    Abdalla ElDaoushy, Institute of National Planning, Cairo, EGYPT

    2

    TrackExpedition Software & Business Needs

    Submittal Reviews

    and determine the impact on theSchedule.

    Manage Design-Changes and distribute Contract-Drawings-Revisions to Contractors.

    Review Change-Orders for financial and technical impact(Cost & Time Impact) and make recommendations to theClient.

    Forecast Project Budget (due to different changes).

    Communicate up to date Project Details to the Clients.

    It is a complete Company Solution based on the concept thatthe Data Stream from the

    Expedition Software

    Field Personnel on the Site to theTop Executive in the Office

    is linked together to form avalidated, comprehensive picture of the Project.

    o Expedition accelerates the Review Process.o It keeps everyone informed.o It gets the Answers you need.o It simplifies your Project Schedule.o Expedition enables sending documents from the Job

    Site to the Home Office and vice-versa.o Expedition enables to share information with all

    Participants.o Received Documents are added to the Project

    Database --- reduces data entry.o E-mail Queue sends multiple documents all at once.o Uses current e-mail system.

  • 8/9/2019 Cont Admin Overview

    3/34

    Abdalla ElDaoushy, Institute of National Planning, Cairo, EGYPT

    3

    o Creating or using predefinedManaging Project Costs: Cost Codes & Titleso Creating Cost Worksheet grouped by CSI

    (Construction Specification Institute) Division or

    Category (see later).

    .

    o Types of Cost Documents: CO: Change Order CON: Contract COR: Change Order Request EST: Estimate INV: Invoice PO: Purchase Order PCO: Proposed Change Order RQS: Requisition . . .

    Communicationo Save Time. :o Get the look that you want.o Show Project Status.

    Key Benefitso Improve Project Information Flow.:o Provide one Central Location for Project Data.o Reduce Errors.o Controls and Manages Work Flow.

    How Do You Benefito

    Same Page, Same Time.

    ?

    Everyone can see different views of the samedata.

    Consistent data regardless of how it is entered. Data is viewed by the tool each person is

    comfortable using.

  • 8/9/2019 Cont Admin Overview

    4/34

    Abdalla ElDaoushy, Institute of National Planning, Cairo, EGYPT

    4

    Project Documents & Budget Control

    Two Essential Components

    1.

    :

    Track Submittals

    o Reviews and Approvals.o Ensures Materials are perfectly to Specifications.

    2.Control Changes

    a. From Initial Cost Estimate through Approval.b.Identifies impact on Project Costs and Project

    Schedule (Time).

    Hint:

    Contract Changes & Submittals are the two keyelements that can slow down progressConstruction Project.

    of a

  • 8/9/2019 Cont Admin Overview

    5/34

    Abdalla ElDaoushy, Institute of National Planning, Cairo, EGYPT

    5

  • 8/9/2019 Cont Admin Overview

    6/34

    Abdalla ElDaoushy, Institute of National Planning, Cairo, EGYPT

    6

    Definitions:

    The Contract Documents could be classified into four

    1.Main Documents (Contracts & Purchase Orders)

    major types

    as follows:

    2.Cost Documents

    3.Change Documents

    4.Other Documents

  • 8/9/2019 Cont Admin Overview

    7/34

    Abdalla ElDaoushy, Institute of National Planning, Cairo, EGYPT

    7

    1.Main Documents

    1.1 Contract

    A Contract

    is a written agreement between two parties inwhich one party agrees to perform specified work for anotherparty for a certain price.

    The Contract usually involves Labor only or Labor &Materials.

    It includes a Description of the work to be performed. A Contract usually includes a list of the Special Terms

    and/or Conditions that apply to the Contract.

    It also lists the Start & Finish Dates along with a NegotiatedPrice.

    oThe Negotiated Price can be Lump Sum and/or UnitPrice.

    Expedition gives you the complete up to date ContractStatus including Pending and Approval Changes.

  • 8/9/2019 Cont Admin Overview

    8/34

    Abdalla ElDaoushy, Institute of National Planning, Cairo, EGYPT

    8

    Printed Prime Contract:

  • 8/9/2019 Cont Admin Overview

    9/34

    Abdalla ElDaoushy, Institute of National Planning, Cairo, EGYPT

    9

    Printed SubContract:

  • 8/9/2019 Cont Admin Overview

    10/34

  • 8/9/2019 Cont Admin Overview

    11/34

    Abdalla ElDaoushy, Institute of National Planning, Cairo, EGYPT

    11

    Printed Purchase Order:

  • 8/9/2019 Cont Admin Overview

    12/34

    Abdalla ElDaoushy, Institute of National Planning, Cairo, EGYPT

    12

    2 Project Cost Management

    2.1 Cost Codes & Cost Worksheet

    A Central Location where we can distribute and monitor ourProject Budgeted, Committed, Funding, and Actual Costs.

    Use Cost Codes to break down costs in the CostWorksheet. For example, you may have a Contract of LumpSum $50,000.00 for which $25,000.00 is assigned for RoughCarpentry and $25,000.00 is assigned for Finish Carpentry

    To track each Carpentrys Cost separately in the CostWorksheet, create 2 Cost Codes (Rough & Finish forexample) and assign $25,000.00 to each of them.

    .

    Some Companies base their Cost Codes on the Standard CSI(Construction Specification Institute) Codes.

    The more meaningful you make the Cost Codes; the easier it isto analyze Cost Details.

  • 8/9/2019 Cont Admin Overview

    13/34

    Abdalla ElDaoushy, Institute of National Planning, Cairo, EGYPT

    13

    Example ofDistributing the Budget of the Project in the CostWorksheet using the Cost Codes

    :

    Cost Code(created)

    Title Value

    01 01040 OH Coordinate Construction $250,000

    01 01300 VN Scheduling Software $7,000

    02 02100 SC Excavation $50,000

    02 02200 SC Earthwork andLandscaping

    $160,000

    02 02500 SC Paving $70,000

    02 02700 VN Utilities Earthwork andPiping

    $20,000

    03 03400 VN Pre-cast Concrete $300,000

    16 16100 SC Electrical System $113,000

    16 16785 SC Security System $30,000

    Total $1,000,000

    2.2U

    InvoicesU

    It is a document for recording billing informationfor contracts and purchase order.

    2.3U

    Request for Payment (Requisition)U

    A request for payment Ufrom Uthe contractor UtoU theowner for a portion of work performed, validated byschedule of values for the work performed, ormaterials installed since the last payment.

  • 8/9/2019 Cont Admin Overview

    14/34

    Abdalla ElDaoushy, Institute of National Planning, Cairo, EGYPT

    14

    2.4 Cost Categories

    oBudgeted Costs represent the target or estimated costs foreach work item. It is usually contractually agreed uponand distributed to the Budget Section of the CostWorksheet.

    o UCommitted costsCosts associated with

    U

    SubcontractsU

    and/orU

    PurchaseUOrdersU, distributed to the UCommitted SectionU of theUCost WorksheetU.

    ( )

    o UActual CostIt is represented by the Requisition & Invoices received

    and issued

    o UFunding CostsTrack money from various services (City, State, andGovernment).

  • 8/9/2019 Cont Admin Overview

    15/34

    Abdalla ElDaoushy, Institute of National Planning, Cairo, EGYPT

    15

    Bud et

    Chan e

    Authorized

    Funding

    (Requisitions)

    Cost Worksheet

    Budget Committed Actual

    Contracts

    Chan es Purchase

    Orders

    Changes

    Invoices

    Payment

    Requests

    (Requisitions)

  • 8/9/2019 Cont Admin Overview

    16/34

    Abdalla ElDaoushy, Institute of National Planning, Cairo, EGYPT

    16

    You can distribute Contracts (or PO) Costs to the Budgeted,Committed, or Funding Section of the Cost Worksheet

    asfollows:

    o Use the Budgeted Section

    for the total amountavailable to spend on the Project (usually betweenthe Owner & the General Contractor).

    o Use the Committed Section

    for amounts you haveagreed to pay someone else (usually between theGeneral Contractor & the SubContractors).

    o Use the Funding Section

    to cost out a Contractfunded by more than one resource.

  • 8/9/2019 Cont Admin Overview

    17/34

    Abdalla ElDaoushy, Institute of National Planning, Cairo, EGYPT

    17

    oThe amount of the contract contained when theproject started.

    Original Amount

    oThe amount due to a change in progress forwhich documents exist and approved.

    Approved Amount

    oDue to a change in progress for whichdocuments exist but are not approved.

    Pending amount

  • 8/9/2019 Cont Admin Overview

    18/34

    Abdalla ElDaoushy, Institute of National Planning, Cairo, EGYPT

    18

    3 1BUChange ManagementU:

    U

    Tracking Contract Change Documents

    After Project Parties accept a Contract or Purchase Orderand work begins, any

    U

    changesU

    resulting from changedspecifications, scope of work, site conditions, orprojectscheduleaffect the initial contract costs.

    The process of formally changing a contract requires severalsteps, each of which should be fully documented.

    U

    Expedition helps you to identify changes from initiationthrough resolution and compresses the time frame for theapproval process.

    U

    Projects Change Process

    o UChange in condition (CIC)A Uchange documentU to notify someone of anunexpected change. (usually from SubContractor toGeneral Contractor).

    oU

    Request for Information (RFI) (Contractinformation)

    A URequest for a change document U that asks for

    information or clarification on some aspects (parts)of a project.

    o UAnswer (ANS)A URequest change documentU to respond to a Requestfor Information (RFI).

  • 8/9/2019 Cont Admin Overview

    19/34

    Abdalla ElDaoushy, Institute of National Planning, Cairo, EGYPT

    19

    o Request for Proposal (RFP)A Proposal Change Document that asks a

    SubContractor to provide an estimate ofrequirements to complete a change.

    (Contract

    information)

    o Proposed Change Order (PCO)A Proposal Change Document that outlines aSubcontractor's price estimate of the cost tocomplete a proposed change.

    (Contract

    information)

    o Change Order Request (COR)A Request Change Document to request action on arecognized problem.

    (Contract

    information)

    oChange Order (CO)A Change Document to specify a redirection in plansor new work items, as well as any

    (Contract information)

    approved cost andeffort.

  • 8/9/2019 Cont Admin Overview

    20/34

    Abdalla ElDaoushy, Institute of National Planning, Cairo, EGYPT

    20

    CIC

    RFI

    ANS

    RFP

    PCO

    COR

    CO

    CO

    Subcontractor

    Subcontractor

    Contractor

    Contractor

    Contractor

    Contractor

    Owner

    Design Professional

    Subcontractor

  • 8/9/2019 Cont Admin Overview

    21/34

    Abdalla ElDaoushy, Institute of National Planning, Cairo, EGYPT

    21

    Documenting the Change Process

    Page 25 ppts Anas Wahdan

    CIC or RFI

    REP or ANS

    COR or PCOCost WorksheetPending Revision

    COCost WorksheetApproved Revision

    Add

    Generate

    Generate

    Distribute

    Cost

    Collect Cost fromCORs or PCOs

    Approved CO

    CostAutomaticallyTransferred

    Add

  • 8/9/2019 Cont Admin Overview

    22/34

    Abdalla ElDaoushy, Institute of National Planning, Cairo, EGYPT

    22

    4 Other Documents

    o Punch List

    A list of items that must be completed before theproject can be finished.

    oU

    SubmittalU

    (Logs)

    A Document that tracks items which must beU

    reviewed and approvedU

    before they can be used in aproject.

    :

    o UTransmittalU(Communication)A memo or cover letter that accompanies projectdocuments or items such as material samples.

    Transmittals accompany items to indicate what,when , and why they were forwarded

    o UDunning letterU(Communication)A letter to remind project participants to deliverspecific items or perform certain tasks.

    o UCost CodesCodes used in the Cost Worksheet to classifydifferent types of work associated with a project.Once a project is underway, you can compareUbudgetedU, Ucommitted U, UfundingU, and UactualU costs foreach cost code.

  • 8/9/2019 Cont Admin Overview

    23/34

    Abdalla ElDaoushy, Institute of National Planning, Cairo, EGYPT

    23

    o(Logs)A term used to identify the company & person

    responsible for an action item.

    Ball in Court (BIC)

    oCompanies & Contacts (Project Participants

    This Module identifies each Player or Party to theContract. Use Contacts to track address, role, andphone identification.

    )

    o Issues (Project Participants)A "folder" that groups different documents relatedto a similar topic so you can access them in one placeinstead of searching for them across differentmodules.

    Issues can include a wide range of project concerns,such as problems that must be resolved before a jobis completed, or conditions that can lead to changesor claims. Organizing project information by issueenables you to quickly review each problem thatmay affect the project schedule or costs atcompletion.

  • 8/9/2019 Cont Admin Overview

    24/34

    Abdalla ElDaoushy, Institute of National Planning, Cairo, EGYPT

    24

    Contracts & Engineering Drawings (Logs)

    The Drawing Log ensures that everyone is building using thelatest Drawings and Specifications.

    Expedition helps you to use the Drawings Log to manageyour Drawings, keep on top of the latest revision, and ensurethe distribution to all ProjectParticipants.

    Tracking Contract Drawingso Compress the Drawing Approval Cycle.o Maintain an accurate history of revisionso Create and maintain Distribution Lists

    Identify Copies Sent and Paper Size

    For each Contact who will be receiving andreviewing Drawings, you can enter thepaper size and the number of copies for eachindividual.

    o Relate Drawing Changes to Financial Changeso Create Transmittals for each Drawing Set sent for

    review or distribution

  • 8/9/2019 Cont Admin Overview

    25/34

    Abdalla ElDaoushy, Institute of National Planning, Cairo, EGYPT

    25

    Steps for Managing Drawings1.Establish Drawings Sets

    a. Drawings are usually contained in Sets foe easierdistribution, review, and record keeping. Typically,sets correspond to Phases such as Schematic,Issued for Bid, and Issued for Construction.

    b. Categorize Standard Drawing Disciplines(AllProjects/Dictionaries/Drawings/Disciplines)

    i. For example: Civil, Mechanical, Electrical,Structural, . . . etc

    2. Define Distribution Lists (Define/Distribution List)Create Distribution Lists for Project Participantsinvolved in the Transmittal, Submittal, or ContractDrawing Processes

    3.Create Multiple Drawings for each Discipline

    4.Log Issued Drawings revisions

    5.Package a group of Drawings as a Set of Drawingsa. Drawings are usually contained in Sets for easier

    distribution, review, and record keeping. Typically,Sets correspond to Phases such as Schematic,Issued for Bid, and Issued for Construction.

    b.When to Use?i. Log/Send revisions for:

    1.Changes or RFIs2.Drawings for a Design Phase

    6.Forward the Drawing Set for Review or Distribution

    7.Update Drawings by Reviewers

  • 8/9/2019 Cont Admin Overview

    26/34

    Abdalla ElDaoushy, Institute of National Planning, Cairo, EGYPT

    26

    Hint:

    Display from the Computer the Drawing Documents& Drawing Sets

  • 8/9/2019 Cont Admin Overview

    27/34

    Abdalla ElDaoushy, Institute of National Planning, Cairo, EGYPT

    27

    Linking Expedition to Primavera Schedule

    Expedition used an ODBC link to:o Create Data Dictionarieso Define link to Schedule Fileo View current Project Scheduleo Refresh information in Expedition using Update Tools

    Linking Submittal Schedule Dateso Use the Schedule tab to link activities defined in P3 or

    P3e to Submittals.

    o This determines when Submittals are required to beprepared and Approved (Required Start & RequiredFinish) before Construction Activities can begin.

    o Enter the Lead Time (duration) and allow Expeditionto calculate the Start & Finish Dates for:

    Delivery Time Fabrication Time

    Release to Manufacture Approved Period Submittal Preparation

    Hint:Show the above discussions on the Computer..

  • 8/9/2019 Cont Admin Overview

    28/34

    Abdalla ElDaoushy, Institute of National Planning, Cairo, EGYPT

    28

    Recording Project Events

    Expedition enables to record Project Events throughMeetings Minutes and Daily Reports beside PrintingDaily Reports& Meeting Minutes

    o Daily Reports (Logs)Expedition provides:

    Report of Daily Work Activities,

    Record Equipment used at the Site,Maintain Totals of Field-Force Labor,Keep a Daily Log of all Site Visitors,Track Materials Delivered to the Job Site,

  • 8/9/2019 Cont Admin Overview

    29/34

    Abdalla ElDaoushy, Institute of National Planning, Cairo, EGYPT

    29

    Printed Daily Report:

  • 8/9/2019 Cont Admin Overview

    30/34

    Abdalla ElDaoushy, Institute of National Planning, Cairo, EGYPT

    30

    o Phone Calls, Meeting, Correspondence, RFIs,and Notices (Communication)

    We can use these modules for recording

    information that may affect both the submittal andchange processes. For example, a change incondition may result in meetings, phone calls, andnotes, then letters and correspondence that lead to aformal contract change.

    o Change Orders and Proceed Orders (ContractInformation)

    Result from changes in the Scope of work, SiteConditions, or Schedule Delays. we can post costsassociated with these changes to the Cost Worksheetso we have a total financial picture of past eventsand projected future costs.

    o Tracking & Statusing Submittals (Logs)Submittals include Contract Drawings, SampleMaterials, etc that need Approval. The Submittalsmodule helps to ensure Contract Compliance bytracking who received what and when they receivedit.

  • 8/9/2019 Cont Admin Overview

    31/34

    Abdalla ElDaoushy, Institute of National Planning, Cairo, EGYPT

    31

    oSubmittal Flow

    Received Sent

    Transmittal

    CorrespondenceSent

    Returned Forwarded

    TransmittalDunning

    Letter

    Review/Approval

    If Days Held> Planned

  • 8/9/2019 Cont Admin Overview

    32/34

    Abdalla ElDaoushy, Institute of National Planning, Cairo, EGYPT

    32

    Printed Submittal:

  • 8/9/2019 Cont Admin Overview

    33/34

    Abdalla ElDaoushy, Institute of National Planning, Cairo, EGYPT

    33

    Printed Insurance Certificate:

  • 8/9/2019 Cont Admin Overview

    34/34

    Printed Punch List: