Upload
truongbao
View
215
Download
1
Embed Size (px)
Citation preview
By:
Mohamed LatheefManaging Director
State Electric Company LimitedMale’
Maldives
Cross Border Energy Trade and Energy Grid
in the Maldives
1
Statistics
Total Population 298,968
Population in Male’ 102,377
Percentage in Male’ 34%
Total number of Islands 1190
Inhabited Islands 185
Number of Atolls 26
Administrative Provinces 7
4
Male’ (Capital City)
Thilafushi(Industrial)
Villingili(inhabited island)
Male’ International Airport
Hu
lhu
ma
le’
(De
ve
lop
ing
Cit
y)
Greater Male’ Region) Gulhifalhu(Developing
City)
Submarine cable is very expensive Male’-Hulhumale’: Estimated US$26.4 million
Male’-Villingilli: Estimated US$10.9 million
Villingilli-Thilafushi: Estimated US$26 millionSource: “Maldives Submarine Cable Interconnection Pre-Feasibility Study” prepared for USAID/SARI-Energy, by
SNC Lavalin and PA Government Services, Inc. (April 2010).
7
The State Electric Company Limited (STELCO) is a 100% state ownedenterprise responsible for the generation, distribution and sale ofelectricity to consumers throughout the North Central Province (NCP) ofthe Republic of Maldives.
North Central Province consists of 4 atolls including Male’ atoll.
Electricity was first provided to the public back in 1949, with a 14kWgenerator supplying electricity to only 50 consumers of Male’.
Over the 63 years of service, the institution was re-named from ElectricityDepartment to Maldives Electricity Board (MEB) and then on 19 June1997 the name was changed by a Presidential’s Decree to State ElectricCompany Limited (STELCO).
8
STELCO now provide its services to 28 islands in NCP with over 33,000consumers and total installed capacity of 78MW covering 37% of thepopulation of Maldives.
Diesel power plants are mainly used in STELCO
1 MW of Solar PV installed in Male’ and few other islands under variousprojects.
The company, although caters to 37% of the population, provides about70% of the electricity generated in the whole country (excluding resorts).This is due to the relatively high energy consumption of the capital zone.
9
7.20 7.20 7.20 7.20
0.00
5.00
10.00
15.00
20.00
25.00
30.00
35.00
40.00
45.00
50.00
55.00
60.00
65.00
2006 2007 2008 2009 2010 2011 2012 2013 2014 2015
[MW
]
Year
Largest Gen-set Out (8/9)
DG 8+9 / 16.0 MW (MAN)
TMP 9-15 / 10.08 MW (Cummins at Gaakoshi PH)
TMP 7-8 / 3.2 MW (Cummins at Canteen area)
TMP 1-6 / 5.4MW (Cummins at Fenmeeru Hingun)
DG 1 - 7 / 26.6 MW (Wartsila)
Peak Load Actual
Linear Peak Load
11
Male’ is very congested No available space. Exhaust Emission Limitations• When the current power project is completed power plant
emission will reach to maximum acceptable limit
Power System Protection• Will reach maximum allowable production capacity
based on system Voltage (appx.55MW)
Network Overloading• Male’ 11kV distribution network requires upgrading and
expansion in the near future Power Generation outside capital island Male’ is the only
option for expansion
12
• Hulhumale’
• Land is available
• Future load center
• Minimal distance (economically more viable)
• Thilafushi
• Land is available
• Future load center (commercial activities)
• Long distance
13
Average size of each island is small
Population less than 1000 on average
Power demand is low
Cost of operation very high
Revenue is small
Operational loss
16
Improves reliability and system efficiency
Phase 1: Interconnect islands in the same reef More than 2 islands in the same reef
These power systems can be interconnected
Possibility of having larger power plants
Phase 2: Interconnect islands across 2 or more reefs within the atoll.
Phase 3: Interconnect the grids across atolls.
17
Until 2012, all our energy production was from diesel (MGO)
GoM has announced its desire to become carbon neutral by 2020
GoM is committed to produce energy from renewable sources
Solar and wind seems the most favorable to Maldives – however studies suggest that wind power is less favourable than solar.
19
Financial & economic barriers Initial investment large Difficulty in getting finance/loans due to high risk of projects
Availability of space for installations Male’
Area is small and few large roof tops Cannot get big space in one area
For islands Space may be available in some islands but still limited in most islands Nearby offshore options available
Expansion of RE investments at commercial scale also requires an interconnected grid
20
Limitations on the level of RE injection Small & Independent Grids Limitation on direct feed RE systems Requires larger grids Submarine cable
Technical Limited Expertise
Institutional & Regulatory Need a framework to encourage RE technologies Policies need to be formulated and implemented at a
national level This is being done by Ministry of Environment and
Energy
23
Currently each island is an independent power grid
National grid will remove this disadvantage
Financial & Technical difficulties due to the unique geographic nature of the country
Maldives can take benefit from the energy grid:
Eliminates the constraints on power expansions
Help to reduce the price of electricity
Increase stability & efficiency
Land issue will also be solved
24
For Male’, demand continues to grow at a very fast rate (12 – 15 % per annum)
Having challenges in power expansion
Further challenges in RE investments
Power expansion limited by the need for a Grid
Constraints on Grid interconnections due to financial and economic issues
A regional grid will give a lot of advantage for the case of Maldives
26