Upload
evadne
View
45
Download
0
Embed Size (px)
DESCRIPTION
Current Telemetry Dashboards. NDSWG August 18, 2009. QSE Telemetry (as of 08/10/09). TDSP Telemetry (as of 08/10/09). Load Observability (as of 08/10/09). State Estimator Daily Convergence Rates: July 2009. http://nodal.ercot.com 5. - PowerPoint PPT Presentation
Citation preview
Lead from the frontTexas Nodalhttp://nodal.ercot.com 1
Current Telemetry Dashboards
NDSWG
August 18, 2009
Lead from the frontTexas Nodalhttp://nodal.ercot.com 2
QSE Telemetry (as of 08/10/09)
Lead from the frontTexas Nodalhttp://nodal.ercot.com 3
TDSP Telemetry (as of 08/10/09)
Lead from the frontTexas Nodalhttp://nodal.ercot.com 4
Load Observability (as of 08/10/09)
Lead from the frontTexas Nodal
State Estimator Daily Convergence Rates: July 2009
http://nodal.ercot.com 5
2009 Monthly Convergence %
Jan: 80% Feb: 70% Mar: 90% Apr: 86% May: 77% Jun: 88% Jul: 87%
Lead from the frontTexas Nodalhttp://nodal.ercot.com 6
State Estimator Monthly Convergence Rates: May 2009 – July 2009
2009 Monthly Convergence %
Jan: 80% Feb: 70% Mar: 90% Apr: 86% May: 77% Jun: 88% Jul: 87%
Lead from the frontTexas Nodal
July 2, 2009
0102030405060708090
100
1 2 3 4 5 6 7 8 9
Test Hour
Co
nv
erg
en
ce
%
0900
1000
1100
1200
1300
1400
1500
1600
1700
Hour Ending
July 1, 2009
0102030405060708090
100
1 2 3 4 5 6 7 8 9
Test Hour
Co
nv
erg
en
ce
%
0900
1000
1100
1200
1300
1400
1500
1600
1700
Hour Ending
June 30, 2009
0102030405060708090
100
1 2 3 4 5 6 7 8 9
Test Hour
Co
nv
erg
en
ce
%
0900
1000
1100
1200
1300
1400
1500
1600
1700
Hour Ending
Key Numbers: 91% Test Average Convergence; 100% for 11 of 27 Test Hours. The majority of
issues were attributable to zonal-nodal mismatches. On June 30, eight of nine test hours achieved convergence rates of 92% or
higher. All issues were attributable to Manual Replacements (MRs) necessary to address zonal-nodal mismatches.
• On July 1, five of nine hours achieved convergence rates of 92% or higher. Convergence rates were affected intermittently throughout the day owing to MRs necessary to accommodate a group of wind farms moving Inter-Control Center Communication Protocol (ICCP) service to a different provider. A nodal database load was conducted in the afternoon, but it did not significantly affect State Estimator convergence.
On July 2, additional MRs were needed throughout the day to accommodate intermittent wind telemetry (carry-over issue from Day Two). MRs were also necessary throughout the day to address a known reactive capability curve issue that was limiting the ERCOT State Estimator’s ability to recognize MVAR values beyond a pre-defined limit (this curve issue was later addressed through code enhancements that were deployed on July 15).
http://nodal.ercot.com 7
FIT III, Week 10 – State Estimator
Lead from the frontTexas Nodal
July 14, 2009
0102030405060708090
100
1 2 3 4 5 6 7 8 9
Test Hour
Co
nve
rgen
ce %
0900
1000
1100
1200
1300
1400
1500
1600
1700
Hour Ending
Key Numbers:
91% Test Average Convergence; 100% for 14 of 27 Test Hours. The majority of issues were attributable to zonal-nodal mismatches.
Day One:
On July 14, the average convergence for the test day finished at 91%. Rates of 92% or higher were achieved during 6 of 9 test hours. Notable issues occurred during the following test hours:
Hour Ending (HE) 0900- the hourly convergence rate dipped to 75% as Manual Replacements (MRs) were made to address telemetry issues that accumulated during the non-Business Hours immediately prior to testing.
HE 1300- the hourly convergence dipped to 86% as MRs were made to adjust telemetry values for a failed Inter-Control Center Communication Protocol (ICCP) link.
HE 1600- the hourly convergence dipped to 75% as MRs were made to adjust telemetry values for a failed ICCP link.
http://nodal.ercot.com 8
FIT III, Week 11 – State Estimator
Lead from the frontTexas Nodal
Day Two:
On July 15, the average convergence for the test day finished at 85%. Rates of 92% or higher were achieved during 5 of 9 test hours. Notable issues occurred during the following test hours:
HE 0900- the hourly convergence dipped to 42% as MRs were made to address telemetry issues that accumulated during the non-Business Hours immediately prior to testing (i.e., same issue as on Day One).
HE 1000- the hourly convergence dipped to 79% as MRs were made to address zonal-nodal mismatches.
HE 1400- the hourly convergence dipped to 82% as MRs were made to address zonal-nodal mismatches.
HE 1700- the hourly convergence dipped to 77% as MRs were made to adjust telemetry values for a failed ICCP link.
A nodal database load was performed in the afternoon, but it did not significantly affect State Estimator convergence rates for the test day.
http://nodal.ercot.com 9
FIT III, Week 11 – State Estimator (continued)
July 15, 2009
0102030405060708090
100
1 2 3 4 5 6 7 8 9
Test Hour
Co
nve
rgen
ce %
0900
1000
1100
1200
1300
1400
1500
1600
1700
Hour Ending
Note:
Code enhancements for the State Estimator exited FAT and were deployed on July 15. The enhancements were implemented to address a reactive capability curve issue that had previously limited the ERCOT State Estimator’s ability to recognize MVAR values beyond a pre-defined limit. At present, the enhancements appear to be supporting State Estimator convergence as intended.
Lead from the frontTexas Nodal
July 16, 2009
0102030405060708090
100
1 2 3 4 5 6 7 8 9
Test Hour
Co
nve
rgen
ce %
0900
1000
1100
1200
1300
1400
1500
1600
1700
Hour Ending
Day Three:
On July 16, The average convergence for the test day finished at 98%. Rates of 92% or higher were achieved during 8 of 9 test hours. Notable issues occurred during the following test hours:
HE 1000- the hourly convergence dipped to 86% as MRs were made to adjust for telemetry not yet mapped in nodal.
http://nodal.ercot.com 10
FIT III, Week 11 – State Estimator (continued)
Lead from the frontTexas Nodal
Key Numbers and Issues: 95% Test Average Convergence 92% or higher for 21 of 27 Test Hours 100% for 18 of 27 Test Hours The majority of issues that arose during the test were
attributable to zonal-nodal mismatches as well as missing nodal telemetry. Shift Engineers logged over 30 manual replacements throughout the test to address unit telemetry not yet mapped in nodal systems. This issue resulted in two noticeable drops in convergence during the test:
The first drop occurred on July 28, when Hour Ending (HE) 1100 converged at 79%.
The second drop occurred on July 29, when HE 1100 converged at 69%.
http://nodal.ercot.com 11
FIT III, Week 12 – State Estimator
Lead from the frontTexas NodalLFC04/20/23
FIT Series
Week Date Day 1 Day 2 Day 3 Average Convergence % for all Test
Hours
100% Convergence Achieved
FIT II Week 1 Oct 21 – 23, 2008 90.18 74.16 91.83 85.39 12 of 27 hrs
Week 2 Nov 04 – 06, 2008 88.17 96.58 97.11 93.95 18 of 27 hrs
Week 3 Nov 18 – 20, 2008 87.17 84.19 82.91 84.76 12 of 27 hrs
Week 4 Dec 02 – 04, 2008 96.04 93.33 93.44 94.27 14 of 27 hrs
Week 5 Dec 16 – 18, 2008 94.74 97.49 96.30 96.18 19 of 27 hrs
Week 6 Jan 13 – 15, 2009 96.00 94.12 95.78 95.30 15 of 27 hrs
Week 7 Jan 27 – 29, 2009 94.07 90.13 93.29 92.49 14 of 27 hrs
FIT III
Week 1 Feb 24 – 26, 2009 75.45 78.86 92.85 82.39 09 of 27 hrs
Week 2 Mar 10 – 12, 2009 96.82 92.97 98.41 96.07 20 of 27 hrs
Week 3 Mar 24 - 26, 2009 85.45 94.98 94.70 91.71 14 of 27 hrs
Week 4 Apr 07 - 09, 2009 97.13 92.60 97.44 95.72 21 of 27 hrs
Week 5 Apr 21 – 23, 2009 87.47 89.87 95.65 91.00 08 of 27 hrs
Week 6 May 05 – 07, 2009 94.34 94.47 91.87 93.56 13 of 27 hrs
Week 7 May 19 – 21, 2009 96.81 97.36 97.04 97.07 18 of 26 hrs*
Week 8 Jun 02 – 04, 2009 88.47 84.09 93.29 88.62 10 of 27 hrs
Week 9 Jun 16 – 18, 2009 97.45 86.14 95.59 93.06 13 of 27 hrs
Week 10 Jun 30 – Jul 2, 2009 94.91 89.89 86.66 90.49 11 of 27 hrs
Week 11 Jul 14 – 16, 2009 91.01 84.70 97.49 91.06 14 of 27 hrs
Week 12 Jul 28 – 30, 2009 95.91 94.73 93.66 94.77 18 of 27 hrs
Trends – FIT II & FIT III
12
* One hour was removed from the Week 7 test results to accommodate a nodal database load.
Lead from the frontTexas Nodalhttp://nodal.ercot.com 13
Appendix: Telemetry & State Estimator
Overview of Reports, Processes, and Data
Lead from the frontTexas Nodalhttp://nodal.ercot.com 14
ICCP
• Telemetry Support• Telemetry Reporting• State Estimator Tuning• New Telemetry Point Addition Process• Telemetry Issue Process• Current Telemetry Status• Telemetry Status Whereabouts
Lead from the frontTexas Nodalhttp://nodal.ercot.com 15
Telemetry Support
• ERCOT Full Time Staff ICCP Support– Advanced Network Applications Support 2 Engineers– Control Room 1 Operations Analyst & 1 Shift Engineer– IT 2 System Analysts– Additional Staff on a part time basis
• Market Participants– Contact for Nodal Issues– Timely Response on detected issues
Lead from the frontTexas Nodalhttp://nodal.ercot.com 16
Telemetry Dashboards
FIT II & FIT III Assessment reports are posted at: http://nodal.ercot.com/readiness/eds3/documents/index.html
• The following Telemetry Dashboards are being posted on the Readiness Center:– Observability– QSER & TDSP Telemetry
• The link for these dashboards is:
http://nodal.ercot.com/readiness/eds1/documents/index.html
• These dashboards are currently being posted monthly following each mid-month Nodal database update.
• Report questions can be sent to [email protected]
Lead from the frontTexas Nodalhttp://nodal.ercot.com 17
Telemetry Dashboards
TelemetryDashboards
}
Lead from the frontTexas Nodalhttp://nodal.ercot.com 18
Telemetry Reporting – QSER/TDSP Dashboard
QSER & TDSP Dashboard
Questions may be sent to: [email protected]
Lead from the frontTexas Nodalhttp://nodal.ercot.com 19
Telemetry Reporting – Observability Dashboard
The number of unobservable buses in the system with all pseudo measurement removed.
The number of current unobservable buses in the system that have a load at the station where
telemetry is required to make the bus observable.
Buses that are unobservable due to a PUN load at the station.
If a number other then 0 is in column B, then there is missing telemetry which requires Market Participant Corrective Action.
Questions may be sent to: [email protected]
Lead from the frontTexas Nodalhttp://nodal.ercot.com 20
Telemetry Reporting
State Estimator (SE) Convergence
• Advanced Network Applications provides analysis assistance and can be reached at the EDS2 email: [email protected]
Lead from the frontTexas Nodalhttp://nodal.ercot.com 21
State Estimator Tuning
• FIT– Monitors Telemetry– Compares Generation between Zonal & Nodal
• ICCP Support Team– Analysis Support of FIT Issues– ICCP Issue Resolution Support– Produce FIT Report
Lead from the frontTexas Nodalhttp://nodal.ercot.com 22
FIT Telemetry Reporting
FIT Report• Log of Events &
Observations– The daily logs published in
the bi-weekly FIT Reports provide a window into the types of issues that affect convergence during FIT testing hours.
• FIT Reports are posted at: http://nodal.ercot.com/readiness/eds3/documents/index.html
Questions can be sent to [email protected]
Lead from the frontTexas Nodalhttp://nodal.ercot.com 23
New Telemetry Point Addition Process
MP (QSER or TSP) has new ICCP point to
activate
MP Consults ICCP Handbook to
determine data point names
MP fills out ICCP Change Request Form
MP creates a Service Request via the Texas
Market Link on ERCOT.com
MP attaches completed ICCP
Change Request form to Service Request
ERCOT ICCP Team receives and
processes each Service Request
No
ERCOT ICCP Team contacts MP to confirm the changes
ERCOT ICCP Team notifies the MP
upon completion of the Service Request
Service Request Issues?
Yes
ERCOT ICCP Team makes changes to
ICCP
No
MP has submitted & completed
Model Change
ICCP Standards Questions?
Yes
Lead from the frontTexas Nodalhttp://nodal.ercot.com 24
Current Telemetry Issue Process
ERCOT or Market Participant detects Telemetry, ICCP or other System Issue
Market Participant investigates to
determine correct ability
Requires ERCOT assistance to
resolve?
Contact ERCOT ANA by email
[email protected] for assistance
Yes
No
ERCOT Analyzes Issue and determines
corrective action
ERCOT Contacts MP to Affect Correction
Issue Resolved?
Done
Yes
NoMP Corrects Issue
During FIT? No
Yes
Contact ERCOT Shift Engineer @
512-248-6345