Upload
sharelyn-nebreja
View
219
Download
0
Embed Size (px)
Citation preview
8/11/2019 Cost Crashing
http://slidepdf.com/reader/full/cost-crashing 1/6
1.
From the following data;
a.
What is the least duration of the project in weeks?
b.
What is its least direct cost corresponding to this least duration?
c.
If the completion of the project is set at two week longer than the least
duration, what is the project’s optimum cost if the penalty is P3,000 per
week for delay and the indirect cost is P7,000 per week?
ACTIVITY TIME IN WEEKS COST COST TO
EXPEDITE/WEEKNORMAL CRASH NORMAL CRASH
1-2 9 6 10,000 16,000 1,500
1-3 8 4 4,000 8,000 1,000
1-4 6 3 2,400 4,800 1,000
2-4 5 2 2,000 3,500 500
2-5 7 4 2,100 2,700 200
3-4 4 2 3,200 3,800 300
3-6 6 3 1,800 2,400 200
4-5 3 1 4,500 5,500 500
4-7 6 2 1,800 2,600 200
5-7 4 2 3,200 5,600 1,200
5-8 8 4 2,400 4,400 500
6-7 5 3 1,000 1,760 380
6-9 5 2 2,400 2,800 2007-9 3 1 3,000 4,600 800
8-10 5 2 7,000 10,000 1,000
9-10 10 6 6,000 8,800 700
1 4 7
2
3
8
6
5
9
8/11/2019 Cost Crashing
http://slidepdf.com/reader/full/cost-crashing 2/6
2.
From the following diagram and data;
a.
What is the least duration of the project in weeks?
b.
What is its least direct cost corresponding to this least duration?
c.
If the completion of the project is specified at two week longer than the
least duration, what is the project’s optimum cost if the penalty is P2,000
per week for delay and the indirect cost is P4,000 per week?
ACTIVITY TIME IN WEEKS COST COST TO
EXPEDITE/WEEKNORMAL CRASH NORMAL CRASH
1-2 8 4 6,000 12,000 1,000
1-3 12 6 7,000 11,000 500
1-4 6 2 2,400 3,200 400
2-3 5 3 4,800 5,400 200
2-4 4 1 1,500 2,400 400
2-5 12 8 4,200 6,000 300
3-5 5 4 1,800 2,600 400
4-5 5 2 2,000 3,000 500
5-6 4 3 2,400 2,900 500
5-7 4 2 3,200 4,000 400
5-8 4 3 3,000 4,500 750
5-9 6 4 2,400 3,200 200
6-9 5 2 2,200 2,000 200
1
4
3
2
8
7
6
5 9
8/11/2019 Cost Crashing
http://slidepdf.com/reader/full/cost-crashing 3/6
3.
From the following diagram and data;
a.
What is the least duration of the project in weeks?
b.
What is its least direct cost corresponding to this least duration?
c.
If the completion of the project is set at two week longer than the least
duration, what is the project’s optimum cost if the penalty is P2,000 per
week for delay and the indirect cost is P4,000 per week?
ACTIVITY TIME IN WEEKS COST COST TO
EXPEDITE/WEEKNORMAL CRASH NORMAL CRASH
1-2 4 1 6,000 8,000 1,000
1-4 6 3 8,000 10,000 1,000
2-3 3 1 4,000 6,000 2,000
2-4 3 1 7,000 8,000 500
2-5 5 2 5,000 6,500 750
4-5 7 3 9,000 10,500 500
4-7 6 3 6,000 6,500 250
5-7 3 1 1,200 2,000 800
5-8 5 1 6,200 7,000 400
5-9 6 2 6,000 9,000 1,000
6-7 3 1 2,000 2,600 600
7-9 4 1 3,600 4,000 200
1
83
2 5
6
9
4 7
8/11/2019 Cost Crashing
http://slidepdf.com/reader/full/cost-crashing 4/6
4.
From the following diagram and data;
a.
What is the least duration of the project in weeks?
b.
What is its least direct cost corresponding to this least duration?
c.
If the completion of the project is specified at two week longer than the
least duration, what is the project’s optimum cost if the penalty is P2,000
per week for delay and the indirect cost is P5,000 per week?
ACTIVITY TIME IN WEEKS COST COST TO
EXPEDITE/WEEKNORMAL CRASH NORMAL CRASH
1-2 3 1 1,000 2,000 500
2-3 2 1 5,000 8,000 3,000
3-4 4 2 8,000 12,000 2,000
3-5 2 1 10,000 12,000 2,000
3-10 10 4 10,000 14,000 1,000
4-7 6 3 6,000 8,000 500
5-6 3 1 6,000 7,000 1,000
6-8 5 2 2,000 3,800 600
7-9 5 2 8,000 9,000 500
8-11 3 2 6,000 7,000 500
9-13 4 1 5,000 5,900 300
10-12 4 1 6,000 7,000 500
11-12 7 3 4,000 6,000 500
12-13 4 2 3,000 4,500 750
13-14 5 2 4,000 5000 100
8/11/2019 Cost Crashing
http://slidepdf.com/reader/full/cost-crashing 5/6
5.
The project engineer constructing a grandstand for the palarong pambansa
expected to complete the project prior to the opening of the games. After
reviewing the construction time estimates, it appears that a certain amount of
crashing will be needed to ensure that the project is completed before the
target date.
From the given time and cost estimate, determine a minimum cost
crashing schedule that will shorten five weeks off the project length.
ACTIVITY PRECEDES NORMAL TIME NORMAL CRASHING COST
FIRST WEEK SECOND WEEK
A B 12 20,000 20,000
B K 14 12,000 12,000
C D,E,F 10 6,000 6,000
D G 17 20,000 22,000
E H 18 16,000 18,000
F I 12 12,000 15,000
G L 15 25,000 25,000
H M,N 8 --- ---
I J 7 30,000 ---
J N 12 25,000 25,000
K END 9 10,000 10,000
L END 3 --- ---
M END 11 40,000 ---
N END 8 20,000 20,000
8/11/2019 Cost Crashing
http://slidepdf.com/reader/full/cost-crashing 6/6
6.
A construction project has indirect costs of P40,000 per week. The following
diagram shows the major activities and time. Determine the optimum time
cost crashing plan.
ACTIVITY CRASHING COSTS
FIRST WEEK SECOND WEEK THIRD WEEK
1-2
2-5
5-7
7-11
11-13
20,000
24,000
30,000
15,000
30,000
24,000
25,000
30,000
20,000
33,000
----
25,000
35,000
----
35,000
1-3
3-8
8-11
3-9
9-1212-13
12,000
----
40,000
3,000
2,00025,000
24,000
----
40,000
8,000
7,000----
28,000
----
40,000
10,000
10,000----
1-4
4-6
6-10
10-12
10,000
8,000
5,000
14,000
15,000
13,000
12,000
15,000
25,000
----
----
----