“Through collaboration and leadership, we deliver a safe, reliable, and integrated transportation system that enables the movement of people and goods.” 0703_011117 WINTER • 2017 TEXAS DEPARTMENT OF TRANSPORTATION DALLAS DISTRICT I-35E PROJECT (SH 183 TO LP 12) CSJ: 0196-03-198 (DALLAS COUNTY) ESTIMATED COSTS Estimated Construction Cost $200 M SOURCE: TxDOT TxDOT graphic PROGRAMMING STATUS MTP (2040 Metropolitan Transportation Plan) NO UTP (2017 Unified Transportation Program) NO STIP (Statewide Transportation Implementation Program, 2017-2020) NO SOURCE: TxDOT TxDOT graphic PROJECT TIMELINE SOURCE: TxDOT TxDOT graphic August 2030 Estimated Letting June 8, 2005 FHWA FONSI Environmental Clearance 2030 2005 2006 - 2029 TBD – Design, Planning & Development; Funding Procurement General Purpose Lanes General Purpose Lanes General Purpose Lanes General Purpose Lanes PROPOSED TYPICAL SECTION TxDOT graphic SOURCE: Texas Department of Transportation. EXISTING TYPICAL SECTION PURPOSE AND NEED Increase capacity to accomodate growth along the corridor. Extend the I-35E Corridor improvements from the other I-35E projects already in progress, by widening the highway and adding additional lanes in each direction. PROJECT DETAILS Limits: I-35E from SH 183 to Loop 12 CSJ: 0196-03-198 Description: Reconstruct and widen from six (6) to eight (8) lanes Project Length: 2.5 miles PROJECT STATUS This project is not in the 2017 Unified Transportation Program and it is not yet funded. Dallas District Office 4777 E. Highway 80 Mesquite, TX 75150 CONTACT INFORMATION Dan Perge, P.E. TxDOT Dallas Advance Project Development Director (214) 320-6283 [email protected] NOTE: Highlighted areas are not drawn to exact scale. TxDOT graphic

CSJ: 0196-03-198 (DALLAS COUNTY) DALLAS DISTRICT I-35E ... · I-35E PROJECT (SH 183 TO LP 12) CSJ: 0196-03-198 (DALLAS COUNTY) ESTIMATED COSTS Estimated Construction Cost $200 M SOURCE:

Embed Size (px)

Citation preview

Page 1: CSJ: 0196-03-198 (DALLAS COUNTY) DALLAS DISTRICT I-35E ... · I-35E PROJECT (SH 183 TO LP 12) CSJ: 0196-03-198 (DALLAS COUNTY) ESTIMATED COSTS Estimated Construction Cost $200 M SOURCE:

“Through collaboration and leadership, we deliver a safe, reliable, and integrated transportation system that enables the movement of people and goods.”

0703

_011

117

WINTER • 2017TEXAS DEPARTMENT OF TRANSPORTATION

D A L L A S D I S T R I C T

I-35E PROJECT (SH 183 TO LP 12)CSJ: 0196-03-198 (DALLAS COUNTY)

ESTIMATED COSTSEstimated Construction Cost $200 M

SOURCE: TxDOT TxDOT graphic

PROGRAMMING STATUS

MTP (2040 Metropolitan Transportation Plan) NO

UTP (2017 Unified Transportation Program) NO

STIP (Statewide Transportation Implementation Program, 2017-2020)

NO

SOURCE: TxDOT TxDOT graphic

PROJECT TIMELINE

SOURCE: TxDOT TxDOT graphic

August 2030 – Estimated Letting

June 8, 2005 – FHWA FONSI Environmental Clearance

20302005

2006 - 2029

TBD – Design, Planning & Development; Funding Procurement

General Purpose Lanes General Purpose Lanes General Purpose Lanes General Purpose Lanes

PROPOSED TYPICAL SECTION

TxDOT graphicSOURCE: Texas Department of Transportation.

EXISTING TYPICAL SECTION

PURPOSE AND NEEDIncrease capacity to accomodate growth along the corridor. Extend the I-35E Corridor improvements from the other I-35E projects already in progress, by widening the highway and adding additional lanes in each direction.

PROJECT DETAILS

Limits: I-35E from SH 183 to Loop 12

CSJ: 0196-03-198

Description: Reconstruct and widen from six (6) to eight (8) lanes

Project Length: 2.5 miles

PROJECT STATUSThis project is not in the 2017 Unified Transportation Program and it is not yet funded.

Dallas District Office4777 E. Highway 80Mesquite, TX 75150

CONTACT INFORMATIONDan Perge, P.E.

TxDOT Dallas Advance Project Development Director(214) 320-6283

[email protected]

NOTE: Highlighted areas are not drawn to exact scale. TxDOT graphic