CONSTRUCTION SEQUENCE OF
PC OUTER WALL FULL CONTANMENT LNG STORAGE TANK
7/22/2019 Construction Sequence LNG Storage Tank
2/31
Legend
: Outline of the tank
: Part under construction
: Concrete part completed
: Mechanical part completed
: Insulation part completed
7/22/2019 Construction Sequence LNG Storage Tank
3/31
SOIL IMPROVEMENT OR PILING,
BLINDING CONCRETE
Soil improvement or piling
Blinding concrete for slab
Blinding concrete for staircase
7/22/2019 Construction Sequence LNG Storage Tank
4/31
CONSTRUCTION OF CONCRETE SLAB
AND STAIRCASE FOUNDATION
Concrete slabForm work
Slab heating conduit
Staircase foundation
7/22/2019 Construction Sequence LNG Storage Tank
5/31
PC OUTER WALL CONSTRUCTION,
ERECTION OF BOTTOM VAPOR BARRIER
1st lift of PC wall
Bottom vapor barrier
Form workStaircase Temporary opening
7/22/2019 Construction Sequence LNG Storage Tank
6/31
PC OUTER WALL CONSTRUCTION,
ERECTION OF BOTTOM VAPOR BARRIER
Staircase
2nd lift of PC wall
Form work
Bottom vapor barrier
7/22/2019 Construction Sequence LNG Storage Tank
7/31
PC OUTER WALL CONSTRUCTION,
PREPARATION FOR ROOF ASSEMBLY
Intermediate lift of PC wall
Staircase
Temporary support for roof assembly
Form work
7/22/2019 Construction Sequence LNG Storage Tank
8/31
PC OUTER WALL CONSTRUCTION,
ROOF ASSEMBLY
Intermediate lift of PC wall
Roof liner supporting frame
Form work
Staircase
7/22/2019 Construction Sequence LNG Storage Tank
9/31
PC OUTER WALL CONSTRUCTION,
ROOF AND SUSPENDED DECK ASSEMBLY
Intermediate lift of PC wall
Roof liner
Staircase
Suspended ceiling deck & hanger
Form work
7/22/2019 Construction Sequence LNG Storage Tank
10/31
PC OUTER TANK WALL CONSTRUCTION,
ASSEMBLY OF ROOF AND SUSPENDED DECK
Top lift of PC wall
Form work
Roof compression ring
PC wall top haunch
7/22/2019 Construction Sequence LNG Storage Tank
11/31
ASSEMBLY OF ROOF AND SUSPENEDED DECK,
PREPARATION FOR ROOF RAISING
Staircase
Temporary blower for roof air-raise
7/22/2019 Construction Sequence LNG Storage Tank
12/31
ROOF RAISING
Air pressure
Temporary blower for roof raise
7/22/2019 Construction Sequence LNG Storage Tank
13/31
WELD GUSSET BETWEEN ROOF AND COMPRESSION
RING, INSTALLATION OF ROOF PENETRATION
Roof liner support, liner and
suspended ceiling deck
Roof nozzle & manhole dome roof penetration
7/22/2019 Construction Sequence LNG Storage Tank
14/31
CONSTRUCTION OF ROOF CONCRETE
Temporary blower for roof
concrete construction
Air pressure
Roof concrete
7/22/2019 Construction Sequence LNG Storage Tank
15/31
CONSTRUCTION OF ROOF CONCRETE,
ERECTION OF WALL VAPOR BARRIER (LOWER)
AND BOTTOM INSULATION (LOWER)
Roof concrete
Wall vapor barrier (lower)
Bottom insulation (lower)
7/22/2019 Construction Sequence LNG Storage Tank
16/31
CONSTRUCTION OF PLATFORM AND
ERECTION OF BOTTOM LINER
Platform
Bottom liner
7/22/2019 Construction Sequence LNG Storage Tank
17/31
CONSTRUCTION OF PLATFORM, RING BEAM FOUNDATION
AND ERECTION OF ANNULAR PLATE
Platform
Ring beam foundation
Annular plate
7/22/2019 Construction Sequence LNG Storage Tank
18/31
ERECTION OF INNER BOTTOM, WALL VAPOR BARRIER,
CORNER PROTECTION, BOTTOM INSULATION, AND
INSULATION FOR CORNER PROTECTION
Bottom insulation (top)Inner bottom
Wall vapor barrier (upper)
Temporary opening
Insulation for corner protection
Corner protection wall
7/22/2019 Construction Sequence LNG Storage Tank
19/31
ERECTION OF INNER TANK WALL, INNER TANK BOTTOM,
WALL VAPOR BARRIER AND BOTTOM INSULATION
Automatic shell welding machine
Inner shell 1st & 2nd course
Bottom insulation (top)
Inner bottom
Wall vapor barrier (upper)
7/22/2019 Construction Sequence LNG Storage Tank
20/31
ERECTION OF INNER SHELL AND PIPING
Inner shell intermediate
Temporary opening
7/22/2019 Construction Sequence LNG Storage Tank
21/31
INSTALLATION OF PIPE SUPPORT, PLATFORM, HANDRAIL,
WALL VAPOR BARRIER, SUSPENDED DECK PENETRATION,
ERECTION OF INNER TANK WALL / GIRDER, AND PIPING
Inner shell upper
& top course
Dome space ladder & walkwaySuspended ceiling deck nozzle
& manhole penetration
Pipe support
Pipe rack or sleeper
Inner girder
7/22/2019 Construction Sequence LNG Storage Tank
22/31
INSTALLATION OF ESCAPE LADDER,
PLATFORM AND HANDRAIL, AND PIPING
Escape ladder
PRV / VRV / instrument platformPlatform & handrail
7/22/2019 Construction Sequence LNG Storage Tank
23/31
INSTALLATION OF PRV,VRV, INNER LADDER,
CRANE, HOIST, AND PIPING
Pump column
Inner ladder
PRV / VRV
Pump loading / offloading
crane or hoist
7/22/2019 Construction Sequence LNG Storage Tank
24/31
CLOSING TEMPORARY OPENING,
AND PIPING
Inner shell temporary
opening closure
PC wall temporary opening closure
Corner protection temporary
opening closure
7/22/2019 Construction Sequence LNG Storage Tank
25/31
HYDROTEST, PNEUMATIC TEST
AND PIPING
7/22/2019 Construction Sequence LNG Storage Tank
26/31
SHELL INSULATION - RESILIENT BLANKET,
PIPING INSULATION, AND PAINTING
Shell insulation -
Resilient blanket
7/22/2019 Construction Sequence LNG Storage Tank
27/31
ROOF INSULATION, ANNULAR SPACE INSULATION - PERLITE, AND
PIPING
Shell insulation - Perlite
Roof insulation
7/22/2019 Construction Sequence LNG Storage Tank
28/31
LNG PUMP INSTALLATION,
COMMISSIONING OF INSTRUMENT AND ELECTRICAL,
LNG pump
LNG pump
7/22/2019 Construction Sequence LNG Storage Tank
29/31
FINAL BOX-UP OF THE TANK,
DRYING AND N2 PURGING
Drying & N2 purging
equipment
7/22/2019 Construction Sequence LNG Storage Tank
30/31
COOLDOWN
7/22/2019 Construction Sequence LNG Storage Tank
31/31
START OPERATION