Contract and Vendor Management Stacia Hayes MBA, CHSP Environment of Care Program Manager Swedish Medical Center

Contract and Vendor Management Stacia Hayes MBA, CHSP Environment of Care Program Manager Swedish Medical Center

Embed Size (px)

Citation preview

Page 1: Contract and Vendor Management Stacia Hayes MBA, CHSP Environment of Care Program Manager Swedish Medical Center

Contractand

Vendor Management

Stacia Hayes MBA, CHSPEnvironment of Care

Program ManagerSwedish Medical Center

Page 2: Contract and Vendor Management Stacia Hayes MBA, CHSP Environment of Care Program Manager Swedish Medical Center

Why we care who is working in our hospitals

Page 3: Contract and Vendor Management Stacia Hayes MBA, CHSP Environment of Care Program Manager Swedish Medical Center

Urethane Floor Work

Page 4: Contract and Vendor Management Stacia Hayes MBA, CHSP Environment of Care Program Manager Swedish Medical Center

Background Swedish made the switch to a urethane wax product.

Lasts longer than traditional waxing Done by a contracted company Usually night shift

Several years ago a staff member had a reaction and was hospitalized in the ICU due to preexisting conditions that were possibly exacerbated by exposure.

Could not test employee to see what caused reaction because she was so sensitive.

Decision made to notify staff via email where work would be done and round with staff member that was hospitalized to make sure she did not go into area. We would also put up plastic to contain smell.

Page 5: Contract and Vendor Management Stacia Hayes MBA, CHSP Environment of Care Program Manager Swedish Medical Center

Fast Forward…

Page 6: Contract and Vendor Management Stacia Hayes MBA, CHSP Environment of Care Program Manager Swedish Medical Center

Investigation Labor and Industries showed up for investigation Internal Investigation paralleled L&I Swedish did not have baseline data from Industrial

Hygienist on exposure level to urethane Contractor did work, but not in location of exposure Contractors contract had not been reviewed

internally and was out of date Contractor did not have a safety plan as required

by Law Contractor did not have appropriate PPE for

Employees

Page 7: Contract and Vendor Management Stacia Hayes MBA, CHSP Environment of Care Program Manager Swedish Medical Center

Investigation Cont… Contractor was using chemicals that had not

been approved by Swedish. No oversight by Swedish of Contractor while

at the hospital doing work. PPE Assessments for all job classifications

Page 8: Contract and Vendor Management Stacia Hayes MBA, CHSP Environment of Care Program Manager Swedish Medical Center

Closure… Decided to remove plastic from process due to

not allowing airflow Continue to notify staff where work will be done

Moving toward Paging Groups vs. email 3rd Party Industrial Hygienist hired to get

baseline Obtained lab results, still waiting for report from

IH Urethane work re-started in January of 2013 March of 2013 Contractor’s contract terminated

due to disregarding PCRA in Sterile Processing which could have caused patient harm.

Page 9: Contract and Vendor Management Stacia Hayes MBA, CHSP Environment of Care Program Manager Swedish Medical Center

Window Washers South West Tower Window washing during day shift right above

the loading dock Near miss

Page 10: Contract and Vendor Management Stacia Hayes MBA, CHSP Environment of Care Program Manager Swedish Medical Center

Pictures of the scene…

Page 11: Contract and Vendor Management Stacia Hayes MBA, CHSP Environment of Care Program Manager Swedish Medical Center

Follow-Up Contract was up to date. Contractor had an active safety plan. Required Contractor to leave direct cell phone

for emergency contact with Dispatch. Contractor followed up with education with

their staff. Window work on this side of the tower is now

scheduled during second shift or on the weekends.

Page 12: Contract and Vendor Management Stacia Hayes MBA, CHSP Environment of Care Program Manager Swedish Medical Center

Questions?