Ce document est la propriété d’EDF. Toute diffusion externe du présent document ou des informations qu’il contient est interdite. D AND D PROJECTS HOW TO ORGANIZE THE TRANSITION PERIOD FROM TAILORED APPROACH TO STANDARDIZED APPROACH AIEA SEMINAR-September 2016-KOREA

D AND D PROJECTS HOW TO ORGANIZE THE TRANSITION · PDF fileD AND D PROJECTS HOW TO ORGANIZE THE TRANSITION PERIOD ... (Post Operational Clean Out) ... How to organize the transition

Embed Size (px)

Citation preview

Page 1: D AND D PROJECTS HOW TO ORGANIZE THE TRANSITION · PDF fileD AND D PROJECTS HOW TO ORGANIZE THE TRANSITION PERIOD ... (Post Operational Clean Out) ... How to organize the transition

Ce document est la propriété d’EDF. Toute diffusion externe du présent document ou des informations qu’il contient est interdite.

D AND D PROJECTS HOW TO ORGANIZE THE TRANSITION PERIODFROM TAILORED APPROACH TO

STANDARDIZED APPROACH

AIEA SEMINAR-September 2016-KOREA

Page 2: D AND D PROJECTS HOW TO ORGANIZE THE TRANSITION · PDF fileD AND D PROJECTS HOW TO ORGANIZE THE TRANSITION PERIOD ... (Post Operational Clean Out) ... How to organize the transition

| 2

Cette réunion aborde des sujets sensibles dont la divulgation peut être préjudiciable àEDF. Chacun s’engage à n’en communiquer les supports et à n’e n relater les échangesqu’avec discernement et en mentionnant explicitement « à ne pas rediffuser / à ne pasdivulguer ».

Cette réunion aborde des sujets de nature confidentielle . Chacun s’engage à tenir secrètesles informations tant écrites qu’orales qui y sont exposées .

Chaque dépositaire de cette présentation s’interdit de la c ommuniquer à quelque tiers quece soit sans l’accord du président de séance.

Chaque salarié s’engage à traiter de façon responsable les i nformations qu’il détient dans le cadrede son travail et respecter les règles de sécurité et de confi dentialité, en particulier concernant lesdonnées sensibles.

CHARTE ÉTHIQUE GROUPE

« Ce document est la propriété d’EDF. Toute diffusion externe du présent document ou des informations qu’il contient est interdite »

CE SLIDE EST DESTINE A RESTER MASQUE. IL PERMET DE CATAGORISER LANATURE DE LA REUNION

PROTEGER LE PATRIMOINE DU GROUPE

Page 3: D AND D PROJECTS HOW TO ORGANIZE THE TRANSITION · PDF fileD AND D PROJECTS HOW TO ORGANIZE THE TRANSITION PERIOD ... (Post Operational Clean Out) ... How to organize the transition

| 3How to organize the transition period | 09/2016

TABLE OF CONTENTS

1. WHAT COULD BE A DEFINITION OF TRANSITION PERIOD

2. A SHORT REMINDER OF THE EDF NPP UNDER DISMANTLING

3. PWR FRENCH CASE-SETTING THE FUNDING

4. PWR FRENCH CASE-PREPARING THE DISMANTLING OF THE FI RST PWR 900 MW TWIN UNIT

Page 4: D AND D PROJECTS HOW TO ORGANIZE THE TRANSITION · PDF fileD AND D PROJECTS HOW TO ORGANIZE THE TRANSITION PERIOD ... (Post Operational Clean Out) ... How to organize the transition

| 4

WHAT IS THE TRANSITION PERIOD ?

For french people, according to regulatory frame, i t is the period between the final shutdown date and the dismantling decree.

On a practical point of view, this is the period fr om final shutdown to the beginning of the first significant dismantling works.

Final shutdown

Start of dismantling

phase

Transition period

Former operation rulesDismantling operation

rules

Theoretical planning How to organize the transition period | 09/2016

Page 5: D AND D PROJECTS HOW TO ORGANIZE THE TRANSITION · PDF fileD AND D PROJECTS HOW TO ORGANIZE THE TRANSITION PERIOD ... (Post Operational Clean Out) ... How to organize the transition

| 5

WHY A 5 YEARS DURATION FOR THE TRANSITION PERIOD ?

The transition period is an opportunity to launch s ome activities :

At Sellafield , it is called POCO phase (Post Operational Clean Out)

No duration is given, but based on previous project s and international feedback , we assume that this period will last fro m 4 to 5 years :

•Fuel removal from site is expected to last 4,5 years

•dismantling files review by safety authority last 3 years ( not including stop and go

periods due to safety authority questions) . Then after the decree publication, it is

possible to wait one year before the dismantling decree is put in force.

Preparing the dismantlingphase :

caracterization, licensing

Reducing the radiologicaland chemical risks :

defuelling , decontamination

How to organize the transition period | 09/2016

Page 6: D AND D PROJECTS HOW TO ORGANIZE THE TRANSITION · PDF fileD AND D PROJECTS HOW TO ORGANIZE THE TRANSITION PERIOD ... (Post Operational Clean Out) ... How to organize the transition

| 6

WHEN TO START THE TRANSITION PERIOD RELATED ACTIVITIES ?

Key factor : to start to think about it obviously before shutdown ( at least 5 years before).

Following fields need time to come to maturity :

How to organize the transition period | 09/2016

Setting wasteroutes

consolidatingD and D funds

setting the licensingframe with the Regulator

planning the staff decreasing curve

training the labour force

preparing the contracts

Page 7: D AND D PROJECTS HOW TO ORGANIZE THE TRANSITION · PDF fileD AND D PROJECTS HOW TO ORGANIZE THE TRANSITION PERIOD ... (Post Operational Clean Out) ... How to organize the transition

| 7

EDF HAS A LONG EXPERIENCE IN DECOMMISSIONING AND WASTE MANAGEMENT

More than 15 years experience :

� EDF has taken 9 units from operatingto decommissioning : 1 PressurisedWater Reactor, 1 Heavy Water

� EDF is a also in preparing AGRdecommissioning that will begin by mid2020s - all closed in early 2030s

� More than 25 years in waste treatment through Socodei (our wastetreatment subsidiary based in France created in 1990)

� Melting, incineration, onsite waste treatment operations

EDF plants under decommissioning : 2- BrennilisCommission date: 1967Shut-down date: 1985

1- ChoozCommission date : 1967Shut-down date: 1991

3- Saint Laurent ACommission dates : 1969 & 1971Shut-down dates: 1990 & 1992

5- Bugey 1Commission date : 1972Shut-down date: 1994

6- Creys-MalvilleCommission date : 1986Shut-down date: 1998

4- Chinon ACommission dates: 1963, 1965 & 1966Shut-down dates: 1973 , 1985 & 1990

Waste treatment operations

Heavy Water Reactor

Pressurized Water Reactor

UNGG ReactorFast-neutron Reactor

How to organize the transition period | 09/2016

EDF recently created a dedicated division to accele rate its development in the waste treatment and decommissioning market

Page 8: D AND D PROJECTS HOW TO ORGANIZE THE TRANSITION · PDF fileD AND D PROJECTS HOW TO ORGANIZE THE TRANSITION PERIOD ... (Post Operational Clean Out) ... How to organize the transition

| 8

EDF’S DEDICATED DIVISION TO DECOMMISSIONING AND WASTE MANAGEMENT

EDF CEO

EDF Group Executive Director for Nuclear & Thermal generation (DPNT)

Decommissioning andWaste Management Division

(DP2D)

�DP2D Division created in 2016

�Directly linked to the executive committee of EDF

�Now 900 people working on Decommissioning & Waste Management

� In charge of :

— EDF’s nuclear dismantlement program worldwideamong which preparing our PWR future decommissioning (thirty four 900 MW, twenty 1 300 MW, four PWR 1 450 MW)

— Managing waste generated by EDF’s nuclear power plants

— Managing and developing waste treatment assets

Existing waste treatment assets in France, Sweden and UK

How to organize the transition period | 09/2016

Page 9: D AND D PROJECTS HOW TO ORGANIZE THE TRANSITION · PDF fileD AND D PROJECTS HOW TO ORGANIZE THE TRANSITION PERIOD ... (Post Operational Clean Out) ... How to organize the transition

| 9

A DEDICATED DEPARTMENT FOR PWR UNITS D AND D

Chooz dismantling project

FOAK site ( 900 MMW-twin units)

Standardisation project

Dismantling decree obtained in 2018

Internals segmentation to start in 2017

How to organize the transition period | 09/2016

Basic design in progress

Dismantling decree file to be ready by the end of 2018

Overall budget for GEN2 dismantling set up

Documentation collection methods set up

TARGET: to take advantage of the experience feed ba ck and to be able consolidate it in a fleet approa ch

CURRENT PROGRESSPROJECTS

Page 10: D AND D PROJECTS HOW TO ORGANIZE THE TRANSITION · PDF fileD AND D PROJECTS HOW TO ORGANIZE THE TRANSITION PERIOD ... (Post Operational Clean Out) ... How to organize the transition

| 10

EDF INITIATED LONG TIME AGO A DOCUMENTED APPROACH TO SET UP THE FUNDING

Since the middle of 90th EDF is working on preliminary studies for the dismantling of PWR fleet in order to secure the amount of the dismantling founds.

The basis of the study is the dismantling of 4 « 900MW reactors » locatedin Dampierre

A first phase ended in 1998

A second one ended in 2009 in order to be more accurate and to take intoaccount the national and international experience feedback

In 2015, the file has be reviewed a commission of national experts on behalf of the Ministry of Economy. They have concluded that the methodto estimate the budget was correct and that the budget target is adequate

How to organize the transition period | 09/2016

Page 11: D AND D PROJECTS HOW TO ORGANIZE THE TRANSITION · PDF fileD AND D PROJECTS HOW TO ORGANIZE THE TRANSITION PERIOD ... (Post Operational Clean Out) ... How to organize the transition

| 11

PWR 900 MW: PARTICULAR CASE OF THE FIRST SITE

Set up of a project organisation in order to be prepared when the decision of shutdown will be taken

� without knowing formally the name of the site that will be choosen.

How to organize the transition period | 09/2016

France through the « energy transition law » decides to limit the nuclear power

to 63.2 GW

2015

When the Flamanville 3 EPR will be put in operation , two 900MW reactors

must be permanently shutdownSince end of 2012

Page 12: D AND D PROJECTS HOW TO ORGANIZE THE TRANSITION · PDF fileD AND D PROJECTS HOW TO ORGANIZE THE TRANSITION PERIOD ... (Post Operational Clean Out) ... How to organize the transition

| 12

PWR 900 MW: SETTING A D AND D PROJECT ORGANISATION

The GEN 1 and the international feed back have been collected and analysed.

A Project risk analysis has been conducted :The following concerns appeared

� The D and D project must be a waste driven one

� securing the budget to suit the allocated dismantling founds

� Particular attention must be paid to knowledge management and specifically to configuration management

� Good preparation of the transition period is the key of the success of the dismantling phase

� Thinking of industrial policy have to be done as early as possible

How to organize the transition period | 09/2016

1

2

Page 13: D AND D PROJECTS HOW TO ORGANIZE THE TRANSITION · PDF fileD AND D PROJECTS HOW TO ORGANIZE THE TRANSITION PERIOD ... (Post Operational Clean Out) ... How to organize the transition

| 13

DECOMMISSIONNING BUSINESS MODEL

Knowledge

management

Engineering

Permitting

Waste routes

Requirements

Transition period Dismantling phase

Configuration milestones

1. Circuits are decontaminated

2. Fuel is evacuated3. Operating HLW are

evacuated4. Chemical wastes are

evacuated5. Dismantling HLW are

evacuated 6. Metalic HL/IL and VLL

are evacuated7. Concrete HL/IL and

VLL are decontaminated

8. Buildings are demolished

9. Site ready for nuclear clearance

OperatingBudget Dismantling

FundsWaste storage

Funds€

Risks Costs

t

Spent fuel

management

services

ILLL

Wastes

HL/IL

Wastes

VLL

Wastes

Conventionnal

wastes

Hazardous

productsRecoverable

materials

Nuclear site

clearance

1

2

34 5 6 7 8 9

Page 14: D AND D PROJECTS HOW TO ORGANIZE THE TRANSITION · PDF fileD AND D PROJECTS HOW TO ORGANIZE THE TRANSITION PERIOD ... (Post Operational Clean Out) ... How to organize the transition

| 14

PWR 900 MW: PROJECT ORGANISATION

How to organize the transition period | 09/2016

PROJECT MANAGER

CONFIGURATION MANAGER

WASTE MANAGERTRANSITION MANAGER

LICENSING FILE MANAGER

ENGINERING MANAGER

Cost, schedulereporting

Feed back manager ,

industrial policy

Page 15: D AND D PROJECTS HOW TO ORGANIZE THE TRANSITION · PDF fileD AND D PROJECTS HOW TO ORGANIZE THE TRANSITION PERIOD ... (Post Operational Clean Out) ... How to organize the transition

| 15

WHAT KIND OF ACTIVITIES DURING TRANSITION PERIOD

�Progressive shutdown of systems

�Removal of hazardous materials and fluids

�Collect of equipment that are identified as spare parts for other plants of the fleet

�Post operationnal cleaning ( drainage,decontaminationof circuits) and zonage optimisation

�Operation waste removal from site

�Dismantling of turbine hall

�building waste temporary storage areas, waste treatment workshops

�Characterisation of nuclear waste

�onstruction/modification of support systems ( ancillary systems)

Operation team

modifications team

How to organize the transition period | 09/2016

CONCLUSION: the transition period must be

considered and managed as an outage lasting 5 years

Page 16: D AND D PROJECTS HOW TO ORGANIZE THE TRANSITION · PDF fileD AND D PROJECTS HOW TO ORGANIZE THE TRANSITION PERIOD ... (Post Operational Clean Out) ... How to organize the transition

| 16

ROLE OF FORMER OPERATING PERSONNEL DURING TRANSITION PERIOD

�Avoids a brutal change in the management of the staff

�Eases the re- deployment of some staff in other power plants.

Point of attention:

the staff costs are quite significant and therefore, particular attention has to be paid

to make suitable the number of staff regarding activities and to avoid « iddling» staff

that would be detrimental for both the Company and the personnel themselves

How to organize the transition period | 09/2016

Decree in force

the nuclear safety responsability

remains under the responsability of the

EDF Department in charge of the

nuclear production

the nuclear safety responsability

belongs to the EDF Department in

charge of dismantling.

Page 17: D AND D PROJECTS HOW TO ORGANIZE THE TRANSITION · PDF fileD AND D PROJECTS HOW TO ORGANIZE THE TRANSITION PERIOD ... (Post Operational Clean Out) ... How to organize the transition

| 17

DEMOBILIZATION CURVE: A REAL CHALLENGE

?

How to organize the transition period | 09/2016

EDF headcount

EDF headcount

Production stop

DEM decree

End of dismantling End of demolition

End of cleaning up

Years

Page 18: D AND D PROJECTS HOW TO ORGANIZE THE TRANSITION · PDF fileD AND D PROJECTS HOW TO ORGANIZE THE TRANSITION PERIOD ... (Post Operational Clean Out) ... How to organize the transition

| 18

PWR TWIN UNIT DISMANTLING - EDF STAFFING

Driver for staffing during the transition phase : fuel removal from site

Until the fuel is removed from site, Internal Emergency Plan( PUI) needs that around 225 EDF personnel be kept to ensure PUI duty roaster

The policy , not yet approved would be to aim at multicompetencies and group for example :

� electrical and I/C� mechanical and valves maintenance

How to organize the transition period | 09/2016

Page 19: D AND D PROJECTS HOW TO ORGANIZE THE TRANSITION · PDF fileD AND D PROJECTS HOW TO ORGANIZE THE TRANSITION PERIOD ... (Post Operational Clean Out) ... How to organize the transition

| 19

TRAINING PEOPLE

When CIDEN (former Decommissioning division in EDF) was created in 2003, the engineers in place were accustomed to work on the operating plants modifications. Only a few knew about dismantling and waste management.

Therefore, at the very beginning, CIDEN organized training courses to give to all the concerned engineers the basic knowledge on dismantling process and related engineering fields.

3 main training sessions were organized about :

• general knowledge about dismantling activities design• site surveillance activities• safety culture

In parallel, some specific training was organized about waste management (nuclear or conventional, radioprotection, environment aspects …).

How to organize the transition period | 09/2016

Page 20: D AND D PROJECTS HOW TO ORGANIZE THE TRANSITION · PDF fileD AND D PROJECTS HOW TO ORGANIZE THE TRANSITION PERIOD ... (Post Operational Clean Out) ... How to organize the transition

| 20

CONCLUSION

� Transition period : A key phase to ensure the sucess of the dismantling phase

� Technical point of view : mainly a clean out phase (the Sellafield term –POCO is quite adequate)

� The management of the phase can be considered as an outage that would last 4 to 5 years

� Success of this transition period : only ensured if some strategic aspects are analyzed and solved before final shutdown , such as : � Waste routes� Fundings� Staff and stake holders consideration

How to organize the transition period | 09/2016