GEN-HSW-9046- 0 MITSUBISHI PROPRIETARY CLASS B
CNRA/WGRNR Workshop
“New Reactor Siting, Licensing and Construction
Experience”
Jinich Miyaguchi
16 September 2010
Nuclear Systems Engineering Department
Mitsubishi Heavy Industries, Ltd.
MITSUBISHI PROPRIETARY CLASS B
Experiences with
Tomari-3 Construction
0
GEN-HSW-9046- 1 MITSUBISHI PROPRIETARY CLASS B
CONTENTS
Background
Tomari-3 Construction
Outline / Construction Schedule
Plant Aspects
Proven Design
New Technology
Advanced Engineering
Construction Aspects
Site-work in winter season
Modularization in Construction
APWR progress report
Towards the future
1
GEN-HSW-9046- 2 MITSUBISHI PROPRIETARY CLASS B
Mitsubishi has constructed 24 PWR NPPs in Japan. Twin APWRs are under licensing.
TOKYO
YOKOHAMA
KOBE TAKASAGO
Tsuruga P/S
Mihama P/S Ohi P/S
Takahama P/S
Genkai P/S Sendai P/S
Ikata P/S
Tomari P/S
in operation
2 2
2 2
2 2
2 2 3
3 3 3 3
3 3
3
4 4 4 4
4
4
4
4 4
N
Number of Loops
under licensing (APWR)
Background
< Contributions for All PWR in Japan >
3 Tomari-3
N
2
GEN-HSW-9046- 3 MITSUBISHI PROPRIETARY CLASS B
‘65 ‘70 ‘75 ‘80 ‘85 ‘90 ‘95 ‘00 ‘05
Background
< History of Mitsubishi PWR Plant Constructions >
2 loop PWR
4 loop PWR
Mihama-1
Mihama-2
Genkai-1
Ikata-1
Genkai-2
Ikata-2 Tomari-1
Tomari-2
Ohi-3
Ohi-4
Tsuruga-2
Genkai-3
Genkai-4
Ohi-1
Ohi-2
3 loop PWR
Takahama-1
Takahama-2
Mihama-3
Takahama-3
Takahama-4
Sendai-1
Sendai-2
Ikata-3 Tomari-3
3
GEN-HSW-9046- 4 MITSUBISHI PROPRIETARY CLASS B
Background
< Continuous Constructions Experiences >
1970s 1980s 1990s 2000s 2010s After 2020
9 units
▼ Tomari-3 (Dec.2009)
Tsuruga-3/4 (2016/2017)
▼▼
US-APWR
Developing
our own
technology
Safety & Reliability Enhancement
Plant Construction ExperiencesPlant Construction Experiences
Economy
Enhancement
Major Components Replacement Projects Major Components Replacement Projects (including Components Supply)(including Components Supply)
7 units 7 units
20 Steam Generator
14* Reactor Vessel Head
4 Core Internal
14* Turbine
6 Control Boards
*:including
2 foreign plants
▲ Sendai-3 (2019)
Japanese APWR
EU-APWR
4
GEN-HSW-9046- 5 MITSUBISHI PROPRIETARY CLASS B
Tomari-3 Construction
< Overview >
Tomari-3
Tomari-1/2 unit1;C/O 1989, 579MWe
unit2;C/O 1991, 579MWe
東京
Kobe
Tokyo
Tomari Heavy snow and
strong wind
in winter
Tomari-3
Utility Hokkaido Electric Power
Co., Inc
Manufacturer
/Constructor
Mitsubishi Heavy Industries, ltd.
Reactor PWR (3 Loop)
Electric power output 912 MWe
Fuel assembly 17 x 17 / 12ft
Number of fuel assemblies
157
Frequency 50Hz
5
GEN-HSW-9046- 6 MITSUBISHI PROPRIETARY CLASS B
Tomari-3 Construction
< Construction Schedule >
2003 2004 2005 2006 2007 2008 2009
Rock Inspection
Loose Excavation
Base Concrete Inner Concrete of
Containment Vessel
Commercial
Operation
Construction of
Containment Vessel
Start-up
Test
Fuel Loading
MEF : Mechanical and
Electrical Facilities
Installation and Function test of MEF
Construction completed just on schedule
License
Approval
6
GEN-HSW-9046- 7 MITSUBISHI PROPRIETARY CLASS B
Plant Aspects Proven Design
3-loop conventional type PWR using highly reliable components
New Technology Fully digital I&C system
Advanced Engineering 3D-CAD engineering
Integrated Database System
Jobsite Construction Control System
Construction Aspects Site-work in Winter Season
Modularization in construction
Tomari-3 Construction
< Plant & Construction Aspects >
7
GEN-HSW-9046- 8 MITSUBISHI PROPRIETARY CLASS B
Proven Design
< Highly Reliable Components >
Tomari-3 Steam Generator was celebrated as MHI’s 100th delivery
with high reliability fostered through long years
manufacturing and maintenance experiences.
8
GEN-HSW-9046- 9 MITSUBISHI PROPRIETARY CLASS B
U.S.A
Turbine: 2units
Mexico
Turbine :2units
Taiwan
RV:3units,Turbine:
6units, RCP:8units,
CHP:24units
China
PBMR Turbine Generator /Core Barrel Assembly
South Africa
Turbine 1unit
Spain
RVCH:3units Sweden
Turbine Rotor 2sets
Slovenia
RV: 1unit
Finland
SG:10units
Belgium
SG:15units
France
RV:Reactor Vessel
RCP:Reactor Coolant Pump
CHP:Charging Pump
Prz:Pressurizer
RVCH:Reactor Vessel Closure Heads
SG:Steam Generator
RVCH : 16units
SG : 6units
Prz : 1unit
Brazil
RVCH:1unit
Proven Design
< World-wide Reliable Components Supply >
9
GEN-HSW-9046- 10 MITSUBISHI PROPRIETARY CLASS B
New Technology
< Fully Digital Main Control Room >
Soft operation Soft operation
Large display panel Large display panel
Improved monitoring and Improved monitoring and operational performance
by integrating controls and
information display
Advanced Control Room Advanced Control Room
Compact operator consoleCompact operator console
10
GEN-HSW-9046- 11 MITSUBISHI PROPRIETARY CLASS B
New Technology
< I&C System Verification Works >
Integrated Factory Acceptance Test.Integrated Factory Acceptance Test.
All the digital systems are connected at All the digital systems are connected at Mitsubishi factory via networks.Mitsubishi factory via networks.
Perform factory acceptance tests including Perform factory acceptance tests including communication check, system failure test communication check, system failure test and response time test.and response time test.
8 months of intensive test schedule.8 months of intensive test schedule.
Validation for total system performance Validation for total system performance before shipping.before shipping.
11
GEN-HSW-9046- 12 MITSUBISHI PROPRIETARY CLASS B
Advanced Engineering
< 3-D CAD Systems >
Layout・Piping Designing
Turbine
Main Component
Construction Planning
Improving design and construction
accuracy and efficiency.
Improving operation and maintenance
management.
Maintenance Demonstration
12
GEN-HSW-9046- 13 MITSUBISHI PROPRIETARY CLASS B
Advanced Engineering
< Integrated Database Systems >
Integrated Database
Inspection of welding
Inspection (on-site)
Material management
Manufacturing by CAM
Construction management
3D-CAD Management Integrated common database
from design, procurement,
inspection and construction
13
GEN-HSW-9046- 14 MITSUBISHI PROPRIETARY CLASS B
Drawing control
- Distribution by E-file. (in parallel with Hard copies)
- Multi-level security control
- Status control
Piping/Support construction progress follow-up
- Bar-code Multi-Tag for each weld point
- Progress monitoring
Advanced Engineering
< Construction Control System >
JCCS (Jobsite Construction Control System)
Final PT
Welding
Fit-up inspection
Joint fit-up 0
10
20
30
40
50
60
70
80
90
100
N F M S D M JNov Feb May Sep Dec Mar Jul 0
50
100
(%) ■R/B01(Plan)
◆R/B01(Result)
●R/B02(Plan)
▲R/B02(Result)
14
GEN-HSW-9046- 15 MITSUBISHI PROPRIETARY CLASS B
Site-work in Winter Season
< Winter Restriction at Tomari Site >
2.2. Heavy Duty Crane should be Heavy Duty Crane should be
used for construct used for construct
containment vessel before containment vessel before
winter seasonwinter season
1.1. Construction is difficult in winter season because Construction is difficult in winter season because
of heavy snow and strong windof heavy snow and strong wind
(end of Nov. (end of Nov. –– beginning of Mar.)beginning of Mar.)
15
GEN-HSW-9046- 16 MITSUBISHI PROPRIETARY CLASS B
Site-work in Winter Season
< Modified Setup Processes >
3. Early setup of outer shield is to enable inside work during
winter season.
16
GEN-HSW-9046- 17 MITSUBISHI PROPRIETARY CLASS B
Modularization in construction
< Shortening Construction schedule >
1. Piping modules
3. CV upper head
2. Packaging modules
17
GEN-HSW-9046- 18 MITSUBISHI PROPRIETARY CLASS B
Modularization in construction
< Modularization History >
18
GEN-HSW-9046- 19 MITSUBISHI PROPRIETARY CLASS B
Modularization in construction
< Piping Modules >
Multiple types of piping modules
19
GEN-HSW-9046- 20 MITSUBISHI PROPRIETARY CLASS B
Modularization in construction
< Packaging Modules >
20
GEN-HSW-9046- 21 MITSUBISHI PROPRIETARY CLASS B
Heavy duty crane
40m diameter
containment vessel
upper head
Advanced methods for shortening construction period.
Modularization in construction
< CV Upper Head Installation >
21
GEN-HSW-9046- 22 MITSUBISHI PROPRIETARY CLASS B
High precision on-site welding for upper head assembly in parallel with CV body construction
Welding & assembling
of upper head
Construction of
CV body
Modularization in construction
< CV Construction in 8-Months >
22
GEN-HSW-9046- 23 MITSUBISHI PROPRIETARY CLASS B
Conclusion
< Tomari-3 Successful Construction >
Completed just on schedule
Proven Design 3-loop conventional type PWR using highly reliable components
New Technology Fully digital I&C system
Advanced Engineering 3D-CAD engineering
Integrated Database System
Jobsite Construction Control System
Modularization in construction
Launch Base for APWR worldwide
application
23
GEN-HSW-9046- 24 MITSUBISHI PROPRIETARY CLASS B
APWR Progress Report
A new generation LWR “APWR” started as Japanese national project more than 20 years ago.
APWR has been standardized for worldwide market as US-APWR and EU-APWR.
Larger output and improved reliability based on best mix of proven technologies 1,700 MWe class power production
24 months fuel cycle with on-line maintenance
4 train safety system with advanced accumulator
Fully digital I&C and computerized MCR
24
GEN-HSW-9046- 25 MITSUBISHI PROPRIETARY CLASS B
US-APWR
DC application under reviewing by USNRC, planned to be
certified in 2011
COL applications for two sites under reviewing
EU-APWR
Design modifications will be finished this year considering
European safety requirements.
(SA, APC, etc.)
Preparing for EUR assessment.
APWR Progress Report
25
GEN-HSW-9046- 26 MITSUBISHI PROPRIETARY CLASS B
Towards the Future
Earlier discussion with utility is important for mutual understanding and to achieve on schedule design, licensing and construction.
Pre-application discussion with licensing authority is quite effective to address important safety issues and to establish clear licensing procedure and schedule
Worldwide cooperation of industries and authorities is useful to establish international standards.
26
GEN-HSW-9046- 27 MITSUBISHI PROPRIETARY CLASS B
Thank you for your attention