Upload
bianca
View
32
Download
2
Tags:
Embed Size (px)
DESCRIPTION
County Operations Center Development Project Update. Presentation to the California Counties Architects and Engineers Association. Department of General Services April Heinze, PE, Director Presenter: Jeff Redlitz, Project Manager February 17, 2012 . County Operations Center Development - PowerPoint PPT Presentation
Citation preview
County Operations Center Development Project Update
Department of General ServicesApril Heinze, PE, Director
Presenter: Jeff Redlitz, Project ManagerFebruary 17, 2012
Presentation to the California Counties Architects and Engineers
Association
County Operations Center DevelopmentProgress Report – February 2012
Project ScopeRedevelop the COC and COC Annex to replace outdated and inefficient buildings that have reached the end of their useful life; consolidate operations; and vacate leased space.• Demolish over twenty (20) buildings totaling over 623,600 sq ft;• Construct in phased development:
Phase 1A• Two (2) approx. 150,000 sq ft, four-story Office Buildings• Seven-level Parking Structure for 1,826 vehicles• New Central Plant and Site Infrastructure• Offsite Improvements to support masterplanned development
Phase 1B• Two (2) approx. 150,000 sq ft, four-story Office Buildings• 15,000 sq ft Conference Center and Food Service
Phase 2, not yet funded• Two (2) approx. 150,000 sq ft, four-story Office Buildings• Seven-level Parking Structure for 2,400 vehicles
• Relocate Registrar of Voters and remaining Annex Occupants• Sell the Annex for an agreed minimum price to Developer upon the completion of
Phase 1B
2
Buildings 203 & 204
Conference CenterHazard Way
Facility
County Operations Center Development Phase 1A and Phase 1B
Buildings 201 & 202
Completed 2010
3
County Operations Center Development Complete Phase 1 and Phase 2
County Operations Center Development Phase 1Progress Report – February 2012 Under Budget
BudgetBudget Actual
Phase 1A $188.5 M $167.8 M $9M Savings to GF;$11.7M Savings to Phase 1B and ROV
Phase 1B $119. 8 M $62 M expended to date
Phase 2 $150.7 M Not yet funded
ROV/COC Annex Relocations
$56 M $31 M expended to date
Contribution to HHSA FRC Relocation, Chesapeake acquisition
Revenue from Sale of the Annex Site
$30 M min. #
# subject to final entitlement
County Operations Center Development Phase 1Progress Report – February 2012 On Schedule
ScheduleApr 2008 Board approved DDA for $531 M over 5 yearsMar 2009 Relocated HHSA FRC with No. Central Public Health CenterApr 2009 Groundbreaking for Phase 1AOct 2010 Ribbon Cutting for Phase 1AJan 2011 Site work for Phase 1B beginsFeb 2011 Parking Structure 1A openedAug 2011 Renovation of Hazard Way buildings completeNov 2011 Purchased 7 acre site adjoining COC campus for ROVJuly 2012 Ribbon Cutting for Phase 1B
Sep 2012 Begin construction of new ROV building
Dec 2013 Ribbon Cutting for new ROV bldg., close sale of Annex to Kaiser
County Operations Center Development Phase 1Progress Report – February 2012
Accomplishments and Benefits
• Constructed 875,155 sq ft, including the Parking Structure:• Phase 1A Office Buildings LEED Gold Certified• Medical Examiner & Forensic Center LEED Silver Certified• Phase 1B Office Buildings designed for Energy Star Rating & LEED Gold• 627,216 kilowatt‐hours/year Photovoltaic System on the Parking Structure
• Demolished over twenty (20) outdated buildings totaling over 623,600 sq ft• Eliminated over 138,000 sq ft of Leased Space• $2.5 M annual savings in Leased -v- Owned space cost
• $400 K Savings by Design Incentives earned
• California Center for Sustainable Energy 7th Annual CCSE Energy All-Star Award for “Outstanding Governmental Building Project” (COC campus Phase 1)
• SDG&E 6th Annual SDG&E Energy Showcase Award for New Construction/ Sustainability (COC campus Phase 1)
County Operations Center Development Phase 1Progress Report – February 2012
Construction Sequencing “Flip Book”
County Operations Center Development Phase 1Progress Report – February 2012 1
County Operations Center Development Phase 1Progress Report – February 2012 2
County Operations Center Development Phase 1Progress Report – February 2012 3
County Operations Center Development Phase 1Progress Report – February 2012 4
County Operations Center Development Phase 1Progress Report – February 2012 5
County Operations Center Development Phase 1Progress Report – February 2012 6
County Operations Center Development Phase 1Progress Report – February 2012 7
County Operations Center Development Phase 1Progress Report – February 2012 8
County Operations Center Development Phase 1Progress Report – February 2012 9
County Operations Center Development Phase 1Progress Report – February 2012 10
County Operations Center Development Phase 1Progress Report – February 2012 11
County Operations Center Development Phase 1Progress Report – February 2012 12
County Operations Center DevelopmentProgress Report – February 2012
13
Phase 2 not yet funded;Shown prior to purchase of Chesapeake site
County Operations Center DevelopmentProgress Report – February 2012
Occupancy9225 Chesapeake Scheduled completion Summer 2012
• Sheriff Inmate Transportation• Probation Work Projects• General Services Facilities Operations 9255 Chesapeake Scheduled completion Summer 2012
• Sheriff Wireless Services• Sheriff Vehicle Coordinator
REGISTRAR OF VOTERS Scheduled completion Dec 2013• Registrar of Voters• DGS Mail Services / A&C Mail Processing / TTC Remittance Processing
HAZARD WAY Occupied Aug. 2010• Agriculture, Weights & Measures• Farm & Home Advisor (UCSD Extension)• Sheriff Alternate Custody Unit
BUILDING 204 – 5530 Scheduled completion Aug 20121.Public Defender/Alt Public Defender Juvenile Dependency Campus Fitness Center
2. Human Resources3.Auditor & Controller Revenue & Recovery Sheriff Pharmacy
4.Auditor & Controller
BUILDING 203 – 5510 Scheduled completion Aug 20121. Planning & Land Use• Permit Center2. Public Works, Fire Authority and SANGIS3. Planning & Land Use4. Public Works
CONFERENCE CENTER Scheduled completion Aug 2012• Public Hearing Chambers• Cafe
BUILDING 201 – 5500 Occupied Oct. 20101.Environmental Health San Diego County Credit Union
2.Environmental Health 3.Public Works Sheriff SID
4.Parks & Recreation5.Treasurer-Tax Collector (conditional)
BUILDING 202 – 5560 Occupied Oct. 20101.Library Public Administrator/Public Guardian (summer 2012)
2.Purchasing & Contracting (summer 2012) Property Management/Security Sheriff JIMS/IT
3.Aging & Independence Services4.General Services
Central Plant
Sheriff Data Services
Sheriff CommunicationsEmergency Operations Center
Fleet Services
Phase 2 Buildings Not Yet Funded
Medical Examiner and Forensic Center
Chesapeake Property Acquired Nov. 2011
County Operations Center Development Phase 1Progress Report – February 2012 On Schedule, Under Budget
Cafeteria – in Conference Center
Parking Structure
Building 2 Shops and Central plantBefore
Today New Central PlantCampus Entry
County Operations Center Development Phase 1Progress Report – February 2012 On Schedule, Under BudgetAugust 2009
February 2012Conference Center
January 2011
Medical Examiner & Forensic Center
Archival Display Project Open Office Work Station Planning
Primary Campus Public Entry
County Operations Center Development Phase 1Progress Report – February 2012 On Schedule, Under Budget
Public Hearing Chamber – in Campus Center
Parking Structure
Central Allee’ Construction
Campus Center – LEED Platinum
County Operations Center Development Phase 1Progress Report – February 2012 On Schedule, Under Budget
August 2009
February 2012
January 2011
Campus Entrance at Overland