Upload
herly-fajrie-hermaiita
View
219
Download
0
Embed Size (px)
Citation preview
8/9/2019 Cost Estimate-S1 Module 3
1/16
Cost EstimateCost EstimateModule 3Module 3
Dr. Ari Sandhyavitri
Engineering Faculty
UNRI, 2004
8/9/2019 Cost Estimate-S1 Module 3
2/16
Cost and PriceCost and Price
Cost : cost directly attributable to an element ofwork plus overhead.
Cost = direct costs + overhead (e.g. 5%-10%).
Price : cost of an element of work plus allowancefor general overhead, insurance, taxes, interest
charges, and profits (contributions).
Price = cost estimate+ risk+ overhead+ profit+mark up/mark down.
8/9/2019 Cost Estimate-S1 Module 3
3/16
Cost ComponentsCost Components
Cost (Direct costcomponents):
Labours
Materials Equipment
Sub-contractors
Price (In-direct cost
components): Taxes
Insurances
Overheads: Offices & adms.
Sites
General conditions
Risks: Contingencies
Loss & profit
8/9/2019 Cost Estimate-S1 Module 3
4/16
Category of EstimationCategory of Estimation
Abduh, 2004 summarised 4 category ofestimation:
Order of magnitude estimation
Budget estimation
Defined estimation
8/9/2019 Cost Estimate-S1 Module 3
5/16
8/9/2019 Cost Estimate-S1 Module 3
6/16
Terms of PaymentTerms of Payment
Price based: ls and unit rate submitted by acontractor in tender.
Cost based: cost reimbursable and target
costs. The actual cost incurred by the
contractor are reimbursed plus fee,
overhead and profits.
8/9/2019 Cost Estimate-S1 Module 3
7/16
1a. Lump Sum1a. Lump Sum
Based on a single tendered price for thewhole works.
Amount to pay is fixed (or subject to
change for escalation). Paid after completion a major stage of work
or a milestone (defined stage of progress)
a planned payment scheme. Inflexible.
8/9/2019 Cost Estimate-S1 Module 3
8/16
1b. Advantages and Disadvantages of Ls1b. Advantages and Disadvantages of Ls
Advantages: High degree of certainty about the final price.
Administration is easy.
Keen pricing.
The promoters mgt. resources are freed for otherprojects.
Disadvantages:
Unsuitable for any changes. The lowest bidder may in the loss situation (bear
the overall financial and economic risks).
Minimum involvement of the promoters and design
org. in the mgt. of construction.
8/9/2019 Cost Estimate-S1 Module 3
9/16
2a. Unit Rate2a. Unit Rate((AdmeasurementAdmeasurement))
Bill of Quantities (BoQ) or Schedule Rates. Items of work are specified with quantities.
Tender rates against each item of works.
Payment : monthly or measuring quantities completed
works or valuing the rates in the tender or new negotiatedrates.
A scheduled of measured works or rates : total price isfixed rates but it changes if the quantities change (+/-15%).
Separate organisation structures.
Completed major design.
Public sector users.
E.g. bridges, roads, schools and urban sewerage systems.
8/9/2019 Cost Estimate-S1 Module 3
10/16
2b. Advantages and Disadvantages of2b. Advantages and Disadvantages ofBoQBoQ
Advantages: Widely used. Offer some degree of flexibility for design change.
May overlap design and construction progress.
Competitive bidders.
Indication of final price (change is low).
Disadvantages: Claims resolution is difficult (Quantity based).
Limited flexibility (involvement of promoters in the mgt. and to
add new items). Under disruption and major change emerge, the final price may not
be determined.
8/9/2019 Cost Estimate-S1 Module 3
11/16
3a. Cost Reimbursable3a. Cost Reimbursable Payment of actual cost + fees (for overhead and profits).
Contractors cost account are open to the promoters (Open-bookaccounting).
The scope and timing of works are uncertain. Almost impossible to define quantity of works and the
programmes.
E.g. installation of pipe works and cables, repairs, services,
demolition, an emergency project/ rescue of disruption projects,and site clearing.
Agreed period (terms).
Monthly or based on an impressed account.
Promoters pay all satisfactory accepted works (reimburse) andsome rejected works.
Contractors technical risks are low.
The contractors profit rate is lower than BoQ.
Contractor is an extension of promoters organisation.
8/9/2019 Cost Estimate-S1 Module 3
12/16
3b. Advantages and Disadvantages of3b. Advantages and Disadvantages ofCost ReimbursableCost Reimbursable
Advantages: Extremely flexible.
Fair pay and good control of risks.
Promoters involvement.
Joint planning.
Knowledge of actual costs.
Disadvantages :
Little incentives to the contractors efficiency.
No estimate of the final price at tender.
Administration procedures are unfamiliar.
8/9/2019 Cost Estimate-S1 Module 3
13/16
4a. Target Costs4a. Target Costs
Promoters and contractors agreed at the start aprobable (target) costs for an uncertain scope ofwork (inadequate definition of work).
Promoters role are significant.
Contractors actual cost monitored andreimbursed.
Final cost Actual cost will be shared (usingincentive mechanism).
Fee of the contractor covers o/h and cost in thecontract (excluding profit).
8/9/2019 Cost Estimate-S1 Module 3
14/16
AC = Actual Cost
TC = Target cost
8/9/2019 Cost Estimate-S1 Module 3
15/16
4b. Advantages and Disadvantages4b. Advantages and Disadvantagesof Target Costof Target Cost
Advantages: Fair payment and control risks.
Flexibility of design changes.
Encourage to be efficient (common interest).
Promoters involvement.
Should ensure adequate resources and methods.
Knowledge improvement.
Disadvantages: Full promoters involvement and need to change
attitude from BoQ contract.
Unfamiliar administration procedures.
8/9/2019 Cost Estimate-S1 Module 3
16/16
ReferencesReferences
Smith, N. J. (Editor), Engineering Project
Management, Blackwell Science, 1999,
UK.
Peurfoy, R, L and Oberlender, G, D, (1989),Estimating Construction Costs, McGraw-
Hill Book Company,USA.