Construction Sequence LNG Storage Tank

Embed Size (px)

Citation preview

  • 7/22/2019 Construction Sequence LNG Storage Tank

    1/31

    CONSTRUCTION SEQUENCE OF

    PC OUTER WALL FULL CONTANMENT LNG STORAGE TANK

  • 7/22/2019 Construction Sequence LNG Storage Tank

    2/31

    Legend

    : Outline of the tank

    : Part under construction

    : Concrete part completed

    : Mechanical part completed

    : Insulation part completed

  • 7/22/2019 Construction Sequence LNG Storage Tank

    3/31

    SOIL IMPROVEMENT OR PILING,

    BLINDING CONCRETE

    Soil improvement or piling

    Blinding concrete for slab

    Blinding concrete for staircase

  • 7/22/2019 Construction Sequence LNG Storage Tank

    4/31

    CONSTRUCTION OF CONCRETE SLAB

    AND STAIRCASE FOUNDATION

    Concrete slabForm work

    Slab heating conduit

    Staircase foundation

  • 7/22/2019 Construction Sequence LNG Storage Tank

    5/31

    PC OUTER WALL CONSTRUCTION,

    ERECTION OF BOTTOM VAPOR BARRIER

    1st lift of PC wall

    Bottom vapor barrier

    Form workStaircase Temporary opening

  • 7/22/2019 Construction Sequence LNG Storage Tank

    6/31

    PC OUTER WALL CONSTRUCTION,

    ERECTION OF BOTTOM VAPOR BARRIER

    Staircase

    2nd lift of PC wall

    Form work

    Bottom vapor barrier

  • 7/22/2019 Construction Sequence LNG Storage Tank

    7/31

    PC OUTER WALL CONSTRUCTION,

    PREPARATION FOR ROOF ASSEMBLY

    Intermediate lift of PC wall

    Staircase

    Temporary support for roof assembly

    Form work

  • 7/22/2019 Construction Sequence LNG Storage Tank

    8/31

    PC OUTER WALL CONSTRUCTION,

    ROOF ASSEMBLY

    Intermediate lift of PC wall

    Roof liner supporting frame

    Form work

    Staircase

  • 7/22/2019 Construction Sequence LNG Storage Tank

    9/31

    PC OUTER WALL CONSTRUCTION,

    ROOF AND SUSPENDED DECK ASSEMBLY

    Intermediate lift of PC wall

    Roof liner

    Staircase

    Suspended ceiling deck & hanger

    Form work

  • 7/22/2019 Construction Sequence LNG Storage Tank

    10/31

    PC OUTER TANK WALL CONSTRUCTION,

    ASSEMBLY OF ROOF AND SUSPENDED DECK

    Top lift of PC wall

    Form work

    Roof compression ring

    PC wall top haunch

  • 7/22/2019 Construction Sequence LNG Storage Tank

    11/31

    ASSEMBLY OF ROOF AND SUSPENEDED DECK,

    PREPARATION FOR ROOF RAISING

    Staircase

    Temporary blower for roof air-raise

  • 7/22/2019 Construction Sequence LNG Storage Tank

    12/31

    ROOF RAISING

    Air pressure

    Temporary blower for roof raise

  • 7/22/2019 Construction Sequence LNG Storage Tank

    13/31

    WELD GUSSET BETWEEN ROOF AND COMPRESSION

    RING, INSTALLATION OF ROOF PENETRATION

    Roof liner support, liner and

    suspended ceiling deck

    Roof nozzle & manhole dome roof penetration

  • 7/22/2019 Construction Sequence LNG Storage Tank

    14/31

    CONSTRUCTION OF ROOF CONCRETE

    Temporary blower for roof

    concrete construction

    Air pressure

    Roof concrete

  • 7/22/2019 Construction Sequence LNG Storage Tank

    15/31

    CONSTRUCTION OF ROOF CONCRETE,

    ERECTION OF WALL VAPOR BARRIER (LOWER)

    AND BOTTOM INSULATION (LOWER)

    Roof concrete

    Wall vapor barrier (lower)

    Bottom insulation (lower)

  • 7/22/2019 Construction Sequence LNG Storage Tank

    16/31

    CONSTRUCTION OF PLATFORM AND

    ERECTION OF BOTTOM LINER

    Platform

    Bottom liner

  • 7/22/2019 Construction Sequence LNG Storage Tank

    17/31

    CONSTRUCTION OF PLATFORM, RING BEAM FOUNDATION

    AND ERECTION OF ANNULAR PLATE

    Platform

    Ring beam foundation

    Annular plate

  • 7/22/2019 Construction Sequence LNG Storage Tank

    18/31

    ERECTION OF INNER BOTTOM, WALL VAPOR BARRIER,

    CORNER PROTECTION, BOTTOM INSULATION, AND

    INSULATION FOR CORNER PROTECTION

    Bottom insulation (top)Inner bottom

    Wall vapor barrier (upper)

    Temporary opening

    Insulation for corner protection

    Corner protection wall

  • 7/22/2019 Construction Sequence LNG Storage Tank

    19/31

    ERECTION OF INNER TANK WALL, INNER TANK BOTTOM,

    WALL VAPOR BARRIER AND BOTTOM INSULATION

    Automatic shell welding machine

    Inner shell 1st & 2nd course

    Bottom insulation (top)

    Inner bottom

    Wall vapor barrier (upper)

  • 7/22/2019 Construction Sequence LNG Storage Tank

    20/31

    ERECTION OF INNER SHELL AND PIPING

    Inner shell intermediate

    Temporary opening

  • 7/22/2019 Construction Sequence LNG Storage Tank

    21/31

    INSTALLATION OF PIPE SUPPORT, PLATFORM, HANDRAIL,

    WALL VAPOR BARRIER, SUSPENDED DECK PENETRATION,

    ERECTION OF INNER TANK WALL / GIRDER, AND PIPING

    Inner shell upper

    & top course

    Dome space ladder & walkwaySuspended ceiling deck nozzle

    & manhole penetration

    Pipe support

    Pipe rack or sleeper

    Inner girder

  • 7/22/2019 Construction Sequence LNG Storage Tank

    22/31

    INSTALLATION OF ESCAPE LADDER,

    PLATFORM AND HANDRAIL, AND PIPING

    Escape ladder

    PRV / VRV / instrument platformPlatform & handrail

  • 7/22/2019 Construction Sequence LNG Storage Tank

    23/31

    INSTALLATION OF PRV,VRV, INNER LADDER,

    CRANE, HOIST, AND PIPING

    Pump column

    Inner ladder

    PRV / VRV

    Pump loading / offloading

    crane or hoist

  • 7/22/2019 Construction Sequence LNG Storage Tank

    24/31

    CLOSING TEMPORARY OPENING,

    AND PIPING

    Inner shell temporary

    opening closure

    PC wall temporary opening closure

    Corner protection temporary

    opening closure

  • 7/22/2019 Construction Sequence LNG Storage Tank

    25/31

    HYDROTEST, PNEUMATIC TEST

    AND PIPING

  • 7/22/2019 Construction Sequence LNG Storage Tank

    26/31

    SHELL INSULATION - RESILIENT BLANKET,

    PIPING INSULATION, AND PAINTING

    Shell insulation -

    Resilient blanket

  • 7/22/2019 Construction Sequence LNG Storage Tank

    27/31

    ROOF INSULATION, ANNULAR SPACE INSULATION - PERLITE, AND

    PIPING

    Shell insulation - Perlite

    Roof insulation

  • 7/22/2019 Construction Sequence LNG Storage Tank

    28/31

    LNG PUMP INSTALLATION,

    COMMISSIONING OF INSTRUMENT AND ELECTRICAL,

    LNG pump

    LNG pump

  • 7/22/2019 Construction Sequence LNG Storage Tank

    29/31

    FINAL BOX-UP OF THE TANK,

    DRYING AND N2 PURGING

    Drying & N2 purging

    equipment

  • 7/22/2019 Construction Sequence LNG Storage Tank

    30/31

    COOLDOWN

  • 7/22/2019 Construction Sequence LNG Storage Tank

    31/31

    START OPERATION