Control Status Readiness Report
12 June 2008 LHC – MAC
Eugenia Hatziangelion behalf of
the CERN Accelerator and BeamsControls Group
1
Outline
• LHC controls infrastructure – overview
• Status Report on Core Controls– Front ends Hardware and Software – Databases– Industrial Controls– Machine Interlocks– The LHC timing system
• Core Services and Applications– Post mortem– Sequencer for HWC– See next talk for Beam Sequencer– Logging– Software Interlock System– LSA (see next talk)
• Controls Security– Role Based Access– Management of Critical Settings– LHC Controls Security Panel
• Controls Infrastructure Tests– Deployment on LEIR, SPS, LHC TL– Dry runs - Commissioning– Scalability Tests– LHC Timing Crash Tests– RBAC tests
• Monitor and Diagnostics– LASER– DIAMON
• Injector Renovation• Summary
12 June 2008 2E. Hatziangeli AB/CO
Outline
• LHC controls infrastructure – overview
• Status Report on Core Controls– Front ends Hardware and Software – Databases– Industrial Controls– Machine Interlocks– The LHC timing system
• Core Services and Applications– Post mortem– Sequencer for HWC– See next talk for Beam Sequencer– Logging– Software Interlock System– LSA (see next talk)
• Controls Security– Role Based Access– Management of Critical Settings– LHC Controls Security Panel
• Controls Infrastructure Tests– Deployment on LEIR, SPS, LHC TL– Dry runs - Commissioning– Scalability Tests– LHC Timing Crash Tests– RBAC tests
• Monitor and Diagnostics– LASER– DIAMON
• Injector Renovation• Summary
12 June 2008 3E. Hatziangeli AB/CO
LHC controls infrastructure – Overview• The 3-tier architecture
– Hardware Infrastructure– Software layers
– Resource Tier– VME crates, PC GW & PLC dealing
with high performance acquisitions and real-time processing
– Database where all the setting and configuration of all LHC device exist
– Server Tier– Application servers– Data Servers– File Servers– Central Timing
– Client Tier– Interactive Consoles– Fixed Displays– GUI applications
– Communication to the equipment goes through Controls MiddleWare CMW
CTRL CTRL
DB
Business Layer
Hardware
Client tier
Server tier
Applications Layer
Resource tier
CMW
12 June 2008 4E. Hatziangeli AB/CO
Outline
• LHC controls infrastructure – overview
• Status Report on Core Controls– Front ends Hardware and Software – Databases– Industrial Controls– Machine Interlocks– The LHC timing system
• Core Services and Applications– Post mortem– Sequencer for HWC– See next talk for Beam Sequencer– Logging– Software Interlock System– LSA (see next talk)
• Controls Security– Role Based Access– Management of Critical Settings– LHC Controls Security Panel
• Controls Infrastructure Tests– Deployment on LEIR, SPS, LHC TL– Dry runs - Commissioning– Scalability Tests– LHC Timing Crash Tests– RBAC tests
• Monitor and Diagnostics– LASER– DIAMON
• Injector Renovation• Summary
12 June 2008 5E. Hatziangeli AB/CO
Front-Ends Hardware and Software
• Hardware Installations– All Front-end controls equipment in place (> 200 VMEBus systems and > 250 industrial
PCs)– WorldFIP infrastructure operational for PO, QPS, Cryogenics and BI (400 km network,
20.000 nodes)– General Machine Timing (GMT) network operational, including transmissions for LHC
Collimators and for LHC Experiments
• Front End Software Architecture (FESA)– FESA V2.10 Framework operational, including support for machine critical settings,
transactional commands and in-depth diagnostics of RT behavior (via Alarms system LASER)– Front-End FESA classes developed by AB equipment groups (> 250 classes deployed on >
400 front-ends)– Deployment process =>AB-CO supports 3 last FESA releases– All industrial PCs running now Linux O/S
• On-going Actions– Two major tendering exercise for the procurement of AB front-end hardware
(adjudication during CERN FC in September 2008)
12 June 2008 E. Hatziangeli AB/CO 6
Accelerator Databases Readiness
Off-line DatabasesLayout• Racks & electronics incorporated
up to a high level of detail• Layout data is now used as
foundation for the controls system
Still to do• More data is being captured
relating layout and assets information
• Tools for data maintenance still to be put in place
Online DatabasesOperational Settings• Data model enhanced to cover
functional extensions for Role Based Access (RBAC) , XPOC, Sequencer
• PS Controls Renovation requirementsLogging Service• New database hosting since Mar. 08• Common logging infrastructure for
the complete accelerator chain• Sustained increasing logging
requirements for HWC& beam data• Improved data retrieval tool
12 June 2008 E. Hatziangeli AB/CO 7
12 June 2008
Service Availability and Data Security
Controls ConfigurationLSA SettingsE-LogbookCESAR
HWC MeasurementsMeasurements
Logging
CTRL CTRL
CTRL CTRL 2 x quad-core 2.8GHz CPU 8GB RAM
Clustered NAS shelf14x300GB SATA disks
11.4TB usable
Additional server for testing: Standby database for LSA
Clustered NAS shelf14x146GB FC disks
• Service Availability – New infrastructure has high-redundancy for high-availability– Deploy each service on a dedicated Oracle Real Application Cluster– The use of a standby database will be investigated
• objective of reaching 100% uptime for LSA
• Secure database account granting specific privileges to dedicated db accounts• DIAMON agent on Oracle Application Servers• For all CO databases
• CO puts the UR, and pays for the hardware• IT chooses the hardware, hosts, supports and maintains
8E. Hatziangeli AB/CO
Industrial Controls
• Industrial Controls for LHC have reached a high level of maturity • All systems, fully deployed for HWC in 2007, are presently in their operational
version– Machine protection (PIC, WIC, QPS, Circuits)– Collimator Environment Monitoring Package (temperature, water cooling)– Survey– Cryogenic controls– Cryogenics Instrumentation Expert Tools (CIET)
• Most of the SCADA applications have been ported to Linux• The front-end FESA software has been ported to Linux• Migration to last version of FESA (v2.10) to be done for next shutdown• The interface toward logging database has been consolidated• DIAMON is used for diagnostics
– PLC agents are available, tested and ready to be deployed– PVSS diagnostics will be soon available
12 June 2008 E. Hatziangeli AB/CO 9
RM78Sector 78 (3.3 Km)
Cryogenics Control System
10
LHCA
QURA
LHCCA
QURCA
QSCCA
LHCCB
QSCCB
LHCB
QSRB
QSCB
QUI
QSAA
Comp 4.5K Comp 1.8KMain DryerComp 1.8K Comp 4.5K
QURCB
Cold Box 4.5K
LN2 Buffer
CB 1.8KCB 1.8K
Connection Box
UCB 4.5K
QSRA
QSKA
QSCA
QSAB
Main Dryer
RM81
Alc
oves
Sector 81 (3.3 Km)
Tu
nn
elC
aver
nS
urf
ace
Shaft
QSDNRM
PAProfibus DP
WorldFIP
Return Module S78 & S81
12 June 2008 E. Hatziangeli AB/CO
Local & CentralControl Rooms
SCADA Data Servers
• The operation of cryogenics sectors has revealed a high risk dependency of the cryo control system on the reliability of the Technical Network
• Steps taken to reduce the dependencies– PLC architecture was rationalized no dependency on Ethernet of
the cryogenics control loops for production equipments– Architecture of the network components was optimized minimum
dependency on communications equipment (switches)– Powering of network component was checked homogenization
where possible with the cryo powering
• Work ongoing– Identify the weak network components and improve (fiber–copper)– Consolidate the restart of communication after a network failure– Ensure interventions on Technical Network (hardware & software) are
carefully planned and agreed with OperationE. Hatziangeli AB/CO 11
Cryogenic Controls Reliability
12 June 2008
12
Machine Interlocks
Powering Interlock System(PLC based)
Beam Interlock System(VME based)
Warm Magnet Interlock System(PLC based)
for Protecting Supra-ConductingMagnets
and Normal Conducting Magnets
for Protecting the Equipments
for Beam Operation
+
Safe Machine Parameters
system(VME based)
12 June 2008 E. Hatziangeli AB/CO
Fast Magnet current Change Monitors (FMCM)
Powering & Warm Magnets Interlocks
Powering Interlock Controllers• 36 units of PLC based system
protecting ~800 LHC electrical circuits• monitored via PVSS Supervision Operational and daily used during
HWC
13
Warm magnet Interlock Controllers• 8 units of PLC based system protecting
~150 LHC normal conducting magnets• monitored via PVSS Supervision Operational and daily used during HWC
12 June 2008 E. Hatziangeli AB/CO
14
Beam Interlock System
BIS will be ready for the machine checkout…
Individual System Tests successfully performed
Beam Interlock Controllers19 VME systems and~200 connections with most of the LHC systems
on going BIS Commissioning (involving all User systems)- done in // with HWC
- 3/8 points already performed
Monitored by Operational Application
12 June 2008 E. Hatziangeli AB/CO
(TT40 incident in 2004)
~110 cmVacuum chamber cut (outside view)
(inside view)
Ejected material opposite cut(inside view)
No marks or damageon magnet flanges
Beam
E. Hatziangeli AB/CO12 June 2008 15
Fast Magnet current Change Monitors - FMCM
• Successful collaboration with DESY– DESYdevelopment + CERN adaptation
• First units successfully used during the SPS Extraction tests and CNGS runs in 2007– currently being re-commissioned for 2008 runs
• Installation and commissioning in progress– 12 monitors deployed in the LHC (+ 14 in Transfer Lines), including ALL septa families– LHC installations to be completed next month (12 devices) 1st version of FESA class and Java supervision available since June 2007
• minor consolidation work in progress
E. Hatziangeli AB/CO16
FMCM trigger 0.1% drop !
time (ms)
I (A)
10 ms
FMCM triggers @ 3984.4 <103
PC current
time (ms)
I (A)
500 ms
View of FMCM board 12 June 2008
Timing System major components
• The LHC central timing– Master, Slave, Gateway using reflective memory, and
hot standby switch• The LHC Injector chain timing (CBCM)
– Master, Slave and Gateway using reflective memory, and hot standby switch
• Timing is distributed over dedicated network to timing receivers CTRx in front ends
• LHC and SPS safe machine parameter distribution
12 June 2008 E. Hatziangeli AB/CO 17
Safe Machine Parameters
• The SPS and LHC safe beam flags and beam energy are distributed on the LHC timing network – Work needs to be done for the final system to be ready
• The CTR timing receiver modules are able to distribute the beam energy and Safe Beam flags without any software to ensures higher reliability
• All timing receivers are monitored by DIAMON– Powerful diagnostics for 1000+ receivers
12 June 2008 18E. Hatziangeli AB/CO
Outline
• LHC controls infrastructure – overview
• Status Report on Core Controls– Front ends Hardware and Software – Databases– Industrial Controls– Machine Interlocks– The LHC timing system
• Core Services and Applications– Post mortem– Sequencer for HWC– See next talk for Beam Sequencer– Logging– Software Interlock System– LSA (see next talk)
• Controls Security– Role Based Access– Management of Critical Settings– LHC Controls Security Panel
• Controls Infrastructure Tests– Deployment on LEIR, SPS, LHC TL– Dry runs - Commissioning– Scalability Tests– LHC Timing Crash Tests– RBAC tests
• Monitor and Diagnostics– LASER– DIAMON
• Injector Renovation• Summary
12 June 2008 19E. Hatziangeli AB/CO
Post Mortem - Towards Beam Commissioning
… …
Data completeness and consistencycheck at system and global level (minimum data, configurable)
Upon beam dump / self triggering, systems start pushing data to PM system, Logging, Alarms, etc…
Individual System Analysis & Checks
I/XPOCIPOC-BISEvent Sequence
Circuit events
BLM, BPM > threshold
Global PM Analysis:Global Event sequence, summaries, advised actions, event DB,…
BLM BPM FGC QPS PIC/WIC BIS XPOCFMCM
Global event sequence Advised ActionsMachine Protection OK
• Validation of machine protection features • Pre-analysis of PM buffers into result files• Flagging of interesting systems/data reduction • Database catalogue
12 June 2008 20E. Hatziangeli AB/CO
Post Mortem Readiness
• Many tools are ready for HWC and tested on sectors 5-6 and 7-8• Implemented since December 2007
– Automatic Test Analysis on three applications (expert override possible)– Calculated result parameters sent to Sequencer for MTF upload.– Well defined GUI for each test step.– Test results electronically signed by role using RBAC– Event recognition with Event Builder– Redundant services for PM collection and data– Scalability tests with first beam clients started (BLM, BPM)
• To do for 2008– Parallel sector commissioning still to be tested– For the 600A circuits many steps are still to be automated.– Further validation tests with beam clients to be done (BLM, BPM, RF, etc…)– Extend framework from HWC to beam operation – Implement higher level of Automated Test Analysis
• Data completeness checks & Individual system tests
12 June 2008 21E. Hatziangeli AB/CO
Readiness of HWC sequencer
• First version of the sequencer deployed in early 2007– Many new versions with improvements deployed since
• HWC Sector 7-8 May-Jul 07 4-5 Winter 08, 5-6Spring 08
– ~ 35 sequences written and maintained by 3 HWC experts– Sector 4-5: over 1700 sequences executed, in 5-6 over 600– Essential tool for HWC
• Overall it works well and satisfies the requirements– Sequencer (the tool) is complete, no important new features needed – Sequences (the tests) are maintained by HWC experts
• Ready for multi-sector / multi-front HWC– Used in multi-front operations for over a year– Recent experience in multi-sector operations
• “normal” HWC is done in sector 78 • training quenches are done in sector 56
– No scalability issues are anticipated
E. Hatziangeli AB/CO 2212 June 2008
Logging Service Readiness
• Logging for Operation– Data logged from PS Complex, SPS, CNGS, LHC HWC, LHC , any type of
equipment– Processes run continuously on dedicated machines – Monitored through Alarms system LASER & DIAMON & diagnostic
application• Logging for equipment commissioning
– Dedicated service, running in the environment of the specialist– Aim: validation of the equipment behavior before operational
deployment– No interference with Operational logging
• Requirement for a watchdog system (coming weeks) – For critical data (INB, CNGS neutrino events, ...) continuous monitoring
of data logged in DB, generation of a specific alarm
12 June 2008 E. Hatziangeli AB/CO 23
Software Interlock System - SIS Overview
• Very useful system to anticipate failures and gives early alarms
• Accommodates complex interlock logic• Complements BIS (hardware) as protection
system• Proved to be reliable tool for operations • Excellent experience in SPS (900 parameters
monitored)
12 June 2008 E. Hatziangeli AB/CO 24
SIS for LHC
• Gives 2 Permits for Injection BICs(Beam1 & Beam2)– All PCs not HW interlocked (~ 800, orbit correctors, warm magnets)– Current of separation dipoles and MCBX orbit correctors– Ring & injection screens (only IN when mode inject-dump)– Extraction screens– Circulating beam intensity limit
• Gives Permit for the LHC ring (dumps the beam - initially alarms)– Integrated field of orbit correctors (beam dump energy tracking)– Extraction screens combined with intensity + energy– Orbit at TCDQ
• Future work – RBAC integration – Critical settings monitoring (MCS) from LSA– Refinement of the configuration as we progress with LHC
12 June 2008 25E. Hatziangeli AB/CO
Outline
• LHC controls infrastructure – overview
• Status Report on Core Controls– Front ends Hardware and Software – Databases– Industrial Controls– Machine Interlocks– The LHC timing system
• Core Services and Applications– Post mortem– Sequencer for HWC– See next talk for Beam Sequencer– Logging– Software Interlock System– LSA (see next talk)
• Controls Security– Role Based Access– Management of Critical Settings– LHC Controls Security Panel
• Controls Infrastructure Tests– Deployment on LEIR, SPS, LHC TL– Dry runs - Commissioning– Scalability Tests– LHC Timing Crash Tests– RBAC tests
• Monitor and Diagnostics– LASER– DIAMON
• Injector Renovation• Summary
12 June 2008 26E. Hatziangeli AB/CO
Role Based Access (RBAC) Overview
Application RBAC
RBAC Token:
• Application name
• User name
• IP address/location
• Time of authentication
• Time of expiry
• Roles[ ]
• Digital signature (RBA private key)
CMW client
FESA
CMW serverAccess MAP
T
T
T
Application Server
Configuration DB
Authentication:– User requests to be authenticated – RBAC authenticates user via NICE user
name and password– RBA returns Tokento Application
Authorization:– Application sends token to Application
Server (3-tier env.) – CMW client sends token to CMW server– CMW server (on front-end) verifies token– CMW server checks AccessMapfor role,
location, application, mode
12 June 2008 E. Hatziangeli AB/CO 27
Need to prevent– Well meaning person from doing the wrong
thing at the wrong moment– Ignorant person from doing anything at any
moment
Management of Critical Settings - MCS
Need to ensure• Critical parameters, which can compromise the safety of the
machine– can only be changed by an authorized person and nobody else– are what they are supposed to be
• MCS ensures – Critical parameters are only changed by authorized person
• RBAC for Authentication & Authorization
– It signs the data with a unique signature to ensure critical parameters have not changed since the authorized person has updated it
• Public-private key digital signatures12 June 2008 E. Hatziangeli AB/CO 28
LHC Controls Security Panel - LCSP
• The LHC Controls Security Panel is mandated to address all the technical and non-technical issues concerning AB security for Controls– Take responsibility for the RBAC data (ROLES and
RULES)• Ensure all critical parts of the machine are protected
– Take responsibility for the CNIC actions• reduction of Trusted list, change of operational account
passwords,..
CNIC: Computing and Network Infrastructure for Controls
12 June 2008 29E. Hatziangeli AB/CO
Outline
• LHC controls infrastructure – overview
• Status Report on Core Controls– Front ends Hardware and Software – Databases– Industrial Controls– Machine Interlocks– The LHC timing system
• Core Services and Applications– Post mortem– Sequencer for HWC– See next talk for Beam Sequencer– Logging– Software Interlock System– LSA (see next talk)
• Controls Security– Role Based Access– Management of Critical Settings– LHC Controls Security Panel
• Controls Infrastructure Tests– Deployment on LEIR, SPS, LHC TL– Dry runs - Commissioning– Scalability Tests– LHC Timing Crash Tests– RBAC tests
• Monitor and Diagnostics– LASER– DIAMON
• Injector Renovation• Summary
12 June 2008 30E. Hatziangeli AB/CO
See next talk
LHC controls infrastructure Scalability• Tests =>Preliminary results, issues & foreseen solutions• Systems which scale to LHC full load
– Software Interlock System SIS– Data Concentrators (BLMs, BPMs)– Alarm system LASER (new architecture) – Controls Middle Ware (CMW) /Java API Parameter Control (JAPC)– Diagnostic & Monitoring tool DIAMON
• Systems potentially critical (tests ongoing- results mid June) – Post Mortem– Logging service
• Scalable to LHC load from all clients except LHC BLM• Preliminary limit : ~ 5000 parameters/second• Bottleneck : SQL calls management by Oracle Server
12 June 2008 E. Hatziangeli AB/CO 31
Failures in Central Timing
• Tests have been performed to validate the behaviour of the Controls Infrastructure when the Central Timing crashes
• These “crash” timing tests are on going• Results
– The behaviour of the control system with no timing is correct
– The application programs, servers and front ends recovered without manual intervention when timing returns
12 June 2008 32E. Hatziangeli AB/CO
RBAC Dry Runs
• The LHC Controls Security Panel (LCSP) is preparing an RBAC dry-run end June/early July
• The RBAC default behavior is changed to– “Access with no RBAC token is refused”– Property not protected is not authorized
• All Equipment servers will be loaded with RBAC access maps• Typical applications will be tested
– LHC 2-tier & 3-tier applications– LHC Core controls (LSA)– Background servers, concentrators– Fixed Displays
12 June 2008 E. Hatziangeli AB/CO 33
Outline
• LHC controls infrastructure – overview
• Status Report on Core Controls– Front ends Hardware and Software – Databases– Industrial Controls– Machine Interlocks– The LHC timing system
• Core Services and Applications– Post mortem– Sequencer for HWC– See next talk for Beam Sequencer– Logging– Software Interlock System– LSA (see next talk)
• Controls Security– Role Based Access– Management of Critical Settings– LHC Controls Security Panel
• Controls Infrastructure Tests– Deployment on LEIR, SPS, LHC TL– Dry runs - Commissioning– Scalability Tests– LHC Timing Crash Tests– RBAC tests
• Monitor and Diagnostics– LASER– DIAMON
• Injector Renovation• Summary
12 June 2008 34E. Hatziangeli AB/CO
Alarms (LASER) for LHC
An important increase in expected alarm events Required availability 365 days/24h
12 June 2008 E. Hatziangeli AB/CO 35
Alarm console extended Allows for dynamic grouping of
alarms New alarm definition database
schema Ensures the data quality by
reducing redundancy and protecting against incomplete data
Alarm server modified fundamentally to allow
Fast response to increase in load Increased resilience to external
failures and improved diagnostics tools
LASER console
LASER CORE
LASER source
LASER source
LASER source
LASER DB
DIAgnostic & MONitoring System - DIAMON
• DIAMON provides– Software infrastructure for monitoring the AB Controls
Infrastructure
12 June 2008 E. Hatziangeli AB/CO 36
– Easy to use first line diagnostics and tool to solve problems or help to decide about responsibilities for first line intervention
Navigation Tree
Group View
Monitoring Tests Details Repair tools
Outline
• LHC controls infrastructure – overview
• Status Report on Core Controls– Front ends Hardware and Software – Databases– Industrial Controls– Machine Interlocks– The LHC timing system
• Core Services and Applications– Post mortem– Sequencer for HWC– See next talk for Beam Sequencer– Logging– Software Interlock System– LSA (see next talk)
• Controls Security– Role Based Access– Management of Critical Settings– LHC Controls Security Panel
• Controls Infrastructure Tests– Deployment on LEIR, SPS, LHC TL– Dry runs - Commissioning– Scalability Tests– LHC Timing Crash Tests– RBAC tests
• Monitor and Diagnostics– LASER– DIAMON
• Injector Renovation• Summary
12 June 2008 37E. Hatziangeli AB/CO
Injector Controls Renovation - Status Report
Injector Controls Architecture - InCA• Architecture validation with critical Use Cases• Check interfacing of the various components
– LSA core– Standard CO components for Acquisition– Standard PS and LSA Applications interfaced to the core
• Check data flow– Low-level trim and monitoring values of correctors– Orbit correction using LHC Beam steering application– High-level trim + drive a front end
• Results– Whole data flow validated– Architecture closer to the final one
Injector Complex FE Renovation – 2nd half of 2008• A "strategic" plan for the renovation of the FE controls infrastructure is
due by mid-2008 • Development and validation of new Front-end solutions in view of their
first deployment in 200912 June 2008 38E. Hatziangeli AB/CO
Summary
• The LHC controls infrastructure had been targeted for readiness for an engineering run at 450 GeV in November 2007 - This goal has been met.
• The ongoing hardware commissioning and the extensive use of programs and databases (“learn by doing”) have significantly changed the specifications and the resulting follow-up and work has been done.
• Additional functionality has been prepared in 2008- network security (RBAC)- diagnostic tools (DIAMON)
12 June 2008 39E. Hatziangeli AB/CO
End