CS P09 Project Management

Embed Size (px)

Citation preview

  • 8/10/2019 CS P09 Project Management

    1/4

    CSL TECHNOLOGIES (M) SDN BHD

    LRC TECH (M) SDN BHD

    Ref. No. CS-P09

    Revision No. 00

    PROJECT MANAGEMENT PROCEDUREEffective Date 01/11/2010

    Page 1 of 4

    This procedure is a controlleddocument and authorized for use. When printed from this share drive,this document is uncontrolled. Before using a printed copy of this document, ensure that it is the same asthe latest version on share drive.

    REVISION HISTORY

    Rev

    No.

    Effective Date Affected

    Page

    Change Descriptions Reviewed

    By

    Approved

    By00 01/10/2010 All New Issue

    Document Distribution Acknowledgement:

    Dept. /

    Position

    Business

    Development

    Director

    Admin Sales &

    Marketing

    Design Production R&D

    Acknowledgement

    Date

    Note: The details and the reason of change are documented in the Revision History state above and file at

    DCC.

  • 8/10/2019 CS P09 Project Management

    2/4

  • 8/10/2019 CS P09 Project Management

    3/4

    CSL TECHNOLOGIES (M) SDN BHD

    LRC TECH (M) SDN BHD

    Ref. No. CS-P09

    Revision No. 00

    PROJECT MANAGEMENT PROCEDUREEffective Date 01/11/2010

    Page 3 of 4

    THIS IS AN UNCONTROLLED COPY OF A CONTROLLED DOCUMENT PRINTED

    4.0 PROCEDURE DETAILS

    4.1 SALES & ORDER PROCESS

    Process Flow Description Documents/ Ref.

    Personnel

    - SIM shall receive the confirmed

    order or project, drawing and

    relevant documents from Sales &

    Marketing Dept.

    - Confirmed BQ

    - Shop Drawing

    - SIM

    - SIM shall then liaise with the

    Production Dept to ensure the

    stock adequacy.

    - If there is a new product andnew mould have to produce, SIM

    should liaise with Production Dept

    and make sure the new mould is

    in order.

    - Shop Drawing - SIM

    - Production

    - SIM shall provide all project

    documentation and information to

    SIC / SIS to ensure all end

    products complies with

    requirements.

    - Confirmed BQ

    & Installation

    Plan

    - SIM /SIC /

    SIS

    - SIC / SIS shall prepare Site

    Inspection Schedule, Project SiteInspection and Site Daily Report

    for the designated task.

    - Daily Site

    InspectionReport

    (CS-F21)

    - SIC /SIS

    - SIC and SIS shall ensure all

    installation of the products is

    completed on schedule.

    - Daily activities records are

    prepared by SIC and submitted to

    SIM for updating, scheduling or

    other improving, to ensure the

    project is in order.

    - Production

    Planning Form

    (CS-F36)

    - Daily Site

    Inspection

    Report

    (CS-F21)

    - SIC /SIS

    - SIM

    - SIM/SIC shall prepare the whole

    project evaluation, including total

    number of meeting & visit,

    expenses for monthly claim, to

    Finance Dept FOR Project Claim

    Form issuance.

    - Monthly Site

    Inspection Form

    (CS-F22)

    - Project Claim

    Form (CS-F14)

    - SIM / SIC

    Confirmation

    Order

    Job Specification

    Daily ActivitiesRecord

    Progress Claim

    Material Drawing

    Contract Dept

    See Overleaf

    Site Evaluation

  • 8/10/2019 CS P09 Project Management

    4/4

    CSL TECHNOLOGIES (M) SDN BHD

    LRC TECH (M) SDN BHD

    Ref. No. CS-P09

    Revision No. 00

    PROJECT MANAGEMENT PROCEDUREEffective Date 01/11/2010

    Page 4 of 4

    THIS IS AN UNCONTROLLED COPY OF A CONTROLLED DOCUMENT PRINTED

    - SIM/SIC shall pass Claim Form

    to customer for

    acknowledgement.

    - Project ClaimForm (CS-F14) - SIM / SIC

    - SIM/SIC shall perform joint

    inspection for verifying the work

    done and claims with customer

    QS.

    - Project Claim

    Form (CS-F14)

    - SIM / SIC

    - Upon completion of the

    installation project, SIM/SIC shall

    prepare final measurement, final

    account and other documents and

    submit to customer.- If there are any dissatisfaction of

    final account, SIM/SIC shall check

    with customer and discuss with

    Director.

    - Final Account /

    Final

    Measurement

    - SM / SC

    - Director

    - The verified final account shall

    be returned to the Finance Dept.

    - SIM/SIC will receive a Final

    Certificate & Claim from Finance

    Dept and to pass to customer for

    acknowledgement.

    - Final Account /

    Final

    Measurement

    - Project

    Payment

    Certificate

    (CS-F15)

    - SIM / SIC

    - Finance

    Dept

    - SIM/SIC shall handover CPC &

    provides solution during any

    defect liability/warranty period

    until retention fund release.

    - CPC - SIM / SIC

    - Product

    Executive

    Verify FinalAccount

    Defect Liability/Warranty Period

    NO

    Continued from previous page

    Handover CPC

    Site Verification

    YES

    Final Account

    Discuss withDirector