*CIAP-PDCB CONSOLIDATED CONSTRUCTORS
PERFORMANCE SUMMARY REPORT (CPES REPORTS)
13TH RELEASE
(ON-GOING/COMPLETED PROJECTS) FROM July 1, 2008- June 30, 2011
*You may access this report on this website http://www.gppb.gov.ph
1
BACKGROUND: This report is prepared in connection with the
implementation of Constructors Performance Evaluation System (CPES) pursuant to Section 12, Annex E - Evaluation of Contractors Performance of the Implementing Rules and Regulations (IRR) of RA No. 9184 (Government Procurement Reform Act). Item 4 - Submission and Dissemination of Evaluation Results of Section 12, specifically mandated PDCB to consolidate the CPES evaluation results of all ongoing and completed projects and disseminate the same to all offices/agencies/corporations concerned. USES OF CPES INFORMATION:
The CPES rating and other information is designed to serve the information needs of the following: a) government agencies undertaking infrastructure projects; b) industry planners and decision makers, c) constructors, d) project owners, e) banking and financing institutions, f) insurance companies, g) consulting firms, h) professional associations, and i) embassies.
Information on contractors CPES ratings shall be used for
the following purposes: a) Pre-qualification/Eligibility Screening of Constructors; b) Awarding of Contracts; c) Project Monitoring and Control; d) Issuance of Certificate of Completion; e) Policy Formulation/Review; f) Industry Planning; and g) Granting of Incentives/Awards, and in adopting measure to further improve performance of contractors in the prosecution of government projects.
REPORT COVERAGE:
This report contains CPES rating and other project-related information of on-going and completed foreign assisted (FA) and locally funded (LF) infrastructure projects being undertaken by either local, foreign or joint venture constructors. The projects presented in these report covers: road, bridge, housing, building, ports and harbor, irrigation and flood control, and water supply projects.
REPORT CONTENTS:
Presented in this report are the names of constructors arranged alphabetically with the corresponding project classification. Information available in this report comprises three (3) parts, as follows: 1) Constructor General Information; 2) Project Data; and 3) CPES Rating.
Part 1 of the report includes the name of constructor/s and
PCAB License Number.
Information contained in Part 2 pertains to the project name, Implementing Agency, contract amount, and status of project (on-going or completed).
CONSTRUCTION INDUSTRY AUTHORITY OF THE PHILIPPINES (CIAP) PHILIPPINE DOMESTIC CONSTRUCTION BOARD (PDCB)
5/F Executive Building Center, 369 Sen. Gil J. Puyat Avenue cor. Makati ave. Makati City Telephone Nos. 896-1801; 897-0791; Fax No. 897-0791
CONSOLIDATED CONSTRUCTORS PERFORMANCE SUMMARY REPORT
CPES Reports - On-going and Completed Projects from July 1, 2008 to June 30, 2011
2
Part 3 includes data on CPES rating per criteria, as follows: a) workmanship, b) materials, c) time, d) facilities, e) environmental,
safety and health, and f) resources deployment, and the CPES visit Rating and over-all /Final Rating and its Qualitative Description.
SOURCES OF INFORMATION
Data contained in this report were culled from the CPES Summary Report submitted by the *Department of Public Works and Highways (DPWH), Department of Transportation and Communications (DOTC), Department of Science and Technology (DOST), National Irrigation Administration (NIA), National Housing Authority (NHA) and University of the Philippines (U.P.) covering the period January 1, 2007 to December 31, 2009
As regards to data on negative slippage, this is when constructor got 0.00 on time for 15% or more negative slippage, this matter
may be brought about by any of the three (3) problems: a) Constructor-Related Problems, Agency-Related Problems; and Other Related Problems. Please see the enumerated problems on each classification on page 6 of this cover page. If you need particular information on the reason for the negative slippage of each concerned contractor, please contact the agency implementing the project.
For particular information on the data of each of the CPES Reports, please contact the person-in-charge of the concerned
implementing agencies listed below:
Engr. Arnel Fortunado (BCDA) Engr. Clarito Magsino (DBP) Arnaldo Reyes (DOST) Wilfredo C. Borbor (DOTC) Tel. No. 304-3511 Tel. No. 726-3508 Tel. No. 837-2071 loc. 2120 Tel No. 726-3508
For further information and queries, you may visit us at Philippine Domestic Construction Board (PDCB), 5th Floor Executive Building Center, 369 Sen. Gil J. Puyat Avenue cor. Makati Ave. Makati City Philippines; call us at 897-0791/896-1801; or e-mail us at [email protected]. You may access this report on this website http://www.gppb.gov.ph.
Melrose Pailma (DPWH) Ma. Otelia F. Eclavea (NHA) Engr. Tess Pantalla (NIA) Atty. Ma. Hiyasmin Delos Santos (PPA) Tel No. 304-3511 Tel No. 928-4561 Tel. No. 927-79-84 Tel. No. 527-8356 loc. 356/541
Mr. Simon Aguilon (PRRC) Dr. Roland Viray (PUP) Dir. Ariel Betan (U.P) 926-5232/926-6449 716-91-53 928-28-63/925-0984
3
CONSTRUCTORS PERFORMANCE EVALUATION SYSTEM (CPES) IMPLEMENTING GUIDELINES
I. ASPECTS OF EVALUATION 1. During Construction (60% for Horizontal Projects such as Road, Bridge, Ports & Harbor, Irrigation and Flood
Control, Water Supply and Sewerage, etc., and 70% for Vertical Projects such as Housing, Building, Power Transmission Line and Substation) - minimum of two (2) visits with the conduct of first visit when the actual project accomplishment is at least 30% except for projects with a duration of 90 calendar days and below which may be subjected to just one (1) final visit.
2. Upon Completion (40% for Horizontal Projects and 30% for Vertical Projects) - final visit when the Implementing
Office reported 100% completion.
II. CRITERIA FOR EVALUATION
Amended Guidelines as Approved by NEDA InfraCom 27 August 2008
During Construction Upon Completion Criteria Maximum Rating Criteria Maximum Rating Workmanship 0.40 Workmanship 0.50 Materials 0.30 Materials 0.20 Time 0.15 Time 0.30 Facilities 0.03 TOTAL 1.00 Environmental, Safety and 0.07 Health (ESH) Resources Deployment 0.05 TOTAL 1.00
4
As approved by NEDA InfraCom
19 May 2005 During Construction Upon Completion
Criteria Maximum Rating Criteria Maximum Rating Workmanship 0.40 Workmanship 0.40 Materials 0.30 Materials 0.30 Time 0.10 Time 0.30 Facilities 0.03 TOTAL 1.00 Environmental, Safety 0.07 and Health (ESH) Resources Deployment 0.10 TOTAL 1.00
As approved by NEDA InfraCom
30 January 1998
During Construction Upon Completion Criteria Maximum Rating Criteria Maximum Rating Workmanship 0.40 Workmanship 0.50 Materials 0.30 Time 0.50 Time 0.10 TOTAL 1.00 Facilities 0.03 Environmental, Safety
and Health (ESH) 0.07 Resources Deployment 0.10 TOTAL 1.00
5
III. CPES RATING & ITS QUALITATIVE DESCRIPTION
CPES Implementing Guidelines as Approved on 27 August 2008
As Approved on May 2005 and 30 January 1998
*CPES RATING Ranges Rating Qualitative Description
>96% Outstanding
>89% but < 96% Very Satisfactory >82% but < 89% Satisfactory >75% but < 82% Unsatisfactory < 75% Poor
*CPES RATING Ranges Rating Qualitative Description
>90% Outstanding
>80% but < 90% Very Satisfactory >70% but < 80% Satisfactory >60% but < 70% Fair < 60% Poor
6
*CAUSES OF DELAY
CONSTRUCTOR-RELATED PROBLEMS AGENCY RELATED PROBLEMS
C-W01 - Insufficient manpower deployed in project site A-VO1-Delays in the approval of variation orders C-EO1 - Breakdown of equipment/equipment not operational A-TO1- Delays in the approval of contract time extension C-EO2 - Lack/Insufficient/Inadequate equipment deployed in project site A-SO1- Delays in the approval of suspension order C-MO1- Lack/Inadequate/Insufficient supply of construction A-DO1- Changes in construction designs Materials A-FO1- Delays in the release of funds
C-RO1- Lack of financial resources A-RO1- Right of Way (ROW) acquisition problem (squatter relocation problems, relocation
of utilities, (i.e. PLDT, MERALCO posts and other similar cases)
7
*CAUSES OF DELAY OTHER-RELATED PROBLEMS O-WO1- Unfavorable weather condition (Occurrence of natural calamities; occurrence of flooding/ siltation on site; unworkable ground condition) O-PO1- Insurgence or peace and order problems/civil disturbances O-TO1- Third Party intervention *Can be a reason for the negative slippage of constructor (please see the CPES reports of constructor from the agency concerned.)
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2008 to June 30, 2011
11-18-70 Construction 32944 Road Concreting at Brgy. Sallacapo 02/28/09 I 0.855 18 C 0.375 0.200 0.300 - - - 87.50
121 Construction Corporation (Formerly:
121 Construction)21686 Impvt. of MPB at Sta. Maria Agro-Industrial High School 11/26/08 III 1.717 90 C 0.365 0.300 0.300 - - - 96.50
121 Construction Corporation (Formerly:
121 Construction)21686 Const. of MPB 11/24/08 NCR 3.821 90 C 0.280 0.200 0.300 - - - 78.00
121 Construction Corporation (Formerly:
121 Construction)21686 Const. of MPB, Brgy. Mabini J. Rizal 06/02/10 NCR 9.315 180 C 0.475 0.200 0.300 - - - 97.50
2H2L Construction 16293 Widening of Antipolo-Teresa Road 11/25/08 IV-A 19.224 180 C 0.261 0.300 0.300 - - - 86.10
2H2L Construction 16293 Impvt. of Flood Control at So. Upper East Kamias & So. East Kamias 03/12/09 IVA 2.692 120 C 0.461 0.138 0.300 - - - 89.90
2H2L Construction 16293 Impvt. of Multi-Purpose Pavement at Brgy. Dela Paz & Brgy. San Isidro 03/12/09 IVA 3.748 150 C 0.479 0.133 0.300 - - - 91.20
2H2L Construction 16293Rehab./Reconst./Upgrading of
Marikina-Victoria Valley-Antipolo Road
08/26/09 IVA 19.222 180 C 0.475 0.200 0.300 - - - 97.50
2H2L Construction 16293Rehab./Reconst./Upgrading of
Marikina-Victoria Valley-Antipolo Road
05/18/09 IV-A 19.221 180 O 0.387 0.239 0.150 0.030 0.025 0.050 88.10
2-R Construction & Supply 15304
Repair/Impvt. of Villasis-Malasiqui San Carlos Road 08/27/08 I 2.410 60 C 0.338 0.200 0.300 - - - 83.80
2-R Construction & Supply 15304
Const. of Additional Classroom @ Comprehensive Nat'l. H/S 05/21/09 I 2.417 120 C 0.496 0.072 0.300 - - - 86.80
NAME OF CONSTRUCTOR
LICENSE NO. PROJECT
DATE OF EVALUATION AMOUNT
(Php, M) DUR (C.D.)
CONTRACT
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FAC*IMPL. AGENCY
07 March 2011* 1st/Final* For DPWH, only the region and PMO office are listed 13th CPES Release Page1
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2008 to June 30, 2011
NAME OF CONSTRUCTOR
LICENSE NO. PROJECT
DATE OF EVALUATION AMOUNT
(Php, M) DUR (C.D.)
CONTRACT
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FAC*IMPL. AGENCY
310 Construction Specialist Corporation 4875
Estrella-Pantaleon Bridge Approaches (Across Pasig River) 11/28/08 NCR 38.627 405 C 0.376 0.200 0.300 - - - 87.60
3FS Construction 30464 Upgrading of Bagahupi-Babatngon-Sta. Cruz, Barugo-Carigara Rd. 03/11/10 VIII 19.289 230 C 0.497 0.189 0.300 - - - 98.60
3FS Construction 30464 Const. of Grouted Riprap @ Brgy. 90 03/18/09 VIII 0.962 70 C 0.381 0.200 0.300 - - - 88.10
3K Builders 27277Repair/Rehab. of MNR, Km.174+000 -
Km.175+000 w/ exception Villasis Section
06/10/10 I 9.996 32 C 0.455 0.133 0.300 - - - 88.80
3K Rock Engineering 27908 Construction of Multi-Purpose Building, Magsaysay 09/03/09 II 0.572 45 C 0.407 0.200 0.300 - - - 90.70
3K Rock Engineering 27908 Const./Repair of Multi-Purpose Building 02/25/10 II 1.735 60 C 0.413 0.133 0.300 - - - 84.60
3K Rock Engineering 27908 Const./Completion of MPB, Liwayway 06/05/10 II 1.445 60 C 0.441 0.133 0.300 - - - 87.40
3K Rock Engineering 27908 Const. of Flood Control, Sangbay 08/18/08 II 0.954 70 C 0.321 0.204 0.300 - - - 82.50
3K Rock Engineering 27908 Const. of Sch. Bldg., Bannawang Integrated School 08/18/08 II 0.578 45 C 0.375 0.218 0.300 - - - 89.30
3K Rock Engineering 27908 Const. of Sch. Bldg., Victoria H/S 11/25/08 II 1.622 100 C 0.375 0.200 0.300 - - - 87.50
3K Rock Engineering 27908 Completion of Multi-Purpose Building, Gundaway 03/06/09 II 1.783 60 C 0.458 0.200 0.300 - - - 95.80
3-L Construction 16745 Const. of 2 Storey Multi-Purpose Bldg. (Brgy. Hall), Brgy. San Gabriel 03/09/09 V 0.955 120 C 0.436 0.175 0.300 - - - 91.10
3-L Construction 16745 Road Upgrading (Gravel to Paved), Sipocot-Cabusao Road 09/09/09 V 6.555 150 C 0.418 0.200 0.300 - - - 91.80
07 March 2011* 1st/Final* For DPWH, only the region and PMO office are listed 13th CPES Release Page2
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2008 to June 30, 2011
NAME OF CONSTRUCTOR
LICENSE NO. PROJECT
DATE OF EVALUATION AMOUNT
(Php, M) DUR (C.D.)
CONTRACT
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FAC*IMPL. AGENCY
3RB Construction & Supply 19541 Const. of Sto. Cristo Seawall 05/28/10 V 2.876 150 C 0.458 0.133 0.300 - - - 89.10
3RB Construction & Supply 19541
Const./Rehab. of Water Supply, Level 1 and II System 08/19/08 IV-A 1.921 30 C 0.288 0.200 0.300 - - - 78.80
3RB Construction & Supply 19541
Road Upgrading along DM Jct.-Leg.-Sto. Domingo-Tab.-Cam. Sur Bdry.,
Tiwi-Tabaco Section02/24/09 V 19.233 150 C 0.488 0.133 0.300 - - - 92.10
3RB Construction & Supply 19541
Impvt. of San Fernando North Road, San Jacinto Section 02/17/10 V 9.450 210 O 0.378 0.240 0.150 0.015 0.035 0.050 86.80
3RB Construction & Supply 19541
Road Conc. & Impvt. of Barangay Road 02/22/10 V 0.959 160 C 0.396 0.139 0.300 - - - 83.50
3RB Construction & Supply/Ajan Jaeda, Inc.
(JV) JV-08-209 Const. of Tagas-Divino Rostro Bridge 09/01/09 V 19.179 202 O 0.384 0.240 0.150 0.030 0.033 0.050 88.70
4 A's Construction 9446 Construction of 1-CL (7x9) Lupigue IS 09/05/09 II 1.108 45 C 0.454 0.133 0.300 - - - 88.70
4 A's Construction 9446 Const./Conc. of Road 02/23/10 II 4.822 330 C 0.413 0.133 0.300 - - - 84.60
4 A's Construction 9446 Construction of Road 08/11/08 II 1.926 90 C 0.326 0.200 0.300 - - - 82.60
4 A's Construction 9446 Asphalt Overlay of Daang Maharlika 03/03/09 II 1.929 30 C 0.464 0.133 0.300 - - - 89.70
4B Construction Corporation 23445
Upgrading and Concreting of Subic-Philseco Road 03/03/09 III 41.616 180 C 0.407 0.163 0.300 - - - 87.00
4B Construction Corporation 23445
Rehab./Reconst./Upgrading of Damaged Paved National Road,
Olongapo-Bugallon Road05/23/09 III 33.265 45 C 0.374 0.200 0.300 - - - 87.40
07 March 2011* 1st/Final* For DPWH, only the region and PMO office are listed 13th CPES Release Page3
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2008 to June 30, 2011
NAME OF CONSTRUCTOR
LICENSE NO. PROJECT
DATE OF EVALUATION AMOUNT
(Php, M) DUR (C.D.)
CONTRACT
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FAC*IMPL. AGENCY
4B Construction Corporation 23445
Rehab./Reconst./Upgrading of Damaged Paved National Road at
Subic-Philseco Rd.05/29/10 III 41.378 120 O 0.321 0.228 0.150 0.018 0.022 0.033 77.20
4B Construction Corporation 23445
Repair/Rehab. of Paete-Famy Pob. Rd., Pangil-Siniloan Sect. Km.109+000
- Km.110+40005/25/10 IVA 9.608 20 C 0.472 0.133 0.300 - - - 90.50
525 Construction 28532 Rehab. of Sta.Rita-Biak na Bato via Pulong Bayabas Road 06/11/10 III 38.180 210 O 0.386 0.300 0.150 0.030 0.038 0.033 93.70
525 Construction 28532 Rahab. of Sta. Rita-Biak na Bato via Pulong Bayabas Road 09/08/09 III 19.049 120 C 0.478 0.133 0.300 - - - 91.10
525 Construction / MGSCC (JV)
JV-07-095/ SLI-SN-005104
Rehabilitation/Improvement of Sta. Rita Biak na Bato Road 03/11/09 III 44.000 200 C 0.405 0.200 0.300 - - - 90.50
525 Construction/MGSCC Joint Venture JV-08-235
Rehabilitation of Sta. Maria-Norzagaray Road 09/07/09 III 46.339 180 C 0.479 0.133 0.300 - - - 91.20
628 Construction Enterprises 30049
Construction of Two Classroom School Building at Lokeb Norte 03/06/09 I 1.369 70 C 0.429 0.178 0.300 - - - 90.70
722 Construction 21923 Rehab./Reconst./Upgrading at Old Cagayan Valley Rd. (Baliuag Sect.) 06/10/10 III 9.547 80 C 0.460 0.133 0.300 - - - 89.30
722 Construction 21923 Rehab./Impvt. of Bocaue-San Jose Road, Tumana & Parada Section 08/29/08 III 3.807 60 C 0.347 0.200 0.300 - - - 84.70
722 Construction 21923Repair/Maintenance of Bigaa-Plaridel via Bulacan & Malolos Road (Barihan
Section)08/27/08 III 4.957 10 C 0.361 0.200 0.300 - - - 86.10
722 Construction 21923 Const. of Water System @ Northville II 08/19/08 NCR 1.424 60 C 0.278 0.177 0.300 - - - 75.50
722 Construction 21923Rehab/Reconst./Upgrading of Old
Cagayan Valley Road (Pulilan Section)
05/28/09 III 9.543 45 C 0.359 0.200 0.300 - - - 85.90
07 March 2011* 1st/Final* For DPWH, only the region and PMO office are listed 13th CPES Release Page4
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2008 to June 30, 2011
NAME OF CONSTRUCTOR
LICENSE NO. PROJECT
DATE OF EVALUATION AMOUNT
(Php, M) DUR (C.D.)
CONTRACT
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FAC*IMPL. AGENCY
722 Construction 21923 Const. of Sch. Bldg., 2 Storey, 2 CL Banga E/S 03/10/09 III 2.290 100 C 0.472 0.133 0.300 - - - 90.50
722 Construction 21923Const. of Multi-Purpose Bldg. Malinta E/S Lawang Bato E/S, Brgy. Lawang
Bato & Natividad Homes03/03/09 NCR 1.882 90 C 0.405 0.136 0.300 - - - 84.10
722 Construction 21923Rehab./Reconst./Upgrading of
Damages Pavement along Mc Arthur Highway
05/31/10 NCR 9.506 120 C 0.436 0.200 0.300 - - - 93.60
722 Construction 21923 Rehab./Reconst./Upgrading along Rizal Avenue Extension 05/27/09 NCR 9.494 120 C 0.380 0.200 0.300 - - - 88.00
722 Construction 10221 Const. of MPB (Day Care) at Brgy. Polo 09/16/09 NCR 1.901 75 C 0.486 0.133 0.300 - - - 91.90
739 Builders 31174 Construction of School Building, Pila E/S, Brgy. Pila 09/07/09 I 0.950 60 C 0.454 0.154 0.300 - - - 90.80
739 Builders 31174 Const. of Drainage Canal, Brgy. VII 05/29/10 I 1.141 80 C 0.444 0.133 0.300 - - - 87.70
739 Builders 31174 Completion of MPB, Brgy. Capangpangan 11/13/08 I 1.518 54 C 0.327 0.200 0.300 - - - 82.70
739 Builders 31174 Road Concreting, Brgy. Napo 02/28/09 I 0.950 20 C 0.364 0.200 0.300 - - - 86.40
747 Builders & Trader 16892 Upgrading/Conc. of Roads with Drainage Impvt., M. Naval St. 11/21/08 NCR 9.589 120 C 0.355 0.200 0.300 - - - 85.50
747 Builders & Trader 16892 Rehab./Impvt. of Manggahan Floodway Eastbank 03/12/09 IVA 14.367 170 C 0.473 0.133 0.300 - - - 90.60
747 Builders & Trader 16892Proposed Rehab./Impvt. of Pres.
Quirino Ave. West Bound (Singalong-Roxas Blvd.)
05/24/10 NCR 14.475 20 C 0.442 0.200 0.300 - - - 94.20
747 Builders and Trader 16892 Rehab./Reconst./Upgrading of Antipolo Circumferential Road "A" 08/26/09 IVA 19.213 180 C 0.411 0.200 0.300 - - - 91.10
07 March 2011* 1st/Final* For DPWH, only the region and PMO office are listed 13th CPES Release Page5
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2008 to June 30, 2011
NAME OF CONSTRUCTOR
LICENSE NO. PROJECT
DATE OF EVALUATION AMOUNT
(Php, M) DUR (C.D.)
CONTRACT
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FAC*IMPL. AGENCY
811 Trading & Construction 21215
Repair/Rehab. of National Roads & Bridges, Mansalay Section 11/19/08 IV-B 4.710 90 C 0.304 0.200 0.300 - - - 80.40
811 Trading & Construction 21215
Repair/Rehab. of Multi-Purpose Building (Phase II) 02/26/09 IV-B 0.288 27 C 0.463 0.133 0.300 - - - 89.60
888 ACY Enterprises 32898Reconst. (Conc. Paving) of Jct. LIR, Buenavista, Carmen-Danao-Getafe
Rd., Poblacion Danao Sect.06/01/10 VII 9.541 419 O 0.360 0.300 0.000 0.030 0.045 0.033 76.80
888 ACY Enterprises 32898Reconst. (Conc. Paving) of Loay
Interior Rd., Trinidad & San Miguel Sect.
06/02/10 VII 14.320 270 O 0.356 0.300 0.000 0.030 0.045 0.033 76.40
888 ACY Enterprises 32898Repair/Rehab. of Tablas Circ. Road,
Calatrava-San Agustin Road (Intermittent Section)
11/25/08 IV-B 9.999 32 C 0.356 0.300 0.300 - - - 95.60
A C J Construction Resources 10635
Concreting of Poblacion Magpet-Nowa-Basak Road (Basak Section) 05/30/09 R-XII 18.797 180 O 0.336 0.300 0.000 0.024 0.055 0.050 76.50
A C O Construction 13105
Const. of Rotonda along National Highway (Zamboanga Peninsula) Cross Rd. Upgrading Project @
Poblacion Ipil
02/25/10 IX 2.829 115 O 0.319 0.300 0.000 0.020 0.042 0.033 71.40
A C O Construction 13105Zamboanga Peninsula Crossroads Upgrading Project (Completion of
Roundabout) Sta.1801+231.50 06/05/10 IX 1.861 60 C 0.476 0.133 0.300 - - - 90.90
A C O Construction 13105
Const. of Rotonda along National Highway (Zamboanga Peninsula Crossroad Upgrading Project) at
Poblacion Ipil
06/05/10 IX 2.829 115 C 0.456 0.133 0.000 - - - 58.90
A C O Construction 13105 Conc. of Liloy-Zamboanga del Norte-Ipil-Zamboanga Sibugay Rd. Ph. I 03/05/09 IX 14.306 150 C 0.425 0.147 0.300 - - - 87.20
A. Ballesta Construction 8446 Const. of Road Network along E. Balite Boulevard Ext. 08/30/08 VIII 14.393 160 C 0.242 0.200 0.300 - - - 74.20
07 March 2011* 1st/Final* For DPWH, only the region and PMO office are listed 13th CPES Release Page6
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2008 to June 30, 2011
NAME OF CONSTRUCTOR
LICENSE NO. PROJECT
DATE OF EVALUATION AMOUNT
(Php, M) DUR (C.D.)
CONTRACT
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FAC*IMPL. AGENCY
A. De Guia Construction 18228Rehab./Reconst./Upgrading of
Naguilian-San Mariano Rd., Villapaz Section
08/25/09 II 19.296 104 C 0.420 0.200 0.300 - - - 92.00
A. De Guia Construction 18228 Concreting of Junction National -Potia Road 08/27/09 II 7.043 110 C 0.410 0.200 0.300 - - - 91.00
A. De Guia Construction 18228 Rehab./Reconst. of Daang Maharlika Road, KO309+300-KO309+878 08/27/09 II 18.811 130 C 0.411 0.200 0.300 - - - 91.10
A. De Guia Construction 18228 Rehab./Reconst./Upgrading of Gamu-Roxas Road (Roxas Section) 02/23/10 II 19.293 240 C 0.402 0.133 0.300 - - - 83.50
A. De Guia Construction 18228 Const./Completion/Continuation of Unfinished On-going Bridges 03/01/10 II 11.574 120 C 0.415 0.133 0.300 - - - 84.80
A. De Guia Construction 18228Rehab./Reconst./Upgrading of
Damaged Paved national Road, Daang Maharlika KO 320+000 - KO 321+000
06/03/10 II 16.396 120 O 0.387 0.295 0.150 0.030 0.042 0.033 93.70
A. De Guia Construction 18228
Rehab./Reconst./Upgrading of Damaged Paved National Road
Santiago-Baluarte-Quirino Bdry. Road KO326+(-)280 - KO328+000 w/
exception
08/27/10 II 15.432 149 C 0.292 0.200 0.300 - - - 79.20
A. De Guia Construction 18228
Restoration of Road Slope & Slope Protection along Naguilian-San
Mariano Road KO395+850 - KO401+800
08/25/10 II 14.471 120 C 0.389 0.150 0.300 - - - 83.90
A. De Guia Construction 18228Road Upgrading (Gravel to Paved) of Jct. Ipil-Panang-Quirino Bdry. Road;
KO366+058 - KO367+11808/27/10 II 17.373 149 C 0.403 0.146 0.300 - - - 84.90
A. De Guia Construction 18228
Rehab./Reconst./Upgrading of Damaged Paved National Roads, Santiago-Baluarte-Quirino Bdry.
Road; KO328+100 - KO331+000 w/
08/27/10 II 18.623 149 O 0.308 0.300 0.091 0.030 0.054 0.017 80.00
A. De Guia Construction 18228Rehab./Reconst./Upgrading of
Santiago-Tuguegarao Rd. Burucboc Sect.
08/25/10 II 9.647 133 O 0.358 0.300 0.000 0.030 0.043 0.000 73.10
A. De Guia Construction 18228
Rehab./Reconst./Upgrading of Damaged Paved National Roads
Santiago-Tuguegarao Road, KO333+500 - KO334+850
08/28/10 II 17.123 149 O 0.347 0.300 0.000 0.030 0.054 0.000 73.10
07 March 2011* 1st/Final* For DPWH, only the region and PMO office are listed 13th CPES Release Page7
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2008 to June 30, 2011
NAME OF CONSTRUCTOR
LICENSE NO. PROJECT
DATE OF EVALUATION AMOUNT
(Php, M) DUR (C.D.)
CONTRACT
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FAC*IMPL. AGENCY
A. De Guia Construction 18228 Conc. of Pob. Burgos-Caliguian Road 11/20/08 II 9.648 180 C 0.344 0.200 0.300 - - - 84.40
A. Montalbo Trading and Construction 32684
Const. of Multi-Purpose Building at Bigain 1st 03/01/10 IVA 1.135 30 C 0.450 0.200 0.300 - - - 95.00
A.A De Vera Construction 6191 Rehab./Expansion of Waterworks System 09/02/09 VII 4.510 240 C 0.417 0.133 0.300 - - - 85.00
A.A De Vera Construction 6191 Const./Rehab. of School Bldg. at Cogon E/S 06/05/10 VII 0.591 35 C 0.415 0.200 0.000 - - - 61.50
A.A De Vera Construction 6191 Const. of Water System Development Project 08/25/10 VII 1.413 90 C 0.497 0.133 0.300 - - - 93.00
A.A De Vera Construction 6191 Const. of 2 Storey, 6 CL Sch. Bldg. @ Lawis E/S 11/21/08 VII 4.175 120 C 0.367 0.300 0.300 - - - 96.70
A.A De Vera Construction 6191 Const./Repair & Completion of Instructional Classroom, Corella CES 06/10/09 VII 0.504 105 C 0.492 0.200 0.300 - - - 99.20
A.A De Vera Construction 6191Completion of Tagbilaran City
Puericulture Center & Maternity House and Related Facilities
06/10/09 VII 4.575 150 C 0.500 0.169 0.300 - - - 96.90
A.A De Vera Construction 6191 Const./Repair/Rehab. of Multi-Purpose Building 06/10/09 VII 0.460 105 C 0.483 0.154 0.300 - - - 93.70
A.A De Vera Construction 6191 Completion of Multi-Purpose Building 03/04/09 VII 0.458 60 C 0.382 0.200 0.300 - - - 88.20
A.B Aponesto Construction Parts &
Supply22998
Road Upgrading (Gravel to Paved) along Compostela-Cateel Rd.,
Osmeña Sect.06/04/10 XI 18.892 180 O 0.355 0.238 0.150 0.030 0.045 0.033 85.10
07 March 2011* 1st/Final* For DPWH, only the region and PMO office are listed 13th CPES Release Page8
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2008 to June 30, 2011
NAME OF CONSTRUCTOR
LICENSE NO. PROJECT
DATE OF EVALUATION AMOUNT
(Php, M) DUR (C.D.)
CONTRACT
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FAC*IMPL. AGENCY
A.B Aponesto Construction, Parts &
Supply22998 Concreting of Montevista-DNAS Road 03/01/10 XI 32.748 300 C 0.353 0.200 0.300 - - - 85.30
A.B Taylan Construction & Development 25273
Const. of RCBC and Canal along Manila North Road (Km. 483+040) 02/22/10 I 4.816 65 C 0.329 0.133 0.300 - - - 76.20
A.C Cunanan Construction 20752
Repair/Rehabilitation of Sewer and Drainage System at Northwing and
Eastwing07/23/08 PUP 1.241 67 C 0.400 0.300 0.300 - - - 100.00
A.C Rivero Development Corporation 5122
Rehab./Reconst./Upgrading of Bacolod South Road Km. 6+862-Km.
8+350 w/ exception09/12/09 VI 26.470 280 O 0.331 0.282 0.150 0.030 0.045 0.033 87.10
A.C Rivero Development Corporation 5122
Const./Impvt. of Multi-Purpose Bldg. at Maasin City (Legislative Building) 03/06/09 VIII 0.934 75 C 0.500 0.133 0.300 - - - 93.30
A.C Rivero Development Corporation (Formerly:
A.C. Rivero Const.)5122
Rehab./Reconst./Upgrading of Bacolod South Rd. Km. 6+862 to Km.
8+350 with exceptions03/06/10 VI 26.337 280 C 0.393 0.200 0.300 - - - 89.30
A.C Rivero Development Corporation (Formerly:
A.C. Rivero Const.)5122 Const. of Subang Daku Bridge 09/04/10 VIII 18.890 345 O 0.382 0.240 0.150 0.030 0.037 0.033 87.20
A.C Soliven Construction & General Merchandise 19278
Channel Impvt./Slope Protection @ San Roque Creek, Camias Creek &
San Vicente Creek02/23/10 III 4.781 60 C 0.445 0.177 0.300 - - - 92.20
A.C Soliven Construction & General Merchandise 19278
Construction of 2 CL S.B. at La Paz H/S 09/01/09 III 0.974 90 C 0.483 0.133 0.300 - - - 91.60
A.D Construction 6946 Conc. of Line Canal along National Road, Concepcion 09/09/09 IVA 1.442 90 C 0.371 0.200 0.300 - - - 87.10
A.D.L Constrak 26442 Const. of Sch. Bldg. @ Roxas Central School 08/21/08 IV-B 0.481 69 C 0.360 0.200 0.300 - - - 86.00
07 March 2011* 1st/Final* For DPWH, only the region and PMO office are listed 13th CPES Release Page9
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2008 to June 30, 2011
NAME OF CONSTRUCTOR
LICENSE NO. PROJECT
DATE OF EVALUATION AMOUNT
(Php, M) DUR (C.D.)
CONTRACT
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FAC*IMPL. AGENCY
A.D.P Construction & Supply 3466
Impvt./Conc. of Access Road, Tubalan Port, Tubalan 06/14/10 XI 58.261 320 O 0.338 0.300 0.000 0.030 0.040 0.033 74.10
A.D.P Construction & Supply 3466
Impv't./Conc. Of Mana-Ticulon-Lagumit-Little Baguio Rd. 08/25/10 XI 47.455 571 C 0.292 0.133 0.000 - - - 42.50
A.D.P Construction & Supply 3466
Const. of Bugasong-Valderrama Road, Liaures Section (Alternate
Route)11/27/08 VI 14.426 178 C 0.335 0.087 0.300 - - - 72.20
A.D.P Construction & Supply 3466
Conc. of Pototan-Lambunao Road, Km. 38+380-Km. 53+000 with
exception)09/05/10 VI 9.419 150 O 0.397 0.240 0.150 0.030 0.047 0.033 89.70
A.D.P Construction & Supply 3466
Rehab./Reconst./Upgrading of Damaged Paved National Road,
Roxas City Boundary-Panitan Road-Jct. Bailan Road, Capiz (KM.112+750-
08/31/10 VI 53.673 225 O 0.364 0.240 0.150 0.030 0.051 0.050 88.50
A.D.P Construction & Supply 3466
Road Upgrading of Sara-Concepcion Road, Sara and Concepcion 09/06/10 VI 66.119 270 O 0.371 0.240 0.150 0.030 0.042 0.033 86.60
A.D.P Construction & Supply 3466 Reconst. of Dumaguete North Road 03/12/09 VII 18.881 230 C 0.442 0.200 0.300 - - - 94.20
A.D.S San Juan Construction 12853
Conc. of Dionisio Anore St., Brgy. Mambog 02/16/10 IVA 1.728 90 C 0.427 0.200 0.300 - - - 92.70
A.F.G Construction & Construction Supply 17161
Const. of MPB (Covered Court) at San Enrique NHS 03/10/10 VI 1.925 78 C 0.405 0.200 0.300 - - - 90.50
A.F.G Construction & Construction Supply 17161
Const. of Diversion/By Pass Road along Kalibo-Iloilo Highway, Banga
Section11/30/08 VI 14.461 180 C 0.351 0.300 0.300 - - - 95.10
A.F.G Construction & Construction Supply 17161 Rehab. of Dumaguete North Road 11/27/08 VII 4.894 42 C 0.324 0.200 0.300 - - - 82.40
A.F.G Construction & Construction Supply 17161
Rehab./Reconst./Upgrading of Damaged Paved National Road, Jct.
Nat'l. Road-Sagay-Bato-Dian-ay-Marcelo Balea Jct National Road
08/29/10 VI 37.184 220 O 0.308 0.238 0.150 0.030 0.042 0.033 80.10
A.F.G Construction & Construction Supply 17161
Rehab. of Amerang Flood Control, Tigum River, Brgy. Amerang 09/05/10 VI 8.159 257 C 0.456 0.133 0.000 - - - 58.90
07 March 2011* 1st/Final* For DPWH, only the region and PMO office are listed 13th CPES Release Page10
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2008 to June 30, 2011
NAME OF CONSTRUCTOR
LICENSE NO. PROJECT
DATE OF EVALUATION AMOUNT
(Php, M) DUR (C.D.)
CONTRACT
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FAC*IMPL. AGENCY
A.F.G Construction & Construction Supply 17161
Rehab. of Bacolod South Rd. (Hingaran Section) 09/15/09 VI 14.221 222 C 0.398 0.133 0.300 - - - 83.10
A.G Cosipag Construction 12700 Balogo CIS 06/1-6/09 NIA 2.144 150 C 0.421 0.126 0.300 - - - 84.68
A.G Herrera Construction Corp. 26307
Construction of Multi-Purpose Building, Sto. Cristo 06/01/09 III 2.381 80 C 0.488 0.133 0.300 - - - 92.10
A.I.P Construction 32458 Road Concreting at Pinget Barangay 03/13/09 CAR 1.872 45 C 0.386 0.200 0.300 - - - 88.60
A.I.P Construction 32458 Rehab. of Kin-iway - Tamboan FMR 06/02/10 CAR 0.987 253 O 0.300 0.300 0.150 0.022 0.030 0.033 83.50
A.I.P Construction 32458 Rehab. of Ambasing-Balugang FMR 08/27/10 CAR 0.800 268 C 0.439 0.133 0.300 - - - 87.20
A.I.P Construction 32458Restoration of Road Cuts along
Bontoc-Baguio Road Alab Section (Km. 383+619-Km. 384+124)
08/27/10 CAR 1.732 70 O 0.318 0.252 0.150 0.030 0.035 0.033 81.80
A.J Lava Builders 22265 Const. of the Makinabang Baliuag FMR 11/24/08 III 4.769 62 C 0.296 0.300 0.300 - - - 89.60
A.J Lava Builders 22265 Repair & Rehab. of Daang Maharlika Road (Guiguinto & Plaridel Section) 08/28/08 III 9.930 20 C 0.257 0.211 0.300 - - - 76.80
A.J Lava Builders 22265 Repair & Rehab. of Gen. Alejo Santos Highway 11/24/08 III 9.927 18 C 0.255 0.300 0.300 - - - 85.50
A.J Lava Builders 22265 Impvt./Rehab. of MPB, Brgy. San Antonio 09/14/09 NCR 2.021 90 C 0.412 0.133 0.300 - - - 84.50
A.J Lava Builders 22265 Impv't./Rehab. of MPB and Alley Fernandez St., Brgy. San Antonio 06/04/10 NCR 0.961 45 C 0.455 0.200 0.300 - - - 95.50
07 March 2011* 1st/Final* For DPWH, only the region and PMO office are listed 13th CPES Release Page11
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2008 to June 30, 2011
NAME OF CONSTRUCTOR
LICENSE NO. PROJECT
DATE OF EVALUATION AMOUNT
(Php, M) DUR (C.D.)
CONTRACT
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FAC*IMPL. AGENCY
A.J Taylan Construction Corporation 2336
Road Opening/Const. of Missing Links of National Road, Solsona-Kabugao Road, Ilocos Norte Side
09/09/09 I 48.199 300 O 0.379 0.250 0.150 0.030 0.050 0.033 89.20
A.J Taylan Construction Corporation 2336 Const. of Seawall 08/25/08 II 14.173 270 C 0.323 0.226 0.000 - - - 54.90
A.L Dare Construction 11932Const./Repair/Rehab. of Slope
Protection along Porac River, Mabical Sect.
08/16/10 III 14.344 90 C 0.481 0.133 0.300 - - - 91.40
A.L Dare Construction 11932 Impvt. of Kennon Road, Camp 4 06/09/10 CAR 7.177 150 O 0.306 0.300 0.150 0.022 0.030 0.033 84.10
A.L Gantuangco Construction 30872
Construction of the Diversion Works and Canal System of Libertad CIP -
Phase 211/15-20/2010 NIA 16.060 202 O 0.373 0.264 0.150 0.023 0.038 0.050 89.69
A.L Gantuangco Construction 30872 Benolho CIS 10/6-10/08 NIA 3.720 90 O 0.277 0.180 0.050 0.020 0.038 0.100 66.50
A.L Salazar Construction, Inc. 3899
Impvt. of FMR, Brgy. Pintong Bukawe, Phase II 11/27/08 IV-A 14.346 120 C 0.267 0.300 0.300 - - - 86.70
A.L.R Construction Corporation 24110 Completion of MPB at Brgy. Zapote 05/27/10 IVA 0.959 30 C 0.458 0.075 0.300 - - - 83.30
A.L.R Construction Corporation 24110
Completion of Two (2) Storey 4-CL at Landayan E/S 08/23/10 IVA 2.302 225 C 0.407 0.165 0.300 - - - 87.20
A.L.R Construction Corporation 24110 Conc.of Road, Inday Subdivision 03/13/09 IVA 0.958 90 C 0.461 0.133 0.300 - - - 89.40
A.L.R Construction Corporation 24110
Const.of Multi Purpose Pavement with Perimeter Fence, Marcelino M.
Santos NHS03/13/09 IVA 0.957 90 C 0.480 0.133 0.300 - - - 91.30
A.L.R Construction Corporation 24110
Const. of Pedestrian Overpass (Phase II) Brgy. Pagsawitan 09/01/09 IVA 2.882 35 C 0.484 0.185 0.300 - - - 96.90
07 March 2011* 1st/Final* For DPWH, only the region and PMO office are listed 13th CPES Release Page12
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2008 to June 30, 2011
NAME OF CONSTRUCTOR
LICENSE NO. PROJECT
DATE OF EVALUATION AMOUNT
(Php, M) DUR (C.D.)
CONTRACT
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FAC*IMPL. AGENCY
A.L.R Construction Corporation 24110
Const. of Multi-Purpose Building at Brgy. Timugan 09/03/09 IVA 2.111 40 C 0.389 0.155 0.300 - - - 84.40
A.L.R Construction Corporation 24110 Conc. of Roads, Brgy. San Luis 02/15/10 IVA 3.358 90 C 0.455 0.200 0.300 - - - 95.50
A.L.R Construction Corporation 24110
Completion of 2-Storey 4-CL @ Landayan E/S 02/24/10 IVA 5.030 225 O 0.354 0.300 0.150 0.015 0.018 0.033 87.00
A.L.R Construction Corporation 24110
Const. of Pedestrian Overpass, Old Manila South Road, Km.34+520 08/23/10 IVA 9.632 167 O 0.381 0.274 0.150 0.022 0.030 0.033 89.00
A.L.R Construction Corporation 24110
Construction of Overpass (Phase I), Pagsawitan 05/30/09 IV-A 3.849 129 C 0.482 0.133 0.300 - - - 91.50
A.L.R Construction Corporation 24110
Const. of Pedestrian Overpass at Brgy. San Antonio and Biñan-Carmona Road Intersection
06/01/09 IV-A 19.203 241 C 0.466 0.133 0.300 - - - 89.90
A.L.R Construction Corporation 24110
Road Upgrading (Gravel to Paved-HDM-4) of Jct. MWCR (Bagong
Silang)-Cabacao Diversion Road, Brgy. Cabacao
08/28/10 IVB 9.649 145 C 0.409 0.198 0.300 - - - 90.70
A.M Ayunan Construction 13983 Const. of MPB at Datu Usman E/S 11/18/08 XII 1.908 75 C 0.319 0.182 0.300 - - - 80.10
A.M Oreta & CO., Inc./IBC Int'l Builders Corp. (JV) JV-07-097
Conc. of Iloilo-Caticlan Highway (Pototan-Passi-Capiz Bdry. Sect.) 05/31/10 VI 158.259 570 C 0.379 0.200 0.300 - - - 87.90
A.M Oreta & CO., Inc./IBC Int'l Builders Corp. (JV) 7096
Kalibo Airport Development Project (Asphalt Overlay of Runway,
Extension of Apron and Construction of Drainage Canal)
04/14/10 DOTC 283.188 360 C 0.449 0.200 0.300 - - - 94.90
A.M Robles Construction 28056 Conc. of FMR, Brgy. Colo 11/17/08 I 1.926 55 C 0.367 0.200 0.300 - - - 86.70
A.M Robles Construction 28056 Construction of Water Supply @ Brgy. San Simon 03/02/09 I 0.530 40 C 0.415 0.184 0.300 - - - 89.90
07 March 2011* 1st/Final* For DPWH, only the region and PMO office are listed 13th CPES Release Page13
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2008 to June 30, 2011
NAME OF CONSTRUCTOR
LICENSE NO. PROJECT
DATE OF EVALUATION AMOUNT
(Php, M) DUR (C.D.)
CONTRACT
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FAC*IMPL. AGENCY
A.M Robles Construction 28056 Completion of Multi-Purpose Building at Pinaglabanan 05/28/09 NCR 4.776 90 C 0.487 0.133 0.300 - - - 92.00
A.P Consebido Construction and Trading 33616 Const. of MPB, Brgy. Alimanguan 08/20/10 IVB 0.974 114 C 0.447 0.200 0.300 - - - 94.70
A.P Palacios Construction 29021 Const. of MPB, Brgy. Pingit 06/05/10 III 4.287 180 C 0.470 0.133 0.300 - - - 90.30
A.P Palacios Construction 29021 Completion/Conc. of Road, Buhangin to ANSHS Road 08/25/08 III 2.170 150 C 0.347 0.206 0.300 - - - 85.30
A.P Palacios Construction 29021 Conc. of Road from Brgy. Bacong to Brgy. San Jose 11/26/08 III 0.702 75 C 0.316 0.300 0.300 - - - 91.60
A.P Palacios Construction 29021 Rehab./Impvt. of Dikidit-Suguit FTMR 09/08/09 III 4.723 150 O 0.300 0.300 0.150 0.030 0.050 0.033 86.30
A.P.B Construction 17055Repair/Rehab. of Baguio-Bauang
Road, Km. 296+050-Km. 297+050 with exceptions
08/29/10 CAR 4.891 47 C 0.456 0.176 0.300 - - - 93.20
A.P.B Construction 17055 Rehab. and Conc. of Road at Brgy. Balligi, Kias Barangay 03/03/10 CAR 1.248 60 C 0.384 0.158 0.300 - - - 84.20
A.P.B Construction 17055 Road Opening at Middle Quirino Hill Brgy. 08/28/08 CAR 0.953 45 C 0.350 0.200 0.300 - - - 85.00
A.P.O General Construction 7010
Rehab./Reconst. of Dungon-Agat Section, Km. 216+648-Km. 217+723
(V.S.) Camp 108/29/10 CAR 4.555 90 C 0.466 0.133 0.300 - - - 89.90
A.Q Loisaga Construction & General Services 32691 Const. of 2 CL in Quillo-Quillo E/S 09/01/09 IVA 2.023 120 C 0.470 0.133 0.300 - - - 90.30
A.R & Mark Builders 31673 Const. of 1 CL Sch. Bldg. @ Talahiron ES 11/20/08 X 0.495 60 C 0.236 0.300 0.300 - - - 83.60
07 March 2011* 1st/Final* For DPWH, only the region and PMO office are listed 13th CPES Release Page14
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2008 to June 30, 2011
NAME OF CONSTRUCTOR
LICENSE NO. PROJECT
DATE OF EVALUATION AMOUNT
(Php, M) DUR (C.D.)
CONTRACT
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FAC*IMPL. AGENCY
A.R & Mark Builders 31673 Const. of @-CL Maramag CES 02/25/10 X 0.989 105 C 0.418 0.133 0.300 - - - 85.10
A.R Lustre Jr. Construction 7680
Rehab./Reconst./Upgrading of Damaged Paved Nat'l. Rds. At Bigaa-Plaridel via Bulacan and Malolos Rd.
08/27/10 III 14.352 90 C 0.367 0.185 0.300 - - - 85.20
A.R Lustre Jr. Construction 7680
Conc. of Puerto-Princesa-Sabang Road 09/11/09 IVB 48.140 284 C 0.419 0.200 0.300 - - - 91.90
A.R Lustre Jr. Construction 7680
Asphalt Overlay along Capitol-Canigaran Road 11/17/08 IV-B 9.697 60 C 0.332 0.300 0.300 - - - 93.20
A.R Lustre Jr. Construction 7680 Const. of Tagbarungis Bridge, PPSR 08/11/08 IV-B 20.378 240 C 0.374 0.200 0.300 - - - 87.40
A.R Lustre Jr. Construction 7680
Puerto Princesa Airport Development Project 8/13-14/09 DOTC 90.817 270 C 0.488 0.200 0.300 - - - 98.80
A.R Lustre Jr. Construction 7680
Rehab/Reconst./Upgrading of Bigaa-Plaridel via Bulacan and Malolos
Road05/28/09 III 13.077 75 C 0.449 0.196 0.300 - - - 94.50
A.R Lustre Jr. Construction 7680 Conc. of Puerto Princesa South Road 08/22/10 IVB 38.599 216 O 0.364 0.300 0.137 0.030 0.055 0.033 91.90
A.R Lustre Jr. Construction 7680
Construction of Multi-Purpose Building 03/07/09 IV-B 0.383 90 C 0.481 0.107 0.300 - - - 88.80
A.R Lustre Jr. Construction 7680
Repair/Rehab/Impvt. of Santiago-Syjuco E/S 09/17/09 NCR 0.482 45 C 0.482 0.000 0.300 - - - 78.20
A.R.L Construction 27645 Repair/Rehab. of School Building BSU 03/03/10 III 0.989 18 C 0.454 0.148 0.300 - - - 90.20
07 March 2011* 1st/Final* For DPWH, only the region and PMO office are listed 13th CPES Release Page15
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2008 to June 30, 2011
NAME OF CONSTRUCTOR
LICENSE NO. PROJECT
DATE OF EVALUATION AMOUNT
(Php, M) DUR (C.D.)
CONTRACT
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FAC*IMPL. AGENCY
A.R.L Construction 27645 Conc. of Brgy. Road Caniogan 08/27/08 III 0.956 12 C 0.318 0.200 0.300 - - - 81.80
A.R.L Construction 27645 Package IV-MRA-08 Asphalt Overlay of Road @ Poblacion 11/24/08 III 0.500 20 C 0.326 0.300 0.300 - - - 92.60
A.R.L Construction 27645 Riprapping of Access Road @ Poblacion 11/24/08 III 0.477 35 C 0.240 0.300 0.300 - - - 84.00
A.R.L Construction 27645 Rehab/Impvt./Upgrading of Pulilan-Calumpit Road (Pulilan Section) 05/28/09 III 9.542 60 C 0.376 0.200 0.300 - - - 87.60
A.R.L Construction 27645Const. of Flood Control (Revetrment), Poblacion, San Sebastian, San Jose,
Sta. Monica,09/04/09 III 6.697 80 C 0.400 0.133 0.300 - - - 83.30
A.R.L Construction 27645 Upgrading/Conc. of Roads with Drainage Improvement 03/04/09 NCR 0.476 45 C 0.364 0.200 0.300 - - - 86.40
A.R.L Construction 27645Rehab./Reconst./Upgrading of
Damaged Pavement along 7th Ave. East
05/31/10 NCR 6.445 90 C 0.409 0.200 0.300 - - - 90.90
A.S Obquia Construction 19844 Completion of MPB 09/03/08 VII 0.175 120 C 0.366 0.300 0.300 - - - 96.60
A.S.M Francisco Dev't and Construction Corp. 19098 Proposed Exterior Repainting Works 03/24/09 U.P. 1.368 120 C 0.400 0.200 0.300 - - - 90.00
A.S.S Construction 31509 Completion of Alaremil Building II 03/2-3/10 DOST 9.607 250 C 0.496 0.200 0.300 - - - 99.60
A.S.S. Construction 31509 Completion of ACA Building II 05/14-15/09 DOST 9.631 210 O 0.380 0.296 0.150 0.030 0.062 0.050 96.80
A.S.S. Construction 31509 Construction of Sports Complex 05/14-15/09 DOST 3.159 90 C 0.391 0.295 0.300 - - - 98.60
A.S.S. Construction 31509 Partial Completion of vast set, PCASTRD & PCIERD bldg. 07/08/09 DOST 7.479 135 C 0.483 0.200 0.300 - - - 98.30
07 March 2011* 1st/Final* For DPWH, only the region and PMO office are listed 13th CPES Release Page16
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2008 to June 30, 2011
NAME OF CONSTRUCTOR
LICENSE NO. PROJECT
DATE OF EVALUATION AMOUNT
(Php, M) DUR (C.D.)
CONTRACT
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FAC*IMPL. AGENCY
A.S.V Construction Supply and Services 13490
Const. of FMR, Venegas St., Brgy. Layac-Sta.Isabel 05/26/10 III 0.473 60 C 0.444 0.133 0.300 - - - 87.70
A.Y.U Engineering and Construction 25632 Conc. of Road at Brgy. Dumoy 12/03/08 XI 9.435 90 C 0.375 0.300 0.300 - - - 97.50
AB Aponesto Construction, Parts &
Supply22998 Conc. of Lublub-Bolilac-Salad Road, Km.277+707.50-Km.278+711 09/05/10 VI 14.425 192 O 0.356 0.240 0.150 0.030 0.042 0.033 85.10
Abesco Construction & Development Corp. 2934
Construction of Multi-Purpose Building @ Cupang Elem. School 05/21/09 III 3.273 88 C 0.484 0.133 0.300 - - - 91.70
Abu Construction 22313 Const. of Multi-Purpose Building 06/10/10 XII 1.926 126 C 0.494 0.133 0.300 - - - 92.70
Abu Construction 22313 Completion of MPB (Mini Gym) at Brgy. San Rafael 06/08/10 XII 1.897 65 C 0.386 0.133 0.300 - - - 81.90
Abu Construction 22313 Completion of MPB (Gym) at Brgy. Baras 06/08/10 XII 0.764 65 C 0.339 0.133 0.300 - - - 77.20
Abu Construction 22313 Rehab. of Potable Water System @ Brgy. Saravia 08/29/08 XII 0.873 120 C 0.338 0.300 0.300 - - - 93.80
Abulug Construction Company, Inc. 5593
Reblocking along Bangag-Allapacan-Magapit Road (BAMR), KO686+400-
KO687+20009/08/09 II 7.999 150 C 0.406 0.200 0.300 - - - 90.60
Abulug Construction Company, Inc. 5593
Concrete Paving of Ballesteros Road (Washington & Luna St.,) 09/08/09 II 1.930 150 C 0.405 0.200 0.300 - - - 90.50
Abulug Construction Company, Inc. 5593 Const. of Zitanga Brgy. Roads 02/17/10 II 9.648 132 C 0.370 0.200 0.300 - - - 87.00
Abulug Construction Company, Inc. 5593
Rehab. of Ballesteros Central School Building 02/17/10 II 0.192 60 C 0.437 0.133 0.300 - - - 87.00
Abulug Construction Company, Inc. 5593 Construction of Deepwell 02/18/10 II 0.289 60 C 0.396 0.133 0.300 - - - 82.90
07 March 2011* 1st/Final* For DPWH, only the region and PMO office are listed 13th CPES Release Page17
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2008 to June 30, 2011
NAME OF CONSTRUCTOR
LICENSE NO. PROJECT
DATE OF EVALUATION AMOUNT
(Php, M) DUR (C.D.)
CONTRACT
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FAC*IMPL. AGENCY
Abulug Construction Company, Inc. 5593
Conc. of Larion-Cabbo Road, Tuguegarao City & Penablanca 08/27/08 II 13.884 240 C 0.358 0.200 0.300 - - - 85.80
Abulug Construction Company, Inc. 5593 Const. of Colony Road 11/13/08 II 2.894 120 O 0.329 0.240 0.100 0.030 0.033 0.100 83.20
Abulug Construction Company, Inc. 5593 Reblocking along MNR 08/26/08 II 19.296 180 C 0.295 0.215 0.300 - - - 81.00
Abulug Construction Company, Inc. 5593
Replacement of Langagan Bridge along MNR 08/26/08 II 4.814 150 C 0.370 0.201 0.300 - - - 87.10
Abulug Construction Company, Inc. 5593
Concreting of Jct. Claveria-Dibalio-Luzon Road 05/21/09 II 9.648 273 C 0.485 0.133 0.300 - - - 91.80
Abulug Construction Company, Inc. 5593 Const. of Public Market (Phase II) 02/23/09 II 1.446 269 C 0.476 0.133 0.300 - - - 90.90
Abulug Construction Company, Inc. 5593 Lucban River Control Project 02/29/09 II 3.858 347 C 0.417 0.133 0.300 - - - 85.00
Abulug Developers & Builders Co., Inc. 2366 Conc. of Luna Street at Centro West 05/24/10 II 0.964 120 C 0.434 0.200 0.300 - - - 93.40
Abulug Developers & Builders Co., Inc. 2366
Emergency Restoration of Cadcadir Bridge #1 Approach KO 600+(-)595
Phase I05/24/10 II 0.995 90 C 0.419 0.200 0.300 - - - 91.90
Abulug Developers & Builders Co., Inc. 2366
Restoration of Scoured Approaches & Eroded Bank of Cadcadir Bridge 2 KO
602+723 Phase II05/24/10 II 0.771 90 C 0.408 0.200 0.300 - - - 90.80
Abulug Developers & Builders Co., Inc. 2366
Restoration of Scoured Approaches & Eroded Bank of Cadcadir Bridge 1
Phase II, KO 600+ (-594)05/24/10 II 0.963 90 C 0.467 0.134 0.300 - - - 90.10
Abulug Developers & Builders Co., Inc. 2366 Const. of Sto.Tomas FMR 05/25/10 II 0.962 105 O 0.277 0.300 0.150 0.024 0.037 0.050 83.80
07 March 2011* 1st/Final* For DPWH, only the region and PMO office are listed 13th CPES Release Page18
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2008 to June 30, 2011
NAME OF CONSTRUCTOR
LICENSE NO. PROJECT
DATE OF EVALUATION AMOUNT
(Php, M) DUR (C.D.)
CONTRACT
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FAC*IMPL. AGENCY
Abulug Developers & Builders Co., Inc. 2366
Reblocking along Manila North Road (Ballesteros-Abulug Section) 09/08/09 II 18.527 210 C 0.407 0.200 0.300 - - - 90.70
Abulug Developers & Builders Co., Inc. 2366 Construction of 1-CL Bessang E/S 09/08/09 II 0.484 60 C 0.404 0.181 0.300 - - - 88.50
Abulug Developers & Builders Co., Inc. 2366
Emergency/Rehab. of Slope Protection KO 590+640, MNR 02/17/10 II 1.495 90 C 0.417 0.200 0.300 - - - 91.70
Abulug Developers & Builders Co., Inc. 2366
Emergency/Rehab. of Slope Protection KO 590+340, MNR 02/17/10 II 0.995 90 C 0.467 0.133 0.300 - - - 90.00
Abulug Developers & Builders Co., Inc. 2366 Concrete Paving of Jones Street 02/12/10 II 0.868 90 C 0.384 0.200 0.300 - - - 88.40
Abulug Developers & Builders Co., Inc. 2366
Reblocking along Manila North Road (/Fugu Bdry. - Bangag Sect.) 02/17/10 II 19.299 234 C 0.394 0.200 0.300 - - - 89.40
Abulug Developers & Builders Co., Inc. 2366
Rehab./Regravelling of Curva to Capallepaan Farm-to-Market Road 02/18/10 II 0.675 60 C 0.353 0.200 0.300 - - - 85.30
Abulug Developers & Builders Co., Inc. 2366
Road Opening of Pimpila Farm-to-Market Road 02/17/10 II 0.820 75 C 0.348 0.200 0.300 - - - 84.80
Abulug Developers & Builders Co., Inc. 2366
Reblocking along Manila North Road (Fugu Bdry.-Bangag Section) 05/21/09 II 19.299 210 O 0.368 0.240 0.150 0.030 0.051 0.033 87.20
Abulug Developers and Builders Co., Inc.
(Formerly: F. Vargas Construction)
2366 Restoration of River Control Project along Goron & Langgangan River 08/19/10 II 12.542 166 O 0.400 0.300 0.150 0.020 0.043 0.050 96.30
Abulug Developers and Builders Co., Inc.
(Formerly: F. Vargas Construction)
2366 Restoration of Slope Protection KO591+320 - KO591+353, MNR 08/19/10 II 1.928 120 C 0.434 0.200 0.300 - - - 93.40
Abulug Developers and Builders Co., Inc.
(Formerly: F. Vargas Construction)
2366 Const. of Slope Protection at KO673+000 - KO673+853 MNR 08/19/10 II 1.929 90 C 0.420 0.200 0.300 - - - 92.00
07 March 2011* 1st/Final* For DPWH, only the region and PMO office are listed 13th CPES Release Page19
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2008 to June 30, 2011
NAME OF CONSTRUCTOR
LICENSE NO. PROJECT
DATE OF EVALUATION AMOUNT
(Php, M) DUR (C.D.)
CONTRACT
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FAC*IMPL. AGENCY
Abulug Developers and Builders Co., Inc.
(Formerly: F. Vargas Construction)
2366 Conc. along Cadcadir-Kabugao Road 08/19/10 II 5.015 166 O 0.352 0.293 0.150 0.030 0.043 0.050 91.80
Abulug Developers and Builders Co., Inc.
(Formerly: F. Vargas Construction)
2366Emergency Rehab. of Slope
Protection KO600+525 - KO602+200, MNR
08/19/10 II 4.195 90 C 0.347 0.200 0.300 - - - 84.70
Abulug Developers and Builders Co., Inc.
(Formerly: F. Vargas Construction)
2366 Conc. along Claveria Dibalio-Luzon-Cagayan Bdry. Road 08/19/10 II 2.938 153 C 0.374 0.200 0.300 - - - 87.40
Abulug Developers and Builders Co., Inc.
(Formerly: F. Vargas Construction)
2366 Retrofitting of Pamplona Bridge, Manila North Road 02/24/09 II 10.290 180 C 0.386 0.200 0.300 - - - 88.60
Aca Construction & Supply 10784
Construction of Multi-Purpose Building, Bancagan 02/26/09 I 0.096 30 C 0.417 0.133 0.300 - - - 85.00
Aca Construction & Supply 10784 Construction of Water Supply 02/26/09 I 0.096 30 C 0.338 0.188 0.300 - - - 82.60
Aca Construction & Supply 10784 Repair of Farm-to-Market Road 02/26/09 I 0.480 30 C 0.343 0.200 0.300 - - - 84.30
Accuracy Builders Enterprise 27507
River Impvt. of Cabalisian River, Brgy. Sta. Lucia 11/24/08 I 4.485 75 C 0.400 - 0.500 - - - 90.00
Acer Industrial/Solid Rock Construction Joint
Venture
SLI-SN-005433/JV-
08-217
Rehabilitation of Libingan ng mga Bayani Road-MRT Road 05/27/09 NCR 4.694 75 C 0.396 0.133 0.300 - - - 82.90
ACJ Construction Resources 10635
Conc. of Paco-Roxas-Arakan Road Kiyaab-Antipas Section (Km. 1648+300-Km.1649+385.63)
09/05/09 XII 16.826 150 O 0.324 0.300 0.150 0.015 0.042 0.050 88.10
ACJ Construction Resources 10635
Conc. of Poblacion-Magpet-Nowa Road, Nowa-Basak Section w/
exception09/05/09 XII 18.798 200 C 0.358 0.200 0.300 - - - 85.80
ACJ Construction Resources 10635
Asphalt Overlay along Davao-Cotabato Rd., Saguing Section 03/01/10 XII 6.765 68 C 0.429 0.200 0.300 - - - 92.90
07 March 2011* 1st/Final* For DPWH, only the region and PMO office are listed 13th CPES Release Page20
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2008 to June 30, 2011
NAME OF CONSTRUCTOR
LICENSE NO. PROJECT
DATE OF EVALUATION AMOUNT
(Php, M) DUR (C.D.)
CONTRACT
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FAC*IMPL. AGENCY
ACJ Construction Resources 10635
Asphalt Overlay along Davao-Cotabato Rd., Paco Section 03/01/10 XII 7.711 71 C 0.429 0.200 0.300 - - - 92.90
ACJ Construction Resources 10635
Const. of Kinamalig Bridge including Concrete Paving of Approach along
Paco-Roxas-Arakan03/02/10 XII 12.815 202 C 0.384 0.142 0.300 - - - 82.60
ACJ Construction Resources 10635
Conc. of Paco-Roxas-Arakan Road, Kiyab-Antipas Section, Km. 1648+300-
Km. 1649+385.6303/02/10 XII 16.826 175 C 0.379 0.143 0.300 - - - 82.20
ACJ Construction Resources 10635
Conc. of Paco-Roxas-Arakan Road, inclined Gap Ipuan Section, Km. 1640+374.10 - Km. 1646+794.28
03/02/10 XII 13.144 189 C 0.394 0.145 0.300 - - - 83.90
ACJ Construction Resources 10635
Rehab./Reconst. of Damaged Paved along Makilala-Allah Junction Road,
La Esperanza Section06/05/10 XII 9.961 55 C 0.436 0.133 0.300 - - - 86.90
ACJ Construction Resources 10635
Rehab./Reconst. of Damage Paved along Matalam-M'lang-Bagontapay
Road06/05/10 XII 14.307 60 C 0.424 0.133 0.300 - - - 85.70
ACJ Construction Resources 10635
Road Upgrading of Matalam-Mlang-Bagontapay Road, Additional Lane
(Poblacion Section)08/27/10 XII 18.338 153 C 0.476 0.127 0.300 - - - 90.30
ACJ Construction Resources 10635 Const. of MPB 08/23/08 XII 9.634 100 C 0.335 0.270 0.300 - - - 90.50
ACJ Construction Resources 10635 Rechanneling of Malamote River 11/22/08 XII 1.443 45 C 0.375 0.188 0.300 - - - 86.30
ACJ Construction Resources 10635
Concreting of Paco-Roxas-Arakan Road (Luhong-Kiyaab Section) 05/30/09 R-XII 18.566 205 C 0.338 0.200 0.300 - - - 83.80
ACJ Construction Resources 10635
Concreting of Poblacion Magpet-Nowa Road (Nowa Basak Sect.) 03/10/09 XII 18.798 180 O 0.356 0.284 0.150 0.030 0.035 0.050 90.50
07 March 2011* 1st/Final* For DPWH, only the region and PMO office are listed 13th CPES Release Page21
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2008 to June 30, 2011
NAME OF CONSTRUCTOR
LICENSE NO. PROJECT
DATE OF EVALUATION AMOUNT
(Php, M) DUR (C.D.)
CONTRACT
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FAC*IMPL. AGENCY
Acme Builders Corp./MWJ Construction JV JV-08-243
Conc. of Burauen-Albuena Road Km. 98+986.50-Km. 986+857.50 w/
exceptions02/22/10 VIII 46.887 240 C 0.411 0.200 0.300 - - - 91.10
Acme Builders Corporation 6442 Const. of Palo East By-Pass Road 03/11/10 VIII 19.260 240 C 0.436 0.200 0.300 - - - 93.60
Acme Builders Corporation 6442
Rehab./Reconst./Impvt./Upgrading of Damaged Pavement, Tacloban
Baybay South Rd.06/17/10 VIII 34.600 150 O 0.366 0.300 0.150 0.030 0.032 0.033 91.10
Acme Builders Corporation 6442
Rehab./Reconst./Impvt./Upgrading of Damaged Pavement, Tacloban
Baybay South Road09/08/10 VIII 33.358 150 C 0.398 0.133 0.300 - - - 83.10
Acme Builders Corporation 6442
Clearing and Rehab. of Mangonbangon & Burayan River 11/25/08 VIII 9.635 150 C 0.312 0.200 0.300 - - - 81.20
Acme Builders Corporation 6442 Construction of Sinugbuhan Bridge 06/04/09 VI 33.384 676 C 0.441 0.133 0.300 - - - 87.40
Acme Builders Corporation 6442
Asphalt Overlay along Tigbao-Pulak-Sta. Fe Road, Km 925+370-Km
926+37903/18/09 VIII 11.310 90 C 0.393 0.133 0.300 - - - 82.60
Acme Builders Corporation 6442 Construction of Bagacay Bridge 03/02/09 VIII 39.122 332 O 0.319 0.288 0.000 0.030 0.023 0.050 71.00
Acme Builders Corporation 6442 Rehabilitation of Mahayahay Creek 03/03/09 VIII 6.709 170 C 0.375 0.133 0.300 - - - 80.80
Acme Builders Corporation 6442
Const. of Palo East By Pass Road (including Bridge) 09/07/10 VIII 28.738 180 O 0.377 0.240 0.150 0.030 0.042 0.050 88.90
Acme Builders Corporation 6442
Rehab./Reconst./Upgrading of Daang Maharlika, Palo-Tolosa Section, Km.
915+000 to Km. 921+70009/07/10 VIII 24.050 200 O 0.385 0.240 0.150 0.030 0.042 0.033 88.00
07 March 2011* 1st/Final* For DPWH, only the region and PMO office are listed 13th CPES Release Page22
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2008 to June 30, 2011
NAME OF CONSTRUCTOR
LICENSE NO. PROJECT
DATE OF EVALUATION AMOUNT
(Php, M) DUR (C.D.)
CONTRACT
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FAC*IMPL. AGENCY
Acme Builders Corporation / B. Vicencio
ConstructionJV-07-066 Const. of Palo East By Pass Road (Const. of Bernard Reed II Bridge) 08/31/09 VIII 57.823 616 O 0.384 0.240 0.150 0.030 0.047 0.033 88.40
Acme Builders Corporation / MWJ Construction (JV)
JV-08-243 Const. of Albuera-Burauen Road including Bridges, Burauen Sect. 09/02/09 VIII 47.235 240 O 0.352 0.245 0.150 0.030 0.045 0.050 87.20
ACV Construction & Surveying 10903
Concreting of FMR @ Various Brgys., Urbiztondo and Mangatarem 03/09/09 I 3.838 60 C 0.353 0.200 0.300 - - - 85.30
ADB Dynamic Builders & Supply 33359
Repair/Rehab. of St., Brgy. Dalupirit; Rehab. of San Roque St., Brgy.
Vinisitahan; Rehab./Repair of St., Brgy. Pilar
03/07/09 VIII 1.437 60 C 0.463 0.200 0.300 - - - 96.30
Adelfa & Charlie Enterprises 11569
Completion/Continuation of Unfinished/Ongoing Bridges, Calaguise Steel Bridge along
Sambolawan-Calaguise-Calubian Road
08/22/08 VIII 34.810 290 C 0.338 0.200 0.300 - - - 83.80
Adelfa & Charlie Enterprises 11569 Mapuyo CIS 10/6-10/08 NIA 1.485 45 C 0.375 0.180 0.300 - - - 85.50
Adelfa & Charlie Enterprises 11569
Construction of MPP Brgy. Hibulangan 03/11/09 VIII 0.142 30 C 0.433 0.133 0.300 - - - 86.60
Adfil Corporation 14437Rehab. of Magaboy and Lucena Bridge Approaches-Slope/Bank
Protection06/13/10 XIII 4.709 105 C 0.450 0.200 0.300 - - - 95.00
Adfil Corporation 14437 Conc. of Butuan City-Pianing-Tandag Road 06/16/10 XIII 18.905 270 O 0.360 0.300 0.150 0.030 0.045 0.033 91.80
Adfil Corporation 14437 Conc. of NRJ Cuevas-Sampaguita Road 06/14/10 XIII 60.039 270 O 0.388 0.235 0.150 0.030 0.055 0.033 89.10
Adfil Corporation 14437 Rehab. of River Dike 06/01/10 XIII 9.649 150 C 0.408 0.179 0.300 - - - 88.70
Adfil Corporation 14437Repair/Maintenance with Asphalt
Overlay of Tabon-Tabon Slip along Agusan- Davao Road
06/17/10 XIII 32.364 225 O 0.371 0.240 0.150 0.030 0.055 0.033 87.90
07 March 2011* 1st/Final* For DPWH, only the region and PMO office are listed 13th CPES Release Page23
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2008 to June 30, 2011
NAME OF CONSTRUCTOR
LICENSE NO. PROJECT
DATE OF EVALUATION AMOUNT
(Php, M) DUR (C.D.)
CONTRACT
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FAC*IMPL. AGENCY
Adfil Corporation 14437 Rehab. of Magsaysay Bridge along Iligan City 09/09/10 XIII 48.161 300 O 0.352 0.300 0.150 0.030 0.055 0.050 93.70
Adfil Corporation 14437 Completion/Continuation of Libertad Bridge & Approaches 09/08/10 XIII 11.224 180 C 0.462 0.189 0.300 - - - 95.10
Adfil Corporation 14437 Conc. of Pulang Lupa-Sta. Josefa Road 09/06/10 XIII 19.249 195 O 0.371 0.265 0.150 0.030 0.055 0.050 92.10
Adfil Corporation 14437 Conc./Repair of Slip along NRJ Cuevas-Sampaguita Road 09/06/10 XIII 47.951 470 O 0.381 0.252 0.150 0.030 0.055 0.050 91.80
Adfil Corporation 14437 Rehab. of Wawa Bridge along Agusan-Davao Road 09/06/10 XIII 110.862 315 O 0.379 0.263 0.150 0.030 0.055 0.033 91.00
Adfil Corporation 14437Rehab./Along Reconst. of Daang
Maharlika (Agusan-Surigao Road) Ampayon-Taguibo Sect.
09/09/10 XIII 35.253 270 C 0.400 0.200 0.300 - - - 90.00
Adfil Corporation 14437Rehab. of Butuan City-Cagayan de Oro-Iligan Road (Agusan-Mis. Or.
Section)08/25/10 XIII 105.123 210 O 0.334 0.300 0.150 0.030 0.050 0.033 89.70
Adfil Corporation 14437Repair/Maintenance with Asphalt
Overlay of Tabon-Tabon Slip along Agusan-Davao Road
09/06/10 XIII 32.398 225 C 0.440 0.133 0.300 - - - 87.30
Adfil Corporation 14437 Completion/Impvt./Rehab. of Libertad Bridge & Approaches 12/02/08 XIII 26.210 210 C 0.348 0.200 0.300 - - - 84.80
Adfil Corporation 14437 Conc. of Butuan City-Pianing/Tandag Road 12/03/08 XIII 4.012 105 C 0.323 0.200 0.300 - - - 82.30
Adfil Corporation 14437Rehab./Reconst. of Damaged Paved National Roads Gingoog-Calveria-
Villanueva Road09/10/09 X 96.400 405 O 0.259 0.300 0.150 0.030 0.061 0.050 85.00
07 March 2011* 1st/Final* For DPWH, only the region and PMO office are listed 13th CPES Release Page24
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2008 to June 30, 2011
NAME OF CONSTRUCTOR
LICENSE NO. PROJECT
DATE OF EVALUATION AMOUNT
(Php, M) DUR (C.D.)
CONTRACT
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FAC*IMPL. AGENCY
Adfil Corporation 14437 Rehab./Reconst. of NRJ Bahbah-Talacogon Road 06/09/09 XIII 19.263 220 C 0.485 0.200 0.300 - - - 98.50
Adfil Corporation 14437
Repair/Rehab./Impvt. of Roads & Bridges along the National Highway Epoxy Sealing of Cracks in concrete girder, deck slab & conc. Pavement
06/09/09 XIII 9.429 180 C 0.464 0.200 0.300 - - - 96.40
Adfil Corporation 14437 Rehabilitation/Concreting of Tagcatong-Vinapor Road 05/25/09 XIII 9.629 210 C 0.489 0.133 0.300 - - - 92.20
Adfil Corporation 14437 Conc. of Dapa-Junction Cancohoy Road 03/07/09 XIII 28.451 241 C 0.414 0.200 0.300 - - - 91.40
Adfil Corporation 14437Rehab./Reconst. of Damaged Paved
National Road along Agusan-Misamis Road
03/02/09 XIII 9.634 180 C 0.405 0.200 0.300 - - - 90.50
Adfil Corporation 14437Rehab./Reconst. of Damaged Paved
National Road along Agusan-Surigao Road
03/03/09 XIII 9.635 180 C 0.408 0.200 0.300 - - - 90.80
Adfil Corporation 14437Repair/Reconst. of Butuan City-
Cagayan de Oro-Iligan Road (Agusan-Misamis Oriental Road) inc. Bridge
03/18/09 XIII 19.198 210 C 0.402 0.200 0.300 - - - 90.20
Adfil Corporation 14437 Repair/Rehab. of NRJ Bahbah-Talacogon Road 03/20/09 XIII 9.633 188 C 0.431 0.200 0.300 - - - 93.10
Adfil Corporation 14437
Rehab./Reconst. of Damaged Paved National Rd. along Butuan City-CDO-Iligan Rd.,(Agusan-Misamis Oriental
Sect.)Libertad-Bancasi Sect.
09/16/09 XIII 54.954 285 O 0.371 0.300 0.150 0.030 0.055 0.050 95.60
Adfil Corporation 14437Const./Completion/Continuation of Unfinished Bridge and Approaches,
Brgy. Libertad09/16/09 XIII 23.830 195 O 0.364 0.300 0.150 0.030 0.055 0.050 94.90
Adfil Corporation 14437 Rehab. of NRJ-Bahbah-Talacogon Rd. 09/13/09 XIII 14.427 210 C 0.416 0.194 0.300 - - - 91.00
07 March 2011* 1st/Final* For DPWH, only the region and PMO office are listed 13th CPES Release Page25
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2008 to June 30, 2011
NAME OF CONSTRUCTOR
LICENSE NO. PROJECT
DATE OF EVALUATION AMOUNT
(Php, M) DUR (C.D.)
CONTRACT
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FAC*IMPL. AGENCY
Adfil Corporation 14437 Concreting of NRJ-Bahbah-Talacogon Rd. 09/13/09 XIII 15.872 225 O 0.371 0.244 0.150 0.030 0.065 0.050 91.00
Adfil Corporation (Formerly: Adfil Construction)
14437 Const. of River Dike Protection, Brgy. Agao 03/10/10 XIII 9.556 90 C 0.485 0.133 0.300 - - - 91.80
Adfil Corporation (Formerly: Adfil Construction)
14437Impv't./Rehab. of Iligan-Cagayan-
Butuan Rd. (Agusan-Misamis Oriental Section)
02/23/10 XIII 67.446 180 C 0.480 0.133 0.300 - - - 91.30
Adfil Corporation (Formerly: Adfil Construction)
14437 Const./Conc. of NRJ San Francisco-Bahi Rd. 03/07/10 XIII 28.892 330 C 0.431 0.133 0.300 - - - 86.40
Adfil Corporation (Formerly: Adfil Construction)
14437 Upgrading/Conc. of NRJ Cuevas-Bislig Rd. 03/07/10 XIII 28.874 315 C 0.485 0.133 0.300 - - - 91.80
Adfil Corporation (Formerly: Adfil Construction)
14437 Conc. of Dapa-Del Carmen (Sayak-Airport Rd.) 02/26/10 XIII 75.947 390 C 0.456 0.133 0.300 - - - 88.90
Adfil Corporation (Formerly: Adfil Construction)
14437 Rehab./Reconst. of Damaged Rd. Gingoog-Claveria-Villanueva Rd. 03/10/10 X 96.400 405 C 0.437 0.200 0.300 - - - 93.70
Adfil Corporation/RID Corporation (JV) JV-06-022
Repair/Rehab. of Patin-ay Bridge along Agusan-Davao Road, Patin-ay 06/08/09 XIII 23.749 658 C 0.458 0.200 0.300 - - - 95.80
Adige Sta. Clara (JV) JV-06-032DPWH Component Project under the
Help for Catubig Agricultural Advancement Proj.
05/30/09 VIII 519.663 1,073 O 0.378 0.300 0.150 0.030 0.050 0.050 95.80
Adige Sta. Clara (JV) JV-06-032DPWH Component Project under the HELP for Catubig Agricultural Project
(HCAAP)08/25/08 VIII 448.581 734 O 0.377 0.300 0.070 0.030 0.050 0.067 89.40
Adimre Construction 25534 Const. of MPB at Brgy. Bunlo (Phase II) 08/28/08 III 1.907 56 C 0.334 0.200 0.300 - - - 83.40
07 March 2011* 1st/Final* For DPWH, only the region and PMO office are listed 13th CPES Release Page26
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2008 to June 30, 2011
NAME OF CONSTRUCTOR
LICENSE NO. PROJECT
DATE OF EVALUATION AMOUNT
(Php, M) DUR (C.D.)
CONTRACT
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FAC*IMPL. AGENCY
Adimre Construction 25534 Marilao Port Development Project 08/20/09 DOTC 2.862 60 C 0.451 0.200 0.300 - - - 95.10
Adimre Construction 25534 Sta. Cruz Port Development Project 08/20/09 DOTC 0.960 30 C 0.460 0.200 0.300 - - - 96.00
Adimre Construction 25534 Sasmuan Port Development Project 08/20/09 DOTC 2.871 60 C 0.459 0.200 0.300 - - - 95.90
Adimre Construction 25534 Hagonoy Port Development Project 10/02/09 DOTC 0.949 30 C 0.460 0.200 0.300 - - - 96.00
Adimre Construction 25534 Baguio Airport Development Project 04/04/09 DOTC 861.940 60 C 0.435 0.181 0.300 - - - 91.60
Adimre Construction 25534
Dumaguete Airport Dev't Project (Completion of Imprv't of Terminal
Building and Purchase/ Installation of Bagage Conveyor)
01/21/10 DOTC 13.500 90 C 0.402 0.199 0.300 - - - 90.10
Adimre Construction 25534Tuguegarao Airport Dev't Project
(Continuation of Widening of Runway)
03/04/10 DOTC 9.588 90 C 0.452 0.200 0.300 - - - 95.20
Adimre Construction 25534
Tuguegarao Airport Dev't Project (Continuation of Widening of Runway
and Improvement of Fire Station Building)
03/04/10 DOTC 12.490 90 C 0.458 0.200 0.300 - - - 95.80
Adimre Construction 25534
Laoag Airport Development Project (Upgrading of Radar Area,
Continuation of Perimeter Fence Construction of Drainage System)
04/09/10 DOTC 9.604 120 C - 0.419 0.200 0.300 - - 91.90
Adimre Construction 25534Laoag Airport Development Project
(Improvement of Fire Station Building)
04/09/10 DOTC 4.821 120 C 0.464 0.200 0.300 - - - 96.40
Adimre Construction 25534Laoag Airport Development Project
(Shoulder Grade Correction including Drainage System)
04/09/10 DOTC 4.793 75 C 0.410 0.200 0.300 - - - 91.00
Adimre Construction 25534Tuguegarao Airport Development Project (Repair/Rehabilitation of
Terminal Building)09/10/10 DOTC 1.927 90 C 0.449 0.200 0.300 - - - 94.90
07 March 2011* 1st/Final* For DPWH, only the region and PMO office are listed 13th CPES Release Page27
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2008 to June 30, 2011
NAME OF CONSTRUCTOR
LICENSE NO. PROJECT
DATE OF EVALUATION AMOUNT
(Php, M) DUR (C.D.)
CONTRACT
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FAC*IMPL. AGENCY
Adimre Construction 25534 Canalate Port Development Project (Improvement of Port) 12/03/10 DOTC 1.919 60 C 0.458 0.200 0.300 - - - 95.80
Adimre Construction 25534 Const. of Standard One Classroom School Building (Modified) at GITMES 09/05/09 III 0.526 24 C 0.442 0.133 0.300 - - - 87.50
Adimre Construction 25534
Camiguin Ports Cluster Project (Construction of Seawall Enclosure at Benoni Port and Repair of Causeway
at Catarman Port)
02/17/11 DOTC 6.231 60 C 0.419 0.200 0.300 - - - 91.90
Adroit Construction 11169 Const. of 4 CL, Central Luzon State University 11/17/08 III 1.800 90 C 0.319 0.300 0.300 - - - 91.90
Adroit Construction 11169 Completion of Bridge, General Luna 2nd Phase 03/02/09 III 3.026 30 C 0.332 0.200 0.300 - - - 83.20
Adroit Construction 11169 Concreting of Brgy. Maligaya Road 03/02/09 III 1.867 25 C 0.404 0.133 0.300 - - - 83.70
Agafer Construction 7912 Const. of Cagayan River Control 11/11/08 II 14.241 240 O 0.318 0.160 0.030 0.030 0.033 0.133 70.40
Aison Dominique Construction & Supply 32805
Const. of Multi-Purpose Building (Cooperative) 02/23/10 VIII 0.473 86 C 0.399 0.200 0.300 - - - 89.90
Aison Dominique Construction & Supply 32805 Const. of Cabucgayan MPB (Phase III) 08/21/08 VIII 1.896 120 C 0.373 0.187 0.300 - - - 86.00
Ajan Jaeda, inc. 17869 Corollary Works for Banquerohan Resettlement Project, Ph. 2 9/14-18/09 NHA 30.991 150 O 0.398 0.245 0.015 0.024 0.070 0.050 80.15
Ajan Jeada, Inc. (Formerly: Jeada
Construction)17869 Impvt. of MPB, BU College of Engineering Campus 02/24/09 V 16.149 240 C 0.457 0.133 0.300 - - - 89.00
AJYSC Marketing 26924
Road Upgrading (Gravel to Paved) along Isulan-H-way Jct. Dukay-
Dagumbayan-Sen. Ninoy Aquino Road (Sarmiento Sect.)
09/09/09 XII 19.094 235 C 0.392 0.200 0.300 - - - 89.20
07 March 2011* 1st/Final* For DPWH, only the region and PMO office are listed 13th CPES Release Page28
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2008 to June 30, 2011
NAME OF CONSTRUCTOR
LICENSE NO. PROJECT
DATE OF EVALUATION AMOUNT
(Php, M) DUR (C.D.)
CONTRACT
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FAC*IMPL. AGENCY
AJYSC Marketing 26924 Rehab./Impvt. of Bulok Bridge along Marbel-Makar Rd. Km. 1710+722 09/10/09 XII 4.764 90 C 0.400 0.200 0.300 - - - 90.00
AJYSC Marketing 26924 Const./Replacement of Banga Bridge and Approaches Phase II 03/08/10 XII 24.657 240 O 0.350 0.240 0.150 0.030 0.040 0.033 84.30
AJYSC Marketing 26924 Const. of Multi-Purpose Pavement, Norala Park 06/11/10 XII 1.907 133 C 0.410 0.200 0.300 - - - 91.00
AJYSC Marketing 26924Const. of Sapali River Bank
Protection/River Control along Lamsugod to Lamian Section
06/11/10 XII 4.803 140 C 0.400 0.133 0.300 - - - 83.30
AJYSC Marketing 26924Repair of Buayan Bridge and
Approaches and its Protection Structures, Brgy. Buayan
09/09/10 XII 18.855 134 C 0.463 0.133 0.300 - - - 89.60
AJYSC Marketing 26924
Road Upgrading (gravel to paved) Based on Gravel Rd. Strategies,
Surallah-Lake Sebu-Maitum Rd., Lake Sebu Section
09/03/10 XII 19.071 252 O 0.363 0.251 0.150 0.030 0.051 0.033 87.80
AJYSC Marketing 26924 Const./Replacement of Banga Bridge and Approaches, (Phase II) 09/03/10 XII 26.942 255 C 0.428 0.133 0.300 - - - 86.10
AJYSC Marketing 26924
Road Upgrading (Gravel to Concrete) along Isulan Hwy. Jct. Dukay-
Bagumbayan-Sen. Ninoy Aquino Rd. (Sitio Nuling Section)
08/31/10 XII 19.114 220 O 0.305 0.239 0.150 0.030 0.042 0.033 79.90
AJYSC Marketing 26924 Const. of River Bank Protection Allah River (Kolambog Section) 08/27/08 XII 2.874 112 C 0.266 0.300 0.300 - - - 86.60
AJYSC Marketing 26924
Const. of Office and Storage Bldg. and other Office/Quarter
Requirements of DPWH Regional Office XII
06/06/09 R-XII 10.437 150 C 0.477 0.200 0.300 - - - 97.70
AJYSC Marketing 26924 Rehab./Improvement of Bulok Bridge along Marbel-Makar Road 06/05/09 R-XII 4.764 90 O 0.271 0.300 0.150 0.030 0.059 0.050 86.00
AJYSC Marketing 26924 Repair of Multi-Purpose Building at San Emmanuel 03/12/09 XII 0.960 105 C 0.433 0.200 0.300 - - - 93.30
07 March 2011* 1st/Final* For DPWH, only the region and PMO office are listed 13th CPES Release Page29
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2008 to June 30, 2011
NAME OF CONSTRUCTOR
LICENSE NO. PROJECT
DATE OF EVALUATION AMOUNT
(Php, M) DUR (C.D.)
CONTRACT
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FAC*IMPL. AGENCY
AJYSC Marketing 26924Road Upgrading (Gravel to concrete)
along Surallah-Lake Sebu-Maitum Road
03/15/09 XII 16.034 289 C 0.476 0.200 0.300 - - - 97.60
AKH Construction and Trading Corporation 20759
Rehab./Reconst. of Damaged Pavement of Legarda St. 08/14/08 NCR 6.713 90 C 0.346 0.235 0.300 - - - 88.10
AKH Construction and Trading Corporation 20759
Repair/Maintenance of Waiting Area / Lounge of Secretary's Office DPWH
Central Office05/19/09 NCR 7.230 60 C 0.500 0.133 0.300 - - - 93.30
AKH Construction and Trading Corporation 20759
Construction of Multi-Purpose Building Phase I, T. Paez Elem.
School02/27/09 NCR 9.645 60 C 0.389 0.013 0.300 - - - 70.20
AKH Construction and Trading Corporation 20759
Proposed Rehab. of MPB at T. Paez Elem. School (Phase 2) 09/01/09 NCR 10.609 90 C 0.476 0.133 0.300 - - - 90.90
AKH Construction and Trading Corporation 20759
Proposed Repair/Rehab. of Roads & Drainage at Brgy. 598/600 02/16/10 NCR 2.888 90 C 0.453 0.133 0.300 - - - 88.60
AKN Construction Corporation (Formerly:
AKN Const.)11845
Proposed Impvt. of Road inc. Drainage System along Magallanes
St., Brgy. Tunasan02/25/09 NCR 19.089 162 C 0.341 0.184 0.300 - - - 82.50
AKN Construction Corporation (Formerly:
AKN Construction)11845 Rehab./Reconstruction/Upgrading of Ninoy Aquino Avenue 06/02/09 NCR 19.092 45 C 0.418 0.200 0.300 - - - 91.80
AKN Construction Corporation (Formerly:
AKN Construction)11845
Rehab./Reconstruction of Muntinlupa Insular Prison Road and its Vicinity,
Brgy. Poblacion09/09/09 NCR 19.113 100 O 0.297 0.219 0.150 0.023 0.035 0.050 77.40
AKN Construction Corporation (Formerly:
AKN Construction)11845
Reconst./Const. of Dikes, Valenzuela-Obando Bdry. Dike, Brgy. Palasan
and Pariancillo Villa08/19/10 NCR 2.850 90 C 0.339 0.200 0.300 - - - 83.90
Al Chris Construction 12406 Concrete Paving of Panglao Island Circ. Road, Songculan 08/24/10 VII 9.075 130 O 0.385 0.233 0.150 0.023 0.037 0.050 87.80
07 March 2011* 1st/Final* For DPWH, only the region and PMO office are listed 13th CPES Release Page30
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2008 to June 30, 2011
NAME OF CONSTRUCTOR
LICENSE NO. PROJECT
DATE OF EVALUATION AMOUNT
(Php, M) DUR (C.D.)
CONTRACT
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FAC*IMPL. AGENCY
Al Chris Construction 12406 Conc. of (LIR) Loay-Loboc-Carmen Road (Loboc Section) 08/28/08 VII 4.492 85 C 0.316 0.042 0.000 - - - 35.80
Al Chris Construction 12406 Const. of Two (2) CL Sch. Bldg. w/o Toilet, San Roque H/S 11/18/08 VII 0.841 240 C 0.390 0.200 0.300 - - - 89.00
AL Chris Construction 12406 Tagbilaran Airport Development Project 03/27/09 NIA 5.756 120 C 0.390 0.200 0.300 - - - 89.00
Al Fahdel Const. and Services 17953
Conc./Impvt. of Tubod-Ganassi Road (Caniogan Section) Sta. 1602+0000-
Sta. 1603+000 w/ exception09/14/09 X 18.126 150 C 0.429 0.200 0.300 - - - 92.90
Al Hussein Construction 18438
Rehab./Reconst./Upgrading along Misamis Oriental- Ma. Cristina Bdry.
Road at Marcelo-Timoga Section, Sta.1532+961 - Sta.1535+068 w/
06/09/10 X 9.255 105 O 0.386 0.240 0.150 0.030 0.055 0.033 89.40
Al Hussein Construction 18438 Conc. of Kibawe-Kadingilan-Kalilangan Road, Kadilingan Sect. 06/14/10 X 73.672 330 C 0.407 0.168 0.300 - - - 87.50
Al Hussein Construction 18438
Rehab./Reconst./Upgrading of Segapod Maigo Kolambugan Section,
Sta. 1564+000 - Sta.1566+000 w/ exception
06/09/10 X 18.546 150 O 0.383 0.240 0.127 0.030 0.055 0.033 86.80
Al Hussein Construction 18438 Rehab. of Linamon-Zamboanga Road, Baroy Section 08/30/08 X 4.525 90 C 0.344 0.200 0.300 - - - 84.40
Alafalfa Construction 29712
Restoration of Roadslip along Nueva Vizcaya-Ifugao-Mt. Province Bdry. Road, Km. 330+800-Km. 330+828,
Phase I
08/25/10 CAR 1.238 136 C 0.445 0.133 0.300 - - - 87.80
Alajeno Construction and Supplies 28713
Const. of Public Market at Brgy. Penoles, Lakewood 06/11/10 IX 0.495 45 C 0.491 0.133 0.300 - - - 92.40
Alajeno Construction and Supplies 28713
Construction of MPB (Municipal Building) Phase II 06/02/09 IX 2.480 120 C 0.440 0.133 0.300 - - - 87.30
Alajeño Construction and Supplies 28713
Const. of MPB (Municipal Bldg.) Phase I 11/27/08 IX 4.595 160 C 0.373 0.164 0.300 - - - 83.70
07 March 2011* 1st/Final* For DPWH, only the region and PMO office are listed 13th CPES Release Page31
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2008 to June 30, 2011
NAME OF CONSTRUCTOR
LICENSE NO. PROJECT
DATE OF EVALUATION AMOUNT
(Php, M) DUR (C.D.)
CONTRACT
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FAC*IMPL. AGENCY
Alajeño Construction and Supplies 28713 Const. of Sch. Bldg. @ Antonio NHS 08/30/08 IX 0.481 30 C 0.209 0.200 0.300 - - - 70.90
Al-B Construction 11740Rehab./Reconst./Upgrading along
Angeles-Porac-Floridablanca-Dinalupihan Rd.
06/01/10 III 18.839 90 O 0.389 0.240 0.150 0.030 0.047 0.033 88.90
Al-B Construction 11740
Rehab./Reconst./Upgrading of Damaged Paved Nat'l. Rd. along Angeles-Porac-Floridablanca-
Dinalupihan Rd.
08/16/10 III 19.175 100 C 0.438 0.160 0.300 - - - 89.80
Alberich Builders 27987 Repair/Impvt. of Masarawang-Mabatano-Pamasan Road 11/13/08 V 0.956 30 C 0.316 0.200 0.300 - - - 81.60
Alberto Uy Construction & Development 20924 Const. of MPB at Buong Lupa 05/26/10 IVB 0.480 43 C 0.447 0.180 0.300 - - - 92.70
Alberto Uy Construction & Development 20924 Const. of Drainage Canal 11/19/08 IV-B 1.889 91 C 0.358 0.200 0.300 - - - 85.80
Alberto Uy Construction & Development 20924
Repair/Rehab. of Multi-Purpose Building @ Sitio Facoma, Bagong
Bayan II05/27/09 IV-B 0.476 45 C 0.424 0.170 0.300 - - - 89.40
Alberto Uy Construction & Development 20924 Concreting of Cantil-Dayhagan Road 02/26/09 IV-B 0.947 69 C 0.436 0.133 0.300 - - - 86.90
Alcel Construction 15129 Const. of San Vicente-Pogo Bridge, San Vicente 03/01/10 I 22.182 380 C 0.333 0.200 0.300 - - - 83.30
Alcel Construction 15129
Repair/Rehab. along Manila North Road, Km. 445+28 - Km.484+897,
Pinili, Badoc, Currimao, Batac & San Nicolas
06/02/10 I 9.649 60 C 0.473 0.133 0.300 - - - 90.60
Alcel Construction 15129Repair/Impvt. of Agoo Processional Road, Km. 235+298-Km. 236+708 w/
exception08/25/10 I 8.652 90 C 0.405 0.133 0.300 - - - 83.80
07 March 2011* 1st/Final* For DPWH, only the region and PMO office are listed 13th CPES Release Page32
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2008 to June 30, 2011
NAME OF CONSTRUCTOR
LICENSE NO. PROJECT
DATE OF EVALUATION AMOUNT
(Php, M) DUR (C.D.)
CONTRACT
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FAC*IMPL. AGENCY
Alcel Construction 15129 Rehab./Impvt. at Kennon Road, Km.244+000 - Km.248+138 06/09/10 CAR 9.616 60 C 0.358 0.200 0.300 - - - 85.80
Alcel Construction 15129 Construction of School Building at Cayucay NHS 03/10/09 I 0.913 75 C 0.394 0.181 0.300 - - - 87.50
Alcel Construction 15129 Rehab./Reconst./Upgrading of Mangaldan-Manaoag-Binalonan Road 08/28/09 I 48.250 240 C 0.422 0.200 0.300 - - - 92.20
Alcel Construction 15129 Completion of MPB, PSU Bamban 08/29/08 I 0.474 60 C 0.292 0.200 0.300 - - - 79.20
Alcel Construction 15129 Conc. of FMR, Brgy. Licsi 11/27/08 I 0.568 30 C 0.379 0.200 0.300 - - - 87.90
Alcel Construction 15129Asphalt Overlay of Sta. Barbara-
Mangaldan Road Km. 203+700-Km. 205+300 w/exception
05/26/09 I 14.473 25 C 0.458 0.133 0.300 - - - 89.10
Aldana Construction 21763 Construction of Perimeter Fence Gate, Slope Protection 03/2-3/10 DOST 6.363 75 C 0.491 0.20 0.30 - - - 99.10
Aldana Construction 21736 Const. of Drainage Poblacion Zone II 03/04/10 I 2.407 90 C 0.398 0.133 0.300 - - - 83.10
Aldana Construction 31174 Road Conc. of Farm-to-Market Road, Brgy. Sallacong (San Mariano) 02/19/10 I 1.901 70 C 0.329 0.200 0.300 - - - 82.90
Aldana Construction 21736 Const. of MPB (Phase V) 06/10/10 I 7.715 125 C 0.447 0.133 0.300 - - - 88.00
Ale Builders Construction & Development Corp. 5180
Drainage Impvt. along Boni-Serrano Avenue 03/02/10 NCR 4.754 90 C 0.440 0.133 0.300 - - - 87.30
07 March 2011* 1st/Final* For DPWH, only the region and PMO office are listed 13th CPES Release Page33
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2008 to June 30, 2011
NAME OF CONSTRUCTOR
LICENSE NO. PROJECT
DATE OF EVALUATION AMOUNT
(Php, M) DUR (C.D.)
CONTRACT
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FAC*IMPL. AGENCY
Ale Builders Construction & Development Corp. 5180
Proposed Const. of Roads and Drainage at Baseco Compound 02/16/10 NCR 72.324 303 C 0.368 0.190 0.300 - - - 85.80
ALE Builders Construction &
Development Corp.5180
Proposed Rehab./Reconst./Upgrading of