Media contact: Kerri Richardson 502.386.2421 [email protected] Construction Update for Omni Louisville Construction Milestones: The Omni Louisville Hotel is now more than two-thirds its total height! By the beginning of Derby week, the structure will be complete through floor 23. A signature feature of the Omni Louisville will be the glass exterior wall that faces 2 nd Street – that glass installation began this month and will continue through May. Interior finishes such as drywall, tiling and wood trim on guestroom floors are underway and the team is making great progress. Large pieces of the property’s laundry equipment have arrived and will be installed soon. The precast parking garage structure will be erected soon. The Omni Louisville Hotel's lower floors facing Second Street will be mostly glass, visually connecting to the city’s vibrant downtown.

Construction Update for Omni Louisville · 4/5/2017  · The Omni Louisville Hotel's lower floors facing Second Street will be mostly glass, visually connecting to the city’s vibrant

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Construction Update for Omni Louisville · 4/5/2017  · The Omni Louisville Hotel's lower floors facing Second Street will be mostly glass, visually connecting to the city’s vibrant

Media contact: Kerri Richardson 502.386.2421

[email protected]

Construction Update for Omni Louisville

Construction Milestones: The Omni Louisville Hotel is now more than two-thirds its total height! By the beginning of

Derby week, the structure will be complete through floor 23.

A signature feature of the Omni Louisville will be

the glass exterior wall that faces 2nd Street – that

glass installation began this month and will

continue through May.

Interior finishes such as drywall, tiling and wood

trim on guestroom floors are underway and the

team is making great progress.

Large pieces of the property’s laundry equipment

have arrived and will be installed soon.

The precast parking garage structure will be

erected soon.

The Omni Louisville Hotel's lower floors facing Second Street will be mostly glass, visually connecting to the city’s vibrant downtown.

Page 2: Construction Update for Omni Louisville · 4/5/2017  · The Omni Louisville Hotel's lower floors facing Second Street will be mostly glass, visually connecting to the city’s vibrant

Fast Facts: Omni Louisville Hotel has remaining group availability for Derby 2018! Groups of 10 or more

should book soon to ensure they’re staying at the newest destination Louisville has to offer.

About 300 workers are on the construction site each day. This includes concrete workers,

electricians, plumbers, mechanical workers, drywall framers and masons.

Follow Omni Louisville on Facebook and Twitter (@OmniLouisville) and Instagram (@OmniLou)

for more insider updates throughout construction!

Follow Eamon O’Brien, Omni Louisville’s director of sales and marketing, on Instagram

@EOBourbonCity.

The Omni Louisville Hotel is now more than two-thirds of its eventual height. Upon completion,

the hotel will rise 30 stories, making it the third-largest building in the downtown cityscape.