8/12/2019 Construction of Factory
1/2
ID Task Name Duration Start Finish BaselineDuration
Baseline Start Baseline Finish DurationVariance
0 Construction of Factory 76 days Tue 01-04-14 Fri 27-06-1494 days Tue 01-04-14Fri 18-07-14 -18 days1 1 Engineering 9 days Tue 01-04-14 Thu 10-04-14 9 days Tue 01-04-14 Thu 10-04-14 0 days
2 1.1 Preparation and approval of plan 3 days Tue 01-04-14 Thu 03-04-14 3 days Tue 01-04-14 Thu 03-04-14 0 days
3 1.2 Prepartion and approval of 3 days Fri 04-04-14 Mon 07-04-14 3 days Fri 04-04-14 Mon 07-04-14 0 days
4 1.3 Preparation and approval of civil 3 days Tue 08-04-14 Thu 10-04-14 3 days Tue 08-04-14 Thu 10-04-14 0 days
5 2 Construction 70 days Tue 08-04-14 Fri 27-06-14 88 days Tue 08-04-14 Fri 18-07-14 -18 days
6 2.1 Site clearance 2 days Fri 11-04-14 Sat 12-04-14 2 days Fri 11-04-14 Sat 12-04-14 0 days
7 2.2 Foundation 10 days Mon 14-04-14 Thu 24-04-14 10 days Mon 14-04-14 Thu 24-04-14 0 days
8 2.2.1 Excavation till required depth 2 days Mon 14-04-14 Tue 15-04-14 2 days Mon 14-04-14 Tue 15-04-14 0 days
9 2.2.2 PCC Works 1 day Wed 16-04-14 Wed 16-04-14 1 day Wed 16-04-14 Wed 16-04-14 0 days
10 2.2.3 Column footing-RCC 5 days Thu 17-04-14 Tue 22-04-14 5 days Thu 17-04-14 Tue 22-04-14 0 days
11 2.2.4 Column till bottom to plinth 5 days Sat 19-04-14 Thu 24-04-14 5 days Sat 19-04-14 Thu 24-04-14 0 days
12 2.2.5 Backfilling 1 day Thu 24-04-14 Thu 24-04-14 1 day Thu 24-04-14 Thu 24-04-14 0 days
13 2.3 RR Masonry below GL 18 days Thu 24-04-14 Wed 14-05-14 18 days Thu 24-04-14 Wed 14-05-14 0 days
14 2.3.1 Excavation 3 days Thu 24-04-14 Sat 26-04-14 3 days Thu 24-04-14 Sat 26-04-14 0 days
15 2.3.2 RRM 1st footing 8 days Mon 28-04-14 Tue 06-05-14 8 days Mon 28-04-14 Tue 06-05-14 0 days
16 2.3.3 RRM upto to pinth beam 7 days Wed 07-05-14 Wed 14-05-14 7 days Wed 07-05-14 Wed 14-05-14 0 days
17 2.4 RCC - Plinth beam 6 days Wed 14-05-14 Tue 20-05-14 6 days Wed 14-05-14 Tue 20-05-14 0 days
18 2.4.1 Rebars and shuttering works 3 days Wed 14-05-14 Fri 16-05-14 3 days Wed 14-05-14 Fri 16-05-14 0 days
19 2.4.2 Fixing of Foundation bolts 1 day Fri 16-05-14 Fri 16-05-14 1 day Fri 16-05-14 Fri 16-05-14 0 days
20 2.4.3 Concreting 1 day Sat 17-05-14 Sat 17-05-14 1 day Sat 17-05-14 Sat 17-05-14 0 days
21 2.4.4 Deshuttering and curing 2 days Mon 19-05-14 Tue 20-05-14 2 days Mon 19-05-14 Tue 20-05-14 0 days
22 2.5 Strucutral Works-PEB 52 days Tue 08-04-14 Fri 06-06-14 56 days Tue 08-04-14 Wed 11-06-14 -4 days
23 2.5.1 Fabrication and supply at site 15 days Tue 08-04-14 Thu 24-04-14 15 days Tue 08-04-14 Thu 24-04-14 0 days
24 2.5.2 Erection of column buitup 5 days Wed 21-05-14 Mon 26-05-14 5 days Wed 21-05-14 Mon 26-05-14 0 days
25 2.5.3 Erection of frames 0 days Mon 26-05-14 Mon 26-05-14 3 days Tue 27-05-14 Thu 29-05-14 -3 days
26 2.5.4 Erection of purlin 0 days Mon 26-05-14 Mon 26-05-14 3 days Fri 30-05-14 Mon 02-06-14 -3 days
27 2.5.5 Erection of roof cladding 0 days Mon 26-05-14 Mon 26-05-14 3 days Tue 03-06-14 Thu 05-06-14 -3 days
28 2.5.6 Erection of wall grits 3 days Wed 04-06-14 Fri 06-06-14 3 days Fri 30-05-14 Mon 02-06-14 0 days
29 2.5.7 Erection of wall cladding 5 days Tue 27-05-14 Sat 31-05-14 5 days Fri 06-06-14 Wed 11-06-14 0 days
30 2.6 Strucutral Works-Proflex 7 days Tue 27-05-14 Tue 03-06-14 0 days Mon 26-05-14 Mon 26-05-14 7 days31 2.6.1 Erection of beams 2 days Tue 27-05-14 Wed 28-05-14 0 days Mon 26-05-14 Mon 26-05-14 2 days
32 2.6.2 Supply, fabrication and 5 days Thu 29-05-14 Tue 03-06-14 0 days Mon 26-05-14 Mon 26-05-14 5 days
33 2.7 Flooring work 19 days Mon 19-05-14 Mon 09-06-14 19 days Mon 19-05-14 Mon 09-06-14 0 days
34 2.7.1 Sand filling and compacion in
3 days Mon 19-05-14 W ed 21-05-14 3 days Mon 19-05-14 W ed 21-05-14 0 days
35 2.7.2 Laying of PCC 2 days Thu 22-05-14 Fri 23-05-14 2 days Thu 22-05-14 Fri 23-05-14 0 days
36 2.7.3 VDF flooring 2 days Sat 24-05-14 Mon 26-05-14 2 days Sat 24-05-14 Mon 26-05-14 0 days
37 2.7.4 Curing 7 days Tue 27-05-14 Tue 03-06-14 7 days Tue 27-05-14 Tue 03-06-14 0 days
38 2.7.5 Laying of tile flooring 5 days Wed 04-06-14 Mon 09-06-14 5 days Wed 04-06-14 Mon 09-06-14 0 days
39 2.8 Masonry work above plinth 5 days Thu 15-05-14 Tue 20-05-1431 days Wed 21-05-14 Wed 25-06-14 -26 days
40 2.8.1 Block work 230mm thk. 0 days Tue 20-05-14 Tue 20-05-14 20 days Wed 21-05-14 Thu 12-06-14 -20 days
41 2.8.2 Plastering work both side 0 days Thu 15-05-14 Thu 15-05-14 16 days Sat 07-06-14 Wed 25-06-14 -16 days
42 2.9 Wall using GFRP Panel 5 days Tue 27-05-14 Sat 31-05-14 0 days Thu 29-05-14 Thu 29-05-14 5 days
43 2.9.1 Erection of GFRP Panels 5 days Tue 27-05-14 Sat 31-05-14 0 days Thu 29-05-14 Thu 29-05-14 5 days
44 2.10 Mechanical Works 10 days Mon 02-06-14 Thu 12-06-14 10 days Thu 12-06-14 Mon 23-06-14 0 days
45 2.10.1 Execution of Mech works 10 days Mon 02-06-14 Thu 12-06-14 10 days Thu 12-06-14 Mon 23-06-14 0 days
46 2.11 Electrical Works 8 days Mon 02-06-14 Tue 10-06-14 8 days Thu 12-06-14 Fri 20-06-14 0 days
47 2.11.1 Execution of electrical work 8 days Mon 02-06-14 Tue 10-06-14 8 days Thu 12-06-14 Fri 20-06-14 0 days
48 2.12 Finishes 23 days Mon 02-06-14 Fri 27-06-14 34 days Tue 10-06-14 Fri 18-07-14 -11 days49 2.12.1 Doors & Window 7 days Mon 02-06-14 Mon 09-06-14 18 days Tue 10-06-14 Mon 30-06-14 -11 days
50 2.12.1.1 Fixing of windows and 3 days Mon 02-06-14 Wed 04-06-14 3 days Tue 10-06-14 Thu 12-06-14 0 days
51 2.12.1.2 Fixing of 2 days Thu 05-06-14 Fri 06-06-14 2 days Thu 26-06-14 Fri 27-06-14 0 days
52 2.12.1.3 Fixing of rolling shutter 2 days Sat 07-06-14 Mon 09-06-14 2 days Sat 28-06-14 Mon 30-06-14 0 days
53 2.12.2 Painting 18 days Thu 05-06-14 Wed 25-06-14 18 days Thu 26-06-14 Wed 16-07-14 0 days
03-03 17-03 31-03 14-04 28-04 12-05 26-05 09-06 23-06 07-0701 March 01 April 01 May 01 June 01 July
Task
Critical Task
Milestone
Summary
Rolled Up Task
Rolled Up Critical Task
Rolled Up Milestone
Rolled Up Progress
Split
External Tasks
Project Summary
Group By Summary
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Baseline
Baseline Milestone
Baseline Summary
Progress
Deadline
Slippage
Page 1
Project: Construction of FactoryDate: Thu 20-02-14
8/12/2019 Construction of Factory
2/2
ID Task Name Duration Start Finish BaselineDuration
Baseline Start Baseline Finish DurationVariance
54 2.12.2.1 Applying wall putty 8 days Thu 05-06-14 Fri 13-06-14 8 days Thu 26-06-14 Fri 04-07-14 0 days
55 2.12.2.2 2 coats of interior paint 5 days Sat 14-06-14 Thu 19-06-14 5 days Sat 05-07-14 Thu 10-07-14 0 days
56 2.12.2.3 2 coats of Exterior paint 5 days Fri 20-06-14 Wed 25-06-14 5 days Fri 11-07-14 Wed 16-07-14 0 days
57 2.12.3 Handing Over 2 days Thu 26-06-14 Fri 27-06-14 2 days Thu 17-07-14 Fri 18-07-14 0 days
58 2.12.3.1 Site cleaning & 2 days Thu 26-06-14 Fri 27-06-14 2 days Thu 17-07-14 Fri 18-07-14 0 days
03-03 17-03 31-03 14-04 28-04 12-05 26-05 09-06 23-06 07-0701 March 01 April 01 May 01 June 01 July
Task
Critical Task
Milestone
Summary
Rolled Up Task
Rolled Up Critical Task
Rolled Up Milestone
Rolled Up Progress
Split
External Tasks
Project Summary
Group By Summary
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Baseline
Baseline Milestone
Baseline Summary
Progress
Deadline
Slippage
Page 2
Project: Construction of FactoryDate: Thu 20-02-14