology. 17
18
The majority of the costs in the MFA category in 2006 were spent on replacement of UNIX 19
servers and on Windows servers. The UNIX server replacement cost has been brought forward 20
from future years to ensure improved system reliability and to respond to and manage projected 21
Bridge
Description 2003 2004 2005 2006 2007 2008 2007 2008
IT Mainframe, Servers, and Storage Program
4.7 1.8 5.9 4.7 3.9 2.7 1.7 1.2
IT Desktops, Laptops, Tablets, Printers & Plotters
2.2 5.0 6.9 5.9 3.9 3.9 1.7 1.7
Telecom Networks & PBX/Voicemail 0.0 2.1 1.7 2.5 0.8 1.4 0.3 0.6
TOTAL 6.8 8.8 14.6 13.2 8.6 8.0 3.7 3.5
Historic Test Years Allocated to Transmission
Table 5IT Minor Fixed Assets Program Capital Expenditures ($ Millions)
Updated: February 23, 2007 EB-2005-0501 Exhibit D1 Tab 3 Schedule 5 Page 11 of 35
annual growth in demand for additional IT processing and storage capacity. The replacement of 1
the UNIX servers with more modern and efficient equipment addresses the end of life issues, 2
which the Company would face with some of the existing UNIX servers. 3
4
Included in the 2006 and 2007 work program are improvements to the current Disaster Recovery 5
(DR) strategy and processes. The DR program allows for the recovery of critical Hydro One 6
systems in the event of a major technology disruption. The DR project will take advantage of the 7
replacement of a number of existing UNIX servers and storage devices by transferring the 8
replaced units to the recovery and back-up role. 9
10
UNIX and Windows servers are used to run business applications, networks, web services and 11
email. Data storage devices are used by business applications and email to store and retrieve 12
data. In assessing when to replace or add additional servers and storage devices vendor’s end-of-13
support-life, capacity requirements, maintenance costs, and systems criticality are assessed. 14
Hardware upgrades are ongoing costs and are needed to maintain reliable service for business 15
applications. 16
17
The funding for the mainframe, servers and storage refresh program varies year to year 18
depending upon hardware lifecycles and business requirements for increased processing 19
capacity. A number of e-mail exchange and file servers were replaced in 2005 and 2006 20
coincident with the Windows XP/2003 project. The costs reflected in 2007 and 2008 work 21
program are indicative of the ongoing required sustainment spend needed to address end of life 22
and capacity issues. 23
Filed: September 12, 2006 EB-2005-0501 Exhibit D1 Tab 3 Schedule 5 Page 12 of 35
2.3.2 MFA: IT Desktops, Laptops, Tablets, Printers, and Plotters Sustainment Program 1
2
Desktop and laptop computers are used by most Hydro One staff for office productivity 3
applications (email, word processing, spreadsheet, presentation, and personal databases) and for 4
business applications such as PassPort, ArcFM and PeopleSoft among many others. Rugged 5
tablet computers are used by field staff using Geographical Information System (“GIS”) based 6
applications for doing system design and asset condition assessments. Printers and Plotters are 7
used by most Hydro One staff throughout the company. 8
9
Hardware upgrades are required to accommodate new software processing requirements, to 10
replace end of life equipment and to maintain reliability. Properly programmed equipment 11
refreshes can maintain or reduce maintenance costs. Hardware maintenance and capability costs 12
tend to increase with aging hardware that is no longer under vendor warranty. Hydro One’s 13
intent is to replace desktop computers every four years, laptops every three years, and printers 14
and plotters every four to five years. This is consistent with industry practice and ensures that 15
spares which are maintained by service technicians are consistent with the computer population 16
at Hydro One. 17
18
Hardware and support service pricing combinations are compared in the market regularly and at 19
times of major purchases in line with corporate procurement policies. 20
21
The funding for desktops, laptops, tablets, printers, and plotters varies year to year depending 22
upon hardware lifecycles and business needs. Funding costs in 2005 and 2006 reflect the 23
acceleration in the laptop and desktop refresh program whereby 2,100 and 2,382 desktop/laptop 24
units respectively were replaced. This was required largely as a result of the Microsoft XP 25
deployment. Tests using XP applications on existing laptop computers, which had been 26
enhanced with additional memory, did not result in acceptable performance. The cost of 27
enhancing the existing equipment combined with the still suboptimal performance of the 28
equipment when XP software was installed, and then combined with the hardware’s end of life 29
Filed: September 12, 2006 EB-2005-0501 Exhibit D1 Tab 3 Schedule 5 Page 13 of 35
issues, negated any business benefit that might have been achieved by delaying the full 1
replacement of the equipment. Therefore, the decision was made to purchase new hardware that 2
met current needs and standards. Ongoing sustainment funding for laptop and desktop equipment 3
replacement, consistent with the refresh objectives noted above, is reflected in the cost 4
projections for 2007 and 2008. 5
6
2.3.3 MFA: Telecom Networks and PBX/Voicemail Sustainment Program 7
8
The telecom assets of Hydro One are many and have a large variety of install dates, lifecycles, 9
and capacities. Data and voice hardware is improved or replaced over time as part of ongoing 10
program management. Continuous initiatives are undertaken to improve data and voice 11
communication efficiency across the wide area networks, the local area networks, the virtual 12
private networks and to ensure systems are supported by third party vendors. 13
14
The telecom MFA program includes the work to rewire local area networks, replace end of life 15
data network switches and routers, upgrade telephone PBX switches, and replace un-interruptible 16
power systems (UPS). Work in this category includes the replacement of end of life hardware 17
and software in the Internet Security Node which is used for authenticating Market Open 18
business to business transactions and for internet access to Hydro One Networks Inc. 19
applications. 20
21
The Telecom MFA program is needed to maintain reliable telecommunications availability plus 22
capacity as well as network security against intrusions by computer hackers, viruses and worms. 23
IT will replace telecommunications hardware facilities that are at end of life, no longer able to 24
meet changing function, capacity or performance needs, and/or expensive to repair and 25
unreliable because they are no longer supported by vendors. 26
27
The telecommunication hardware includes wiring, switches, and routers used to provide local 28
area network (“LAN”) and wide area network (“WAN”) services to offices throughout Ontario. 29
Filed: September 12, 2006 EB-2005-0501 Exhibit D1 Tab 3 Schedule 5 Page 14 of 35
The business telecom network is used to transmit data required to run business applications, for 1
email, and for web sites. 2
3
PBX/Voicemail hardware includes private branch exchange (“PBX”) and key set telephone 4
switches, and voice mail equipment used to provide business telephone services to Hydro One 5
employees at central and field locations throughout the province. 6
7
Within the Hydro One voice and data network there are more than 500 routers/switches and hubs 8
that connect to 70 PBX’s and 35 smaller multi-line office sets. A majority of the routers/switches 9
and hubs are reaching end of life. 10
11
The investment in business telecommunications Networks and PBX/Voicemail is undertaken to 12
replace end-of-life assets and to maintain service reliability and security. The strategy is again to 13
replace equipment that is no longer supported by vendors. For network equipment the refresh 14
occurs about every five years and about every ten years for PBX/Voicemail equipment. 15
16
The funding for business telecommunications Networks and PBX/Voicemail varies year to year 17
depending upon hardware lifecycles, business needs for increased bandwidth and availability of 18
resources. Changes to business applications and work methodologies may require the upgrades 19
to occur more frequently. 20
Updated: February 23, 2007 EB-2005-0501 Exhibit D1 Tab 3 Schedule 5 Page 15 of 35
2.4. IT Development Projects Capital Expenditures 1
2
Table 6 lists the capital development project expenditures of IT. 3
4
5
6
The following IT Capital projects are active in the Bridge year 2006 and/or are planned for the 7
Test years 2007 and 2008. 8
9
2.4.1. Cornerstone Project 10
11
The major software applications used by Hydro One consist of Peoplesoft (Finance and HR), 12
Passport (Supply Chain, Procurement, Accounts Payable) and Customer One (CIS: Customer 13
Information System). These systems were implemented in anticipation of the de-merger of 14
Ontario Hydro and to address Y2K concerns. The applications were modified extensively 15
following their implementation to provide the required business functionality. Functionality of 16
these core systems was also enhanced by the addition of some 700 separate applications, which 17
allow the field and head office staff to complete their work. 18
Bridge
Description 2003 2004 2005 2006 2007 2008 2007 2008
Cornerstone – Phase 1 0.0 0.0 0.0 0.0 102.0 28.0 57.0 15.8
CIS/CSS Hybrid Upgrades 0.0 0.0 0.0 0.4 9.3 0.0 0.0 0.0
CTI Upgrades 0.0 0.0 1.5 3.3 0.0 0.0 0.0 0.0
ArcFM 2.7 6.3 0.0 0.0 0.0 0.0 0.0 0.0
APCi/WEP 0.0 0.9 8.7 8.0 0.0 0.0 0.0 0.0
IREIS 1.4 0.3 0.0 0.0 0.5 0.0 0.3 0.0
PeopleSoft Upgrade 0.8 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Mobile IT 0.6 0.6 0.0 0.0 2.9 2.9 1.6 1.6
Asset Data Collection and Data Mart 1.6 0.0 0.6 0.6 1.5 1.0 0.8 0.5
TOTALS 7.1 8.2 10.8 12.5 116.3 31.8 59.7 17.9
($ Millions)
Historic Test Years Allocated to Transmission
IT Development Projects Capital ExpendituresTable 6
Updated: February 23, 2007 EB-2005-0501 Exhibit D1 Tab 3 Schedule 5 Page 16 of 35
1
These core systems are aged and beyond economical maintenance. They no longer efficiently 2
fulfill the Company’s growing needs for information management and reporting. The PassPort 3
system has been the daily source of asset and work information since its inception in the de-4
merger days of the late 1990’s. The financial system, Peoplesoft, uses PassPort information and 5
derives financial reporting information. The CIS system is used for billing and collections and by 6
customer service representatives to address customer inquires on a daily basis. The systems have 7
limited interconnectivity, which has resulted in the requirement for manual input duplication or 8
other workarounds. Bridging of data and the development of workflow between systems is costly 9
and complex. 10
11
All three of these extremely critical systems have been customized and altered to varying degrees 12
to meet the current needs of the Company, over the past several years. Vendors are unwilling to 13
support these older applications and have been unable to help with add-on customized changes 14
that have been initiated. As software vendors for these applications are moving to new 15
architectures, support for these older applications is being phased out. This leaves the Company 16
with the option of continuing with these applications and developing its own support expertise or 17
migrating to more current versions, or potentially replacing the existing applications with a more 18
integrated and current application platform. 19
20
Continuing with these applications however limits the company’s ability to employ current 21
technology, to make use of mobile business solutions, and to address evolving business needs 22
and processes. Even if the Company were to support its own legacy applications, the risk with 23
the business systems would increase as the existing hardware would also require replacement 24
with more modern systems. These more modern systems might not be able to operate the older 25
applications. 26
27
This investment, which addresses replacement of the core business systems, in a phased 28
approach, positions the company on a robust, secure and flexible enterprise base and will allow 29
Updated: February 23, 2007 EB-2005-0501 Exhibit D1 Tab 3 Schedule 5 Page 17 of 35
the replaced applications to be upgrade on a continual basis, without the cost of a significant one 1
time upgrade. 2
3
The Cornerstone name and concept has been adopted inside the company to assist in 4
communicating with every employee the ‘how’ and ‘when’ of changes that will benefit them 5
throughout the conversion. 6
7
The Cornerstone Project envisions four staged replacements of core applications which are 8
scheduled to occur between 2006 and 2011. Hydro One intends to retain outside consultants and 9
software application vendors, through a competitive bidding process, to assist it with its 10
replacement program. 11
12
The capital work program for Cornerstone will commence in 2007 following completion of the 13
preliminary research that took place in 2006. 14
15
The four phases of the Cornerstone Project are: 16
17
Phase 1 – EAM (Enterprise Asset Management) Core Functionality (Target In-Service Q2 2008) 18
19
The EAM initiative has an estimated capital cost of $130 million in the period from 2007 to 2008 20
and will replace the existing Passport applications with modern EAM solution. The result will be 21
an integrated EAM application which will allow for more effective information transfer within 22
the Company and provide the basis for connectivity with the other core systems as they are 23
replaced or upgraded. 24
25
The first part of Cornerstone is to replace the current installation of PassPort 6. The current 26
version, which supports work management, supply chain and certain asset management 27
processes is old, unsupported, and has been heavily customized since its installation in 1998 and 28
has been “locked down” since 2004. 29
Updated: February 23, 2007 EB-2005-0501 Exhibit D1 Tab 3 Schedule 5 Page 18 of 35
1
PassPort 6 is no longer supported by the software vendor, Indus. This means that the vendor will 2
not provide ongoing application fixes for the application and may not be able to fix the 3
application if it breaks. Additionally the continuous customization which was undertaken to 4
extend the life of the Version 6 now significantly complicates upgrading the current application 5
and requires the system be replaced. 6
7
In replacing the PassPort application with a more current application, Hydro One will be able to 8
take advantage of new functionality inherent in the application, without having to make further 9
customizations. This will enable Hydro One to maintain reliable asset and work information 10
readily available to all stakeholders on a current software platform, which can be upgraded and 11
maintained. Having access to available vendor support will allow the Company to take advantage 12
of leading industry practices, and ensures it has forward compatibility with newer operating 13
platforms, existing and future hardware, other applications and improves system reliability and 14
recovery in the event of a system problem. 15
16
The EAM application upgrade will be an “off the shelf” software solution, provided by a leading 17
T&D utility software vendor. Hydro One will work with the systems integrator and software 18
vendor to follow current best practices for implementing software applications. The Company 19
will rely on the application vendor to enhance the application’s standard functionality, rather 20
than customizing the application to meet only Hydro One’s needs. 21
22
The application replacement is also needed to provide increased automation and functionality to 23
meet changing business needs in the areas of supply chain management and to continue to 24
provide more efficient compliance with Ontario Bill 198 for financial controls and reporting. 25
26
PassPort 6 has numerous "bolt-on" applications and point-solutions, many of which were 27
custom-built thus creating additional costs and efforts to maintain. A major objective of the first 28
Updated: February 23, 2007 EB-2005-0501 Exhibit D1 Tab 3 Schedule 5 Page 19 of 35
phase of Cornerstone is to bring together various asset data and to thereby eliminate duplicate 1
versions of data. 2
3
Phase 1 has been approved by the Hydro One Board of Directors and the IT Steering Committee 4
of the Board and is moving forward toward implementation. This follows an exhaustive selection 5
and discovery process undertaken in 2006 and early 2007 to confirm cost and scope. A similar 6
exercise has not been completed for future phases and the costs associated therein are to be 7
reviewed at an appropriate point prior to final approval. Therefore, the following discussion 8
herein on Phases 2, 3 and 4 does not include cost estimates. As well, costs for Phases 2 through 9
4 are not reflected in the 2007 and 2008 revenue requirement. 10
11
Phase 2 – Enhanced EAM Functionality 12
This phase is intended to enhance the functionality and information available to the Asset 13
Manager. Key deliverables for Phase 2 include: 14
15
• the release of the additional functionality offered by the system replacement implemented in 16
Phase 1 (EAM-Core) 17
• replace most of the existing end-user applications with the EAM solution or with specialized 18
packaged point solutions designed to integrate with the EAM, especially focused on Asset 19
Management capabilities 20
• enhance reporting capabilities 21
• integrate the asset repository with Geospatial Information Systems and technology. 22
23
24
Phase 3 – Upgrade PeopleSoft – HR and Finance Functionality 25
26
The PeopleSoft financial and HR modules were installed in 1998 and the HR module was 27
upgraded in 2002 and subsequently customized. PeopleSoft has been purchased by Oracle, and 28
Updated: February 23, 2007 EB-2005-0501 Exhibit D1 Tab 3 Schedule 5 Page 20 of 35
support for older versions of the PeopleSoft applications will be phased out as PeopleSoft moves 1
to an integrated platform with Oracle applications. 2
3
As in Phase 2, the main objective is not only to install an off-the-shelf solution, but also to adopt 4
industry-standard practices that are enabled by the off-the shelf packages. 5
6
Integration of the new financial and HR application with the modules installed in Phase 1 and 2 7
will enhance financial reporting capabilities. 8
9
Phase 4 - Replace Customer Information System Functionality 10
11
The Customer Information System known as CSS or Customer -1 was purchased in 1997 from 12
Andersen Consulting. The application has undergone significant modifications in order to 13
address the changes in the Ontario regulatory environment and to meet OEB requirements. This 14
is an extensively customized product which is very costly to maintain and very costly to modify 15
to meet new business needs. 16
17
The Hydro One IT strategy is to make modifications to the existing system to extend its useful 18
life and to address known regulatory and business requirements. The system itself is robust but 19
difficult to work with. Improvements to the system, which are discussed below, are intended to 20
stream line work processes, provide additional functionality and to make changes to the 21
application less costly. 22
23
To obtain full functionality with the newer systems, and to improve workflow and improve 24
customer satisfaction the intent of Phase 4 is to replace the existing Customer -1 system with a 25
more integrated application which would interface with the application suite implemented in 26
Phases 1-3. 27
28
Updated: February 23, 2007 EB-2005-0501 Exhibit D1 Tab 3 Schedule 5 Page 21 of 35
Andersen Consulting no longer supports the application and Hydro One is part of a user group 1
who continue to maintain the core functionality of the Customer -1 application. The number of 2
users in the user group, who support the application, is however declining, as more of the utilities 3
using the Customer-1 application are switching to newer integrated CIS applications. 4
5
Inevitably, the Customer -1 application will have to be replaced. 6
7
Updated Cornerstone Estimate 8
9
The preliminary high-level Planning estimates for Phase 1 were included in the material filed 10
with the OEB in September of 2006. The Planning estimates was based on information 11
provided by independent consultants who were asked to provide preliminary estimates for a 12
more narrowly defined replacement of just the present Passport V6 application and current 13
functionality. The estimates were treated as indicative of what the project costs might be and 14
were used as a preliminary Planning estimate to be confirmed through the RFP process and 15
Discovery stage. 16
17
During the summer of 2006, a public RFP document was issued and qualified vendors were 18
selected through a competitive process. This included the selection of a Systems Integrator 19
(Accenture) and an enterprise software application (SAP). The RFP was designed to meet Hydro 20
One’s desire to implement a proven, widely-used, off-the-shelf application or applications which 21
provided the required functionality applicable to a T&D utility environment. 22
23
OM&A costs were incurred in 2006 related to the RFP and the vendor selection process as well 24
as the first part of the Discovery stage. The purpose of the Discovery stage was to establish an 25
appropriate scope, to confirm planning and resourcing and to provide a detailed estimate for 26
project approval, implementation and monitoring. 27
28
Updated: February 23, 2007 EB-2005-0501 Exhibit D1 Tab 3 Schedule 5 Page 22 of 35
In 2006 the Hydro One Board of Directors established an independent committee of the Board to 1
review the Cornerstone Project and to act as an advisor and overseer to the project Steering 2
Committee and to the Cornerstone Project. The IT Committee of the Board has been involved 3
with the project since its inception and has provided an independent review mechanism for the 4
project. 5
6
The Discovery stage took the ’off the shelf’ SAP enterprise asset management application, 7
infrastructure and systems and identified the likely complexity of implementing the solution and 8
the process changes required within the Hydro One environment. The Discovery stage allowed 9
Hydro One to assess the Accenture High Performance Utility Model (HPUM) templates used at 10
other utility companies and to consider and more fully understand the implementation of the 11
required process changes to accommodate the HPUM practices with a non-customized SAP 12
application. HPUM practices as discussed more below. 13
14
Hydro One management has recommended, and the Hydro One Board has approved in February 15
2007, after extensive review and discussion with the IT Committee of the Board, proceeding 16
with Phase 1 of the project for a capital cost of $130 million for the period 2007 and 2008. 17
18
These project costs represent higher estimates than those originally filed in 2006. The following 19
reasons explain the change: 20
21
• The preliminary Planning estimates were provided at an early stage in the Planning 22
process. These estimates were provided prior to selection of an integrator or product and 23
prior to the more detailed Discovery stage which was conducted in the second half of 24
2006. 25
• Initially, the team viewed the project as a simple “like for like” replacement of end – of 26
- life systems. However, during Discovery, the view of the potential for the project 27
changed such that it was viewed as a key enabler of productivity through adoption of 28
Updated: February 23, 2007 EB-2005-0501 Exhibit D1 Tab 3 Schedule 5 Page 23 of 35
more efficient, standardized business processes in areas served by the existing PassPort 1
application. This revised view meant Phase 1 became more extensive, complex and 2
transformational. Rather than a simple IT system replacement, the executive team 3
decided to take advantage of the project to change the way we do work in many areas 4
and to address shortcomings in our existing processes. Changes included the 5
advancement of new and simplified business processes, better understanding of data 6
requirements, and a solution which while more complex would be more advantageous 7
than a straight application replacement. In turn these changes drove an increased 8
hardware complexity, increased reliance on external support for the solution 9
implementation, more accurate license counts, a better understanding of the nature of the 10
licenses that would be required, and increases to contingency and overhead amounts. 11
• The Hydro One IT area has embraced the strategy of integrating off-the-shelf products 12
rather than employing custom applications. Adopting the principle of “no 13
customization” of software makes it necessary to undertake extensive business process 14
changes, which the business units agree are required. Adhering to this principle with the 15
selected software has resulted in more change management and business process change 16
than what was originally envisioned in the planning estimate. 17
• More extensive data conversion work and costs to prepare the data required for the new 18
SAP system 19
• Costs for interest, overheads and taxes consistent with Hydro One’s guidelines for 20
capitalization of projects have increased commensurately with the increase in the core 21
project cost. 22
• Project contingency costs estimated at 20% of total costs are higher largely resulting 23
from the increase in core project costs. 24
25
Phase 1, with the selection of the SAP application, establishes the financial footprint and 26
financial application structure required which had earlier been forecast for Phase 3. Bringing this 27
Updated: February 23, 2007 EB-2005-0501 Exhibit D1 Tab 3 Schedule 5 Page 24 of 35
partly forward into Phase 1 also allows the Phase 2 application to be more effective and 1
beneficial to business reporting and decision making earlier. 2
3
Adopting the Accenture HPUM will require the business to make fundamental changes to how it 4
operates. These changes are intended to allow Hydro One to operate more effectively with the 5
existing staff that it has and to partially address expected staffing losses due to retirements. 6
7
The HPUM process will standardize business processes across the organization, collect and 8
centralize corporate knowledge and improve the efficiency of existing business processes. Use of 9
the SAP application and associated utility asset management applications will allow the Hydro 10
One asset management organization to better align its asset management decisions with the goal 11
of improving or maintaining system efficiency in an investment effective manner. 12
13
2.4.2 CIS/CSS Hybrid Upgrade Project 14
15
The Customer Information System is the term given to a suite of billing and customer 16
applications. To improve their existing performance Hydro One intends to make a series of 17
investments in the applications ($0.4M in 2006 and $9.3M in 2007) to improve current 18
performance and reliability. 19
20
Some aspects of previously planned work to update applications in Customer Care will be 21
become part of the Cornerstone project. 22
23
This project is allocated 100% to distribution account categories. The upgrade is labeled as 24
“hybrid” because some components will be upgraded and others will not, rendering the resultant 25
configuration as a hybrid application, rather than a replacement or upgrade. 26
27
Updated: February 23, 2007 EB-2005-0501 Exhibit D1 Tab 3 Schedule 5 Page 25 of 35
The Customer-1 application is the predominant part of the Customer Information System (“CIS”) 1
suite of applications. It provides the technology backbone for billing, customer care, field 2
services, and open market services to customers and key constituents. 3
4
The upgrading of the CIS platform that started in 2006 and carried into 2007 will improve the 5
operational efficiency of this aging system by reducing the time and effort required to maintain 6
and make changes to the system. The project also consists of the creation of a Customer Data 7
Mart which will result in a new customer information repository. This will allow for the more 8
cost efficient use of customer information for managing assets, outages, work programs, and 9
reporting. 10
11
Undertaking the Hybrid project will enable the CIS application to remain functional until its 12
upgrade or replacement in 2011. It is expected through investment in a Hybrid program, rather 13
than in replacement of the existing CIS application at this time, that Hydro One will maintain 14
flexibility and have a number of options available to it in light of the Government’s smart 15
metering program. 16
17
2.4.3 CTI Upgrades 18
19
This project completes the work begun in 2005 to upgrade the contact centres’ applications 20
required for the computer-telecom-interface (CTI) technology which enables contact centre 21
agents to handle customer inquiries in a variety of media, such as telephone calls, emails, faxes 22
and posted letters. These changes will provide for the requisite flexibility to meet growing and 23
changing customer needs going forward. This project is allocated fully to Distribution accounts. 24
Updated: February 23, 2007 EB-2005-0501 Exhibit D1 Tab 3 Schedule 5 Page 26 of 35
1
2.4.4 ACPi/WEP Project 2
3
This project will complete the IT provisioning for work planning, crew scheduling, dispatching 4
and time recording functions to the Lines of Business users such as Customer Operations, Grid 5
Operations and E&CS. The result will be the Work Planning and Reporting System (WPRS). 6
7
This will be achieved by leveraging the system integration tool that is being delivered through 8
the ACPi (ArcFM, CSS, Passport integration) project. The WEP project will add work planning 9
and crew scheduling plus the application to view assigned activities for time capture and job 10
status. New applications will be utilized by Customer Operations regarding the dispatch of the 11
high-volume of short duration jobs. 12
13
While the project's main function is to deliver the integrated tools mentioned above, the business 14
benefits also include process alignment between the LOBs to plan work and schedule crews 15
between their organizations more effectively. This will facilitate program management in the 16
future once the businesses have completed their transitional learning curve. 17
18
There is a wide range of benefits for this project including efficiency in resource utilization by 19
organizing work orders by geographical area and better tracking of resource assignments. There 20
are additional benefits for Finance in the areas of time capture and up front time approval. 21
22
The WEP application will interface with the Cornerstone solution through the use of hub 23
technology developed in the ACPi project. 24
25
2.4.5 IREIS Project 26
27
This project converts and stores geospatial information data, which will be accessed through the 28
Integrated Real Estate Information System. 29
Updated: February 23, 2007 EB-2005-0501 Exhibit D1 Tab 3 Schedule 5 Page 27 of 35
1
2.4.6 Mobile IT Project 2
3
Mobile IT ($2.9 million in each of 2007 and 2008) will equip field forces with the tools required 4
to access current and planned asset data applications when in the field. This project also 5
supports the Company’s response to staff and vehicle location safety needs, Smart Network 6
preparedness and Smart Metering initiatives. The project will utilize the functionality made 7
available through the Cornerstone project. This investment provides additional commercial 8
software products, enhancements to existing software products and the installation, configuration 9
and integration of those products along with associated hardware (database and application 10
servers and upgraded hand-held devices). This project will permit field management and staff 11
access to critical systems and information regarding work crew projects, field assets and optimal 12
scheduling as part of work management processes. 13
14
2.4.7 Asset Data Collection and Data Mart Project 15
16
Work related to converting older drawings to digital files has resulted in portions of the project 17
being postponed into 2007. 18
19
Through the use of handheld tablets system information data is being collected on the current 20
state of the Distribution system. Project costs of $0.6 million in 2006 concludes the work to 21
enhance existing software applications used to collect and store information on the location, 22
condition, and connectivity of distribution line assets in the field. The scope of the project 23
provides software to analyze the information and allow it to be transferred and used in the 24
corporate Geographical Information System (GIS). The information will assist in the efficient 25
expansion, operation, and maintenance of the distribution system. 26
27
Updated: February 23, 2007 EB-2005-0501 Exhibit D1 Tab 3 Schedule 5 Page 28 of 35
3.0 FACILITIES & REAL ESTATE 1
2
This section addresses the capital expenditures that are required to acquire (own or lease) and 3
maintain Hydro One Networks Inc.’s workspace (office space and service centres). The 4
transmission facilities represents approximately $3.8 M of overall capital estimated spending in 5
2007 and $4.1 million in 2008, as illustrated in Table 7, below. 6
7
Table 7 8
Total Real Estate Capital Expenditures ($ Millions) 9
10
Historic Bridge Test Years Allocated to
Transmission
Description 2003 2004 2005 2006 2007 2008 2007 2008
Major 2.3 5.1 2.6 3.0 6.8 7.3 3.8 4.1
MFA 0.5 0.8 0.0 0.6 0.4 0.4 0.2 0.2
Total 2.8 5.9 2.6 3.6 7.2 7.7 4.0 4.2
11
3.1 Major Capital 12
13
The Real Estate major capital program allows for the provision of workspace of head office 14
facilities, including Ontario Grid Control Centre – Barrie, field administrative & service centre 15
facilities, and other work locations such as the London call centre. 16
17
The capital program focuses on undertaking critical component replacement work on a priority 18
basis (e.g. roof replacement). As a result of the planned and corrective replacement of these 19
critical components, the amount of capital spent varies year over year. Contracted facility service 20
providers conduct regular inspections of administrative and service centre sites across the 21
province to ensure critical building/site components are inspected regularly and major structural 22
and related problems are identified. Maintaining building and site assets in a condition that 23
Updated: February 23, 2007 EB-2005-0501 Exhibit D1 Tab 3 Schedule 5 Page 29 of 35
ensures their longer-term viability, while meeting the workspace needs of employees on a day to 1
day basis, is critical to the successful completion of a variety of corporate work activities. 2
Equally important is ensuring that employee workspaces are consistently maintained to a 3
standard that meets current work requirements and complies with all corporate, legislative and 4
other related safety and environmental regulations. This program also considers the facilities 5
portfolio accommodation strategy in terms of facility improvements, building additions, and new 6
facilities in line with the Company’s changing operational requirements. 7
Key Program work activities include: 8
9
• Replacement of major building components including roof structures, windows, heating, 10
ventilating and air conditioning (HVAC) systems and other structural elements and building 11
systems; 12
• Dealing with environmental issues that may arise such as mould; 13
• Water treatment upgrades to improve quality and reliability of water supply, including 14
conversions to municipal supply; 15
• Facilities Improvements: Service, Administrative Centres; and 16
• Head Office and Administrative Facilities - New/ Additional workspace demand – 17
accommodation planning. 18
19
The level of funding in the bridge period and test years provides for facilities improvements, 20
resulting from assessments of aging facilities infrastructure across the Province. The facilities 21
infrastructure base is comprised mainly of aged buildings, legacy building systems and 22
components, many of which are reaching the end of their asset life cycle. 23
24
3.2 Minor Fixed Assets (MFA) 25
26
As noted in Table 7 above, spending on MFA is generally less than $1 Million each year and is 27
spent on replacement of furniture. 28
29
Updated: February 23, 2007 EB-2005-0501 Exhibit D1 Tab 3 Schedule 5 Page 30 of 35
4.0 TRANSPORT AND WORK EQUIPMENT (TWE) 1
REPLACEMENT PROGRAM 2
3
This section identifies the TWE capital expenditures for the period 2003 to 2008. The increase 4
in capital expenditures is directly related to the increase in work programs. Fleet capital 5
requirements are primarily based on industry standards (manufacturer’s recommendations) for 6
life cycle expectancy, the remaining capital value, and operating cost drivers which are then 7
linked to the Business Plan and Work Programs. Light vehicles are replaced after 6 years or 8
180,000 km, service trucks are replaced after 6 years or 200,000 km, and work equipment is 9
replaced after 8 to 10 years or 230,000 km. 10
11
Table 8 12
Capital Expenditures From 2003 – 2008 ($ Millions) 13
14
Historic
Bridge
Test Years
Allocated to
Transmission
2003 2004 2005 2006 2007 2008 2007 2008
Total Cost 53.5 13.5 40.5 41.2 43.5 40.6 10.4 9.7
15
The objective of the TWE Replacement Program is to promote an orderly system of purchasing 16
and funding a standardized fleet replacement process and to plan for future transportation 17
requirements. The TWE Replacement Program annually analyzes 5-year cycles for capital 18
investment requirements and maintains a safe and efficient fleet. It is critical to evaluate and 19
forecast spending requirements to minimize fluctuating spending patterns and to stabilize long 20
term capital investment. The fleet capital program, on an annual basis, is evaluated against the 21
business plan and is subject to the work program prioritization and forecasting process. 22
23
Business cases for the program are prepared and approved and the equipment is strategically 24
procured through a tendering process. 25
Updated: February 23, 2007 EB-2005-0501 Exhibit D1 Tab 3 Schedule 5 Page 31 of 35
The TWE Replacement Program reviews: 1
2
• Equipment capital forecast; 3
• Equipment productivity, functionality, and future requirements; 4
• Equipment standards, equipment age, mechanical condition, kilometers traveled and cost per 5
kilometer, downtime, and repair time; 6
• Safety/risk; 7
• Work programs, evaluating staff and equipment complement; 8
• Tendered procurement process; 9
• Fleet's Original Capital Value and Net Book Value; 10
• Historical and future utilization; 11
• Strategic procurement; and 12
• Cost versus 5-year business plan. 13
14
The guidelines for vehicles considered for replacement are based on vehicles meeting 15
predetermined criteria including, but not limited to: manufacturer’s life expectancy, average cost 16
per kilometer, regulated maintenance standards, safety/risk, and beneficial purchasing cycles. As 17
vehicles reach the targeted criteria, a vehicle maintenance evaluation is performed and, in some 18
cases, the unit may be reassigned to other functions with “low usage” requirements. The 19
replacement program measures the age and value of the fleet and meets the requirements and due 20
diligence of a typical Utility fleet. 21
The benefits of our replacement program include: 22
23
• Maximum safety, productivity and utilization; 24
• Minimum downtime, repair time, and fleet complement; 25
• Reduced operating costs. 26
27
Updated: February 23, 2007 EB-2005-0501 Exhibit D1 Tab 3 Schedule 5 Page 32 of 35
4.1 2003 to 2008 Period Analysis 1
2
Hydro One Networks Inc. Fleet Operations has increased its yearly capital expenditures 3
significantly in order to replace its aging equipment. 4
5
Over the 2003 to 2008 period, the Sustainment, Development, and Operations work programs 6
have grown by over 70% and is aligned with the growth of the TWE replacement program. 7
8
$20 million of planned capital was brought forward to 2003 from 2004 based on the substantial 9
increase in the work program for 2004 and 2005. This advancement was justified and approved 10
to allow for the equipment to be manufactured and available for January 2004. This reduced the 11
requirement for high cost short-term rentals and took advantage of 2003 strategic procurement 12
contracts. This resulted in totals of $53.5 million in 2003 and $13.5 million in 2004. 13
14
As noted in Exhibit C1, Tab 4, Schedule 1, the overall size of Hydro One Networks Inc.'s fleet 15
was adjusted to 4,522 vehicles and other equipment in 2005 to match the work programs. New 16
vehicles costs were $41.2 million in 2006 and are forecast to increase in 2007 ($43.5 million), 17
then decrease into 2008 ($40.6 million) based on the number of vehicles required to execute the 18
planned work programs. The peak in 2006 and 2007 is primarily related to specialized 19
equipment supporting the expanded capital work programs. 20
21
4.2 Capital vs. Operating Leases 22
23
The evaluation of leasing as a financial alternative to the approved capital program was 24
evaluated during the 2003 strategic sourcing initiative. The evaluation included the review of 25
both capital and operating leases and the total operating costs. The risks and benefits generated 26
by leasing were evaluated and it was decided the risks outweighed the modest benefits. The 27
results therefore indicated that leasing was not cost effective. 28
29
Updated: February 23, 2007 EB-2005-0501 Exhibit D1 Tab 3 Schedule 5 Page 33 of 35
The requirement for short term rentals (as distinct form long term rentals) is recognized and is 1
included with our operating expenses in Exhibit C1, Tab 4, Schedule 1. 2
3
4.3 Procurement Initiatives 4
5
Fleet Services follow capital procurement objectives for material and service, listed below, to 6
achieve cost reductions over the next five years: 7
8
• Profile the commodities, collect and analyze cost drivers; 9
• Analyze the supply market; 10
• Develop a strategy for sourcing; 11
• Select the suppliers through a rigorous RFP process; 12
• Conduct negotiations. 13
14
These procurement initiatives have allowed Hydro One Networks Inc. to lock in pricing for 3 15
year terms with preferred vendors. 16
17
5.0 SERVICE EQUIPMENT 18
19
Table 9 below identifies the expenditures for Service Equipment for the 2003 to 2008 period. 20
21
Table 9 22
MFA Service Equipment 2003 – 2008 ($ Millions) 23
24
Historic Bridge Test Years Allocated to Transmission
2003
2004
2005
2006
2007
2008
2007
2008
Total Cost 6.4 4.9 3.1 3.9 7.3 6.5 3.1 2.8
25
Updated: February 23, 2007 EB-2005-0501 Exhibit D1 Tab 3 Schedule 5 Page 34 of 35
Minor fixed assets for service equipment represents capital items ≥ $2,000 required by our staff 1
to carry out the construction and maintenance work programs. Capital items < $2,000 are 2
expensed to OM&A. Minor fixed asset expenditures for service equipment are required to 3
replace end of life service equipment, replace technologically obsolete service equipment when 4
new standards and safer work practices come into effect, and provide for sufficient levels of new 5
service equipment consistent with work program expansion. 6
7
Purchases in this category include specialized transportation equipment for off-road work sites 8
and mobile equipment required to carry out a variety of work. 9
10
Specialized transportation equipment includes equipment such as all terrain vehicles, boats, 11
barges, snowmobiles and related accessories. 12
13
Mobile equipment includes oil tankers, degassifiers, and dry air machines required for 14
transformer maintenance, SF6 gas carts required for the maintenance of SF6 breakers, and a 15
variety of other miscellaneous equipment necessary to analyze, test, and carry out the 16
construction and maintenance of the transmission work program. 17
18
Year over year changes in spending are the result of end-of-life replacement of specific large 19
equipment. For example, oil tankers, degassifiers, and air supply equipment used to overhaul and 20
maintain large power transformers and manage the related oil requirements. Spending in 2007 21
and 2008 is focused on additional service equipment required to accommodate the growth in the 22
work program. 23
24
Updated: February 23, 2007 EB-2005-0501 Exhibit D1 Tab 3 Schedule 5 Page 35 of 35
6.0 OTHER SHARED SERVICES 1
2
Table 10 3
Other Shared Services Capital ($ Millions) 4
5
Historic Bridge Test Years Allocated to Transmission
2003
2004
2005
2006
2007
2008
2007
2008
Total Cost (0.1) (2.2) 3.1 6.1 0 0 0 0
6
Other costs comprise a variety of minor element costing. 7
8
2003 to 2005 costs represent an (over)/under recovery of burdened rates which were assessed to be 9
attributable to the capital program, but not applied back to specific programs; as well as other 10
adjustments to capital projects. 11
12
The 2006 other costs represent capital contribution adjustments in accordance with OEB 13
compliance bulletins. 14
15